Rothesay Pavilion to Albert Pier Active Travel Project
Stage 1&2 Combined, Engagement Report 
DATE:  November 2024  REF:  501053 VERSION: Draft

Page 2

MARK RINKUS                      
Managing Director                       
Mark.rinkus@connectedtp.com                 
Contents
1 APPROACH TO TRAVEL BEHAVIOUR CHANGE AND COMMUNITY ENGAGEMENT .............................. 1
2 STAGE 1 SURVEY QUESTIONNAIRE RESULTS ................................................................................. 15
3 STAGE 1 COMMUNITY FEEDBACK TOOL (CFT) RESULTS ................................................................. 28
4 STAGE 1 STAKEHOLDER FEEDBACK ................................................................................................ 33
5 STAGE 1 BARRIERS AND OPPORTUNITIES ..................................................................................... 37
6 STAGE 2 – COMMUNITY ENGAGEMENT ........................................................................................... 39
7 STAGE 2 - SURVEY QUESTIONNAIRE RESULTS ............................................................................... 44
8 STAGE 2 - COMMUNITY FEEDBACK TOOL (CFT) RESULTS .............................................................. 64
9 STAGE 2 - STAKEHOLDER FEEDBACK .............................................................................................. 78
10 OUR LESSONS LEARNT .................................................................................................................... 83
APPENDIX A – PROJECT HANDS UP SURVEY RESULTS .............................................................................. 86
APPENDIX B – STAGE 1 AND 2 PUBLIC EVENT ATTENDEES LIST (EVIDENCE) ........................................... 87
APPENDIX C – ISLE OF BUTE NEWS SAMPLE EXTRACTS ............................................................................ 88
APPENDIX D – STAGE 2 SURVEY RESPONSES ............................................................................................ 89

Page 3

2 | P a g e
www.connectedtp.com 
`
APPROACH TO TRAVEL BEHAVIOUR CHANGE AND COMMUNITY ENGAGEMENT

Page 4

1 | P a g e
www.connectedtp.com 
1 APPROACH TO TRAVEL BEHAVIOUR CHANGE
AND COMMUNITY ENGAGEMENT
1.1 Relevant Previous Engagement and Consultation
This project seeks to improve pedestrian links into Rothesay Town Centre and to
the Rothesay Pavilion making allowances for potential future active travel
connections.
The study is aligned with the 2017, Rothesay Town Heritage Initiative (THI),
town centre spatial strategy and was identified by the community during 2016
Rethink Rothesay Charrette.
Stakeholder Mapping
A stakeholder mapping matrix was developed in conjunction with the design
team's relevant experience. The stakeholder mapping aims to identify all
stakeholders to be involved within the study and seeks to quantify each
stakeholders forecast level of interest in the project and likely influence over the
project.
The stakeholdes mapping process was led by the council and supported by the
community council using their knowledge of the community.  The stakeholders
were categorised into engagement tiers reflecting their engagement hierarchy
using the mapping matrix (shown opposite). 
The process was collaborative with members of the study steering group
including the community council helping to define the stakeholder mapping which
evolved through the project lifecycle.
1.2 Engagement Planning
A consultation and engagement plan were developed setting out the studies
stage 1 engagement programme.  The plan was used to identify all proposed
activities, the activity order, potential audience and engagement method.   
Tiered stakeholder mapping developed mapping matrix

Page 5

2 | P a g e
www.connectedtp.com 
The plan provides a reference point to ensure that all parties were made aware of
forthcoming actions and had a chance to contribute. This provided the
opportunity to incorporate local knowledge and best practices. The plan identified
a range of activities, which would support comprehensive engagement.  
A summary of the key project engagement activities considered in support of
stage 1 is summarised as follows:
 Study Branding Identity.
 Project Press Release.
 Study Facebook Page.
 Regular Community Visits.
 Study Website Space.
 Engagement with Local Groups.
 Press and Media Support.
 Community Feedback Tool (CFT).
 Schools Engagement.
 Public Community Engagement Event.
 Community Group Meetings.
 Stakeholder Meetings (virtual and face to face). 
A summary of each action plan is provided in the remainder of this chapter. 
1.3 Study Branding / Study Identity
Whilst some active travel studies can benefit from the development of a bespoke
study branded title and logo, it was agreed with the project steering group, at the
project outset that no branding should be applied to this project.  The primary
reason being that the community council stated that the strong community ethos
in Rothesay would help spread awareness of the project far better than any
bespoke branding would and that the design teams time would be better spent
working with the community.
1.4 Project Press Release (PPR)
Public Notification
The council’s Marketing and Communications (M&C) team was engaged for
support.  The PPR is typically authored by the lead council sponsor in conjunction
with the M&C team.  The resulting PPR would then be circulated internally to all
council departments and issued externally to local press and media outlets.
Councils’ Services Notification
From our experience of other active travel projects, whilst the project is managed
by Argyll and Bute Council (ABC) strategic transportation team, other council
services have an important role to play in enabling active travel projects to
progress. This means it is important that all council services which have a role to
play or interest in the project are informed and engaged from the start of the
project. ABC manage a portfolio of active travel projects, where all projects are
advertised and communicated within and across the council.  The portfolio

Page 6

3 | P a g e
www.connectedtp.com 
supports the sharing of project information. The PPR was issued to this portfolio
by ABC.
1.5 Facebook Study Page
As part of the study lifecycle, a bespoke study Facebook Page was developed. 
Information was also posted on the Isle of Bute community Facebook page as the
community council advised that it has a wide following in the community and to
be the best way to raise awareness of the project.
The design team posted updates that encouraged anyone with an interest in the
study to engage.  The Facebook page was effective with the community engaging
to ask questions throughout the duration of the study.  The page was used as a
direct channel of communication between the design team and the community.
Our study team managed the page to maintain responsiveness.  The page was
used to inform the community of upcoming project events, advertise the teams’
visits to the community and publish our visit itinerary.  The page was also used to
share post visit photos and videos. These were produced to provide a post event
snap-shot of the design team's community interaction and to assist those unable
to attend in person. 
1.6 Community Visits
A key ambition of the project was to ensure the community remained central to
the project and would feel a strong collaboration through ‘face to face’ meetings.  
To achieve this aim, our engagement strategy centred around the design team
being physically present within the community where appropriate.
Using the community Facebook pages, we advertised our visits which included a
day within the community where the design team invited and met with local
groups, school and the community council. We advertised an itinerary of our
visits providing an opportunity for the community to ‘drop-in’ to our evening
public event.
The Community Facebook page was well used to support the project

Page 7

4 | P a g e
www.connectedtp.com 
To support the conversations, we used our digital ‘platform’ of materials.  These
included our pre-prepared constraints mapping used to record ideas and note
comments, barriers and aspirations.  
The plan was then digitised, comments added to our Community Feedback Tool
(CFT) and used as the foundation of the constraints mapping process and route
development. 
The ability to demonstrate to the community how their comments had been
considered is key to developing trust and engagement between the design team
and the community. 
1.7 Study Website 
To support the lifecycle of the project, a study webpage was developed and
hosted within the Connected Transport Planning Ltd (CTP) website. 
The website utilised our project template which was personalised to reflect the
project community using images of Rothesay recognisable buildings to assist in
making the space familiar to the community. 
The website provided a key consultation tool for the community to access the
project, designed to be accessible 3 weeks during the consultation time and not
just a ‘bolt on’ point of reference.  The site provided access to all public exhibition
and materials, videos, a range of feedback tools and general project information. 
The site also incorporated a range of functions including a news feed, a Facebook
link and an interactive constraints and option map from where a series of micro-
animations visualisations could also be accessed. These animations were
developed from local photos taken at key points along the study route and
designed to present a vision to the audience that would assist their understanding
of the project’s possible outcomes.
The website enabled those unable to speak with us in-person to view and
comment on any of the materials at any time during the consultation period that
suited them.  Noting the challenges of consultation with a busy community, the
use of the website was a perfect tool to support wide-reaching engagement on
Bute. 
Constraint mapping and face – face meetings were constructive

Page 8

5 | P a g e
www.connectedtp.com 
The website was open to access by the public for a period of 3 weeks following
the stage 1 public event.   
1.8 Survey Questionnaire 
A survey questionnaire was developed for the project to provide an opportunity
for the community to share there existing travels habits and existing travel
modes, requirements for a new route appetite for a route and improvements to
active travel.  The survey was designed using our experience of supporting similar
projects, where we noted that to maximise community feedback, the survey
should be less than 15 questions to minimise survey fatigue and maximise the
chance of receiving complete responses.
Using questions from previous studies as a reference, a bespoke stage 1 survey
questionnaire was developed that would capture key respondent demographics
and sought to learn how the community currently travel and their aspirations for
any future improvement. The survey formed a core component of the
engagement process and was the primary informant of quantitative feedback,
used to support the design process.
To maximise accessibility by all possible user groups and abilities, the survey was
hosted online via the study website using QR codes, website URLs and by contact
email.  The survey also included links to the study website tools such as the
Community Feedback Tool (CFT) which would assist the community in providing
comments by location on a map.
Physical copies of the survey were distributed at various locations including the
Discovery Centre and the co-op noticeboards.  The leaflets were also hand issued
by the design team for a period during a day within the foyer of the larger Co-op
Rothesay Pavilion to Albert Pier website including custom local images

Page 9

6 | P a g e
www.connectedtp.com 
supermarket with a number of community representatives supporting wider
distribution.
1.9 Media Support
To raise the community’s general awareness of the study, the local press and
radio stations that cover Rothesay were contacted, the radio station however did
not respond after multiple contact attempts.  The local newspaper in Rothesay;
The Isle of Bute News were happy to assist in promoting awareness for the local
community. The paper prints provided physical and digital advertisement of the
study and was again used to advertise our contact details. ABCs Communications
Team also promoted the study and consultation events on the Council's social
media pages. The community Facebook study group was another source used to
raise the community’s awareness.    
Around 1,500 event advertisement leaflets were distributed to advertise the
community events.   A number of the locations planned to post the flyers either
couldn’t accept the flyer or were unable to display it. Notwithstanding, the flyers
were successfully posted at various locations. These included:
 Various Victoria Street frontage businesses,
 Discovery Centre;
 Local residential properties;
 Co-op;
 Albert Pier businesses;
 Montague Street businesses. 
Flyers were also utilised to communicate a post-event ‘Thank You’ to the
community and to continue the promotion of the digital feedback options offered
via the project website.
This approach meant that those members of the community unable to attend the
advertised event would still have the option to provide feedback or ask the design
team questions, enabling wide-reaching community engagement. 
Advertising leaflets were distributed across the community

Page 10

7 | P a g e
www.connectedtp.com 
Argyll Media Coverage of the study helped raise awareness

Page 11

8 | P a g e
www.connectedtp.com 
1.10 Event Pop-Up
To raise the community’s awareness of the project and consultation event, the
study team set up a pop-up event within the foyer of the Co-op foot store.  The
event lasted for 3 hours within which the team issued advertising leaflets to
shoppers, to raise awareness of the evenings public event that evening in the
Discovery Centre. 
1.11 Community Feedback Tool (CFT)
Our bespoke engagement platform supports community feedback using a project
map and comment pins. The tool allows comments to be added by location with
comments visible to everyone.  The tool was hosted within the project website
and again used a series of QR codes, website URLs and a named email contact to
support access to other feedback methods and information platforms.  The CFT
was pre-populated with comments noted by the community on the constraint
plan. 
Community Feedback Tool (CFT) allows comments to be added by location
Co-op Pop-up event was used to advertise to the public

Page 12

9 | P a g e
www.connectedtp.com 
1.12 Schools Engagement
Rothesay Joint Campus
Rothesay Joint Campus catchment for Primary Schools pupils covers the southern
section of Bute including Rothesay, while for Secondary School pupils the school
serves the whole of Bute.  The school role includes 240 primary pupils and 272
secondary pupils.
The design team arranged to meet the Primary 6 pupils (22 pupils) for a 2-hour
period to learn more about the younger generation's views and thoughts
regarding walking and cycling.  The timing of the meeting worked well as it
developed on the classes ongoing theme of problem identification and solutions.  
Following introductions and a project discussion, an interactive Hands-up Survey
(HuS) exercise was undertaken using stickers and travel mode pictures.  The use
of this approach ‘energised’ the primary and secondary school pupils to
participate in the engagement discussion whilst also providing a visual result of
their current travel mode decisions.  The results show in Appendix A and show
that the majority of the school pupils currently travel by car or bus to school and
some also stated they walk and no pupils cycle to school.
Following the HuS, the team discussed with the school pupils and teachers how
they would feel about the project improvements.  100% of the pupils and 100%
(1) teacher supported the proposal and agreed it would be a positive addition.  
A summary of the school children’s feedback about what they think is important
in the design is also shown in Appendix A.
With the children in ‘problem-identification mode’, the team utilised our bespoke
primary school asset pack to work with the children to develop their own ideas for
a streetscape and how they would solve the travel issues they had earlier
identified.  The children were then split into two groups and tasked with
developing/exploring ideas using the kit, using drawings and plasticene to help
people and animals move around within the space they had created.  Some very
creative options were explored and positive feedback from parents via the
Facebook Page. 
Feedback from the Rothesay Primary School was positive

Page 13

10 | P a g e
www.connectedtp.com 
Engineers of the future? Rothesay Primary made great use of the asset pack to design a streetscape

Page 14

11 | P a g e
www.connectedtp.com 
1.13 Parent Teacher Association (PTA)
To maximise the reach of the engagement, the school was approached to
advertise awareness of the project through communication with the local parents
via the Parent Teacher Association (PTA).
1.14 Community Public Event
Following the physical and digital advertisements, an event was hosted by the
design team and ABC within Rothesay Discovery Centre on the 27th of February
2024.  The event opened to the public at 17:30 to 20:45 with the start time set to
maximise attendance. 
10 large format, graphically designed A0 presentation boards were displayed to
provide the audience with a story map of the study, process and consultation
purpose. The event was made more visible to the community through the use of
banners and bunting that was installed.  The team also posted live Facebook
updates.
All attendees were given the choice of completing the project survey
questionnaire or accessing our range of digital tools to provide feedback via QR
codes and URL links.  A key advantage of the digital platform is that the materials
could still be accessed and commented upon at a time that best suited the
consultees. 
This was particularly relevant noting the event took place on a dark winter’s
weekday night with only 61 people managing to meet the team.  A register
extract presented as evidence of those attending the event is shown in Appendix
B.

Page 15

12 | P a g e
www.connectedtp.com 
A weekday dark winter night may have had an adverse impact on the community’s attendance at Stage 1 Public Event

Page 16

13 | P a g e
www.connectedtp.com 
1.15 Micro-Visual Transition Animations
To assist the public in understanding how and what an active travel route may
look like within their community a series of transition animations and sketches of
the future were developed.  Each animation was based on a photographed
viewpoint of locations along the route that the public would recognise.
The transitions lasted 10 seconds and showed the transformation of the existing
viewpoint to a proposed future vision.
The animations were hosted as part of the study website experience and
embedded within the large format constraints and options maps. 
1.16 Community Group Meetings
A number of requests to meet were issued to the various local groups within the
community.  
Unfortunately, no responses were received from the groups noting their members
may still have provided representation through the public survey questionnaire
and online materials. 
Micro-Transition Animations were effective in showing what could be developed

Page 17

14 | P a g e
www.connectedtp.com  STAGE 1 SURVEY QUESTIONNAIRE RESULTS

Page 18

15 | P a g e
www.connectedtp.com 
2 STAGE 1 SURVEY QUESTIONNAIRE RESULTS
2.1 Sources of Community Feedback
The multiple engagement platforms made available to the community
supported them to engage with the project providing feedback both digitally
and in person.  
A summary of the received feedback by the various engagement platforms
used is summarised in the following table.
 Format  Responses Received
 Survey (Paper)  5
 Survey (Digital)  35
 Community Feedback Tool (Digital)  5
 Total Quantitative Responses  45
 Community Public Event Attendees  61
 Stakeholder Meetings  0
 Total Non-Quantitative Responses  61 
1https://www.citypopulation.de/en/uk/scotland/argyll_and_bute/S19002472__r
othesay/
2.2 Survey Sample Validation
A total of 45 quantitative responses were received from Rothesay’s population of
4,4001 residents.  This represents a sample size of 1% which is lower than the 10
– 15% aimed for.  This equates to a total sample size of 0.7% when considering
the population on the whole of the Isle of Bute which has 6,498 residents
(c.3,328 households)2.   The winter dark nights / changing of the season may
also have impacted on the community’s appetite to attend the public event. 
2 Census 2022

Page 19

16 | P a g e
www.connectedtp.com 
2.3 Survey Participant Demographics
2.4 Participant Demographics
This question was asked as it is important to capture the views of people with
varying levels of life experience to assist in the design process.
Of the participant responses received 
 32% were between 40-59 years old (26% Census 2022).  
 51% were aged between 60-79 (34% census 2022). 
 5% were older than 79 (8% census 2022). The results indicate that the survey
was completed by a disproportionately greater number of over people
between 40- and 79-year-old.  
Only 8% of participants were younger than 40 (33% Census 2022). 3% preferred
not to say how old they were. 
These results highlight that the survey has not captured the views of the younger
community (0% younger than 21-year-old).  
However, the school engagement event was well attended and their views have
been recorded through less prescriptive measures than the survey questionnaire
and are not therefore included in this summary.

Page 20

17 | P a g e
www.connectedtp.com 
2.5 Participants by Gender
Of the total respondents, 54% were women / girls (52% census 2022) and 41%
as men / boys (48% census 2022). No respondents identified as non-binary and
5% of respondents indicated that they would prefer not to say.
Overall, we consider the respondents reflect a reasonable cross-section of the
community however the results are slightly skewed more towards the views of
females, as data from 2022 census demonstrates there are 4% more women
have completed the project survey. 
2.6 Participants Relationship with the Area
Respondents were asked if they lived in Rothesay.  This question was relevant to
ask as it is important to understand if the respondent is responding with longer
term experience of the community or as a tourist/visitor.  100% of respondents
are full time residents in the community and none of the respondents have either
lived in the community historically, or visited at least once a year.

Page 21

18 | P a g e
www.connectedtp.com 
2.7 Participants Health
The majority of participants considered themselves to be able-bodied and did not
have a health or disability that impacted on their everyday mobility (71%). None
of the respondents indicated they did have some health or disability which limits
their day-to-day activity a lot, 21% indicated their disability or health issue would
affect them a little and 3% say they are limited a lot.  5% of respondents
indicated that they would prefer not to say. 
2.8 Participants Health Issues
Of the respondents indicating they did have a health-related disability, 38%
indicated their disability was related to mobility or stamina. 8% of the
respondents say they have breathing or stamina conditions that affect them. 8%
indicated a challenge relating to hearing. 8% respondents have mental health
conditions
0% related to poor vision and 8% indicated they’d prefer not to say.  
These questions are important to ask as they assist the design team in designing
for all user groups, including those with protected characteristics.

Page 22

19 | P a g e
www.connectedtp.com 
2.9 Participants Employment Status
Participants were asked to qualify their employment status. This question was
relevant to ask as the design team will need to consider how the project would
support economic activity and support the movement of people to and from
places of work. 
16% of respondents indicated that they are currently not employed.  24%
indicated they were employed full time and 13% work part time, 13% indicated
they were self-employed and 34% of respondents said they were retired or not
applicable. 
2.10 Results Comparison with 2022 Census                                                
3 https://www.citypopulation.de/en/uk/scotland/argyll_and_bute/S19002469__rothesay/
To assist in understanding more about how representative the study
demographics are, the survey results were compared with the 2022 Census for
Rothesay3.  The results indicate that the project feedback demographic by age
and all genders is broadly comparable with the census analysis. The community
has a marginally higher proportion of female to males and a mature population
with 23% over 65 years of age.  These results align with the survey feedback
with a slightly more female responses be received than male.  However, the
survey results include a much larger proportion of responses are from more
mature members of the community. 
Overall, the study results are considered to capture a good sample of the
community, capturing the views of both able bodied and those less able, those in
work and those unemployed.

Page 23

20 | P a g e
www.connectedtp.com 
2.11 Views on Opportunities and Barriers to Walking, Cycling &
Wheeling?
Participants were asked how often they walked or cycled.  This question is
relevant as it helps us understand the popularity of walking and cycling within the
community at present.  69% of respondents indicate that they walk or cycle daily,
11% roughly 3 times a week, 3% twice a week and 17% roughly once a week. 
These results indicate the community is relatively active and that cycling and
walking is a popular travel mode. 
2.12 Participants Travel Habits Along Victoria Street
Following on from this question, participants were then asked how often they
typically travelled along Victoria Street.
Only 11% of respondents indicated that they travel along the road one day a
week, 11% twice a week, 17% 3 times a week, 56% said they travel along
Victoria Street more than three times a week, and 6% said they don’t travel along
the road.
The results of this question indicate that participants don’t travel along the road
frequently.

Page 24

21 | P a g e
www.connectedtp.com 
2.13 Participants Parking Habits Along Victoria Street
Following on from this question, participants were then asked how often they
park a car along Victoria Street.
3% of respondents indicated that they park a car along Victoria Street once a
day, 21% twice a week, 26% three times a week, 18% said they don’t own a car,
and 32% said they don’t park along the road.
The results of this question indicate that participants don’t regularly park along
the road. 
2.14 Participants Travel Mode Influences
Participants were asked to provide an insight into the factors influencing their
travel mode decisions.  Participants provided a variety of reasons they viewed to
be barriers to travel by sustainable travel modes along the project route. To
enable the processing and presentation of data, the responses were categorised
into a number of themes.  A summary of the themes is presented as follows:  
 Road is too wide
 Animal Droppings
 Poorly Parked Cars
 Speeding Traffic
 Poor pavements
 Other
 Don’t Have Any
Considering the responses received, the majority of travel barriers relate to the
perception of traffic speed, poorly parked cars and the conditions of the
pavements. 
Many of these issues are within the scope of this project design and could be
directly addressed through design development.

Page 25

22 | P a g e
www.connectedtp.com 
2.15 Future Opportunities to Improve Active Travel
2.16 Participants View of Concept
Participants were asked to consider if they believed that the provision of a car
free route within the project area would encourage them to walk or cycle more
often. 9% of respondents believed that the provision of a route as described
through the public engagement process would encourage them to walk and cycle
more often and 91% said it would not.

Page 26

23 | P a g e
www.connectedtp.com 
2.17 Participants Travel Corridor Preference
To assist the design team in developing the most appropriate route corridor, the
community was asked which of the route options is best suited between the
pavilion and the ferry junction.  51% chose option 1, 3% chose option 2, none
chose option 3.
3% chose option 4, and 5% chose option 5.  The other 38% said that no
improvement is required. 
2.18 Community Route Preference
The community was asked was, which of the route options works the best
between the section of the route between the ferry junction and Albert Pier.  
 53% of respondents indicated that Option A worked best (Widen route
and provide path on inland side keeping road as it is), 
 8% of respondents said Option B worked best (Widen route and provide
path on coastal side keeping road as it is). 
 None of the respondent chose option C (Shared use of West Princess
Street then widen route and provide a path on inland side of road).  
 39% said that none of the options should be considered.

Page 27

24 | P a g e
www.connectedtp.com 
2.19 Participants Views Regarding Front Green
The community was then asked whether or not the front green should be
improved.  To which 35% of respondents indicated that an improvement would
be welcomed, 58% of respondents said they didn’t want it to be altered, and 8%
said they didn’t know.

Page 28

25 | P a g e
www.connectedtp.com 
2.20 Participants Thoughts and Aspirations for Improvements
Participants were asked about their thoughts, aspirations and considerations the
proposed design should take cognisance of. To enable the processing and
presentation of the responses, the responses were again categorised into a
number of themes.  A summary of the themes is presented as follows and shown
in the chart opposite.
 Reduction in Parked Vehicles
 Don’t do Anything
 Everything
 Improved Lighting
 Cycle Lanes Removed
 More Crossing Points
 Return Fairy Lights
The feedback from the community to this question provides a good level of
insight into the challenges the design is required to address and highlights the
challenges in maintaining a design balance that will address all the points
proportionately.

Page 29

26 | P a g e
www.connectedtp.com 
2.21 Participants View on Future Project Locations
Participants were then asked whether there were any other locations on the Isle
of Bute, the community think should be looked at for improvement. To enable the
processing and presentation of the responses, the responses were categorised
into areas.  A summary of is presented as follows and shown in the following
chart.
 The High Street
 Albert Pier
 No
 Kerrycroy
 Port Bannatyne
 Townhead

Page 30

27 | P a g e
www.connectedtp.com  STAGE 1 COMMUNITY FEEDBACK TOOL (CFT) RESULTS

Page 31

28 | P a g e
www.connectedtp.com 
3 STAGE 1 COMMUNITY FEEDBACK TOOL (CFT)
RESULTS
Five initial responses were received through the Community Feedback Tool (CFT)
followed by a further 21 which were added by the design team to capture the
publics views following the public engagement.  The responses were provided
anonymously.
Participant's comments were located along the route.  In the majority, comments
were positive with participants providing concerns relating to visibility, a lack of
provision for pedestrians to cross with concerns that once the Pavilion opens,
more pedestrian traffic will be generated.  
Some of the comments provided detailed summaries of localised challenges which
will greatly assist the design development process.
The stage 1 feedback received is presented by location and verbatim in the
following figure and table.  Each comment reference is shown in the figure.

Page 32

29 | P a g e
www.connectedtp.com 
Stage 1 Community Feedback Tool comments by location

Page 33

30 | P a g e
www.connectedtp.com 
 1  Narrow section of esplanade at this location
 2  When leaving Mackinlay street to turn right into town, it’s
really difficult to see past parked cars. This is very
dangerous when driving, but while on a bicycle I have
several times had to go far into the road in order to see
both ways, once or twice being dangerously closely
passed by cars which I couldn’t see were coming while
further back. The curve of the road exacerbates this.
Having lights there could help, and when the Pavilion
opens, I would expect more pedestrians to want to cross
from the prom to the Pavilion.
 3  Intersection of ferry traffic lanes and road ignores the
interests of pedestrians. The junction here is also
hazardous for cyclists. In fact the whole section between
the Pavilion and the pier is hazardous for cyclists (parked
vehicles, vehicles negotiating the mini roundabouts,
cobbled strips across the road, cars, lorries, buses all
competing for space). Maybe reduce the space devoted
to parked cars (there are underused parking spaces
elsewhere in town, e.g. near the main co-op store).
Maybe idealistic but there is an excellent bus service on
Bute, it could be used more. Encourage people out of
their cars, pedestrianise Montague Street, apart from
buses, have a dedicated bike or bike/pedestrian lane
right through from Prospect House to Craigmore.
 4  I think we need a safe crossing at the ferry crossing for
pedestrians. There is already a set of lights, it should
have a ‘green man’ as well as the lights for cars. If this is
not a suitable spot, then perhaps the raised areas
opposite the Discovery theatre should be a safe
pedestrian crossing, I believe it was previously one.
 5  No provision for pedestrian crossing at ferry junction
location
 5  Waste of Money!
 6  I am opposed to the plan. Money can be spent much
more wisely and usefully. eg. designated lane for
disabled users to get onto the ferry lift
 7  Not enough parking as it is, so don’t prefer any option
that cuts down parking, Option 1 takes least change to
roads and uses a matured foot path that exists
 8  There is no designated parking for disabled passengers
who need to travel by car
 9  Review pinch points - Ardbeg Po, Brechans, Gallowgate

Page 34

31 | P a g e
www.connectedtp.com 
 10  Spend money on Albert Pier to Glenburn road
 11  There is not enough parking in town as it is, so option 1
route should not impinge on the road way
 11a  Option 1 preferred route
 12  Option 1 preferred
 13  Include Palm trees in the middle of the road
 14  Putting greens and gardens must be maintained for
attracting tourists
 15  Could this not be extended to the end of Battery Place?
 16  Flower beds in centre of the road
 17  pedestrian lights wanted at Victoria street/ high street
junction
 18  So many eye sores around ferry terminal that it would be
a real shame to lose the lovely areas around the winter
gardens
 19  Important to retain the coach parking at Albert Pier
 20  Dangerous pavements here
 21  Too many small Manhole covers on the pavement on
Gallowgate
 22  Pelican crossing in front of pavilion is preferable
 23  Better curbs for wheelchair users

Page 35

32 | P a g e
www.connectedtp.com  STAGE 1 STAKEHOLDER FEEDBACK

Page 36

33 | P a g e
www.connectedtp.com 
4 STAGE 1 STAKEHOLDER FEEDBACK
To support the design optioneering process, a number of stakeholders identified
within the stakeholder mapping were engaged with. A range of engagement
methods were used for each group.
Stakeholder Meetings
The study team met with a range of stakeholders identified through the study
mapping process.  We utilised consultation mandates to plan 1-2-small group
workshop sessions with key stakeholders to introduce the team and discuss the
study.  Stakeholders included:
 Key council staff;
 Key local groups;
 Local Community Councils;
 Other key stakeholders. 
The workshops followed a similar format providing an introduction to the study,
setting ambitions, and introducing the team.  
ABC Network Management
The team met with James Ross of ABC Network Management virtually to discuss
the Rothesay project. Following a presentation of the project to date, a
constructive conversation explored a number of topics including:
 Route alignment challenges, particularly relating to the sea defence
impacts, minimising future maintenance obligations and Roads
Construction Consent (RCC).

Page 37

34 | P a g e
www.connectedtp.com 
4.1 Council Statutory Consultees
The stakeholders identified through the stage 0 of this project and noted within
the stakeholder mapping were consulted as part of the project.  A summary of
the other stakeholder feedback received is summarised as follows.
4.2 Non-Council Statutory Consultees
A summary of the non-council stakeholder feedback received is summarised as
follows. 
4.3 Community Groups
Community groups have been engaged through the public engagement process. 
No direct response has been provided.
4.4 Traditionally Harder to Reach Groups / Individuals
Engagement was undertaken with the residents of the community.  The design
team arranged a meeting with Bute Prides chairperson Angie Webb.  As a keen
cyclist within the community Angie was able to provide a great insight to the
challenges faced by those less heard voices. A number of issues were identified
including:
 The area is considered pretty safe already for walking and cycling when
compared with other urban locations;
 Noted that for older less mobile people, a lack of dropped kerbs and
coherent routes may limit travel options;
 Familiarity with the local area has added compliancy to accepting the
issues;
 Tractors in the area are massive and can be intimidating when cycling
along Victoria Street;
 The Front Green is noted to be ‘going downhill’ and would benefit from
improvements.
The Royal National Institute for the Blind (RNIB) was consulted and highlighted
that there is no specific representation for Rothesay available to provide
comment.
4.5 Landowners and Affected Parties
The design team worked with the local community / stakeholder feedback to
identify potentially impacted landowners.  The Registry of Scotland (ROS) was
contacted to obtain current legal land ownership details.  These details were
 ABC Marine Operations  Not consulted as no service
impact
 ABC Fleet Public Transport  Not consulted as no service impact
 ABC Outdoor Access  Not consulted as no service impact 
 ABC Youth Services  Not consulted as no service impact
 ABC Community
Development Team
 Not consulted as no service impact
 ABC Economic Development  Not consulted as no service impact
 SEPA  Not Consulted
 Scottish Water  No Issue. Details to be provided
 SSE  No Issue. Details to be provided

Page 38

35 | P a g e
www.connectedtp.com 
included within our landowner engagement tracker and recorded within our
stakeholder mapping and constraint mapping (shown in circles).
The ROS confirmed that the study area is within the ownership of Argyll and Bute
Council (ABC).

