ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 22 FEBRUARY 2024
CAPITAL PLAN SUMMARY REPORT 
1. EXECUTIVE SUMMARY 
1.1  This report details the revisions proposed to the capital plan approved in
February 2023 for the period 2024-25 to 2025-26 and extends the capital plan
for a further year to 2026-27. The revisions are based on updated capital funding
assumptions, phasing and cost changes. 
1.2 The Council has experienced a reduction in the level of its General Capital Grant
settlement over the last five years, falling from £12.262m in 2019-20 to £8.834m
in 2024-25 which has put significant pressure on the ability to deliver the capital
programme. This pressure is amplified further by the impact of the COVID-19
pandemic along with the UK exit from the European Union, the Russian invasion
of Ukraine and sanctions on Russian owned entities which have resulted in
significant price increases as well as disruptions to the supply chain and longer
lead in times. These all have an effect on the overall contract price and make it
extremely challenging to manage expenditure and the availability of supply
across the life of the programme. 
1.3 In February 2023 the Council approved estimated capital grant settlements for
2024-25 and 2025-26 of £9.771m to reflect what was actually received in 2023-
24. This estimation was based on the Capital Spending Review undertaken by
Scottish Government which advised that the capital settlements were likely to
stay constant over the next five years. 
1.4 The settlement received for 2024-25, excluding any ring-fenced funding, was
£8.834m therefore £0.937m less than anticipated. However the 2023-24 final
settlement was £0.046m higher than budgeted for within the capital programme
therefore this can offset the £0.937m reduction resulting in a funding gap of
£0.891m each year. This equates to a decrease across the already approved
capital programme of £1.782m for 2024-25 and 2025-26 combined.  
1.5  In addition to the £8.834m general capital grant there is ring-fenced funding of
£0.379m for Walking Cycling & Safer Streets which will also be built into the
capital programme. 
1.6 The amount of capital resources allocated to Private Sector Housing Grant
(PSHG) is £1.033m per annum, similar to previous years. However, it should be
noted that the amount received from Scottish Government in relation to this is
only £0.941m therefore an additional allocation of £0.276m over the three year
capital programme is passed to Private Sector Housing Grants.   
1.7 Restricted capital funding of £5.122m is noted within Appendix 2.  This relates to
income which is restricted to specific projects and has been matched with
expenditure against the project, thereby showing the gross cost of the project.

Page 2

1.8 The capital plan as at December 2023, including the new block allocation for
2026-27, has been compared to the estimated funding and there is a gap up to
2026-27 of £2.076m. After adjusting for the anticipated shortfalls and cost
pressures as detailed within section 3.5 of this report, the total gap within the
capital programme is £29.843m.

Page 3

ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES                                          22 FEBRUARY 2024
CAPITAL PLAN SUMMARY REPORT 
2. INTRODUCTION 
2.1  This report details the revisions proposed to the capital plan approved in
February 2023 for the period 2024-25 to 2025-26 and extends the capital plan
for a further year to 2026-27. The revisions are based on updated capital
funding assumptions, phasing and cost changes. 
3. DETAIL 
3.1 Estimated Capital Funding 2024-25 to 2026-27 
3.1.1 Funding for the capital plan comes from the Scottish Government (General
Capital Grant and Specific Ring-Fenced Capital Grants), other capital grants,
capital receipts from asset disposals, revenue contributions to capital,
prudential borrowing and borrowing funded by the loan charges provision in the
revenue budget. 
3.1.2 The Local Government Finance Circular published on 19 December 2023
provides detail of the provisional total capital funding allocations for 2024-25.
The provisional total funding allocations form the basis for the annual
consultation between the Scottish Government and COSLA ahead of the Local
Government Finance (Scotland) Order 2024 presented to the Scottish
Parliament.  The Finance Order is due to be laid in Parliament on 7 February
with Stages 1-3 between 8 February and 27 February with the Finance Order
Debate taking place on 28 February.   
3.1.3 The General Capital Grant allocation for 2024-25, excluding any ring-fenced
funding amounts to £8.834m which includes a general capital grant flooding
allocation of £0.156m.   
3.1.4 The estimated General Capital Grant for 2026-27 is based on the 2024-25
settlement of £8.834m therefore comparing this to the settlement for 2023-24,
and again taking into account the flooding allocation of £0.156m, this results in
a decrease of £0.891m in 2026-27. The Scottish Government had previously
advised that the indicative General Capital Grant settlements up to 2025-26
would remain constant at the same level as the 2021-22 settlement, however
the settlement for 2024-25 has proven this not to be the case. 
3.1.5  The amount of capital resources allocated to Private Sector Housing Grant
(PSHG) is £1.033m per annum.  This amount has remained at the same level
since 2016-17. The settlement from the Scottish Government includes an
allocation of £0.941m for Private Sector Housing therefore £0.092m less each
year than what is currently built in to the budget position. To reduce the
allocation by £0.092m each year would result in a saving of £0.276m across the

