Page 1

Appendix 1 
Education Service
PROPOSAL PAPER 
We are looking for your views on a Proposal to
relocate the 
Tobermory 2-18 Campus, Erray Road 
Closing date for written responses: 
2nd October 2026 
A public meeting will be held on: 
17th September 2026 in Tobermory 2-18
Campus at 6.00pm 
This document has been issued by Argyll and Bute Council for consultation under the
terms of the Schools (Consultation) (Scotland) Act 2010. 
If you need this information in another language or format, please contact us to
discuss how we can best meet your needs. 
Phone: 01369 708576
Email: argyllhousereception@argyll-bute.gov.uk

Page 2

CONTENTS 
1. The Proposal and Consultation Process
2. Implementation Date for the Proposal
3. Background
4. Educational Benefits Statement
5. Assessing the impact on the local community affected by this Proposal 
6. Employee Implications
7. Conclusion 
8. Responding to the consultation 
Appendices:
Appendix 1  Distribution List
Appendix 2 Map of the location of the new campus
Appendix 3  Map of the Tobermory South site
Appendix 4  Map of Catchment Area
Appendix 5  School Roll Data
Appendix 6 Consultation Response Form

Page 3

1.0 THE PROPOSAL AND CONSULTATION PROCESS 
1.1      The Proposal being consulted on is as follows: 
To relocate the current Tobermory 2-18 Campus at Erray Road to a new
purpose-built 2-18 campus school building.  The Proposal, if approved, will be
implemented when the new accommodation has been completed. 
1.2      Decision to Undertake the Consultation 
This Proposal is being advanced because Tobermory 2-18 Campus currently
suffers from poor accommodation that struggles to suit modern education
practices. Relocating the school would permit the construction of a new purpose-
built campus building and considerably improved Education accommodation. 
The opportunity to build a new campus has arisen from the successful
application for funding from the Scottish Government’s Learning Estate
Investment Programme (LEIP). 
1.3     Consultation on the Proposal 
Under the Schools (Consultation) (Scotland) Act 2010 (the 2010 Act), if a local
authority proposes to relocate a school, it must undertake a statutory
consultation involving the ‘relevant consultees’ affected by the Proposal. In this
instance, located within the current campus: 
• Tobermory ELC 
• Tobermory Primary
• Tobermory High 
and the following primary schools that are associated primaries: 
• Dervaig Primary School 
• Salen Primary Gaelic and English medium School and ELCs
• Lochdonhead Primary School and
• Ulva Primary School 
are the “affected schools” in terms of the 2010 Act. 
For the avoidance of any doubt, this proposal does not include the incorporation
of the associated primaries into the new campus building, will not change the
current leadership and management structure within the 2-18 campus, nor will it
involve any school closures. 
The formal consultation on the Proposal within this document will be undertaken
under the terms of the 2010 Act. The consultation period will start on 24th
August 2026 (with due written notice of the Proposal issued to the relevant
consultees listed in Appendix 1) and end on 2nd October 2026. Written

