Rothesay Pavilion to Albert Pier Active Travel Project 
Stage 1 & 2, Options Feasibility Report
DATE:  February 2025  REF:  501053 VERSION:  FINAL v2

Page 2

MARK RINKUS                                   
Managing Director                                   
Mark.rinkus@connectedtp.com                                         
Contents
1 OUTLINE BUSINESS CASE ..................................................................................................................................................................... 1
2 OPTIONS DEVELOPMENT AND APPRAISAL ......................................................................................................................................... 25
3 DEVELOPING THE CONCEPT ............................................................................................................................................................... 41
4 DESIGN PROCESS QUALITY AND INNOVATION ................................................................................................................................. 57
5 PROJECT DELIVERABILITY AND DESIGN COLLABORATION .............................................................................................................. 64
APPENDIX A – EXTENT OF APPROXIMATE COUNCIL OWNERSHIP ............................................................................................................. 66
APPENDIX B – SOCIAL AND EQUALITY IMPACT ASSESSMENT (SEQIA) ..................................................................................................... 67

Page 3

1 | P a g e
www.connectedtp.com 
1 OUTLINE BUSINESS CASE
1.1 Introduction and Study Overview
The Rothesay community consists of around 4,2071 people with the town
providing the service centre for the Isle of Bute. The island is located on the coast
of the Firth of Clyde. The A844, Victoria Street passes through the centre of
Rothesay and serves as the Main Street providing access to essential amenities
and education facilities and will connect to neighbouring settlements via the B878
and B881 roads that connect Rothesay to the wider Isle of Bute.
The proposed study route spans between the Rothesay Pavilion and the Albert
Pier along the A844 Victoria Street.  A distance of c.965m.  The route can be
considered in two sections split at the ferry terminal and high street junction.
Each section reflects different challenges relating to land use and corridor space.  
This Outline Business Case (OBC) seeks to provide a ‘snapshot’ of the options to
improve walking and cycling within the study extent, setting out a baseline from
which future monitoring and evaluation can be referenced.
This report should be considered in conjunction with the Stage 1 Community
Feedback and Monitoring and Evaluation Report; reported separately. 
1 https://www.nrscotland.gov.uk/files//geography/2022-
census/Census2022_SpatialDatasetsFileSpecification.pdf                                                               
1.2 Recent Study History
Options to improve the town facilities have been considered for a number of
years.  These include:
• In 2010, The Highlands and Islands Regional Transportation Partnership
(HITRANS) commissioned an audit of existing active travel infrastructure
in Rothesay, with the aim of recommending priority areas for future
investment. The actions focused on four key priorities for encouraging
active travel: Priority 1: Clear and simple sign for Rothesay (both
signposting and mapping) Priority 2: Introduction of contra-flow cycling
on Rothesay's one-way streets Priority 3: Montague Street - Bridge Street
town centre shared space system Priority 4: School campus to town
centre (High Street).
• In 2015-16 Remaking Rothesay Charette was produced in response to
the growing concern about population decline on the island. A series of
community and stakeholder engagement events were held in 2015,
gathering ideas and opinions from businesses, community groups, school
pupils, and members of the public. The key outs of the charette are:
-  Redesign of circulation and way finding between harbour and town;
https://surf.scot/wp-content/uploads/2023/04/Remaking-Rothesay-Charrette-
Report-1.pdf

Page 4

2 | P a g e
www.connectedtp.com 
- Detailed reconfiguration of movement and parking across the wider
town;
- Accessibility awareness and improvements;
- Connected transport and active travel.
- The Charette also identified plans for improving the town including a
‘Low Speed Environment’ and also imposing an idea of different
‘Series of civic spaces and connecting routes’.
• In 2013 Fyne Futures, the Sustainability subsidiary of Fyne Homes, and
partners in the Toward Zero Carbon Bute group, sought to undertake a
review, identification and implementation of actions to enable active 
travel on Bute. In Rothesay, the work focused on progressing key actions
identified in the Rothesay Active Travel Audit, and included: 
-1. The development of a cycle signposting strategy for the island,
including routes to Rothesay, although no strategy was proposed. 
-2. The design of a walking and cycling map of the island, including
Rothesay, showing key active travel routes, destinations and transport
modes. 
-3. The review and phasing of developing the esplanade/promenade as
an active travel route between Port Bannatyne and Ascog Bay. The
implementation of the route was split into three phases, with Rothesay
town centre (from the Pavilion to East Prince Street) included in phase 2. 
• In 2016 Argyll and Bute Council commissioned a review of pedestrian and
cycling movements in the harbour and promenade with the aim of
identifying improvements to the poor connectivity in the area. The
present feasibility study builds on that review and addresses the issues,
suggestions and comments raised during the public consultations as part
of Remaking Rothesay Charette.
• During 2018 the town was examined as part of The Rothesay Town
Initiative investigating how the town is being used and accessed.  The
resulting spatial strategy identified several improvement options.  
• Argyll and Bute Council (ABC) have been progressing an active travel
route within the community since 2017.  This study focuses on the route
between the Joint Campus to the north of the town towards the ferry
terminal junction via High Street.  Through a process supporting
community engagement, the project has concluded detailed design
(Sustrans PfE stage 3) with funding now being sought to supported by
the routes technical design prior to future construction.
• Caledonian MacBrayne (CalMac) as the ferry operator commissioned a
safety assessment during 2019. The study examined the layout, access
and operation of the port and made recommendations for safety related
improvements.
1.3 Project Alignment with National and Local Strategy / Policy

Page 5

3 | P a g e
www.connectedtp.com 
As an active travel enabler2, this project seeks to support the connection of 20-
minute neighbourhoods3, linking people and places whilst enabling the movement
of people of all ages and abilities.  The project will seek to reduce car
dependency, reducing the need for car based short-journey trips whilst enabling
the benefits of the healthier options of walking and cycling in undertaking
everyday journeys by sustainable travel modes.
The project seeks to directly contribute to safety and resilience objectives through
the creation of a safe walking and cycling space.
The project is therefore directly and indirectly aligned with national, regional and
local policy and aligned with the strategic objectives of Argyll and Bute Council
(ABC).  
The following strategies and policies are considered relevant to this study:
• The Scottish Government’s National Performance Framework
• Scottish Government Infrastructure Investment Plan
• Active Scotland Outcomes
• Physical Activity Implementation Plan – A More Active Scotland
• Scottish Government Creating Places
• Preventing Obesity in Scotland
• The National Walking Strategy
• The Cycling Action Plan for Scotland (CAPS) 
2 A project which enables travel behaviour change.
• The Climate Change Plan
• The Road Safety Framework; and
• The National Transport Strategy (NTS)
A figure summarising the Scottish government's journey towards reducing car
dependency for single occupancy trips is presented below. 
3 https://www.sustrans.org.uk/our-blog/get-active/2020/in-your-community/what-is-a-20-minute-
neighbourhood
The National Picture

Page 6

4 | P a g e
www.connectedtp.com 
1.4 Population and Demographic Assessment
Rothesay currently has a population of 4,3204 residents based on the 2022
census. The population shows an overall small decline since 2001, summarised in
the following table.
Year Population
2001 5,140
2011 4,637
2022 4,320
The population is evenly split between males and females and weighted towards
ages 60 – 69 years old and upwards.   
4 2022 Census Supporting Information | National Records of Scotland (15 August
2021). "Appendix 2: Population and households on Scotland's Inhabited
Islands" (PDF). Statistical Bulletin: 2022 Census: First Results on Population and
1.5 SIMD Assessment
To understand Rothesay's social challenges, the Scottish Index of Multiple
Deprivation (SIMD) area statistics for 2022 were examined.  The results indicate
that Rothesay is ranked low overall at 558 out of 6,976 places, all social indexes
receiving a low score of between 1-3 out of 10.  
Thirteen out of the ABC area’s 125 data zones were identified as being amongst
the 20% most overall deprived data zones in Scotland.  These thirteen data zones
are located in the towns of Rothesay, Dunoon, Campbeltown, Helensburgh and
Oban. 
All of these data zones are located in the area’s towns, however, deprivation can,
and does, occur elsewhere.  Because the SIMD identifies concentrations of
deprivation, smaller pockets and instances of individual deprivation are not picked
up by the index.
The town has a low level of car ownership with 41% not having access to a car or
van when compared with wider Scotland (31%).  The low ownership presents
opportunities through the study scope to positively influence travel mode choice
through improvements to infrastructure to support everyday travel by walk and
cycle modes. Limited access to a private car will limit accessibility to services and
opportunity by restricting the ability to move around with evidence showing that
Household Estimates for Scotland Release 1C (Part Two) (PDF) (Report).
SG/2013/126. Retrieved 14 August 2021.

Page 7

5 | P a g e
www.connectedtp.com 
residents in smaller communities are typically disadvantaged by being more
reliant on car ownership and exposed to greater costs of accessing goods and
services. 
Most people living within Rothesay commute to work within the town with the
largest movement outside the town being north east to adjacent settlement of
Craigmore.  Residents also commute off-island with reliance on the ferry service.
Travel within the ward is likely but cannot be disaggregated from the reported
census data.
The islands primary employment industries are agricultural and tourism with the
ferry services providing a critical lifeline to the movement of goods and services.
The town suffers from comparably high levels of unemployment. 
1.6 Rural Deprivation
In recent years there has been a greater understanding of the impacts of
transport poverty; where people lack access to services or work and the
contributions that a lack of affordable transport options creates.    
Rothesay SIMD low ranking
Census 2011 Rothesay travel to work
Destination

Page 8

6 | P a g e
www.connectedtp.com 
It is important to consider the aspect of island and rural inequalities, which
creates challenges to living that are different from communities within larger
urban areas5. In reviewing employment in rural areas, the SRUC report highlights
a significantly larger percentage of those in part-time or smaller contract jobs,
often with lower hourly rates or salaries than counterparts in urban population
centres. Many rural areas have become increasingly reliant on the tourism
industry, as a result, many jobs are seasonal and in demand, reducing the overall
hours or contracts available over the year. 
Fuel Poverty Living outside larger urban areas is likely to increase the costs of
goods overall – primarily due to the cost of the supply chain network required.
This can be seen in the fuel cost with a predominant market of independent
providers, unable to offer the prices of larger national outlets. This issue raises a
secondary cost to residents, with island /  rural communities relying more on
private transport, and often having to travel further for services. Ultimately, for
residents of communities such as those in Bute and Islay, more fuel is required to
travel for day-to-day work and leisure. 
A report on the Minimum Income Standard for Remote Rural Scotland and
research on the subject highlights that the cost of food and consumable goods
are between 10-50% higher in rural areas, whilst clothing and household goods
are between 30-50% higher. These estimates do not consider the impact of living 
5 The Scottish Rural Policy Centre (SRUC) published a report entitled ‘Rural
Scotland in Focus’
in the most remote locations where the costs associated with the movement of
goods and services can be even more disproportionate.
The cycling organisation Sustrans through their research has identified three key
areas which can assist in addressing transport poverty.  These are:
• People-centred transport planning;
• Provision of quality accessible, frequent and affordable public transport
service; and
• Development of a transport network that supports the movement of
people to places irrespective of user’s social status. 
Whilst these options may not address the inequalities of island / local transport
challenges; improving accessibility and access to goods and services, through
sustainable travel modes, will provide the community with improved travel
choices better aligned with the National Transport Policy.  In time, these
measures have the potential to reduce car dependency for short journey trips
whilst contributing to people’s health and well-being through increasing daily
physical activity.  The reprioritisation of our streets to a more equitable
distribution of limited space, combined with the reallocation of road space to
support sustainable travel, landscaping, ecological and placemaking will improve
the social and environmental experience of the area.  Transport and access within

Page 9

7 | P a g e
www.connectedtp.com 
the community are a core consideration in helping to mitigate some of the
challenges of rural social deprivation. 
1.7 Understanding Place
Rothesay as a Town
Rothesay is the principal town located on the east side of the Isle of Bute. The
town can be reached by ferry from Wemyss Bay, which offers an onward rail link
to Glasgow.
Rothesay is a Victorian seaside resort and the main town, with a traditional
appearance and Victorian heritage including a Victorian frontage around Rothesay
Bay. Dominating the shoreline amongst the esplanade front green is the
refurbished Isle of Bute Discovery Centre, a unique 1920s circular structure of
cast iron and glass, The centre incorporates a cinema, theatre and many
interactive displays providing tourist information.
The community includes Rothesay Castle and its dungeons. Just behind it is
located Bute Museum.
To the north of Rothesay, through the small community of Port Bannatyne,
lies Ettrick Bay, Bute’s most accessible beach, which is attractive destination for
able swimmers.
Rothesay supports access to several everyday community services:
• Coop supermarket
• Rothesay Academy (Joint Campus)
• Rothesay High Street, supplying most everyday service essentials;
• St Andrews and Rothesay Primary Schools (Joint Campus);
• Rothesay Leisure centre;
• Esplanade Gardens including putting greens and palm trees; 
• Rothesay Castle, Victorian Toilets and cabbie’s shelter;
• Bute Museum;
• Discovery Centre (tourist information) and Cinema; and
• Churches, supporting all aspects of community activity. 
Due to the town’s few surviving examples of Victorian design and styling the town
is a conservation area.
Rothesay Esplanade
Rothesay is famous for its pier and promenade which have been built on
reclaimed land. The original shoreline being located about 200m further inland,
just in front of Rothesay Castle.
The esplanade spans from the ferry terminal east along the coast. The esplanade
is formed as a solid surfaced shared use footway which is as wide as c.14m. The
route is formed in two parts consisting of a wider boulevard located between the
front green and the sea and spanning from the ferry terminal (Victorian toilets) to
around St Johns Place.  From here the esplanade is formed adjacent to the A844