Page 39

36 | P a g e
www.connectedtp.com  STAGE 1 BARRIERS AND OPPORTUNTIES

Page 40

37 | P a g e
www.connectedtp.com 
5 STAGE 1 BARRIERS AND OPPORTUNITIES 
5.1 The Challenges to Active Travel
The community engagement programme has identified a number of barriers to
travelling sustainably.  These have been categorised and summarised as follows:
 lack of lowered curbs;
 Dangerous pavements;
 Access to the ferry terminal limited;
 Protecting the front green is a concern;
 Lack of provision for disabled and minority user groups;
 Lack of pedestrian crossings;
 Vehicle speeds a concern;
 Dangerous road crossings at points;
 Improvements to pedestrian and cycle crossing on Victoria Street, at the 
ferry terminal junction and the pavilion; 
 A clear preference for no impact on parking;
 Minimise the impact on Albert pier due to tourist traffic and coach parking;
 Why here and why such a short section of route;
 Limited support for investment or change;

Page 41

38 | P a g e
www.connectedtp.com 
STAGE 2 – COMMUNITY ENGAGEMENT

Page 42

39 | P a g e
www.connectedtp.com 
6 STAGE 2 – COMMUNITY ENGAGEMENT 
6.1 Further Engagement
Following the conclusion of the stage 1 consultation and completion of the stage
1 options feasibility report, option 2 (road corridor with route on coastal side) was
shortlisted for further development and consultation. The decision to progress the
design was partly due to the limited responses received during stage 1 and the
anticipation that by providing an example of what could be achieved, a greater
proportion of the public would engage during stage 2.
The scheme was also extended from Albert Pier to Glenburn Road to address
some of the stage 1 feedback regarding the useability of the route and concerns
raised regarding developing short sections of route.
To support the process, the engagement plan as described within the stage 1
section of this report was repeated.  This included:
 A second public event was held on the 21st August 2024 at the Discovery
Centre between the times of 16:30 and 20:30; 
 A interactive discussion session with s4 pupils of Rothesay Academy to
review the concept ‘fly though’ animation, capture views and test the
engagement materials.
 A drop-in session at Rothesay Swimming Pool using the ‘Toblerone’
interactive podium. The event lasted 1 hour and captured the views of the
community within the swimming pool foyer; 
 Production of a 40-minute-long Project Podcast to explain the Frequently
Asked Questions (FAQ). The podcast was hosted on-line within the project
virtual room; 
 A post public event Community Council public meeting was hosted by the
council on the 26th September.  Two one -hour long meetings were
facilitated to present the scheme and allow further question and answers of
the community’s concerns; The event was advertised by the Community
Council utilising social media and leaflet distribution.  The design team also
advertised the event on social media; and
 Production of a 4-minute-long video infomercial to provide an explanation to
the project and limitations to funding. The use of an video format had been
developed successfully on other projects and supported more meaningful
engagement with the community.
Similar to the stage 1 event, 5 large formats graphically designed A1 presentation
boards were developed to explain the project along with 3 x 1.5m x 2.0m long
concept design prints.  
It was noted that during the stage 1 event, the public experienced some difficulty
in working with the map-based images. To improve on the publics interface with
the study materials a ‘fly along’ video was produced for stage 2 using a
combination of Google Earth and the scheme concept design. The ‘fly through’
was projected onto the Discovery Centre wall using a large format projector and
supported by narration provided by the study team.

Page 43

40 | P a g e
www.connectedtp.com 
The event was advertised to the community through the use of local press
coverage in Appendix C (Isle of Bute News), local poster advertising and support
offered from the Rothesay Community Council.  The team again posted regular
updates using social media in advance of the event. 
These updates being reposted by the community multiple times across the
community’s own social media space including the Isle of Bute Facebook Page.
All visitors attending the event were given the choice of completing the project
survey questionnaire or accessing our range of digital tools to provide feedback
via QR codes and URL links.  A key advantage of the digital platform is, that even
with the poor impact of weather on attendance, the materials could still be
accessed and commented upon at a time that best suited the consultees. 
The event took place on a wet and rainy weekday night. A total of 110 people
managed to meet the team (90% increase from the 61 attendees for stage 1). 
During the event, the majority of visitors were observed by the design team to
bypass the project information boards provided and congregated around the ‘fly
through’ video.  A number of visitors attended promptly and prior to the
completion of video / event set-up. Many of the visitors were noted to repeat the
same questions regarding project funding, parking impacts and how the
pavement parking ban would impact on their businesses.  This information being
available within the bypassed boards.
The team struggled to manage the surge of visitors and the number and
frequency of repetitive questions, with many being raised by new visitors joined
the rear of the group. 
Due to the loud voices of a few, a number of visitors who were supportive of the
project felt uncomfortable speaking up in public resulting in many of the louder
and more aggressive voices dominating the event.  A number of those in support
of the project investment did reach out and engaged with the design team later
during the event.
It is noted, the value offered by the online engagement platform also allowing the
islands community to still provide their feedback for a period of six weeks post
event. A register extract of those attending the event is shown in Appendix B.
Post event, leaflets and surveys were left on the counter of Rothesay’s Discovery
front desk and the large format concept plans left on display for a period of four
weeks, before being reused at the Community Council public meeting.
The design team met and spoke with a number of people in the community,
visiting the Rothesay joint campus and the Discovery Centre.
All school pupils engaged in project conversation and either completed a survey
response on their own or provided feedback that the team used to complete a
survey on their behalf at that time.

Page 44

41 | P a g e
www.connectedtp.com 
6.2 Event Advertising
The advertising approach to stage 2 was similar to stage 1 with the key
difference of scaling back the leaflet production following further advise and
support from the community council and BUTE BID.  It was agreed that the use
of paper-based leaflets would have limited value within Rothesay as the island is
more reliant on digital media (Facebook) and word of mouth.  Accordingly, only
100 leaflets were printed for stage 2 and advertised through the town three
weeks in advance of the planned public event. Leaflets were this time distributed
by BUTE BID whilst the design team issued leaflets to the Library, town
businesses, Discovery Centre and Co-Op.
The study Facebook page alongside the community page were used to advertise
the event with a number of post prompts issued in advance.
A paid for advertisement was also take out within the Argyllshire Advertiser who
subsequently printed a number of editorial extracts (weekly).
During the design teams visit to the island the digital ‘Toblerone’ advertising
totem was also deployed to raise community awareness of the forthcoming event
and project.
Rothesay joint Academy also agreed to circulate information to parents and pupils
through the PTA and student council.
The public engagement event was open to the public for comment for a total
period of six weeks (two weeks in stage 1) to maximise the opportunity for public
feedback. The consultation period was supported again through the use of virtual
engagement room which had subsequently also been revised and improved.

Page 45

42 | P a g e
www.connectedtp.com 
Photos from August 24th Public and Schools Engagement

Page 46

43 | P a g e
www.connectedtp.com 
Stage 2 Concept 3D Flythrough Extract

Page 47

44 | P a g e
www.connectedtp.com 
7 STAGE 2 - SURVEY QUESTIONNAIRE RESULTS
7.1 Sources of Community Feedback
The multiple engagement platforms made available to the community
supported the community to engage with the project providing feedback
both digitally and physically.  
A summary of the received feedback by the various engagement platforms
used is summarised in the following table.
 Format  Responses Received
 Survey (Paper)  22
 Survey (Digital)  603
 Community Feedback Tool (Digital)  85
 Total Quantitative Responses  710
 Community Public Event Attendees for
stage 2
 110
 Stakeholder Meetings  4
 Community Council Public Meeting
Attendance
 19
 Total Non-Quantitative Responses  133                                                
4 Census 2022 
7.2 Survey Sample Validation
A total of 710 quantitative responses were received from the island’s population
of 6,498 residents (c.3,328 households)4.  This represents a sample size of
around 11% which is aligned with the 10 – 15% typically received on other
similar projects. This equates to sample size of 16% when considering the
population of Rothesay.
The results are also higher sample rate than those received for stage 1 (45
responses - 1% sample).  
The higher stage 2 level of response is a positive reflection on the additional
methods invested to engage with the community, the value of utilising an
extended six-week consultation period and possibly the extension of the route to
include Battery Place to Glenburn Road.  
These results are despite the event being undertaken during a wet and windy
summers night which will have had an adverse impact on the community’s
appetite to visit the event.
An analysis of the survey responses received is provided in the remainder of this
chapter. The free text comments provided as part of the survey responses are
included in Appendix D.

Page 48

45 | P a g e
www.connectedtp.com 
Stage 2 – Section A - Participant Demographics
7.3 Participants Age
This question was asked as it is important to capture the views of people with
varying levels of life experience and perspectives. 
Of the participant responses received:
 16% were aged under 40 (16% census 2022).
 40% were aged between 40-59 (26% census 2022).  
 33% were younger than 60-79 (34% census 2022).  
 2% were older than 79 (8% census 2022).  
These results highlight that not only have more people participated in the project
but a wide range of age groups across the community have been consulted. The
results indicate a slight over representation of 40–59-year-olds (40% project vs.
26% census).  However, all other age bands are well aligned with the census
2022 for the Rothesay ward area. 
The under 40 years olds are now also better represented when compared with
the stage 1 results (16% stage 2 vs. 8% stage 1).

Page 49

46 | P a g e
www.connectedtp.com 
7.4 Participants Gender
Of the total respondents, 52% were women / girls (52% census 2022) and 37%
as men / boys (48% census 2022).  1% of respondents identified as non-binary,
0.50% were transman and 0.17% transwomen. 9% of the respondents indicated
that they would prefer not to say.
Overall, the results reflect a reasonable cross-section of the community and are
broadly aligned with the census demographic split, albeit slightly less respondents
identifying as men / boys.  A key difference from the stage 1 results is that the
views of females are better represented aligning well with the census data (52%
project vs. 52% from 2022 census). 
7.5 Participants Health
The majority of participants considered themselves to be able-bodied and did not
have a health or disability that impacted on their everyday mobility (72%). No
person indicated they have some health or disability which limits their day-to-day
activity a lot, However, 13% of respondents did indicate that their disability or
health issue would affect them a little. 16% participants preferred to not say
anything.

Page 50

47 | P a g e
www.connectedtp.com 
7.6 Details of Participant Health
Of the respondents indicating they did have a health-related disability, 20%
indicated their disability was related to mobility or stamina but not breathing
related.  
These questions are important to ask as they assist the design team in designing
for all user groups, including those with protected characteristics. 
7.7 Participants Employment Status
Participants were asked to qualify their employment status. This question was
relevant to ask as the design team will need to consider how the project would
support economic activity and support the movement of people to and from
places of work as part of ‘everyday’ journeys.
1% of the respondents indicated that they are currently not employed.  50%
indicated they were employed either part time or full time, 30% indicated they
were self-employed and 18% of respondents said they were retired or not
applicable.

Page 51

48 | P a g e
www.connectedtp.com 
7.8 Results Comparison with 2022 Census
To assist in understanding more about how representative the survey
demographics are, the survey results were compared with the 2022 census5 for
Rothesay.  The results indicate that the project feedback demographic by age and
all genders is broadly comparable with the census analysis noting that the under
21 years olds is a small proportion of the community at only 3%.
Overall, the study results are considered to capture a good sample of the
community, capturing the views of both able bodied and those less able, those in
work and those unemployed or studying.
The results also show an improvement on the stage 1 results with the
demographics presenting a more representative match with the census. This is
partly due to the increased sample size. 
5https://www.citypopulation.de/en/uk/scotland/argyll_and_bute/S52000547__rot
hesay/
7.9 Participants Residential Status
Respondents were asked if they lived in Rothesay.  This question was relevant to
ask as it is important to understand if the respondent is responding with longer
term experience of the community or as a tourist/visitor.  
 70% of respondents are full time residents in the community.
 25% have either lived in the community historically, or visited at least once a
year.
The results indicate that ¾ of the respondents are commenting as longer-term
members of the community.

Page 52

49 | P a g e
www.connectedtp.com 
Stage 2 – Section B - Participant Travel Habits
7.10 Walking and Wheeling between the Pavilion to Glenburn Road
All participants (residents and visitors) were asked how often they currently walk
or wheel from the Pavilion to Glenburn Road. A summary of the results is
presented below.
 45% of the participants said they travel this section less than once a week or
never.
 39% say they travel this route more than once a week. 
 17% indicated they travel the route more than once a day.
Overall, 45% of respondents do not walk or wheel the route regularly. With 39%
using the route at least once a week and 17% using the route more than once a
day.
Overall, the route between the Pavilion and Glenburn Road is not well used
currently by walking or wheeling modes as part of respondent’s everyday travel. 
It may be possible that part of the route is more popular but this would require
further investigation through survey to qualify.

Page 53

50 | P a g e
www.connectedtp.com 
7.11 Cycling between the Pavilion to Glenburn Road
All participants (residents and visitors) were asked how often they travel from
Pavilion to Glenburn Road using a bicycle.
 85% say they never cycle this route. 
 13% say they travel this route more than once a week. 
 1% indicated they travel the route more than once a day.
Overall, more than 85% of respondents do not own a bike or cycle the route
currently. A further 13% travel the route less than once a week with only 1%
cycling regular every day.
The route is therefore not popular for regular cycling as part of everyday
journeys.  Similar to walking results from the previous question, it may be
possible that part of the route is more popular but this would require further
investigation through survey to qualify.

Page 54

51 | P a g e
www.connectedtp.com 
7.12 Parking Along the Route at Victoria Street or Albert Pier
All participants (visitors and residents) were asked How often do they park on
Victoria Street or Albert Pier.  
 25% of the participants said they rarely park 
 12% say they don’t own a car.
 9% said they park once a week, 
 9% also say they park less than once a week, 
 8% park two days a week, 
 8% park 3 days a week, 
 6% of the participants say they park on this route once or more a day, 
 5% park on the route 4 times, 
 5% times a week, 4% park 6 days a week and 
 only 2% park along the route at the weekends only.
Overall, a relatively small proportion of the total survey respondents parked a
vehicle within the study area on a regular basis.  This is relevant when
considering in conjunction with the number of comments provided by
respondents in relation to overall parking deficiency within the study area. These
are qualified later within this chapter.

Page 55

52 | P a g e
www.connectedtp.com 
7.13 Views if the Concepts Offers Benefit to the Community
All participants (visitors and residents) were asked if they felt the proposed
concept design suited the community’s needs?  This question helps us understand
the communities’ thoughts on the appropriateness of the design and their
understanding of the project aims and funding limitations.  
Residents
95% of resident’s respondents who own a car or drive said ‘No’ and 5% of
respondents said ‘Yes’.  2% answered ‘Don’t know’. These results indicate the
community is overall unsupportive of the concept design and the value it may
bring. This level of response, may indicate issues with the concept, concerns
reading change or a lack of understanding of project aims and funding. 
Visitors
Visitors to the island who also drive responded with 86% saying ‘No’ and 14% of
respondents said ‘Yes’. These results indicate that visitors to the community are
also unsupportive of the proposed scheme, but less so than the residents (5%
residents support concept vs. 14% of visitors). The slight difference in positive
opinion might reflect difference in opinion regarding the ‘fear of change’ with
visitors more open to changes

Page 56

53 | P a g e
www.connectedtp.com 
7.14 Views on Concept Community Benefits by Car / Non-Car Drivers
The resident community (only) results were interrogated further to better
understand how their views are aligned with their mobility habits. An analysis of
residents (only) views on the concept designs benefit to the community based on
their preference to own or use a car was examined.
Non-Car Users
A total 17 respondents (5/5%) indicated that they did not regularly use a car.
This is lower percentage of non-car owners than the census 2022 (43%) and
reflects that not all respondents disclosed their use of car.  A total of 59% felt
that the concept design would not offer benefit to the community, with some
expressing concerns relating to the design’s safety. A total of 41% of resident
respondents felt that the concept would offer benefit to the community and
offered a welcomed addition. 
Car Users
A total 292 respondents indicated that they did regularly use a car or park within
the study area. Of these a total of 96% felt that the concept design would not
offer benefit to the community, with some expressing concerns relating to the
value of investing in other more necessary improvements including additional
parking. A total of 2% of resident car user respondents felt that the concept
would offer benefit to the community and offered a welcomed addition.
Overall, it appears that the non-car users are more supportive than car users
(non-car 41% support vs. car users 2%).  The overall number of non-car users is
however much lower than those regular car users reflecting a small sample. 
Additional surveying would be required to assist in qualifying any relationship
between response and car use.

Page 57

54 | P a g e
www.connectedtp.com 
7.15 Views on Concepts Community Benefits by Gender 
The resident community (only) results were interrogated further to better
understand how their views relate to their stated gender. An analysis of residents
(only) views on the concept designs benefit to the community based on their
gender was examined. To aid in reporting, the multiple gender groups have been
combined into two groups, female and male.
Residents
A total 205 respondents indicated they were women, girl or trans female. Of
these a total of 95% felt that the concept design would not offer benefit to the
community. A total of 3% of resident respondents felt that the concept would
offer benefit to the community and offered a welcomed addition. 
A total 165 respondents indicated that they were male, boy or trans man. Of
these a total of 86% felt that the concept design would not offer benefit to the
community. A total of 13% of male grouped respondents felt that the concept
would offer benefit to the community.
Overall, it appears that the women grouped respondents are slightly less
supportive than male grouped of the concept (female 3% support vs. male 13%).

Page 58

55 | P a g e
www.connectedtp.com 
7.16 Views on Concept Community Benefits by Employment Status 
The resident community (only) results were interrogated further to better
understand how their views relate to their employment status. An analysis of
residents (only) views on the concept designs benefit to the community based on
their employment was examined. 
Residents
A total 148 respondents indicated they were not currently employed, retired or in
education. Of these a total of 87% felt that the concept design would not offer
benefit to the community. A total of 11% of resident respondents felt that the
concept would offer benefit to the community and offered a welcomed addition.
2% remain unsure and did not comment. 
A total 232 respondents indicated that they were in employment. Of these a total
of 94% felt that the concept design would not offer benefit to the community. A
total of 6% of respondents felt that the concept would offer benefit to the
community. A total of 1% indicated they were unsure.
Overall, it appears that the employed grouped of respondents are slightly less
supportive than male grouped (not-employed 11% support vs. employed 6%).

Page 59

56 | P a g e
www.connectedtp.com 
7.17 Views on Concept Community Benefits by Age 
The resident community (only) results were interrogated further to better
understand how their views relate to their stated age. An analysis of residents
(only) views on the concept designs benefit to the community based on their age
was examined. To aid in reporting, age bands have been grouped into 21 and
under and 21 and over.
Residents
A total of only 8 respondents indicated they were 21 or under. Of these a total of
25% felt that the concept design would not offer benefit to the community. A
total of 75% of resident respondents felt that the concept would offer benefit to
the community and offered a welcomed addition. 
A total 240 respondents indicated that they were aged over 21. Of these a total
of 93% felt that the concept design would not offer benefit to the community. A
total of 5% of respondents felt that the concept would offer benefit to the
community. A total of 2 % indicated they were unsure.
Overall, it appears that respondents under 21 years are old are more supportive
of the concept.  However, with only 8 respondents, the sample size is noted to be
small and potentially under representative. Those older than 21 are more likely to
be employed and are less supportive of the proposed change.

Page 60

57 | P a g e
www.connectedtp.com 
7.18 Views on Design Measures Supporting Future Walking and
Wheeling
The community (both residents and visitors) were asked, whether the concept
measures are likely to improve opportunities for future walking and wheeling
within Rothesay.  The majority 90% think the design will not result in any
increased walking or wheeling activity.  The remaining 10% support the design
and believe it will encourage more walking and cycling for the community. 
7.19 Views on Appropriateness of Concept with Current Community
Needs
To help us understand how participants currently feel about the concept’s
alignment with current community needs. Respondents were asked if they were
overall pleased with the concept would address current mobility concerns.  These
concerns were raised by the community through the 2016 design charette.  90%
of respondents said they were concerned and thought the concept was
unsatisfactory.  The remaining 10% indicated that they were pleased with the
concept and that it would support the community’s current mobility needs.

Page 61

58 | P a g e
www.connectedtp.com 
7.20 Respondents Views Regarding Perception of Project Value and
Intended Use
The results of the survey feedback were further interrogated to better understand
how the community have responded to the concept.  Each survey response was
interrogated to further understand how well informed the respondents are whilst
providing feedback.  The comments were varied in detail with some statements
including excessive detail, negative slurs, personal attacks on individuals and the
use of explanative language.  These types of response are not typically associated
with a civilised community.
In some cases, and by contrast a proportion of responses included a copy and
paste of a short statement with a clear indication of completing and submitting
the survey as quickly as possible.
From a review of the surveys a number of observations were made.
 A total of 1,686 individual comments were provided6 across the 603 surveys
received.  
 In the majority, most respondents when providing a comment noted they
would prefer the project to be ‘scrapped’ or consider it to be a ‘waste of
money’ (22% of all comments and 62% of all surveys received).  
 18% of the comments suggested changes that are beyond the scope or
reach of the project. These comments would therefore indicate the
respondents lack of understanding of the projects aim, limitation in how the                                                
6 Users were limited to single use IP addresses.
funding can be used.  A number of comments referenced other general
feedback which could also indicate the respondent is making comment
through influence of others.  It was noted through social media that a
number of people within the community were influencing feedback either
through provision of mis-information or seeking to increase their personal
status as community contributors.
These comments have been recorded by the design team as ‘project
misunderstood’ and accounted for just over half of the feedback received. C. 51%
of the total survey responses received.
 A total of 16% of the comments made indicated that the project was not
needed or unwanted.  These direct rejection comments accounted for just
under half of the surveys received (45%).
 A total of 13% of comments indicated that respondents felt the project
would not be used once complete. These comments accounted for 35% of
all survey responses received.
7.21 Respondents Views on the Suitability of the Design
Only 10% of all comments received related to views expressed (positive or
negative) referenced the suitability of the concept design. These comments
accounting for 27% of all survey responses received. 
Details of concept design suggested changes are summarised as follows.

Page 62

59 | P a g e
www.connectedtp.com 
 A total of 6% of comments indicated that the design was ‘too focused on
cycles’ and /or would introduce potential safety concerns. These comments
being mentioned in 16% of all surveys received.
 A total of 4% of all comments received suggests that the project would be
best relocated elsewhere.  Alternative locations were however rarely
suggested.  These comments accounted for 11% of all surveys received.
A summary of the comments received by percentage popularity and a summary
of comments received as a percentage of total survey responses received is
presented in the following charts.

Page 63

60 | P a g e
www.connectedtp.com

Page 64

61 | P a g e
www.connectedtp.com

Page 65

62 | P a g e
www.connectedtp.com 
7.22 Summary of when Responses were Received
Analysis of the timeline of when the surveys have been received was also
undertaken.  This analysis is relevant as it can assist in understanding how the
community have reacted to both the range of engagement methods used but also 
the strength of feeling of the respondents.
It was clear from the stage 2 public event that a portion of the community did
have concerns regarding the concept design and were very vocal to make their
opinions known.
Analysis of the survey entries shows that the majority of responses received were
submitted within the first 48 hours. On the 21st of August 279 (34%) surveys had
been completed on day one. 
A further ‘thank you’ Facebook post was issued by the design team to the
communities group page ‘The Isle of Bute’ and ‘Rothesay, Pavilion To Albert Pier
study page’ following the event.  This increased the survey results by 387 (47%)
to 81% within the first two days.
It is observed following multiple social media public ‘call to action’ posts issued
within the six week consultation period, only a small increase in surveys were
received.  
Ongoing social media debate indicated a lack of support for the scheme which did
not translate into additional survey responses.  It is therefore concluded that the
majority of the population ‘active’ on social media submitted a survey at the study
outset within the first 24 hours with the limiting ‘one survey per IP address’
preventing repeat survey submissions.
The results in combination with the low level of stage 1 feedback, indicates that
the majority of surveys have been completed by a ‘group’ of the community
active on social media and generally unsupportive of the project.
The timeline analysis of response is shown in the following chart.

Page 66

63 | P a g e
www.connectedtp.com  STAGE 2 - COMMUNITY FEEDBACK TOOL (CFT) RESULTS

Page 67

64 | P a g e
www.connectedtp.com 
8 STAGE 2 - COMMUNITY FEEDBACK TOOL
(CFT) RESULTS
8.1 Summary
A total of 85 additional responses (stage 2) were received through the
Community Feedback Tool (CFT) for the stage 2 consultation (110 total).  The
responses were provided anonymously.
Participant's comments were located along the route.  Comments covered a wide
range of subjects including providing challenge on the detail of the concept
operation with a focus on septic tank conflicts, parking and access to the church
and approach to the project.
The stage 2 CFT feedback received is presented by location and verbatim in the
following figure and table. Each stage 2 comment reference is shown in the
figure.  
Stage 1 comment reference are not shown in the following figure to avoid
confusion.

Page 68

65 | P a g e
www.connectedtp.com 
Stage 2 -Community Feedback Tool comments by location (all comments)

Page 69

66 | P a g e
www.connectedtp.com 
 
 24
 The council already have a problem funding existing flowerbed.
Introducing more flowerbeds beds will not be well maintained in the
future. Getting the existing pedestrian infrastructure into good order
should be a priority. The pavements and footpaths are dangerous
especially in Montague Street. I wouldn't like to have poor eyesight
when trying to navigate my way around bad paving slabs.
 25  First this area is used by the fair every year, where is it to go. Second it is
ideal for walkers with without dogs, cyclists and pedestrians do not mix.
 26  As people get older, they tend to rely on wheelchairs or even mobility
scooters to get around. Narrowing the pavement in this plan will make it
more difficult for them and other pedestrians. I would be extremely
surprised if such a proposal to narrow a pavement (which the pavement
parking ban is trying to address) could pass any competent equality impact
assessment. Narrow pavements are also a problem for people with prams.
 27  Do not impose floating pavements - where pedestrians/ bus passengers
have to negotiate the cycle path in order to get on/ off a bus. RNIB are
running a campaign highlighting the dangers of these crossings for bus
users - especially those who are elderly or have visual impairments.
 28  There is definitely conflicting views about the track. Your plans on this site
show the paths which are already round the promenade area and not the
plans which have been produced for the front page of the local paper. Local
people realise that this money is confined only to the Cycle Path but what
about the condition of the pavements. Are you going to repair the parts
where the track has to go and leave the rest in a bad condition?
 29  Along this stretch of pavement local residents and holiday makers actually
walk but you are making this pavement smaller - are parents/grandparents
out walking with prams meant to walk in single file and not communicate to
anyone along the cycle route? What about people with disabilities - are they
meant to walk/manage wheelchairs for example next to cycles whizzing
past? What about residents with hearing difficulties and accidentally wander
into the track. Will you make bikes have loud bells on them? Please do not
return the advice that people could walk on the prom part as if weather is
inclement this is not viable: this part of the prom was blocked off to vehicles
etc due to part of it being unsafe. This whole cycle route will be a disaster
for residents and despite what you say you are not listening to residents.
 30  You have omitted to change this since the last consultation where you were
advised that the ferry terminal can be very busy and cars are parked to as
near the road as possible, leaving enough room for pedestrians to cross. It
was a pity that you were not here during the Highland Games to see the
volume of traffic. If you put the cycle lane at this part where are pedestrians
meant to cross or are you trying to make Bute residents cross where you,
who do not live on the island or actually listen to the residents, decide we
have to cross.
 31  Council can make extra parking places here but there is a crossing which
dictates how near cars can be to the crossing, unless you wish everyone to
break the law.
 32  Increased parking for coaches means you are reducing parking, which is at
a premium, to cars. Where are residents meant to park? The other side of
the road you intend to put in more parking places which is something the
council could do as they will collect the money from car parking places. You
are only talking about two extra spaces at the most at this location. 
 33  Where are pedestrians given the right of the pavement which they are
entitled to? Are parents meant to keep youngsters on a short leash so they
do not stray on to the proposed cycle path? 
 34  An overflow carpark for the pier should be considered but never at the
expense of the winter gardens. This area has HUGE cultural significance to

Page 70

67 | P a g e
www.connectedtp.com 
the island and it must never be used for anything other than recreational
use. 
 35  With the increase in volume of motors on the island this year, when the pier
is full cars are seen overflowing along Victoria street. The weekend of
butefest saw motors cue to the pavilion. the narrowing of the road for a clue
path will create more issues for island residents 
 36  Due care and attention is required around the town cenotaph. A cycle lane
along front of this monument is a sheer mark of disrespect. 
 37  More Cobble stones should be installed as a traffic calming measure.
 38  Removing parked cars from this pavement will certainly be more sightly.
However, with homes and guest houses along battery place, homeowners
will have nowhere to park. 
 39  Narrowing of road is not advised, even if cycle lanes were installed, road
cyclists will not use them and will make road conditions more dangerous
when overtaking. With the narrowing of the road along Victoria street,
visibility will be worse for larger vehicles(tractors, HGV, bin lorrys,
Emergency services) spotting pedestrians 
 40  Parking heavy buses on the seawall is not advised 
 41  Any new area of pavement created will require bollards to prevent
pavement parking. 
 42  Create more car-parking (not less) for tourists bringing their tourist money to
Bute. Formally permit pavement parking (permitted and tolerated for years)
on the ocean-side pavement of E Princes St and Battery Place. Guest
houses and hotels in Battery Place already suffer with inadequate street
parking. This proposed cycle-lane plan makes it worse. Eventually, all
Rothesay businesses will suffer when guest houses can't attract Bute
visitors for lack of parking.
 43  Pedestrianise Montague Street, reduce through traffic to
residents/shopkeepers and deliveries with moveable bollard.
 44  Victoria Steet should foster designs utilised in Montague street that work to
subtly reduce speed of traffic. Road is level with pavement, reduces car
priority, pavement is maintained across side streets to denote pedestrian
priority. Ambiguity in road design can work well to encourage drivers to be
more courteous and considerate.
 45  The 3 coach parking bays on the harbourside would block the view to the
harbour for local cafes. Additionally more difficult for coaches to manoeuvre
in and out.
 46  I think that Rothesay already IS a 20 minute neighbourhood, but even if it's
not - I have a query about why the Promenade (broad, runs from Pavilion to
Ferry Terminal) is not being utilised for this? Similarly, on the other side,
there is the pavement at high level and a lower level path - can't one of
them be utilised as cycle path. Narrowing the road (which is already pretty
narrow) feels like the wrong option.
 47  Speed bumps need to be installed or speed cameras . Daily witness
vehicles r speeding along here .
 48  Persistent inconsiderate parking long term by large motor homes block the
pavement at Albert Pier just past the phone box. Albert pier also currently
used as a dumping ground for unused trailers and the odd caravan when
not being used. What is happening to the derelict building?
 49  Taxi rank must be sustained to allow for 11 taxis (current level)
 50  Make the lights pedestrian and traffic flow controlled. The crossroads are
busy and getting across can be challenging
 51  Toilets at Albert pier need demolished and for it to have proper spaces for
coaches as they currently have to park up on the pavement