Page 4

representations must be received by the close of business on the closing date in
order to be taken into account. 
At the outset of the consultation period, the Council will also publish details of the
consultation exercise, including a copy of this Proposal Paper, on the Council’s
website for the wider public to access the consultation materials and submit
responses. 
1.4     Public Meeting 
A public meeting will be held on Thursday 17th September 2026 at 6pm in
Tobermory 2-18 Campus, Erray Road to discuss the Proposal. Anyone wishing
to attend the public meeting is invited to do so. The meeting will provide those in
attendance with an opportunity to: 
• Hear about the Proposal;
• Ask questions about the Proposal, and
• Express views about the Proposal. 
A note will be taken of any views expressed and/or questions asked at the public
meeting so that they can be taken into account as part of the consultation
process. A representative from His Majesty’s Inspectorate of Education in
Scotland (HMIE) will attend the public meeting as an observer. In addition to the
public meeting, written representations will be able to be made during the
consultation period. A copy of the Consultation Response Form can be found at
Appendix 6. 
1.5      Children’s Views 
Children who are capable of forming their own views will be able to express them
as part of the consultation exercise. In particular, officers from the Education
Service will conduct visits to the affected schools to undertake face-to-face
engagement sessions with pupils, supported by school staff that know the
children well. The school staff will provide relevant support and specific
adaptions for the children according to their needs to allow them to participate
fully in the session and to express their views. During these sessions, officers
intend to use a consistent set of PowerPoint presentation slides, which will be
shared with school staff in advance, and any adaptations required for any
individual children or specific groups of children will be made prior to the
sessions. 
The presentation slides will clearly explain what a consultation is, outline the
specific Proposal that is being consulted on, and set out that the Authority are
seeking pupils’ views on the proposed relocation of the school building. All views
expressed by the children will be recorded during the session in a variety of ways
appropriate to the specific groups being engaged. For example, some pupils may
prefer to provide oral responses, which the school staff and officers will write
down for them. Other pupils may choose to draw, type, or write their response
themselves during the sessions. For engagement with Early Years children,
officers plan to use a Floor Book to facilitate gathering and recording their views.

Page 5

A standard response form will be used for each school to ensure the pupils’
views are collated in a consistent and structured way. 
The above approach will be tailored to individual groups of pupils to ensure that
pupils are provided with full, accessible, diversity-sensitive and age-appropriate
information about their right to express their views freely. The consultation
process has also been planned to ensure that children’s views are given due
weight as part of the review of the Proposal at the conclusion of the consultation
period. These steps in particular are being taken to ensure that the consultation
exercise is compatible with the United Nations Convention on the Rights of the
Child (Incorporation) (Scotland) Act 2024, and in particular, Articles 2, 3, 6, 12,
28 and 29 of the Convention. 
1.6      HMIE Involvement 
At the start of the consultation period, the Council will provide HMIE with a copy
of this Proposal Paper. When the consultation period has ended, the Council will
collate all of the written and oral representations. Thereafter, this information will
be provided to HMIE and include; 
• A copy of written representations made to the Council on the Proposal
(or summary of them if agreed with HMIE),
• A summary of oral representations made at the public meeting, and
• Other relevant documentation, so far as is practicable. 
HMIE will prepare a report on the educational aspects of the Proposal taking
account of the above, and insofar that HMIE considers them relevant, any
written representations made directly to them. HMIE may also visit the schools
affected by the Proposal and make any other enquiries as they consider
appropriate. HMIE require to send their report to the Council no later than three
weeks (or longer if agreed with the Council) after having received the above
listed information from the Council. 
1.7     Consultation Report  
After receiving HMIE’s report, the Council will review the Proposal taking
account of written representations received during the consultation period, oral
representations made during the public meeting, children’s views gathered from
the facilitated focus groups with pupils (outlined at Section 1.5, above), and
HMIE’s report. The Council will then prepare and publish a Consultation Report,
which will include a recommendation regarding implementation of the Proposal
and make it available for inspection. The Consultation Report will be published
no later than three weeks before it is formally considered by the Council’s
Community Services Committee. 
1.8      Inaccuracies or Omissions 
Where any inaccuracies or omissions are discovered within this Proposal
Paper, the Council will determine whether relevant information has been
omitted or, if there has been an inaccuracy. Appropriate action will then be

