ARGYLL AND BUTE COUNCIL  PLANNING, PROTECTIVE SERVICES    
AND LICENSING COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH            17TH DECEMBER 2025 
Local Development Plan 3 – Evidence Report Stage Engagement 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to notify PPSL Committee of the first stage of
engagement for Local Development Plan 3 (LDP3), which Members may recall
is significantly changed due to changes in the planning legislation. 
1.2 The planning authority is required to prepare an Evidence Report to inform and
justify the content of the next Local Development Plan (LDP3).  The issues to
be covered by the Evidence Report are also determined by legislation and are
set out in the report. They are divided into 18 Topic Papers and cover a wide
range of issues including: Housing, Transport, Infrastructure, Biodiversity,
Economy, Flooding, and Play Space.   
1.3 The Evidence Report will be informed by the views of stakeholders including
key agencies, children and young people, and the general public, to ensure
collaborative and transparent evidence gathering. A variety of engagement
methods are being employed including the Place Standard Tool.  Over the
coming months, draft Topic Papers will be placed online for public comment
regarding their accuracy and sufficiency to develop LDP3. Once the
engagement process has been completed and the Evidence Report finalised,
this will be presented to Members at Full Council for approval prior to
submission to Scottish Ministers for a Gatecheck, which essentially will seek to
confirm that there is sufficient evidence presented to form the basis of
preparation of LDP3.. 
1.4 Recommendations
It is recommended that PPSL:
i) Note the contents of this report and the engagement process being
undertaken to inform the LDP3 Evidence Report.

Page 2

ARGYLL AND BUTE COUNCIL  PLANNING, PROTECTIVE SERVICES    
AND LICENSING COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH            17TH DECEMBER 2025 
Local Development Plan 3 – Evidence Report Stage Engagement 
2.0 INTRODUCTION 
2.1 The planning authority is required to prepare an Evidence Report to inform and
justify the content of the next Local Development Plan (LDP3). This will be
collated around policy topics, and in addition to the 18 Topic Papers, will be
supplemented by additional work including a Play Sufficiency Assessment.
The Evidence Report is to be informed by the views of stakeholders including
key agencies, children and young people, and the general public, to ensure
collaborative and transparent evidence gathering. 
3.0 RECOMMENDATIONS 
3.1 Recommendations
It is recommended that PPSL:
i) Note the contents of this report and the engagement process being
undertaken to inform the LDP3 Evidence Report.   
4.0 DETAIL 
4.1 The planning authority is required to prepare an Evidence Report to inform and
justify the content of the next Local Development Plan (LDP3). 
4.2  Section 15 (5) of the Town and Country Planning (Scotland) Act 1997 (as
amended by the Planning (Scotland) Act 2019) (“the Act (as amended)”) sets
out the matters which must be taken into account through the Evidence report,

Page 3

which will be collated around policy topics.  To comply with this, 18 Topic
Papers will be prepared and these are listed below:
1. Climate Change
2. Biodiversity, Woodland and Forestry, and Soils
3. Landscape, Rural Development, and Tourism
4. Historic Assets and Places
5. Vacant and Derelict Land
6. Energy (Renewables)
7. Transport
8. Local Living, and Design, Quality and Place
9. Housing
10. Infrastructure
11. Green and Blue Infrastructure
12. Play Space
13. Flood Risk and Water Management
14. Economy
15. Town Centres and Retail
16. Aquaculture
17. Minerals
18. Green Belt   
4.3  Additionally, under section 16(D) of the Act (as amended), the planning
authority must assess the sufficiency of play opportunities in its area for children
in preparing the evidence report. The Town and Country Planning (Play
Sufficiency Assessment) (Scotland) Regulations 2023 set out the form and
content that is required of a Play Sufficiency Assessment (PSA) as well as the
consultation requirements for this. 
4.4 Section 16(B) of the Act (as amended) requires that, in preparing the evidence
report the planning authority are to seek the views of, and have regard to any
views expressed by:
(a)  the key agencies,
(b)  children and young people, in particular school pupils, youth
councillors and youth parliament representatives,
(c)  such other persons as may be prescribed, and
(d)  the public at large 
4.5    Additionally, for the PSA, The Town and Country Planning (Play Sufficiency
Assessment) (Scotland) Regulations 2023 require that, in preparing the PSA,
the planning authority must consult: 
(a)  children, 
(b)  parents and carers,
(c)  community councils within the planning authority’s area
established under Part IV of the Local Government (Scotland) Act
1973(3), and such other community bodies or persons whom the
planning authority consider should be consulted, and 
(d)  the public