Page 10

8 | P a g e
www.connectedtp.com 
Victoria Street and continues north along the coast essentially becoming a
footway.  The esplanade at this location is considerably narrower at just over 2m
in width. The esplanade provides a number of functions incorporating an inner
and outer coastal defence wall providing protection to the front green from the
Scottish weather and tidal surges. From the esplanade, access can be gained to
Rothesay’s beaches via stairs.  The esplanade is designed in keeping with the
Victorian style incorporating ornate ironwork fences and is a car free route.
Albert Pier
Albert Pier forms the western boundary of the study area located to the west of
the ferry terminal. This section of the study area is shorter than the esplanade at
only 230m in length.  The route is however complex incorporating a narrow route
corridor between the harbour and buildings located on the inland side of Victoria
Street.  With the extent of Albert Pier there are a number of land uses including:
• A 20-vehicle taxi rank formed as a taxi layby on the coastal side of Victoria
Street; 
• A bus stance supporting access to island bus services. The stance is located
on both sides of Victoria Street at the harbour;
• Access to Bishop Street via a mini roundabout;
• Access to Albert Pier car park providing c.20 vehicle spaces;
• Access to a range of frontage business and residential flats.
Limited land space at Albert Pier combined with seasonal high on-street parking
demand will likely be key route design considerations. 
Rothesay Ferry Terminal
The ferry terminal is owned by Argyll and Bute Council and operated by
Caledonian MacBrayne. A commercial ferry port, the port is a lifeline to the island
supporting access for goods and services. The terminal is a 30-minute journey
from the mainland at Wemyss Bay. 
The terminal consists of a terminal building with waiting room, toilets and ticket
terminal.  Access to the terminal from the town is via a pedestrian walkway
adjacent to a covered harbour stance that historically provided shelter to horse
drawn cabs and buses. A relatively new swing bridge provides access across the
inner harbour mouth to the terminal building.
Vehicular access to the terminal is via the Victoria Street / High Street junction
(the principal junction in Rothesay), the terminal is formed as a fourth arm to the
junction configured to provide a 3m wide vehicular drop-off lane supporting
access direct to the terminal building.  Adjacent to this is 6 stacking lanes (1 HGV
and 5 car) for traffic waiting to board the ferry and a single 2.5m traffic lane used
by all traffic existing the ferry.
Traffic movements are supervised by marshals who provide drivers with the
necessary instructions.
The Victoria Street / High Street / Ferry junction is an unusual layout
incorporating non-standard road geometry with some very wide sections of

Page 11

9 | P a g e
www.connectedtp.com 
carriageway. The junction is partially signalised, providing priority to egressing
traffic from the ferry utilising loop detectors in the carriageway.
The signals do not include any support for pedestrian or cyclist movements.
Pedestrians wishing to cross the ferry arm are required to traverse 30m of
carriageway unsupported.  Similarly, crossing of Victoria Street at this location
could also be a challenge as there are no pedestrian signals, provided and the
road often has cars parked along both sides of the carriageway.  Overall,
measures to support access and mobility by those less able have not been
included within the junction design.
Notwithstanding, the separate Ferry Terminal to Joint Campus active travel route
did identify a number of smaller scale junction improvements designed to
improve pedestrian and cyclist mobility. The proposed changes are shown in the
figure opposite.
The design has been developed on the understanding that the majority of
vehicular traffic arriving from the ferry will travel east or west along Victoria
Street / Albert Pier with few drivers choosing to travel directly ahead onto High
Street.    High Street / Ferry Terminal Proposed Changes

Page 12

10 | P a g e
www.connectedtp.com 
Victoria Street
Victoria Street is located to the east of the ferry terminal. This section of the
study area is longer than Albert Pier at around 640m in length.  The route leads
on from Albert Pier at the High Street junction supporting access through the
town to the west. The route is wide with a carriageway of around 18m flanked by
two footways, the coastal side being c.3m and the inland side being 2m.  The
widths of the footways vary along the route.  Within the study extent, Victoria
Street is fronted by a number of businesses including accommodation services. 
The street supports access to the main shopping area on Montague Street located
behind Victoria Road.  Access to the Chapelhill Car Park can also be gained from
Victoria Street noting that the street is often well used for parking with vehicles
parked along both sides of the carriageway.  A number of bus-stops are located
along the route.  A few pedestrian crossing points have been formed using
cobbled ramps to manage vehicular speeds and carriageway buildouts to reduce
pedestrian crossing widths and improve visibility between parked vehicles.
Rothesay Pavilion
Rothesay Pavilion is an internationally recognised building of architectural and
cultural significance.  The building is A listed and is currently being redeveloped
with the intention of becoming a social hub and economic multiplier for the
community, as well as a catalyst for the creative and digital industries in keeping
with its heritage and a magnet for tourists, particularly architectural industrial
design enthusiasts and fans of popular music, dance and entertainment.
Upon completion and once open to the public, the Pavilion is anticipated to
become a key trip attractor / generator and will increase trips from the town
centre.
The Pavilion is also anticipated to include a frontage placemaking design which
will ideally ‘tie-in’ to this project. 
2016 Pavilion Concept showing Placemaking

Page 13

11 | P a g e
www.connectedtp.com 
1.8 Infrastructure Condition
The esplanade is predominately surfaced using a bound surface asphalt between
the sea defence walls. The surface is in generally good condition. Lighting is
provided via Victorian style lighting columns installed on the inland side.
Victoria Street is also in generally good surface condition with both the
carriageway and footways showing only a few signs of failure.  Victoria Street is
lit from the lighting columns on the seaward side and from lighting installed on
the building fronts.
Some dropped kerbs have been installed along the length of Victoria Street
although there are few locations where tactile paving has been provided.
The road includes a number of footways buildouts helps pedestrians cross the
wide road. Sections of cobbled inserts have been used to manage vehicle speeds.
Whilst the surface condition is generally in good condition, the streetscape is a
mish-mash of changes.  Double rows of parked cars and limited formal crossing
opportunities will create challenges for pedestrians seeking to cross the road.
The adjacent front green provides a key recreational space for the town and a
welcoming green space to visitors.  The greens include putting greens, benches
and bins with the benches and bins supporting pedestrians walking the length of
the esplanade.
Overall, the infrastructure within the study area is in generally good condition.  
Rothesay’s Road Surface is in Comparably Good Condition

Page 14

12 | P a g e
www.connectedtp.com 
1.9 Tourism, Visitors and Local Economy
Rothesay High Street provides a core function as the heart of the Rothesay
community and provides a service centre to the wider region.
The High Street consist of a wide range of retail and commercial uses supporting
everyday services. Like all towns, Rothesay businesses face a challenging
economic headwind having suffered through the COVID-19 pandemic with the
cost-of-living crisis, fuel cost rises adversely impacting the viability of businesses
to be able to afford occupying high street spaces.  As an island community, the
decline in footfall due to alternative online / home delivery options is less
pronounced. 
In Rothesay tourism is a core component of the island’s economy, architecture
and heritage such as Mount Stuart, Bute Museum, Rothesay castle, Victorian
Toilets and seafront which all attract tourists and bring business to the town. 
Cycling is also popular with the island which is part of the five ferries challenge
route with many cyclists travelling west to Rhubodach ferry terminal.
1.10 Utilities and Known Constraints
To understand the utilities within the area, a search of utility apparatus within the
study area was undertaken.  These are summarised as follows:
Water supply 
The Scottish water plan has indicated a 90mmm HPPE pipe below Victoria Street
along the extent of the route. Consideration should be taken for any works
undertaken within the vicinity of the pipe work in line with Scottish water
guidance.  
Electricity
Line search before you dig has indicated multiple HV main cables in the vicinity
of the project route. Consideration should be taken for any works undertaken
within the vicinity of the cables in line with SSE guidance. 
Foul/Surface Water
Scottish water GIS plan has indicated a water main is present along Victoria
Street.  
Communications
Telecommunication apparatus was noted to be located along Victoria Street. 
Gas
Gas apparatus was noted to be located along Victoria Street. 
Flood Risk
An extract of the SEPA flood risk for the project area is supplied separately.  The
extract confirms that the project route is not at risk of flooding from a 1:200-year
event.

Page 15

13 | P a g e
www.connectedtp.com 
1.11 Landownership and Rights of Access
The project route extent consists of road space publicly adopted by Argyll and
Bute Council.  The Front Green and Discovery Centre are owned by Visit Bute
whilst much of the land on the wider Isle of Bute is owned by the Mount Stuarts.
The project area is flanked by commercial and residential properties. 
The approximate extent of public road adoption excluding public road adoption is
presented in Appendix A.
1.12 Understanding Travel Behaviour
The study route forms one of the two major traffic routes in Rothesay.  The route
will complement the ongoing Joint Campus to Ferry Terminal route currently
undergoing development.  Once complete, both routes would provide network
within the town centre supporting access from key trip generators to key trip
attractors.  This will include trips to and from local services and towards the
residential areas.
1.13 School Travel
A sample Hands-up Survey (HuS) was undertaken during February 2024 to
understand how the community’s younger members currently travel to the
primary school.  The results of the sample survey show that pupil’s dependency
on travel by car (60%) and bus (40%).  Only 1% of the surveyed children walk to
school and even fewer cycle.
The school engagement has confirmed that a number of the town's younger
members do own bikes and regularly walk or cycle along the route.  The school’s
location relative to the study area is however unlikely to be a key indicator of
suppressed active travel demand for the project route. 
Travel Mode Morning Trip Afternoon Trip
Walk 0 2
Cycle 0 0
Bus 7 11
Car 14 7
Ferry 1 0
Whilst pupil walking is popular, the school is located remote from the study area

Page 16

14 | P a g e
www.connectedtp.com 
1.14 Public Transport
Bus services around the town are contracted by Argyll and Bute Council and
currently operated by West Coast Motors who provide public transportation
services in various regions of Scotland. They offer a schedule of bus services
connecting the various towns to Rothesay including Ardbeg and Ettrick. 
A review of the bus services offered suggest that the town benefits from an
effective public transport service with a wide range of services operating on a 30-
minute service frequency.
1.15 Baseline Data
To support this project, a number of data sources were commissioned to provide
a snapshot of people and traffic volumes speeds and movements during February
2024.  The town is a known tourist destination with many visitors arriving
between May and September.  Any traffic survey undertaken during the peak
seasonal period of May to September will therefore likely reflect seasonal peak
(worst case) results.
The surveys consisted of Automatic Traffic Counters (ATC) installed for 7 days
along A844 Victoria Street, Albert Pier.   Junction Turning Counts (JTC) were
undertaken at Victoria Street / High Street and the Albert Pier / Bishop Street
junctions.  The counters recorded all vehicle movements including speeds by
direction continuously.  
To support an understanding of parking behaviours in the area, parking surveys
were also commissioned to capture parking on-street along Victoria Street and
Albert Pier including two car parks.
In addition to the ATCs, Non-Motorised Users (NMU) surveys were also
undertaken during the same period.  The NMU surveys were located at key
locations along the route corridor. 
Location and range of survey data collection

Page 17

15 | P a g e
www.connectedtp.com 
1.16 ATC Results
The results of the surveys indicate that the typical traffic volumes along Victoria
Street in the vicinity of the Pavilion are around 1,8006 vehicles per day in both the
southbound and northbound directions. These volumes are low when compared
with the roads theoretical design capacity.  Vehicle speeds were noted to be in
excess of the speed limit with an 85th percentile speed of 34mph being recorded
(30mph limit).
Nearer to the ferry terminal junction, eastbound vehicle numbers increase to
around 2,800 vehicles per day.  This indicates that traffic travelling along
Montague Street turns right onto Victoria Street as part of a ‘gyratory’ loop. 
Westbound traffic flow is 1,600 vehicles per day.  85th percentile speeds of
vehicles were noted to be under the speed limit with the eastbound recorded at
25.5mph and the westbound at 26.5mph.
To east at Albert Pier, the number of vehicles travelling in both the eastbound
and westbound directions was notably lower at around 1,000 vehicles per day. 
85th percentile speeds were noted to be around 24mph with vehicles travelling
westbound noted to be marginally slower at 22mph.  This may be as a result of
vehicles having to slow down on approach to the Bishop Street roundabout.
Traffic composition along this route is 86% cars or light vans with 14% classed as
Heavier Goods Vehicles (HGVs). 
6 February 2024 12-hr AAWDT 
1.17 Non-Motorised Users (NMU’s)
During the same survey period, NMU surveys were located on the terminal
junction and the Bishop Street / Albert Pier junction and recorded a single-day
snapshot of pedestrian and cyclist movements.  The surveys captured all
ATC results by location

