Dunoon to Hunters Quay Active Travel Route : Concept Design and Future External Funding

Argyll and Bute Council · 3 September 2024
Back to Bute and Cowal Area Committee — 3 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  Bute and Cowal
DEVELOPMENT AND ECONOMIC
GROWTH 
03 September 2024 
DUNOON TO HUNTERS QUAY ACTIVE TRAVEL ROUTE : CONCEPT DESIGN
AND FUTURE EXTERNAL FUNDING 
1.0 EXECUTIVE SUMMARY 
1.1. This report provides an update to Members on the Dunoon to Hunters Quay
active travel route, highlights the next steps and seeks support from Members
for the continuation of the project to complete the design process.  A further
report will be presented to Members prior to any construction stage. 
1.2. The funding for this project has come from Transport Scotland through the
Sustrans administered Places for Everyone programme (PFE) which is a highly
competitive challenge fund that requires designs to adhere to strict design
parameters in order for them to be considered by the PFE funding application
assessment panels. 
1.3. An initial concept design in line with PFE design requirements that included a
dedicated segregated cycle track was issued for public consultation between
May and June 2023. This consultation received 383 responses. The majority of
responses to this concept design were largely negative, primarily due to the
proposed removal of on street parking required to deliver the scheme. 
1.4. Following this feedback it was agreed with the project funders that a revised
concept design which minimised loss of on street parking would be produced
that responded to the comments received from the public consultation. 
1.5. To help gauge views and opinions from key stakeholders on the new emerging
concept design a series of workshops were held between the 27th November
2023 and the 17th January 2024. 
1.6. A public consultation on the new concept design was held between 29th January
and the 26th February 2024 March and a drop in day was held in the Queens
Hall on the 31st January. 
1.7. This consultation received 207 responses, out of a resident population of 9,140
in Dunoon. 42% of respondents said that they were supportive or very
supportive of the new concept design; 46% of respondents said they were
unsupportive or very unsupportive of the new concept design. 
1.8. Although a slightly higher percentage of respondents said they were
unsupportive of the route the main concerns appear to be in relation to the

Page 2

sections of the route that run through Kirn and between Kirn and Hunters Quay
and are in relation to the loss of on street parking. 
1.9. An additional stakeholder workshops were held post consultation on 13th March
to provide feedback on the findings of the consultation and to provide an update
on the design. 
1.10. If members approve the progression of this project, additional funding for the
developed and technical design stages will be required. At present the primary
route to access further funding for this project (and other active travel
infrastructure projects) would be through the Transport Scotland PFE
programme. 
RECOMMENDATIONS 
It is recommended that the Bute and Cowal members: 
• Note the progress made to date.
• Support the continuation of the project and the submission of a new PFE
funding application for design stage 3 (Developed Design) and stage 4
(Technical Design) to complete the design work required.

Page 3

ARGYLL AND BUTE COUNCIL  Bute and Cowal
DEVELOPMENT AND ECONOMIC
GROWTH 
03 September 2024 
DUNOON TO HUNTERS QAUY ACTIVE TRAVEL ROUTE : CONCEPT DESIGN
AND FUTURE EXTERNAL FUNDING 
2.0 INTRODUCTION 
2.1. This report provides an update to Members on the progress made to date on the
Dunoon to Hunters Quay active travel project, highlights the next steps and
seeks support for the project from Members. 
3.0 RECOMMENDATIONS 
3.1  It is recommended that the Bute and Cowal members: 
• Note the progress made to date.
• Support the continuation of the project and the submission of a new PFE
funding application for design stage 3 (Developed Design) and stage 4
(Technical Design) to complete the design work required. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. In 2023/24, the Active Travel Team secured £2.56M external funding for the
development and delivery of a total of 22 projects across Argyll and Bute, including
the Dunoon to Hunters Quay Active Travel Route Project.   
4.3. Transport Scotland’s Places for Everyone (PFE) programme is structured
around 8 project stages with a highly competitive challenge fund; with the 32
local authorities, 7 regional transport partnerships, two national parks and
numerous community groups across Scotland competing against each other to
secure the funding each project requires. 
4.4. A minimum of three new competitive funding submissions are required to
complete a project using PFE funding, with competitive applications required, as
a minimum, prior to Stage 0 (Strategic Definition), Stage 3 (Developed Design)
and Stage 5 (Construction).  The project stages are (0) Strategic Definition, (1)