Page 71

68 | P a g e
www.connectedtp.com 
 52  Need to ensure enough spaces for taxi rank
 53  Must allow for parking / pulling in to drop off passengers for when Pavilion
reopens
 54  Albert Pier area is a weed strewn mess. Any chance of sorting this building
and getting the fences down?
 55  Trying to cross the road at this roundabout is difficult.
 56  Will Camper Vans and motor homes be moved off the pavement at East
Princes Street
 57  Ferry Traffic makes this side of the road difficult to cross.
 58  The cobbled area at the pier side of Guildford Square is too difficult to
negotiate in a wheelchair comfortably or safely. The zebra crossing kerbs
need to be dropped more. Crossing most of the roads on the way along
from the start of the town at battery place to the pavilion can be very difficult
in a wheelchair and potentially unsafe as the chair can get stuck, the
dropped kerbs are not dropped enough in some areas and as a result can
be painful. There is also difficulty in accessing dropped kerbs due to drivers
parking inconsiderately beside them. Please allow some dropped kerbs
along the way on the opposite side of the road to the intended route for
wheelchair users to be able to cross safely from.
 59  If you want to promote cycling why not look at providing a safe cycle path
from the Port to Ettrick? A very popular route and you could use the existing
overgrown walkway 
 60  This is a waste of money as we have a wide promenade where you can
cycle already or road is perfectly safe to cycle. 
 61  Cyclists that come onto the island will not use a cycle path as they will be
happier on the road and will be travelling much further than the cycle lane
and will be travelling faster than safety would allow. I’m not really sure who
this path is designed to be used by? It doesn’t go anywhere and anyone
accessing it will have had to ride on the road to get there…. Riding through
Rothesay is not dangerous but mixing cycling and pedestrians is. 
 62  This entire stretch of Battery Place includes a large number of guest houses
/ B&Bs, and multi-story apartment buildings. Consequently there is
insufficient parking on the inland side of the road, as a result of which many
cars park on the wide pavement on the shore side of the road - not out of
disregard for the law, but out of necessity. The proposed plan offers no
relief to this situation, but in fact makes it worse, but turning the roadside
half of the shoreside pavement into a cycle path, which would therefore
make it doubly an offence for cars to park there. Thus the plan (debateably)
enhances the experience of a tiny minority of cycle users, at the expense of
a very substantial number of resident vehicle users. 
 63  How’s about making the taxi rank better looking and en outing for electric
taxis
 64  Argyll & Bute Council's prime consideration should be first and foremost for
the residents before accepting external funds for a vanity project that
benefits few but adversely impacts on the lives of residents in E Princes
Street and Battery Place. For many years parking has been allowed on the
ocean-side pavement where this proposed new few hundred yards of cycle
track is to be. Despite the law prohibiting pavement parking that A&B
Council will be enforcing by the end of 2024, it is quite within the power of
the Council to legitimise parking on the ocean-side pavement so that
residents can continue to live harmoniously instead of squabbling over few
remaining parking spots. With government encouragement, over the years
houses have been sub-divided into multiple occupancy. Where there was
once a three-storey home with perhaps a maximum of two vehicles, there
are now properties along Battery Place that have been sectioned off into 3,
requiring parking for up to six vehicles. E-Princes St to the end of Battery
Place requires and deserves parking both sides of the road. A&B Council

Page 72

69 | P a g e
www.connectedtp.com 
have the power to do this instead of considering a non-sensical cycle track
along this route and a ridiculous waste of tax-payer money to simply
redesign the coach parking and car parkings and rip up characterful
cobbled paving to replace with unsightly tarmac. Why is this plan also
reducing the number of taxi stands from eleven to four? Are the taxis to
double-park elsewhere? There are simply too many bad elements to this
proposal.
 65  I have a separate question which we need to start a community chat about.
The question: Is Argyle and Bute Council the most incompetent Council in
Scotland? From all the holiday resorts in Scotland I have been to the areas
the council are responsible for looking after are easily in the worst state of
repair. Any repair they do undertake is half finished and barricaded with
Herras fence. Rothesay is becoming like a building site where all the Herras
fencing will eventually join to encircle us! A resolution to an actual problem
would be useful. Middle of the busy season or any other season for that
matter is there any difficulty walking or cycling from the Glenburn to
Rothesay? None I have ever seen. So what exactly is the problem being
resolved here? The resolution of a non problem is clearly causing many
actual problems for real residents and holidaymakers. Many roads have one
pavement. Battery place has 3 and one of them is wide enough to fit a bus
and still have space to walk and cycle on but somehow Battery place needs
more space for walking and cycling. Have the designers been to Battery
Place? There are very few side streets so no real alternative for parking.
This proposal needs to introduce full parking both sides of the road all the
way along east Princess Street and Battery Place and beyond. This affects
so many businesses, residents and holiday makers. Hotels, B&B’s, cafes,
working people. Some of the residents may be retained fire fighters for all
these designers know. They need access to their vehicles!
 66  The scheme appears to have limited thinking it neither adds to Rothesay
being a contemporary destination with ease of access, nor does it add to
the connectivity of the town. The current scheme ignores the awesome
opportunity of integrating the promenade with a cycle path. the island has
more mobility scooters and access to the promenade is a bit tortious in
places, so any improvement would be a benefit. Overall the proposed
scheme does not connect anything for people in town, what would be of
benefit would be a cycle pathway from the ferry to the school, connecting
the doctors, the hospital and the health center 
 67  Battery Place towards to Glenburn Hotel do not need a cycle lane to cost
more space problem which is already has. As there is most B&B located
here, business need the car park space. Passed weekend just between 3
B&Bs there are 40 car space needed on both side road plus car space for
residents alone the road. This plan will not benefit anyone on Rothesay.
The pedestrian pass along the seafront is enough and safe for people walk
pass Battery Place. 
 68  Road is far too narrow for large vehicles passing or when cyclists who will
use the road 2 abreast it will be impossible to pass them leaving 1.5m
 69  I think extending the pavement in front of vehicle access to the pier and
ferry will cause chaos.
 70  Waste of money in my opinion. Will cause more problems than benefits.
Bute is already a safe cycling zone and the distance you have proposed is
ludicrous.
 71  This whole scheme is not suitable for this area. It will cause congestion and
difficulty for pedestrians to walk along this area. Emergency vehicles going
to emergencies will also have difficulty passing this area. Where will people
park their cars, especially guests at hotels and b&b’s? It is not required and
a complete waste of money. It will also impede entrance to the ferry
terminal. There are many more reasons not to go ahead with this proposal a

Page 73

70 | P a g e
www.connectedtp.com 
main factor being none of residents living on the island neither want it or
asked for it.
 72  Parking is very limited as it is. Residents/businesses require parking that
sustains all.
 73  This is a complete waste of money. There is a high proportion of elderly
people on Bute and narrowing the pavement and road for a cycle lane that
would be seldom used at the expense of what is already there and
adequate for prams, mobility scooters and wheelchairs is just virtue
signalling at it’s worst.
 74  Cars parked on one side of the road and on the pavement at the other side
of the road. Cars continually speeding at ridiculous speeds along the road
and it's only a matter of time before someone is seriously injured or killed.
 75  Not enough spaces for the amount of taxis that the island currently has
 76  This junction is bad enough at the moment for near misses, it will only result
in a few crashes if they make the roundabout smaller/ reduce sightlines
 77  This whole scheme needs to be abandoned, the vast majority of the
community are against it
 78  Absolute nonsense. This will cause chaos at Battery Place and badly affect
businesses there. There is approx 20 miles of safe cycling road on the
island.
 79  Loal residents and accommodation businesses need the parking that will
disappear from Battery place. Note the word 'need', there are no
alternatives. This section at least must be cut from the plans.
 80  New roundabout is far too small for buses to turn around.
 81  If the public transport service was better then perhaps less people would
drive. This would lead to less cars on the roads and make it safer for
cyclists without the need to cause enormous disruption to create a cycle
lane where it is not necessary.
 82  The town in general needs adequate parking.
 83  The pavement between between Ettrickdale and Ardmaleish has been
broken and extremely unsafe for years, this has to be addressed.
 84  Public gardens and verges should be maintained to ensure the town is
presentable to all visitors.
 85  All railings along the sea front areas are in dire need of repair. They are not
only unsightly but unsafe.
 86  It's quite obvious from all the comments by residents and business owners
along E Princes St and Battery Place that car-parking is a major problem.
This needs to be addressed by Argyll & Bute Council. This proposed cycling
path along Battery Place simply creates more of a resident problem with
parking in favour of a minority of possibles that might actually use this cycle
path before it evaporates at the Glenburn Hotel. Argyll & Bute Council,
listen to your rate payers!! Bin this part of the cycling lane proposal along E
Princes St and Battery Place and, instead, legitimise the parking on the
ocean-side pavement (already wide enough to be shared by parked cars
and pedestrians). Will you listen to residents? Or will you bulldoze through
your vanity project?
 87  This Rothesay Pavilion to Glenburn Road Walking and Cycling Project
proposal appears to simply involve an expensive rearrangement of parking
at Albert Pier without much gain (if any) in additional parking. The proposal
for a cycling lane along the ocean-side pavement on E Princes Street and
Battery Place is bad, ill-conceived and detrimental to residents in so many
ways. It’s dangerous and is a huge waste of taxpayer money. Cyclists
currently share the road with motorists. Over the past few years there has
been wide publicity to ensuring cyclists rightly receive better courtesy,

Page 74

71 | P a g e
www.connectedtp.com 
awareness by motorists, and protection to avoid collision with motorists to
the extent that nowadays any cyclists sharing the road in Battery Place are
given a wide berth when overtaken by motorists. This proposal now has
cyclists sharing a dedicated path with pedestrians. Whereas before there
was little chance of a cyclist colliding with a pedestrian, a dog or a child
there is (by the very design of this proposal) an increased chance of this
happening. This proposal continually touts increased parking as one of its
benefits without referring to the fact that parking along the ocean-side
pavement will be permanently lost for up to as many as 30-40 vehicles in
high season. Yes, there is government legislation banning pavement
parking, but Argyll & Bute Council has the power to legitimize parking for
vehicles on the E Princes and Battery Place ocean-side pavement which
would be consistent with what has been allowed for decades. Over the
years various governments have encouraged the conversion of houses into
multiple flats. This has occurred in Battery Place. Where there was a single
house with a parking need for one or two motor vehicles, houses have been
converted into three flats (for example) resulting in the parking need for
many more vehicles at the same address. With no other parking available,
residents and businesses have for decades been allowed to park on the
ocean-side pavement along E Princes Street and Battery Place. The
concerns of residents and businesses for parking need to be addressed by
Argyll & Bute Council. It’s not debatable whether there is a need for parking
on the ocean-side pavement along E Princes Street and Battery Place. The
merits of this cycling path proposal are, however, highly questionable and
debatable as to whether it should exist here at the expense of required
parking. In Battery Place this vast pavement is 4.60 metres wide, certainly
enough for pedestrians to stroll along shared with parked cars. A stationery
car must surely be preferable to walk past for pedestrians than having to
share the path with cyclists travelling toward them silently and at
speed…often unsighted. It’s easy to envisage an infant or dog straying into
the path of a cyclist with this proposal. A collision is inevitable. And how
might a cyclist take immediate evasive action? Duck off the cycle path and
onto the road into the path of an oncoming vehicle? If the avoidance of a
potential cyclist/motorist collision is a prime motivation for this cycling path,
why not have cyclists share the promenade with pedestrians. It is 3 metres
wide and completely removes any possibility of a cyclist and motorist
collision. But, is there really any need for a cycle path along this short
stretch of road at all? The inevitable question that needs to be raised with
this proposal as it affects the stretch of road along E Princes St and Battery
Place is “Why?” A lot of taxpayer money is going to spent to achieve what?
Are cyclists really going to benefit from a few hundred metres of cycling
path that ends at Glenburn Road? Are pedestrians better off sharing the
pavement with cyclists? Would pedestrians not be safer and better off
sharing the 4.6m wide pavement with stationery cars than with cyclists?
Would the residents of E Princes Street and Battery Place not be better off
with formalized, legalized parking on this pavement instead of losing it?
 88  Buses currently move into layby, thus avoiding congestion along Victoria
Street. With this plan, a bus pulling in will cause the traffic to come to a halt.
 89  People getting off the buses will be forced to walk across the cycle path
 90  Must maintain Taxi Rank "As Is" to cater for all taxis on the island. Proposal
is for 4 spaces, but there are regularly 5 taxis in place waiting for the ferry,
and there are 10 licensed taxis in the town. Taxis are important to foot
passengers, many of whom are either elderly or have youngsters with them
 91  Would not want any changes made to the Winter Gardens or putting green
area. This is a tourist attraction in a tourist town and should be considered a
conservation area
 92  I can see no provision for parking along this section of the proposed route.
The council has not considered the needs of local residents

Page 75

72 | P a g e
www.connectedtp.com 
 93  I think for this junction, that pedestrians and bicyclists should not have a
route across the ferry lanes; that is, the North facing side remains dedicated
to vehicle traffic, and that the north-west and north-east edges get their
walls extended to section off the ferry ramp from non-vehicle traffic. I am
also not in favour of the access to/from the ferry lanes getting smaller.
Then, the pedestrian/bicyclist/other get a route from the north-west corner
across victoria street, across the high street onto the north-west corner of
Guildford Square, and back onto the north-east corner of the junction. I
think this helps focus Guildford Square as a starting/stopping point or a hub
of travel on the route, along with it's other travel connections, and I think
improving the separation between vehicle and non-vehicle traffic in the
north facing area of the junction, without restricting ferry lane access is a
benefit.
 94  Difficult to see how the coaches parked here (according to the plan) will be
able to U-Turn in order to return to the ferry, given that the proposal is to
narrow the road to "Standard". Note that the coaches would also have to
cross the cycle path and footpath
 95  Putting marked parking bays in Victoria Street will encourage the
introduction of pay and display or other such chargeable parking. This will
make it expensive to visit the town. We don’t want it !!!
 96  You said that you intended to narrow the road to a "Standard Width". Have
you considered the wider vehicles such as tractors and trailers that regularly
have to use this stretch of road from Argyle Street through Victoria Street
and all the way out to the Glenburn?
 97  How well will this be maintained afterwards? Who will pay for the ongoing
maintenance Will it be allowed to decay like the pavements on Montague
Street and Guildford Square?
 98  Rothesay is supposed to be a designated Conservation Area - Are you
REALLY going to dig up and remove the historic weigh bridge ?
 99  How wide will the parking spaces be? The map doesn't seem to be to scale
 100  Proposed parking spaces on this corner - Will they be wide enough for
modern cars?
 101  Increase the availability of parking spaces by enforcing restrictions on those
who dump cars here, park trailers and caravans, carry out repairs. Employ a
permanent traffic warden.
 102  This extension appears to be a complete waste of money. There is a
beautiful walk for pedestrians right along the sea front which could be
improved. Improved parking for residents/island visitors staying at the
numerous guest houses would be far more beneficial than a short length of
cycle path to the Glenburn Road. The real danger is that you simply
encourage people to park on the road further down therefore creating a
much more dangerous environment for pedestrians and cyclists.
 103  Move some of the taxi parking from Albert Place into this area
 104  Reduce the unnecessarily wide, and poorly maintained, pavement area in
front of the job centre and telephone exchange to provide an additional and
legitimate car parking area. This would be extremely useful for visitors to
the castle and relieve car parking pressure elsewhere near to the busiest
areas of the town.
 105  Where do all the other taxis park if there are only 4 spaces?
 106  Making the roundabout smaller will make it near impossible for buses and
larger vehicles to turn round 360 degrees as they frequently do without
some element of reversing therefore creating a new hazard.
 107  Would rather you spent the money repairing the pavement/railings along
Ardbeg Road which was washed away in 2021. Temporary repairs are now

Page 76

73 | P a g e
www.connectedtp.com 
3 years old. This repair should qualify for the funding you are chasing for
this monstrosity that the majority dont want

Page 77

74 | P a g e
www.connectedtp.com 
Summary of Respondents Views by Category
In order to enable processing of the wide range of comments received, an
analysis of the CFT comments received was undertaken.  From an initial review of
the comments a number of categories were developed to assist in categorising
comments into a format that would assisting reporting. These comments reflect
categorise the design team believe best summaries the points being raised in the
comments.  
By grouping comments into categories, a better understanding of the
communities’ overall views on the concept can be understood.  
Each individual locational specific comment will be utilised as part of any stage 3
design development.
A review of the data indicates that:
 43% of the comments made related too issues beyond scope of the
project. This may include funding or considerations for a different route.
These comments accounted for 28% of the total CFT comments received. 
The proportion of comments is noted to be broadly comparable to those
received via the survey feedback and again indicates a lack of community
understanding of the projects aims and limitations.
 32% of the CFT comments related to parking concerns (21% of all CFT
comments).
 10% of the comments related too the concerns of the extended scheme
to Glenburn Road (6% of all CFT comments received)
 22% of the comments expressed concerns regarding road safety. 20% of
the comments received expressed a concern for road geometry. Both
these items accounted for 14% and 13% of the total CFT comments
received. 
 11% of comments related to the scheme not being value for money
whilst 14% of all comments received were related to congestion or
operational concerns. This equates to 7% and 9% respectively of all CFT
comments received.
A summary of this analysis by reported category is provided in the following
charts.

Page 78

75 | P a g e
www.connectedtp.com

Page 79

76 | P a g e
www.connectedtp.com

Page 80

77 | P a g e
www.connectedtp.com  STAGE 2 – STAKEHOLDER FEEDBACK

Page 81

78 | P a g e
www.connectedtp.com 
9 STAGE 2 - STAKEHOLDER FEEDBACK
Following the public engagement process, the emerging network was refined
through a workshop with key stakeholders. A range of engagement methods
were used for each group. These included:
 Face to Face meetings;
 Digital meetings; and
 Emails of proposals / details.
9.1 Project Consultees
A summary of the stakeholder engagement action by group and feedback
received is summarised as follows: 
 Consultee  Summary
 ABC Roads  Four workshops / meetings in total
concluding with no issues with
resulting concepts as presented to
the public.  
 ABC Fleet Public Transport  No known issue
 ABC Outdoor Access  No known issue
 ABC Planning  No known issue
 ABC Marine Operations /
Piers and Harbours
 Consulted. Summary provided.
 ABC Youth Services  No known issue
 ABC Community
Development Team
 No known issue
 ABC Economic Development  Consulted. Summary provided.
 Rothesay Community
Council
 Consulted. Summary provided.
 Bute Bid  Consulted. Summary provided.

Page 82

79 | P a g e
www.connectedtp.com 
9.2 Argyll and Bute Network Management (Workshop 2)
 Due to carriageway construction and drainage arrangements, developing the
route on the A844 route on coastal footway side was agreed to be the
preferred route option.
 The operational carriageway width should be maintained at 6.5m in width
(5.5m is standard minimum) to give extra space allowance for HGVs and
Buses.  It was agreed that reducing the road width to 6.5m would improve
pedestrian crossing opportunities and help encourage lower vehicle speeds.
 Noting the potential impacts of the concept on the ferry queue area, the
Harbour Master and CalMac operator should be consulted to understand
better any operational impacts.
 Improvements to parking capacity along the route are supported. Any
changes should consider seasonal parking impacts and the demand for
coach and camper van parking where possible.
 Improved access options should explore the use of ramps and avoid the
suggested gate in the sea defence wall. This will improve connectivity for
cyclists and wheelchair users to access the winter gardens from the CalMac
terminal.
 The trees located along Victoria Road should ideally be retained as the public
may have concerns regarding removal.
 There is no limited to no scope to revert the roundabouts on the A844 to
Priority T-junctions. The town operates as a one-way gyratory and noting
the industrial activity to the north, the roundabouts must be retained to
support industrial traffic access onto the A844 from Bishop Street.
 It was agreed that there is scope to repurpose road space to better
accommodate different user groups.  This should ideally avoid the need for
the design to be widened into the front green / gardens.
 Any redesign of Albert Pier car park to maximise car parking capacity is
desirable.
 Exploring the use of herringbone parking layout solution at parking area
opposite Albert Pier should be considered.  End-in parking is undesirable and
should be removed through the design process due to safety concerns
relating to vehicle manoeuvring. This will most obviously impact on the
existing taxi rank.
Based on the feedback received, the concept design was developed considering
the above noted points.  The emerging design was again subject to review by
ABC network management and maintenance representatives.
9.3 Argyll and Bute Network Management (Workshop 3)
A third stakeholder workshop was held to discuss the approach to review the
emerging concept. The following points were noted:
 Due to limited road space, a cycle buffer strip width of 0.5m is promoted in
lieu of the 1m required for the road speed limit.  This change was suggested
acceptable noting the majority of the route would be subject to parking
restrictions which would limit cars parking adjacent to the cycle route.

Page 83

80 | P a g e
www.connectedtp.com 
 The accommodation of the design within the existing carriageway kerbing is
noted to significantly reduce drainage concerns and overall project
construction costs.
 The proposed ramp solution at the sea defence wall just behind the Winter
Gardens in lieu of steps will provide improved connectivity between the
Esplanade and the CalMac terminal.
 The introduction of a drainage system is an option that ABC would support
but would increase the overall capital cost of the project.
 Improved and formalised parking capacity was welcomed.  The formalising
of on-street parking is noted to be a benefit. The improved parking capacity
at Albert Pier was noted to be beneficial. 
 Parking impacts at Albert Pier should be subject to further conversations with
ABC Economic Development team to confirm ABC aspirations to provide
additional coach parking.
 The Scottish Water building within the Albert Pier car park must be retained.
The design should be revised to include this.
 There is limited scope to resize the existing roundabouts but changes can be
considered subject to vehicle tracking analysis to ensure access by larger
vehicles can be maintained.
9.4 Caledonian Macbrayne Ferry Operations and ABC Piers and
Harbours
A stakeholder workshop was held to discuss the concept and proposed alterations
to the ferry terminal junction and emerging concept. The following points were
noted:
 Supportive of concept overall;
 Have not been involved in previous Ferry Terminal to Joint Campus route
and have therefore not previous viewed the proposed junction design
produced at that time;
 Would prefer to see introduction of overhead gantry drive information
system also;
 No concerns raised regarding full time signalisation of all approaches;
 Noted the improved layout of the access junction is likely to reduce
marshalling support necessary at peak times.
9.5 ABC Economic Development
A stakeholder workshop was held to discuss the concept and proposed alterations
to Albert Pier and Coach Parking. The following points were noted:
 Supportive of concept overall;
 Kiosk at Albert Pier is currently being demolished. No fixed proposal for use
of space;
 Scottish Water building on the pier is to be retained;

Page 84

81 | P a g e
www.connectedtp.com 
 Potential to increase coach parking from current 3 bays.  No details yet
available;
 Noted condition of the pier and structural integrity would need to
investigated art next stage;
 Noted ambition to include public shower and changing facility within the pier.
Details not available although it was agreed that the proposal will have a
‘small’ footprint and could likely be located within the concept.
9.6 Non-Council Statutory Consultees
A summary update of the non-Council stakeholder feedback received is
summarised as follows.
9.7 Community Groups
Community groups have been engaged through the public engagement process.
9.8 Rothesay Community Council
Three stakeholder workshops were hosted to discuss the concept. The following
points were noted:
 Group is supportive overall of concept overall;
 Would like more time to consider Front Green opportunities within the
project;
 Concerned regarding the use of the coastal side footway from Albert Pier
to Glenburn Road during inclement weather and high tides as the
footway can be flooded by waves and sea spray.
 Welcomed additional parking;
 Noted that peak season use of ferry terminal creates significant
operational challenges.  Concerns offered relating to increasing number
of car-based ferry journeys and limited infrastructure to accommodate
vehicle waiting to board the ferry.
9.9 BUTE BID
Two stakeholder workshops were hosted to discuss the concept. The following
points were noted:
 Supportive overall of concept overall;
 Unaware of Ferry Terminal to Joint Campus proposal;
 Concerned regarding impact of scheme on pavement parking from Albert
Pier to Glenburn Road. There are many B&B businesses that rely on car
base access and parking to operate;
 Would welcome additional parking;
 SEPA  Not Consulted. No change to
road surface area or water runoff
are proposed. No change to
existing watercourse.
 Scottish Water  No response received
 SSE  No response received

Page 85

82 | P a g e
www.connectedtp.com 
 Concerned regarding the use of the coastal side footway from Albert Pier
to Glenburn Road during inclement weather and high tides as the
footway is regularly flooded.
 Noted that peak season use of ferry terminal creates significant
operational challenges.  Concerns offered relating to increasing number
of car-based ferry journeys and limited infrastructure to accommodate
vehicle waiting to board the ferry.
9.10 Traditionally Harder to Reach Groups / Individuals
The Royal National Institute for the Blind (RNIB) was again attempted by phone. 
The resulting call confirmed that there is no specific representative for Bute
available to discuss potential design impacts.
It is noted that feedback received does include representation by minority groups
and those with protected characteristics.
9.11 Landowners and Affected Parties
It is noted that the scheme is located within the public adopted road.

Page 86

83 | P a g e
www.connectedtp.com 
10 OUR LESSONS LEARNT
During the engagement plan, records of each activity were maintained to assist in the evaluation of how effective the engagement process has been.  The review
process included a single design team workshop session, where the teams’ thoughts and ideas were shared to assist in ‘destressing’ and improving future engagement
both during Stage 1&2 of this study but also all future studies.  
The summarised results of the workshop sessions are summarised in the following table.
 Observation / Issue  Mitigation
 Face to Face meetings have been most effective in supporting feedback  Maximise time within the Community
 Lack of engagement with traditionally harder to reach groups  Work with care centres to capture views of older and younger community members
including those with registered disabilities 
 Under representation from younger adults  Focused workshop with younger adults during Stage 2
 Use of digital engagement materials, podcast, flythrough offers greater
audience participation 
Progress service offers in the future using more interactive digital material
 Facebook and social media study page offers limited value to project
feedback and are best reserved for use as event advertising 
Use community pages as alternative to study page
 Mis-information distributed via social media cannot be controlled if
using community social media pages 
Minimise messaging and provide references. Social media also provides an "echo
chamber" for views and can encourage some respondents to adopt views of the loudest
voices rather than taking the time to fully understand the project for themselves
 Project materials note being effectively engaged with or understood  Consider using easier to understand materials to assist the public to engage with the
materials provided.  Options include videos and infomercials as alterative to presentation
boards
 Terminology including "active travel" and "wheeling" are not well
understood across the whole community 
Consider use of project language. Avoid use of Active Travel and explain on wider
mobility improvement in plain English
 Working with local press can influence the effectiveness of published
information.  Reporters will revert to ‘making up’ information to fill in
blanks. 
Provide press information pack. Work with press reps direct
 Survey questionnaire design too long to be completed effectively.   Reduce the number of free form responses to aid in survey analysis. This introduces a
risk that the public perceive a ‘closed’ already decided survey.  Open form format
questions must be character restricted to 100 characters max.