Page 4

three year capital programme. Members may wish to review the amount
allocated to PSHG. 
3.1.6 As part of the revision to the funding assumptions for the capital plan, a detailed
review of anticipated capital receipts has been undertaken by Commercial
Services. During 2023-24 the level of capital receipts has fallen below what was
estimated which has an impact on the funding of the capital programme.
However, adding on the anticipated capital receipts for 2026-27 there is an
estimated overall increase in sales income across the capital programme of
£0.499m. The estimated level of receipts will be kept under review as market
conditions change, as will values following due diligence undertaken by
prospective purchasers on the condition of asset. The assets to be disposed of
are listed in Appendix 1.   
3.1.7 The restricted capital funding of £5.122m is noted within Appendix 2.  This
relates to income which is restricted to specific projects and has been matched
with expenditure against the project, thereby showing the gross cost of the
project. 
3.1.8 Included in the funding table below is prudential borrowing in relation to the
Harbour Investment Programme. The Council is currently working to a ten year
asset management plan for Piers and Harbours which is being funded through
prudential borrowing utilising a fee increase over and above inflation to pay for
the loan charges incurred. 
3.1.9 There is also funding from the loans fund review, earmarked reserves, COVID-
19 funding and previously agreed additional funding allocations made. 
3.1.10 The estimated capital funding to 2026-27 is set out in the table below. 
2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Total
£000
General Capital Grant 9.569 9.569 9.569 8.678 37.385
Change to General Capital Grant - Post
Budget 2023-24 0.047 0.046 0.046   0.139
Change to General Capital Grant - Post
Budget 2024-25   -0.937 -0.937   -1.874
General Capital Grant Flooding Allocation 0.155 0.156 0.156 0.156 0.623
Specific Scottish Government Grants 0.376 0.379     0.755
Campbeltown Flood Scheme Allocation 5.424   0.618   6.042
Local Government Pay Deal 2.131       2.131
Additional Scottish Government Grants 5.879 0.364 0.391   6.634
Capital Grant - Area Control Accounts 0.051       0.051
Less Allocation to Private Sector Housing
Grants -1.033 -1.033 -1.033 -1.033 -4.132
Capital Receipts 0.484 0.750 0.750 0.400 2.384
Capital Receipts - Vehicles 0.027       0.027
Capital Receipts - HWD 1.000       1.000
Restricted Funding/Ring Fenced Capital
Grant 1.485 2.553 0.084   4.122
Harbour Investment Programme 3.200 24.110 39.000 17.585 83.895