Page 4

Preparation and Brief, (2) Concept Design), (3) Developed Design, (4) Technical
Design, (5) Construction, (6) Handover & Close Out and (7) In Use.                                           
January – June 2023: Stage 0-2 Concept Design 
4.5. Following the confirmation of PFE funding that was awarded specifically for this
project a concept design for an active travel route between Dunoon and Hunters
Quay was developed between January and March 2023 through a series
stakeholder workshops. 
4.6. One of the key stakeholders involved in shaping the concept design was the
paid PFE funding manager, Sustrans, who requested that the new route should
provide the highest level of service as set out by Cycling by Design and
wherever possible this should be achieved through the reallocation of existing
road space in favour of non-motorised users. 
4.7. The concept design that emerged proposed the introduction of a continuous
bidirectional segregated cycle track from Dunoon Ferry Terminal to James
Street, Kirn. The creation of the new bidirectional cycle track was to be achieved
through the reallocation of carriageway space, primarily through the removal of
existing on street parking bays along the seaward side of the route. Two on
street parking surveys were carried out that appeared to suggest that the design
provided sufficient on street parking capacity along the route to accommodate
parking demand through the provision of parking bays along the landward side
of the route and the retention of some parking bays along the seaward side
where this was possible. For safety the new cycle track also proposed replacing
the mini roundabouts on the A815 at Pier Esplanade and at John Street with
priority junctions. 
4.8. Due to existing width constraints the section of the route between James Street
and Hunters Quay proposed three design options and asked people to select
their preferred option. 
4.9. A public consultation on this concept design was held between 10th May and
26th June 2023 with a public drop in session held at the Queens Hall on the 16th
May; Around 100 people attended the event with 83 leaving comment. The
public consultation received a total of 383 responses. 
4.10. The main barriers to walking and wheeling were listed as: the weather (47%);
the need to carry too many things (28%); traffic speeds (23%); concerns with
safety/lack of safe off road paths and footways (22%); it takes too long (21%). 
4.11. The main barriers to cycling were listed as: The weather (42%); the need to
carry too many things (27%); concerns with safety/lack of safe off road paths
and footways (26%); do not enjoy cycling (25%) traffic speeds on road (24%). 
4.12. 57% of respondents said they strongly disagreed with the proposed reduction in
parking bays between Dunoon and Hunters Quay to accommodate improved
walking, wheeling and cycling, 11% disagreed, 9% agreed and 8% strongly
agreed with the proposal.