Page 6

taken by the Council, which may include issuing corrections, re-issuing a
corrected Proposal Paper or an extension of the consultation period. In any of
these events, all of the Relevant Consultees (and where applicable the
notifier(s) of any omissions or inaccuracies) and HMIE will be advised of the
action that is taken. 
1.9      Integrated Impact Assessment 
The Council is required to carry out impact assessments in relation to certain
policy and service changes to ensure it considers how those changes may
impact different groups, in accordance with the Council's statutory duties
relating to equalities, inequalities of opportunity, children’s rights and wellbeing,
consumers and island communities. 
The statutory consultation exercise will enable officers to consult with the
above-mentioned groups and gather evidence pertaining to potential impacts of
the Proposal. Those impacts will be assessed by officers on an ongoing basis,
and an Integrated Impact Assessment will be published alongside the Council’s
Consultation Report. 
2.0  IMPLEMENTATION DATE FOR THE PROPOSAL 
2.1  The Proposal, if accepted, would be implemented when the building works for
the new school campus have been completed. Officers currently anticipate that,
in accordance with the current project plan, this will be from late 2030.  This is
an estimate, is dependent on a number of milestones set out in the current
project plan and therefore may be subject to change. 
3.0  BACKGROUND 
3.1 Tobermory 2-18 Campus is a co-educational, non-denominational school
serving the town of Tobermory along with the surrounding area.  The school is
situated in Erray Road, in Tobermory. Tobermory Campus is an all-through
school with children and young people aged 2 – 18 years. The campus consists
of an early learning and childcare (ELC) provision, a primary and a high school.
The campus has three different buildings associated with it along with a Pre5
unit.  The original block B was built circa 1930s with Block F being added in the
1970s.  The Art block was then added between 1980/1990 and the Pre5 unit
built in 2010.   
The ELC setting provides flexible placements for 38 weeks of the year during
term time.  Children and young people attending ELC and Primary are usually,
but not exclusively, based in Tobermory while the Secondary School serves
North and Central Mull, with associated primary schools of Dervaig,
Lochdonhead, Salen and Ulva Ferry. 
There are also children and young people attending the secondary school on
placing requests (from Highland Council and from the South of the island).
Children and young people benefit from Gaelic Learner Education delivered

Page 7

across the school and Literacy and Gàidhlig in the secondary stages. The
catchment areas for the primary and secondary are shown in Appendix 4. 
The school roll, as at 22nd April 2026, is as follows:   
Primary P1 P2 P3 P4 P5 P6 P7 Grand
Total
8 12 10 19 7 6 17 79
Secondary S1 S2 S3 S4 S5 S6  Grand
Total 
36 25 22 36 27 16  162 
ELC total  15 
3.2 Given current Tobermory Campus is assessed to be ‘C - poor’ in terms of
suitability there is a requirement to improve the situation. This is currently the
only school building in Argyll and Bute with that suitability rating.  The lower
grading of Tobermory Campus building is largely driven by accessibility,
restrictive drop off space, lack of social spaces and restricted specialised
classes. The building currently sits at 41.91% incline with little scope to improve
this. Analysis of the council expenditure on the campus also highlights a trend
of increasing reactive or maintenance spend and a sizable sum of investment
on addressing degrading fabric at the school over the past five years. Roof
works, water ingress and building fabric repairs are common sources of
expenditure.  The condition of the building can be improved from further
investment; however, the suitability is much more challenging to be upgraded
without significant refurbishment.  Such year-on-year construction can be
detrimental on both pupils and staff over long periods of time, and/or would
require decanting of operations for periods.  Other environmental (climate
change) standards or digital enhancements also remain below the minimum
standard compared to a new build LEIP school.   
3.3 In December 2021 the Cabinet Secretary for Education and Skills outlined to
the Scottish Parliament that LEIP Phase 3 would seek projects within 12
months.  The project team worked on developing the application adhering to the
detailed requirements set out by the Scottish Government:
• Local investment priorities and their context within the ‘Place’
• The proposed Vision, Strategic Outcomes and Objectives for the project(s)
• Alignment with Learning Estate Strategy 2019 Guiding Principles
• Ensuring political and financial commitments are in place for the investment
priorities
• Demonstrating implementation of the terms and conditions of the programme
on Phase 1&2 projects (where applicable). 
The Council submitted a bid for Scottish Government LEIP funding in October 
2022 for a 2-18 campus on Mull. In October 2023, the bid was accepted. The 
bid met the LEIP eligibility criterion on the condition that funding would be 
provided on a “like for like” basis to replace the existing Tobermory campus.

