ARGYLL AND BUTE COUNCIL                                                   BUTE AND COWAL 
AREA COMMITTEE     
ROADS AND INFRASTRUCTURE                     SEPTEMBER 2022
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 This report format and frequency for these reports were agreed as part of the
previous Council. The purpose of the report is to provide a general update on
key activities of the Service over recent months and to enable a discussion on
key, high level topics and projects. As part of developing future committee
structure and workplans, the purpose and effectiveness of this standing item
should be reviewed. 
1.2 As part of the normal course of business, we provide all members with regular
weekly briefings on topical projects and ongoing service delivery. We have been
doing this weekly for over 60 editions now and these prove to be a useful tool for
delivering regular service updates. They are all available as part of the wider
resource portal on the Member Zone system which also includes specific topic
briefing sheets and key policy documents. We are also in the process of
developing a seminar programme on specific topics, which we are hoping to
make as interactive as possible with various site visits.     
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Area Committee note and consider the contents of this
report, and provide feedback on the content, format and frequency. 
3.0 DETAIL 
COVID Absence/Resource Availability 
3.1 For the period of the previous report two reports in March then June absence
rates as a result of self-isolation requirements remained high in the case of the
former report and tapered down more in line with pre-COVID trends in the latter
report. This remains largely the case, and absence levels continue to be in line
with pre-COVID trends, although there do remain a few isolated absences
attributed to COVID, the overwhelming percentage of absences are non-COVID
related

Page 2

3.2 A more pressing issue in terms of resource availability is around recruitment
particularly for manual roles in our Operations team. We are finding that we are
having to go out three or four times for some posts, and even then we continue
to have some long-term unfilled vacancies. At the time of writing this report
there are 18 vacant posts which we are trying to recruit to in our Operations
team. Even in the posts we are successfully recruiting to, we are finding that
we have far fewer applicants than we would have done for similar posts
previously. 
Capital Roads Reconstruction Programme 
3.3 The focus of the roads reconstruction programme is to recover the network
through the delivery of a mix of carriageway resurfacing schemes,
patching/surface dressing and in-situ road surface recycling, which follow the
principles set out within the Roads Asset Management Plan. 
3.4 This Council has approximately £100M of backlog maintenance in the road
network. This means that over £100M would need to be invested to bring the
road network up to an A1 standard. Most councils are in a very similar position.
Clearly in the current financial climate we are not going to see the level of
investment required to bring the road network up to an A1 condition. However,
over the last decade there has been a carefully applied strategy of delivering
revenue and capital funding collectively and delivering a series of works
designed to minimise reactive work, carry out right first time repairs wherever
possible and to deliver surfacing techniques and specifications which
maximises the amount of repairs and resurfacing which is delivered. As with
almost all council services there is insufficient funding available to treat all the
sections of road that we’d like to do, the focus being on treating sections where
we can maximise the financial return and in so doing reduce the amount of
reactive repairs carried out. Unfortunately, the available funding means that
almost all roads authorities, including Argyll and Bute, are unable to treat every
section of road they would like to do.  
3.5 The total programme for this financial year for roads reconstruction is £8million
Council capital allocation and £1.6million from the Strategic Timber Transport
Scheme, which is used to match fund existing schemes on the council network
where timber extraction is programmed to be carried out. 
3.6 Oil and bitumen prices have increased significantly this year, and the situation
with costs is highly fluctuating. Coated roadstone used for surfacing our road and
footways has increased by approximately 20%. This will impact our programmes
of work. A report detailing the implications of the recent price increases was
presented to the June ED&I Committee. 
3.7 The Council capital allocation for the Bute and Cowal area is £1,406,200, and the
scheme list is available on the Council website here. As well as the programme
itself, the online resources include financial values and short explanations of
engineering methods/solutions.