Page 5

TIF - Borrowing paid from NDR 0.113 0.563     0.676
Prudential Borrowing/Borrowing
supported by loans charges 3.276 17.004 1.393   21.673
Additional Funding from Revenue 0.142       0.142
Funded by Reserves 1.009 2.296 0.191   3.496
Loans Fund Review 2.694 1.331 0.000   4.025
COVID Funding 0.095 0.558 0.279   0.932
Unallocated General Fund 7.759 1.042 0.000   8.801
Service Concessions 4.772 4.816 0.550   10.138
Funding Consistent with Revenue Budget 48.655 63.567 51.057 25.786 189.065   
3.2 Summary of Capital Plan reported as at 31 December 2023 
3.2.1 The capital plan included in the December capital monitoring is summarised in
the table below: 
2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Total
£m
Executive Director - Douglas Hendry:          
Education 6.037 5.006 3.521 0.000 14.564
Facility Services - Shared Offices 1.910 3.343 0.977 0.000 6.230
Major Projects/CHORD 8.989 2.461 0.105 0.000 11.555            
Executive Director - Kirsty Flanagan:          
ICT 1.474 1.593 1.221 0.000 4.288
Roads and Infrastructure 24.731 46.640 44.028 17.623 133.022
Development and Economic Growth 3.424 2.653 0.000 0.000 6.077            
Health and Social Care Partnership 0.972 2.085 0.477 0.000 3.534            
Live Argyll 1.084 0.636 0.427 0.000 2.147            
Total 48.621 64.417 50.756 17.623 181.417 
3.3 Proposed Revisions to Capital Plan 
3.3.1  As part of the capital planning process, departments reviewed the approved
capital plan in terms of the timing and cost of projects and updated the Priority
Investment Plans (PIPs) accordingly. 
3.3.2 The main adjustments reflect:
 Adding in a further year of flood prevention funding which is now £0.156m
(2024-25 and 2025-26 allocations need to be increased by £0.001m). 
 The inclusion of new funding for Cycling Walking Safer Streets totalling
£0.379m. 
 The inclusion of new funding for Community Bus Fund in 2023-24 of
£0.233m.

Page 6

 The inclusion of new funding for Nature Restoration Fund in 2023-24 of
£0.489m. 
All of these amounts above result in additional funding and additional
expenditure so has no overall impact to the budget gap. 
3.3.3 Other amendments include re-profiling of anticipated expenditure across the
programme. The revisions are summarised in the table below. 
2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Total
£m
Executive Director - Douglas Hendry:          
Education 0.000 0.000 0.000 0.000 0.000
Facility Services - Shared Offices 0.000 0.000 0.000 0.000 0.000
Major Projects/CHORD 0.000 0.000 0.000 0.000 0.000            
Executive Director - Kirsty Flanagan:          
ICT 0.000 0.000 0.000 0.000 0.000
Roads and Infrastructure 0.233 0.001 0.001 0.156 0.391
Development and Economic Growth 0.489 0.379 0.000 0.000 0.868            
Health and Social Care Partnership 0.000 0.000 0.000 0.000 0.000            
Live Argyll 0.000 0.000 0.000 0.000 0.000  
0.722 0.380 0.001 0.156 1.259 
3.4 Proposed Block Allocations 2026-27 
3.4.1  The block allocation to Services for 2026-27 is based on the General Capital
Grant award for 2024-25 of £8.834m less the flooding allocation of £0.156m and
adjusted to remove the PSHG allocation of £1.033m leaving a block allocation
available to spend on capital projects of £7.645m. 
3.4.2 The block allocation is allocated to services based on a proportionate
percentage basis. Services have each prepared PIPs in which they outline the
projects they would propose to spend their block allocation on.   
3.5 Cost Pressures and Risks 
3.5.1  As capital projects are based on cost estimates at a point in time, there is
always a risk they will cost more than originally planned, particularly where there
has been project delays.  Where there are major change projects there is a high
likelihood of the project requiring more budget than is currently in the capital
programme which has been emphasised over the last three years with projects
still catching up from the impact of COVID-19. 
3.5.2 Although the direct impact of COVID on most local services has reduced or
even ceased altogether over the last 12 months, COVID-19 in conjunction with

