ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 23 FEBRUARY 2023
RESERVES AND BALANCES – UPDATED FOR BUDGET PACK 2023-24 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to advise Members of the overall level of
reserves held by the Council as well as providing detail on the monitoring of the
earmarked balances held within the General Fund. 
1.2 The Council has a total of £394.480m unusable reserves that are not backed with
resources.  They are required purely for accounting purposes. 
1.3 At 31 March 2022 the Council had a total of £103.183m usable reserves.  Of this: 
• £2.682m related to the Repairs and Renewals Fund
• £4.414m related to Capital Funds
• £96.087m was held in the General Fund with £88.990m of this balance
earmarked for specific purposes.
1.4 The Council’s General Fund contingency remains at 2% of net expenditure.  This
monetary level has been adjusted to take account of the revised net revenue
expenditure proposed for 2023-24.  The revised contingency of 2% of net
expenditure amounts to £5.684m. 
1.5 As at 31 December 2022 the forecast outturn for 2022-23 was estimated to be an
underspend of £3.408m, however, this is subject to change, particularly as the last
three months of the financial year are the time of winter maintenance and the level
of expenditure is difficult to predict. This underspend is as a result of the treasury
gain of £5.398m due to receiving a discount on the early repayment of three PWLB
loans offset by £1.491m recognised for the net expected shortfall in funding from
the 2022-23 pay award and other forecast overspends within the Departments
totalling £0.499m.  As a result, the forecast surplus over contingency at 31 March
2022 is estimated to £8.109m, however, this is an estimated position and subject to
change. 
1.6 Assessing the adequacy of reserves should take account of the strategic,
operational and financial risks facing the Council and should consider both internal
and external factors.  There are 19 categories included in the risk analysis and 5
have been assessed as low, 3 low/medium, 7 medium and 4 medium/high.  The
medium/high risks are in respect of the potential impact of the UK exit from the EU,
future funding, inflation rates and the general financial climate.

Page 2

ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 23 FEBRUARY 2023
RESERVES AND BALANCES – UPDATED FOR BUDGET PACK 2023-24 
2. INTRODUCTION 
2.1 This report outlines current balances on all of the Council’s reserves, both
usable and unusable. It also provides detail on the monitoring of the earmarked
balances within the General Fund.   
3. DETAIL 
3.1 Types of Reserves 
3.1.1 Usable Reserves - Councils have powers to establish certain resource backed
reserves which can be used to fund expenditure.  The powers of councils to
establish reserves are laid out in Schedule 3 of the Local Government
(Scotland) Act 1975.  These allow councils to establish a Renewal and Repairs
Fund, Insurance Fund and Capital Fund. Councils can also establish a Useable
Capital Receipts Reserve.  The Council must also maintain a General Fund and
can earmark balances for specific purposes within the General Fund. 
3.1.2 Unusable Reserves – Councils are also required to establish certain reserves
that are not backed by resources. They are required purely for accounting
purposes and do not represent resources available for councils to utilise. The
Pensions Reserve, Revaluation Reserve, Capital Adjustment Account, Financial
Instruments Adjustment Account and Accumulated Absences Account fall into
this latter category of accounting reserves. 
3.2 Reserve Balances at 31 March 2022 
3.2.1 The balances on each type of reserve at 31 March 2022 are set out in the two
tables below, updated as per the Audited Accounts for 2021-22. 
Unusable Reserves £000
Revaluation Reserve 157,645
Capital Adjustment Account 241,327
Financial Instruments Adjustment Account (2,198)
Pensions Reserve 4,634
Accumulated Absences Account (6,928)
Total Unusable Reserves 394,480 
Usable Reserves £000
Repairs and Renewals Fund 2,682
Capital Fund and Usable Capital Receipts Reserve 4,414                                                                                                                
General Fund  96,087
Total Usable Reserves  103,183
Total Reserves  497,663

Page 3

3.2.2 The Revaluation Reserve represents the unrealised gains in the valuation of
fixed assets. The Capital Adjustment Account represents the difference
between depreciation based on proper accounting practice and statutory
charges for financing capital expenditure. The Financial Instruments Adjustment
Account represents the difference between gains and losses on borrowing and
statutory capital financing charges. The Pensions Reserve represents the
difference between pension costs based on proper accounting practice and
payments made for pension costs. The Accumulated Absences Account
represents the costed difference between holiday pay entitlement and actual
holidays taken at 31 March. 
3.2.3 The Repairs and Renewals Fund was established to support funding of renewal
and replacement of school equipment.  Schools can only draw on the Repairs
and Renewals Fund to the extent they have previously paid into the Fund and
contributions must be contained within schools devolved budgets. 
3.2.4 The Capital Fund was established to receive all capital receipts generated by
the Council and can be used to support the capital plan or meet the principal
repayments on loan charges. The Council decides as part of the budget
process each year how it wishes to draw funding from the Capital Fund. 
3.2.5 The Usable Capital Receipts Reserve relates to the accumulated unspent
capital receipts from sale of council houses prior to transfer of the housing
stock. The reserve forms part of the Council’s Strategic Housing Fund and can
only be used for investment in social housing. The reserve will be used in
accordance with the approach to investing in housing agreed by the Council in
August 2012. 
3.3 General Fund 
3.3.1 The General Fund balance at 31 March 2022 can be analysed as follows: 
Balance
31/03/22
£000
Balance on General Fund as at 31 March 2021 78,245
Increase to General Fund balance at end of 2021-22 17,842
Earmarked Balances (88,990)
Contingency allowance at 2% of net expenditure (5,256)
Unallocated balance as at 31 March 2022 1,841