Page 5

4.13. There was particular concern raised from businesses at Kirn about the loss of
parking around Kirn and the impact this could have on the viability of their
businesses. 
4.14. Following the largely negative responses from the community to the initial
concept design it was agreed with the PFE fund manager, Sustrans, to prepare
a new concept design that did not required to remove significant levels of on
street parking.  Officers secured additional funding from the Scottish
Government Cycling Walking and Safer Routes (CWSR) fund to cover the
additional cost of developing a new concept design. 
July 2023 – March 2024: Revised Stage 0-2 Concept Design 
4.15. The design team developed a revised concept design taking account of the
comments previously received.  The revised concept design sought to retain
existing levels of on street parking with the route primarily being a widened
shared use path with improved connections where there were level differences
between the path and the A815 and better crossing facilities over the A815 
4.16. In response to the feedback from the earlier consultation the following additional
technical surveys were also commissioned 
• 7 day on street parking, duration of stay, occupancy and turnover survey
within Kirn ( between the hours 0700 and 1900)
• 3 day on street parking beat survey for the project area out with the Kirn
survey (between the hours 0700 and 2000)
• A classified junction turning count for the Hunters Quay ferry terminal
junction (between the hours 0700 and 1900) 
4.17. A new programme of stakeholder workshops was subsequently drawn up. The
pre consultation workshops which are shown in the table below were arranged
to help develop a design that could be supported in principle by the project
sponsor and key stakeholders 
Format Date Stakeholder
Virtual Workshop 27/11/2023 Argyll and Bute Council Officers 
Sustrans
Virtual Workshop   06/12/2023  Argyll and Bute Council Officers
Virtual Meeting  13/12/23 Dunoon Presents 
Virtual 1-1
Meeting
09/01/2024 Western Ferries
In-Person
Meeting 1
17/01/2024 Argyll and Bute Council Officers 
Argyll and Bute Council Elected Members
Live Argyll
Local Community Organisations 
In-Person
Meeting 2
17/01/2024 Argyll and Bute Council Officers 
Argyll and Bute Council Elected Members
Local Businesses

Page 6

4.18. A public consultation on the new concept design was held between 29th January
and the 26th February 2024 and a drop in day was held in the Queens Hall on
the 31st January.   
4.19. The concept design was split into 4 sections for the consultation; Section A-
Victoria Parade to Riverside Leisure Centre. Section B – Riverside Leisure
Centre to Kirn. ; Section B – Through Kirn and Section D Kirn to Hunters Quay
at a location approximately 100m south of the ferry terminal. 
4.20. Section A proposed a design for a bidirectional segregated cycle track utilising
the existing available road and footway width without the need to remove any on
street parking. 
4.21. Sections B-D proposed widening the footway to create a wider shared surface
path for walking, wheeling and cycling. This was largely achievable by using the
existing road verge; however as the route approaches Hunters Quay the
available usable verge width significantly reduces and it was proposed to extend
the existing double yellow lines from the Hunters Quay ferry terminal further
south towards Kirn to allow for the wider footway and be able to retain the
required carriageway running widths. 
4.22. The design also contains a series of improved crossing facilities along the length
of the route.  The proposed crossing at Kirn required the removal of
approximately 5 on street parking bays to allow for safe visibility lines. The
proposed crossing at John Street required the existing road lay out be changed
from a mini roundabout to a priority junction. None of the other crossing required
significant changes to the existing road layout. 
4.23. The consultation received 207 responses, a drop of 176 from the previous
consultation. The results on the new concept design were more evenly split with
42% of respondents saying that they were supportive or very supportive of the
new concept design and 46% of respondents saying they were unsupportive or
very unsupportive of the new concept design. 
4.24. Although a slightly higher percentage of respondents said they were still
unsupportive of the design the main concerns appear to be in relation to
sections C and D of the route between Kirn and Hunters Quay and again these
concerns focused on the loss of on street parking, both formal parking through
the loss of parking bays required for the new controlled crossing at Kirn and
informal parking through the extension of the double yellow lines from Hunters
Quay south towards Kirn. 
4.25. Further amendments were made to the final concept design based upon the
findings of the public consultation. These final changes were: 
• Relocating the proposed formal crossing facility in Kirn to provide
additional space for on-street parking and loading activity associated with
the Kirn Variety Store and Java Walk businesses on the east side of the
A815.