Page 7

the UK exit from the European Union and the Russian invasion of Ukraine,
continues to affect worldwide supply chains. This has the impact of reducing the
availability of supplies and materials resulting in cost increases through a
combination of higher prices and longer materials delivery lead times. 
In recent years additional funding of £10.803m has been allocated to the capital
programme for this purpose which has mitigated the impact to date however, as
detailed in the table below, £2.703m remains unallocated to projects facing
inflationary pressures. 
Funding for Capital Inflationary Pressures £m
COVID-19 Funding 0.257
February 2021 Budget Meeting - Capital Cost Pressures 4.646
February 2022 Budget Meeting - Capital Cost Pressures 3.900
February 2023 Budget Meeting - Capital Cost Pressures 2.000
Total Additional Funding Allocated to Capital 10.803
Allocated to Projects within Capital Programme (5.779)
Committed for future years (2.321)
Balance Remaining 2.703 
3.5.3 At the budget meeting in February 2023 additional funding was allocated to
Rothesay Pavilion which will allow the project to progress towards success by
supporting completion of Stage 1.  This stage of the project is currently on time
and to budget.  At February 2023, the costs to complete stages 2 and 3 were
£13.1m.  These estimates were based on January 2023 prices and were not
market tested at that point. Policy and Resources Committee subsequently
endorsed £9m of Rural Growth Deal Funding to be used for Rothesay Pavilion
which would leave a gap of £4.1m.  However, current estimates to complete
stages 2 and 3 are now £20.125m, therefore increasing the gap from £4.125m
to £11.559m.  Existing funders may contribute circa £2.7m which would reduce
the gap to £8.859m, however, this funding is not certain.  It should also be
noted that these figures will not be certain until after the tender exercise is
complete on 26 April. 
3.5.4 
3.5.5 
The Councils bid to the Scottish Government’s Learning Estate Investment
Programme (LEIP) for funding for a new school campus on Mull was successful.
While this is good news and will provide welcome investment in the school
estate it does come with a financial pressure that will require to be funded if the
project is to proceed. The Scottish Government will fund up to 50% of eligible
costs therefore the Council will be required to fund in excess of £20m. £9m of
earmarked reserves were previously allocated for this project therefore leaving
a pressure of circa £11m. Detail regarding this potential project is included in
Appendix 4.  
Surveys have been completed across the Council’s Learning Estate in relation
to Reinforced Autoclaved Aerated Concrete (RAAC) with only 1 building
confirmed as having it present with steps underway for its removal. This will
include a decant of the students for approximately 9 months plus total removal
and replacement of the roof during 2024. The estimated costs associated with
this are £3m which will require additional funding.

Page 8

3.5.6  As a result of a significant weather event on 7 October 2023, Argyll and Bute
Council activated the Bellwin scheme in relation to the recovery costs
associated with the incident. The funding from this scheme is welcomed
however eligibility criteria of costs are restrictive. Capital expenditure does not
qualify therefore any long term replacements to infrastructure such as bridges
cannot be claimed through the scheme. Works to the value of £3.248m have
been identified in the short term with future long term works costing circa £1.1m
being identified, both will require capital funding.
3.5.7  The Capital Programme has been structured to address the majority of the
Council’s high risk assets.  In 2024-25, service asset managers will develop
business cases and plans to tackle the other high risk assets which are not
addressed by projects within the Capital Programme for 2024-25 to 2026-27.
3.6 Comparison of Revised Plan to Estimated Capital Funding 
3.6.1  The capital plan as at 31 December 2023, including the new block allocation for
2026-27, has been compared to the estimated funding (noted in section 3.1). 
2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Total
£m
Capital Plan as at December 2023 48.621 64.417 50.756 17.623 181.417
Proposed revisions to capital plan 0.722 0.380 0.001 0.156 1.259
Estimated future years block
allocation       7.645 7.645
Projected overspend as at December
2023 0.024 0.458 0.000 0.338 0.820            
Total Revised Plan 49.367 65.255 50.757 25.762 191.141
Total Revised Funding 48.655 63.567 51.057 25.786 189.065
Total Surplus / (Gap) (0.712) (1.688) 0.300 0.024 (2.076) 
3.6.2  The total gap currently within the capital programme to 2026-27 is £2.076m. 
Various elements contribute to this gap as summarised in the table below.  After
adjusting for the cost pressures identified within section 3.5.1 of this report, the
total gap within the capital programme is £29.843m, see table below. 
Summary Detail £m
Projected
overspend as
at 31
December
2023
As reported in December Capital monitoring report there is
an anticipated overspend of £0.820m in the Capital Plan.
This is made up of Campbeltown Flood Scheme (£0.710m)
and Waste POPs Infrastructure (£0.110m). 
(0.820)
2024-25
Capital Grant
Funding adjustment due to reduction in General Capital
Grant received for 2024-25.
(0.891)
2025-26
Capital Grant
Capital grant was estimated at the same level as the 2023-
24 reduced settlement however there has been a decrease
in the 2024-25 settlement.
(0.891)