Page 4

3.3.2 The General Fund includes balances that the Council has agreed to earmark for
specific purposes. Some of these earmarked balances will be spent during the
current financial year and some of them will be held over and spent in later
years. The table below shows the balance at 31 March 2022, the amounts that
are currently invested or set aside for major initiatives, the amount already
spent and planned to be spent in the current year, the amount to be spent in
future years and any sums no longer required to be earmarked. Appendix 1
provides further details on the breakdown of unspent budget.  Officers have
reviewed and updated the spending profiles. 
3.3.3 Investment in Affordable Housing £0.100m – this earmarked balance provides
cash backed reserves for the loans to registered social landlords.  It is

Page 5

estimated that as at 31 March 2023, the balance on the remaining loans will be
£3.200m, therefore £0.100m can be released back to the general fund.   
3.3.4 Due to there being no planned expenditure, an earmarking for capital
expenditure on a leased property of £0.025m has been released back to the
general fund.   
3.3.5 In 2020-21 and 2021-22, the Council received allocations for the administration
of Business Support Grants which currently sit within the COVID-19 earmarked
reserves. There is a balance remaining of £0.411m which is no longer required
for this purpose and is being released to the General Fund. 
3.3.6 The last of the redundancy payments in relation to the Kintyre Recycling
unspent budget earmarking have been drawn down so remaining balance of
£0.017m can be released back to the general fund. 
3.4 Unallocated General Fund Balance 
3.4.1 The General Fund contingency is set at 2% of net expenditure for 2022-23 and
amounts to £5.256m.  This contingency is held to provide a working balance to
help cushion the impact of uneven cash flows and cushion the impact of
unexpected events.  It is up to authorities to make their own judgement on the
level of reserves taking local circumstances into account, for example, previous
call on contingency and amount of unallocated reserves held.  The contingency
needs to be updated to reflect the updated budget for 2023-24.  The budgeted
net expenditure based on the proposed budget contained within the revenue
budget overview report is £284.206m.  2% of this balance amounts to £5.684m.
There is currently a contingency of £5.256m, therefore £0.428m will require to be
moved from the unallocated General Fund balance to supplement the
contingency. 
3.4.2 The revenue budget position as at 31 December 2022 was estimated to be
£3.408m underspent, however, this is subject to change, particularly as the last
three months of the financial year are the time of winter maintenance and the
level of expenditure is difficult to predict. Note that this underspend is largely as
a result of the treasury gain of £5.398m due to receiving a discount on the early
repayment of three PWLB loans offset by £1.491m recognised for the net
expected shortfall in funding from the 2022-23 pay award plus other forecast
variances within the Departments netting to a £0.499m overspend. 
3.4.3 The Current Forecast Outturn at December includes an overspend against the
Social Work service of £0.253m.  The Chief Financial Officer of the IJB is
confident that the spend will be brought in line with budget by the end of the
financial year using slippage from growth projects and anticipated additional
funding allocations. Social Work began to accumulate reserves at 31 March
2022 therefore it is expected that any residual overspend that materialises
would be covered from those reserves and the General Fund of the Council
would not be impacted.  
3.4.4  The table below summarises the position of the unallocated General Fund
balance taking into consideration the points noted above.

Page 6

Heading Detail £000
Unallocated
General Fund as
at 31 March 2022
This is the balance that is unallocated over
and above the 2% contingency which
amounts to £5.256m
1,841
Budgeted
allocation to
General Fund for
2022-23 Budget
Per the Budget Motion at Council on 24
February 2022
2,482
Earmarked
Balances no
longer required
Per paragraph 3.3.3 to 3.3.6 – amounts
previously earmarked that can be released
back to general fund
553
Transfer of
contingency to
maintain 2% level
Per paragraph 3.4.1 (428)
Forecast Outturn
for 2022-23 as at
31 December 2022
Per paragraph 3.4.2 3,408
Social Work
outturn adjustment
Per paragraph 3.4.3 253
Estimated
Unallocated
General Fund
Balance as at 31
March 2023 
8,109 
3.4.5 
3.5 
The HSCP in partnership with the Council are looking to engage with Hub North
to develop a strategic business case relating to the provision of services for
older adults and other vulnerable people across Argyll and Bute. One of the
several options anticipated to be considered in this piece of work is the
possibility of a ‘Care Village’ development on part of the Lochgilphead hospital
site. The cost associated with this is £0.100m and it is recommended that this is
funded from the estimated unallocated General Fund balance. 
Loans Fund Review 
3.5.1 At the Council meeting on 27 February 2020, it was agreed that the one-off re-
profiling gain of £20.561m generated by the loans fund review should be used
partly to create a provision for the increasing principal repayments over the next
10 years (£7.649m) with the remainder of the gain (£12.912m) used to fund the
known liabilities/cost pressures. The table below shows what has been drawn
down against the one-off gain and the remaining balance.