Page 7

• Retaining some on-street parking between Kirn and Hunters Quay
through amendments to the extent of new double yellow lines.
• Proposal for a new formal crossing facility outside Fountain Quay Care
Home.
• The retention of the mini-roundabout at the junction between John Street
and the Esplanade (rather than a new priority junction) and the removal
of the formal crossing facility proposed at this location.
• Incorporation of a raised table at key junctions (rather than a continuous
footway) 
• Inclusion of zebra crossing facilities across the segregated cycle track in
proximity to the Dunoon Ferry Terminal 
4.26. A stakeholder meeting was held with Police Scotland on 12th March who raised
no major concerns about the design at this stage. 
4.27. A post consultation workshop with stakeholders was held on 13th March to
provide feedback on the findings of the consultation and to provide an update on
proposed next steps. 
4.28. As a complete package this project has so far produced 
• A Concept Design Package which includes:
o General Arrangement Plans and Cross Sections
o Technical Surveys: 
▪ On street parking beat surveys
▪ On street parking, duration of stay and occupancy surveys
▪ Automatic traffic counter and traffic flow speeds surveys
▪ Car park occupancy surveys
▪ Classified junction turning counts
▪ Walking, wheeling and cycling flows surveys
▪ Topographical survey
▪ Utilities survey
▪ Desk top flood risk review.
o Preliminary Ecological Appraisal
o Stage 1 Road Safety Audit
o Constraints Plan 
• A Business Case which includes:
o Benefit cost ratio appraisal
o Risk registers
• A Behavior Change Plan
• A Monitoring and Evaluation Plan
• Equalities and Impact Assessment

Page 8

Next Stages 
4.29. If members approve the progression of this project, additional funding for the
developed and technical design stages will be required. At present the primary
route to access new funding for this project (and other active travel infrastructure
projects) would be through the Transport Scotland PFE programme. 
4.30. The PFE funding for is a highly competitive challenge fund that requires designs
to adhere to strict design parameters in order for them to be considered by the
PFE funding application assessment panels. 
5.0 CONCLUSION 
5.1. Two public consultations have been held to help inform the production of a
concept design for a new and improved active travel route between Dunoon and
Hunters Quay. The last public consultation showed a split of 42% of
respondents in support of the design and 46% unsupportive of the design. 
5.2. The potential loss of on street parking in the vicinity of Hunters Quay and, to a
lesser extent, to enable a new pedestrian crossing in Kirn, remains the main
reason why 46% of respondents were unsupportive of the design. In response
to this further amendments have been made to the concept design with the
proposed crossing at Kirn now located further south along the A815 so that no
on street parking capacity in the vicinity of the Kirn Shops is reduced and six on
street parking bays have been introduced into the design in the vicinity of
Hunters Quay.  
5.3. External funding from PFE has been sought for 2024/25 to progress the concept
design through design stages 3 and 4. However, the award of this funding is not
guaranteed. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
Local Outcome Improvement Plan (2024-34) outcomes
1: Transport Infrastructure and 3: Community
Wellbeing. The project is in keeping with LDP2. The
project also supports achievement of the Scottish
Government’s objectives set out in the Cycling Action
Plan for Scotland (CAPS) and Let’s Get Scotland
Walking - The National Walking Strategy.
6.2. Financial The design and any land purchase will be funded by
external competitive funding applications. The Council
has not contributed any funding to design costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have
improved physical and mental health and are less

Page 9

likely to require social care services in later life which
could result in a future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support any land purchase.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide enhanced
opportunities within the project area for people to
travel more sustainably and actively by walking,
wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route will improve access to essential services,
retail, leisure and employment opportunities for local
residents, with studies demonstrating those who
travelled actively had a higher monthly spend in local
businesses than those who travel via motorised
transport.
The design will also offer opportunities for individuals
to travel for leisure, again encouraging spend in local
businesses connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe and if
community support for the project is not obtained.
6.8. Customer
Services  
None.
6.9. The Rights of the
Child (UNCRC)
Completion of this project will provide enhanced
facilities designed to be suitable for use by an
unaccompanied 12 year old. The route has been
designed to be DDA compliant and will provide a safe
and accessible route for children with disabilities.

Page 10

Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
17 July 2024 
For further information contact:  Douglas Grierson,    
Sustainable Transport Coordinator    