Page 87

84 | P a g e
www.connectedtp.com

Page 88

85 | P a g e
www.connectedtp.com

Page 89

86 | P a g e
www.connectedtp.com 
APPENDIX A – PROJECT HANDS UP SURVEY RESULTS

Page 90

87 | P a g e
www.connectedtp.com 
APPENDIX B – STAGE 1 AND 2 PUBLIC EVENT ATTENDEES LIST (EVIDENCE)

Page 91

88 | P a g e
www.connectedtp.com 
APPENDIX C – ISLE OF BUTE NEWS SAMPLE EXTRACTS 
Isle of Bute news front cover / Page 6 - August 23rd
Isle of Bute news page 5 –October 4th

Page 92

89 | P a g e
www.connectedtp.com 
APPENDIX D – STAGE 2 SURVEY COMMENTS 
Within the Stage 2 survey respondents were offered the opportunity to provide a free text comment to three questions.  Each respondent had the opportunity to
provide multiple comments to each question. 
How is the design aligned with the needs of the community?
Very happy with the design
I think this design is almost perfect just needing some changes
I think this design makes it a way better experience for anyone on a wheelchair or just walking 
Creates a space for cyclists to ride without worrying about cars allowing more uneasy or scared bike riders to get out and ride.
very good
I'm really pleased with the design I like the design for the cycling route 
you don't need much space for cycling so yeah 
Key areas are hit, and will improve the speed of the roads.
The cyclists are discouraged to cycle as drivers are a tad too reckless, this would boost the quantity of cyclists & decrease and no. cars on the road.
im quite pleased with how to design is aligned
erterged
gfdgdsfgsdg
Concerned that this short section doesn't sufficiently benefit the community, a sign making the prom shared between walkers and cyclists would cost the price
of a sign and the money put towards the section up to school
i would like it if there was more nature
well done
The community needs, stuff for young people to do, not a pointless late for 50 year olds in lycra
Wasted money!
Not needed 
Not needed, waste of money 
This will only add further pressure to the town and surrounding areas to park your vehicle 
It's just a con like the Simpsons monorail 
We have been fine for years why would you try and mess up a good system. Ohh I know to line pockets with gold 
Not needed
This does not need to happen. Better more important things these funds could improve/fix
Waste of time and money, the saying don’t fix what isn’t broken springs to mind
Whoever is in charge has not contacted business at all to see how this would affect us

Page 93

90 | P a g e
www.connectedtp.com 
It does not align with the needs of the community and you don’t seem to want to listen
Yes, front needs to be improved and design will help develop a more pedestrian front 
There is no need for this project, certainly not bikes on the island to justify such a large cost undertaking 
This will not improve anything, will just include a huge cost and massive disruption to the island. 
‘The community’ does not want, nor need, this.
Utterly ridiculous, uncalled for, waste of funds.
Not needed
Not needed the pavilion to pier already has esplanade that could be used and all along battery place has a wide pavement and a footpath 
Consultant clearly not interested in anyone with an opposing view
Totally unnecessary 
No
Not needed 
There is already plenty of room for cyclists.
We don’t need this crazy scheme.
If it aint broke dont fix it. People have been cycling and walking the route for years without any issues so this would be a waste of money
I am concerned that the views of the vast majority of the community are actively being ignored, Mark literally says in his video presentation that if 99% of the
respondents don’t want it then is that really a reparation of the community, we can almost guarantee if it was the other way around he would say that that
was conclusive to the community wanting this scheme. From my own research and understanding from the community of Bute that I have spoken to face to
face and who’s comments that I have read online this is not wanted, and the fact that in his own words Mark admits that the community said they did not
want it during the first consultation that it has gone to stage 2 is staggering and is telling the community that their views simply do not matter and that as a
group you will do whatever you like. This is a democratic process, the community do not want it and so far you have been unable to legitimately answer
concerns and questions raised. Mark has been quoted in the paper saying that it doesn’t matter if this will be poorly maintained it should still go ahead, this is
an absolutely ludicrous comment to make and reinforces the reason for the scheme not to go ahead in the first place! This scheme will not be of any benefit to
Bute or it’s community.
No, we already have wide pavements right along the route, a prom etc that are away from the road that cyclists already use, this is a waste of time and much
needed community money and resources.
Again this is not needed! Please listen to our community and provide us with something that will benefit us. 
It's not need at all!  The roads are great as it is for bikes amd the very wide pavement are all ready perfect for children to, bike, scoot, skate safely. Please use
this money for something the community and locals actually need! 
Don’t need it
Fix the prom and it will be good as it is
Its not needed .
Completely unnecessary 
The community doesn’t want this.
Money could be used on other things

Page 94

91 | P a g e
www.connectedtp.com 
Not needed total waste of money 
Absolutely not. 
It really is not necessary. There is a perfectly adequate walkway from the glenburn to the esplanade.
The island needs other amenities before this nonsense.
Other routes are required 
Roads in Bute are pretty quiet compared to other places so cyclists have no problem on the road for this short proposed route. I would onlt5reduce pavement
on Battery Place to aliw
Complete waste of taxpayers money as is the consultation process
Total waste of time
Completely uneccesary
The roads are wide enough for both cars and cyclists and the pavements are wide enough for prams, wheelchairs and pedestrians
Concerned enough that the road will be narrowed, basically there is no need for this
Waste of money
I am very concerned that this plan is even under consideration as it is totally unnecessary and unwanted
NOT NEEDED
Not required
Rothesay has an elderly population many of whom require use of their own cars, also busses and taxis. The road is currently adequate for the tiny proportion
of cyclists using it. These plans will destroy valuable car parking spaces in particular on Victoria Street & Battery place, and will also lower the number of taxi
rank spaces to more than HALF the current required demand for daytime.
It is not required. Butes residents and visitors have managed without a cycle lane where it is proposed for ever. There has never been an accident yet. This
whole idea will impact travel, social care and emergency services in a very negative way. We don't want or need a cycle lane.
The project is not required 
No one has thought about the locals only about the tourist side of things.
The area is already designed for a safe walking space why do we need to waste more money on it, instead of improving the island in other ways 
Very concerned at the negative impact
Waste of money. There is ample safe space just now for walkers and cyclists everywhere on bute my 9yr old does it regularly without any issues 
Project is primarly geared to making cycle lanes without any improvement to walking
The community should have been consulted on what improvements could be made before appointing consultants to design cycle lanes then ignore initial
feedback and launch a design concept
Bute does not want this 
Not needed
This is a total waste of public money, considering the state of the roads and pavements on Bute. The money could be better spent elsewhere. The public
should have had far more say in this venture.
Bute is already a great place to cycle and walk. We don't need this. 
No one asked for this to be added

Page 95

92 | P a g e
www.connectedtp.com 
The pavement is already 8ft wide and there is also the prominade 
No one asked for or wanted this
We have an ageing population on Bute, most young people drive everywhere. No one will use this
The concept of safe cycle zones is great but where you have positioned it is ridiculous.  Make a cycle pathway from the schools.  Or fix the road at Ardbeg to
allow for both cyclists and pedestrians to walk safely.
This plan is absolutely ridiculous and whoever was brought in to make these plans really has no grasp of what our community actually needs.
I have brought up a family over the last 20 plus years and we’ve cycled, walked and ran from Craigmore to Port Bannatyne on numerous occasions without
needing these suggested adaptations. We, as a family, have completed training for half marathons, sponsored cycle runs and raised extensive funds for
charity. What we have on Bute currently is ideal for this type of training. 
It’s a waste of money 
Community do not want this 
It does not address the needs of the community one iota. Repairs to the sea wall on Ardbeg Road, doing something about the former Royal Hotel and The
Pavillion plus an elderly care home on the island would actually meet the needs. Not this utter nonsense.
There is already a good promenade for walking. Except at Ardbeg Road where the storm damage from several years ago has yet to be properly repaired. But
you ate not interested in that!!!
Not essential in the slightest 
Not required 
Absolutely no need to waste time and money on a stupid idea
Our pavements and shore side walking are big enough for walkers cyclists belong on the road there is no real issue with heavy traffic on Bute
This project is not required. I understand that if this money us not used for this purpose on Bute then the island gets none of it - that is preferable to the
chaos that this ludicrous scheme will cause. The promenade and battery place to craigmore pavements have more than enough room to have a cycle lane
painted - no need for any construction - 
Totally not required
There are far better things to spend this money on 
Waste of time and money 
I think there are other projects that would benefit from spending this public money, no need to restrict traffic further with these plans
Waste of time and money
The community does not need this ! 
Total waste of tax payers money 
It’s really not needed and if it’s a way to get funding to include road repairs be upfront and say this is design is being used as a way of fixing the roads!
There is adequate walking,cycling and mobility transport without this design.
The community clearly doesn't want this
Bin it 
We don’t want it. 
I don't think the pedestrian crossings near the ferry are safe.

Page 96

93 | P a g e
www.connectedtp.com 
Not extensive enough.  Build a pavement to the Eco houses at Loch Fad so children living there have a safe way to walk to school.  There won't be enough car
and disabled driver parking or coach parking or campervan parking in your scheme which will cause chaos!
What a waste of tax payers money, if it’s not broke don’t try fix it, funds can be relocated and spent where needed, and 10 years to complete the proposal as
quoted by mark is a joke 
Not required or needed
Not rewuired
Other areas need attention not just the front 
You. An only improve when base is solid 
As above, the roads need improved across the whole island to improve cyclist safety. Loose gravel clippings, uneven surfaces and potholes have caused me to
damage my bike and skid dangerously.
I must say that whatever this consultation costs, the salaries of those involved could maybe explain where Victoria Road is, there is a Victoria STREET but
that’s not mentioned,.
Reduction in main road through towns width. Will cause congestion at ferry terminal entrance at busy periods. Smaller roundabout recipe for disaster for larger
vehicle. 
Don't think it will help at all, if you want to cycle uou would want to go further than Pavilion
Rubbish idea,can't even get names right Victoria St not Road!
A waste of resources 
Completely against community views
The community has made it clear that this scheme is neither wanted or needed.
Cancel waste of money
The community want the money spent elsewhere
What happens to the taxi’s you are now making redundant? There is only space for 4 taxi, on average there is 8 taxis minimum on at one time - all very busy,
who will be responsible for these redundancies? How will these companies continue to provide a service with half the service ? 
Based on responses on Facebook group this is not a welcome development. 
This is not in the best interest of the community
Pointless
The roads, pavements and Promenade are absolutely adequate!
Completely a waste of money and you know it
We don't want it
Completely unnecessary and detrimental. 
With our climate and number of aged people cycling is highly unlikely to increase to the extent required to justify this waste of public funds regardless of what
virtual piggy bank it comes from. 
Very concerned
Narrowing of road & roundabout and not enough parking which is required for overflow for ferry!! 
Sort the Promenade for all walking, wheeling, cycling to enjoy and mobility to enjoy

Page 97

94 | P a g e
www.connectedtp.com 
Perfectly good promenade that could be used
Use what we already have a prominade
Rothesay has a huge obesity and ill health issue the more we can encourage people to walk or be active the better
We have to remember many people do not have access to a car or cannot drive the people shouting loudest here have cars
This proposal is Not needed in Rothesay
No consideration how removing parking spaces will impact the community as we will lose safe parking spaces in a town which is already struggling to
accommodate the many vehicles you find on island particularly on weekends 
As stated before there is no need for this in a small island community. The distance proposed is miniscule and will not improve the experience of walkers or
cyclists in any form.
Who has proposed this and why?? There are more urgent priorities to spend money on. 
Need to put it on the prom not change road/parking
No need for this, many more things in the town are needed or need repaired
None
The proposed design and measurment are a waste of money.
They do not aligne with the needs of the community.The paths , pavements and roads are perfectly adequet for pedestrians and cyclists as they are.
Meets no needs for the community 
Waste of money 
Total waste of time and money and especially when the pot holes on the road are always a temporary fix it’s a disgrace and to think we pay our taxes for this
nonsense 
You only need to look at the cars parked o. The pavement it’s simple we need more parking for cars and viditord
Don’t believe this is needed or wanted.  Most cyclists don’t use these layouts, preferring to use the normal road network 
The real needs of the community are being overlooked here.  
Waste of money 
We have a prom for walkers, we need parking 
Insane idea 
What a complete waste of our council taxes - appalling stupidity 
Rothesay is a fantastic town to walk and cycle around at present
The local need is not for upheaval to create cycle routes which will not be utilised to their fullest. Better planning of parking areas and development of the
town would better serve the community
It's not needed
Not needed 
Not needed 
Definitely Not
This is of No use

Page 98

95 | P a g e
www.connectedtp.com 
Doesn’t meet community needs, more an exercise in using funding
Simple solution would be to enforce current parking restrictions 
Our community does not need a cycle pathway. 
We already have pathways and walkways. We do not need this project. 
As usual with these things, pushed through when more pressing matters are of concern, another vanity project
Not needed
See above 
What is there is already more than adequate and to implement this plan would be a waste of tax payers money which could and should be used wiser 
Can't see the need for this with the cost involved, has there been any accidents?? The island lacks In care for elderly and nothing to do for kids, why not
address the things that matter
These are so.e of the safest areas for cyclists, would be better spent for school road. 
The community of Rothesay and Bute as a whole has far greater needs elsewhere where funding is vital but lacking. Crumbling sea defences still to be
repaired after three years, play spaces for children, social spaces for teens, care for those with disabilities, adequate care for the elderly, incentives for small
business owners, restoration of derelict buildings, community wellbeing projects etc should all take priority over this project and be more worthy of the
funding.
There is no need for the project at this location. There is already ample space for walking, wheeling etc along the pavement, roadway and esplanade.
It Isn’t Needed Or Wanted
Whoever Designed It Is A Fuckin Idiot
From young to old most are drivers on Bute not cyclists 
I hope enough people object to stop this from happening we don’t need it 
Not a requirement the islanders require 
Unuseful project
Not aligned at all with community needs
Waste of money 
I’ve observed, both as a driver and a cyclist, that most people are very tolerant of other road users, especially in Rothesay.
There are very few accidents inRothesay. Statistics should be a considered as a measure of need.
The community do not want these changes but they are being forced through by some mandate which is, no doubt, financially driven
There is no evidence to support the need for change.
Not much of a problem actually exists but you are generating plenty of new problems.
Not much of a problem actually exists but you are generating plenty of new problems.
Irrelevant
Not interested
A lot of nonsense and not required
Waste of my tax paying money

Page 99

96 | P a g e
www.connectedtp.com 
I believe my displeasure at the misalignment of your proposal with what this community needs have been clearly expressed already in this lazy, cobbled-
together survey
Read all comments already stated
Not listening to the community
Tell me why it's required? 
You are creating something just to justify your contract 
There is no need for this in our town we have adequate facilities 
This is not needed and should be scrapped
This is not required , it will make walking more dangerous 
Concentrate on actually improving the town not wrecking it. 
Waste of time and money 
11 Taxis on the island, the planners assumed 7 so 4 spaces on a rank is ridiculous 
Absolute waste of money. The current pavements need to repaired and more wheelchair friendly lowered curbs out in place. To improve safety for elderly,
disabled and particularly sighted or blind. 
Would suit you better to fix the pavements for elderly and wheelchair chair users
Please listen to our community - this would be a gross misuse of public money
The ridiculous proposal of a cycle lane when it isn't required. Argyll and Bute council you are an absolute joke
Money could be better spent elsewhere.
Unnecessary.
Last thing the island needs is this pathway
This is a walking community already.
Total waste of money. Not needed and not wanted
The community does not need more routes for cyclists or walkers due to already having a pavement and road. I'm concerned that money is not funding the
correct projects on Bute which would meet the needs of Bute.
The design is not needed as the route is already wide enough for cyclists and walkers to be safe and its accessible.
The money spent on design and consultation is already a waste of scarce resources.
Proposed area is already very safe & pedestrianised to sea front
Very concerned - disruptive & unnecessary 
If the roads, pavements and the prom was maintained properly 
We already have the facilities in place. You are going to narrow the access to the pier. On busy weekends cars are queued along Victoria Street waiting to get
on the ferry. Examples Bute Feast and Highland Games, Bank Holidays. This is a holiday resort. Also an island that needs it town to be accessible and useable
by all. Not hindered by fewer parking spaces and narrowed roads. You are going to affect the businesses in the town. Just because there is funding for this
bike path dies not mean it is needed nir necessary. .  Holidays. 
Nonsense 
Spend the money properly on something that is needed for the town

Page 100

97 | P a g e
www.connectedtp.com 
The town centre is in decline, mainly due to the state of the Royal Hotel and empty shops, this is the last thing money should be spent on. 
Plenty of space to walk no need for anything else
Who will enforce parking on the pavement, it is not a police re4sponsibility and we have one traffic warden who only visits once a month
People are going to get hurt need to walk on the road not the pavement 
Cyclists are already a nightmare whether you are a driver or a pedestrian, I don't see how they benefit me anymore than they do now whilst out enjoying
walks with my dog and family
Why waste money on this design, it would be better spent improving safety of children to and from the joint campus which is an absolute nightmare with the
cheese factory too. It's dangerous and need improved urgently. This way kids could walk/cycle safely and maybe help parents feel safe for their child to do so. 
Not required at all ..cyclists cycle on the road there is more important things to spend money on 
I feel there are so many other ways the money is needed on the Island. This is a waste of money and time. 
The entire thing is not appropriate
This is not aligned with any of the needs of the community!!!
Not needed add a cycle lane to the promenade - if necessary. 
This is neither wanted or needed
this is neither wanted or needed 
No need this is just ABC wasting money.. our island use to look beautiful NOT now. U pay a dog and traffic warden and yet our town is a DISGRACE!! 
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park.
Absolute waste of funding. I used to cycle along the whole bay for work for years never had an issue along any of the front roads. Even as a child I felt safe
cycling. This is really a wast of money and is going to affect the local community not help it. 
It is not necessary. 
This should never happen. It's a waste of money and not needed. I don't know what benefits the people working on this get for forcing it down our throats but
Bute is NOT happy with this.
You clearly have no idea what your proposing as it is an utter waste.
I think our island lacks in parking spaces for vehicles and you close the street off for a cycle lane is ludicrous!! The worst idea yet. I'm sure the funds can be
used on much more needed things to our island 
I think you need to rethink your ideas as our island is deprived enough let alone adding this to the situation 
If this is all you can come up with to improve our island, then there is something very, very wrong!!!
Waste of money, use the money to provide essentials to the community that pays council tax.
Not neede
Not needed
Fixing the current pavements and installing more dropped curves would be more beneficial
Once it gets damaged you won't fix it, same as the current situation. 
No one in the community wishes this 
Worst project ever proposed pathments should e fixed and roads before this

Page 101

98 | P a g e
www.connectedtp.com 
I’m concerned that this is being pushed through regardless of what the community wants, 
Not needed! We have many places to walk and cycle which are preferable to the proposed route. 
They is no issue so why change it
Pointless
You parked on a bloody footpath and have shown a lack in understanding of the highway code
The roads are wide and quiet. The Lycra brigade will not use a new cycle route. Pedestrians will wander along oblivious to cycle markings listening to
headphones . Money that would be better spent elsewhere on Bute will be squandered
Cycling route and car parking provision is clear but not the other elements
There’s already wide pavements along this route
This project shouldn’t go ahead
Ridiculous  cycle route not enough traffic
Rubbish idea
Not needed 
What prat came up with the idea 
ANGRY that this money is being spent on something we do not want or need. There are many other things we are in need of in the island rather than a
useless expensive cycle lane.
We do not want this on our island 
There is no need to make this change. Community doesn't need this. If anything improvements needs making up high St for route to academy. Not along the
front.
Waste of time and money- upheaval to do works is not worth it
Money is desperately needed elsewhere
No need for it. Perfectly adequate 
Inverclyde set up a similar routes that cost thousands, to be only used by a handful of cyclists. This has increased congestion and reduced parking in allot of
areas. It was classed as a very expense of verly little value in return. 
That the council and project manager are not listening to the community, and are hell bent on pushing this through. Just like the route from the town to the
school, taking no account of the access through parts that would be unsafe in the dark winter months. 
Not needed in this area 
This is NOT needed on the island !!! Put the money to other much needed things 
It is an unnecessary impingement 
It is not needed
Money should be spent in Other problems 
Money should be spent on other projects
Waste of money some of the town is falling down
Cycle lane not necessary, educate cyclists to safely move over when appropriate for vehicles to pass.

Page 102

99 | P a g e
www.connectedtp.com 
If it's not broke, don't fix it.
Leave Bute don't come back 
Wasted money 
Totally not about the community
Cornc
The community doesn’t need a walking/cycling track
Access to the ferry terminal is problematic when demand is high and the ferry terminal is full. Cars currently queue ad hoc on / Victoria Street until space
becomes available. The current width of Victoria Street allows this without any problems
The only issue at the moment is the poor state of the pavements and roads (Pot holes and uneven paving), which is caused by poor / lack of maintenance.
Resolve this, and walking / "wheeling" / cycling becomes much easier
Not needed
Not needed, we have l big wide pavements, this is a disgraceful waste of money
It doesn’t improve what is there and is a waste of money
The community has not been engaged and its requirements are not known. 
We do not need this, and it is Victoria Street.
Don't waste money 
Waste of money 
Waste of money
I don’t believe this is a good idea to the town as it’s cutting off more parking spaces and it’s leaving the taxi rank with only 4 spaces. 
Not needed not good for tourists parking not enough space to widen for a cycle path!! Rubbish not needed 
As above!!! Just LISTEN to local people 
LISTEN TO THE COMMENTS 
This would be an embarrassing waste of money
Don't think it is beneficial 
Overall there is nothing wrong with what we already have.
This design is not required for Rothesay.
This is a serious miss use of funding when there are pavements roads and buildings falling apart all over the town centre. This is not a priority for the
community and points of views should be adhered to as we the community need to live and use these areas daily 
Ban parking on the pavement at Battery Place once access to designated are on the Esplanade 
The whole point about cycle friendly roads should be the laying of decent tarmac surfaces, thereby avoiding potholes. 
Cery
Won’t benefit anyone
Nit at all needed
Scrap it

Page 103

100 | P a g e
www.connectedtp.com 
Not necessary.
Probably take over 5 years to complete 
Extremely concerned that the planner’s have not did their research and assume there is only 7 taxis on the island and only 4 work at a time. There is 11 taxis
in total. Where would the other 7 rank ???
There is ample footpaths for walking and cyclists will not use a path. This is obvious from what i have witnessed on the mainland 
Absolute waste of money. This will not benefit the community and the funds could be better utiliised in many ways
This is a solution looking for a problem. Money could be better spent elsewhere.
This is NOT wanted or needed.
This is not necessary there is plenty of space for cycling and walking. Focus on more important issues 
Concerned for business which will be affected by the scheme
There have been no cycling incidents on the island for years, most yous the pavements when necessary. It will loose the taxi company business and the
business surrounded by shortening pedestrian crossing
Waste of money & no one will use it
I cycle all over the isle and there is simply no need for this consultation, it really concerns me that after the debacle that was the school walk cycle route you
now plan to "enhance" and already sufficient route and seem to be pushing on in the face of public dismay. Your premise is flawed we do not want or need
this enhancement and would rather see cash put into existing services that are being cut i.e, Police, lolly pop men, public conveniences, gardeners,,,,,, geeze
this list could go on but you get my point, so please listen and stop!
There is zero need to improve the already good service that exists 
This seriously is not needed on this island and is a complete waste of money. The most concerning point is I don’t know one person on the  island that is for
this yet it seems to be going ahead  
Money couldn’t be well spent elsewhere
There is absolutely no need to do this to the front of the town. Just leave it alone, we don’t need it, don’t want it. It could affect business with the taxi rank
and other parts along the route. Someone is profiting from this and there is no need for it at all
Waste of space time and money
Waste of space time and money 
There are no issues with the route currently
Without exception anyone I’ve talked too is utterly bemused as to why this project is being funded. Its aims could be achieved by simply maintaining the
existing route in an overall better condition. 
The Isle of Bute has far greater concerns than the road/pathway system we should be able to choose where and what the council puts investment into. 
If people aren’t currently walking and cycling on this route design won’t change things. It’s not a communities route.
Why this route. It’s not the main route in the town. From the town to the campus would make more sense to focus on. It’s very busy during that e day and
when children are going and coming from school.It needs to be made safer and cycle/walk friendly.
Just a way for the fat cats to make more money regardless of the community's feelings
There is no need to build something else, the payments we have already are suitable for wheelchair access and pedestrian walking. If maintained properly
there is non need for this honest farcical proposal. All you br doing is creating more issues for something that would not benefit anyone. I cycle and have

Page 104

101 | P a g e
www.connectedtp.com 
never encountered a problem that would require a separate lane. I also push my kid about in a pram along the proposed new walkways and again no issues
doing so. There is no need to waste money here.
This is an honestly terrible design and serves none of the intended purpose
Public seem to be getting ignored by organisers 
Not needed and not practical 
The present if sufficient for walking and cycling 
Waste of resources 
Cyclists will not use it they prefer to disrupt motorists by blocking the road cycling 2 & 3 abreast
Idiotic design! The amount of “give ways” on the cycle route that cyclists will take absolutely no notice of. If you observed the local zebra crossings you would
realise that cyclists take no notice and pass through when pedestrians are on the crossings. The roundabout die to be reduced is already too small as coach
drivers have to conduct a 3 point manoeuvre in order to turn. 
Concerned that this scheme is ignoring some of the critical issues already being experienced around standard of existing pavements etc in order to promote a
'blue sky tick.box scheme'
Rather than looking to make more obstacles funding would be better served improving the pavements, roads, drop kerbs etc
Community doesn’t want it 
Poor survey design there. Am more than concerned. Totally oppose it 
There are so many better things that could be done with this money.  The traffic on Bute does not warrant spending this sort of money on a "solution" that
probably less than 1% of the population will see any benefit from.
I don't believe this will benefit our community at all a complete waste of money that would be better spent elsewhere such as play parks etc
Typically cyclists use cycle paths to avoid pedestrians 
Again, not required 
Not needed
Many in community agree change are a waste of money
The road and pavements are already adequate 
2 way cycle lane I feel would be more dangerous than what we have just now
Are we suddenly going to get hundreds of cyclists coming over. The community is mostly elderly and getting older all the time. Not all will be able to cycle. We
already have racing and many bikes that have enjoyed the island as it is. 
It will not meet the needs of the community 
The promenade is wide enough already. Not required. Cyclists have no problem as they weave where they want to anyhow
There is absolutely no need for a cycling path on this stretch of road whatsoever. 
There is absolutely no need for a cycling path on this stretch of road whatsoever. 
I do not think it's needed 
Upheaval, mess and it's not needed 
As mentioned before most people ride their bikes along the seafront because let’s be honest that’s why they come to Rothesay. This is a pointless tick box
exercise and a complete waste of public money which would be better spent elsewhere.

Page 105

102 | P a g e
www.connectedtp.com 
As previously mentioned there is absolutely no need for a cycle lane here. It’s hardly Hackney. The road traffic is not high enough. 
Seems only to benefit a handful of cyclists
Plenty room at the sea front for cycle route and pedestrians.
Reducing parking spaces is detrimental to the town.
Just why?!!!
Roads and pavement wide enough 
Wast of money no need for a cycle lane 
Everyone is concerned, this is not aligned with the “needs” of the community in any way shape or form
It will improve nothing
Very poor and ill conceived with poor value for money 
Why not survey existing users and community ?   Ferry users are notoriously friendly and a captive survey audience 
It will reduce parking & cause congestion 
How can it improve walking when the pavement is being used by cyclists.
The community has made it abundantly clear that they do not see a need but they are being ignored by an unaccountable organisation that appears to do this
kind of thing all over the country for no good reason. Well no good reason for the community but clearly it is profitable to Sustrans.
Mega concerned 
Rubbish 
Money could be well spent on town
Just going to cause trafic congestion which will increase accidents
Not an appropriate idea at present for the town centre
Esplanade as it is has always been able to accommodate pedestrians and cyclists.
I think the money spent so far has been a complete waste
Whoever has come up with this project does not seem to know the island as a cyclist at all
We don't need it.  Money could be better spent elsewhere
We have a perfectly adequate space available at present
I see on average 6 to 8 cyclists / week in the height of summer. The majority of them tourists. Rothesay is a quiet town. If a cyclist is cycling along the
promenade and people are walking, a simple ring of their bell currently works to alert the walkers. In my opinion, money would be better spent on improving
the existing promenade surface and painting on a cycle lane
I think repairing the current surface of the promenade and painting on a cycle lane (as Troon and Largs has done - which is extremely effective by the way)
would offer the same benefits 
It will hinder drivers, hotel, guest houses, air b&b’s
Leave our island roads alone. 
This is a waste of money
I feel that the majority of the community prefer to use their car and won't see this as a benefit

Page 106

103 | P a g e
www.connectedtp.com 
Yes, within the proposed developement
Scrap it
There isn't a problem
It doesn't need improving
Waste of money
Plenty of space on existing prom
Population is mainly elderly people who do not cycle
We don't need this
We don't need this
It isn't aligned to any relevant local transport priorities 
The community have been very vocal in not supporting this move, yet we are being ignored, even with our genuine concerns. It is quite clear that this is
already going ahead regardless of what we say.
It does look quite expensive given all the other priorities that we are told there is no money for.  I think a slimmed down version would stand more chance of
getting community support and funding.
Not aligned with community
Not needed
See previous comment. The only complaints I've noted from cyclists have concerned the uneven condition of some of the island's back roads, well out of the
town centre.
The design is a sledgehammer to crack a nut. Traffic volumes are low, cycle volumes are very low. Cycling/walking along the whole of the stretch is already
both easy and safe.
I think it will future proof the uskanx for future changes in transport
I thinkbut future 
Bute is very popular with cyclists and has been for years. Groups come regularly and cycle round the island with no issues. This scheme has been dreamed up
simply to tap into funding
Totally ludicrous proposal
If the surface and layout were improved this area already caters for pedestrians and cyclists especially if you remove parking in the pavement 
There are other places on Bute more in need of improvement 
No concern 
Will be excellent for community 
Plenty of paths already 
Making roads narrower and dangerous
Not needed
Already used by all the local community, no need to change anything.
Not required on Bute.

Page 107

104 | P a g e
www.connectedtp.com 
DThis has to be the most ridiculous project yet.  I have seen the chaos of addding these cycle lanes have made to Aberdeen city. Fix Rothesay pavements
In an aging community fixing pavements and walkways are uppermost.  
There is a wide promenade to cycle or road no need for cycle path
This is waste of our money
There are so many paths and ramps that these changes make zero difference.
You have not taken on any of the negative feedback that the whole community has given you.
its not broke so no need to fix it 
The current situation offers a great walk, wheelchair route, walked it all my years living here and enjoy it every time 
Feel like it’s a way of lining the companies pockets with absolutely no interest in the community 
It would help after looking at the drawings etc but the prom is already sufficient for cycling and walking 
This doesnt appear to provide enough parking for future pavilion demand. 
Mark out a route on esplanade and save a fortune
Unnecessary
Waste of money
The amount of people using this area of footpath is very minimal. Most people use the promenade to walk on so to convert this is a brilliant idea
Some of the ideas are good but not all 
Wasted money, address the problem with roads and pavements, money better spent.
Waste of time and money 
Very much in line with parts of the community, including me. I see that only 1% of the resident population responded to  the previous consultation. This was
hardly representative. At this week's consultation, I noticed a few very vocal objectors. They don't speak for me. 
Yes. There needs to be better segregation of motor vehicles from pedestrians and particularly cyclists. Cyclists are currently very exposed riding in Rothesay.
Nobody here has asked for a cycle path on the area you are proposing
It's not needed 
Some absolutely stupid idea to waste money 
What a waste of time and money 
Community being overlooked again
Going to be an absolute disaster 
Not wanted or needed by the local community 
Scrap it completely
Money would be better spent elsewhere. The seafront and prom is crumbling and needs urgent attention more than this.
As said previously Bute needs kids soft play or similar rather than this,I live and work in Bute and cycle daily with no worries or issues about my safety and see
plenty of families cycling also
Not necessary and waste of hard to come by money 
NOT NEEDED, SCRAPIT AND USE MONEY MORE APPROPRIATELY

Page 108

105 | P a g e
www.connectedtp.com 
Present facilities are adequate for everyone in every category mentioned.
No I don't there will be any improvement 
Absolutely not. I am a walker and this would impede me from walking along this area, no room for prams and wheelchair users.
I feel that this whole idea is a vanity project, ignoring the vast majority of islanders who have lived here for many years. It would impede on parking for
emergency vehicles and care workers going to clients and emergencies. Walkers, wheelchair users and prams would have limited space. It is. It people
friendly. We have a large elderly population on the island who do not and cannot use a bike, they depend on cars and mobility scooters to get from A-B. 
The wrong area for a bike lane
Will cause more issues
At the moment I find it difficult to use the pavements in my wheelchair as they are in poor repair and every bump can be painful when already in pain. The
proposed changes just so happen to start near my house at 8 Mountstuart Road and as long as it’s easy enough for me to cross the road to access it, I’m
hopeful that it will encourage me to get out more in my wheelchair which is much more sociable rather than needing to be driven
For me personally I think it will make an improvement but I think people locally are concerned about the impact on parking spaces
‘Concerned’ doesn’t cover it - I’m dismayed and frustrated at this proposed waste of public money.
As above. This is not needed, will not provide significant benefit and will make some areas worse (e.g queuing for ferries and parking at Battery Place)
Concentrate on the prom.
This is going to be a huge waste of money, why not upgrade the walk/path ways we already have going out towards the Glenburn and the pavillion? The
island needs the money spent on a lot of other areas rather than a cycle path
It’s not needed
Not required 
As a non driver and a regular walker of this route I think the idea of needing a dedicated cycle path is ludicrous and has clearly been drawn up by pencil
pushers who have likely never been to or spent much time on the island 
As Above 
As above 
Clearly, done by someone with no care for Bute.
Totally agree with it. We don’t need it, we don’t want it, it impacts negatively. Try listening olease
Will make life worse for the islanders
Improving access on a route where it’s already good. Plenty other paths and routes need I lroved
No requirement in that route for this there is in other areas of the town
Absolutely flabbergasted at the fact that it has even got to this point. A shambles. Total and complete waste of money that could be used elsewhere. Will
affect the roads that are already affected with heavy traffic when the ferries are busy. 
I have heard hundreds of people taking about this and all were against it. This has to be stopped. 
This project is not wanted nor needed. The money needs to go elsewhere
Has the design team tried and tested this route.  I think local knowledge has not been well enough considered regarding this work.
Repair existing footpaths is more important than cycle lanes.
Not heard any positive aspect of the inclusion of the plans

Page 109

106 | P a g e
www.connectedtp.com 
As above. Please listen to the people who live here, this is not required or wanted.
It is not safe to share a walking path with bicycles. What about the buses turning at the island, how is that going to work if you narrow the island. People who
live and work here depend on current bus routes.
Waste of money, not needed
Please start listening to voters not activists
Traffic on island isn't busy enough to fuss with this nonsense
I think anything encouraging safe cycling on the island is a wonderful thing we have a great deal of selfish drivers but sadly my opinion will be in the minority
as people here don’t walk the length of themselves never mind cycle if they can drive here 
I think it’s a start in the right direction too many drivers on a very small island 
Not sure why some people are objecting so strongly. The council still has the same duty to upkeep the roads and mend potholes, doesn't it?
£6 million
Money should be spent on prom roads that are horrendous on this islanDel
Completely unnecessary 
Did whoever thought up this idea even visit Rothesay and look at what the town really needs ,ie the state of the Royal hotel, the empty shops,trees growing
out of buildings and they think a cycle lane is the main priority then they should try living here
There is very few who cycle in the town. 
It's a waste of resources money could be spent on other pressing matters 
It's a waste of resources money could be spent on other pressing matters 
Don’t know who came up with idea but absolutely no need.
No need for all this.
The local community doesn't want this
If this goes ahead in Rothesay it will be another example of the shambles of our council
Your trying to fix a problem that’s not broke and improvise a change that is not needed
No improvement. Will have negative impact for the residents.
There was no box option for Displeased ! Please amend your survey
Not needed
Total waste of time
Waste of money 
It is a waste of time and money and other things can be done. I cycle and have never felt it needed. Why is this even being proposed? Noone has asked for
this. Seems to be a waste of time and some way of laundering money I'm sure. Despite what the community has said I am sure you are still going to do this
as I'm sure some money has gone under the desk to make sure certain companies get the work. I even doubt you will read this. Rather than add this why not
fix what needs fixed first
We have other issues that should be dealt with 1st
Action re pavement parking required 
Scrap it.