Page 8

3.4  The Council, in April 2024, decided to commence the Business Case, 
undertake engagement exercises and commence the site selection process. 
3.5 In August 2024, the council issued an open call for sites for the new campus to 
identify potentially suitable sites. The council carried out an extensive 
community engagement exercise in September 2024 to ask the community 
what was important to them when considering a site for the new campus. 
Councillors considered the findings in December 2024:
Community Engagement Analysis Report 
On 20th December 2024, the Council confirmed that the new Campus would 
continue on a single-site basis.
A detailed site appraisal was carried out with the output presented to the 
Council on 7th March 2025. This process included an Integrated Impact 
Assessment, and views were sought from community groups to inform this to 
supplement the Engagement Analysis Report. 
3.6  On 7th March 2025 the preferred site was confirmed at the Special Council
meeting as ‘Tobermory South’. The site is situated to the southern  edge  of
Tobermory with the western boundary adjacent to the A848. This is  illustrated
in relation to the existing campus on the map in Appendix 2. Councillors made
this decision based on evidence presented through a comprehensive preferred
site recommendation report with a large suite of appendices, the culmination of
six months of activity. The meeting minute and  report are available at this link:  
Special Meeting, Argyll and Bute Council - 7th March 2025
3.7  Following the decision on the preferred site, as Tobermory South, by  
councillors, it was thereafter appropriate to formally consider a statutory
relocation Proposal in parallel with the development of the outline business
case. 
On 5th June 2025, the Council’s Community Services Committee agreed to
undertake a statutory consultation exercise on a Proposal to relocate the
current Tobermory 2-18 Campus. However, before that consultation exercise
could commence, a Petition for Judicial Review was lodged in the Court of
Session – challenging the Council’s decision of 7th March 2025 to locate the
new campus on the Tobermory South site. 
Members of the Community Services Committee thereafter considered a report
on 28th August 2025, seeking the Committee’s endorsement of officers’ actions
not to commence the statutory consultation exercise previously agreed, and to
pause all other work on the Project, due to the material change in
circumstances that had arisen by virtue of the Judicial Review court
proceedings. Now that the matters pertaining to that earlier decision have been
concluded, and following the Council’s consideration of a further report and
decision on 29th April 2026 to resume the Project under a revised timeline, it is
now considered appropriate to revisit the Proposal for a statutory relocation
consultation under the 2010 Act.

Page 9

3.8 The new building will include the appropriate number of learning   
spaces, modern practical subject specific rooms, a larger gym hall and a larger 
dining  hall. The outdoor environment will be accessible and suitable for 
outdoor learning. 
3.9 More information about the Campus is available on the Council’s website. 
4.0 EDUCATIONAL BENEFITS STATEMENT – ASSESSMENT OF THE LIKELY
EFFECTS OF THE PROPOSAL 
4.1  Benefits for Present Pupils at Tobermory Campus 
Should the school be relocated and built on the new site, there will be benefits
for current pupils. A new purpose-built campus will be a significant, more
efficient improvement on the current establishment. These improvements
include better-quality accommodation, more attractive learning environment,
access to modern technology, improved disability access and improved indoor
and outdoor learning environment.  The Education Service also have
confidence that the new building will provide excellent facilities for use outwith
school hours that could be used to help meet the learning, leisure and social
needs of the children and young people and the community. 
The design of the new campus will ensure that accessibility for all, including
learners with disabilities complies with the Council’s Accessibility Strategy and
the Equality Act 2010.  It will be designed in such a way as to promote
accessible and inclusive learning which will meet the needs of learners
including those with Additional Support Needs. It will be designed to be an
inspiring learning environment which is fully able to support new and innovative
digital learning and engage pupils with the curriculum. 
4.2  Benefits for Future Pupils of Tobermory Campus 
The development of a new campus in Tobermory will see children and young
people benefit from a well-resourced single site which retains capacity to meet
future educational needs as they arise. A new purpose-built campus offers the
prospect of strong educational benefit arising from improved accommodation
and learning environment for the pupils.  A degree of flexibility and adaptability
will be built into the design in order to provide options to alter spaces in the
future in response to the changing needs of the campus population. This
approach is likely to optimise the use of available space. 
The new campus will include new sports facilities which will significantly
enhance opportunities for Physical Education and related activities. Pupils will
have the opportunity to make links within and across disciplines through
interdisciplinary learning adding depth and relevance to experiences. It would
be expected that these improvements in facilities and the associated impact on
practices would have a positive impact on the Health and Wellbeing of children
and young people.