Page 7

Agreed
Allocation
Transferred
to
Earmarked
Reserves /
20-21 / 21-22
Budget
Transferred
to
Earmarked
Reserves /
22-23
Budget
Balance
Remaining 
£000 £000 £000 £000
Provision for the increasing
principal repayments 7,649   7,649
Provision to Support
Organisational Change 500 (500)  0
Estimated Cost of 2020-21
redundancies that are part of
budget savings proposals
600 (600)  0
Future Redundancies
Provision 1,500 (1,500)  0
Spend to Save Route
Optimisation 100 (100)  0
Funding Gap in Capital
Programme 2,619   2,619
Capital Programme
Intolerable Red Risks 574 (574)  0
Campbeltown Flood
Prevention Scheme 1,406  (1,406) 0
Significant Strategic Change
Projects  5,013 (2,856)  2,157
2020-21 Revenue Budget
Contribution  600 (600)  0 
20,561 (6,730) (1,406) 12,425 
3.6 Review and Risk Assessment 
3.6.1 Assessing the adequacy of reserves should take account of the strategic,
operational and financial risks facing the Council and should consider both
internal and external factors.  Appendix 2 to this report identifies the range of
issues in terms of budget assumptions and financial standing and management
that should be considered in assessing the level of reserves.  It relates only to
consideration of the contingency to be held in the General Fund balance.  A
separate financial risk analysis report has been prepared looking at the overall
financial risks relating mainly to the revenue budget but notes a couple of risks
in respect of the capital budget also. 
3.6.2 There are 19 categories included in the risk analysis and 5 have been assessed
as low, 3 low/medium, 7 medium and 4 medium/high.  The medium/high risks
are in respect of the potential impact of the UK exit from the EU, future funding,
inflation rates and the general financial climate.   
3.6.3 Based on the above and taking cognisance of the level of unallocated general
fund balance that remains, it is recommended that the contingency for the
General Fund balance should be retained at 2%.   
4. CONCLUSION 
4.1 The report outlines the overall reserves and balances for the Council covering
the purpose and level of each reserve.  It also provides detail as to expenditure
against earmarked balances held within the General Fund.  There is currently

Page 8

an estimated surplus over contingency of £8.109m after adjusting for the
forecast outturn for 2022-23 and the estimated impact of pay awards still to be
settled.   
5. IMPLICATIONS 
5.1 Policy - Earmarked funds and funds set aside for delivery of
Single Outcome Agreement are available to support
Council Policy.
5.2 Financial -  Outlines the balances held with the Council’s usable and
unusable reserves.     
5.3 Legal -  None.
5.4 HR -  None.
5.5 Fairer Scotland Duty- See Below
5.5.1 Equalities None
5.5.2 Socio-Economic
Duty
None
5.5.3 Islands Duty None
5.6 Climate Change None
5.7 Risk -  A contingency of £5.684m (equivalent to 2% of net
expenditure) has been set aside as part of the general
fund.  This has been subject to a risk assessment. 
5.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director/Section 95 Officer 
9 February 2023 
Policy Lead for Finance and Commercial Services: Councillor Gary Mulvaney 
APPENDICES
Appendix 1 – Earmarked Reserves breakdown of unspent budget as at 31 December
2022
Appendix 2 – Risk Assessment for Review of Reserves 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 9

APPENDIX 1
Earmarked Reserves - Unspent Budget
As at 31 December 2022
Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
001 Chief Executive's
Unit
Community
Planning
Communities and
Partnership Team
8,855 0 8,855 8,855 0 The funds have originated from externally sourced income due to an employee being
seconded to the Scottish Community Development Centre (SCDC).  The funds will be used
to support the team in relation to meeting its priorities of Building Back Better
(Communities), Climate Change and the review of the Argyll and Bute Outcome
Improvement Plan.
8,855 0 0
002 Chief Executive's
Unit
Community
Planning
Gaelic Development 8,235 8,235 8,235 0 To fund Gaelic specific work and project work of the Community Planning Partnership
including the development of the new 10 year Outcome Improvement Plan
8,235 0 0
003 Chief Executive's
Unit
Financial Services Financial Systems 114,000 80,252 33,748 33,748 0 To fund the completion of the implementation of the Oracle Fusion Financial
Management System, a software update for cash receipting to ensure card payments can
still be taken and the procurement and implementation of a new system to manage the
requirements of the IFRS16 Leases accounting standard.
114,000 0 0
004 Chief Executive's
Unit
Financial Services Accounting and
Budgeting Team
Resilience
95,000 64,336 30,664 0 30,664 To fund the implementation of a new staffing structure in 2022/23 as agreed at ELT on 12
April 2022.  This will provide funding to cover the additional staffing costs in 2022/23 and
the training costs over the period 2022/23 to 2026/27
64,336 16,664 14,000
005 Chief Executive's
Unit
Financial Services CIPFA 32,530 3,565 28,965 2,000 26,965 CIPFA Training - To fund the professional training costs for staff undertaking the CIPFA
professional accountancy qualification.
5,565 6,000 20,965
006 Chief Executive's
Unit
Financial Services Scottish Government
Funding - Welfare
Reform/Discretionary
Housing Payments
(agreed at Council
February 2014)
18,595 18,595 0 18,595 The Council was allocated additional funding of £550k from the Scottish Government late
in 2013-14. This money was allocated to support the Community Learning and
Development Team to provide courses to support Universal Credit claimants 2019/2020
to support the recruitment of casual tutors and the purchase and upgrade of laptops. The
monies were not utilised however it will now be required to top up the Scottish Welfare
Fund and DHP monies for 2023/24 earmarking ref 008 and 012 as it is likely that given the
current cost of living crisis that more people will be in need of support through these
funds
0 18,595 0
007 Executive Director
(Douglas Hendry)
Across Services /
Education
Digital Projects
(Supply Staff Booking
System)
35,000 9,900 25,100 0 25,100 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
9,900 9,900 15,200
008 Executive Director
(Douglas Hendry)
Commercial
Services
Rothesay Pavilion
Charity
750,000 750,000 90,000 660,000 Agreed at Council meeting February 2020, £750k additional revenue support subject to
conditions which seek to minimise the risk to the Council as far as is reasonably
practicable including requirement for adequate business and financial management and
regular reporting by RPC.
90,000 660,000 0
009 Executive Director
(Douglas Hendry)
Commercial
Services
Demolition of former
Lochgilphead Primary
and Rothesay
Secondary School
320,000 320,000 105,000 215,000 To fund the demolition of the former Lochgilphead Primary School and former Rothesay
Academy (subject to the removal of the listing).
105,000 215,000 0
010 Executive Director
(Douglas Hendry)
Commercial
Services
Rothesay Pavilion
Essential repairs
306,400 306,400 0 306,400 Essential repairs to deal with potential health and safety risks and to avoid further
deterioration.  Budget provision was approved by the Policy and Resources Committee on
21 August 2014. 
0 0 306,400
011 Executive Director
(Douglas Hendry)
Commercial
Services
Estates - NDR
Revaluation Appeals
84,688 84,688 0 84,688 The Council agreed to make provision to meet the cost of appealing Non Domestic Rates
(NDR) revaluations which were imposed from 1st April 2017. The remaining funds were
carried forward to the 2023 revaluation cycle however a recent change in position by the
Scottish Government may restrict the appeals which can be made. This is still under
discussion and Gerald Eve Surveyors have been appointed as specialist advisers on this
matter. In the event that appeals are limited there may be an opportunity to utilise
Gerald Eve for more general valuation advice subject to Procurement approval.
0 84,688 0

