ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 22 FEBRUARY 2024
UPDATES TO BUDGET PACK  
1. EXECUTIVE SUMMARY 
1.1 This report provides updates to the Council budget pack since it was
published on 8 February 2024. 
1.2  The updates to the pack are summarised as follows:
 Changes to Scottish Government funding, following the
publication of the Draft Local Government Finance Order on 8
February, with information not received until 13 February 2024. 
 LEIP.
 HSCP access to Strathclyde Pension Fund Gain.
 A new funding request from MacTaggart Leisure Centre.
 An update to recommendations within the Budget Pack. 
1.3 Following the publication of the Draft Local Government Finance Order
on 8 February, information was provided on 13 February 2024 with detail
of the changes to the provisional financial settlement that was published
on 21 December 2023.  The General Revenue Grant has increased by
£3.328m and whilst there are a number of reasons for this increase the
bottom line impact on the Council’s revenue budget is an overall
reduction of £0.065m due to distribution changes.     
1.4 Other changes to the provisional finance settlement include:
£2.125m of Teacher funding now being distributed via specific grant. 
£4.270m provided for Carers Service, Respite Care and Living Wage
£0.030m provided for Scottish Disability Assistance
£0.986m provided for Discretionary Housing Payments
£0.232m provided for Early Learning and Childcare expansion. 
1.5 The payment to the HSCP will increase from £74.326m (as outlined in the
budget pack) to £78.611m after the new monies are passed through to
the HSCP as detailed in paragraph 3.1.4. 
1.6 In order to balance the budget the increase to Council Tax would need
to be 6.15% after accounting for the distribution changes.   
1.7 The change in the potential Scottish Government contribution to LEIP,
as outlined in section 3.2 of this report, has significant financial
implications for the Council in terms of the financial commitment that
would be required for the project to progress.  On that basis, further work
is required on potential financial models for the project and it is proposed
that a further report with more detail regarding the financial aspects of

Page 2

LEIP be the subject of a Members Seminar and then brought to the
Council meeting in April 2024 for Member’s consideration. 
1.8 The recommendation in respect of the HSCP accessing the gain
received from the reduction in the Strathclyde Pension Fund Employer’s
Contribution rate between 17.5% and 6.5% requires to be amended. 
Following a conversation with the HSCP Chief Financial Officer, the
HSCP are looking to access up to £1m of this gain towards balancing
their revenue budget in 2024-25 (this is not dissimilar to the Council
proposals).  As such, the recommendation needs amended as the
wording, as it stands, only permits access to the Fund for
transformational/spend to save projects. 
1.9 A further funding request was received from MacTaggart Leisure Centre
on 9 February 2024 asking for £30,000. 
1.10 Updated recommendations: 
a) Approve the revenue estimates for 2024-25 and that consequently
the local tax requirement estimated at £63.179m is funded from
Council Tax.  Approve the following rates and charges for the year,
2024-25: 
1. Council Tax to be paid in respect of a chargeable dwelling in
Band “D” of £1,570.17 representing a 6.15% increase.
2. Council Tax to be paid in respect of a chargeable dwelling in
each of the other valuation bands in accordance with Section
74(1) of the Local Government Finance Act 1992 as amended.
3. Business Rates as determined by Scottish Ministers. 
c) In respect of the gain received from the reduction in the Strathclyde
Pension Employer’s Contribution rate between 17.5% and 6.5% over
2024-25 and 2025-26:  
1. Note that £2m is proposed to be used towards the Council
revenue budget each year over the next 4 years (see
management/ operational savings).  
2. Agree that the balance remaining attributable to all Council
employees is transferred to the General Fund and set aside
for transformational/spend to save projects.   
3. Agree that HSCP projects that fit the above criteria (point 2
above), or if the HSCP need any funds to balance their budget
within 2024-25, be eligible for funding up to the value of
£6.106m with the release of any funding delegated to the
Chief Executive and the Executive Directors of the Council in
consultation with the Leader, Depute Leader, Leader of the
largest Opposition Group and Policy Lead for Health and
Social Care. 
4. Note that reports on the drawdowns from the General Fund
balance will be submitted to Policy and Resources Committee
as part of the monitoring pack.