Page 4

4.6 Key agencies, as well as other relevant stakeholder groups, are being engaged
with prior to public engagement on each Topic Paper. Additionally, the Topic
Papers will be sent to the neighbouring planning authorities at the same time
as these are each made available for public engagement. 
4.7 In order to comply with section 16(B) of the Act (as amended), public
engagement will be undertaken by publishing each Topic Paper online for a
period of 6 weeks. A form will be made available for members of the public and
community groups to complete to provide their views on whether the evidence
is accurate and sufficient, to determine the implications for LDP3. It is
anticipated that the 18 Topic Papers will be split into around 3 batches, with
between 5 and 7 Topic Papers (and associated appendices) being online at
one time, with the first set going online in early 2026. 
4.8 Separately, to inform the Design, Quality and Place Topic paper, Place
Standard Tool engagement is being used (as recommended in the LDP
Guidance. This is a method that is suitable for children and adults alike, and
which has been used by the council previously. In addition to public online
engagement, Officers are working with schools to undertake targeted youth
engagement. 
4.9 In order to comply with section 16 (D) of the Act (as amended), as well as The
Town and Country Planning (Play Sufficiency Assessment) (Scotland)
Regulations 2023, two online surveys have been developed – one for children
and a separate one for parents / carers and the wider public. 
4.10 Following this engagement and subsequent finalisation of the Evidence Report,
this will be presented to Members at a full Council Committee before being
submitted to Scottish Ministers for Gatecheck, as required by Section 16 (B) (5)
and (6) of the Act (as amended).   
5.0 CONCLUSION 
5.1 Engagement in the preparation of LDP3 is a vital component in the Town and
Country Planning (Scotland) Act 1997 (as amended). The engagement
process outlined herein will ensure collaborative and transparent evidence
gathering to inform and justify the content of LDP3.   
6.0 IMPLICATIONS
6.1 Policy – Local Development Plan 3 will replace Local Development Plan 2
(adopted 28th February 2024) in due course.

Page 5

6.2 Financial – The Evidence Report stage engagement is being undertaken in-
house with no cost pressure. The costs for Gatecheck and Examination are
outwith the Development Policy budget and are a cost pressure. Based on
previous experience of the existing system these are likely to be in the order
of £70-£100k. 30% of this cost would be anticipated in 2026/27 for the
Gatecheck.
6.3  Legal – there is a statutory duty to engage during the Evidence Report stage
of LDP preparation.
6.4  HR - None
6.5 Customer Service – This report sets out how customers can get involved in
the early stage of the LDP3 process. The formal consultation period will be
held following production of the Proposed Plan.
6.6 Risk - The preparation of LDP3 will run over 5 years and therefore there is an
uncertainty regarding resource levels. Further reduction in resource levels
would impact on delivery of LDP3 and could result in failure to meet legislative
requirements and Scottish Government performance targets.
6.7 Climate Change - LDP3 will provide an up-to-date position in terms of land
use development and climate change impacts against which to assess
planning applications. A Strategic Environmental Assessment (SEA) will be
carried out as part of the LDP3 process.
6.8  Fairer Scotland Duty - The engagement at Evidence Report stage (as well as
subsequent stages) is being handled to encourage engagement with all. An
Equalities Impact Assessment will be undertaken as part of the LDP3 process.
6.9 Equalities - protected characteristics. The engagement at Evidence Report
stage (as well as subsequent stages) is being handled to encourage
engagement with all. An Equalities Impact Assessment will be undertaken as
part of the LDP3 process.
6.10 Consumer Duty - The engagement at Evidence Report stage (as well as
subsequent stages) is being handled to encourage engagement with all. An
Equalities Impact Assessment will be undertaken as part of the LDP3 process.
6.11 Island Communities - The engagement at Evidence Report stage (as well as
subsequent stages) is being handled to encourage engagement with all. An
Equalities Impact Assessment will be undertaken as part of the LDP3 process.
6.12 Children’s Rights and Wellbeing - LDP Preparation Guidance requires that
Local Authorities make provision for inclusion of children and young people
within the preparation of LDPs. 
Kirsty Flanagan,
Executive Director with responsibility for Development and Economic Growth

Page 6

Policy Lead: Councillor Gordon Blair 
28th November 2025                                                  
For further information contact: 
Kim de Buiteléir - kim.debuiteleir@argyll-bute.gov.uk 
APPENDICES
None