Page 9

Capital
Receipts
Adjustments
within existing
programme
Additional capital receipts for year 3 of the programme. 0.499
Vehicle Sales Vehicle Sales as at December 2023 have been received
totalling £0.027m which were not previously built into the
funding.
0.027
Total Surplus / (Gap) prior Cost Pressures (2.076)
Cost Pressure The removal of RAAC from 1 school within Councils Learning
Estate as detailed in paragraph 3.5.5.
(3.000)
Cost Pressure The additional costs associated with the weather incident in
October 2023 which are not covered by the Bellwin Scheme
as detailed in paragraph 3.5.6.
(4.348)
Cost Pressure Stage 2 and 3 of Rothesay Pavilion assuming funding will be
received from external bodies and that costs will not rise as
part of tender exercise as detailed in paragraph 3.5.3.
(8.859)
Other
Potential
Pressures
Council contribution to new school campus funded through
LEIP as detailed in paragraph 3.5.4.
(11.560)
Remaining Surplus / (Gap) (29.843) 
3.6.3  Council should give consideration as to how to fund the £29.843m gap within the
capital programme.  It should be noted that this gap assumes that external
funders will provide £2.7m in additional funding towards the completion of
Rothesay Pavilion. 
3.7 Funding Options Identified to reduce gap and address pressures 
3.7.1  The following are options Members may wish to consider to help bridge the gap
in the capital programme: 
Remove LEIP and undertake refurbishment works with the
£9m earmarking already set aside
11.560
Use some of one-off Strathclyde Pension Fund Gain 2.000
Use some Crown Estate Allocation from 24-25 and 25-26 2.000
Earmarked Reserves released to the General Fund (refer to
Reserves and Balances report within budget pack for detail)
2.212
Use Asset Management Fund 2.070
Use Capital Contract Increases towards Forecast Overspend 0.820
Total Funding Options 20.662 
This would still leave a gap of £9.181m that will require additional funding.   
3.7.2 Further funds that may be considered are noted in the table below. 
Use Capital Contract Increases remaining balance 1.883
Priority Investment Fund 6.150
Pension Fund Gain Remaining Balance 3.750
Total Funds 11.783

Page 10

Note that the utilisation of the £1.883m balance for capital contract increases
should be done with caution as projects continue to see substantial price
increases since initial tenders were undertaken. The removal of this Fund could
result in existing projects no longer being able to reach completion. 
3.7.3 A further option is that the PSHG allocation could be reduced to match the
actual funding received from the Scottish Government which would generate a
saving of £0.276m across three years. 
3.7.4 Borrowing could be taken out to cover the gap in the programme however this
creates a revenue cost. Every £1m of borrowing for the capital programme
creates a revenue pressure of circa £0.064m on average per annum. 
3.8 Updated Capital Plan 
3.8.1 The table below shows a summary of the updated capital plan and further detail
is contained within Appendix 3.  This excludes the anticipated shortfalls and cost
pressures identified as these are subject to Member approval.   
2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Total
£m
Executive Director - Douglas Hendry:          
Education 6.037 5.006 3.521 1.988 16.552
Facility Services - Shared Offices 1.910 3.343 0.977 0.382 6.612
Major Projects/CHORD 8.989 2.461 0.105 0.000 11.555            
Executive Director - Kirsty Flanagan:          
ICT 1.474 1.593 1.221 0.688 4.976
Roads and Infrastructure 24.988 47.099 44.029 21.940 138.056
Development and Economic Growth 3.913 3.032 0.000 0.000 6.945            
Health and Social Care Partnership 0.972 2.085 0.477 0.382 3.916            
Live Argyll 1.084 0.636 0.427 0.382 2.529            
Total 49.367 65.255 50.757 25.762 191.141 
4.  CONCLUSION 
4.1 
4.2
The capital plan funding assumptions have been updated, the plan extended for
a further year and block allocations allocated to services for the additional year. 
Taking into consideration the current capital programme and cost pressures there
is a reported gap of £29.843m. If borrowing was taken out to fund this gap every
£1m of borrowing for the capital programme creates a revenue pressure of circa
£0.064m on average per annum. 
The capital programme faces other significant pressures in the years beyond
2024-25 with the key areas highlighted within section 3.5 of this report.
Consideration should also be given as to how these can be funded and the further
pressures highlighted within the PIPs.