Page 10

The new campus will be fully responsive to future learning requirements, and
the design process will ensure that all spaces support learning and teaching
relevant to the society pupils will enter as adults.  It will be designed to be an
inspiring learning environment which is fully able to support new and innovative
digital learning and engage pupils with the curriculum and allow them to
develop skills for lifelong learning. 
Facilities such as a science laboratory, technology workshop, home economics
room, music suite, and library will support and enhance learning as well as
supporting transitions. These facilities will also benefit pupils who access
mainstream/enhanced provision learning arrangements across the wider
campus.  With carefully considered timetabling, the whole campus would have
access to the facilities. 
Outdoor Learning provision will also be improved for all learners and will be at
the heart of the design process. This will provide enhanced opportunities for
learning beyond the classroom for all learners. As part of the design for the
outdoor environment consideration will be given to ensure safe pick up and
drop off points for pupils arriving by a variety of transport modes and suitable
parking facilities for staff and visitors. This should include a safe walking route
and will allow better management of any risks in and around the vehicle and
pedestrian interface.  Appropriate use of CCTV will help manage/reduce
unauthorised entry, bullying and vandalism and can also help pupils feel more
secure. 
The digital learning environment would be enhanced through implementation of
the Proposal. Staff knowledge and skills in using digital platforms for learning
and teaching will be more effectively shared among colleagues, and teachers
across the campus and across the authority will work collaboratively to build
online learning experiences and resources.  Such improvements in provision
would be underpinned by the advanced digital facilities and accessibility
planned into the design of the new campus. 
4.3  Effects on Other Users of the School’s Facilities 
In line with Argyll and Bute’s Learning Estate Strategy and in accordance with
the Scottish Government Learning Estate Investment Programme (LEIP)
requirements the use of the new building should benefit the wider community.
This ensures high quality partnership working and community engagement is at
the heart of the Education Service.  For the new campus this would involve
planned use of the library and sports facilities and the opportunity to book
rooms, at appropriate times, by other users in the community.  The new
campus may also have the benefit of attracting and retaining staff as they could
be drawn to the first-class working environment at the new campus. 
4.4  Effects on Pupils of Tobermory Campus 
As the new campus will be located a short distance from the current site, there
is not expected to be any significant effect on school transport arrangements for

Page 11

pupils. However, the Education Service would monitor the suitability of transport
arrangements prior to, during and following any move to a new campus on an
ongoing basis to assess the ongoing suitability of school transport
arrangements, and take steps to mitigate any adverse impacts for individual
pupils. 
Key aspects that will improve the environment for pupils will be considered
during the design phase. These include acoustics and noise, air quality,
lighting, temperature control and classroom size. The improved physical
environment is likely to impact positively on attendance   as pupils will find the
new environment a nicer place to be. In addition to this, improved physical
spaces can result in a physically and mentally healthier environment leading to
less time off for illness. 
The Education Service also plan to prepare for the transition of pupils over to a
new campus to ensure that this takes place as smoothly as possible for all
children and young people. This planning process will consider the individual
needs and requirements of pupils with a view to mitigating any adverse impacts
that could potentially arise for children and young people as a result of
changing their learning environment. However, as stated above, the physical
learning environment is anticipated to be significantly improved within a new
campus. Accordingly, no significant adverse effects arising from the same are
currently anticipated. Nonetheless, the position will be continually monitored by
the Education Service on an ongoing basis, with a focus on the individual
needs of pupils. 
In addition to enhancements to the physical environment, improvements to the
layout of the teaching areas and classrooms will encourage high levels of
collaborative and collegiate work among the educational staff, positively
impacting on levels of attainment and achievement. Opportunities for inclusive
and collaborative learning (where appropriate) through access to flexible
learning spaces can further promote positive attitudes to diversity.  The flexible
learning spaces will facilitate working across school stages, allowing varied and
enhanced social interactions and provide opportunities for pupils to experience
quiet spaces when required, which positively impacts on emotional wellbeing.
Strengths across the school will be shared. Existing good practice will be
recognised and identified within the school and incorporated into strategic
planning to improve provision and ensure equity of experience for young people
across the school. 
4.5 Implications for Pupils if the Proposal was not Implemented 
The Council’s Learning Estate Strategy 2021 sets out an ambition to provide a
school estate that is of category A or B in terms of suitability and condition plus
a number of other modern standards.  Delivering a new campus in Tobermory
supports that ambition, because Tobermory 2-18 campus currently has poor
suitability accommodation as outlined in the school condition survey for the
campus. Relocating the campus would permit the construction of a purpose-
built campus.