Page 18

16 | P a g e
www.connectedtp.com 
pedestrian and cyclist numbers by travel direction within a 12hr day 07:00 to
19:00 over a typical off-peak weekday. 
The results of the surveys indicated that at the ferry terminal junction the daily
pedestrian flow was 144 people travelling east/ west on the northern side of the
footway (coastal) and 132 travelling east /west on the inland footway.  Pedestrian
movements along the Victoria Street section to the High Street junction is noted
to be high with around 614 movements recorded on the inland footway. The
majority of these movements then turn right and travel south along High Street.
Unsurprisingly, the cycling numbers are low at this location, noting the time of
year (February). Around 7 were recorded over the course of the day, favouring
the coastal side footway. 
1.18 ABC Cycle Counters
ABC have installed a permanent pedestrian and cycle loop counters on the
Esplanade.  With the exception of when the counter has malfunctioned, the
counter captures data continually 24hours per day and by each day of the year.
The data can be used to understand how the number of pedestrians and cyclists
change over the year. 
The results of the counter indicate that since 2020, the number of pedestrians /
cyclists have declined up to 2022 which may be the result of COVID19 on tourist
visitors to the island.  From 2022 the counter would appear to be malfunctioning. 
Ferry Terminal Junction Off-Peak 24hr Pedestrians and Cyclist Movements
Victoria Street Zebra -Off-Peak 24hr Pedestrians and Cyclist Movements

Page 19

17 | P a g e
www.connectedtp.com 
Notwithstanding the above, the data captured by the counter for 2019 would
appear to be complete.  Using this data a comparison of pedestrian’s and cyclist
demand between an off-peak month and day (February) and a peak season
weekday in September can be estimated.
The results of the comparison are shown in the following figure and indicate that
during the peak season, the number of pedestrian / cyclist trips increases from
174 to 282. This is an increase of 62%. 
1.19 Parking
Parking surveys were undertaken during early February 2024. The surveys
included Chapelhill and Alber Pier off-street car parks and on-street parking. The
survey results indicate that Chapelhill has a capacity of a round 25 spaces with
around 40% of these unused during successive town visits.  Albert Pier has an
official parking capacity of 20 vehicles but during both the weekday and weekend
surveys around 18 to 22 vehicles were parked within the car park and a peak
parking occupancy of 31 vehicles was observed.
Summary of Esplanade Counter Walk / Cycle Data
ABC Off Peak-to-Peak 2019 Pedestrian Cyclist Comparison

Page 20

18 | P a g e
www.connectedtp.com 
The parking duration for vehicles parking regular within the car parks is noted to
be long at over 5 hours suggesting that the spaces are used by the staff of
nearby businesses or local residents. 
Albert Pier Weekday / Weekend Parking Summary

Page 21

19 | P a g e
www.connectedtp.com 
February 2024 Off Peak Parking Survey along A844 Victoria Street / Albert Pier

Page 22

20 | P a g e
www.connectedtp.com 
1.20 Road Safety 
A review of the Crash Map Road Safety7 website indicated that there have been
no incidents documented in the vicinity of the study route between 2018 and
2023. The nearest recorded accidents occurred in the public car park opposite the
kiosk, just off Vicotria Street. The accident was serious, involving only one vehicle
and one casualty. A second serious incident was recorded on the Guildford
square.  No details were available.
It's important to note that this does not necessarily imply that no accidents have
taken place within the study route, but rather that emergency services were
either not required or not notified. 
7 https://www.crashmap.co.uk/
Accident History 2018 - 2023

Page 23

21 | P a g e
www.connectedtp.com 
1.21 Parking, Access and Management
Parking within the study area is split between off-street car parks and on-street
parking.
Within the study area is located a number of off-street parking areas, all free of
charge, consisting of:
• Chapel hill Road. Providing 25 vehicles spaces. During the February site visit, it
was noted that a number of the parking spaces are occupied by the bins from
surrounding properties or caravans.
• Albert Place Car Park. Proving parking for around 20 vehicles.
• East Princess Street. Providing parking for a round 5 vehicles.
There is adequate designated parking along the promenade to cater for all
observed parking numbers. It’s noted there is a lot of pavement parking in the
southeastern section of Rothesay due to the narrow width of the road and
parking on the opposite side residents and visitors are parking with all 4 wheels
on the footway.
For electric vehicles, two 22kW, 32A charging points are available at Guildford
Square Car Park, Rothesay, less than 100m from the Terminal Building.  
The Isle of Bute historically operated a Community Car Club which was open to
both residents and visitors. 
Pavement parking is a common occurrence

Page 24

22 | P a g e
www.connectedtp.com 
1.22 Current Travel Patterns
The 2011 census data for Rothesay was examined to understand current travel
behaviours and travel patterns within the project area.     
It is noted that more rural locations are more likely to be more dependent on
private car use when compared with the Scottish average.  However, as stated
previously, car ownership for Rothesay remains comparably lower at 41%.  
Rothesay is currently participating in the 2024 ‘Beat the Street’ Active Travel
programme.  The results of the initiative may be available for the stage 2 of this
project. 
1.23 Understanding The Communities Demographics
The National Records of Scotland data as at 2022 shows the population of
Rothesay was 4,320.  14.3% were children, 55.1% were aged 15-64, 30.6%
were over 65 years of age and over.  
There is a greater percentage decrease in the population aged 0-15 years
compared to Highland or Scotland.8 The National Records of Scotland shows the
population has decreased by 16% in the period 2002 to 2022 with a difference 
8
https://www.citypopulation.de/en/uk/scotland/argyll_and_bute/S19002472__ro
thesay/
between age groups concerning population change. There was a 63% increase in
the 65+ age group, which occurred year on year since 2002
Over the next 10 years, the population of Argyll and Bute is projected to decrease
by 6.2% due to natural change (more deaths than births). Notwithstanding, Total
net migration (net migration within Scotland, from overseas and from the rest of
the UK) is projected to result in a UK population increase of 0.5% over the same
period.9 
9 https://www.nrscotland.gov.uk/files/statistics/council-area-data-sheets/argyll-
and-bute-council-profile.html

Page 25

23 | P a g e
www.connectedtp.com 
1.24 Where do People Currently Cycle?
Rothesay is part of the Bute Cycle Network, a 23-mile loop around the Isle of
Bute which runs through Rothesay and right along the A844 Victoria Street which
is the site of the proposed development. This demonstrates demand for cycling in
the Rothesay area, and a key tourist attraction. 
1.25 Health and Wellbeing
Being more physically active can benefit everyone and can reduce the chances of
developing preventable conditions such as diabetes and heart disease. Active
travel as promoted by this project will encourage individuals to be more physically
active as part of their daily routine by incorporating physical activity into everyday
tasks.  This reduces the need to find extra time, money or motivation for
exercise. 
The route could also offer savings to some users by saving on fuel, and vehicle
running costs. Making short journeys using active travel helps to reduce the
number of vehicles on the road and improves local air quality and environmental
amenities.
Investment in active travel can also deliver economic benefits with shoppers who
are actively spending less per visit but making more frequent visits and spending
more. Active travel is affordable and delivers value for money in achieving health,
transport and wider policy objectives. 
Studies on the economic benefits of walking and cycling interventions in the UK
revealed an average return of £13 for every £1 invested and returns as high as
£19 for every £1 invested.  
Cycling and Walking Activity from Strava

Page 26

24 | P a g e
www.connectedtp.com  OPTIONS DEVELOPMENT AND APPRAISAL

Page 27

25 | P a g e
www.connectedtp.com 
2 OPTIONS DEVELOPMENT AND APPRAISAL
2.1 Investigating the Network
In advance of the Stage 1 Community engagement process undertaken during
February 2024, the design team worked with the steering group to identify
multiple route corridors which could be used to help identify the community’s
appetite for change and set the ambition for the design.  
The concepts were developed in stages set out as follows:
• A constraints plan was developed to capture all known geographic,
ecological and physical considerations within the identified route
corridors.  Following engagement with Bute Community Council and ABC
a land ownership register was produced to accompany a land ownership
plan.  A suite of data collection surveys was commissioned, including
traffic surveys, NMUs. The results were consolidated and considered.
• The previous 2020 spatial masterplan report for Rothesay Town and the
route concept options developed between the Pavilion and Ferry Terminal
junction were examined.
• The results of the traffic surveys were considered in conjunction with the
route design guidance provided within Transport Scotland’s Cycle by
Design Guidance 2021 update.  
• Through a workshop discussion between the design team and ABC
representatives it was noted that the study corridor is formed in two
halves, each with a different set of challenges. A section between the
Pavilion and the ferry terminal junction benefits from additional road
space and therefore a number of potential group options are possible.
Between the ferry terminal and the Albert Pier Carpark the route corridor
is more constrained and the development of a route option would be
more challenging. There are fewer options available for the route in this
location.
• It was noted that the Esplanade already provides a good quality walking
and cycling route which should ideally support the majority of the route
design. The use of the Esplanade was also noted to be a key objective of
previous studies.  The Esplanade was debated within the design team
and the number of technical challenges were identified. These included
avoiding alteration to the sea defence and the challenges of tying the
route at the terminal back to the ferry terminal junction. On reflection it
was agreed that the Esplanade must be promoted as an option for
consideration
• Between the Pavilion and the ferry terminal junction a total of five
concept route alignments were identified. 
• Between the ferry terminal junction and Albert Pier, a total of three route
alignments were identified.
• Utilising the design team experience in conjunction with the guidance
provided within Cycle by Design 2021, the concept options were created.

Page 28

26 | P a g e
www.connectedtp.com 
It was agreed appropriate that the stage 1 of the project should be to sample the
community’s preference on route corridor.  The options considered are
summarised as follows and graphically overleaf. 
Option Pavilion to Ferry Terminal Route Concept Description
1 Route formed on Esplanade. Use existing route and connect back to
Victoria Street at the Ferry Terminal either through the inner harbour
or along the side of the Front Green
2 Widen existing footpath into winter gardens. Route on inland side of
A844
3 Widen footpath on inland side to suit width constraints.  Maintain
current road widths by widening onto coastal side of A844
4 Reallocation of road space to suit new widened footpath on coastal
side of A844
5 Reallocation of road space to suite new widened footpath on inland
side of A844

Page 29

27 | P a g e
www.connectedtp.com 
Option Ferry Terminal to Albert Pier Route Concept Description
A Widen route and provide path on inland side 
B Widen route and provide path on coastal side 
C Shared use of West Princess Street then widen route and provide a
path on the inland side of the road
A844 Albert Place Typical Cross Section Options

Page 30

28 | P a g e
www.connectedtp.com 
All Route Corridor Options Initially Considered

Page 31

29 | P a g e
www.connectedtp.com 
2.2 Pavilion to Ferry Terminal Junction: Route Summary
Descriptions
Each of the route options are described in greater detail as follows.
Option 1: Route formed on Esplanade. Use existing route and connect
back to Victoria Street at the Ferry Terminal
Length 646m
Description Widen the pinch points on the esplanade and provide improved
connection to Ferry Terminal junction
Key 
Challenges
• Avoid impact on sea defences
• Ramps and stairs will require realignment
• Limited corridor space at terminal end
• May not present as attractive alternative to Victoria Road (not
direct enough)
• Busy during summer peaks
• Coastal exposure
Key
Opport’ies
• Most direct route for tourists from ferry
• Car free route
• Lower capital costs
• No impact on bus, servicing or loading
• More pleasing environment
• Limited impact on existing drainage systems
• Limited impact on the front green area 
Option 2: Widen existing footpath into winter gardens. Route formed on
inland side of A844
Length 604m
Description Following Victoria Street, the route would be formed on the inland
side of the street. The road cross section would be maintained with
the whole road being shifted into the front gardens area by around
2m
Key 
Challenges
• Major impact on kerbs, drainage and services
• Increased risk of cycle / pedestrian conflict
• Higher capital cost
• Potential impact on Front Green
Key
Opport’ies
• Cycle route on busiest inland side nearest all key trip attractors
• Most direct route
• Avoid changes to front green
• Simpler interface with Ferry Terminal Junction  
Option 3: Widen footpath on inland side to suit width constraints. 
Maintain current road widths by widening onto coastal side of A844
Route
Length
604m
Description Following Victoria Street, the route would be formed on the coastal
side of the street. The road cross section would be maintained with
the improved active travel facilities extended into the front gardens
area
Key 
Challenges
• Major impact on kerbs, drainage and services
• Some impact on front green area

Page 32

30 | P a g e
www.connectedtp.com 
• Higher capital cost
Key
Opport’ies
• Cycle route near all key trip attractors
• Most direct route
• Simpler interface with Ferry Terminal Junction 
Option 4: Reallocation of road space to suit new widened footpath
on coastal side of A844
Length 604m
Description Following Victoria Street, the route would be formed on the
inland side of the street. The road cross section would be
adjusted to narrow the carriageway width to avoid impact 
Key 
Challenges
• Major impact on kerbs, drainage and services
• Some impact on front green area
• Higher capital cost
Key
Opport’ies
• Cycle route near all key trip attractors
• Most direct route
• Simpler interface with Ferry Terminal Junction 
Option 5: Reallocation of road space to suite new widened footpath
on inland side of A844
Length 604m
Description Following Victoria Street, the route would be formed on the
coastal side of the street. The road cross section would be
adjusted to narrow the carriageway width to avoid impact with
the gardens area by around 2m
Key 
Challenges
• Some impact on kerbs, drainage and services
• Higher capital cost
Key
Opport’ies
• Cycle route near all key trip attractors
• Most direct route
• Simpler interface with Ferry Terminal Junction