Page 110

107 | P a g e
www.connectedtp.com 
Scrap it.
No benefit to community 
Will not improve anything 
The community needed to be asked sooner, maybe even speak with the schools and local groups, Bute wheelers would also be a good starting place
Don’t need this !
Not needed in my opinion
We don't need a cycle lane,
Utterly  useless 
I’m gobsmacked that anyone with an ounce of common sense could dream up this ridiculous idea
Not needed ar all, waste of money/ time 
Waste of money 
Needs of the community,  come here and look for yourself,  the last thing we need is thousands spent on a bike lane
There is a pavement/ promenade....cyclist's will still use the road due to their sense of entitlement 
Not fir disability
It will be a pain for drivers
This can be easily improved if time is spent on bute to see practicalities of concept.
Absolutely no one is backing this 
Sea wall falling to bits and roads in pavements are in shocking condition 
No. Firstly, if someone wants to knock over a cyclist, they’re going to knock over a cyclist, “safer” routes isn’t going to help that. Secondly, those pavements
are of historical significance, just look at the Rothesay in days gone by Facebook, everyone’s granny has a photo walking along that pavement. Plus, everyone
hates cyclists, that’s only going to get worse if you destroy the natural beauty of the town with a cycle lane
They did the whole cycle thing in Greenock and wasted millions of tax payers pounds. This is a terrible, terrible idea. This would be Rothesay’s breast feeding
mermaid gable end, don’t do it. Nobody even cycles on the island.. Look at The Real Isle of Bute Facebook Page, you’re not doing this for the people of the
island, they don’t want this. Building a cycle lane isn’t going to get rid of the eyesore rotting academy on the hill or the catastrophic let down that is the
pavilion renovation - finish that before you build cycle lanes. 
Total waste of money. The town needs regeneration, not a bloody cycle path!
We have a promenade that runs from the town to the Pavilion. This is wide enough to accommodate all.
It will NOT meet the needs of ALL the community. It will be divisive, causing frustration towards cyclists and traffic issues
The route and proposed plans are not well enough thought out
No communication with residents and the whole scheme is being pushed through with no care for what the residents want or need.
The whole scheme will cause disruption and delays to motorists due to restricted width of the roads in places where changes want to be made.
Total waste of resources 
Very concerned 
Access to pier for ferry traffic

Page 111

108 | P a g e
www.connectedtp.com 
Already plenty of opportunities around the island 
Narrowing the pavements for un-needed cycle paths disrupts walkers, parents with prams and strollers, and wheelchair users.
Putting in cycle paths on the pavement areas will mean an extra set of kerbs for folk to trip on.
The community doesn't need this change because there is no need for it - the pavements, the promenade, the pathways are all perfectly fine.  The idea of
reducing the size of the roundabout is absurd - how are the buses to negotiate it?  the idea of reducing the taxi parking is inhumane - the taxis are essential
for people who have no cars.  Public transport doesn't cover the whole island, and elderly or disabled people coming back from medical appointments rely on
having plenty of taxis available.  They are also needed for the many visitors who come to Bute.
There is no need to change anything - there is plenty of room for walkers, cyclists, wheelers, and anyone with mobility problems already.
Misplaced plans to fix something that does not require to be fixed whilst simultaneously creating problems that didn’t previously exist and compounding those
that did.  That's an emphatic 'No' from me!
Misplaced plans to fix something that does not require to be fixed whilst simultaneously creating problems that didn’t previously exist and compounding those
that did.  That's an emphatic 'No' from me!
Lack of parking due to the cycling layout 
Need to revise the placement of the cycling lane. All the space on the promenade which is empty and not used.
I regularly walk the route from the Gleburn to town. There are three separate paths which can be used and they are more than adequate. There are a number
of dangerous flagstones and potholes in town, the money would be better spent repairing these and employing a dog warden to address the issue of dog
fouling in this area! 
There was very little information or publicity about the initial phase of this plan, I don't feel the community has been adequately consulted or listened to
regarding this. 
Good, but could be enhanced.
In general yes.
pointless exercise
do not proceed with this
I think the design is totally inappropriate for the needs of the community of Bute 
Very concerned. I can categorically say that at least 90% of the population of Bute are totally against this ridiculous proposal. 
Not really, it can all be done already, it is a small community
Due to the fact that there  ar  2  pavemented areas from albert pier to the  glenburn ( one of which is a wide pavement)   and already problems with parking
on this road, this would be  insane.
For the route from albert pier there is again broaded pavements and the prominade,  so  again no need for this. I do not believe this is a  good way to spend
public money.
Not needed, waste of money
A 2 way cycle lane on one side of the roafd will create dangers for people like my sons who have learning disabilities. It will not stop cyclists cycling 3 abreast
on lane and road. It will cause chaos for pier traffic, it will narrow the road , it prevents parking for residents. With the Highway Code hierarchy of road users
this is not needed. Especially at a cost of 6 million.. 6 million !.. has the government this amount of money to spend!!           
The community does not want this wast of money and badly designed cycle path

Page 112

109 | P a g e
www.connectedtp.com 
There is no issues in regard to cycling in these areas and as stated multiple times above it is a waste and does not benefit the community in anyway
No it is an unnecessary waste of money which could be used to improve and fix the places we on the island already have available to cycle on ie the widest
pavements ever the prom and the coastal path along battery place  
We do not need cycld paths
It’s pointless
Pointless
Nonsensical concept
Waste of time and money
Apart from not being wanted or needed, this will be an absolute nightmare getting onto the ferry lanes, especially at busy times.
If you were really interested in the needs of the community you would scrap the whole idea!
The town would be losing much needed parking. Battery place is made up of flats and many b&bs, where do you propose residents nevermind visitors park?
The taxi rank proposed isn't ample for what the island requires, where will they go? The ferry que is asking for trouble during peak times. Another point of
where will the overflow go and wait?
Unnecessary 
The demographics of the island are changing and over 55% of islanders are over 55years of age .  Not the group who would take up cycling radio. The cycle
route connects nothing in town for folk to commute too. The driving standards on the island are terrible so adding to the 
Absolutely ridiculous idea
Extremely concerned
Waste of money 
Car congestion
Pointless waste of funds
There are far more important issues that need addressing 
Not needed !! Waste of money 
We don’t need this ! Waste of money . 
Absolutely not,  this is not taking pedestrians and families into consideration at all - does this mean cyclists have the right of way when people are attempting
to cross? Vehicles going to and from the ferry? 
It’s quite frankly a lot of rubbish - build something people actually want! 
Extremely concerned. It's as if it's been designed with no forethought whatsoever to community. Which is shocking & disrespectful.
No as previously stated there are already areas that can be utilised for these activities. 
A total waste of public money. The sooner this hare brained scheme is consigned to the rubbish bin, the more money will be saved by not paying over priced
consultant fees.
Therr is alot more needing money spent on than investiing in thist
As a frequent cyclist and walker I see no benefit in this concept
We do not need this we should spend the money on something useful 
Don’t do this

Page 113

110 | P a g e
www.connectedtp.com 
Worst idea waste of money resources and more. 
The whole thing is unnecessary
As above
Why does it require 6 bodies ,who all will be taking their  "cut "  Our council tax can be better used. My vote is a big NO 
Existing system already works for us
New system not required in Rothesay
No.
The design does not meet the needs of the community in any positive way.
Designed by someone who does not know Rothesay 
Where is Victoria Road?
I don’t consider cycling and walking paths should be the same pathway. 
It is not aligned with the needs of the community. 
Hugely disappointed that this has been given any time of the day stop the pen pushers making decisions for a community just ask them and deal with the
answer instead of this farce we are going through 
This plan is terrible non local think he knows best ridicules 
I'm concerned that taxpayers money is not being better used.
See comments above
The Promenade along Battery Place already caters for walking, wheeling, cycling and future mobility
This is another hardship foisted on Rothesay residents by Argyll & Bute Council which says it's open to feedback and then simply ignores residents' comments
and imposes Council's will regardless. On any given day and night there are around 20-25 vehicles parked on the pavement  along East Princes Street and
Battery Place. There is nowhere else for residents to park their vehicles. Residents along these roads were hoping that the current tolerated parking on the
pavement opposite would be formally permitted to counter the blanket ban on pavement parking enacted.  Simply because funds are available for a project
does not mean it should go ahead. This proposed change to create cycling lanes will pit resident against resident for the limited remaining parking. Rothesay
guest houses (already) dwindling as a result of recent prohibitive changes will continue to throw in the towel and simply quit running guest accommodation.
Not needed 
Use the prom
Needs of the community are overshadowed by need to push through new but long term unsustainable ideas.
Will merely increase hostility to the few cyclists who might use it.
It's a waste of money 
They are no better than what is already in place 
As above. would need to get the full detail specs to fully support it. Maybe if funding limits ability to hit all details require for safe spaces, it would be better to
forget bicycle lane and focus on creating a slower, better designed street through surfacing and planting. Cycling was my main mode of transport growing up
here and living in Glasgow for uni, I am passionate about urban design and active travel, my dissertation was a critical analysis of bicycle infrastructure in
Glasgow so i am familiar with many designs both good and bad. I think good street design really cracks into the subtle psychological cues to reduce driver

Page 114

111 | P a g e
www.connectedtp.com 
priority and a powerful tool within that can be ambiguity! Overall something absolutely needs done about the towns streetscape and am fully supportive of
proposals to make changes. Please don't let those who shout the loudest dissuade plans to make changes. 
Yes but the devil is in the detail with street design
Do not take into account local knowledge and concerns.
Worried local feedback is ignored as ‘free money’ available. Get grants to get Hanson to do something with Royal Hotel eyesore before pandering to nonsense.
Please
A waste of money , would be better making a completely off road cycle path adjacent to the tramway path. The roads in Bute are too narrow for any more
space to be taken by extra lanes 
I think it will make it worse , there will be more accidents with people crossing the lanes, if there is a reduction in parking then this is not inclusive for disabled
people , it will impact on local businesses if there is a reduction in parking so people can get into town.
I don’t believe it’s needed
I don’t believe it’s required 
Waste of money. Money could be spent better in the town . It’s not ideal either for those with mobility issues 
Not pleased at all. I think its a pointless idea.
We haven't got a problem for  cycling or walking in Rothesay so why change it?
Just don’t see the need for change
Not necessary. Promenades are quite adequate as they are. This could cause difficulties for cars turning onto the pier 
Im totally against this happening 
The upheaval this would cause to the town would be ridiculous LEAVE IT ALONE 
Taking the majority of space for cyclists from Albert Pier to the Glenburn and just leaving the narrow path on the seaward side for pedestrians who walk with
dogs, prams, children etc is disproportionate and not necessary 
This appears not to have taken any account of the local community or their wishes. 
The design doesn't meet the needs of the community. Many more things need doing before this unnecessary design. 
The pavements and roads are already adequate 
Too much space used for cycling 
Plenty walking facilities on island  and safer than the bottle neck that is going to happen in the  town centre     
Waste of time and money 
The busiest street in town will be the most dangerous 
The majority of the local community don’t want this 
As mentioned before I don’t think this path is needed on the chosen route. I think the route that should be considered is to the school as it would benefit the
kids (and parents/teachers) and give us a safe path to cycle. 
I don’t think the route chosen needs a dedicated cycle path as there is already a safe and adequate path in place. 
Terrible 
seems like a money making scheme for a few people. pointless project 
Think money could be spent on more urgent improvements such as roads/pavements and seawall

Page 115

112 | P a g e
www.connectedtp.com 
The person in charge MR rinkus just isn’t listening to my locals and very arrogant   
1%of the population is pretty poor engagement in my view 
I dont think this is a particularly useful or cost effective way to improve either walking or cycling in this particular section of town. Pavements here are mostly
already quite wide and conducive to walking. There is alrrady a walki g route on the promenade. Waste of money that could be spent usefully elsewhere. 
Not interested as this island is determined to be run to the ground 
Pavement parking at busy times in the Albert Pier to Glenburn section works well and costs nothing.  Why spend public money to change it? 
This is a sledgehammer to crack a very small nut.  Walking and cycling on this section of the A844 is no more dangerous than on other roads in the town. 
Adding a pedestrian light to the traffic lights would be sensible, and perhaps a pedestrian crossing by the Visitor Centre, but apart from this the whole project
is an unnecessary waste of public money. 
Existing measure only need improved 
Imposing on limited parking, existing taxi rank, roundabouts, entrance/exit ferry terminal 
Very happy with the idea. How does it relate/join to the active travel route up the High Street to the school? 
The community does not need nor want this. 
There is sufficient pavement space for walkers and wheelers in the proposed location. Cyclists can continue to cycle on the road like they already do with no
issue 
Not needed 
Waste of money, not needed 
I'm pleased about this project as a start but I'd prefer if the route was more connected eg. to Mount Stuart, which have extremely dangerous and innacessible
route for cycling and pedestrians especially out of season when gate at Kerrycroy is closed 
Many Bute residents are in capable of cycling or walking 
This design is seeking to address a central target as opposed to a local issue. I would rather the money was spent elsewhere. The more 
Absolutely not. 
The community neither needs nor wants this 
I cycle every day on the island and usually in Rothesay. There is absolutely no need for any change from what we have. There are many cyclists here and the
vehicle traffic on the roads is used to them and patient with them. I have always felt safe cycling here and this would be a total waste of money. It would not
be used and would probably just annoy everyone. I would rather the potholes were fixed so I don't need to swerve to avoid them. 
This is a virtual signalling exercise , nothing more 
The promenade has ample space to create cycle lanes 
This is going to create a lot of problems at the peir 
It’s ridiculous 
Waste of money 
Not in the slightest 
There is absolutely no need for this 
Pointless interference 
Spend the money on fixing potholes.

Page 116

113 | P a g e
www.connectedtp.com 
No consideration for the local community. One size does not fit all. 
Lack of interaction with the community 
Absolute waste of time, resource and money. As a keen cyclist, pedestrian and motorist I see absolutely no benefit whatsoever from this project. 
Fix the existing walkways 
Just causes more upheaval for little gain & a minority of people 
The community didn't ask for it because it doesn't need it.  The route is nonsensical. The money should be given to a town that would be improved by a cycle
path. 
This is a really badly designed survey. 
Stop interfering with things that don’t need fixed 
This idea is a load of nonsense 
I object to the plans. This is a waste of time and money and upheaval and no benefit to the community or visitors. Why put a cycle path in a place where one
isn't needed? The cycle changes could be made to improve access up High Street to the Academy. 
Improve the surface of the promenade and the Albert Pier area 
The path simply will be underused 
The whole project is pointless, unnecessary & a waste of money. 
Its a waste of communuty money when the park is a mess with the grass cutting being no lifted, theres no football goals, skateparks, the the kids parks needs
a facelift. The prom wall is falling down, theres weeds growing everywhere. Understaffing the council in alot of departments. The roads are a mess and full of
pot holes and lets not start on the pavillion and whats happened there. 
There is not enough cycling on rothesay to justify this 
Not needed fix all the other roads and pavement s 
Waste of money 
Taking over a large part of the pavement is not appropriate - are people meant to walk in single file along the pavement so they do no disturb the cyclists? 
Very concerned as it appears that no negative comments are being put forward on the other page. 
No, there is no barrier between cycle path and pavement - dangerous for pedestrians, narrowing the pavement also a hazard as is introducing floating bus
stops.  This plan will limit the number of people wanting to walk in the town and will reduce customers to local shops as they may decide to walk along
esplanade instead. 
Not heard any voices in support of this plan 
Not needed 
As per above 
Unless I am mistaken? The plan is for people to cross a cycle path to get on a bus? Not acceptable 
This is a terrible idea and a total waste of money 
I think the design is aligned to the needs of the community, but the benefits to pedestrians and wheeled transport users could be emphasised more. At the
moment, car owners seem to be directing their frustrations at cyclists, which seems to be missing the point... 
Not needed 
There are plenty of of walking pavements already

Page 117

114 | P a g e
www.connectedtp.com 
Leave as is and spend the money allocated in a more beneficial way. 
The volume of traffic particularly in the summer months needs more car parks. 
No need for a cycling line at all, for people walk pass battery Place there is enough space and safe areas. Cyclists also have enough space to pass on the
normal road. 
We do not needed, by only think about the cyclist, the project would hurt all accommodation business along battery Place.  Alos will make problems to
residents to park up their own cars. It is unnecessary project for Rothesay 
The project is not a bonus to the island at all 
This area already has a very good pedestrian access 
Community don’t want or need this 
Don’t want or need this 
The plan does not allow connectivity within town now does it take into account actual needs of community - this is an aging community so mobility scooters
are an issue 
The route does not connect anything that is useful for those that live on the island (wet and windy one). The connectivity is needed up the high street to the
doctors, the hospital the sports center the cheese factory and school. 
Existing pavements require to be resurfaced and left as they are. 
I’m concerned that nobody will pay attention to what the majority want and that is to CANCEL THIS IDEA. 
The funds should be used to reinstate the pavements at the broken sea walls along Ardbeg Road, this would improve the walking experience for everyone. 
This would make walking into town worse as the pavement would be narrower. I don’t like walking along the prom! 
Don’t want or need it 
Don’t need it. I walk a lot I this area and don’t think it’s necessary 
No need to spend valuable resources on this. 
Do we really want to spend money on this? 
I think it is the wrong project for a town in decline 
All ready adequate for all of the above 
Waste of money the community does not need this money could be better spent elsewhere 
if it works then great.   the parking and traffic flow needs sorting 
This really isn't a priority for the needs of the community. 
Please spent your money on something that is needed and benefit the residents 
The pavements are wide, mobility users cyclis twalkers all get along. This is not a big computer city town etc where it might benefit 
How on earth can this be justified when improvements are. Ended toTidy 
I do not believe a cycle track is needed through town, it goes nowhere, useful, and at the end of it cyclists will have to return to the road. It does not appear
at all to be aligned with the needs of the community. 
The design will not improve the experience for walkers and will create safety issues.The design will not improve the experience for walkers and will create
safety issues. There is nothing in this design that will persuade people out of their cars.

Page 118

115 | P a g e
www.connectedtp.com 
I don't have faith that this scheme brings any benefit to the community. In fact I think it will actively harm pedestrians that will be expected to use poorly
thought through floating bus stops. 
A good idea, but I would rate as a higher priority the dereliction of Albert Pier and the old Royal Hotel and the dilapidation of some of the seafront buildings.
These badly need the speedy attention of ABC. 
This is a crazy idea 
Very concerned, dangerous and stupid idea 
More pressing issues 
Not listening 
It will cause problems for cars entering the ferry terminal and lanes. People will not be able to walk safely in this area due to less pavement. 
You cannot walk and cycle in the same lane. People with poor mobility, wheelchair users and prams users would not be able to get out of the way of cyclists. 
Feel like the community are being totally ignored 
Not needed 
Only considers cyclists 
I believe some aspects of the design are damgerous to the public. 
Not pleased as it isn't aligned with the needs of the community 
It really is not required. 
Not required as there are parallel paths.  
It is all very well saying it is ringfenced for such purposes - fine, spend it somewhere where it will be of benefit, don't waste it here. 
I truly do not think there is any problem with existing pedestrian, cycling or motor traffic through the town 
Rothesay does not need a cycle lane. Traffic is light and there's ample room on the prom for kids to ride their bikes safely. 
No actual feedback from people who use this daily. The reduction in car parking will harm the town as it’s already a struggle at times - especially busy periods
for those waiting to get into the ferry queue when it’s full. Narrowing the road here makes no sense whatsoever. Reduction in parking for taxi’s also ridiculous
- four spaces are not enough for them. 
Plenty of walking opportunities currently. Plenty of cyclists use the area with no complaints other than the roads need resurfaced in places. There are better
ways this could be done and the lack of understanding by those delivering these meetings is unbelievable. It’s been done with no community interest. 
No cycle path required in town 
No cycle path required in town 
whole project is not required on Bute 
you are over engineering a problem that doesnt exist and I will be monitoring if the community oppositions are noted in this ‘survey’ response 
It will actually cause more harm when visitors are trying to leave the island, the pier is also destined to cause accidents 
This has absolutely no place on Bute as we have an adequate promenade for this already 
Very concerned. The scheme appears to have ignored public opinion from the stage 1 consultation, and the proposed design is out of touch with local views.
The design does not offer any value for money and completely ignores far more practical, and less damaging options to create the scheme which are permitted
under the design guidance. 
Cycle lane not required

Page 119

116 | P a g e
www.connectedtp.com 
No requirement for cycle lane 
The community have very loudly said that they neither need nor want this project 
There is plenty of room at present for walkers and cyclists to move between the Pavilion and the Glenburn areas. 
The community have made it quite clear that the proposal is not needed and that there are far more pressing areas in need of funding. 
In an ideal world fine. We’re not in an ideal world, so put the money to better road and traffic management use. 
In my local experience, Bute cyclists will continue to cycle where they want to. 
Unnecessary. 
I don't recall a local petition requesting this, but I do see a lot of opposition to it 
The consultation exercise appears to be biased in favour of going ahead with it, regardless of local opinion 
No-one asked for it and very few want it 
Overkill. No thought has been given to residents needs 
a much needed investment and well considered project.  Well done in trying. 
I think part of the difficulty with any proposal for change in Rothesay is the lack of community feeling. 
Pedestrians and cyclists, but particularly pedestrians and those with mobility needs, are poorly served by the current provision of pedestrian crossings. The
lack of pedestrain crossings and the lack of control on traffic speeds means that people have to cross roads at dangerous locations. 
As with a lot of these schemes, whilst trying to improve provision for walking/cycling there is an adverse effect on the day to day routines of local residents.
Putting pedestrians and cyclists side by side does not make for a safer environment in this instance. Given the nature of the area around the discovery centre/
putting greens a lot of people will find themselves crossing the cycle path rather than walking along it and therefore increasing the likely hood of a serious
accident between pedestrian and bike. Moving the cycle route along the seafront where there is far more room would minimise this risk. 
I only found out about this by accident, I don't do Facebook etc so I fear many people have missed out on the opportunity to participate in the consultation
hence the low turnout so far. 
I think it's very hard from the provided material to get a good grasp of what outside the largest features are. I 
You receive a negative response on the required question because I'm required to provide on 
Put these lanes in a bigger town 
Sort the roads and pavements out first please 
as a cyclist i have no safety concerns for present cyclists on the road. I would not use this proposed cycle path. 
to focused on bikes. 
Why would anyone use it? it's too short and goes no where. maybe a better idea would be to use the funding to create a safe path up to the school. Walkers
will be vulernable to being hit by a cyclists and dog walkers too are at risk. 
Better using funds for potholes 
All residents and visitors need access to shop, amenities and services in rothesay. Some need it to park on the front street and infact their homes and
residentsies 
Improvement is not needed in this town

Page 120

117 | P a g e
www.connectedtp.com 
What changes would you prefer the design to include more of?
More crossings to benefit wheelchair users
All looks great
Pedestrian access, parking bays
The marking of parking spaces, as normally people don't park correctly taking up too much space 
Pedestrian crossings, Parking bays
increase taxi spaces, make some kids park or something on the green
more space for the taxes
maybe more things for people and tourists to do, maybe adding better and bigger parks and dog parks and maybe more to do i have no more ideas but
1) Narrowing of the road will consequently reduce speed of the cars, I see this as an additional gain of the project. 2) Pedestrian Crossing is low more will
boost use.
more taxi spaces
hn
kjjjjjjjkjhijh
clarity on crossing priority
crossing at the roundabout from Honeyz cafe side to the Fyne Homes side. Some sort of junction to make it easier to then go up towards the High Street.
Lights which allow bikes to go first at junctions
cycle rute to the school ,more nature , .
Spend the money on more important things 
Not needed!
Not needed 
Not applicable 
It’s not needed
No cycle lane on the pavement or over the pier to Albert pier. Just use the promenade it's been used as a cycle root for years and is perfect.
Not happen at all! 
More road less cycle lane
There is no need for this scheme 
The drawbacks far far outweigh the positives
Parking along battery place
Nothing, waste of money and resources. 
Space for existing road users.
No cycle paths 
None, whole thing is an unnecessary waste of money and will make life worse for most.
Not needed

Page 121

118 | P a g e
www.connectedtp.com 
Do not go aheaf
Cancel the proposal
Nothiing
To stop wasting taxpayers money on non useful plans such as these.
Car Parking 
We don't need this
Don’t need cycle path
Cancel
Things for children to do 
Spaces needed for taxis, there’s normally 8 operational during the day.
Not needed
Nothing. Ridiculous idea. 
It is not required on our island.
Cognisance of areas without already well defined routes 
Stop it completely
Sc the design
Absolutely no need for it at all. Waste of money!!! Spend money on I.proving pavements pedestrian crossings and drop kerbs
None, total waste of taxpayers money
Waste of money that could be spent elsewhere
There should be no need for change as it should not be built.  
Bin the whole design 
I do not endorse this design at all
Nothing. This is ludicrous 
Less cycle space
Implementation of bute community and residents concerns
Safe crossings
I would prefer the town left as it is
Not too happen 
20mph limited
Do not go ahead with the design 
It is not required, scrap the whole idea.
Create more parking as a bus stop should not be beside a roundabout
We don't need a cycle lane
Scrap the whole plan, spend the money fixing potholes instead

Page 122

119 | P a g e
www.connectedtp.com 
Scrapping the design
An alternative cycle path in another area.
None, it is totally ludicrous to suggest that any intervention is needed to the current layout 
Don’t want the route to happen at all.  Complete waste of money.  A lot more important things needing done for the community first
I think it is a waste if taxpayers’ money
Not needed ,
No changes. Whole thing is a joke 
I think it is a preposterous decision to put that into place on a small island
Not
Stupid idea
No need for cycle path
Use of areas already accessible to bikes
Waste of money
Disabled parking
The wide pavement from the Albert pier to be made into car parking bays.
Cancel. waste of money.
None. It’s a lot of shite that’s not wanted. 
Prioritising pedestrians. Not safe to have crossings next to hatched yellow areas near the ferry terminal as traffic often waits on the hatched areas.
Use the prom as a cycle route 
Anandoned
Controlled car spaces
The money would be better spent improving the roads for cyclists. I’ve buckled 2 tyres on the potholes recently!
Funds to keep the gardens along the prom in a good condition as it used to be
Scrap it
Scrap the whole idea
Think it should be scrapped waste of money
Move the cycle lane to the prom
Leave pavements and roads as they are 
Better parking
Pavements are for peoplem not bikes.
Cancelled waste of money
No cycle lane required
Parking
Routes for families / children ie to schools

Page 123

120 | P a g e
www.connectedtp.com 
Keeping children safe first at the schools
Car parking 
Parking
Absolutely none of what you are proposing! We don't need any changes in this area!
Leave it as is
Don’t think it is necessary for our island
Status quo
Nil
Parking
More car parking for short term stops
No change
Better existing path surface
Consideration of safe parking spaces for cars
Money going to other local projects and repairs to existing buildings and the promenade. No need for money being wasted on cycle lanes. The pavements are
adequate and the traffic are courteous of cyclists not to require a lane. 
Parking
N/A
None,I'd prefer the proposed design to be rejected.
Sack mark rinkus 
Parking for cars 
I don’t see what benefits to the community will be released through this scheme 
Parking 
Drop the design completely as a waste of public money 
Improved parking around town in particular for residents of areas of flats
Abandon this ridiculous idea which will only make things more difficult for the town and for the elderly inhabitants
It's not needed
Don’t need it , total waste I money 
Scrapped all together ad other things need attention first 
Scrap it 
Enforce parking restrictions round Albert Pier
Leave as it is
not needed
No to introduce e it at all as not necessary and redirect the funds somewhere more needed e.g fixing the broken storm wall in Ardbeg.
Not to happen