Page 10

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
012 Executive Director
(Douglas Hendry)
Commercial
Services
Site Investigation
Works
21,013 21,013 21,013 0 For Site Investigation works in relation to Tweeddale Street Car Park and Oban Airport
Business Park, exploring commercial opportunities to develop the sites and raise revenue
income for Argyll and Bute Council. HUB North were instructed to procure contractors to
undertake the site investigations these are now complete. The remainder of the budget is
intended to be utilised for other site investigation and pre-development works to further
develop commercial opportunities across the council area.
21,013 0 0
013 Executive Director
(Douglas Hendry)
Commercial
Services
Catering and Cleaning
Restructure Costs
17,000 17,000 0 0 0 To support the catering and cleaning team restructure 17,000 0 0
014 Executive Director
(Douglas Hendry)
Education Education
Transformation Fund
187,526 40,852 146,674 0 146,674 At the Council meeting on 27 February 2020, it was agreed to input £400k into Education
Digital Learning.  The additional funds have been spent in 20/21, 21/22 and 22/23 as part
of the ongoing transformation work in the Education service, focussing on digital and
virtual learning technology and the development of learning clusters.  This will continue
into 2023/24.
40,852 146,674 0
015 Executive Director
(Douglas Hendry)
Education Education Learning
Estate Condition
Surveys
77,440 46,853 30,587 30,587 0 To fund the delivery of School Core Facts (SCF) compliant Condition Surveys for prioritised
School Buildings.
77,440 0 0
016 Executive Director
(Douglas Hendry)
Education Skype for Business for
Education / Digital
Projects (Skype for
Business)
10,000 10,000 10,000 0 To fund the initial capital costs for the implementation of Skype for Business for
Education.  This will bring the Education service in line with other council departments
and will improve staff collaboration and modernise school telephony to deliver the 
service more efficiently and cost effectively.
A balance has been released back to the general fund because the rollout project is
almost complete with only £0.01m expected spend in 22/23.
10,000 0 0
017 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Education Purchasing
Officers
210,000 210,000 0 210,000 The earmarked funds will be used to fund an education purchasing team within the
Procurement Service for two years.  The team will embed good procurement practice,
train headteachers on current procurement process requirements, develop spend plans
that evidence best value.
0 105,000 105,000
018 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
NDR - One off
contribution to 22/23
Budget
200,000 200,000 0 0 0 To fund one off operational saving CS04 agreed for the 2022/23 budget. 200,000 0 0
019 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
NPDO Schools
Contract
166,000 166,000 0 0 0 To fund one off operational saving LRS01 agreed for the 2022/23 budget 166,000 0 0
020 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Transformation
Agenda QIO
100,259 74,274 25,985 0 25,985 Ongoing funding for the QIO post to lead the implementation of the service
transformation programme. The QIO will assist the Executive Director to deliver the
Council’s transformation agenda by developing, analysing and monitoring initiatives and
projects which deliver the vision, values and strategic objectives of the Council.
74,274 25,985 0
021 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Digital Projects:
Hybrid Council
meetings
55,000 55,000 30,000 25,000 Per paper agreed at SMT October 2021 - allocation from Digital Projects (General
Provision to be allocated).  To fund the costs of livestreaming of Council meetings. 
30,000 25,000 0
022 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Councillor IT
Equipment
65,000 65,000 25,000 40,000 To meet the cost of provision of IT equipment for all new Elected Members as a result of
the Local Government Election in May 2022.
25,000 25,000 15,000
023 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Debt Counselling &
Welfare Rights
27,025 27,025 5,573 21,452 To meet the cost of a Debt Counselling and Welfare Rights Management System. 5,573 5,965 15,487
024 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Community Safety
Partnership
16,000 16,000 0 16,000 To earmark the Community Safety Partnership funding received for 2021/22 to be used
for Community Safety Partnership purposes. These monies will be spent on future
Community Safety requirements – most likely to be additional CCTV spend as required -
Likely to be amalgamated with 076 in future.
0 16,000 0
025 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Microsoft 365 300,000 300,000 0 300,000 To be added to existing earmarked reserves to meet increasing MS365 licensing costs
from 2022/23 onwards
0 0 300,000
026 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Growing our Own and
Modern Apprentices
109,150 109,150 95,790 13,360 Funding earmarked to support trainee development and modern apprenticeship
opportunities based on priority workforce risk areas. These areas have been identified
and proposals developed. £95,790 to be spent in 22/23 and £13,360 to be spent in 23/24
to fund a graduate trainee and 3 apprentices to deliver trainee development and modern
apprenticeship opportunities
95,790 13,360 0