Page 33

31 | P a g e
www.connectedtp.com 
2.3 Ferry Terminal Junction to Albert Pier: Route Summary
Descriptions
Each of the route options are described in greater detail as follows.
Option A: Widen route and provide path on inland  
Length 245m
Description Route would be formed on inland side of A844 Victoria Road
Key 
Challenges
• Limited route corridor space will limit the extent of design
possible.
• Impact on taxi and bus rank
• Albert Pier Car park will be impacted
• Area is heavy parked
• Will impact on coach parking at Albert Pier
Key
Opport’ies
• Route coherence
• Most direct route option 
Option B: Widen route and provide path on coastal side 
Length 245m
Description Route would be formed on coastal side of A844 Victoria Road
Key 
Challenges
• Limited route corridor space will limit the extent of design
possible.
• Impact on taxi and bus rank
• Albert Pier Car park will be impacted
• Area is heavy parked
• Will impact on coach parking at Albert Pier
Key
Opport’ies
• Route coherence
• Most direct route option 
Option C: Shared use of West Princess Street then widen route and
provide a path on the inland side of the road.
Length 260m
Description Using West Princess Street at a mixed traffic street to avoid the
taxi and bus rank, the route would rejoin Victoria Street at Albert
Pier. The route would then be formed on the coastal side
Key 
Challenges
• Limited route corridor space will limit the extent of design
possible.
• Albert Pier Car park will be impacted
• Area is heavy parked
• Least direct option, may not be used
Key
Opport’ies
• Route coherence
• Avoid Impact on taxi and bus rank

Page 34

32 | P a g e
www.connectedtp.com 
2.4 Considering The Technical Challenges
Albert Pier Coach and Vehicle Parking
The Albert Pier car park has a marked capacity for 20 vehicles consisting of 17
cars and 3 coaches. Parking capacity is nearer 30 vehicles with cars and
campervans often parking along the waterfront footway.  The car park is
irregularly shaped limiting the options to reconfigure the space to increase
parking capacity.  A key feature of the facility is the provision of 3 coach sized
parking bays.  These are understood to be well used during the peak summer
months and should ideally be retained.
A derelict pier building currently occupies the site and is noted to be an eyesore.
Demolition of the building would contribute towards providing additional parking
capacity whilst the building itself could be reinvested as a public toilet or an active
travel community hub.
Taxi Rank
The taxi rank is located between the ferry terminal junction and the Bishop Street
roundabout.  The taxi rank is large supporting around 20 taxies (parked end in).
The taxi rank is well used but could be reduced in scale.  This would provide
some additional road space within this constrained location. 
It is unclear at the time of writing what the optimum capacity of the taxi rank
should be. It is also noted that currently taxies are parking end in. This requires a
reversing manoeuvre on the main road which is considered less safe and best
avoided. 
Bus Stance
The bus stance is located adjacent to the taxi rank in front of the harbour and
Guildford square. The stance can support a total of 4 coaches (2 per direction)
within the lay-bys provided. Access between the stops is supported by a zebra
crossing which ais also aligned with the pedestrian access to the inner harbour
and ferry terminal building
Ferry Junction
The ferry junction is a key node point in the network. The junction is an irregular
shape and partially signalised to support the egressing movements of ferry
vehicles. The junction does not support the movement of pedestrians, cyclists of
other non-motorised users.

Page 35

33 | P a g e
www.connectedtp.com 
Traffic Volumes 
It is noted to be very challenging to accurately predict any changes to traffic
volumes as a result of the concept being implemented.  This is primarily due to
the challenges in forecasting drivers route decision making within a complex
urban area which reflects the level of congestion and vehicle speeds at that time. 
Vehicle numbers are noted to be in excess of the 300 vehicles per day Cycle by
Design threshold with Victoria Street and Albert Pier catering for over 10% in
Heavy Goods Vehicles.  As a result, a facility segregated from the carriageway will
be required. As the route is within a 30mph area, the segregation strip may be a
narrow as 0.5m subject to agreement of technical standards.
Loading and Servicing
Currently, a loading and servicing along Victoria Road is catered for by frontage
access.  Service vehicles park where they can (sometime across bus stops) and
utilise pallet trucks to make deliveries through the businesses front doors.  It is
understood that many of the business have the ability to take delivery via the
rear but find frontage servicing agreeable. 
Road Safety
Feedback received through the stage 1 engagement combined with on-site design
team observation indicates that there are a number of road safety challenges that
could be addressed through the project design process. These include:
• Crossing of pedestrians on Victoria Street which often required
pedestrians to cross between parked cars. A lack of formal crossing
points limits the mobility of those less able. The most obvious points for
crossing support are the ferry terminal junction, at the Pavilion and
Victoria Street Frontage Loading

Page 36

34 | P a g e
www.connectedtp.com 
outside the Discovery Centre.  Higher vehicle speeds and lower level of
lighting during the darker winter months exacerbate this issue.
• Cycling along Victoria Street / Albert Pier is not comfortable for less
confident cyclists as they are required to cycle on the live carriageway
between parked cars and moving vehicles.
• High Street / Ferry Terminal junction is unwelcoming to pedestrians and
cyclists with no pedestrian crossing provision and wider crossing
distances increasing crossing risk.
• Cyclist / pedestrian conflicts along the esplanade could be addressed
through segregation of the user groups.
• Pedestrian routes to the ferry terminal junction are not well sign posted
for visitors.
• There is no cohesive cycle network to support access south along High
Street towards the joint campus.
Street Trial 
The idea of a street trial to test concept 1 was raised during the public
engagement event.  Street trials are normally reserved for Category 4 (or bigger)
PfE funded projects where the scale of the project would justify the additional
costs of appraising the concept.  Notwithstanding, Rothesay is a small scheme
with a likely small cost associated with producing a Temporary Traffic Regulatory
Order (TTRO) and temporary surfacing works required to test the concept. The
preparation of the temporary order will however take time requiring public
notification and collaboration with Argyll & Bute Council.  
Following discussions with the study steering group, it has been agreed that a
street trial is not a practical option to test as the extent of temporary works
required to safely implement the concept would be excessive and ultimately
unmanageable.
Maintaining The Design
A key challenge to all placemaking design options relates to the development of a
robust maintainable design. Often the choice of materials that meet the
maintainability criteria will be restrictive as the Argyll & Bute Council will need to
maintain a store of the materials to support future repair works.
A number of services are noted to be present along Victoria Street.  Evidence
recorded on site indicates that ongoing repair and replacement works by utility
service providers will continually disturb any new design.
It is unlikely to be possible to relocate the services as part of the design process
due to the likely disproportionate costs.  Alternatively, the design and material
selection should take cognisance of the need to access services and be provided
to improve the quality of any repair works.
The choice of design materials will require careful consideration as part of the
next stages of the project and will be discussed in greater detail in the next
chapter of this report.

Page 37

35 | P a g e
www.connectedtp.com 
Preliminary Flood Risk Assessment 
The site has been reviewed for potential sources of flooding following ABC
Supplementary Guidance on Flood Risk. These are outlined below along with a
qualitative assessment of the risk they pose to the route. 
• Fluvial Flooding: The SEPA Indicative Flood Map shows that the
location of the site is not within the area of fluvial flood risk. 
• Pluvial flooding: The SEPA Indicative Flood Map shows that the location
of the site is not within the area of high pluvial flood risk. 
• Coastal Flooding: The SEPA Indicative Flood Map shows that the
location of the site is not within the area of high coastal flood risk.
To summarise, the site is not considered at risk of flooding and no further
investigation is deemed necessary.
Community Feedback
Reference is drawn to the results of the community and stakeholder feedback
reported within the Community Feedback Report.  A summary of the community’s
feedback is summarised as follows:
Concerns relating to the use of the existing road route
• Parking is a premium within the town. Many of the town’s frontage
buildings do not have alternative parking locations.  Parking stresses
increase with the influx of summer tourists
• Parking at the Albert Pier end of town is particularly challenged. Camper
vans, tour buses / coaches are understood to park on and along the
footways.
• The town roads are well trafficked by a number of HGVs (14%). These
are often larger tractors or lorries.
• The ferry terminal area is considered unsightly. There is opportunity to
improve connection.
• The front green should be protected.
• The ferry terminal / High Street junction is noted to limit access by some
user groups. The junction does not include a provision for the mobility
impaired and is difficult to navigate.
• There is a lack of crossing opportunities along Victoria Street to support
the movement of pedestrians and cyclists.
• Improve cycle walking connectivity between the ferry terminal and the
Esplanade and between the Esplanade and Albert Pier.
Aspirations for the future design
• Victoria Street could be improved to include a central boulevard including
palm trees. This would improve crossing potential and reduce
carriageway width.

Page 38

36 | P a g e
www.connectedtp.com 
2.5 Initial Options Sift Workshop
The design team met to discuss the feedback of stage 1 consultation and
investigate the route options being considered.
Victoria Street
The options were debated during a design team workshop.  It was noted that
option 1, the esplanade was strongly preferred by the small community sample
with the primary justification being to avoid any negative impact on Victoria
Street parking. The route would however require alterations to the sea defences
in a number of locations including the installation of a sea defence gate.  These
changes were not acceptable to ABC due to risk of reducing effectiveness of flood
defences and would require further investigation.  Notwithstanding, option 1,
when compared with the option Victoria Street options, would also be a less
direct route for those wishing to pass along Victoria Street with the route being
further disconnected from local everyday High Street services.
It was also noted that the widening of the route (options 2 and 3) into the front
green offered similar benefits to options 4 and 5 but would add significant
additional cost to the project. It was therefore concluded that these options
should only be considered if options 4 and 5 that used the existing road space
could not be realised.
Using the street width measured from OS mapping in combination with the
options cross sections and feedback received, it was concluded during the
workshop that options 4 and 5 can be accommodated within the existing 
road space, maintaining on-street parking.  Further investigation of these two
options highlights that the option four with the route formed on the coastal side
would be the most deliverable option.  
Option 5 was felt to also reflect the most direct and coherent of the route options
retaining cycle and walking activity on the businesses and residential side of the
street and avoiding the need for promoting additional crossing movements.

Page 39

37 | P a g e
www.connectedtp.com 
Albert Pier
Options A, B and C were considered further with option C – using Princess Street
discounted on the basis that the route is too convoluted to be utilised. The taxi
rank design was investigated further and it was noted that should this facility be
rescaled and reorganised, the route could be accommodated along Albert Pier to
the Albert Pier car park with no adverse impact on parking.
It was noted that Albert Pier car park has a capacity of c.20 vehicles with a
typical parking demand for 30 vehicles, even during the off-peak February survey.
It has been concluded that all the design options would have an impact on the
car park and / or on-street parking capacity. Consideration should therefore be
given to either truncating the route option at the Ferry Terminal junction or
seeking to identify alternative parking mitigation options to offset the parking
impacts from both this project and the Joint Campus to Ferry Terminal. 
The route design standard was subjected to review using Transport Scotland’s
Cycling by Design 2021 guidance.  Noting the results of the vehicle traffic/speeds,
the number of potential NMUs.
Stakeholder Feedback
Reference is drawn to the results of the community and stakeholder feedback
reported within the Community Feedback Report.   
2.6 Route Appraisal Against Cycling by Design (CbD) 2021 
The route corridor was subjected to a review using the Sustrans route
assessment criteria in combination with Cycling by Design 2021.  The concepts
were scored ranging between 1 – 3 with 1 reflecting a ‘high level’ of service and 3
a ‘low level’ of service. The assessment was undertaken by the design team as a
workshop discussion to allow each route option and assessment criterion to be
discussed and scored.
The criteria considered in the assessment included:
• Indicative Cost;
• Deliverability;
• Accessibility;
• Local Need;
• Coherence;
• Directness;
• Comfort;
• Attractiveness; and
• Adaptability.
The resulting assessment identified that a number of the concepts, unsurprisingly
would need further investigation to determine an appropriate standard of design
provision.  
No consideration of the relative weighting of the evaluation criteria has been
undertaken.