Page 12

Whilst there have been ongoing maintenance and improvement works; the
current school is grading “C - Poor” for suitability which means the physical
element of the campus does not carry out its function effectively without
continuous repair and it shows considerable signs of age. There are significant
issues with accessibility due to the multiple sets of stairs and changes in level
throughout the campus and narrow corridors. 
If this Proposal is not implemented, this is likely to have a negative effect on
student perception, comfort and well-being whilst learning within the building. In
addition to this, students or staff with limited mobility will struggle to access all of
the current school. There have in recent years been representations from senior
pupils asking for improvements.   As an older school building, the ongoing
maintenance required to keep the campus in a useable condition can be
disruptive to learning and routines.  Classroom environments can be noisy as
they are not designed for modern teaching methods.  Another consideration is
that classrooms can often be too hot or too cold, with no real way to regulate the
temperature at a consistently comfortable level. In addition to this there are
challenges with the external environment, this is evident through insufficient
parking and a tight road infrastructure serving the current site.  This affects bus
drop off and pick up points and active travel routes for the current site. 
5.0 ASSESSING THE IMPACT ON THE LOCAL COMMUNITY AFFECTED BY
THIS PROPOSAL 
5.1 With the construction of the new purpose-built campus, there may be
potential benefits for the local communities of the affected schools.  These
include the current ELC, primary and secondary sectors of the campus as
well as the associated primary schools of Dervaig, Lochdonhead, Salen, and
Ulva Ferry.  Schools influence the attractiveness of an area for potential
residents and, in turn, the value of future housing developments. A new
campus in Tobermory may have potential to contribute towards an increase
in the value of properties in the area, as well as making it more attractive for
families with children to move to the area.  This may also apply to the local
areas that are in the catchment area for Tobermory secondary.  Community
members will also benefit from opportunities to access new sports facilities
and library in evenings and weekends at the new campus. 
6.0 EMPLOYEE IMPLICATIONS 
6.1 Staffing arrangements will continue to be consistent with the Argyll and Bute
Council Staffing Standards and other local arrangements. For the avoidance of
any doubt, this proposal does not include the incorporation of the associated
primaries into the new campus building, does not require any school closures,
nor will it change the current leadership and management structure within the 2-
18 campus. 
6.2 Key aspects that will improve the environment for staff will be considered during
the design phase. These include acoustics and noise, air quality, lighting,
temperature control and classroom size. Improved physical spaces can result in
a physically and mentally healthier environment leading to less time off for