Page 11

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
027 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Security Operations
Centre Subscription
76,455 76,455 0 76,455 There is a requirement to pay for a 3-year subscription at £60,000 per annum with a cost
pressure being added to the ICT revenue budget to cover the costs from year 4 onwards. 
There is unallocated funding of £103,545 from the earmarking (172) created at 2020/21
year end for 'Digital Projects' combined with this earmarking to cover these costs for 3
years.
16,455 60,000
028 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Learning and
Development
36,508 36,508 36,508 0 In order to maximise the opportunities and efficiencies of digital learning, this funding will
be used to support the extension of digital learning in order to deliver the Digital Learning
Strategy, which was approved in FQ4 20/21.
36,508 0 0
029 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Implementation of
Gaelic Language Plan
30,000 30,000 0 30,000 Agreed at Council Meeting February 2021.  Provision of funding for delivery and
implementation of the council’s Gaelic Language Plan in recognition of the contribution
that Gaelic makes to economic growth and to the tourism sector, and to enable delivery
of key activities within the plan which currently receive no revenue funding.
0 30,000 0
030 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Establishing HR
Service Centre
30,000 30,000 18,000 12,000 To facilitate the implementation of technical efficiency improvements and new processes 18,000 12,000 0
031 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Business
Development Training
27,601 27,601 1,000 26,601 This budget is funding ongoing leadership development, coaching, action learning sets
and commissioned training including Priority Management.
1,000 26,601 0
032 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Oban TIF (Tax
Incremental
Financing)
709,700 709,700 60,000 649,700 Will be used to fund the TIF Programme office for a further 3 years as well as the
programme office for Rural Growth Deal beyond the funding that was agreed at Council
for this in February 2021.
60,000 116,000 533,700
033 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Strategic Events &
Festivals
115,764 115,764 35,000 80,764 At the Council meeting on 25 February 21, a decision was taken to agree £90k funding for
Events and Festivals for 22/23, in order that the application process can commence
during 21/22 and that this agreed figure be augmented by any underspend remaining
from the 20/21 financial year.  At 24 February 22, decision made to agree £90k for 23/24,
in order that the application process can commence during 22/23 and that this agreed
figure be augmented by any underspend remaining from the 21/22 financial year
35,000 80,764 0
034 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Island Post 50,461 50,461 0 50,461 To fund a temporary post at LGE11 to assist with the National Islands Plan
Implementation Route Map 2020-2025.
0 50,461 0
035 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Royal National Mod 40,000 40,000 20,000 20,000 One off funding allocation for the Royal National Mod agreed as part of the budget
setting process for 2019/20. Grant contract issued. Proposed payment of £20k per annum
starting 2020/21  (2023/24 final payment of £20k)
20,000 20,000 0
036 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Variation
Monies
1,492,997 1,492,997 0 1,492,997 This would be used to fund/part-fund various waste infrastructure projects that will
support the council’s compliance with the 2025 ban on the Landfill of Biodegradable
Municipal Waste, including the development of landfill cell construction works at
Gartbreck.  £640k for Capital works on Gartbreck completed in 2022/23, reserve will be
drawn down for this in 2023/24.
0 1,066,000 426,997
037 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Climate Change 500,000 500,000 500,000 0 At the Council meeting on 27 February 20, it was agreed to input £500k budget to
mitigate the impacts of weather related damage and climate change with specific
emphasis on gully cleaning and drainage improvements.  Spend has been delayed due to
COVID and the intention is to spend the funds on 2 Gully Motors plus staff over next 2
years. Vehicles have been received and budget will be drawn down to cover their cost.
The remaining budget will be used towards running the vehicles.
500,000 0
038 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
3G pitches / Tarbert
Sports Pitches
427,286 44,660 382,626 5,340 377,286 In November 2018, the Council agreed to a maintenance funding package to be
progressed for a number of 3G pitches including Tarbert. This funding will provide an
estimated 6.5 years’ worth of ongoing maintenance up to 2025-26.  Final drawn down for
22/23 will be done closer to year end once final costs are confimed.
50,000 90,000 287,286
039 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Green Transport
Initiatives
400,000 400,000 260,000 140,000 At the Council meeting on 27 February 20, it was agreed to input £400k in Green
transport, investment in footway and cycle path maintenance supporting the healthy
wellbeing and green agenda.  Spend has been delayed due to COVID and this will be taken
forward in 23/24. £260k Footways Reconstruction programme now spent and will be
drawn down against capital programme during 23/24. £140k Ardrishaig North Project will
be soent in 22/23 and drawn down in 23/24.
260,000 140,000 0
040 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Strategy 363,000 56,070 306,930 49,211 257,719 To fund/part-fund various waste projects that will support the council's compliance with
the 2025 ban on the Landfill of Biodegradable Municipal Waste.  Final draw down in
22/23  for Welfare Units at Waste Disposal sites on Mull and Tiree and Shed
Improvements on Tiree once final invoices are received.
105,281 129,000 128,719
041 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Management 256,753 10,040 246,713 19,960 226,753 Will be used towards long term waste management strategy/model, including but not
limited to scoping work for the creating of a waste transfer station at Helensburgh. 
Consultancy fees and ground investigation works in 22/23 to be drawn down once final
invoice is received.
30,000 135,000 91,753