Page 11

4.3  Estimated funding for the 2026-27 capital programme has been based on the
General Capital Grant received in 2024-25. The Scottish Government has
previously confirmed that the indicative General Capital Grant settlements up to
2025-26 will remain constant at the same level as the 2021-22 settlement
however the reduction in 2024-25 has proved this is not the case. 
5. IMPLICATIONS 
5.1 Policy – Sets out the approach to capital planning. 
5.2 Financial – Outlines the funding and commitments for the capital plan 2024-27. 
5.3 Legal - The funding for new expenditure may not address all the Statutory and
Regulatory requirements in relation to Health and safety.   
5.4 HR - There are risks that the funding available will have an impact on the
sustainability of the Property Design Team and the design team within Roads and
Amenity Services. 
5.5
5.5.1
5.5.2
5.5.3
Fairer Scotland Duty – None. 
Equalities – None. 
Socio-Economic Duty – None. 
Islands Duty – None. 
5.6 Climate Change – The Council is committed to addressing climate change and
reviews of how Services are delivered is ongoing within the available budget
resources. 
5.7 Risk - There are risks around level of capital receipts which could result in red
risk assets not being addressed. 
5.8 Customer Service – None. 
5.9 The Rights of the Child (UNCRC) - None  
Kirsty Flanagan
Executive Director/Section 95 Officer
6 February 2024 
Councillor Gary Mulvaney - Policy Lead for Finance and Commercial
Services 
APPENDICES:
Appendix 1 - Proposed Asset Disposals
Appendix 2 - Restricted Funding 
Appendix 3 - Proposed Capital Plan 2024-27 
Appendix 4 – LEIP 
For further information please contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 12

Appendix 1 - Proposed Asset Disposals
Property
Glencreran Schoolhouse
Land at Former Police Station, Garelochhead
Site of former Cowal Teacher's Centre, Sandbank
Ground at Baliscate Roads Depot
Ashfield Primary School
Bridge of Orchy School
Auchenlochan access
Shop, 3 Montague Street
Ground at 26B Hillfoot Street
Area of ground adjoining Pier House Fionnphort, Isle of Mull
Land at Broom Road,
Ardchonnel Primary School
Former Girl Guide Hut, Dunclutha Lane
Former Erray Road Depot
Former Registrar Office, Witchburn Road
Witchburn Road site, former Finance Office
Ground at 125 Frederick Street
Former Appin Roads Depot
Blairvadach site, Shandon, Helensburgh (Phase 2)
Dunclutha Children's Home
Site behind former Lochgilphead High School (site 2)
Former Lochgilphead Primary School

Page 13

Appendix 2 - Restricted Funding
2023-24
£m
2024-25
£m
2025-26
£m
Total
£m
Education
Scottish Government Island Funding - Tigh Na Rhuda 0.000 0.000 0.050 0.050
Education Total 0.000 0.000 0.050 0.050
Roads & Infrastructure Services
STTS 0.387 0.000 0.000 0.387
Rural Growth Deal - Public Convenience Upgrades 0.200 0.000 0.000 0.200
Roads & Infrastructure Services Total 0.587 0.000 0.000 0.587
Development & Economic Growth
H&L Cycleways 0.150 0.000 0.000 0.150
SPT Cycleways 0.000 0.290 0.000 0.290
SPT Bus Infrastructure 0.000 0.025 0.000 0.025
Coastal Communities Funding (Crown Estate) 0.605 0.000 0.000 0.605
Rural Growth Deal - RGD Projects 0.137 0.000 0.000 0.137
Rural Growth Deal - Dunoon STEM Hub 0.000 1.750 0.000 1.750
Waitrose Section 75 -  RGD - Clyde Engineering 0.025 0.000 0.000 0.025
Scottish Island Fund - Tobermory Rails Phase 2 0.250 0.000 0.000 0.250
Development & Economic Growth Total 1.167 2.065 0.000 3.232
Major Projects
Helensburgh Waterfront Development 1.000 0.000 0.000 1.000
Kilmory Business Park -0.522 0.488 0.034 0.000
Rothesay Pavillion 0.253 0.000 0.000 0.253
Major Projects Total 0.731 0.488 0.034 1.253
TOTAL FUNDING 2.485 2.553 0.084 5.122

