ARGYLL AND BUTE COUNCIL  Bute and Cowal Area Committee 
DEVELOPMENT AND ECONOMIC
GROWTH 
03 June 2025 
Rothesay Pavilion to Albert Pier Active Travel Project: Updated Reports 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates members in relation to amendments made to the “Rothesay,
Pavilion to Albert Pier Car Park Active Travel Project Stage 1&2 Combined,
Options Feasibility Report” and “Rothesay Pavilion to Albert Pier Active Travel
Project Stage 1&2 Combined, Engagement Report” documents for the Rothesay
Pavilion to Albert Pier Active Travel Project as requested by this Committee on
04 March 2025. 
1.2. Further to the work reported on the Rothesay Pavilion to Albert Pier Active Travel
Project and previous work to develop a concept design for a route linking
Rothesay Ferry Terminal to the Rothesay Joint Campus, Officers have submitted
an application to Transport Scotland’s Active Travel Infrastructure Fund 2025/26
for funding to enable these two concept designs to be progressed developed
design stage.  This would be for a T-shaped route linking Rothesay Pavilion,
Rothesay Ferry Terminal, Albert Pier and Rothesay Joint Campus, including other
key destination along the B833 High Street.  The application excludes the
potential extension between Albert Pier and The Glenburn Hotel as this did not
receive community support from those who responded to the consultation. 
1.3. Transport Scotland’s Active Travel Infrastructure Fund requires the submission of
a length and detailed competitive application for each individual project, with every
individual project competing against every other project from across Scotland for
the limited funding available. Is expected the fund be significantly oversubscribed
due to the number of high value projects being progressed across Scotland and
will therefore be highly competitive.  If funding is awarded, it is only for a single
financial year and a new competitive application requires to be submitted each
financial year and compete against all submissions in that year.  As such, there is
no guarantee that this or any other application submitted for projects within Argyll
and Bute will be successful in any given financial year, and having previously
secured funding for a project does not guarantee that funding will be secured for
that project in future years. 
RECOMMENDATIONS 
1.4. It is recommended that the Bute and Cowal members: 
1.4.1. Approve the amendments made to the initial feasibility and concept design reports
for the Rothesay Pavilion to Albert Pier Active Travel Project.

Page 2

ARGYLL AND BUTE COUNCIL  Bute and Cowal Area Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
03 June 2025 
Rothesay Pavilion to Albert Pier Active Travel Project: Updated Reports 
2.0 INTRODUCTION 
2.1. This report updates members in relation to amendments made to the “Rothesay,
Pavilion to Albert Pier Car Park Active Travel Project Stage 1&2 Combined,
Options Feasibility Report” and “Rothesay Pavilion to Albert Pier Active Travel
Project Stage 1&2 Combined, Engagement Report” documents for the Rothesay
Pavilion to Albert Pier Active Travel Project as requested by this Committee on
04 March 2025. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Bute and Cowal members: 
3.1.1. Approve the amendments made to the initial feasibility and concept design reports
for the Rothesay Pavilion to Albert Pier Active Travel Project. 
4.0 DETAIL 
4.1. Rothesay, Pavilion to Albert Pier Car Park Active Travel Project Stage 1&2
Combined, Options Feasibility Report has been updated to correct the following
points. 
4.1.1. Conservation Area (p.7): updated to reflect Rothesay’s many examples of
Victorian design and conservation. 
4.1.2. Direction of Travel (p.9): traffic survey data referenced in relation to the travel
direction of vehicles leaving the CALMAC Ferry Terminal. 
4.1.3. Land Ownership (p.13): updated to reflect Visit Scotland ownership of the
Discovery Centre and Council ownership of the Putting Greens, Flower Beds
and Promenade. 
4.1.4. Loading and Servicing (p.33): updated to reflect the need for businesses on
Victoria Street (A846) to use frontage access for loading and servicing. 
4.1.5. Parking (p.50): table and associated text updated in line with final concept
design.

Page 3

4.2. Rothesay Pavilion to Albert Pier Active Travel Project Stage 1&2 Combined,
Engagement Report was updated to more accurately reflect the stated position
of Bute Community Council. 
4.3. Further to the work reported on the Rothesay Pavilion to Albert Pier Active Travel
Project and previous work to develop a concept design for a route linking
Rothesay Ferry Terminal to the Rothesay Joint Campus, Officers have submitted
an application to Transport Scotland’s Active Travel Infrastructure Fund 2025/26
for funding to enable these two concept designs to be progressed developed
design stage.  This would be for a T-shaped route linking Rothesay Pavilion,
Rothesay Ferry Terminal, Albert Pier and Rothesay Joint Campus, including other
key destination along the B833 High Street.  The application excludes the
potential extension between Albert Pier and The Glenburn Hotel as this did not
receive community support from those who responded to the consultation. 
4.4. Transport Scotland’s Active Travel Infrastructure Fund requires the submission of
a length and detailed competitive application for each individual project, with every
individual project competing against every other project from across Scotland for
the limited funding available. Is expected the fund be significantly oversubscribed
due to the number of high value projects being progressed across Scotland and
will therefore be highly competitive.  If funding is awarded, it is only for a single
financial year and a new competitive application requires to be submitted each
financial year and compete against all submissions in that year.  As such, there is
no guarantee that this or any other application submitted for projects within Argyll
and Bute will be successful in any given financial year, and having previously
secured funding for a project does not guarantee that funding will be secured for
that project in future years. 
5.0 CONCLUSION 
5.1. The reports submitted to the Bute and Cowal Area Committee on 04 March 2025
have been updated to take account of the amendments requested by this
Committee. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
Outcomes Improvement Plan outcomes 1: Transport
Infrastructure and 3: Community Wellbeing. The project
also supports achievement of the Scottish
Government’s objectives set out in the Cycling Action
Plan for Scotland (CAPS) and Let’s Get Scotland
Walking - The National Walking Strategy.
6.2. Financial The design and construction is planned to be funded by
external funding applications. To date, the Council has
not contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to require

Page 4

social care services in later life which could result in a
future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and Traffic Regulation
Orders (TROs) should these be necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in Rothesay to travel more sustainably and actively
by walking, wheeling and cycling. This is particularly
important to the 41% of households in Rothesay (2022
Census) don’t have access to a motor vehicle.
The route has been designed to be DDA compliant and
will provide a safe and accessible route for those with
mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel, which
are lower cost than alternative modes of transport.  The
route will also improve access to essential services,
retail, leisure and employment opportunities for
residents living along the route, with studies
demonstrating those who travelled actively had a higher
monthly spend in local businesses than those who
travel via motorised transport.
The route will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel for essential journeys will help lower
Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.

Page 5

6.9. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates support for the
delivery of the improvements from younger members of
the community. Wider engagement with school pupils
indicates that the majority of pupils across Argyll and
Bute strongly support the provision of new active travel
infrastructure, even where it would adversely impact
other modes of transport. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr John Armour 
12 May 2025                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Rothesay Pavilion to Albert Pier Active Travel Project Stage 1 & 2,
Options Feasibility Report 
Appendix 2: Rothesay Pavilion to Albert Pier Active Travel Project Stage 1 & 2,
Engagement Report