Page 124

121 | P a g e
www.connectedtp.com 
More relevance to the community’s needs.
Need A Decent Car Park Not A Cycle Path
Rothesay needs a car park not a cycle route 
Call the roads their correct name in order that survey may be completed correctly, there is no victoria road on the Island!!
To not happen at all
Not needed
Cancellation 
None – it’s a waste of money.
Better signage, ie road markings, NO vehicles parked on the pavements. 
Nothing, I don't want it
A resolution to an actual problem. Middle of the busy season or any other season for that matter is there any difficulty walking or cycling from the Glenburn to
Rothesay? None I have ever seen. So what exactly is the problem being resolved here? The resolution of a non problem is clearly causing many actual
problems for real residents and holidaymakers. Many roads have one pavement. Battery place has 3 and one of them is wide enough to fit a bus and still have
space to walk and cycle on but somehow Battery place needs more space for walking and cycling. Have the designers been to Battery Place? 
Not required
It's not needed at all
Spend the money repairing the sea wall
Scrap it
Money spent on an area for kids
The design is not required, just because money is available to do something does not mean you have to do it. 
We don’t need it 
Leave route as it is,no cycle or walking lanes as not needed
Scrap this nonsense
Cancel it 
Scrap the idea
The promenade can be used for walking and cycling and the pavements are perfectly suitable for walking
More consideration of busy traffic route - you shouldn’t narrow it
Spaces to sit
Unnecessary
There is already a perfectly good pathway between both sites already
No changes needed here
No change at all
None
Nothing

Page 125

122 | P a g e
www.connectedtp.com 
Cancel the plan
Parking
To use the existing paths that are already there. The prom, the wide pavements. Absolutely no need for this. 
I wouldnt because it is not needed
Don't do it
None, leave as is
Left as it is
Repair properly the damage done by the ?Nov 2022 storms to the Ardbeg Road pavement & railings, and infrastructure. 
Just leave it the way it is 
Taxi spaces for visitors, 4 is nowhere near enough. 
Spend money more wisely 
Don’t know
Not required at all 
I think there are better ways to spend money on the Island. 
There is no need for this so scrap the whole design
Scrap the idea! Many more needed improvements should take precedence!! 
it's not needed 
Parking
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park.
Change to be no route. It’s not needed. 
No renovations. Cycling lanes are NOT needed. A taxi rank is.
Not to go ahead 
Scrap said Proposals altogether. Waste of money 
Fix the pier 
Cancel the plans
Scrap this plan, not needed
Fixing the currently pavement 
I think this is a terrible idea I would spend money on better free parking
We don’t need this! STOP this ridiculous proposal! 
Scrap it
Forget the idea 
We don't want it
Not needed
Wider cycle routes

Page 126

123 | P a g e
www.connectedtp.com 
Complete segregation of bicycles from pedestrians. If you can’t do that, scrap the idea and put cyclists back on road 
It isn't clear in the drawing how access and mobility will be improved for disabled people and wheelchair users
Not to waste money on doing it in the first place
Cycle route not needed 
Scrap the plan. It's clear that nobody wants it. You're looking at these results right now trying to figure out how to spin it into a positive (I've been there), but
this is a glaringly obviously loss.
Scrap it 
Bin it 
Not bother leave everything as is currently make no changes
Scrap it and use the funds else where
Print on soft paper to wipe my derriere
Route is not suitable going through the town, use the promo along the sea wall as this is understandable used. 
Plans to scrap the idea 
It should be abandoned 
Please spend this money on maintaining existing paths, roads and railing
Total waste of money
Spend the budget for this more wisely.
Don't happen 
More of leaving this area as is 
I don’t want the cycle track
Keep road current width in order to get past delivery vehicles 
No changes
Not needed
The project is not necessary and money could be better spent elsewhere. 
Improved road conditions for pot holes and surface of the road
Don't do it to begin with 
Don't start it
No need for it, do not waste any more money 
Scrapped
More parking
Not needed 
Not needed
Nothing
Just repair existing roads and pavements

Page 127

124 | P a g e
www.connectedtp.com 
None
The layout there is sufficient space along the sea front
Scrap the plan as designed
None ludicrous idea
Money spent on more pressing matters 
Fix the pavements on both sides of Victoria Street
Leave it as it is.
It's not needed. 
VICTORIA STREET not road
No need for a cycle lane
Scrap this ridiculous idea. Not needed or wanted.
This is not necessary there is plenty of space for cycling and walking. Focus on more important issues 
No cycle lane
None, it shouldn’t happen
It not to happen 
No design no projects 
Don’t do it
Don’t do it
None 
Just don’t do it
Do not think it is needed 
NA
More parking 
None. I see absolutely no benefit in this scheme
Update the promenade for walking and cycling.keep pedestrians away from cars. As little development as possible.
This is not needed on our island
It should not happen at all
Spend the money elsewhere it is not needed 
None
Don’t feel this is required traffic isn’t such an issue on Bute
Cancel 
Scrap the idea
Walking space needs to be priority over cycling. More people walk this route and squeezing the walking space down to 1.5 is not a good idea 
Do not believe it is needed

Page 128

125 | P a g e
www.connectedtp.com 
Repairs to existing pavements
Not required 
Free parking 
As opposed to architecturally changing Bute perhaps a wee bit of paint along the super wide pavements to create a non invasive cycle path might be more cost
effective
None
No changes to layout 
Not to waste money
Move it to the prom
Parking
Fix the potholes on the roads
Nothing 
1. Why do you need to place it there. It’s a ridiculous location. There is the seafront to cycle along. 
Parking.
Not needed 
No cycle lane  wate of money 
Scrap the project 
Keep existing 
Greater use of existing infrastructure, to reduce costs and provide more impact .
Scrap the idea, won’t work & cause congestion 
Abandone what is clearly a pointless waste of taxpayer's money that has ZERO local support.
Use the esplanade for overflow pier traffic and extra parking if required 
Could do other things on bute
None
Common sense  
Pavements levelled out for better wheelchair acces.
Planning
Parking spaces in town centre
N/A
None we do not need it
Expand to the whole island
Nothing wrong with what we have
More thought for what the people of the island actually want
Road

Page 129

126 | P a g e
www.connectedtp.com 
Not required 
None, Great Plan
From the marina to Glenburn Road, the shore pathway is in need of resurfacing and repair
Scrap the whole ridiculous project and spend the money on something useful. 
More parking
Existing infrastructure is good
Reduction cycling/walking lanes 
We don't need this
Cancellation 
None of the above. The path towards port Bannatyne or Ardbeg seawall would be more useful
Improved safety for cyclists using the road - for some reason drivers have a problem giving way to cyclists on those two roundabouts.  A lot of cyclists are
heading into the town so still need to use the roads.
More money spent on repair of Albert Quay
Coach parking
Spend money on something the town ny
More parking along Battery Place
Look to increase car parking spaces as much as possible on Albert pier
Total waste of money to impose this nonsense on a rural island community 
Good surface for walking and cycling 
None
N/A
More parking for cars ..
Keep pavement as it is perfectly ok.
To extend it up to Ardbeg or Port bannatyne. 
None
Don't need a cycle path.  There is the promenade to cycle if unsure on road for this stretch
Cancel the whole thing.
just drop some pavements 
Money spent elsewhere
Don't think we need one
More Car Parking Spaces
I would prefer this not to be spent in this but on routes to the school
Scrap it
No cycle tracks

Page 130

127 | P a g e
www.connectedtp.com 
In different areas such as port bannatyne
Where is money coming from 
Not needed
More parking for cars 
A longer length, e.g to 'the fountain' aka Prospect House
Pier is too rich for turning now especially with Commercial vehicles 
We do not need a cycle path there we can use the promenade
Scrap the plan for cycle lane
Parking on Battery Place pavement 
Cars
Scrap it completely
It isn’t needed at all, this question is rigges
More parking for residents
Nothing, money should be used on other things in the town.
We don't need a cycle lane 
Not to happen at all. As it will take away valued pavement for eg walking, wheelchair users and prams
No changes. The idea is useless and will cause more risk of bike accidents 
This cycle path is not wanted and not needed
Most important no 1
This is not needed, and is a waste of money. The promenade and pavements are already wide enough for walking, push chairs, wheel chairs etc. We don’t
have a major problem with space for cyclists - our roads are not hugely busy. 
Cancel the idea
I would scrap it 
Pedestrian crossings
Wouldn’t have it at all. Waste of finances when plenty of open space to cycle a long prom already. 
Not required at all
For the idea to be scrapped but instead for the money to be used to fix the prom as this is where people regularly walk and cycle anyway  
N/A
The design should be scrapped.
Scrap it and where exactly is Victoria Road on Bute ?
Use promenade 
Use existing wide walkways at shore side
Common sense
Not to happen

Page 131

128 | P a g e
www.connectedtp.com 
Repair of existing pavements/pathways
Increased and improved parking facilities within the town centre
More design with trees and some style, bike parking, markers with every kilometre/ mile
Pavements should be for pedestrians only. There is already plenty of paths in existence. Cyclists have no issue using existing roads. I would be too frightened
of using a path shared with cyclists.This is a waste of money and will cause a huge headache for residents.
Don't want it
Where possible use existing sea path, just do a cycle lane, it’s wide enough and put signs 
Stop forcing active travel on unwilling voters
Extend to full blown cycle lanes on island 
More taxi parking places perhaps
Nothing money would be well spent on other things
More parking
More parking
It's a waste of resources money could be spent on other pressing matters 
No changes just scrap the idea
Cancel the project 
This area is already wide for bicycles so not needed in this area.  Ardbeg to Rhubodach would be far a more useful route to change.  The ferry entrance on this
design will NOT work with cars, trailers, HGV’s trying to navigate a very sharp narrow turn
As a regular cyclist, I say scrap it, not needed or wanted
Not needed
Fix pot holes
More spaces for taxis as I’m a taxi driver and we have 11 taxis on the island and not just the 4  you’re making space for  
Repair Ardbeg Road. 
Speed control measures especially from roundabout out towards Battery Place 
None 
Scrap it.
No benefit to anyone 
The route is wrong, this area isn’t an issue for cyclists, roads are wide enough for people to overtake
We don’t need this . Period .
Funding go to other community needs
Car parking
None
I would prefer it to be scrapped altogether 
More parking

Page 132

129 | P a g e
www.connectedtp.com 
Don't bother, redirect the money where it's needed
Don’t do it at all not needed
Should be cancelled
N/A
Stop it 
Parking for cars
Short term parking. Taxi and coach parking ( more users per vehicle). People with additional needs.
It shouldn't go ahead 
None 
Not being there
Cancel it completely 
More consideration for ALL locals and tourists
No alterations to road layout
Scrap it
Stop wasting money on a useless idea 
Don't do it 
Design is not the issue. We have a prom why not utilise that? 
Would prefer it not to go ahead
These roads are already safe for cycling 
I would prefer the design to leave Bute and take itself to where it is needed, like some dangerous roads in Sandbank for instance.
SCRAP THE PLAN.Misplaced plans to fix something that does not require to be fixed whilst simultaneously creating problems that didn’t previously exist and
compounding those that did.  That's an emphatic 'No' from me!
Car parking availability 
Not to spend the money on a cycle route that isn't needed.
More pedestrian crossing points.
common sense
Leave as it is pavement could do with a repair in places 
do not proceed with this
I would prefer the existing roads along the shoreline of proposed ludicrous development to be properly repaired
Parking spaces
I don't want 20 min neighbourhood 
No bike lane 
Use  of the promenade  
Waste of money

Page 133

130 | P a g e
www.connectedtp.com 
We don,t need any changes to the walkway from pavilion to Albert pier
Scrap it
Actually listening to the community and locals who do not feel this is necessary 
Vehicle parking 
More ambitious. A cycle path is required along the flat from Port Bannatyne to Kerrycoy. The roads are not safe for cyclists.
Cycle route not needed
Sensible removal of concept
1 We do not need it!
Remove the cycle lanes, they're unnecessary 
To make more use of the under utilised space on the Promenade  
Total waste of money
Stop the consultation. The proposal is not required
Scrap the design sounds the money  on more useful stuff 
Parking
Parking spaces
Abandon it 
None of proposed 
Shared Cycling area on prom instead 
Proper car parking spaces in Battery Place
Notjing as its a waste of time and money
No cycle roads and paths fixed and maintenance 
As a frequent cyclist and walker I see no benefit in this proposed concept!
None 
Not needed
Nothing 
Don’t do this
I don’t feel we need this 
None, money could be spent on more essential things
No changes needed
Work on the promenade and seawall at Arbeg . Try walking on the sloping pavement between th sailing club and Arbeg. Money needs to be spent there
The "design" is all wrong! Here is sufficient infrastructure at present and we'll maintained pavements to allow walking, wheelchair use on this route. Some
pavements could be lowered and additional parking space offered
No design required at all
I would rather there was not such widespread changes to the town.

Page 134

131 | P a g e
www.connectedtp.com 
Nothing, spend the money on the war memorial which is in a disgraceful state.
Leave things as they are
No parking by drop kerbs as a mobility scooter user this would help me enormously
No
More spaces for coaches. Is this area still one way?   North to South direction or West to East means exit from bus appear to exit at the seaside meaning
restricted space to disembark 
Scrap it
What a prodigal waste of time and money thought up by someone who has to come up with change of some sort and can’t think of anything else. The route is
already used for cycling in three ways. First the road then the existing pavement and also walkway along the bay and two of these ways are already used for
walking.
If there must be a cycle lane, use the promenade and either widen the road along Battery Place to allow car-parking both sides of the road or allow dedicated
car-parking on the pavement where the cycling lanes are proposed along Battery Place
Totally unnecessary 
No bikes
More use of existing promenade rather than roadway.
Fix the sea wall on the Ardbeg Road 
Your centres
Don't do a cycle lane 
No changes
Raised surfaces on carriageway to denote pedestrian priority, would like to see this from Albert Pier to Pavilion ideally, but definitely at area between guilford
square and pier and at designated crossings
It’s unnecessary for the volume of cyclists 
I would like more parking for cars
More room for cars to park on coastal side from Albert pier to Glenburn by reducing size of pavement, with cycle lane nearest gardens.
I do y believe it’s necessary
Cancel the idea in the first place
Signage for cycling in the countryside and not the town
No changes to present situation required 
Im against the bike route our town has problems that need money spent on them first
N/A
Better parking both locals and visitors on the island 
I don't like orthink Bute needs this design or rout
Safe parking 
Not needed scrap it  cause more congestion

Page 135

132 | P a g e
www.connectedtp.com 
Proper consultation with locals.
Reject: what benefits to the community 
Unsure 
Just don’t do it the people of Bute don’t want it
bin it
N/A
Working public toilets 
None it’s not suitable 
Pedestrian crossings
Fixing sea wall 
None
Visitor parking
Proper separation of cyclists from pedestrian routes.  Joint user routes, even with white lines, are increasingly dangerous.
Improved pavements
More parking on Battery Place
Like many others in the local community, I do not want this project to go ahead
Extend route to entire island or at least to Port Bannatyne
It's not needed
Not needed
Visualisations of core changes from pedestrian view
No comment
Unnecessary
We don't need any changes. Waste of money. 
Scrap 
Why not use the existing promenade 
Don’t bother with it 
This whole idea should be scrapped
Sustainable maintenance costs for local council
We need more car parking not less. We have an ageing population, I would inmagine they would find it difficult to cycle to the shops everyday. 
Parking is hard enough
None - scrap it is it not needed
Abandon this project 
1, Don't want it 
I think the whole idea makes no sense.

Page 136

133 | P a g e
www.connectedtp.com 
Fix various steps down to beaches
None of it
No cycle route necessary - improve the prom instead 
Not to be built
Scrap it and use fund elsewhere
Fix roads
The cycle path be rethought as it will not enhance the Isle of Bute
Put the cycle path on the esplanade
No need for it
Make roundabout bigger.Make sure cycle path is not in front of a bus stop. Do not make pavements narrower. Consider sight and hearing impaired
N/a
Ensure that the cycleway is safer and faster than using the road. This means clear delineation between the cycleway so that pedestrian users of the
promenade, road crossings and bus stops do not stray into the cycle lane.
Reduce pavement to allow vehicles easier access for parking in battery place
Safer pavements to walk on and not to be cycled on.  More parking spaces made available.
N/A
Scrap the project
It’s not necessary 
A more imaginative scheme that includes the sea front walk so it can fully integrate walking and cycling.  
I would include COMMON SENSE! I would NOT go ahead with this idea!
The design is a total waste of taxpayer’s money.
Leave
Don’t do it
Don’t think this design is necessary 
More car parking, less electric charge points, less taxi parking space
None a cycle path isn’t required 
some of it looks good.   something needs done
No "floating bus stops"
Don’t build it it’s not wanted or needed
This is a waste of money and not needed 
Leave it as it is
I would like more consideration to be given to the safety of pedestrians with consideration in particular to those with  disabilities 
More consideration of pedestrians using the proposed floating bus stops - which are dangerous and difficult for the elderly / disabled / wheelchair users /
prams / visually impaired impaired individuals etc.

Page 137

134 | P a g e
www.connectedtp.com 
Unnecessary plan
A longer route to go along to Ardbeg. 
Ridiculous idea
Not required 
Object to any changes
Don’t feel there’s any need for it
Prefer it not to exist
Better ease of parking and access for larger vehicles
Car parking
More parking spaces for vehicles as the island had an elderly population.
Evidence that it is needed. The design is ill thought out and will cause considerable difficulty with access to the pier. There will be restrictions in parking too
and as owner of the Veterinary Surgery in Argyle Street this will cause difficulties for clients accessing our surgery with ill pets. You do not seem to be
interested in the views of the Rothesay business community who will be seriously affected by the creation of this and the consequences.
Discarded
Consideration for existing users of this route
We don't need a cycle lane. It's a complete waste of time and money 
Additional parking along Battery Place
Pavement extended to Kerrycroy
this project is not needed or wanted and you are ignoring people’s feedback
Stop trying to force what is clearly not wanted 
The current proposals do not offer socio-economic value to the local community. 
Don’t want cycle lane
To not happen 
Using existing space such as esplanade/pier etc plus ground signage etc rather than wasting money on whole new construction. 
I do not think the proposed route would be used anywhere near enough to justify the disruption and inconvenience to others. 
More money spent on the buildings that are empty 
More car parking spaces for Battery Place
Unnecessary design.
Maintain parking on the section along Battery Place towards the Glenburn
Car parking pass along Battery Place
front green should be included
More traffic speed controls

Page 138

135 | P a g e
www.connectedtp.com 
Complete ban on parking along Gallowgate (enforced) and enforced short term loading only. This is the most dangerous section of road for pedestrians and
cyclist alike and the traffic regularly blocks the roundabout due to illegal parking here. Enforcing parking resections would help to improve safety far more than
this scheme.
██████
Not needed here
Cars parking along the side of cycle path can open doors onto cycle path and can put cyclist endangered
Pavement area for walking
Scarp it
Total segregation of walkers and cyclists
.
More parking
Consider an area that needs improvement and not the front of Rothesay
Use the prom

Page 139

136 | P a g e
www.connectedtp.com 
What changes would you make to the design?
None
Covers for cycling lanes, more parking
Add more parking space for taxis as in somedays they're needed a lot, so instead of 4 spaces i would say that 5 is a better5 option
Covers for cycling lanes, More Parking 
none
a place for skateboarding 
nothing really
rain cover for bikes
more room at ferry terminal's 
sfghsfghfshg
improved clarity of crossing points
The part that goes parallel to the prom could be omitted and make the prom shared pedestrians/cyclists. I also am a little concerned about what happens to
get on and off the cycle lane - if you needed to cross with your bike. I find in other places that it's the transitions that cause problems.
cycle rute to the school ,more nature .
Scrap it 
Scrap design
Not beeded
For it not to go ahead
It’s not needed
Scrap it
No parking box outside bed shops yard needs to be at least 2 metres each side to allow swing for vans and vans with trailers enough swing to use the yard as
it’s used daily
Scrap it
No money spent on it. The discovery centre needs to be saved and the facade of the front is in ruin. Do something that will actually benefit the community
instead of this box ticking exercise
Better pedestrian crossings
Scrap it, see above 
Cancel it completely 
No cycle paths 
None, scrap it.
Not needed
Not needed
Cancellation x 3

Page 140

137 | P a g e
www.connectedtp.com 
I wouldnt start it
Cancellation of this idea.
Scrap it it’s not required and not wanted by the community, this is plain to see online 
Please don't waste the money and get something the island needs
Don’t do it
Cancel
Island doesnt nees a cycle path on the prom when the prom is a perfectly good cycle place as it is
Give it up completely and spend the money on something better.
Cancel all
Scrap the whole lot. 
Scrap it. Scrap it.scrap it.
Change route to includes areas without already well defined wide spaces for active travel 
Scrap it
I would scrap the design
Scrap it all together
Scrap it
Traffic not heavy enough and not enough cyclists to warrant a cycle lane
No change don’t build it
The whole design is not needed 
Cancel the whole plan
Scrap it
As above
All of the above
Remove all together
I would cancel the whole thing
Not too happen
Scrap cycle track
Cancel it
As question 5
None don’t agree
Scrap it
Scrap the whole design, waste of time and money
Making any changes as this is an unnecessary waste of money

Page 141

138 | P a g e
www.connectedtp.com 
The whole concept.  You have taken the safest area on the whole island when there are many more places like the high St for instance that would benefit from
a cycle path.
Scrap these plans
Don’t want this to happen 
Scrap it
Scrap the whole designe and project , waste of public money 
The lot. Scrap and spend on other things 
Drop the whole design
Not 
Scrap it 
No need for cycle path
Less destruction of green land
Scrap the design 
Quite happy with the existing design that has been there for over 100 years.
Not to proceed with it.
Scrap it
If it was put in the bin 
I'd look at sea defences first.  No point in introducing new scheme until the sea defences eg next to the prom are repaired.  Global warming will cause more
extreme weather in the future and protecting sea defences is the main priority.
The hole thing 
Abort
Not to extend to glenburn road
More parking is needed for cars. We do not need a bike lane and I’m a regular cyclist.
Not really needed
Scrap it 
Of little or no use to the community as a whole. Expensive mistake
Scrap plan
Where do you cycle after the pavilion 
Do not do any of it
More parking and seperate area for tour buses 
scrap it completely.
Cancelled waste of money
No cycle lane required
I wouldn’t implement the design without being sure that there is an actual need for something like this.

Page 142

139 | P a g e
www.connectedtp.com 
For it to not exist 
None, waste of time and money 
For the design not to exist 
Scrap it, 
Get rid of it, not needed
Scrap it altogether
Shred it
Not installed 
Parking
Wouldn’t have the proposed path , there is more needing done to the town than this path
None
Scrap it8
Shelve the idea altogether 
Delete the design. No need for it.
Cycle lane on existing prom/path
N/A
Reject the design .
Buy paint for the royal hotel instead 
More parking for cars 
Make more use of the prom space.  There is already wide pavements & prom from town to pavilion 
Cancel it not what the town needs
Abandon completely 
I don’t feel that this design meets the needs of the island  Bute generally is great for cycling at present as someone who cycles regularly on the island
The whole scheme is a ridiculous white elephant
Discard it
Stop the process now! 
Scrap all together other things need attention first 
Leave it .
See no point in this if parking restrictions are not enforced 
Do not agree with this design
not needed
See above 
Scrap it
Relocation of the project to a location more in need.

Page 143

140 | P a g e
www.connectedtp.com 
Scrap It
Change it completely invest in parking space, support locals encourage tourists 
No route for cycles required
Not have it happen 
Cancel it
Cancellation
As for Q5
Good surfaces
Do nothing there is ample space for safe travel and the accident records prove that.
Concentrate funding on actual problems. Railings, poor buildings on front, fixing damaged pavements. 
Not required 
It's not needed at all
Leave as it is
Listen and take heed of the opinions clearly expressed on local social media pages.
Delete 
Revert to main housing to school routes
Scrap the design and put money to better use 
Scrap it
Scrap the design 
Cancel it
Abandon it! 
Scrap it altogether
Move it
Don't build it. Waste of money 
Use the money elsewhere.
Scrap it,scrap it,and scrap it
Get rid of it
Spend the money elsewhere
Money to be spent elsewhere
Scrap it
Cancel it completely – it’s a waste of money that (in the Scottish government didn’t ring fence stupid spending) could be spent on more pressing problems.
No scheme needed - proposed area is very safe already for pedestrians 
Scrap it 
Not needed better things to spend money on

Page 144

141 | P a g e
www.connectedtp.com 
Throw in the bin
None, leave as is
Stop the cycleway from the peir to the glenburn
Scrap it altogether
Just leave it the way it is 
Take away cycle lanes, they won't stick to them anyway. 
Want to spend money on fixing pathways 
None
Not required 
I wouldn’t have it in the first place. 
Forget it! Forget it!! Forget it!!!
See 5.
it's not needed 
It's not needed
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park.
For the idea to be scrapped 
I wouldn't use it.
Not to go ahead 
None, scrap it and do something more beneficial for the community and visitors alike!
Fix the pier 
Cancel the plans
Change it so that it doesn't happen
Maybe have someone that listens to the local voices head it
Cancel it 
I’d scrap it altogether! 
Scrap it
Bin it 
Just spent the money on fixing out roads u know the potholes 
Don’t do it
Wider walking/cycle route
Replace painted separation lines with kerbs and a different surface to prevent pedestrians and cyclists from using same space
Location of dropped kerbs for wheelchair or other mobility aid users
There’s already wide pavements between these two locations on the sea side of the road
Cycle route  rubbish idea

Page 145

142 | P a g e
www.connectedtp.com 
Scrap the plan. 
Bin it 
I’d put the design in the bin 
As above not bother doing the work
Scrap everything
Make paper planes
Scrap the project
Abandon the idea 
I would drop it  
Please spend this money on maintaining existing paths, roads and railing
Scrap it
Just improve the road and pavement surfaces we already have.
Rip it up and burn it 
Scrap it 
I don’t want the cycle track
Am concerned about the proposed width of access into the ferry port for HGVs / Coaches / Larger Vehicles coming from Victoria Street. Proposed access seems
very small and it appears that drivers would need to "Double Back" on themselves
Scrap it
Not needed 
Scrap it
Improve existing road for driving
Don't do it to begin with 
Rip it up
Don't do it
Scrapped
Keeping the taxi rank as it is
Not needed 
We don’t need it
Scrap it
Ditch design and repair existing walkways 
Get rid of this numpty.
Move it completely it won’t be useful to the community 
Scrap it
To abandon idea

Page 146

143 | P a g e
www.connectedtp.com 
Money spent on more pressing matters 
Scrap it
Scrap it.
Cancel the plans
SCRAP IT
Removal of the cycle lane
See answer to q.5
This is not necessary there is plenty of space for cycling and walking. Focus on more important issues 
Scrap it
None – shouldn’t go ahead
Cancel this before you waste more public money on a pointless scheme 
Erase them all and fix potholes 
Don’t do it
Don’t do it
Scrap it
Just don’t do it
For it to be shelved 
I’d leave the existing ‘route' exactly as it is 
More free parking
Cancel it 
Move it to town to School campus route. This route would improve things for the school,college,sports centre, health centre and hospital.
Scrap it completely
Scrapp it
Cancel it, already a very safe route along the promenade
Cancel it
Na
Cancel the project 
Scrap it
Prioritise space given to walking path. 1.5 is far to.narrow for families to walk together. I am a cyclist and would not use the path underhand circumstances. I
have had experience with this sort of design. When the walking space is squeezed pedestrians simply spill over into the cycle path often causing it to be
unavailable or increasing the risk of collision. Young children especially jump low barriers or use them as climbing entertainment. I have had a few near misses
so simply would avoid them
Don’t implement any of it 
Scrap it and spend the money where it's actually needed and would benefit more people

Page 147

144 | P a g e
www.connectedtp.com 
N/A
Nothing really as I haven't seen the design 
Personally, I’d throw it in the recycling bin.
None
Cycle lane not needed
Scrap it
Move it to the prom which will give more space and not impact vehicles
Rip it up
There is absolutely no need for a cycling path on this stretch of road whatsoever. 
Scrap it 
Move it elsewhere it’s not required. 
Scrap the whole thing - a waste of money
Move rout to seafront.
Get rid of it 
No cycle lane 
Give up with this stupid idea 
Scrap it 
Consult the community in advance of proposing a solution to a problem that  the community and visitors do not consider to be a priority 
Scrap the idea & use on other area that would benefit from wider pavement like between Port Bannatyne & Ettrickdale that frequently gets used by
pedestrians & some cyclists prefer to use the footpath rather than the road but the footpath isn’t wide enough for pedestrians & bicycles 
Cancel it
Scrap it 
Spend it on a play park
Scrap the plans
The placement of the route heavy volumes of traffic around the pier are dangerous enough without adding to it!
None.
The route, the pier is extremely dangerous with the constant heavy flow of traffic adding more to the mix will be sure to result in an accident! 
Put cycle path on the Promenade not the road 
Cancel the project
As above 
Scrap the whole project
Nothing wrong with what we have
Resurfacing of the existing promenade 
Disregard whole thing

Page 148

145 | P a g e
www.connectedtp.com 
Scrap and start again
Not required on island
None.
As above
Sack the guy with the white BMW who had the check to illegally park his car at the presentation 
Scrap it
Leave the existing infrastructure.
Abandon it all
We don't need this
Scrap
The loss of parking fir taxis. Parking removed from cars on Victoria Street, the extended pathway will lead to congestion
Make more use of existing infrastructure eg the prom
Abandon
Lose the cycle lane
Not required 
Discard the narrowing of the vehicular access to the ferry lanes
Incorporate some more parking around the pavilion 
Scrap it
Not sure 
Make it longer in the future 
N/A
Scrap the lot
Scrap all of the proposed idea. 
More spaces for taxis
None
No design not needed
I'd stop making changes that aren't required.
none 
Just not do it
Leave as it is
Reduce cycle lanes
Not to proveed
Scrap it
Scrap it

Page 149

146 | P a g e
www.connectedtp.com 
None
Unsure
Scrap it
Don’t do it 
Extend length, 2, 3
Scarp it all 
The design 
Scrap the plan
Parking on Battery Place pavement 
Scrap it
Scrap it completely
to not move ahead with it and use the money elsewhere
Waste of time and money as not needed 
Scrap it altogether, waste of time, money and effort.
We don't need a cycle lane running through our town 
Stop it all together as it is an unnecessary project and a complete waste of time and money. 
Have no bike lane
Scrap it completely 
Plenty of dropped kerbs and disabled parking bays as there is a shortage of both then people park illegally in them
Drop the whole thing. This is going to have minimal positive benefit and numerous negative effects
Cancel
Scrap it 
Keep bishop st roundabout same size
I would better invest the money in a cycle path in the countryside similar to the West Island way. 
Scrap the plans
For it to be binned
N/A
Scrap the whole idea.
Scrap it and don’t come over here parking on pavements and double yellow lines, telling us what is best
Cancel whole design. Not required.
Don’t do it
Cancel the whole plan. 
Scrap the plans
Scrap it.  Cycling lanes are seldom used.