Page 12

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
042 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Replacement Signage
and Bins
135,366 135,366 135,366 0 Replacing key road signage. This will help to reduce future budget pressures for
replacement of signs and would also help to enhance the streetscape and general
appearance of the area.  The bulk of Road signs have been delivered and installation is
now in progress and will be completed during 2022/23.
135,366 0 0
043 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Kintyre Recycling
Redundancy Costs
36,000 19,588 16,412 0 0 0 To fund redundancy costs associated with Kintyre Recycling. 19,588 0 0
044 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Amenity Services
introduction of
management
information system
28,099 28,099 0 28,099 Delay with introduction of amenity time recording system due to increased costs. 
Discussions ongoing to find alternative cheaper solution.
0 28,099 0
045 Non Departmental Non
Departmental
Underwriting
development of
Rothesay Pavilion
1,000,000 1,000,000 0 1,000,000 Funding to meet additional costs identified as necessary for the refurbishment of
Rothesay Pavilion.
0 0 1,000,000
046 Non Departmental Non
Departmental
Loans Fund 385,279 385,279 0 385,279 At the Council Budget meeting on 24 February 2022, Saving FS01, a Loans Fund
Management/Operational saving for 22/23 budget of £0.500m was agreed with at least
£0.200m to come from underspends in 21/22.  The underspend position for 21/22 is
£0.385m and this earmarking is being released as a saving to help bridge the 2023/24
budget gap.
0 385,279 0
047 Non Departmental Non
Departmental
Utilities 283,000 283,000 283,000 0 To contribute towards the expected adverse impact on the 2022/23 budget of utility
costs inflation as per Budget Pack. Funding will be drawndown by the end of March 2023.
283,000 0 0
048 Non Departmental Non
Departmental
Digital Projects
(General Provision to
be allocated)
103,545 103,545 60,000 43,545 It has been agreed to use the balance of this earmarking towards the Security Operations
Centre Subscription unspent budget request - per Appendix 2.1  This sum plus earmarked
reserve (85) combine to £180k and will cover the subscription for 3 years 22/23 / 23/24 /
24-25
60,000 43,545 0
049 Non Departmental Non
Departmental
Community Resilience
Fund
76,447 76,447 0 76,447 Fund established in 2012/13 to be spent over more than one year. Fund reduced at the
Council meeting on 11 February 2016
0 0 76,447
050 Non Departmental
/ Chief Executive's
Unit
Across Services /
Chief Executive's
Unit
Information
Management
(Balance of Funding)
209,844 209,844 0 209,844 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
0 0 209,844
051 Non Departmental
/ Executive
Director (Douglas
Hendry)
Across Services /
Commercial
Services
Information
Management (Estates
Survey Work)
12,697 12,697 0 12,697 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
0 12,697 0
052 Non Departmental
/ Executive
Director (Douglas
Hendry)
Across Services /
Legal and
Regulatory
Services
Information
Management
(Digitalisation of Title
Deeds)
92,000 92,000 0 92,000 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k (delay on spending due to COVID-19), document
management and workflow system for Planning, Building Standards and Environmental
Health £77k and a balance of funding to explore information management solutions in a
strategic and coherent way £209k
0 92,000 0
053 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects (Digital
Customer
Engagement Projects)
73,000 73,000 73,000 0
To deliver a number of Digital Service Transformation Projects, specifically Customer
Engagement.  These include £25.5k for an upgrade to contact centre systems (Converse),
£9.7k for a voice chatbot pilot, £15k for Alexa smartspeaker services, £22.8k for Proactive
Notification Service (Eloqua).   All of these have been implemented in 2022/23 and will be
drawn down in January.
73,000 0 0
054 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects
(Increase in Schools
Bandwidth)
63,455 63,455 0 63,455 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
0 63,455 0

Page 13

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
055 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects
(Replacement
Learning
Management System)
11,470 11,470 11,470 0 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
11,470 0 0
056 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Development
and Economic
Growth
Information
Management
(Document
Management and
Workflow for
Planning, Building
Standards and
Environmental
Health)
57,491 36,314 21,177 0 21,177 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
36,314 21,177 0
10,458,934 869,704 16,412 0 9,572,818 2,033,656 7,539,162 2,903,360 3,932,364 3,606,798

