Page 1

Classification: OFFICIAL#
AREA TOWN/VILLA
GE EXISTING LOCATION COUNCIL OWNED PROPOSED THEME PRIORITY COMMENTS
STRACHUR MEMORIAL HALL Y 1 x RAPID 1 1
This would provide for a network gap between Dunoon
and Inveraray/Arrochar. This is a third party oned site - we
have had positive initial discussions with the owners
GUILDFORD SQUARE Y 1 x RAPID 1 1
Rapid charging provision has now been provided via the
FASTER project noted below. It may be the case that, with
the 2x RAPIDs prvided at Rothesay Harbour, the Guildford
Square site needn't be as high a priority.
GUILDFORD SQUARE Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
1 x SLOW GUILDFORD SQUARE Y
This charger has reached the end of its economical life
and we are seeking to decommission it and, in time,
when funding becomes available, replace it with a FAST
or RAPID charger
CHAPELHILL ROAD CAR PARK Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
2 x RAPID ROTHESAY HARBOUR Y 1 2
Delivered 2x RAPID chargers as part of HITRANS FASTER
project 2023. This provides additional capacity over and
above what was planned, in agreement with HITRANS in
order to access and maximise funding. Also bolsters the
provision given the issues with the Guildford Square
charger noted above.
ROTHESAY HARBOUR Y 1 x FAST or
SLOW [TBC] 2 2 Different type of charger at this site to provide for those
ferry passengers who would leave their car.
TIGHNABRUAICH1x RAPID
AND 1x FAST ROCKBANK Y 1 2 Previousy committed to via 2019/20 TS LAIP funding, now
delivered
INNELLAN SANDY BEACH Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
PORT BANNATYNE ON-STREET PARKING BAY
[EXACT DETAILS TBC] Y 1 x FAST 2 1 On the basis that there is no off-street car park proposed
on street to meet network gap
Sites delivered since last update December 2022
Sites expected to be delivered in 2025
Chargers beyond economic life and removed from use
BUTE & COWAL
ROTHESAY
Key
Chargers beyond economic life to be replaced via CCG to comply with new regulations
Chargers beyond economic life and replaced as part of FASTER Project

Page 2

Classification: OFFICIAL#
1 x FAST AND
1 x RAPID
COAL PIER ALEXANDRA
PARADE Y Rapid charger beyond economic life and to be replaced
via CCG to comply with new regulations
HANOVER STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
KIRK STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
ARGYLL STRET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
GLENMORAG CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
JANE VILLA CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
MOIR STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
SANDBANK TSC CAR PARK Y 1 x FAST 2 1
Population 1,000 to 2,000 - one car park. It should be
notedhere that there is another car park owned by a local
community group which may provide for a better location
[Ardnadam]
LOCHGOILHEAD SHORE ROAD CAR PARK Y 1 x FAST 2 1 Population fewer  than 1,000 but known tourist hotspot
15
ADDITIONAL CHARGERS DELIVERED THROUGH HITRANS FASTER
BUTE AND
COWAL DUNOON 2 x RAPID COAL PIER
PROJECT AUTUMN/WINTER 2023
BUTE & COWAL
DUNOON