Page 150

147 | P a g e
www.connectedtp.com 
Don't agree with the design and would not include a designated cycle lane
Make like Poland which shares cycling and pedestrian use
This is simply not needed or wanted by us who live here.
None, not wanted at all
See above 
Buildouts are pointless with this level of traffic
None
Could it not go along the prom in places where the prom is very wide?
Scrap it
Scrap it
Scrap it
It's a waste of resources money could be spent on other pressing matters 
Scrap it completely 
Stop stop stop now
The location, Ardbeg to Rhubodach makes far more sense to offer cyclists a path.  Forget the changes at the ferry lanes if the location isn’t changed.  Don’t
take away car parking on Victoria STREET
I’d scrap it completely
Put it in the bin
Fix pot holes in road
More taxi space. No cycle lane as won’t get used 
Don't do it, utterly pointless and has no benefit to community 
? No commented derelict building at pier 
None 
Scrap it.
Don’t do it
Scrap the whole thing, it needs to be totally reevaluated 
It’s waste of our money !
Cancel it
Scap it
Bin it
Scrap it
Bin in
Don't bother , redirect the money where it's needed
Scrap the whole idea

Page 151

148 | P a g e
www.connectedtp.com 
Stop it altogether
Abolish it
Cancel it
Parking for cars
Battery place pavement should be parking area. Taxi rank needs more spaces ( huge user group on bute ). More drop kerbs lined up on both sides for
wheelchair users.
Spend the money elsewhere
Spend the money on something more essential 
It not being there
Rub it out!
Lose the traffic congestion areas
Scrap the whole idea
Scrap it
Don’t design it
Don't do it
See anove
Would not go ahead
Take away the cycle path as these roads are safe
I would erase it and leave things as they are.
SCRAP THE PLAN: LISTEN TO THE MAJORITY.
Bigger entrance to ferry lanes 
Listening to the community and not going ahead with the cycle route. 
Pedestrian crossing with 'lights' where you cross over to go to and from the ferry terminal (over the bridge).
scrap it
Just don’t need it scrap the idea 
do not proceed with this
Reject the proposal and fix the roads and pavements on Bute 
Parking spaces
Completely unnecessary 
No bike lane
Abolish  it
Not needed
Project is a waste of money 
Scrap it

Page 152

149 | P a g e
www.connectedtp.com 
Get rid of it there is no need for wasting money on something so unnecessary 
Do not want cycle paths
Extension of cycle path as above.
Scrap it and spend the money on something more important
Scrapped totaly
Don't do it
Make the cycle lanes on the promenade that's already more than wide enough to facilitate them
Place the cycle route on the prom and improve the signage and sight lines for the elderly drivers on the island
For the money to go to better use on the island
Scrap the design
Scrap the whole thing 
More parking
Cancel this pointless project
Scrap it 
Complete waste of money 
LISTEN & actually do as community wants & not waste money & cause unnecessary upheaval for islanders.
Scrap the whole ridiculous scheme
Srcap the whole idea
Reject it
As a frequent cyclist and walker I see no benefit in this proposed concept! Improve the existing road and pavement surfaces
None
Scrap it
All off it
Don’t do this 
I don’t wish for any of this
Scrap it
No changes needed
Abandon it
I think it warrants full reconsideration
Design not required at all. Leave roads and pavements as they are
I would use the money to improve the promenade and walk ways already present on the island
Scrap it.
Don't change anything leave as is
None

Page 153

150 | P a g e
www.connectedtp.com 
Put
Attention to parking at Battery Place 
Make more parking for cars and free
If taxpayers money is involved I would advise that this unnecessary project should be reviewed.
Abolish the project. Simply because central government is throwing funds at Council is not good enough reason to impose an unwelcome plan on residents.
Not needed
Scrap it 
Move all cycle traffic to existing prom area. Keep existing wide access to ferry queuing. Sack ‘consultants’ to save taxpayers money
Scrap it and do something that's actually beneficial 
Scrap it
Don't do it
No changes
Coach parking in albert pier away from harbourside
Scrap it.
As above 
Not sure
I don’t believe the proposed is needed, maybe for a very few
Cancel the idea in the first place 
Scrap it. Its not needed and will cause a lot of problems and accidents. Unfortunately most, not all cyclists now seem to think they have overall ownership of
the highway. They are silent, and dangerous. 
Leave the roads as they are
The council should be ashamed of themselves if this is allowed to happen 
N/A
Scrap it - the number of Glenburn guests using bicycles is negligible. 
The money should be used for more pressing needs in the town 
No need for separate cycling lane
Nothing  scrap it 
Scrap it
By tearing it up or shredding it and putting it to recycled into something useful like a blank sheet of paper.
I think the location is wrong. I would rather see a route to the school via the meadows.
Don’t do it
bin it
N/A
Working public toilets

Page 154

151 | P a g e
www.connectedtp.com 
Scrap the idea isn’t suitable for the island 
Dont think it is necessary for this area. 
Clean up the Island first 
Didn't want it at all
The narrowing of the entrance to the ferry queue
Remove cycleway between pavement and bus stop. The prosed plan would create more danger than it would prevent
Motor cycle parking  
Make sure the roundabout is big enough for buses to do a complete turn on
Scrap the entire plan
None
Wouldn't have it done
Scheme not need3d
Extending the route to Mount Stuart and/or to Ardbeg
Assuming getting rid of the design is not  an optionssue seeing my answers below
Scrap
Scrap it. We don't need it.
File it away, not needed 
Not reduced access to pier 
STOP
Stop it 
Take a black marker pen and scrub it out
Scrap it. 
Exclude cycle path put in zebra crossing at discovery centre
None - scrap it is it not needed
Abandon this project 
Scrap it & use the money for something useful 
I would scrap the whole thing.
Scrap the cycle lanes
Object to it - no need for this work
Spend the money improving Albert Pier parking area
Scrap it now before wasting more money
Is this the best way to spend the money when the rest of the town is a mess
Don't 
I would take it back to the drawing board and listen to the residents.

Page 155

152 | P a g e
www.connectedtp.com 
Scrap the plans entirely - complete waste of money and a danger to pedestrians 
Don't waste money on
Make roundabout easy for buses and Lorrie’s to use.
Scrap it 
Think about the ends the the cycleway. Too often the cyclist is just directed back onto the road at an inappropriate or even dangerous place. What about
cyclists who are travelling in the opposite direct (Glenburn to Pavilion)? How will they be encouraged and enabled to cross the road safely without interruption
to their journey? Could the cycleway continue on the promenade as a dual-use track shared with pedestrians beyond the Glenburn and Pavilion?
Scrub the hole idea 
Do away with a proposed cycle route as cyclists already have use of the road.
There is no need a cycle line for battery Place 
Not to go ahead
Use the budget for something we need
Re routing the cycle lanes to fully integrate the sea walk promenade 
SCRAP IT! 
Scrap it in its entirety. 
No changes 
Don’t do it
Would not implement this to start with 
Already stated
I’d scrap 
the entrance to the pier, is it too small
I'd scrap it. I don't see any need for it and I'm a cyclist of many years.
Don’t do it x3
This project is waste of time and money 
Scrap it now
Clear signage to mark the end of the route and a safe route back onto the road
I think the design as a whole is a "solution looking for a problem" and as such I think it should be scrapped. We have a perfectly adequate multi-use esplanade
that covers the majority of the route. Cyclists and motorists should be able to share the short stretch of roadway as it exists.
Cancel the whole scheme
The taxi rank probably needs more spaces. Your design shows 4 spaces only.
Don’t do it
There is not enough car parking 
Object to the whole design. 
Scrap it

Page 156

153 | P a g e
www.connectedtp.com 
None. Bin it
Vehicle entry to ferry terminal too restricted especially for large vehicles 
Scrap it
Scrapping it.
Scrap the idea, observe the existing traffic through town, and acknowledge that the idea is needless.
N/a
..
I would cancel altogether
We don't need a cycle lane. It's a complete waste of time and money 
Remove the pathway from Victoria Street – it’s not needed
Pavement extended to Kerrycroy 
All of it. This is not a required project
Where are the other 4 taxi rank spaces? 
Whilst the proposed scheme appears to offer no benefit to the community, the design also fails to consider the opportunities available under the Cycling by
Design Manual. Almost the entire route could benefit from utilising existing footways on the sea-side of the flood wall along the whole route, by developing
them into a shared cycle and footway, as per chapter 3 of the manual.
Don’t want cycle lane
Cancel
See 5
Findings that were undertaken to justify this proposal should be made public - how many people are in favour of it?
Put money into the places that need attention 
Do away with whole project 
Cancel whole thing.
Maintain parking on the section along Battery Place towards the Glenburn
Abandon the scheme altogether
more taxi spaces
Although probably not possible at this stage (but could be something for the future), and if opposition meant that the section along Battery Place was
abandoned, it would be good to extend the scheme as far as Port Bannatyne. This would give a connection between the two communities and, also, provision
for pedestrians who frequently use the northward route from Rothesay for exercise.
Improve the existing footpath along the sea front at Battery Place and provide proper parking on the coast side of the road to separate pedestrians. This would
also make it safer for cyclists.
Victoria Street - High Street - Ferry terminal junction: No pedestrian island nor bikelane across the north facing side. Leave ferry lane access alone. Route
pedestrians/bicyclists in a U shape around the junction, and section off the north-west/north-east edges to discourage non-vehicle traffic crossing the ferry
lanes.
Not needed here

Page 157

154 | P a g e
www.connectedtp.com 
Cycle lanes on road and not pavement
Leave the bays same size and not obstructor traffic at chapel hill area
Scarp it
Put the cycle lane on the road
Forget the plan
More parking
Forget it, Scrap it
Scarap it 
.
none 
none 
idk 
idk 
more taxi bays 
traffic lights unnecessary 
fgshsfhf 
sghfsghfsgh 
cycle rute to the school 
more nature 
Scrap design 
Scrap design 
Not needed 
Not needed 
Cancel the project 
See above 
Fire all in charge 
Not to do it 
Just scrap the idea 
The taxi rank would be to small for the 10 plus taxis and buses would struggle to get round a smaller round about 
Scrap it 
And again, scrap it 
Scrap it 
As above 
As above

Page 158

155 | P a g e
www.connectedtp.com 
No cycle paths 
No cycle paths 
Not needed 
Not needed 
Use money elsewhere 
Please give the island something that will improve it, as this is not it. 
Please listen to the community of the isle of bute 
Don’t do it 
Don’t do it 
Not required 
Not suitable 
Fix Ardbeg Road shoreside it’s an eyesore. 
Fix the towns eyesores. 
Cancel 
Cancel 
Sack whoever’s idea this was. 
Set fire to the plans.   
Improve the parking bays and introduce more zebra crossings 
Narrowing the entrance to the ferry lanes will create traffic jams, especially if the road has been narrowed 
Spend the money on fixing the esplanade 
As above 
As above 
Scrap it 
SCRAP IT 
Like into something for youths 
Put the money elsewhere 
Impose 20mph limit 
improve parking 
Making any changes as this is an unnecessary waste of money 
Making any changes as this is an unnecessary waste of money 
There is already a safe area for bikes and pedestrians that requires no crossing of roads, so literally all you are doing is paying to put down paint. 
Use the money to put in safe zebra crossings at all the schools 
Listen to the public on Bute 
Stop spending money unnecessarily

Page 159

156 | P a g e
www.connectedtp.com 
Scrap it 
Scrap it 
Na 
Na 
Spent money wisely in the town 
Happen 
To 
Scrap it 
Scrap it 
Finish projects already started 
Fix roads 
Use of areas already bike and walk friendly ie the prom 
Scrap the design 
Scrap the design 
Why not use the existing promenade and widen  at battery place . This would save money on the grass cutting.!! Also other councils have made exemptions
to pavement parking why can’t Argyll and Bute council enforce this ? 
As above 
Wide pavement made into car parking bays 
Bin it 
Bin it 
Improving road safety, but no point in trying to do this if enforcement just means the occasional visit from a traffic warden who doesn't patrol around much of
Rothesay let alone the rest of the island. 
You've not allowed for enough parking.  Adult cyclists prefer to cycle on the road.  Disabled pedestrians will wall on the area closest to them even if it
becomes designated as a cycle lane. 
Parking on Albert pier for coach’s won’t work when people can’t park properly 
Abort 
Abort 
Parking to be monitored 
Sort out paths so not trip hazard 
Scrap it 
Scrap it 
Scrap plan 
Leave taxi rank as it is 
Stop plans

Page 160

157 | P a g e
www.connectedtp.com 
More taxi rank space as you seem to have reduced it 
Public toilets so tourists actually want to walk around and explore 
Cancelled waste of money 
Cancelled waste of money 
Children 
Elderly 
and burn it! 
rip it up 
Do it somewhere else 
Leave it alone 
Don’t build it 
It’s not needed or wanted 
Bin it 
Just maintain existing roads and seafront eg storm damage in Ardbeg Road untouched for 2+ years 
Nil 
Nil 
Parking 
Parking 
As above 
Sort roads and pavements we already have 
Scrap the plans. 
To be scrapped. 
Not to lose parking 
N/A 
N/A 
As above 
As above 
Fix the pot holes 
Fix the potholes 
Parking for card 
Public toilets 
Cancel it 
Cancel it 
Provide covered bike storage in town

Page 161

158 | P a g e
www.connectedtp.com 
Spend the money in other areas on the island where it’s needed such as road maintenance or dedicated cycle areas out of town on some of the narrower
roads 
Go away and leave us alone 
What part of go away don’t u understand? 
.. 
No cycle lanes 
Waste of money 
not needed 
NOT NEEDED 
See above 
See above 
Spend money on something of benefit to community 
Waste of money when these areas are safe, when was there an accident??? 
No cycle path between Glenburn Road and Rothesay Pavillion 
No Road alterations between Glenburn Road and Rothesay Pavillion 
Do not take up space on the roads for cycle lanes 
The design is ridiculous and would cause chaos on our roads 
Stop wasting money on this proposed project 
Not have it happen 
Not have it happen 
Cancel it 
Cancel it 
Cancellation 
Cancellation 
None 
None 
Do nothing there is ample space for safe travel and the accident records prove that 
Do nothing there is ample space for safe travel and the accident records prove that 
Building improvements 
Fixing damage 
Spend the money on repairing the promanade 
Listen to views being clearly expressed by local residents using platforms beyond your lazy survey which can’t even get street names correct. How insulting
that is to local people!

Page 162

159 | P a g e
www.connectedtp.com 
You should have advertised the link to the survey clearly and repeatedly on local social media sites. Feedback from dozens there clearly state that until
recently they had no idea where to find the survey to express objection 
Change it to something that would provide an are fir kids like battery park in gourock/greenock 
Only spend money on changes that will improve life's or increase economic growth 
Scrapping it 
Scrapping it 
Sack the consultant 
Start spending it on the pavements replacing cracked slabs that have been neglected for too many years. Oban has no cracked slabs. 
Cancel it 
Cancel it 
Use the prom which is already there 
Use the money elsewhere. 
Use the money elsewhere. 
Put in bucket 
Rip it up 
Money saving 
Reinvesting the money elsewhere 
Cancel the plan. Redirect the funds to higher priority problems. 
See above (there can only be one MOST important change. 
People need to have car parking spaces 
You are narrowing already narrow roads 
Waste of money 
We the community of Bute don't want it.. 
Leave the taxi rank 
Scrap the idea 
More parking for cars in battery place by making the pavement narrower 
The head of the pier is already a dangerous junction when the ferries are busy so not making it worse 
Want to spend money on fixing the roads 
Want to spend money on more disabled parking spaces 
Nome 
Scrap the whole project! 
Spend the money of more worth while causes! 
Why has this been allowed to continue in the face of public opinion. 
it's not needed

Page 163

160 | P a g e
www.connectedtp.com 
it's not needed 
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park. 
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park. 
I'd throw it in the bin 
Just scrap the whole idea. 
Fix pot holes 
More public toilets 
Pen pushing, box tickers from the council 
Put project in bin 
Spend money on better things for community 
A cycle lane up High street to the Joint Campus would be more beneficial to the community. 
Waste of money. The community does not want this!! 
Scrap it 
Scrap it 
Move on to somewhere else. 
RIP the proposal up 
Don't change anything! 
This will causes a issue with parking 
Don’t do it 
Don’t do it 
More benches 
Don’t mess up the roads 
Move it into the prom 
Don't  need this on the island 
Waste of money 
Scrap the plan. 
Scrap the plan. 
Big bin fit consultants in 
Spend the money on something the Island needs 
Cancel it. We don’t want it 
WE DO NOT WANT OR NEED THIS 
As above 
None required 
As above

Page 164

161 | P a g e
www.connectedtp.com 
As above 
Better use the money on other services 
Cancel all plans 
Stop the whole idea !!! 
I would leave the route unchanged 
Leave the area untouched 
Please spend this money on finishing pavilion 
Please spend this money on royal hotel 
Scrap it 
Scrap it 
Do not waste the town 
Stopped prepositions 
Burn it 
Ripe it up 
Keep the Bus Stop Lay-bys. Current bus stop lay-bys allow all other road users to pass when buses are picking up passengers. Moving the bus stop into the
road will inconvenience other road users, thus causing congestion / increasing exhaust emission levels 
Reinstate parking outside Rothesay Pavilion. Parking here will be especially required when it eventually reopens 
Burn it 
We don't want it!!!!! 
Spend the money on something that the community actually needs 
As above 
As above 
Don't do it 
Don't do it 
Repair our paths and roads 
Use the cash for repairs 
Scrap it 
Scrap it 
None 
None 
None 
Stop it going ahead 
Scrap it 
Scrap it

Page 165

162 | P a g e
www.connectedtp.com 
More public convenience open for longer 
Spend the money making appearance more inviting. 
Not needed 
Would be detrimental to the area 
4 taxi bays ? There are 11 taxis in Rothesay and every one of these spaces are required 
What a waste of money. The council budget will never cover the cost of maintaining this 
Stop 
Not going ahead with the project 
Stop wasting money 
Dont do it 
Leave the community alone 
Do nothing 
Do nothing 
Move the route 
Cyclists are a bloody menace - keep cycling on pavements and nearly knocking people over especially the blind and partially sighted who don't see them
coming 
Just don't do it!!!!! 
See above 
See above 
Cancel the project 
Cancel this wasteful project 
Scrap it 
Scrap it 
Cancel the Albert Pier to Glenburn stretch as this stretch of road needs more off road parking 
Nothing 
Use the existing esplanade 
None 
None 
Change size think of the lorry’s and tractors using the road 
Needs to be moved as you can’t make the roads smaller 
Don't do it 
Forget it 
There is absolutely no need for a cycling path on this stretch of road whatsoever. 
There is absolutely no need for a cycling path on this stretch of road whatsoever.

Page 166

163 | P a g e
www.connectedtp.com 
Pavements sorted 
Pot holes sorted 
Move it elsewhere 
Where are people goi g to park in Victoria Street. Parking is restrictive enough. 
Survey aimed at walkers and cyclists. Ask drivers and local shops what would be best for town 
Take away the restrictive entrance for vehicles your design shows. 
Ferry terminal entrance 
Ferry terminal entrance 
No cycle lane 
Sack  mark arrogant and incompetent 
Give up with this stupid idea 
Give up with this stupid idea 
Scfap 
Scrap 
Do not hinder access to ferry terminal . It is creating a conflict between users and inviting a collision 
Cancel it 
Scrap the whole idea 
Scrap the whole idea 
Scrap the plans 
More carparking in town 
Upgrade the Promenade surface and seawall 
Ditti above, it is not required. 
As above 
As above 
Just stop this project 
Use the money for this project for something else 
Consultation into a cycle path between Port Bannatyne and Ettrick Bay 
Painting a specific cycle lane on the existing promenade 
No needed 
Cycle lanes will not be used 
Improve the parking at Albert Pier - Cars parking 30 mins limit 
Not required on island 
Not required on island 
Scrap it

Page 167

164 | P a g e
www.connectedtp.com 
Cancel the whole plan 
No improvements to existing route needed 
Abandon it all 
Abandon it all 
We don't need this 
We don't need this 
Cancellation 
Stop wasting money on white elephants 
I don't think preventing traffic from turning left into the ferry queue is realistic.  Maybe an all red phase on the lights for people to cross in all directions.  Also
lights need to stay on green when the ferry is unloading, otherwise the turnaround of the ferry can be delayed and active travellers miss train connections! 
Provide somewhere dry for cyclists who are waiting to board the ferry.  Only needs a small bus shelter.  How does making people with bikes stand in the rain
for ages in the middle of winter encourage cycling?! 
Coach parking isn’t adequate 
Taxi rank isn’t big enough 
See above 
See above 
Discard the unnecessary cycle lanes 
Do not add light control of crossings - "zebra" style crossings more than suffice 
Incorporate more cycle parking 
Do not implement these proposals 
Once they start this it will expand all over town to tap into the funding. 
Not sure 
Not sure 
Connect 
More dropped curbs 
Scrap the lot 
Scrap the lot immediately 
Scrap all of this idea. 
Scrap all of this idea. 
instead of roundabouts make crossing 
None 
None 
No design not needed 
No design not needed and I cycle regularly

Page 168

165 | P a g e
www.connectedtp.com 
Don't do the redesign 
Nobody wants it. 
Absolutely no need to do it 
Pure nonsense 
Spend the money on route up to the school or out to port bannatyne 
Used the esplanade 
Scrap it 
Scrap it 
Scrap it 
Scrap it 
Extend length 
Scrap it 
Scrap it all 
Because we don't need it 
Means nothing 
Increase taxi rank 
Not to encroach ferry terminal parking 
And again 
Scrap it again 
Scrap it completely 
Scrap it completely 
Scarp this as waste of money put money to kids soft play or sumilar 
Scrap as not needed, as a daily cyclist plenty of room in road, pavement and promenade already 
Ditto 
Ditto 
For it to be completely binned. The roads are too narrow and the pavements are required  eg  walkers, wheelchair users and prams. It would restrict the
number of essential taxis at the rank. Cause congestion and stop traffic from getting easy access to the ferry therefore causing more congestion.  nu 
Not to happen it is the most stupid and inconsiderate idea, there are other places in Bute where it would be better to put a cycle lane eg out past the yachting
club and Skeoch woods, a much more sensible area. 
Have no bike lane 
Have no bike lane 
As above 
As above 
Ideally spend the money improving the safety of the pavements at Ardbeg and Ettrickdale

Page 169

166 | P a g e
www.connectedtp.com 
If the money cannot be spent improving current active travel walkways, the give funds back and don’t waste taxpayer’s money. 
Don't waste money on it 
CalMac port entrance - new design is completely impractical 
Gallogate Roundabout is very difficult to navigate on foot and need complete redesign with crossing for walkers/cyclists 
Scrap tje plans 
As above 
As above 
Scrap the whole idea 
Scrap the whole idea. 
Scrap this and listen to the community 
Scrap this and listen to the community 
Use the money elsewhere like to widen the pave,EMT and improve routes up to the campus 
Use the shore side paths 
Use the money to fix the pa event and fence on Ardbeg Road 
Use the money to fix the prom 
None 
Waste of money 
Cut cost so can do other work. Signage to cycle track along sea wall 
Use a lane in sea walk 
Retain parking improvements 
Scrap it 
Scrap it 
Scrap it 
Scrap it 
More parking 
It's a waste of resources money could be spent on other pressing matters 
It's a waste of resources money could be spent on other pressing matters 
As above 
Forget the idea 
Cancel the whole thing 
Scrap this nonsense 
Location - not needed for the area you’re proposing.  Change location 
LOCATION, LOCATION, LOCATION 
Leave the island alone and scrap it

Page 170

167 | P a g e
www.connectedtp.com 
Listen to the residents and scrap it 
Don't do it, utterly pointless and has no benefit to community 
Don't do it, utterly pointless and has no benefit to community 
Speed control for cars etc 
Leave route as it is 
Leaving route as it is 
Look at better routes, for example a safe route for children to cycle to school. 
Stop wasting more money on these surveys, if you are not going to listen to the views 
Cancel it 
Cancel it 
Burn it 
Rip it up 
As above 
As above 
Scrap it 
Scrap it 
Battery place left dide pavement should be parking. This will encourage visitors to leave car and walk to town. 
Taxi rank increase in spaces. 
Ardbeg shoreline needs fixed 
Pavilion needs fixed 
Leaving the town alone 
Not changing what already works 
Forget it! 
Scrap it! 
Consider a different route, one that will benefit folk, not just a change for changes' sake 
Instead of telling locals what they want, actually ask them 
Don't alter anything that already exists 
Don't change the road layout 
Don’t design it 
Don’t design it 
As above 
As above 
SCRAP THE PLAN: LISTEN TO THE MAJORITY. 
SCRAP THE PLAN: LISTEN TO THE MAJORITY.

Page 171

168 | P a g e
www.connectedtp.com 
Coach space made realistic 
The narrowing of the roads 
Actually look at the community you're proposing doing this in and get the names of the streets it'll affect right. 
Check the highway code, apparently the person in town promoting this thinks that people should just park on cycle paths if they need to. 
Traffic Calming (keep speeds below 20mph in town centre) 
Listen to the locals 
Put the idea in the bin 
do not proceed with this 
do not proceed with this 
No need for a cycle lane. As a cyclist for over 30 years the roads in Bute are safe for me and my children to cycle on 
As above 
Scrap it 
It will be hell for disabled drivers. 
It will be mayhem 
Fix the prom with the money 
Install more drop kerbs to current system 
Stop the consultation 
Cycle route nearer the sea 
Pedestrians with prams . Wheelchairs pavement cars 
Repair ardbeg sea walk instead 
Repair promenade instead 
Scrap  the whole idea 
Scrap it 
Have a more family friendly promenade 
Make something for children 
Abandon & start over 
Use the areas that are already available instead of withdrawing amenities that have & needed. 
Scrap it  
As a frequent cyclist and walker I see no benefit in this proposed concept! Improve the existing road and pavement surfaces  
As a frequent cyclist and walker I see no benefit in this proposed concept! Improve the existing road and pavement surfaces 
None 
None 
Scrap it 
Scrap it

Page 172

169 | P a g e
www.connectedtp.com 
Take away the plans all together 
We don't need this 
Don’t do this 
Don’t do this 
No changes needed 
No changes needed 
Abandon it 
Abandon it 
Lower pavements 
Parking space 
N/A 
N/A 
Bin 
In 
Improve the failing structure of the promenade 
Reconsider the parking at Albert Pier. The space for 3 coaches is totally inadequate and in the wrong position against the seawall. The old toilet building at
Albert Pier needs consideration 
Do something with the pavilion it is an eye sore 
Fix roads 
Review the process which led to this project being suggested 
Spend the time and money in some better way. There must be a better way. 
If there MUST be a cycle lane on E Princes St and Battery Place, make use of the promenade 
Instead of the cycle-lane along E Princes Street and Battery Place, formalise permitted car parking on the pavement that has already been permitted and
tolerated for decades. 
Use existing prom rather than costly changes. 
Scrap it and do something that's actually beneficial 
Scrap it and do something that's actually beneficial 
Same 
Same 
No changes 
No changes 
pavement extension at Pier, blocks route to pick up/ drop off zone when approaching from north. would be better as a raised deck (like big speed table)
reduces speed, pedestrians have more protection, traffic can still flow. 
uni directional cycleways on either side of road as opposed to bi-directional on one side of road. Proven to reduce conflicts at junctions

Page 173

170 | P a g e
www.connectedtp.com 
Ditch this nonsense 
Sack the clown consultant at the meeting who park illegally for starters. 
As above 
As above 
Coaches to park Albert Pier 
More room for cars to park Albert Pier to Glenburn 
As above 
As above 
The design is unnecessary 
The urination of that part of Rothesay 
Leave it as it is 
Scrap the idea, utter waste of money 
Way too narrow particularly at bottom of bishop street / roundabout for buses and emergency vehicles 
bin it 
bin it 
N/A 
N/A 
Working public toilets 
Working public toilets 
Keep well away from the exit from the ferry 
Completely waist of money other things fixed first 
Fix the roads 
Don't want it 
Don't want this change 
The narrowing of the entrance to the ferry queue area is too restrictive. 
The section including East Princes Street and Battery Place will eliminate much needed parking for both residents and visitors to the guest accommodation. 
Improving on parking 
Secure access 
Add extra trees along the seafront 
Use pavement outside Victoria Street shops to increase parking 
Wouldn't have it done 
Wouldn't have it done 
Scheme not needed 
Scheme not needed

Page 174

171 | P a g e
www.connectedtp.com 
Cycle route on the seafront behind Winter Gardens 
I would not block off the vehicle access to the peer in the way the design does. This will almost certainly increase congestion. when loading ferries 
I would not increase the number of pedestrian lights as opposed to crossings in the design. 
Idea 
Whole 
N/a 
N/a 
Perfectly god esplanade to walk and cycle this route 
Parking in town limited at present any further reduction would have economic impact on town 
Use promenade 
Don’t waste our tax payers money 
Take a red marker pen and cross it out 
Try to forgive the clueless consultant who dreamt up the scheme. 
Zebra crossing 
Zebra crossings 
Abandon this project 
Abandon this project 
It doesn't go ahead 
Spend the money on something actually needed 
Give the money to a town that needs it or to fund a community buyout of the discovery centre. 
Scrapping the scheme. 
Fill in the potholes 
Make wheelchair accessible kerbs 
Renovate or demolish the Albert Pier Building 
Do not build 
Save money 
Don't  do it 
Not needed 
Listen to the residents. There appears to be a lack of thought re people with disabilities and young children.  The pavements are fairly wide in parts but if you
take away a large proportion of that then other people are at a disadvantage.  If a child runs out in front of a cyclist who is cycling on the pavement who is
liable?  The roundabout being made smaller is another indication that the people who are carrying out the survey do not live in the island as the buses have to
get round it!!  Albert Pier having more space for buses means that yet again car parking is being lost and where will the cars who have to park along the road
to the Glenburn going to park.  The road here is narrow and the bus can struggle to get through.