Page 14

APPENDIX 2     
Risk Assessment for Review of Reserves
Risk Category Comment Assessment
Cost and Demand
Pressures
As part of maintaining the medium term budgetary outlook, cost and demand
pressures for 2022-23 and beyond have been kept under review.  The cost
and demand pressures for 2023-24 amount to £4.428m for Council services
which includes an additional pressure equivalent to 0.5% of the Council
budget.  A general allowance for unidentified cost and demand pressures
has been built into the budget outlook for 2024-25 and future years: 
£0.250m per annum in the mid-range scenario and £0.500m per annum in
the worst case scenario. 
Medium
(2022-23 Medium)
Service Income Service income levels have been reviewed as part of constructing the
budget. In addition fees and charges have been reviewed. The long term
effects of the COVID-19 pandemic and the impact of high inflation on the
cost of living for customers are likely to affect the uptake of some Council
services and the amount of income generated. 
Medium
(2022-23 Medium) 
Council Wide Cost
Risks
The financial risk analysis identified 6 council wide cost risks currently
amounting to £5.621m as follows: 
• The pay award exceeding 3.5% has been categorised as likely with an
assessed financial impact of £2.200m based on the estimated cost of a
5% uplift being agreed with Trade Unions. This assessment is based on
a combination of the ongoing high levels of inflation and the outcomes to
date of the 2022/23 pay negotiations which have been settled for SJC
staff but are ongoing in relation to the Teachers and Chief Officers pay
settlements; 
Medium
(2022-23 Medium)

Page 15

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
• Four risks covering utility costs, the IJB referring to Council for additional
funding, Council Tax Income and a general inflationary risk have been
categorised as possible with a combined assessed financial impact of
£3.408m; and 
• The risk of a shortfall in savings options being delivered fully has been
categorised as unlikely with an assessed financial impact of £0.013m. 
Funding Risks The Scottish Budget was announced on 15 December 2022 and the finance
circular with the local authority allocations issued on 20 December 2022.   
The other element of funding is Council Tax.  There is a proposed increase
to Council Tax of 4.33%.  Collection rates have been negatively impacted by
the ongoing cost of living crisis affecting households with high levels of
inflation caused by the long term effects on the UK economy of the COVID-
19 pandemic, Brexit and the ongoing conflict in Ukraine. 
In May 2022 the Scottish Government published the Investing in Scotland’s
Future: Resource Spending Review which was intended to provide a guide
to the Scottish Government’s funding envelope over the period 2022/23 to
2026/27. For local Government, the review suggested that funding for local
government would be on a flat cash basis until at least 2025/26. Given the
ongoing significant impact of high inflation on local government costs, a flat
cash position means a real terms reduction in the spending power of
Councils and, subsequently, the Council is likely to continue to have make
challenging decisions about service delivery in order to stay within its future
budgets. 
Medium/High
(2022-23 Medium/High)

Page 16

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
The Scottish Government undertook a Capital Spending Review in 2020-21
which provided an outline five-year indicative allocation for general capital
grant. It suggested that the settlement in 2021-22 would remain constant
until 2025-26 therefore this was used as the basis for funding the Capital
Programme over the next five years. However, there has been some
variation in 2022/23 (less than the 2021/22 baseline by £0.027m) and
2023/24 (more than the 2021/22 baseline by £0.020m) which creates some
uncertainty regarding future funding allocations, however these variations
have been minimal. 
As a result of all issues noted above, this risk has been kept as
Medium/High. 
Savings Risks The Council agreed to a number of management/operational and policy
savings as part of previous budgets that would deliver an additional £0.151m
of savings in 2023-24.  There are also further savings proposals amounting
to £9.426m for 2023-24 which includes £4.831m arising from new service
concession arrangements for NPDO schools, which is guaranteed to be
delivered, leaving a balance of £4.595m to be delivered by services. The
Council has a good track record on delivering savings options but due to the
value of savings to be achieved, the risk is increased to Medium. 
Medium
(2022-23 Low/Medium) 
Inflation Rates Between November 2021 and November 2022, CPI inflation has increased
by 10.7%.  The volatile evolution of price pressures has occurred due to
soaring energy prices, triggered in large part by the war in Ukraine, coupled
with rising interest rates and global supply chain bottlenecks. 
The Bank of England Monetary Policy Committee reported in November
2022 that the Bank expects inflation (CPI) to reduce during 2023/24 to
Medium/High
(2022-23 High)

Page 17

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
around 4% by the 1st quarter of 2024. However, the forecast suggests that
the pace of the reduction is likely to be slow with the most significant
reduction not forecast until late 2023. 
Given the volatility of inflation levels in the last year and the ongoing
challenges facing the UK economy it would be prudent to consider a level of
inflation over above and the unavoidable/ inescapable provision and a
general 2% inflation has been included within the worst case scenario for
2023-24 onwards (of £800k per annum).  For 2023-24, despite the overall
rate of inflation being forecast to reduce over the year, officers expect that
inflationary pressures on utility costs will continue to be a point of financial
pressure throughout the year and Finance staff will work in conjunction with
colleagues in Property Services to monitor the situation very closely. 
Interest Rates The Council has a large proportion of its borrowing secured at fixed rates
which reduces the risk to increases in interest rates. Borrowing is being
managed to reduce where possible surplus cash available for investment
subject to working capital/cash flow requirements. 
Surplus funds are invested and although investment returns have increased
in 2022/23, the Council return is currently below the target SONIA rate but
this is due to market fluidity and is not a regular occurrence. Current
forecasts of interest rates are based on advice from our treasury advisors.
Current investment rates are forecast to improve as interest rates increase –
assuming no change in direction by the Bank of England – and the Council
will continue to look for the best rates of return for new investments. 
Low
(2022-23 Low) 
Financial risks The Council has managed surplus funds invested to reduce exposure to
risks associated with money market deposits. It retains a working balance of
Low
(2022-23 Low)