Page 13

illness. Improved accessibility will make the building suitable for anyone
experiencing mobility issues.  The new campus’s enhanced digital technology
capabilities will empower staff to design and deliver modern lessons while fully
integrating digital tools across the curriculum. 
7.0 CONCLUSION 
7.1  This is a Proposal to relocate Tobermory 2-18 Campus. The matter is being
considered by way of a statutory consultation exercise in accordance with the
2010 Act. 
8.0     RESPONDING TO THE CONSULTATION 
8.1     Interested parties are invited to respond to the consultation exercise by making
written submissions on the Proposal, using the form at Appendix 6, by no later
than close of business on 2nd October 2026. 
Responses can be posted to: 
Argyll and Bute Council
Customer Services: Education
Argyll House
Alexandra Parade
Dunoon, PA23 8AJ 
Or emailed to:  argyllhousereception@argyll-bute.gov.uk    
8.2 Those submitting a response, whether by letter or email, should be aware that 
their response will be published as part of the Council’s final Consultation 
Report. 
8.3 If they do not wish their response to be publicly available, they should clearly
indicate on the document by ticking the box which states: “I wish my response
to be considered as confidential with access restricted to elected members and
officers of Argyll and Bute Council.” Responses received from children will be
anonymised. Otherwise, it will be assumed that the respondent agrees to their
response being made publicly available

Page 14

Appendix 1 – Distribution List 
Distribution list and how to access a copy of the Proposal Paper 
A Summary of this Proposal (including details of where/how to access the full
Proposal Paper) will be provided to the following ‘Relevant Consultees’ in terms
of the Act: 
• The Parent Councils of Tobermory 2-18 Campus
• The Parent Councils of Dervaig, Salen, Lochdonhead and Ulva Primary
Schools
• The parents of pupils at all affected schools
• The parents of any children expected to attend any of the affected schools
within two years of the date of publication of this Proposal Paper
• The pupils at the affected schools (in so far as the Education Authority
considers them to be of suitable age and maturity)
• The pupils at the associated primary schools – Dervaig, Salen, Lochdonhead
and Ulva Primary Schools (in so far as the Education Authority considers them
to be of suitable age and maturity)
• All employees at the affected schools
• Trade union representatives of employees at the affected schools
• Mull Community Council
• All relevant users of the Tobermory 2-18 Campus
• Argyll and Bute Community Planning Partnership 
A Summary of this Proposal (including details of where/how to access the full
Proposal Paper) will also be made available to: 
• Argyll and Bute Councillors for Ward 4 – Oban South and the Isles
• The constituency MSP for Argyll and Bute
• List MSPs for the Highlands and Islands region
• The constituency MP for Argyll, Bute and South Lochaber
• Mull and Iona Community Trust 
The steps listed below have also been taken to ensure that the proposal is
widely available: 
• This Proposal Paper will be published on the Argyll and Bute Council website
• This document can be made available in alternative forms or translated by
contacting Argyll House, Dunoon, telephone: 01369 708576 or
argyllhousereception@argyll-bute.gov.uk;
• Hard copies of this Proposal Paper will also be available for inspection, free of
charge, at the following locations:
a) Council Headquarters – Kilmory, Lochgilphead
b) Tobermory 2-18 Campus

Page 15

The steps outlined below will also be taken to ensure that the Proposal is made
available to children potentially impacted by the proposal in a child-friendly way,
in compliance with the UNCRC requirements, and in particular Article 12
(respect for the views of the child):
Officers from the Education Service will conduct visits to the affected schools to
undertake face-to-face engagement sessions with pupils, supported by school staff
that know the children well. The school staff will provide relevant support and specific
adaptions for the children according to their needs to allow them to participate fully in
the session and to express their views. During these sessions, officers intend to use a
consistent set of PowerPoint presentation slides, which will be shared with school staff
in advance, and any adaptations required for any individual children or specific groups
of children will be made prior to the sessions.
The presentation slides will clearly explain what a consultation is, outline the specific
Proposal that is being consulted on, and set out that the Authority are seeking pupils’
views on the proposed relocation of the school building. All views expressed by the
children will be recorded during the session in a variety of ways appropriate to the
specific groups being engaged. For example, some pupils may prefer to provide oral
responses, which the school staff and officers will write down for them. Other pupils
may choose to draw, type, or write their response themselves during the sessions. For
engagement with Early Years children, officers plan to use a Floor Book to facilitate
gathering and recording their views. A standard response form will be used for each
school to ensure the pupils’ views are collated in a consistent and structured way. 
The above approach will be tailored to individual groups of pupils to ensure that pupils
are provided with full, accessible, diversity-sensitive and age-appropriate information
about their right to express their views freely. The consultation process has also been
planned to ensure that children’s views are given due weight as part of the review of
the Proposal at the conclusion of the consultation period.