Page 175

172 | P a g e
www.connectedtp.com 
You have indicated more parking on Victoria Street, however when cars come off the ferry and turn right it is already a tight corner. There is also traffic lights
and cars should not be within the zigzag lines and not near the corner of the street so where would parking be? 
Keep full width of the pavement - important as more people use wheelchairs and mobility scooters as they get older 
Remove floating bus stops -RNIB campaign highlights their dangers 
Scrap the proposals 
This is the same question as above. 
Could some car-parking be included along the stretch of road towards the Glenburn. Cars are currently parking (illegally) on the promenade. 
As above. 
Keep pavements clear for pedestrians.  People should not have to cross a cycle lane to get to Rothesay town centre. 
There is no need a cycle line for battery Place 
There is no need a cycle line for battery Place 
Probably the only area on the island NOT to have a cycle lane 
Save the Council money to spend elsewhere 
Don’t need this 
Don’t want this 
Ideally the cycle route should be for connectivity in the town and should be from the ferry to the school and factory 
something that is useful and includes mobility scooters 
Forget this absolutely ridiculous idea which nobody wants. 
Use money for something sensible that is required. 
Forget the Battery Place leg of the scheme. 
If this hare brained scheme has to proceed then it should run along the prom from the Victorian toilets to the pavilion. 
None 
None 
Don’t do it 
A refurb of Guildford Square would be better 
Spend the money upgrading the building in Rothesay town centre 
All above 
Scrap it 
Scrap it 
parking 
Money wasted 
Waste of money which could be put to much better use 
Scrap it now 
Scrap it now

Page 176

173 | P a g e
www.connectedtp.com 
Reduce the road speed through the town to 20 mph. This will make the road even safer for cyclists. It will also make crossing the road safer for pedestrians. 
The road through Rothesay is already very safe for cyclists, The majority of cyclists who visit or  live on the island are Road cyclists who would not use the
cycle path. 
The only dangerous part of the route is at the traffic lights for the ferry terminal. It wasn't clear how that would be separated from cars. Will it be raised? Will
the cycle route have its own traffic lights? 
Don’t do it 
Don’t do it 
Demolition of Royal Hotel 
More pressing issues 
Can it be changed to the promenade. The money could be well spent repairing the promenade and creating a safe cycle and walking route. 
Spend money on existing pavements 
Spend money on existing roads 
Scrapping it. 
Scrapping it. 
Abandon the idea 
Look for genuine improvements to spend money on 
Do not proceed with the design 
Have consideration for the thoughts of the community 
Don’t reduce access to pier 
No cycle path required in town 
No cycle path required in town 
give up now 
to not proceed 
Legal compliance with crossings, bus stops, 
Scrapping the idea altogether and spending on improving our local hospital/dental services 
As above -even though the scheme is not required - minimal amendments to existing footpaths can be made to create shared cycle/footways as permitted
under the design guidance. 
Don’t want cycle lane 
Don’t want cycle lane 
Discard 
To not be considered 
Direct funding where it is needed most - this proposal is a waste of money. 
Ditto above 
Ditto above

Page 177

174 | P a g e
www.connectedtp.com 
Maintain historic weigh bridge outside the ferry terminal. This is meant to be a conservation area 
Maintain layout of taxi rank. It works, and it allows for more than 4 taxis during busy periods, which can immediately set off in any direction without the need
to turn round 
Fix the pavements 
20mph traffic speed limit through the busiest area 
Do not make the roundabout smaller, people already have difficulty here. 
Move the cycle route to the sea front which already runs to the Pavilion. The cycle hire station is already located in a prime position here so some
improvements to this area seems a more logical choice and avoids sending cyclists to the busiest junction on the entire island. 
Waste of money 
sign markings end of route cycles must move off the pavement 
the present scheme is creating potential danger to both cyclists and pedestrians. There needs to be barrier seperating them 
buffer needs to be bigger for car doors to avoid hitting cyclists. 
its mych to short, why would anyone want to use it 
.. 
Just because funding is available, does not mean you have to use it. 
Not required 
Look at other areas on the island 
Not needed in the area, period 
Not needed! 
Not needed 
Not applicable 
It’s not needed 
We need more parking and wider space for cars no need for a cycle lane 
Something Isle of Bute doesn't need! 
Spend money fixing the prom the existing cycle lane 
Don’t do it 
Additional parking for ferry waiting 
Spend the money on improving other existing infrastructure   
Safe walking and cycling space separated from vehicles, not on a shared roadway IE the PROMENADE 
More parking 
Do not go ahead 
As above 
Dont waste money 
The community deserves something useful

Page 178

175 | P a g e
www.connectedtp.com 
Don’t need cycle path 
Not required 
Skate/cycle park 
Scrap the project and fix the eyesores all over the town 
Waste of money 
Waste of time and money. 
It is definitely not required 
Scrap the design 
Would be better spending money to complete sea wall works at ardbeg 
It is a waste of money and 
Even less cycle space 
Implementation of bute residents and community concerns and scrap all of this 
Car parks 
This is a vanity project which will have a negative impact on our town 
More parking spaces 
Scrap it all together 
Redesigning this nonsense so that it doesn’t exist 
An alternative cycle path in another area. 
Utterly pointless 
Na 
Spend money on a dog warden 
To 
Stupid idea 
Plenty of room for all 
Waste of money 
The road repaired 
Common sense 
We do not want it 
More disabled parking. 
Cycle lane up the high street to the school 
Abandoned 
Cars not to park on drop curbs 
From Albert pier to Glenburn, the road needs more official car parking 
Scrap it

Page 179

176 | P a g e
www.connectedtp.com 
Don't go ahead with it 
Bay parking means cars reversing on to the main road, dangerous 
Instead repair any uneven or damaged sections of the pavement 
Bike shelters 
Cancelled waste of money 
Parking 
Looking after the elderly 
Motorbike parking 
as above 
Do not touch 
Don’t want it at all 
As existing 
Nil 
Parking 
More car parking in Montague street no shops reserving the space outside their shops 
Consideration of more taxi spaces 
Funding to help restore the Royal hotel. No need for a cycle lane. 
Improving existing prom/pavement 
N/A 
As above 
Tell the job centre he left voluntarily 
Parking for coached 
Disabled drop kerbs monitored by parking attendants 
Less emphasis on dedicated cycle areas 
Stop wasting money 
.. 
Use money elsewhere within our community 
not needed 
Consultation for the locals   
Waste of money 
A more useful location. 
Both locals and visitors need parking 
The answers in the survey are taken on board 
To not happen at all

Page 180

177 | P a g e
www.connectedtp.com 
Not beeded 
No parking on pavements 
As above 
NO pavement obstructions! 
Nothing, I don't want it 
The actual width of pavements (there are 3) and roads along Battery Place is massive. Plenty room for parking both sides of the road, a cycle lane and
walking path. Come up with a solution that resolves everything not just one or two individuals priorities. As mentioned above, all issues are already resolved
and have been for decades so someone is finding problems that don’t exist. 
Scrap it. It is not needed 
Use the funds for other better local uses 
Leave route as it is, this is not needed 
It doesn’t happen 
Ridiculous idea cyclists will not use it 
Not required 
There was a plan to widen the road up to the school and make a Cycle route- what happened to this? 
Use the 3rd putting green as a playpark, fenced off, as area for kids waiting ferry in a safe space 
All unnecessary 
Waste of money 
NO CHANGE AT ALL 
See answer 1 
Not narrowing the road 
There are already road users Highway Code  rules regarding the space cars and vehicles must give  bicycles 
Burn ithe proposal 
We do need the taxi rank 
I cycle on the road 
Not taking away walking and driving spaces in a narrow enough lanes 
Don't come up with stupid ideas 
Don’t know 
Get rid of it all together 
it's not needed 
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park. 
Use the money for something else. 
More public toilets 
Sorting proper parking in town so idiots don't park on the pavement

Page 181

178 | P a g e
www.connectedtp.com 
Free parking 
Keep pedestrians safe by rebuilding the sea wall at Ardbeg. 
Scrap it 
Ludicrous proposals 
Wase of money 
Not needed 
More seats to stop at 
Secondly, not to do it 
Not needed in Rothesay 
As above 
Waste of time get someone with a brain to stop it 
Burn it 
Pointless will make no improvement 
As above 
Keep cyclists and pedestrians well away from each other, due to the fact blind or deaf persons would be a great risk of collision and accidents 
Other ways Money should be spent on more needed things 
It is unwanted 
Please spend this money on finishing pavilion 
Same as above 
Improve the road and pavement surfaces that are already there. 
Stop wasting money 
Spending money on repairs 
Add parking / allow pavement parking on/near Battery Place to facilitate residents and Guest Houses in that area 
Repair current roads 
More traffic wardens would help traffic flow and punish council employees who park illegally in white BMWs. 
Footpath to be even and less patchy 
As above 
Do not start it 
Scrapped 
Repair the paths and roads 
None 
Reintroduce access to Esplanade for vehicles to park:as it is rarely used by pedestrians thereby reducing pressure on parking in the town centre and Battery
Place 
None

Page 182

179 | P a g e
www.connectedtp.com 
Scrap the bike plan completely 
Not necessary 
Ample space already for walking and cycling 
Do not implement this. Cyclists do what they want and the majority will not use it they are more content cycling the wrong way on one way streets 
Taxi rank is vital and should not be altered 
No cycle lane 
Waste of money 
Reallocate the funds 
Fix the pavements instead 
Don’t do the plan 
Taking away parking 
N/A 
3 spaces for taxis is not enough 
Car parking along Battery Place. You can easily have up to 40 cars parked on the pavement you are considering for the cycle route at any given time in the
summer. 
Walking and cycling separate from cars 
Waste of money 
See above 
None 
Cancel 
Scrap it 
The area around the busy ferry terminal needs more not less parking to accommodate large coaches etc. 
Repairs to existing roads 
N/A 
Safe walking 
None 
Fix potholes 
Listen to the people who live here 
Use the money elsewhere 
Parking 
Level the pavements for users 
Getting the pavements and pot holes sorted 
2. Why do t you put in a cycle lane up towards Rothesay campus which would be beneficial to the health and safety of the students. 
Safer pedestrian crossings at ferry vehicle entrance exit.

Page 183

180 | P a g e
www.connectedtp.com 
Not needed 
No cycle lane 
Waste of money 
Keep existing 
Invite suggestions and benefits of schemes that are less costly and obstructive to other road users( eg damaged paths nearer Port Bannatyne ) 
Scrap the whole idea 
None 
.
Resurface roads and pavements 
N/A 
As above 
resurface the rutted roads of the island 
Less virtue signalling 
Parking spaces 
Waste of Government money 
The shore railings are in need of replacement or repair 
Improved parking is needed on the seafront. Spend money on this and not this stupid project. 
Better Road Markings 
Change to existing infrasyructure not needed. 
Keep parking available 
Would rather have speed bumps along battery place along to pavilion 
Removal 
Making sure vehicles don't park where they block the route.  No-one does anything about the parking on the footway on Battery Place so how will this be any
different 
Spend money keeping a bank on the island 
Taxi rank 
See above 
More priority given to pedestrians rather than cyclists 
Ensure parking regulations are enforced 
This is a conservation area with a huge wide Victoria. promenade for cycling and walking 
Separate from traffic 
Keep pavements as is 
No cycle lane required already use pavement to cycle on. 
None

Page 184

181 | P a g e
www.connectedtp.com 
More important things to waste money on 
It should be cancelled. 
none 
Roads fixed 
There are already broad pavements and esplanades that can be safely used just mark them up 
Scrap it 
Not needed 
Scarp 
The money would be better spent on fixing the current pavements and roads 
Make cycle lane in high street 
Increase size for taxis 
Deck chairs 
Scrap it completely 
More parking for visitors 
Ditto 
Common sense it is not required 
No bike lane 
Parking on Battery place for businesses and residents is way more important than any cycle path 
Cars have no option but to queue along Victoria Street when the ferries are busy. The proposed changes are going to make this even more of a problem, with
complete blockages along our main thoroughfare highly likely. 
Stupid 
I wouldn't put it in place 
Shared space at roundabouts 
As above 
The design should be scrapped. 
Scrap it and listen to the community 
Use existing facilities 
Invest in a play area 
Consideration for the opinions of the whole of Bute 
This is not needed 
Easier access for those with mobility issues 
Keep separate from road traffic 
Waste of money 
ZebraCrossings

Page 185

182 | P a g e
www.connectedtp.com 
As above 
A workshop to educate car drivers on how to safely pass cyclist's 
Nothing 
More parking 
Less cycling route 
It's a waste of resources money could be spent on other pressing matters 
As above 
The project should be scrapped 
HGV’s trying to navigate a very sharp narrow turn 
As a regular cyclist I’d say scrap it 
Boat traffic will be a nightmare 
Repair road near boat yard 
Landscaping especially at Albert pier 
Scrap it. 
Safety this would make things worse 
The majority of the island roads are suitable and safe for cycling, this will not encourage people to cycle more 
Funding go to other community needs 
Total waste of money 
Less cycle path 
As above 
Don’t do it at all not needed 
Stop it 
Short term paid parking 
Waste of money 
None 
No cyclists 
No benefit to the island 
A more intelligent route 
Use existing wide off road areas I.e. the promenade 
Stop wasting money on a useless idea 
Wider roads 
More parking 
As above

Page 186

183 | P a g e
www.connectedtp.com 
SCRAP THE PLAN.Misplaced plans to fix something that does not require to be fixed whilst simultaneously creating problems that didn’t previously exist and
compounding those that did.  That's an emphatic 'No' from me! 
Parking monitoring and illegal parking dealt with 
Not wasting money which will affect the accessibility of taxi services and parking in town. 
Traffic calming measures (reduce motor traffic speed). 
Weeds removed from kerbs 
do not proceed with this 
Abandon the proposal 
Rubbish bins 
As above 
Scrap the project 
Actually use the money to fix the places bikes can already use ie the prom 
Vehicle parking 
Improving the appearance around the pier 
2 We do not want it! 
Improve the parking, or leave as it currently is. 
Safe for elderly drivers 
Total waste of money 
Its not required 
Bikes off road 
Parking spaces 
Abandon it 
Update/maintenance of prom for cycling to occur  
As a frequent cyclist and walker I see no benefit in this proposed concept! Improve the existing road and pavement surfaces 
None 
Waste of money 
Leave it the way it is 
Don’t do this 
No changes needed 
As above 
For designers to consult local people properly 
Leave existing system in place 
The removal of parking spaces in the proposed areas will impact business across the town 
Stopping vehicles parking on pavements.

Page 187

184 | P a g e
www.connectedtp.com 
Bike 
Parking at Battety Place needs fixing . Although Battery Place seaside pavement is regularly used for car parking that indicates the necessity to create proper
parking bays in this area. 
Fix the roads 
Common sense. 
Improve/ extend waiting area for ferry 
Fix the railings along Ardbeg road 
Town parking 
No changes 
cycle way must be different height to main carriageway and pavement. Essentially 3 levels. when the pavement and cycleway are same level, it creates
conflicts between pedestrians and cyclists 
It causes undue problems to buses and emergency vehicles managing the proposed changes. 
I would like it not to cut off the pier for ferry traffic 
Having the coaches park on the Albert pier and rest of proposed area for cars. 
Safety for pedestrians 
As above 
The promenade needs repaired 
Proper maintenance of existing prom for walking 
The design should be rejected 
Good walking pavements 
Has there been a Health / safety done 
Fix the islands roads , so many potholes potentially dangerous to cyclists 
bin it 
N/A 
Working public toilets 
Cleaning side of pavements as full of weeds 
None 
Provision for parking between Albert Pier and Glenburn Road. 
Bollards 
Plenty of crossing places for pedestrians 
Roads need fixed first 
Not needed 
No comment 
Unwanted

Page 188

185 | P a g e
www.connectedtp.com 
N/a 
Waste of money that could be gainfully in other parts of the island 
Parking 
Abandon the plan 
More road space for cyclists who will not use the cycle path. They will use the road. 
The existing infrastructure is poorly maintained so what hope do we have that they will maintain the proposed scheme. 
More parking 
None - scrap it is it not needed 
Abandon this project 
It doesn't happen 
Small quiet seaside towns don't need cycle lanes. 
.More drop kerbs for wheelchairs 
Scrapped 
Fix pavement 
Same as above 
keep the full width of the pavement for pedestrians, especially those using wheelchairs, mobility scooters or even prams 
Cycle path not in front of bus stop 
N/a 
The extra parking spaces at Albert Pier are welcome, but are these intended specifically for ferry users (which is important) or will they be taken by local
residents? How will the scheme ensure that parking for ferry passengers is prioritised? 
Open up the promenade so vehicles going for the ferry can park instead of waiting on Victoria street 
Safer pavements. 
N/A 
Do not go ahead 
We don’t need it 
Opportunity to repurpose the sea front promenade and make it a real facility for the town 
If you cannot even get the name of Victoria Street correct then there is no hope for us! 
Don’t block the access of the cars entering the pier. 
It 
Don’t do it 
Spend the money on other things Rothesay needs 
More parking access to shop for elderly but not yet disabled 
Don’t need cycle path waste of money 
sort parking out with bays

Page 189

186 | P a g e
www.connectedtp.com 
It’s not needed 
See above 
Scrap it now 
Separate, completely cyclists from pedestrians 
Better access to the ferry terminal for drop off and pick up purposes - the current plan looks to severely restrict existing vehicular access in this regard 
Ridiculous idea 
Crumbling buildings 
People going on a bus will have to cross over the cycling lanes. On the mainland this has caused many accidents. 
Bus parking 
Pot holes fixed 
Evidence that it will be of any benefit at all 
Less disruption 
Make use of the esplanade 
No cycle path required in town 
this will cause disruption beyond it’s so called benefits 
Proper legal compliance with bus stops, crossings, entrances and egress’s 
The survey data provided in slide 3 provides no context to allow the reader to make an informed judgement. Is it parking surveys? bicycle use surveys? From
local knowledge, it would be expected that extremely low numbers of bicycle users along the proposed routes would be identified, which, when considered in
context of the potential CAPEX for the scheme will indicate little value in the scheme. 
Don’t want cycle lane 
Not necessary 
There are more pressing needs on the island for development and funding. 
Mend paths 
More residential car parking spaces for Battery Place 
Maintain layout of taxi rank. It works, and it allows for more than 4 taxis during busy periods, which can immediately set off in any direction without the need
to turn round 
Waste of money 
Delay the scheme until route from ferry to school have been constructed 
route up to the school to make it useful instead 
No Cycling 
This idea restricts other users accessing services in the town and  infact access to the island is hindered 
no alteration to existing roads and pavement
Not needed! 
Not needed

Page 190

187 | P a g e
www.connectedtp.com 
Not applicable 
It’s not needed 
Spruce up the buildings spend the money on that maybe make a play area for kids at the putting green anything but a deranged cycle lane that nobody wants 
Waste of money! 
Scrap the whole idea 
There are more important things needing attention 
This is just a vanity project put together without the consultation of the community 
No cycle paths 
Do not go ahead 
As above 
Nothing 
Why not use the money for a safe school crossing up at the medows/ hospital 
Same 
Not suitablw 
Keep wide promenades they’re safer. 
Total rubbish 
Utterly ridiculous. 
Not needed.....not applicable 
Scrap the design 
Build a playpark on putting green next to ferry 
Is totally unnecessary 
Zero cycle lanes 
Implementation of bute residents and community opi unions re scraping whole project 
Child safe areas 
No cyle track 
Implementing something more useful, like more parking around the town 
An alternative cycle path in another area. 
Not needed 
Na 
More parking places for cars on shore side at battery place 
Happen 
Stupid idea 
Why take it to the pavilion, is there a plan to get this finished? 
Waste of money

Page 191

188 | P a g e
www.connectedtp.com 
The Albert pier area cleaned up 
Don’t want 
Camper vans will park in the coach parking if they're moved off the pavement at Battery Place. 
Abandoned 
Pot holes to be addressed so people on mobility scooters can drive on pavement rather than road 
Help the small shops along the front 
Scrap it 
Make the road wider 
Increase number of kerb drops for disabled users 
Accessible water and air pump stations 
Cancelled waste of money 
Getting the derelict buildings up to use for the community 
Any parking 
as above again, hope you are getting the message! 
Do other work first for the community 
Not needed and a waste of money 
None 
Nil 
Parking 
Shuttle bus from a car park to Pier for commuters who park along Victoria street  go on boat and don’t come back until night time 
Funding for repairing the sea wall and pavements along by the sailing club towards Port Bannatyne. 
No effect to existing parking 
N/A 
As above 
And scrap the idea 
Parking for taxis 
Childrens corner rebuilt 
No loss of existing roadways 
Not needed 
.. 
Do not proceed with this project 
not needed 
Transparency regarding the responses to the questions the community is asking   
Money could be spent on other areas

Page 192

189 | P a g e
www.connectedtp.com 
More consideration towards a wider demographic of Bute’s population. 
I believe a cycle route will put tourists off visiting 
Not happen at all 
Not needed 
Priority for pedestrians 
As above 
Speed limit signs on road. 
Nothing, I don't want it 
Resolve Rothesays actual problems. The railings that the council never fix properly, the pavements damaged by storm never fixed properly, a building upgrade
program to the front of Rothesay to improve image and encourage tourism. This plan discourages tourism in many ways by making parking a nightmare.
There are very few side streets on Battery Place so nowhere for people to park. This is hotels, B&B’s, cafes, residents who may be retained fire fighters for all
the designers know. They need access to their vehicles. 
Scrap it. The vast majority of the local community does not want this 
Support routes for school children cycling 
Leave route as it is, this is not needed 
Consultant learns to park in a proper parking space 
Sort out the route up to the school - there is room to widen in places there and it it’s dangerous for cyclists. Walkers and wheelers can use the promenade on
the waterfront. 
Do not put in a cycle lane. This is a total waste of money when you could be spending this money on Thomson court day centre or keeping the discovery
centre open 
All unnecessary 
Give community funding to make their own changes to benefit community 
No change at all 
See answer 2 
No scheme needed 
The alteration to the front of Rothesay for a minority of users 
Lot of crap not needed 
Put in Pedestrian Crossings for the kids coming down from the joint campus 
Just get the roads fixed 
More coach spaces for tourists so they stop using Guildford square 
Preposterous idea 
Don’t know 
Spend the money on repairing the pathways and roads we already have 
it's not needed

Page 193

190 | P a g e
www.connectedtp.com 
None of it- washing money ABC just like you have on the pavilion. How about reducing prices for the Bute Highland Games in OUR PUBLIC park. 
Less ignorance towards the islanders who LIVE HERE and listen to us when we say we do not want this. 
Fix pot holes 
Fix the potholes! 
No need for it at all 
We already have a promenade. A cycle lane could be introduced there. 
Scrap it 
Waste of money 
Going to cause a headache 
Are you getting the hint yet? 
Thirdly, cancel the project 
Not enough traffic on island for cycle route 
As above 
Consultants to pay back there fee 
Get rid of it 
Just coz money ring-fence for job doesn't mean its a good idea 
As above 
Better car parking bays within the town, as there is lack of parking and bus stops are getting blocked by parked cars. 
Rip it up 
It is unnecessary 
Please spend this money on royal hotel 
Same as above 
Improve local local buildings/infrastructure with the budget for this instead. 
Don't wreck our town 
More of what locals actually want 
Taxi Rank allows only for 4 vehicles, but there are consistently more taxis using the rank. This is important to have as many available as possible when the
ferry comes to port in order to prevent people from being kept waiting, especially when raining. There is nowhere for the 5th taxi to park. 
We don't want it 
Rothesay is already as safe as it can be for cyclists and the current routes, while in need of urgent repair, already provide the community with what it needs. 
Better lighting 
As above 
Waste of money 
More parking needed 
None,  make it disappear

Page 194

191 | P a g e
www.connectedtp.com 
Resurface roads in the town centre, particularly Battery Place to make them more cycle friendly 
None 
Spend money on essentials as opposed to hairbrain ideas. 
Waste of funds that would be better spent elsewhere. 
Community don't want this change 
The extra pedestrian crossings are not required and will only increase congestion 
Waste of money 
We don’t need a cycle lane 
Go away 
Use the money wisely this is not needed 
Leave the place as is 
Money could be better used elsewhere on the island 
NA 
As little development as possible. 
Would be better off repairing the roads and pavements so people can walk without tripping.   
See above 
None 
Cancel 
Scrap it 
Removing parking on the Albert Pier to Glenburn stretch will cause problems 
Repairs to existing benches & shelters 
N/A 
Space to push a pram or wheelchair 
None 
In force parking rules ie double yellows 
Cyclists local and who come here have had no serious accidents 
Don’t do it 
Parking 
Build housing for residents 
More lower kerb. For chairs 
3. 1 and 2 
.
Not needed 
No cycle lane

Page 195

192 | P a g e
www.connectedtp.com 
Spend money elsewhere 
Keep existing 
Use of existing roadway to form painted marked cycle lane . 
Make more parking for cars and disabled people 
None 
N/A 
As above 
Try going out with a cyclist and see the actual issues 
Improvement of the existing tarmac surface at the promenade 
No changes needed to existing roads 
The grass bank and borders are in need of tidying up 
Listen to the views of the public and don’t force this on us. 
Forget the Rothesay Cycle Lane 
The routd is fine as it is 
Tearing up the plans 
N/a 
Community objection 
Less cruise ships more local visitors 
See above 
Increase parking around the pavilion 
It is totally unnecessary, whole community is against it 
Wide enough for pedestrians and cyclists 
Leave our town alone 
Town doesn’t need this change to accommodate cycling and walking. 
None 
This is waste of our money 
Stop making changes for the sake of it. 
none 
Pavements fixes 
More parkibg 
Scrap it 
Not needed 
Scrap 
Upgrade the lighting and walkways we have currently

Page 196

193 | P a g e
www.connectedtp.com 
Not to encroach ferry terminal parking 
Buses 
Scrap it completely 
More parking for ahoppers 
Ditto 
For money to be used elsewhere eg to make the promenade safe before it collapses 
No bike lane 
Parking along battery place is already difficult. This proposal will make that worse. 
Don't waste the money on it 
Ker separation from carriageway 
As above 
The design should be scrapped. 
Scrap it and listen to the community 
Fix sea wall 
Or just don’t bother with this at all 
This is a waste of money 
No silly cones to separate cycle and road traffic 
As above 
Expand to ettrick bay via Ardbeg 
Nothing 
More parking 
It's a waste of resources money could be spent on other pressing matters 
As above 
Please stop this waste of valuable resources 
Don’t take away any parking spaces. Parking is already very limited 
As an experienced cyclist who has cycled all over the world, I say scrap this totally 
Finish pavilion 
Scrap it. 
Safety can’t see how this would make anyone safer 
Parking will be an issue for all the residents along this route 
Funding go to other community needs 
More parking 
As above 
Don’t do it at all not needed

Page 197

194 | P a g e
www.connectedtp.com 
Stop it 
Large vehicle parking ( less carbon footprint print) 
Not wanted 
None 
Not existing 
Waste of money, that could be better spent elsewhere 
Joined up thinking. Just because it looked good on paper or worked in another area, does not mean it'll work here 
Stop wasting money on a useless idea 
As above 
SCRAP THE PLAN.Misplaced plans to fix something that does not require to be fixed whilst simultaneously creating problems that didn’t previously exist and
compounding those that did.  That's an emphatic 'No' from me! 
Road markings clearer 
Listening to the community who are stating that money should be spent on other things that are needed far more than a cycle route which we'll only serve a
very small number of cyclists. 
A repaint of railings 
do not proceed with this 
As above 
Makes the road more dangerous for drivers and pedestrians 
And more vehicle parking 
Improving the appearance 
3 Please go away and leave our main street as it is! 
Take account of the demographics 
Total waste of money 
Safe pedestrian and cycles to get to Montague street 
Parking spaces 
Abandon it 
More consideration for where residents park. Which is area of proposed cycle path.  
As a frequent cyclist and walker I see no benefit in this proposed concept! Improve the existing road and pavement surfaces 
None 
Waste of time 
More car parks 
Don’t do this 
No changes needed 
As above

Page 198

195 | P a g e
www.connectedtp.com 
To LISTEN to the views of locals 
Leave existing roads and pavements 
The disruption to the community in bringing these changes in will be a net negative to the community in the immediate near future. 
Lane 
Improve the weakness issues at the Promenade. Why not take the route in this direction and stabilise the reported weakness on the main promenade. 
Make better parking areas with in Rothesay instead of taking it awau 
Clear thinking. 
Fix the foot path at ettrickdale 
Traffic lights at Gallowgate 
No changes 
The changes to the vehicle queue at Calmac ferry is a nonsense and will cause chaos. 
I would like it to not take away space from the road 
Make all wider pavements small for cycle lane from Pavilion to pier and narrow pavement at taxi rank.. 
Safety for cyclists AND motorists. 
As above 
The sea wall at Ardbeg needs repaired 
Stop wasting money on unwanted projects and focus on improving the existing building stock 
The design would ruin a the town 
Mothball it waste of money 
The bike hire closed there was so little trade 
bin it 
N/A 
Working public toilets 
Paint Building's all over the Island 
None 
Adequate parking 
20mph speed limit 
Waste of money 
Not needed 
No comment 
Unneeded 
N/a 
Why is this project being railroaded onto the locals file it away 
Listen to the community

Page 199

196 | P a g e
www.connectedtp.com 
Scrap this scheme and stop over-paying consultants. 
We need safe places for children to cycle and we already have a prom just maintain it !! 
More parking 
None - scrap it is it not needed 
Abandon this project 
Scrap the idea 
Who asked for this?  Who’s needs dors it address? 
Stop people cycling on pavements 
Waste of money 
Fix seawall 
Same as above 
Do not impose floating pavements in the area - see RNIB campaign for why they are so dangerous to pedestrians 
Sight and hearing impaired 
N/a 
More parking made available for all drivers whether it be cars or coaches. 
N/A 
Scrap the project 
Not needed 
Not to have cycle lanes in this manner 
I would in-ring fence the money and use it to repair the sea walls in Ardbeg Road. 
Don’t take away any of the pavement running along beside the road. 
Alone 
Don’t do it 
Do something about the Royal Hotel instead 
Allow other uses when the cyclists only use it on high days and jolidays 
None we don’t need a cycle path 
cycling on the roads are dangerous a cycle lane is a good idea but how will it work 
It’s a waste of money 
See above 
Leave it as it is 
Ensure that cyclists do not continue along the pavement at each end of the cycle routeroute 
Ridiculous idea 
Overall state of Town 
Elderly and less able bodied will have difficulty getting on a bus and keeping out of the way of oncoming cyclist therefor this will  be dangerous for them.

Page 200

197 | P a g e
www.connectedtp.com 
Loading bays 
Pavements repaired 
Acknowledgement that it will be detrimental 
More parking 
No cycle path required in town 
do not change existing situation 
An official meeting with and Argyll and Bute concil representatives present 
Don’t want cycle lane 
Will not benefit the town 
The railings and pavements all need attention. 
Sort out the places that a person with a pram or mobility problems that can get across the roads without all stepping up curbs 
More car parking facilities on Battery Place 
Maintain historic weigh bridge outside the ferry terminal. This is meant to be a conservation area 
Present the route can only be accessed by road - it ques to no where useful and is a waste of money and funding 
Ensure bikes leave the footpath at the end of cycle route 
Hinders flow of traffic access to pier