Page 3

d) Approve a base allocation to the Health and Social Care Partnership
of £78.611m for 2024-25.  Approve indicative base allocations for
2025-26 of £78.611m and 2026-27 of £81.664m.  The level of future
years funding is subject to the level of Scottish Government funding
and the Council’s overall financial position in future years. 
f) Consider the six funding requests received as set out within
Appendix 8 of the Revenue Budget Overview Report and within this
supplementary report. 
i) Approve the contingency level for the General Fund balance at a
level of 2% of net expenditure, equivalent to £6.188m and note the
report on reserves and balances. 
k) In respect of LEIP: 
1. Note the successful award of a major bid funding bid.
2. Note the funding provided by Scottish Government is not a
capital grant for full cost of project – in summary SG will provide
up to 50% of eligible costs over a 25 year period following
completion.  The Council will require to pay the total cost up
front.
3. Note due to the 1 year time delay of LEIP announcement the
requirement to open the new Campus by December 2027
(which was the original timescale) cannot be met – now forecast
for October 2028 at earliest.
4. Note the updated timescale programme forecast as outlined at
Appendix A + B.
5. Agree in the light of the update on funding that no decision as
to whether or not to proceed be taken at this time and that
officers prepare a further report with more detail regarding the
financial aspects of LEIP to be the subject of a Members
Seminar and then brought to the Council meeting in April 2024
for Member’s consideration.

Page 4

ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 22 FEBRUARY 2024
UPDATES TO BUDGET PACK  
2. INTRODUCTION 
2.1 This report provides updates to the Council budgeting pack since it was
published on 8 February 2024. 
3. DETAIL 
3.1 Updated Funding Information 
3.1.1 Following the publication of the Draft Local Government Finance Order
on 8 February, information was provided on 13 February 2024 with
detail of the changes to the provisional financial settlement that was
published on 21 December 2023.   
3.1.2 The General Revenue Grant (GRG) has increased by £3.328m as
outlined in the following table: 
Category Funding
Increase /
(Decrease)
£000
Impact on Budget
Teachers (2,125) No bottom line impact as
GRG funding now moved
to Specific Grant (see para
3.1.3 for further info).
Carers Service,
Respite Care and
Living Wage
4,270 No bottom line impact as
this funding has to be
passed over to the HSCP
(see para 3.1.4)
Scottish Disability
Assistance
30 No bottom line impact as
50% of this funding will be
passed over to HSCP and
50% spent within
Education (see para 3.1.4)
Discretionary
Housing Payments
986 No bottom line impact as a
corresponding expenditure
budget is required. 
Early Learning and
Childcare Expansion
232 No bottom line impact as a
corresponding expenditure
budget is required to
deliver on this
commitment.

Page 5

Other small changes
across various
distribution lines
(65) Reduction will increase
budget gap by £65k and
per the model in the
budget pack Council Tax
would have to increase to
6.15% to balance the
budget (see para 3.1.5).
Total 3,328 
3.1.3 The Scottish Government have now advised that £145.5m of funding in
relation to teacher numbers will be distributed via a Specific Grant and
will be conditional on Councils agreeing to maintain teachers numbers. 
This amounts to £2.125m for Argyll and Bute Council and there is a risk
that the Scottish Government withhold some of the funding following the
teachers census later in the year. 
3.1.4 As a result of the additional funding now distributed in the Draft Finance
Order, the payment to HSCP will increase by £4.285m to £78.611m in
2024-25 as noted below:   
 £230m of funding for the Carers Service, Respite Care and Living
Wage has now been distributed of which our share of £4.270m
and this is a straight pass through to the HSCP.
 Scottish Disability funding of £3.449m has also now been
distributed of which our share is £0.030m. This is split 50/50 with
Education therefore £0.015m should be passed to the HSCP. 
Draft
2024-25
£000
Mid-
Range 
2025-26
£000
Mid-
Range 
2026-27
£000
Mid-
Range 
2027-28
£000
Mid-
Range 
2028-29
£000
Payment to
HSCP as
reported in
budget pack
74,326 74,326 77,379 77,379 77,379
Carers Service
and Respite
Care
4,270 4,270 4,270 4,270 4,270
Scottish
Disability
Funding
15 15 15 15 15
Updated
Payment to
HSCP
78,611 78,611 81,664 81,664 81,664 
3.1.5  The change to the budget gap as a result of the Draft Finance Order is a
reduction of £0.065m due to distribution changes.  As outlined in
paragraph 3.10.2 of the Revenue Budget Overview report in the budget
pack, in order to balance the budget Council could consider rejecting
the Council Tax Freeze and increasing Council Tax to balance the