Page 16

Appendix 2 – Map of location of the new campus site

Page 17

Appendix 3 – Potential Site Layout of the South Tobermory site

Page 18

Appendix 4 Catchment areas

Page 19

Appendix 5 – Tobermory 2-18 School Roll Data and Projections 
ELC Primary Secondary 
Roll  School Roll  School Roll  
2014-15    61 139 
2015-16  17 59 139 
2016-17  17 63 144 
2017-18  21 58 143 
2018-19  24 61 126 
2019-20  17 62 132 
2020-21  16 62 136 
2021-22  26 68 138 
2022-23  18 76 160 
2023-24  15 73 151 
2024-25 19 80 154 
2025-26 12 78 162 
* Historical roll figures taken from Census of each year.
* Current school session figure accurate as at 22nd April 2026.       
ELC Primary Secondary 
Roll  School Roll  School Roll  
2026-27 15 70 157 
2027-28 15 77 156 
2028-29 15 80 156 
2029-30 15 63 168 
2030-31 15 66 181 
2031-32  66 190 
*NHS provide birth data up to January 2026 - all projections after this is based
on averages. 
*ELC projections based on NRS data with calculation to differences in actual starts each session.

Page 20

Appendix 6 – Response Form
CONSULTATION RESPONSE FORM 
Education Service 
Please use this form to let us know what you think about the proposal
You can complete this feedback form in Adobe Acrobat and print it out, or print and
complete it by hand, using block capital letters. Return the form to: Customer Services
Education, Argyll House, Alexandra Parade, Dunoon, PA23 8AJ
Or as an e-mail to argyllhousereception@argyll-bute.gov.uk. 
The closing date for responses to be received by the Council is 5pm on 2nd October
2026. 
Proposal 
Argyll and Bute Council is seeking the views on the following proposal, namely: 
• To relocate the current Tobermory 2-18 Campus School building to a new
school building located on the site which is situated to southern edge of
Tobermory with the western boundary adjacent to the A848. 
If you do not wish your response to be publicly available, you must tick the box
below. Otherwise, it will be assumed that you agree to your response being made
publicly available. 
“I wish my response to be considered as confidential with access restricted
to elected members and council officers of Argyll and Bute Council.” 
Name 
Address 
I agree with the proposal (please tick) Yes  No  Undecided

Page 21

If you wish to comment on the Proposal please use the space below. Please attach
another sheet should you require to do so:

Page 22

I am responding in my capacity as a (please indicate by ticking the appropriate
box) 
Parent/ carer of child at  
Tobermory ELC/Primary
/Secondary 
Trade Union 
Parent/ carer of child at 
affected primary school (Dervaig,
Lochdonhead, Salen, Ulva Primary
School) 
Elected representative 
Pupil  Community Council 
Tobermory PS / Tobermory HS
Parent Council 
Member of the public/ community 
Dervaig, Lochdonhead, Salen,
Ulva Parent Council 
Member of staff 
Other  Details: _________________________ 
Handling your response - Please note that:
• We will use the information you provide for the purpose(s) of this consultation,
including statistical and analytical purposes;
• We will pass a full copy of your written response to Education Scotland or a
summary of it of agreed with them; and
• We are subject to the provisions of the Freedom of Information (Scotland) Act
2002 and therefore would have to consider any request made under that Act for
information relating to written responses/ records of oral representations made
to us relating to this consultation.
This consultation, and all other school consultation exercises, can be viewed online on
the Council website at:
School consultations and proposals | Argyll and Bute Council
Thank you for taking time to respond.