Page 18

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
£10m to meet cash flow needs. Investments are managed based on the
credit worthiness of agreed counterparties based on credit scores of
recognised agencies. This should avoid having to borrow in an unplanned
way from the money markets. 
Strategic risks The strategic risk register is subject to a formal review by SMT bi-annually,
and these reviews have already taken place in April and October of 2022.  
SMT have agreed the current actions to address the risks. 
Medium
(2022-23 Medium)
Operational risks Operational risks are reviewed formally each quarter by Departmental
Management Teams.  Any operational risks that are identified as high are
reported to the Strategic Management Team as part of the bi-annual review
of the Strategic Risk Register.  
Medium
(2022-23 Medium)
Impact of UK
withdrawal from the
EU
On the 31st December 2020, with the Transition Period concluding, EU Law
jurisdiction in the UK, and access to the EU Single Market ended. The UK-
EU Trade Cooperation Agreement (TCA) agreed on 24th December 2020
and ratified by the UK Parliament on 30th December (European Union
(Future Relationship) Act 2020) covered the most urgent matters. 
While it is not easy to disentangle the impact of EU Exit, COVID-19 and the
situation in Ukraine, it is clear that the local Argyll and Bute economy has
witnessed the anticipated impacts from the trade friction caused by replacing
membership of the EU Single Market and Customs Union with a relatively
narrowly drawn Free Trade Agreement.
The UK Government has decided to further delay some elements of the new
import controls into 2023. These delays have exacerbated uncertainty in
terms of the future impact of import control measures on food supply chains
Medium/High
(2022-23 Medium/High)

Page 19

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
and what that will mean for Argyll and Bute in terms of the ongoing recovery
of agri-food sector. 
A major concern at present is the skills gaps and recruitment challenges
faced by a number of sectors, such as hospitality, care and construction,
which are of key importance to the Argyll and Bute economy and
communities. This is further exacerbated by the cost of living crisis for many
residents and communities, coupled with a cost of doing business crisis, due
to the significant and spiralling inflationary cost pressures and availability of
goods and labour, which has been a direct impact from EU Exit as well as
the unrest in the external environment. 
On this basis, the overall risk assessment is still Medium/High. 
General financial
climate
The finance settlement only covers 2023-24 and the Scottish Government is
still to meet its commitment to provide a three year settlement.  A prudent
approach to estimating income from council tax has been taken. Risks
arising from inflation, interest rates, cost pressures and demand led
pressures have been outlined above. 
Due to ongoing uncertainties associated with the UK’s withdrawal from the
EU, the potential medium to longer term impact of COVID-19 and high
inflation and interest levels on the economy it would be prudent to retain this
risk to medium/high. 
Medium/High
(2022-23 Medium/High) 
Availability of
contingency funds
The Council currently has sufficient contingency funds to meet its target.  Low
(2022-23 Low)

Page 20

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
Overall financial
standing 
The Council has managed to achieve its contingency target in previous
years. Actual costs are normally contained within budget.  Borrowing costs
are largely fixed at the moment, as the Council’s need to borrow is currently
very low due to the high levels of funds it is holding, and improvements in
the rates of return for the investments made by the Treasury team are
generating better than budgeted returns with the surplus funds generated
supporting the Council’s overall financial position.. In addition to the
contingency there are significant earmarked funds. Cost and demand
pressures are identified and provided for if necessary and the impacts of
inflationary changes are continually monitored and adjusted for in the
Council’s financial forecasts   
Low/Medium
(2022-23 Low/Medium) 
Track record in
budget
management
The Council has a good track record of containing expenditure within
budget. The Council is on track to contain costs within budget for 2022-23
however the Social Work element of the Health and Social Care Partnership
is forecasting a modest overspend, however, this is expected to be
managed within the Health and Social Care Partnership. 
Low
(2022-23 Low) 
Financial
information and
reporting
arrangements
Revenue and capital budgets are monitored on a monthly basis with budget
allocated to responsible managers. A risk based approach is taken to budget
monitoring and the budget monitoring process is continually being reviewed
to identify ongoing improvements. 
Low/Medium
(2022-23 Low/Medium) 
Insurance cover The Council has adequate insurance cover. Low
(2022-23 Low) 
Internal controls The statement of internal controls identifies a generally adequate control
framework although there are areas for improvement. An audit plan is
approved and delivered each year to monitor internal controls. The Council’s
Low/Medium
(2022-23 Low/Medium)

Page 21

Risk Assessment for Review of Reserves
Risk Category Comment Assessment
Audit and Scrutiny Committee continues to actively develop and adopt good
practice. 
Health and Social
Care Partnership
Financial Position
It is prudent to have a factor in terms of the Health and Social Care
Partnership financial position.  If there is an overspend within Social Work,
that cannot be funded by IJB reserves or by an underspend by the other
partner body, then the Council will require to give an additional payment. 
Any additional payment would require to be paid back to the Council in the
future.  As part of the Council’s risk analysis we have reported a risk of £1m
to the Council in 2023-24. The risk factor remains at Medium at this stage.   
Medium
(2022-23 Medium)