Page 40

38 | P a g e
www.connectedtp.com 
Route /
Option
Length
(m)
Proposed Intervention
Structures
Required /
Altered 
1 High level of Service 10-14
2 Medium level of Service 15-23
3 Low level of Service 24-30
Costs
Deliverability
Accessibility
Local Need
Safety
Cohesiveness
Directness
Com
fort
Attractiveness
Adaptability
Total
Option 1  646 Route formed on Esplanade. Use existing route and
connect back to Victoria Street 
yes 2 1 2 2 1 2 2 1 2 2 17
Option 2 604 Widen existing footpath into winter gardens. Route
formed on inland side
no 3 3 1 1 2 1 1 2 1 1 16
Option 3  604 Widen footpath on inland side to suit width constraints. 
Maintain current road widths by widening onto coastal
side
no
3 3 1 1 2 1 1 2 1 1 16
Option 4  604 Reallocation of road space to suit new widened footpath
on coastal side
no 2 2 1 1 2 1 1 2 1 1 14
Option 5 604 Reallocation of road space to suite new widened
footpath on inland side
no 1 1 1 1 2 1 1 2 1 1 12
Option A 245 Widen route and provide path on inland side keeping
road as it is.  
no 2 2 1 1 2 1 1 2 1 1 14
Option B 245 Widen route and provide path on coastal side keeping
road as it is.  
no 2 2 1 1 2 1 1 2 1 1 14
Option C 260 Shared use of West Princess Street then widen route
and provide a path on the inland side.
no 1 1 3 1 2 3 3 2 2 1 19

Page 41

39 | P a g e
www.connectedtp.com 
2.7 Recommended Stage 1 Outcomes
• Option 1 should be progressed subject to detailed conversations with ABC
stakeholders regarding sea defence changes and scope of connection
through to CalMac terminal. 
• Options 5 should be developed to concept stage 2 with route provided on
coastal preferred as smaller works and cheaper, space available, coherent
and consistent with Albert Pier
• Option B Coastal for Albert Pier should be progressed to stage 2 concept
design
• Recommend redesign of Albert Pier as parking demand at this location is
will negatively ‘over shadow’ the other merits delivered by the project.
Alternatives are to explore community car park near albert pier.  This
may provide joint benefit to offset parking impacts associated with the
Ferry to Joint Campus route.
2.8 Considering Those with Protected Characteristics
An appraisal of the project has been undertaken using a Social and Equality
Impact Appraisal template (SEQiA). The results of the assessment are included in
Appendix B.
Taking cognisance of the appraisals summarised previously it is noted that all
concepts would be provided to achieve a Cycle by Design ‘High standard’ of 
10 Subject to reducing total traffic flow
provision10.  Once a preferred route alignment has been determined the design
should consider best practices to maximise the route accessibility for all user
groups and abilities.

Page 42

40 | P a g e
www.connectedtp.com 
NEW CHAPTER  
DEVELOPING THE CONCEPT

Page 43

41 | P a g e
www.connectedtp.com 
3 DEVELOPING THE CONCEPT
3.1 Developing the Options
Following approval of progress by Argyll and Bute Council Officers, Option four,
‘Reallocation of road space to suite new widened footpath on coastal side’ has
been selected for further development. 
3.2 Designing with Nature
A key consideration of the design process is to avoid an impact on flora and
fauna.  A Preliminary Ecological Appraisal (PEA) was commissioned in support of
the options development process. The assessment identifies and reports on a
limited number of ecological points of note within the study route. The ecological
constraints plan was overlaid on the concept option plan to check that the
concept does not impact on any ecological matters.
The check confirmed that the concept is not likely to have any impact.  Further
validation should be undertaken at stage 3, detailed design.
3.3 Developing the Design
The concept was subject to continual development to address the challenges
noted. These included:
• Redesigning Albert Pier Car Park layout to maximise parking capacity by
reducing circulation space and removing the derelict kiosk building.
• Improve parking capacity of the off-street parking area opposite Albert
Pier by standardising the parking layout and adopting a herringbone
layout.
• Improve coach parking by avoiding reversing and manoeuvring space
promoting a drive in and drive out layout.
• Address existing pavement parking by separating the pavement from the
parking area by including the coach parking in between. This layout is
anticipated to reduce pavement parking along Albert Pier.
• Formalise on-street parking by introducing marked bays.  These will
assist in maximising parking capacity by supporting drivers to park within
the spaces provided.
• Reduce the overall operational carriageway width to 6.5m.  This will allow
improved crossing opportunities for pedestrians.
• Increased the number of pedestrian crossing points along the route. The
crossing points are located where the community expressed a need for
improved crossing. 
• Redesigned the CalMac entrance to reduce carriageway space whilst
retaining the same vehicle stacking capacity for the ferry.
3.4 Maintaining the Concept
A key challenge of any design is ensuring the robustness and minimising future
maintenance requirements of any network changes.  To support this, a series of

Page 44

42 | P a g e
www.connectedtp.com 
workshops were held with Argyll and Bute Network Management Representatives
in advance of developing the final concept design.  In advance of each workshop
a concept option plan was shared to support discussion.  The key points of each
workshop are summarised in the remainder of this chapter.
Argyll and Bute Network Management (Workshop 2)
• Due to carriageway construction and drainage arrangements, developing
the route on the A844 route on coastal footway side was agreed to be
the preferred route option.
• The operational carriageway width must be maintained at a 6.5m
minimum to give extra space allowance for HGV and Buses.  It was
agreed that the road narrowing would improve pedestrian crossing
opportunities and help encourage appropriate vehicle speeds.
• Noting the potential impacts of the concept on the ferry vehicle access,
the Harbour Master and CalMac operator should be consulted to
understand better any operational impacts.
• Improvements to parking capacity along the route are supported. Any
changes should consider seasonal parking impacts and the demand for
coach and camper van parking where possible.
• Improved access options should explore the use of ramps and avoid the
suggested gate in the sea defence wall. This will improve connectivity for
cyclists and wheelchair users to access the winter gardens from the
CalMac terminal while not risking reducing the effectiveness of the sea
defences.
• The trees located along Victoria Road should ideally be retained as the
public may have concerns regarding removal.
• There is limited scope to revert the roundabouts on the A844 to Priority
T-junctions. The town operates as a one-way gyratory and noting the
industrial activity to the north, the roundabouts must be retained to
support industrial traffic access onto the A844 from Bishop Street.
• It was agreed that there is scope to repurpose road space to better
accommodate different user groups.  This should ideally avoid the need
for the design to be widened into the front green / gardens.
• Any redesign of Albert Pier car park to maximise car parking capacity is
desirable.
• Exploring the use of herringbone parking layout solution at parking area
opposite Albert Pier should be considered.  End-in parking is undesirable
and should be removed through the design process due to safety
concerns relating to vehicle manoeuvring. This will most obviously impact
on the existing taxi rank.
Based on the feedback received, the concept design was developed considering
the above noted points.  The emerging design was again subject to review by
ABC network management and maintenance representatives.

Page 45

43 | P a g e
www.connectedtp.com 
Argyll and Bute Network Management (Workshop 3)
A third stakeholder workshop was initiated to discuss the approach to review the
emerging concept. The following points were noted:
• Due to limited road space, a cycle buffer strip width of 0.5m is promoted.
• The accommodation of the design within the existing carriageway kerbing
is noted to significantly reduce drainage concerns and overall project
construction costs.
• The proposed ramp solution at the sea defence wall just behind the
Winter Gardens in lieu of steps will provide improved connectivity
between the Esplanade and the CalMac terminal.
• The introduction of a drainage system is an option that ABC would
support but would increase the overall capital cost of the project.
• Improved and formalised parking capacity was welcomed.  The
formalising of on-street parking is noted to be a benefit. The improved
parking capacity at Albert Pier was noted to be beneficial. 
• Parking impacts at Albert Pier should be subject to further conversations
with ABC Economic Development team to confirm ABC aspirations to
provide additional coach parking.
• The Scottish Water building within the Albert Pier car park must be
retained. The design should be revised to include this.
• There is limited scope to resize the existing roundabouts but changes can
be considered subject to vehicle tracking analysis to ensure access by
larger vehicles can be maintained.
3.5 Vehicle Tracking Analysis
The concept design was subject to a vehicle tracking analysis using vehicle
tracking simulation software.  The tracking was undertaken at the locations
where the design was estimated to impact on the operational layout and
included: 
• The entrance, exit and circulation of the parking at Albert Pier;
• Access, egress and access to parking bays in the parking area opposite
the Albert Pier car park;
• Access, queuing and exit of the CalMac ferry terminal junction; and
• The resized roundabouts along the route length.
Vehicle tracking results can be found below:

Page 46

44 | P a g e
www.connectedtp.com 
Albert Pier Coach and Car Tracking

Page 47

45 | P a g e
www.connectedtp.com 
Albert Pier Coach and Car Tracking

Page 48

46 | P a g e
www.connectedtp.com 
CalMac Junction HGV / Car Tracking

Page 49

47 | P a g e
www.connectedtp.com 
Bishop Street HGV Tracking

Page 50

48 | P a g e
www.connectedtp.com 
3.6 Considering the Ferry Junction Operation
It was a decision by the stakeholders that the ferry junction should be
consulted regarding the proposed changes. A meeting was set up with CalMac
ferry’s manager and the Harbour Master for Rothesay to review the emerging
concept. Key outcomes of the meeting included:
• General agreement regarding the operational layout changes to the CalMac
junction layout. Particularly that the layout might help queuing on access
back along Victoria Street.  This would reduce the requirement for occasional
marshal intervention and also improve the operation of the vehicle waiting
are for CalMac staff. 
• Consideration of options to improve visitor legibility of the queuing lanes and
intended operational management plan.
• Avoidance of the use of lines and signs due to longer term maintenance
challenges within a coastal location and the skewing movement of vehicle
tyres wearing road line markings.
3.7 Value Engineering Route Extent
As the design has been developed it was noted that the concept would offer
additional benefits from being extended from the current end point at Albert
Pier west towards Craigmore.  Following design team and client discussion, it
was agreed that the route should be extended to Glenburn Road where the
corridor width increases. This revised end point was agreed as this location
would afford more route options for future extension and therefore provided a
logical termination point for this project. 
3.8 Peak Season Parking Surveys
To better understand the parking demand within the study area and noting the
towns role as a key summer tourist destination, a second parking survey /
assessment was undertaken during June 2024. 
The surveys followed a similar scope to those undertaken during February 2024
to assist in comparison of the results. 
The June 2024 survey results are summarised as follows.

Page 51

49 | P a g e
www.connectedtp.com 
June 2024 Peak Parking Survey along A844 Victoria Street / Glenburn Road

Page 52

50 | P a g e
www.connectedtp.com 
Understanding Parking Impacts 
Using the June 2024 parking data, an assessment of forecast parking capacity
impacts has been estimated.  A minimum parking bay space of 6m in length
has been assumed to allow space for vehicle manoeuvring. 
For each section of the route as defined by the February parking survey
sections, an estimate of theoretical capacity of the current road layout has been
undertaken by calculating the length of available road space by section
available for legal parking and dividing this by the 6m bay length. The
calculation includes allowance to avoid parking across accesses and on existing
parking restrictions. 
The results of the comparisons for the on-street and off-street parking provision
is shown in the following tables.  The results indicate that as a result of the
concept design, the total number of parking bays has been increased by around
15 parking spaces.   
The majority of these additional spaces are located towards the Albert Pier end
of the route where the February parking surveys and stage 1 community
feedback have indicated parking stress  is at its greatest.
In general parking between the Pavilion and Albert Pier remains broadly
unchanged from the existing arrangement. 
On Street Parking
Route
Section Description Road
side
Existing
Parking
Bays
Proposed
Parking Bays Difference
A Pavilion
St Johns Place
South 19 20 1
North 0 7 7
B St Johns Place
Chapel hill Car Park
South 7 7 0
North 7 5 -2
C Chapel hill car park
Chapel hill Road
South 10 10 0
North 10 10 1
D Chapel hill Road
Gallowgate
South 5 3 -2
North 0 6 6
E Gallowgate
Tower Street
South 10 12 2
North 10 11 1
F Tower Street
High Street
South 8 7 -1
North 8 4 -4
G High Street
Bishop Street
South 5 10 6
North 0 0 0
H Bishop Street
Albert pier
South 13 13 0
North 0 0 0
I Albert Pier  South 8 8 0
North 0 0 0
J Bishop Terrace Brae
Commodore Guest House
South 38 0 0
North 0 0 0
K Commodore Guest House
Glenburn Road
South 40 0 0
North 0 0 0
Total 221 120 15

Page 53

51 | P a g e
www.connectedtp.com 
3.9 Coach, Taxi and Visitor Parking
The proposed concept includes three 17m long coach parking bays located
within Albert Pier which will replace the existing three coach bays currently
provided.  The coach parking will be accessed via a one-way in and one-way
out gyratory style operation.  This method of operation will ensure that no
coaches are required to reverse within the public road spaces whilst ensuring all
patrons are able to alight and disembark on the footway side away from the
road.
The proposed taxi layout will be redesigned to align vehicles parallel to road to
improve access for passengers and remove need to reverse off the main road.
This will reduce parking capacity to four allocated spaces.  Additional taxi
spaces may be  possible through reallocation of adjacent public parking spaces.
The bus-stops located along Victoria Road will remain in approximately the
same location. 
3.10 Route Safety Audit
The emerging concept design were submitted to Drummond Black Ltd who
undertook a Stage 1 Road Safety Audit in support of the design. 
Full details of the audit and designers’ response are supplied separately
3.11 Developing Route Cross Sections
The proposed concept design route cross-sections taken at various locations
across the scheme are shown in the following figure. 
Car Parks
Car Park  Existing Bays Proposed Bays Difference
Chapel hill 21 21 0
Albert Pier 28 31 -2
Bishop Street 16 17 1
Total 70 70 0

Page 54

52 | P a g e
www.connectedtp.com 
3.12 Forecast Construction Costs Estimates
An initial assessment of the capital cost of constructing each of the concept
option is set out in the following table.  
The estimates have been prepared by CTP using SPONS cost information and
relevant previous experience. The cost estimates should be treated as indicative
until complete estimates of construction costs are prepared during the stage 3
detailed design.
The option includes a 44% Optimism Bias reflecting the early concept design
stage.