Page 6

budget.  The increase to Council Tax would need to be 6.15% after
accounting for this distribution change.   
3.1.6 As a result of the changes in the paragraphs above, Appendix 7 to the
Revenue Budget Overview has been updated and is now attached as
Appendix 2. 
3.2 LEIP 
3.2.1 Members require to have sufficient information to allow them to take an
informed decision in respect of the LEIP project.  The position is
continually evolving. 
3.2.2 In the budget pack, it was noted that the funding offered by the Scottish
Government is not a grant nor is it for the full cost of the building.  It will
cover up to 50% of eligible costs and this will be paid over a 25 year
period, which means the Council has to fund at least 50% of the project
costs.  The entire design, land acquisition (if required) and build costs
will require to be met up front by the Council and the Council will require
to borrow.  The Scottish Government do not contribute to the cost of
servicing borrowing and as this cost will have to be paid by the Council
the Council’s overall share of the total cost of the project will be much
higher than 50%.   
3.2.3 The Scottish Futures Trust (SFT) advised in correspondence this week
that in some cases from LEIP 1 and 2 the contribution could be as low
as 35% and we are now aware of two Councils from the earlier stages
of LEIP who received a 37% contribution and a 43% contribution. 
Multiple factors impact on this including being higher / lower than
metrics, uses / function and abnormal costs depending on site.  No
deals have been struck at LEIP 3 yet so there is no direct comparable
evidence on current programme so far, particularly in an island location. 
SFT have advised for a project on Mull, based the project outline at this
stage, a contribution in the range of 40-45% would be a reasonable
forecast.   
3.2.4 This change in circumstances obviously has significant financial
implications for the Council in terms of the financial commitment that
would be required for the project to progress.  On that basis, further
work is required on potential financial models for the project and it is
proposed that a further report with more detail regarding the financial
aspects of LEIP be the subject of a Members Seminar and then brought
to the Council meeting in April 2024 for Member’s consideration. 
3.3 HSCP Access to Strathclyde Pension Fund Gain 
3.3.1 The recommendation in respect of the HSCP accessing the gain
received from the reduction in the Strathclyde Pension Fund Employer’s
Contribution rate between 17.5% and 6.5% require to be amended. 
Following a conversation with the HSCP Chief Financial Officer, the
HSCP are looking to access up to £1m of this gain towards balancing

Page 7

their revenue budget in 2024-25 (this is not dissimilar to the Council
proposals).  As such, the recommendation needs amended as the
wording as it stands only permits access to the Fund for
transformational/spend to save projects. 
3.4 New External Funding Request 
MacTaggart Leisure Centre (Islay) 
3.4.1 A further funding request was received from MacTaggart Leisure Centre
on 9 February 2024.  Rising costs with inflation has left the organisation
really unsure and concerned as to what lies ahead for the Centre.  At
the moment the financial situation of the Centre is very worrying with an
estimated £50k shortfall this year.  This would have been the case last
year had they not received the extra support/funding from Argyll and
Bute Council.  Due to the unprecedented rising costs last year the
additional £30k extra over and above our Service Level Agreement, was
a saving grace to the financial worries and implications that the Centre
were facing.  The same issues have arisen this year (actually worse, as
costs keeps rising).  With the budget meeting ahead, the Centre wanted
to make Council aware of the financial crisis they are going through and
how this extra funding would help in keeping the Centre open.   
3.4.2 The request is for 1 year funding of £30,000.  Members are asked to
give consideration to this request and how it would be funded. 
3.5 Update to Recommendations within Budget Pack 
3.5.1 The issues raised above require the recommendations noted within the
introductory report on pages 8 to 10 of the budgeting pack to be updated. 
The recommendations that require update are recommendation (a),
recommendation (c), recommendation (d), recommendation (f),
recommendation (i) and recommendation (k).  A full set of revised
recommendations is included in Appendix 1. 
Updated recommendations: 
a) Approve the revenue estimates for 2024-25 and that consequently
the local tax requirement estimated at £63.179m is funded from
Council Tax.  Approve the following rates and charges for the year,
2024-25: 
1. Council Tax to be paid in respect of a chargeable dwelling in
Band “D” of £1,570.17 representing a 6.15% increase.
2. Council Tax to be paid in respect of a chargeable dwelling in
each of the other valuation bands in accordance with Section
74(1) of the Local Government Finance Act 1992 as amended.
3. Business Rates as determined by Scottish Ministers.