Page 3

3.8  Overall progress with the programme has been excellent and works remain on
schedule. As well as the full programme [link above] which is updated monthly,
we provide weekly updates on schemes via our weekly briefing. At the time of
writing this report 10 of the 19 individual schemes in Bute and Cowal have been
completed. 
Winter Maintenance  
3.9 The annual winter policy update is being reported to EDI in September. The
proposed policy is largely unchanged from previous years and should it be
agreed, it will form the basis of the delivery of our winter maintenance activities
over winter 22/23.   
3.10 A key aspect of the winter service is the provision of public information on what
we do and why we do it. There is a range of online resources available on the
Council website here. 
Bridge Maintenance 
3.11 The Infrastructure Design team continue to carry out bridge inspections to all
approx 900 structures on a rolling programme across Argyll and Bute to ensure
they are safe and fit for purpose. This inspection regime identifies necessary
remedial works which are programmed for delivery. 
3.12 The team were also successful in a highly competitive bidding process for the
Scottish Government’s £32 million Local Bridge Maintenance Fund, receiving a
funding award of £5,5 million. The fund will be used to undertake proportionate
works on bridges in need of repair, identified through our inspection
programme/records. 
3.13 There are two schemes identified in this area, a £517,000 scheme at Cothouse
Bridge on the A815, which has an indicative siteworks start date of December
2022; and a £198,000 scheme on Lochgoilhead Bridge on the B839, which has
an indicative siteworks start date of June 2023. More details on these schemes
will follow as the projects develop. The indicative programme for this fund for the
whole Council area was reported to EDI in June and is available here. 
Rothesay Outer Harbour Berthing Facility 
3.14  An update on this project was recently provided in our weekly briefing [Edition 61
5th August] which read: The Principal Contractor, Teignmouth Maritime Services,
restarted site works on 22 June 2022 and has installed the pontoon system, piles
and access gangway.  At the time of writing a specialist subcontractor, Gael Force
Engineering, is due on site to install utilities for the berthing facility and the secure
access fencing.  Following this the Principal Contractor will then oversee the
testing and commissioning of the facility in preparation for handover to the
Council. 
3.15 The latest update is that our expectation is that this project will conclude in early
course, and will provide a fantastic new option for visitors to the island, helping to

Page 4

tap into the marine tourism sector and providing a real, meaningful boost to the
local economy. This schemes follows on from successful pontoons projects in
Oban and Campbeltown, with both towns benefitting economically as a result of
increased visitors. 
Play park funding 
3.16 Funding of £76,000 was allocated in financial year 21/22, with a further £79,000
this financial year. In order to provide for a meaningful programme of improvement
works targeted at the high priority sites, as well as a works package with is
attractive to what it is a limited supplier/contractor market, the funds have been
rolled together into a single package. Sites were given a priority rating based on
asset inspections and feedback form the Youth Forum, in compliance with the
Scottish Government’s grant requirements. The full list of prioritised sites was
reported to EDI in June and is available here. In this area the priority site is
Sandbank.   
3.17 An update on this was recently provided in the weekly briefing [Edition 61 5th
August] which read: The recent tender process failed to generate any bids. We
requested feedback as to why there were no applications and we were advised
that the timescales for completion of work were too short. A request for more time
to complete was made and this is currently being assessed by our procurement
team. A further re-tender process will be looked at this month. 
3.18 A further verbal update will be provided on this at the Committee meeting.   
4.0 CONCLUSION 
4.1 This report provides a general update to local members on recent Roads and
Infrastructure activities. 
5.0 IMPLICATIONS 
5.1 Policy – various policies referred to within the body of the report 
5.2 Financial – none 
5.3  Legal – the Council has various statutory obligations which are the
responsibility of RIS and set out in various Acts, such as the Roads Scotland
Act 1984. The services provided are in line with our statutory obligations 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known 
5.5.2   Socio-economic Duty – none known

Page 5

5.5.3 Islands – none known 
5.6. Climate Change – none 
5.7  Risk – none known 
5.8  Customer Service - none 
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan 
Policy Lead for Roads and Transport
Councillor Andrew Kain 
August 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services; or Mark Calder, Project
Manager