Page 55

53 | P a g e
www.connectedtp.com 
3.13 Route Re-Appraisal Against Cycling by Design (CbD) 2021 
The route option was again subjected to a review using the Sustrans route
assessment criteria in combination with Cycling by Design 2021.  The concepts
were scored ranging between 1 – 3 with 1 reflecting a ‘high level’ of service and 3
a ‘low level’ of service. The assessment was undertaken by the design team as a
workshop discussion to allow assessment criterion to be discussed and scored.
The criteria considered in the assessment included:
• Indicative Cost;
• Deliverability;
• Accessibility;
• Local Need;
• Coherence;
• Directness;
• Comfort;
• Attractiveness; and
• Adaptability.
The resulting assessment identified that a number of the concepts, unsurprisingly
would need further investigation to determine an appropriate standard of design
provision.  
No consideration of the relative weighting of the evaluation criteria has been
undertaken.

Page 56

54 | P a g e
www.connectedtp.com 
Route /
Option
Length
(m)
Proposed Intervention
Structures
Required /
Altered 
1 High level of Service 10-14
2 Medium level of Service 15-23
3 Low level of Service 24-30
Costs
Deliverability
Accessibility
Local Need
Safety
Cohesiveness
Directness
Com
fort
Attractiveness
Adaptability
Total
Option 5 604 Reallocation of road space to suite new widened
footpath on inland side
no 1 1 1 1 2 1 1 2 1 1 12
Option B 245 Widen route and provide path on coastal side keeping
road as it is.  
no 2 2 1 1 2 1 1 2 1 1 14

Page 57

55 | P a g e
www.connectedtp.com 
3.14 Considering Those with Protected Characteristics
An appraisal of the project has again been undertaken using ABC Social and
Equality Impact Appraisal template (SEQiA). The results of the assessment are
included in Appendix B.
Taking cognisance of the appraisals summarised previously it is noted that both
options would be provided to achieve a Cycle by Design ‘Medium standard’ of
provision.  
3.15 Considering Construction Phasing
Due to the overall route length and complexity of island delivery, it is highly
unlikely that the identified route corridor will be constructed as a single delivery
project.  It is more likely that the route will be delivered in a staged order as
funding becomes available.
Taking cognisance of the known challenges at this stage of the network
development, the following construction order is suggested. 
3.16 Recommendations and Next Steps
Following consideration of the material provided within this assessment, it is
recommended that the concept route is promoted and developed further during
the stage 3 design process.
The developed version will both reduce the unknown risks in the construction
costs and improve deliverability but will also align with key stakeholders’
requirements.
The design builds on the feedback provide by the community to focus less on
cycle provision, improve more opportunities to cross the road, improve parking
and address provision for overnight parking, coach and campervan parking.  The
concept improves connectivity between the Esplanade and the CalMac terminal
and promotes a direct route that benefits pedestrian and cyclists through the
town. 
Ref Route Section Route
Length(km)
Phase 1 Option 5 - Esplanade to Ferry Junction 0.58
Phase 2 Option B - Ferry Junction including Albert
Pier
0.25
Phase 3 Option B - Albert Pier to Route end 0.62

Page 58

56 | P a g e
www.connectedtp.com  DESIGN PROCESS QUALITY AND INNOVATION

Page 59

57 | P a g e
www.connectedtp.com 
4 DESIGN PROCESS QUALITY AND
INNOVATION
4.1 Outline Design Process
The project will be developed to align with the Places for Everyone (PfE) design
development programme.
4.2 Design Guidance and Quality
A wide range of design guidance and standards have been used to develop the
project proposals.  The core documents include: 
• Designing Streets;
• Cycling by Design (2021);
• The National Roads Development Guide (NRDG); and
• Inclusive Mobility (2021).
The detailed design process will use these standards and include:
• Design Manual for Roads and Bridges (DMRB);
• Traffic Signs and Regulations and General Directions (TSRDG);
• Local Transport Notes (LTN); and
• Traffic Advisory Leaflets (TAL).
These references represent the core design guidance however other documents
such as Sustrans Design Guidance Documents and other examples of best
practice have also been considered.

Page 60

58 | P a g e
www.connectedtp.com 
4.3 Considering Wider Area Improvements
The concept design process will include several key considerations in support of
the emerging network. These include:
• Improvement to accessibility, walking and cycling links between people
and place;
• Developing a signage and wayfinding strategy;
• Promoting a cycle-welcoming intervention;
• Introducing a Travel behaviour change programme; and
• Providing cycle parking and storage measures.
4.4 Considering Streetscape and Landscape Improvements
The route on its own will not create the maximum opportunity to support the
movement of people, create a place and encourage community ownership. 
Rothesay is a key service centre for the regional community which relies heavily
on the use of motorised travel to support the movement of the community.  
To support lasting change to travel behaviours the design process must include
placemaking potential giving priority to maximising the communities’ assets and
access to public transport as well as the opportunity to walk and cycle while
retaining car-based access. 
4.5 Planting, Drainage and Local Environment
Within the proximity of any areas where there would be works such as seating,
way finders, and shared surfaces, planting of native species will enhance the
environmental improvements.  
Not only will planting create an attractive setting but it will also be encouraging
and increasing biodiversity. Salt-tolerant species can be used for foraging and can
be educational.  The changing seasons are marked with the advent of spring with
blossom flowers followed by autumn leaf colour changes.

Page 61

59 | P a g e
www.connectedtp.com 
4.6 Developing Streetscape
Sensitively designed rural street furniture and public art can be incorporated as
part of the concept design process and is aimed at enriching the experience of
everyday journeys and visits to the area.  
Whilst keeping in mind the coastal environment; seating, opportunities for
incidental play, and way-finders would be appropriate.
As a rural area with period style street lighting, the lighting design must be
provided very sensitively. Lighting can become a design feature in its own right,
by marking at ground level or by enhancing seating areas by incorporating
lighting into the structures. 
Paving materials will avoid any garish colours and patterns which would be more
associated with an urban area; again, as they are not in keeping with the style of
the road. The linear nature of the site naturally establishes a physical connection
through the site which can be punctuated with environmental improvements such
as seating areas and viewpoints. 
Examples of bike stands combined with seating
Examples of Bike Stands

Page 62

60 | P a g e
www.connectedtp.com 
Example of Seating and Planting
Example of Route Signage
Example of Paving

Page 63

61 | P a g e
www.connectedtp.com 
Examples of Rural Route Lighting Solutions

Page 64

62 | P a g e
www.connectedtp.com 
Designing for Equality and Accessibility
The proposed Active Travel network must support access by all user’ groups that
includes accessibility by all ages and abilities.  As the route corridor design
progresses, consideration must be given to ensuring that the network remains
safe and inviting to everyone.  This includes how those more vulnerable in our
society will be supported by the design.
The design is supported by a Social and Equalities Impact Assessment (SEQiA)
which is included in Appendix B.
4.7 Flood Prevention
With a changing climate, the importance of designing with flood risk in mind is
paramount.  The SEPA flood risk maps indicate that the route is not at risk of
1:200-year coastal flooding event.  A summary of the flood risk map is supplied
separately. 
4.8 Traffic Modelling
No traffic modelling is considered necessary at this stage of the concept
development. 
4.9 Preliminary Ecological Appraisal (PEA)
A Preliminary Ecological Appraisal has been undertaken for the existing route
corridor.  The PEA is supplied Separately.

Page 65

63 | P a g e
www.connectedtp.com  PROJECT DELIVERABILITY AND DESIGN COLLABORATION

Page 66

64 | P a g e
www.connectedtp.com 
5 PROJECT DELIVERABILITY AND DESIGN
COLLABORATION
5.1 Landownership
The project route is predominately located within Argyll & Bute Council owned or
adopted lands.  There are no sections of the route where third-party land
ownership is expected to be required. 
Additional frontage landowners may need to be consulted at the next stage of the
design development depending on the route standard developed.
5.2 Designer Risk Register
Similar to the Project Risk Register, the Designer Risk Register provides a
summary of the risks and risk management associated with the technical delivery
of the design.  The Designer Risk Register is supplied separately.
5.3 Project Budget Forecast
A whole-life project forecast has been provided (Supplied separately).

Page 67

65 | P a g e
www.connectedtp.com  APPENDICES

Page 68

66 | P a g e
www.connectedtp.com 
APPENDIX A – EXTENT OF APPROXIMATE COUNCIL OWNERSHIP

Page 69

67 | P a g e
www.connectedtp.com 
APPENDIX B – SOCIAL AND EQUALITY IMPACT ASSESSMENT (SEQIA)
Argyll and Bute Council: Equality and Socio-Economic Impact Assessment
Section 1: About the proposal  
Title of Proposal
Rothesay, Pavilion to Glenburn Road Walking and Cycling Improvement  
Description of Proposal
Stage 2 Concept design of a 1.45km Active Travel Route through Rothesay  
Purpose and Aims of Proposal
To provide safe walking and cycling route between Pavilion and Glenburn Road, local community services. To encourage everyday cycling and walking
as an alternative to private car use. To improve the islands travel and mobility options. To improve access for those less able.  
Intended outcome of proposal
Concept design for the route aligned with the funding requirements of the Scottish Government active travel programme.  Intervention to be
proportionate and affordable to the communities requirements and maintain the islands character whilst providing infrastructure improvement.  
Business Outcome(s) / Corporate Outcome(s) / National Policies to which the proposal contributes/relates
Aligned with National and local policy interventions regarding promotion of sustainable travel modes, reduction in single journey car dependency.
Design reflects use of Cycle By Design 2021 update.  
Lead officer details:

Page 70

68 | P a g e
www.connectedtp.com 
Name of lead officer Colin Young
Job title Strategic Transportation Delivery Officer
Service / Company ABC
Contact Details colin.young@argyll-bute.gov.uk  
Appropriate officer details: 
Name of appropriate officer Colin Young
Job title Strategic Transportation Delivery Officer
Service / Company ABC
Contact Details colin.young@argyll-bute.gov.uk  
Sign off of EqSEIA
Approver Signature  
Approver Name  
Approver Job title  
Date of sign off  
Revision Number 1  
Who will deliver the proposal?
ABC Strategic Transportation Team  
Individuals involved in developing the EqSEIA 
Name Colin Young
Job title Strategic Projects Officer
Service / Company ABC
Contact Details colin.young@argyll-bute.gov.uk
Name Mark Rinkus
Job title Managing Director

Page 71

69 | P a g e
www.connectedtp.com 
Service / Company Connected Transport Planning Ltd
Contact Details mark.rinkus@connectedtp.com
Name Jack Munro
Job title Engineer
Service / Company Narro Ltd
Contact Details jmunro@narroassociates.com 
Section 2: Evidence used in the course of carrying out EqSEIA     
Who does the proposal impact?
Will impact on everyone as it is a community asset and part of core infrastructure.  Key receptors include local frontage property owners, local residents
and visitors to the community     
Are there any aspects which explicitly address discrimination, victimisation or harassment?
No.  The project is a supporting element of infrastructure that will connect people with place.     
Are there any aspects which explicitly promote equal opportunities?
No.  Through good design aligned with current guidance and design standards, the project will be designed to support access by all user groups and
abilities.  Through appropriate design, the project will promote a safe environment for all user groups seeking to support the movement of people     
Are there any aspects which explicitly foster good relations?
Potential concerns regarding project location and route and the negative impact of unwanted construction and parking impacts     
Are there any aspects which explicitly promote socio-economic equality?