Page 8

c) In respect of the gain received from the reduction in the Strathclyde
Pension Employer’s Contribution rate between 17.5% and 6.5% over
2024-25 and 2025-26:  
1. Note that £2m is proposed to be used towards the Council
revenue budget each year over the next 4 years (see
management/ operational savings).  
2. Agree that the balance remaining attributable to all Council
employees is transferred to the General Fund and set aside
for transformational/spend to save projects.   
3. Agree that HSCP projects that fit the above criteria (point 2
above), or if the HSCP need any funds to balance their
budget within 2024-25, be eligible for funding up to the value
of £6.106m with the release of any funding delegated to the
Chief Executive and the Executive Directors of the Council in
consultation with the Leader, Depute Leader, Leader of the
largest Opposition Group and Policy Lead for Health and
Social Care.
4. Note that reports on the drawdowns from the General Fund
balance will be submitted to Policy and Resources Committee
as part of the monitoring pack.   
d) Approve a base allocation to the Health and Social Care Partnership
of £78.611m for 2024-25.  Approve indicative base allocations for
2025-26 of £78.611m and 2026-27 of £81.664m.  The level of future
years funding is subject to the level of Scottish Government funding
and the Council’s overall financial position in future years. 
f) Consider the six funding requests received as set out within
Appendix 8 of the Revenue Budget Overview Report and within this
supplementary report. 
i) Approve the contingency level for the General Fund balance at a
level of 2% of net expenditure, equivalent to £6.188m and note the
report on reserves and balances. 
k) In respect of LEIP: 
1. Note the successful award of a major bid funding bid.
2. Note the funding provided by Scottish Government is not a capital
grant for full cost of project – in summary SG will provide up to
50% of eligible costs over a 25 year period following completion. 
The Council will require to pay the total cost up front.
3. Note due to the 1 year time delay of LEIP announcement the
requirement to open the new Campus by December 2027 (which
was the original timescale) cannot be met – now forecast for
October 2028 at earliest.
4. Note the updated timescale programme forecast as outlined at
Appendix A + B.
5. Agree in the light of the update on funding that no decision as to
whether or not to proceed be taken at this time and that officers

Page 9

prepare a further report with more detail regarding the financial
aspects of LEIP to be the subject of a Members Seminar and then
brought to the Council meeting in April 2024 for Member’s
consideration. 
4. CONCLUSION 
4.1 This report provides updates to the Council budgeting pack since it was
published on 8 February 2024. 
4.2 As a result of the issues raised, there are updates to 6 of the
recommendations noted within the introductory report on pages 8 to 10
of the budget pack. 
5. IMPLICATIONS 
5.1 Policy – None from this report. 
5.2 Financial – The report provides an update to the budget pack published
on 8 February 2024.  The change in funding has resulted in an increase
to the budget gap of £0.065m.   
5.3 Legal – Any legal implications in respect of LEIP will be considered as
part of the report to Council in April 2024, if required. 
5.4 HR – None from this report. 
5.5 Fairer Scotland Duty – See below 
5.5.1 Equalities – Equality and Socio-Economic Impact Assessments in
respect of LEIP will be considered as part of the report to Council in
April 2024 if required. 
5.5.2 Socio Economic Duty – Equality and Socio-Economic Impact
Assessments in respect of LEIP will be considered as part of the report
to Council in April 2024 if required. 
5.5.3 Islands Duty - Equality and Socio-Economic Impact Assessments in
respect of LEIP will be considered as part of the report to Council in
April 2024 if required. 
5.6 Climate Change – The Council is committed to addressing climate
change and reviews of how Services are delivered is ongoing within the
available budget resources. 
5.7 Risk – There is a separate report on risks in the budget pack.  There is
a risk that the Scottish Government withhold some of the specific grant
funding following the teachers census later in the year.    
5.8 Customer Service – None from this report. 
5.9 The Rights of the Child (UNCRC) – None.

Page 10

Kirsty Flanagan
Executive Director /Section 95 Officer
16 February 2024 
Policy Lead for Finance and Commercial Services:  Councillor Gary Mulvaney 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk
Appendix 1 – Full Set of Amended Recommendations. 
Appendix 2 – Revised Appendix 7 to Revenue Budget Overview Report

Page 11

APPENDIX 1 – Full Set of Amended Recommendations 
It is recommended that the Council: 
a) Approve the revenue estimates for 2024-25 and that consequently the local
tax requirement estimated at £63.179m is funded from Council Tax.  Approve
the following rates and charges for the year, 2024-25: 
1. Council Tax to be paid in respect of a chargeable dwelling in Band “D”
of £1,570.17 representing a 6.15% increase.
2. Council Tax to be paid in respect of a chargeable dwelling in each of
the other valuation bands in accordance with Section 74(1) of the Local
Government Finance Act 1992 as amended.
3. Business Rates as determined by Scottish Ministers. 
b) Approve the revenue budget for 2024-25 as set out in the revenue budget
overview report. 
c) In respect of the gain received from the reduction in the Strathclyde Pension
Employer’s Contribution rate between 17.5% and 6.5% over 2024-25 and
2025-26:  
1. Note that £2m is proposed to be used towards the Council revenue
budget each year over the next 4 years (see management/ operational
savings).  
2. Agree that the balance remaining attributable to all Council employees
is transferred to the General Fund and set aside for
transformational/spend to save projects.   
3. Agree that HSCP projects that fit the above criteria (point 2 above), or if
the HSCP need any funds to balance their budget within 2024-25, be
eligible for funding up to the value of £6.106m with the release of any
funding delegated to the Chief Executive and the Executive Directors of
the Council in consultation with the Leader, Depute Leader, Leader of
the largest Opposition Group and Policy Lead for Health and Social
Care.
4. Note that reports on the drawdowns from the General Fund balance will
be submitted to Policy and Resources Committee as part of the
monitoring pack.   
d) Approve a base allocation to the Health and Social Care Partnership of
£78.611m for 2024-25.  Approve indicative base allocations for 2025-26 of
£78.611m and 2026-27 of £81.664m.  The level of future years funding is
subject to the level of Scottish Government funding and the Council’s overall
financial position in future years. 
e) Endorse the new management/operational savings as outlined in Appendix 5
of the revenue budget overview report and approve the policy savings options
as outlined in Appendix 6 of the revenue budget overview report.

Page 12

f) Consider the six funding requests received as set out within Appendix 8 of the
Revenue Budget Overview Report.  
g) Approve the following in relation to fees and charges with effect from 1 April
2024 unless otherwise noted: 
1. Approve the proposals for the fees and charges inflationary increase of
6% and approve the charges that are over and above inflation.  Note
that this would generate additional income of £0.385m in total.   
2. Approve no increase to school meal charges in 2023-24 as detailed in
section 3.6.2 of the Fees and Charges report.
3. Approve the changes proposed to the Social Work fees and charges.
4. Approve all other charges as noted within the Fees and Charges
Schedule. 
h) Note the financial risks analysis. 
i) Approve the contingency level for the General Fund balance at a level of 2%
of net expenditure, equivalent to £6.188m and note the report on reserves and
balances. 
j) Approve the capital plan as set out in Appendix 3 of the capital plan summary
report, noting that consideration needs to be given as to how to fund the
£29.384m gap. 
k) In respect of LEIP: 
1. Note the successful award of a major bid funding bid.
2. Note the funding provided by Scottish Government is not a capital grant for
full cost of project – in summary SG will provide up to 50% of eligible costs
over a 25 year period following completion.  The Council will require to pay
the total cost up front. 
3. Note due to the 1year time delay of LEIP announcement the requirement
to open the new Campus by December 2027 (which was the original
timescale) cannot be met – now forecast for October 2028 at earliest.
4. Note the updated timescale programme forecast as outlined at Appendix A
+ B.
5. Agree in the light of the update on funding that no decision as to whether
or not to proceed be taken at this time and that officers prepare a further
report with more detail regarding the financial aspects of LEIP to be the
subject of a Members Seminar and then brought to the Council meeting in
April 2024 for Member’s consideration. 
l) In respect of Rothesay Pavilion note that a further paper will be available for
Members at the Special Meeting of the Council prior to the budget meeting

Page 13

which will provide detailed information on the project and recommendations
for consideration.    
m) Approve the Corporate Asset Management Strategy and Plan including the
Asset Group Summaries.