Page 72

70 | P a g e
www.connectedtp.com 
No.  The project will contribute towards socio economic growth through better provision of a safer route between people and place     
Consultation / engagement undertaken
Consultation Details Date(s) Summary of Findings
Online via Facebook study page and community pages Various. See
Consultation Report Support for the project
Community visit x4 Various. See
Consultation Report Support for the project
Public Consultation x2 in including digital dial in workshop Various. See
Consultation Report
Support for the project. Some
landownership concerns
Local Community Primary School x1 Various. See
Consultation Report
Support for the project. 
Include colourful infrastructure
Local Community High School x1 Various. See
Consultation Report
Support.  No interest in play
equipment  
LGBTQIA+ Pride community Various. See
Consultation Report Support for the project
Community Social Services x1 Various. See
Consultation Report
Support. Concerned relating to
speeding cyclists and cycle
priority scheme
General interactions with the community x10 Various. See
Consultation Report
Supportive. Concerns raised
relating to off-road routes
around rear of Rothesay
Regular steering group sessions Various. See
Consultation Report
Helped guide engagement with
the community     
Have people who identify with any protected characteristic(s) been involved in the development of the proposal?
Yes. Individuals would self-identified as having protected characteristics of age, sexual orientation, race and disability have engaged in the project     
Data Sources

Page 73

71 | P a g e
www.connectedtp.com 
Census 2011 and 2022, 2019 previous engagement outputs, project traffic data (2023 off and on peak), community feedback     
Other information
Various design standards but primarily Cycle by Design 2021 update.     
What is known currently about the experience of people under each characteristic?
Protected characteristic What is currently known Source(s) Gaps in Evidence
Age
Including the experiences of young people
(age 18 and under) and older people.
Young adults live in the community and use a bus or
parent transport to get around.  Older populations
have expressed concerns regarding cycle priority
vs.. pedestrian priority.  Kerbs, poor visibility,
changes in surface delineation are challenges to
mobility.  Ensuring older people do not need to step
into the cycle route and have sufficient time to hear
an oncoming cyclists. Particularly relevant for those
trying to cross the concept at points beyond the
allocated pedestrian crossings.
Meetings and
feedback with primary,
secondary schools. 
The general public
and through previous
project experience
such as conversations
with the RNIB.
none
Disability
Physical and mental. Including the
experiences of people with long term
limiting health conditions.
Older mobility challenged residents live in the
community.  They use mobility aids to get around. 
Changes in surface levels such as kerbing can limit
some people’s ability to physically move their bike. 
Those with hearing impairment have expressed
concerns regarding ability to hear and see oncoming
traffic or cyclists and have sufficient time to take
action
Face to face meeting
with residents in the
community and survey
feedback from the
public.  Previous
experience from other
projects. none
Ethnicity
Including impact relating to skin colour,
nationality, language spoken and country
of origin. People identifying as Gypsy /
Travellers are protected by this
characteristic.
Some users from some ethnic groups have a view
that they may be more  vulnerable to assault or
verbal abuse as members of particular ethnic
groups.  Safety concerns relate to the creation of
unsupervised spaces and places that might support
Online data search. 
Points shared through
design team
conversation
No empirical evidence to
support what might be a
generalised viewpoint. 
Feedback reflects subjective
view of some individuals and

Page 74

72 | P a g e
www.connectedtp.com 
intimidating behaviour by some individuals. 
Promotion of natural surveillance and appropriate
lighting is important to inclusive / welcoming design.
Challenges also relate to signage and language
barriers. 
may not reflect the group
overall.  Not all ethnic groups
surveyed or view points have
been recorded so there is a
high risk of generalisation.
Sex
Some user groups feel they are unsafe passing
through or along spaces which is less well lit. 
Appropriate levels of  lighting and natural
surveillance can help address these perceptions.
Online data search. 
Points shared through
design team
conversation.
No evidence to support what is
likely to be a personal view
held by the individual.  No
safety concerns relating to sex
have been received via the
community survey.
Gender reassignment
Where someone is living part / full time as
the opposite gender to their assigned sex
at birth.
Some user groups suffering from gender dysphoria
may feel they are unsafe or more vulnerable to
attack when passing through or along spaces which
are less well lit.  Appropriate levels of  lighting and
natural surveillance can help address these
perceptions.
Online data search. 
Points shared through
design team
conversation.
No evidence to support what is
likely to be a personal view
held by the individual.  No
safety concerns relating to
gender have been received via
the community survey.
Marriage and Civil Partnership
Some male or females living together out with
marriage or in a civil partnership may feel less
secure  or victimised by other people using the travel
route. This perception of risk may be the result of
religious belief.
No data available.
No evidence to support what is
likely to be a personal view
held by the individual.  No
safety concerns relating to
marital status have been
received via the community
survey.
Pregnancy and Maternity
This covers women as soon as they
become pregnant. In the workplace this
includes pregnancy-related illness. When
a woman gives birth or is breastfeeding,
this characteristic protects them for 26
weeks.
Parents in the community do walk the project route
but numbers are low are proportionately lower.  Use
of private car is preferred for ease and convenience
noting the  space between places, weather and
concerns have been raised regarding shared use of
the road and safety challenges of maintaining
access for those reliant upon car use.
Face to face meeting
with residents in the
community and survey
feedback.
Few participating parents to
provide comment by anecdotal
evidence provided from wider
island community

Page 75

73 | P a g e
www.connectedtp.com 
Religion / Belief
Including the experiences of people with
no religion or belief.
Some user groups have a view that they may be
more  vulnerable to assault or verbal abuse as
members of particular religious groups.  Safety
concerns relate to the creation of unsupervised
spaces and places where would anti-social activity
might take place.  Promotion of natural surveillance
and appropriate lighting is important to inclusive
design. There are multiple churches on the island
supports some religious groups and can be
accessed via the road.
Online data search. 
Points shared through
design team
conversation
No empirical evidence to
support what might be a
generalised viewpoint. 
Feedback reflects subjective
view of some individuals and
may not reflect the group
overall.  Not all religious
groups surveyed or view points
have been recorded so there is
a high risk of generalisation.
Sexual Orientation
Some people can feel they are unsafe passing
through or along spaces which they believe they
have less than appropriate lighting and natural
surveillance.  In these situations their perception of
risk due to verbal or physical assault is elevated. 
The inclusion of spaces with limited natural
surveillance can also present opportunities to
individuals with protected characteristics.
Online data search. 
Points shared through
design team
conversation.
No evidence to support what is
likely to be a personal view
held by the individual.  No
safety concerns relating to
sexual orientation have been
received via the community
survey.
Other marginalised groups
Including but not exclusive to the
experiences of unpaid carers, homeless
people, current and ex-offenders, people
with addictions, care experienced people,
people living in rural areas.
Some people from some marginalised groups have a
view that they may be more  vulnerable to assault or
verbal abuse as members of particular marginalised
groups.  Safety concerns relate to the creation of
unsupervised spaces and places where anti-social
behaviour might occur.  Promotion of natural
surveillance and appropriate lighting is important to
inclusive design. As a rural community the distance
and acceptance of the challenge of access to
everyday services is considerably greater than that
on the mainland. 
Online data search. 
Points shared through
design team
conversation
No empirical evidence to
support what might be a
generalised viewpoint. 
Feedback reflects subjective
view of some individuals and
may not reflect the group
overall.  Not all marginalised
groups surveyed or view points
have been recorded so there is
a high risk of generalisation.
Cross Cutting
Where two or more characteristics overlap
and the proposal affects those people in a
specific way
The project will support access to improved walking
and cycling travel.  The promotion of walking is at
odds with the needs of cyclists and vice versa. 
Some user groups are at 'odds' with the needs of
local drivers who wish to access places quickly. 
Conversations and
Community feedback.
Conversations and Community
feedback.

Page 76

74 | P a g e
www.connectedtp.com 
These needs are in turn at 'odds' with the actions of
tourists  arriving on the island by private car.   
What is currently known Source(s) Gaps in Evidence
Mainland rural population
The island co-exists through a dependency with the
mainland through the passenger ferry service. 
Access to Rothesay is via car, ferry and bus service
provides support.  The equality challenges are
typical to those associated with rural island living.
Community
conversations. 
Census and
Placemaking tool
results. No gaps identified.
Island populations
The community consists of many people who live
throughout the area, have many different aspects of
travel with no difficulty.
Community
conversations. 
Census and
Placemaking tool
results No gaps identified
Low income
There is no single definition or measure of
low income. Some indicators suggest that
low income is where individuals living in
households receive below 60% of UK
median income. Scottish Government’s
Children in Families With Limited
Resources Across Scotland 2014-2016
defines low income as ‘household income
below 70% of the Scottish median after
housing cost’.
Access to travel is not a challenge for Rothesay. The
movement of goods and services are often at a
higher comparable cost to the mainland.  This cost
disparity can exacerbate difference in wealth, health
and welfare.
Online research.
Published research
no gaps identified
Low wealth
Not having access to wealth (including for
example, financial products, equity from
housing, decent pension, accessible
saving). People who have low wealth lack
protection from socio-economic
disadvantage.
Access to travel is not a challenge for the
community.  The movement of goods and services is
often at a higher comparable cost to the mainland. 
This cost disparity can exacerbate difference in
wealth, health and welfare.
Online research.
Published research.
No gaps identified.

Page 77

75 | P a g e
www.connectedtp.com 
Material deprivation
Inability to access basic goods and
services.
Access to travel is a challenge for rural communities
and remote communities.  The movement of goods
and services is often at a higher comparable cost to
the mainland.  This cost disparity can exacerbate
difference in wealth, health and welfare.
Census and place
standard tool feedback
None
Area deprivation
Areas where there are concentrations of
deprived households.
Access to travel is not a challenge for area
deprivation as many residents own cars and drive
quite often, some areas also have bus stops which
can pass in and out of Rothesay.
Online research.
Published research
no gaps identified
Socio-economic background
Relates to the context in which a person
has been raised or in which they live.
Disadvantage may arise from parents’
education, employment and income
(social class).
Access to travel is a challenge for rural communities
and remote communities.  The movement of goods
and services is often at a great comparable cost to
the mainland.  This cost disparity can exacerbate
difference in wealth, health and welfare.
Online research.
Published research.
No gaps identified.
Communities of place
Refers to people who are bound together
because of where they live, work, visit, or
otherwise spend a continuous portion of
their time. This may include rural, remote
and island areas.
Challenges associated with community living
including higher car dependency and cost of living
Census and place
standard tool
feedback.
None. 
Section 3: Impact of proposal         
Impact on service users
Protected
characteristic Negative No Impact Positive   Don’t Know
Action
required
for impact
be known  
Details
(incl. action taken to
minimise negative and/or
maximise positive impact)
Age
Including the
experiences of
young people (age   
Any proposal
will have
some
positive and
Consider
user group
design
separation  
Many of the communities
younger generation are
independently mobile.  The
travel distances in the

Page 78

76 | P a g e
www.connectedtp.com 
18 and under) and
older people.
negative
challenges
to people of
different
ages and
abilities. 
Overall, the
proposal
wont
prioritise one
age group
over another
if space
allows
community between places
mean travel by car is the only
practical option even though
many of the children show a
willingness to walk and cycle
and do walk and cycle regular.
Personal safety is not currently
a community concern with
some of the younger adults
often cycling and walking
during the hours of darkness. 
The more mature generation
has expressed concerns
relating to accessibility
challenges, noting the limited
road width and loss of access
through changes to parking. 
Steep gradients should be best
minimised or avoided.  Cycle
speeds can be intimidating
(particularly e-bikes) to some
older people and measures to
clarify the priority of the route to
pedestrians and provide cycle
speed control measures cannot
yet be effectively managed.
The concept will seek to
minimise road crossings by
keeping the route on the same
side of the carriageway as
much as reasonably
practicable.    The design
includes additional benches as
requested by the community to

Page 79

77 | P a g e
www.connectedtp.com 
provide more frequent rest
opportunities for the less able-
bodied noting the overall length
of the route is around 1.45km.
The design does include for
user segregation meaning that
multiple user groups which will
address some of these
challenges but will create other
challenges for crossing the
route beyond the allocated
crossing points.  No additional
play areas are promoted as the
community did not identify them
as preference.  Lighting is
provided via existing street
lighting.
Disability
Including the
experiences of
people with long
term limiting health
conditions.        
Any proposal
will have
some
positive and
negative
challenges
to people of
different
abilities. 
Overall, the
proposal will
be a net
improvement 
overall as it
provides
infrastructure
where there
Consider
user group
design
separation.
Install
measures
to manage
cyclist
speeds.  
We have considered
accessibility by those less able,
noting the design is a shared
use path which supports
segregation of user groups. By
using the existing road route we
have avoided steep or lengthy
inclines and declines which
keeps the route accessible by
the mobility impaired. We have
ensured pedestrian priority in
the project as far as possible
with the route changes seeking
to provide a more coherent and
continual route.  This is
achieved by removing

Page 80

78 | P a g e
www.connectedtp.com 
is currently 
none
vegetation and improving
sightlines.    
Ethnicity
Including impact
relating to skin
colour, nationality,
language spoken
and country of origin.
People identifying as
Gypsy / Travellers
are protected by this
characteristic.  
The route concept includes
good practice design to
minimise people accessing
dark or unwelcoming spaces
that might discourage use
by some user groups. 
However, the island is a
remote community and
much of the route does not
benefit from natural
surveillance          
The ethnicity of the population
in the community is Scottish /
white.  The spoken language is
English and Gaelic.  Route
signage will be provided  bi-
lingual. The route is being
designed to support access by
all races and we are unaware
of any design features that
would influence users within
this category.  There are no
published details of  path
design considerations relevant
to race that are not equally as
relevant to other user group
criterion.
Sex  
The route concept includes
good practice design to
minimise people accessing
dark or unwelcoming spaces
that might discourage use
by some user groups. 
However, the island is a
remote community and
much of the route does not
benefit from natural
surveillance          
The concept design supports
mobility by all user groups.  The
route design is promoted to
support mobility by a
unaccompanied 12 year old. 
We are not aware of any design
criterion relevant to path design
that is unique to this category.