Page 14

APPENDIX 2 (PREVIOUSLY APPENDIX 7 TO THE REVENUE BUDGET OVERVIEW REPORT)
SERVICE SUMMARY OF BUDGET POSITION 2024-25
Department Service 2023-24
Budget
Other Base
Budget
Adjustments
Settlement
Commitments
Updated
Base Budget
Employee
Budget
Changes
Non-Pay
Inflation -
Inescapable
Cost and
Demand
Pressures
Live Argyll
Management
Fee
Adjustment
Measures to
Balance the
Budget
Social Work
Pressures
Absorbed by
HSCP
Finance
Order
Updates
2024-25 Draft
Budget
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Council Departments:
Chief Executive's Unit Chief Executive 922 33 0 955 40 0 0 0 (104) 0 0 891
Executive Director (Douglas Hendry) Executive Director (Douglas Hendry) 41 14 0 55 (26) 0 0 0 0 0 0 29
Executive Director (Douglas Hendry) Head of Commercial Services 11,689 431 0 12,120 (630) 552 115 (363) (291) 0 0 11,503
Executive Director (Douglas Hendry) Head of Education 99,573 4,288 7,634 111,495 1,882 680 525 0 (206) 0 (1,878) 112,498
Executive Director (Douglas Hendry) Head of Legal and Regulatory
Support
15,651 141 0 15,792 (332) 658 480 0 (92) 0 0 16,506
Executive Director (Kirsty Flanagan) Executive Director (Kirsty Flanagan) (410) 12 0 (398) (15) 0 0 0 0 0 0 (413)
Executive Director (Kirsty Flanagan) Head of Customer Support Services 9,004 30 0 9,034 (418) 131 63 0 (15) 0 0 8,795
Executive Director (Kirsty Flanagan) Head of Development and Economic
Growth
7,911 579 0 8,490 (626) 18 140 0 (216) 0 0 7,806
Executive Director (Kirsty Flanagan) Head of Financial Services 5,711 (56) 0 5,655 (328) 35 353 0 (25) 0 986 6,676
Executive Director (Kirsty Flanagan) Head of Roads and Infrastructure
Services
32,022 954 0 32,976 (1,249) 697 1,175 0 (546) 0 0 33,053
Non Departmental:
Joint Boards Joint Boards 1,496 0 0 1,496 0 61 0 0 0 0 0 1,557
Other Operating Income & Expenditure Elected Members 1,261 0 0 1,261 (62) 0 0 0 0 0 0 1,199
Other Operating Income & Expenditure Sundry Services 2,325 (464) 0 1,861 0 425 0 0 (1,594) 0 0 692
Other Operating Income & Expenditure Unfunded Pensions 1,554 0 0 1,554 0 0 0 0 0 0 0 1,554
Non Controllable Costs:
Insurances 1,768 0 0 1,768 0 95 126 0 0 0 0 1,989
Non Domestic Rates 5,095 0 0 5,095 0 0 0 0 0 0 0 5,095
Apprenticeship Levy (Council) 545 22 0 567 46 0 0 0 0 0 0 613
Capital Charges (loans charges) 12,125 685 0 12,810 0 0 18 0 0 0 0 12,828
COUNCIL TOTAL 208,283 6,669 7,634 222,586 (1,718) 3,352 2,995 (363) (3,089) 0 (892) 222,871
Health and Social Care Partnership:
Social Work Chief Officer (704) 14 (35) (725) (28) 0 0 0 0 (1,929) 4,285 1,603
Social Work Acute and Complex Care 20,216 161 0 20,377 (342) 0 0 0 0 0 0 20,035
Social Work Children & Families 16,718 395 207 17,320 (828) 0 0 0 0 0 0 16,492
Social Work Health and Community Care 39,516 555 295 40,366 (374) 0 0 0 0 0 0 39,992
Social Work Strategic Planning and Performance 507 15 0 522 (33) 0 0 0 0 0 0 489
SOCIAL WORK TOTAL 76,253 1,140 467 77,860 (1,605) 0 0 0 0 (1,929) 4,285 78,611
Rounding (1)
TOTAL 284,536 7,809 8,101 300,446 (3,323) 3,352 2,995 (363) (3,089) (1,929) 3,393 301,481
Funding:
Scottish Government Funding 242,230
Council Tax Income 67,179
Balance to reserves - Council (6,875 one off pension saving less 2,000 released for 24-25) (4,875)
Social Work - one off pension saving to be held in Council reserves (3,053)
OVERALL FUNDING SURPLUS / (GAP) 0