Page 81

79 | P a g e
www.connectedtp.com 
Gender
reassignment
Where someone is
living part / full time
as the opposite
gender to their
assigned sex at birth.  
The route concept includes
good practice design to
minimise people accessing
dark or unwelcoming spaces
that might discourage use
by some user groups. 
However, the island is a
remote community and
much of the route does not
benefit from natural
surveillance          
The concept design supports
mobility by all user groups.  The
route design is promoted to
support mobility by a
unaccompanied 12 year old. 
We are not aware of any design
criterion relevant to path design
that is unique to this category. 
We also note participation of
two individuals within the
community feedback who suffer
from gender dysphoria and
inclusion of Bute Pride within
the concept design
consultation.
Marriage and Civil
Partnership       
Not
measurable.      
Pregnancy and
Maternity
This covers women
as soon as they
become pregnant. In
the workplace this
includes pregnancy-
related illness. When
a woman gives birth
or is breastfeeding,
this characteristic
protects them for 26
weeks.    
The
separation of
user groups to
provide level-
priority
walking route
that is not
shared with
vehicles will
improve the
projects
attractiveness.        
The concept design supports
mobility by all user groups.  The
route design is promoted to
support mobility by a
unaccompanied 12 year old.

Page 82

80 | P a g e
www.connectedtp.com 
Religion / Belief
Including the
experiences of
people with no
religion or belief.  
The intervention will include
good practice design to
minimise provision of dark or
unwelcoming spaces that
might discourage use by
some user groups. 
However, the area is a
remote community and
much of the project does not
benefit from natural
surveillance          
The concept design supports
mobility by all user groups.  The
route design is promoted to
support mobility by a
unaccompanied 12 year old.  
The route will continue to be
available to persons of any
religion or belief. The location
of the route nearer the coast
may appeal to some individuals
with a religious belief rooted in
nature.
Sexual Orientation                
Other marginalised
groups
Including but not
exclusive to the
experiences of
unpaid carers,
homeless people,
current and ex-
offenders, people
with addictions, care
experienced people,
people living in rural
areas.  
The intervention will include
good practice design to 
minimise provision of dark or
unwelcoming spaces that
might discourage use by
some user groups. 
However, the area is a
remote community and
much of the project does not
benefit from natural
surveillance          
The concept design supports
mobility by all user groups.  The
route design is promoted to
support mobility by a
unaccompanied 12 year old.   
Cross Cutting
Where two or more
characteristics
overlap and the
proposal affects
those people in a
specific way  
Conflicts between cyclists,
pedestrians and vehicles.          
The standard of design
includes a low level of provision
narrow but segregated cycle
route.  User groups are
expected to interact sensibly. 
This may present a risk to
some user groups such as the
older and less able who have
difficulty in hearing oncoming

Page 83

81 | P a g e
www.connectedtp.com 
vehicles or cyclists.  The design
will include some basic
wayfinding signage that should
seek to reinforce pedestrian
priority. The route has a high
level of coherence making it
easier for  groups to navigate
between and across sections.
At these locations, user conflict
risk is increased.  There is little
can be done from a design
perspective to manage user
group behaviours.  It is also
noted that visiting drivers can
often choose to arrive by car
and place continued strain on
available community parking.  
Fairer Scotland Duty
Mainland rural
population                
Island populations   x

Page 84

82 | P a g e
www.connectedtp.com 
Low income
There is no single
definition or measure
of low income. Some
indicators suggest
that low income is
where individuals
living in households
receive below 60%
of UK median
income. Scottish
Government’s
Children in Families
With Limited
Resources Across
Scotland 2014-2016
defines low income
as ‘household
income below 70%
of the Scottish
median after housing
cost’.    
Improved
access to
services will
address the
challenges
noted through
the SIMD and
Place scoring
tool.        
Accessible routes will support
the movement of people on all
points of the social scale.  The
routes should provide some
support to social interaction
between the community. During
the stage 1 engagement, it was
noted that promotion on a route
along the existing road corridor
would be preferred as it is
within this space that the
majority of the communities
social engagement occurs.
Whilst no data is known about
low income families within the
community the principle of
providing improved access to
people to place by improved
sustainable travel options is
known to support individuals
from all income abilities.
Low wealth
Not having access to
wealth (including for
example, financial
products, equity from
housing, decent
pension, accessible
saving). People who
have low wealth lack
protection from
socio-economic
disadvantage.    
Improved
access to
services will
address the
challenges
noted through
the SIMD and
Place scoring
tool.        
Accessible routes will support
the movement of people on all
points of the social scale. The
route may support new
business opportunities through
tourist cycling groups which
could contribute to wealth
creation. Whilst the route is not
directly linked to wealth it is
again supportive of wealth
creation.

Page 85

83 | P a g e
www.connectedtp.com 
Material
deprivation
Inability to access
basic goods and
services.  
Intervention is unlikely to
create a significant enough
impact to address the areas
overall rural remoteness and
the cost of living in a
community.          
The intervention is unlikely to
create a significant enough
impact to address the areas
overall rural remoteness and
the cost of living in a
community.  The route links
Rothesay's pavilion to Glenburn
Road which might provide
some betterment to the
communitas located to the
West or East of Rothesay
noting these folks will still need
to travel to Rothesay to access
goods and services in any
case.  The route will not provide
any improvement to the
location of services but may
accessing services more
comfortable.
Area deprivation
Areas where there
are concentrations of
deprived
households.  
Intervention is unlikely to
create a significant enough
impact to address the areas
overall rural remoteness and
the cost of living in a
community.          
Intervention is unlikely to create
a significant enough impact to
address the areas overall rural
remoteness and the cost of
living in a community.

Page 86

84 | P a g e
www.connectedtp.com 
Socio-economic
background
Relates to the
context in which a
person has been
raised or in which
they live.
Disadvantage may
arise from parents’
education,
employment and
income (social
class).    
Improved
access to
services will
address the
challenges
noted through
the SIMD and
Place scoring
tool.        
Accessible routes will support
the movement of people on all
points of the social scale.
Communities of
place
Refers to people who
are bound together
because of where
they live, work, visit,
or otherwise spend a
continuous portion of
their time. This may
include rural, remote
and island areas.    
Improved
access to
services will
address the
challenges
noted through
the SIMD and
Place scoring
tool.        
Accessible routes will support
the movement of people on all
points of the social scale.  The
route should support social
interaction between the
community. The route will be
located along the existing road
as promoted by the community.
This will continue to support
community social interaction
and maintain a community
connection with the residents.
Communities of
interest
Refers to groups of
people who share an
identity or an
experience. They do
not need to live in
the same area,
however.    
Improved
access to
services will
address the
challenges
noted through 
the SIMD and
Place scoring
tool        
n/a

Page 87

85 | P a g e
www.connectedtp.com 
If you have identified any impacts on service users, explain what these will be.           
Impact on service deliverers (including employees, volunteers etc)
Protected characteristic Negative No Impact Positive   Don’t Know
Action
required
for impact
be known  
Details
(incl. action taken to minimise
negative and/or maximise
positive impact)
Age
Including the experiences of young
people (age 18 and under) and older
people.  
x           As per Service Users.
Disability
Including the experiences of people
with long term limiting health
conditions.  
x           As per Service Users.
Ethnicity
Including impact relating to skin colour,
nationality, language spoken and
country of origin. People identifying as
Gypsy / Travellers are protected by
this characteristic.  
x           As per Service Users.
Sex   x           As per Service Users
Gender reassignment
Where someone is living part / full time
as the opposite gender to their
assigned sex at birth.  
x           As per Service Users.
Marriage and Civil Partnership   x           As per Service Users.

Page 88

86 | P a g e
www.connectedtp.com 
Pregnancy and Maternity
This covers women as soon as they
become pregnant. In the workplace
this includes pregnancy-related illness.
When a woman gives birth or is
breastfeeding, this characteristic
protects them for 26 weeks.  
x           As per Service Users.
Religion / Belief
Including the experiences of people
with no religion or belief.  
x           As per Service Users.
Sexual Orientation   x           As per Service Users.
Other marginalised groups
Including but not exclusive to the
experiences of unpaid carers,
homeless people, current and ex-
offenders, people with addictions, care
experienced people, and people living
in rural areas.  
x           As per Service Users.
Cross Cutting
Where two or more characteristics
overlap and the proposal affects those
people in a specific way  
x           As per Service Users.
Fairer Scotland Duty
Mainland rural population   X           As per Service Users.
Island populations   x           As per Service Users.
Low income
There is no single definition or
measure of low income. Some
indicators suggest that low income is
where individuals living in households
receive below 60% of UK median
income. Scottish Government’s
Children in Families With Limited
Resources Across Scotland 2014-
2016 defines low income as  
x           As per Service Users.

Page 89

87 | P a g e
www.connectedtp.com 
‘household income below 70% of the
Scottish median after housing cost’.
Low wealth
Not having access to wealth (including,
for example, financial products, equity
from housing, decent pension,
accessible saving). People who have
low wealth lack protection from socio-
economic disadvantage.  
x           As per Service Users
Material deprivation
Inability to access basic goods and
services.  
x           As per Service Users.
Area deprivation
Areas where there are concentrations
of deprived households.  
x           As per Service Users.
Socio-economic background
Relates to the context in which a
person has been raised or in which
they live. Disadvantage may arise from
parents’ education, employment and
income (social class).  
x           As per Service Users.
Communities of place
Refers to people who are bound
together because of where they live,
work, visit, or otherwise spend a
continuous portion of their time. This
may include rural, remote and island
areas.  
x           As per Service Users.
Communities of interest
Refers to groups of people who share
an identity or an experience. They do
not need to live in the same area,
however.  
x           As per Service Users.

Page 90

88 | P a g e
www.connectedtp.com 
Section 4: Interdependencies  
Is this proposal likely to have any knock-on effects for any other activities carried out by or on behalf of the Council?
No  
Details of knock-on effects identified.
None 
Select the overall assessment result, 1-4, which applies
Overall Assessment Result Justification
No major change
If this is selected you are confirming that the EqSEIA demonstrates the proposal is
robust and there is no possible adverse impact.
n/a
Continue the proposal
If this is selected you are confirming that the EqSEIA identifies possible adverse impact
or missed opportunities but the proposal can be justified.
At this early stage, the project options can be developed to provide
a positive influence on all user groups within the community. 
Consideration of a project alignment which supports access by
those less able will increase the interventions attractiveness for use
by a wider audience.
Adjust the proposal
If this is selected you are confirming that the EqSEIA identifies possible adverse impact
or missed opportunities which suggest the proposal needs to be adjusted.
n/a
Stop and remove the proposal
The proposal shows actual or possible unlawful discrimination. It must be halted or
significantly changed.
n/a   
High Level Amendments made to Proposal due to EqSEIA

Page 91

89 | P a g e
www.connectedtp.com 
Protected characteristic Specific Adjustments
made due to EqSEIA Lessons Learned
Age
Including the experiences of young people (age 18 and under) and older people. None n/a
Disability
Including the experiences of people with long term limiting health conditions. None n/a
Ethnicity
Including impact relating to skin colour, nationality, language spoken and country of
origin. People identifying as Gypsy / Travellers are protected by this characteristic.
None n/a
Sex None n/a
Gender reassignment
Where someone is living part / full time as the opposite gender to their assigned sex at
birth.
None n/a
Marriage and Civil Partnership None n/a
Pregnancy and Maternity
This covers women as soon as they become pregnant. In the workplace, this includes
pregnancy-related illness. When a woman gives birth or is breastfeeding, this
characteristic protects them for 26 weeks.
None n/a
Religion / Belief
Including the experiences of people with no religion or belief. None n/a
Sexual Orientation None n/a
Other marginalised groups
Including but not exclusive to the experiences of unpaid carers, homeless people,
current and ex-offenders, people with addictions, care experienced people, people
living in rural areas.
None n/a
Cross Cutting
Where two or more characteristics overlap and the proposal affects those people in a
specific way.
None n/a
Fairer Scotland Duty 
Mainland rural population None n/a

Page 92

90 | P a g e
www.connectedtp.com 
Island populations None n/a
Low income
There is no single definition or measure of low income. Some indicators suggest that
low income is where individuals living in households receive below 60% of the UK
median income. Scottish Government’s Children in Families With Limited Resources
Across Scotland 2014-2016 defines low income as ‘household income below 70% of
the Scottish median after housing cost’.
None n/a
Low wealth
Not having access to wealth (including for example, financial products, equity from
housing, decent pension, accessible saving). People who have low wealth lack
protection from socio-economic disadvantage.
None n/a
Material deprivation
Inability to access basic goods and services. None n/a
Area deprivation
Areas where there are concentrations of deprived households. None n/a
Socio-economic background
Relates to the context in which a person has been raised or in which they live.
Disadvantages may arise from parents’ education, employment and income (social
class).
None n/a
Communities of place
Refers to people who are bound together because of where they live, work, visit, or
otherwise spend a continuous portion of their time. This may include rural, remote and
island areas.
None n/a
Communities of interest
Refers to groups of people who share an identity or an experience. They do not need
to live in the same area, however.
None n/a 
Section 6: Monitoring and Review   
How will the equality and socio-economic impacts of the proposal be monitored and evaluated?

Page 93

91 | P a g e
www.connectedtp.com 
Update the SEQiA at the next stage of the project once the design is developed.   
Action to be taken to: Provide a best practice design
• Mitigate possible negative impact(s) (listed under Section 3);
• Promote possible positive impact(s) and;
• Gather further information or evidence.
Action Lead Timescale                                 
When is the proposal due to be reviewed?
Jul-25