Page 14

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Overall Summary
Service
2023-24                                           
£000s
2024-25                 
£000s
2025-26                
£000s
2026-27                 
£000s Total
Education 6,037 5,006 3,521 1,988 16,552
Shared Offices 1,910 3,343 977 382 6,612
ICT 1,474 1,593 1,221 688 4,976
RIS 24,988 47,099 44,029 21,940 138,056
DEG 3,913 3,032 0 0 6,945
HSCP 972 2,085 477 382 3,916
Live Argyll 1,084 636 427 382 2,529
CHORD 8,989 2,461 105 0 11,555
Overall Total 49,367 65,255 50,757 25,762 191,141

Page 15

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Education
Category Service Project
2023-24                     
£000s
2024-25                 
£000s
2025-26                
£000s
2026-27
£000s
Total
£000s
Asset Sustainability Education Asbestos Control/Removal Works 7 0 0 0 7
Block Allocation - Education 216 866 520 1,988 3,590
Digital Inclusion 20-21 9 0 0 0 9
Free School Meals 379 900 1,495 0 2,774
Homeless Houses - Housing Quality Standard 1 0 0 0 1
Internal Refurbishment Budget 7 0 0 0 7
Primary Schools 3,370 2,420 1,280 0 7,070
School Houses - Housing Quality Standard 13 0 0 0 13
Secondary Schools 852 820 226 0 1,898
Asset Sustainability Total 4,854 5,006 3,521 1,988 15,369
Service Development Education Bowmore Primary School - Gaelic Medium Grant 38 0 0 0 38
CO2 Monitoring - Covid Mitigation in Schools 113 0 0 0 113
Early Learning and Childcare - 1140 Hours 320 0 0 0 320
Service Development Total 471 0 0 0 471
Strategic Change Education Campbeltown Schools Redevelopment 38 0 0 0 38
Dunoon Primary School 234 0 0 0 234
Kirn Primary School 34 0 0 0 34
Replacement of Oban High School 406 0 0 0 406
Strategic Change Total 712 0 0 0 712
Overall Total 6,037 5,006 3,521 1,988 16,552

Page 16

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Shared Office
Category Service Project
2023-24     
£000s
2024-25      
£000s
2025-26      
£000s
2026-27        
£000s
Total
£000s
Asset Sustainability Shared Offices Argyll House, Dunoon 9 0 0 0 9
Asbestos Capital Property Works 51 0 0 0 51
Block Allocation 152 298 427 382 1,259
Bowmore Area Office 76 0 0 0 76
Burnett Building 3 107 0 0 110
Capital Property Works 38 0 0 0 38
Fire Risk Assessment Works 14 0 0 0 14
Helensburgh and Lomond Civic Centre - Emergency Heating Pipework 130 0 0 0 130
Hill Street Dunoon Rewire 33 0 0 0 33
Kilmory Castle 0 1,409 0 0 1,409
Legionella Control Works 144 0 0 0 144
Manse Brae Roads Office 2 0 0 0 2
Our Modern Workspace 683 480 0 0 1,163
Asset Sustainability Total 1,335 2,294 427 382 4,438
Strategic Change Shared Offices Campbeltown Office Rationalisation 1 0 0 0 1
Clean Energy - NDEEF1 224 143 0 0 367
Clean Energy - NDEEF2 50 540 550 0 1,140
Helensburgh Office Rationalisation  (FPB,REC) 300 0 0 0 300
Net Zero 0 366 0 0 366
Strategic Change Total 575 1,049 550 0 2,174
Overall Total 1,910 3,343 977 382 6,612

Page 17

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Major Projects
Category Service Project
2023-24    
£000s
2024-25    
£000s
2025-26     
£000s
2026-27          
£000s
Total
£000s
Strategic Change CHORD CHORD - Dunoon 27 0 0 0 27
CHORD - Helensburgh -Public Realm Imprv 28 0 0 0 28
CHORD - Oban 626 0 0 0 626
CHORD - Rothesay 6,737 1,973 71 0 8,781
Helensburgh Waterfront Development 977 0 0 0 977
HWD - FFE 34 0 0 0 34
Kilmory Business Park Phase 2AA 560 488 34 0 1,082
Strategic Change Total 8,989 2,461 105 0 11,555
Overall Total 8,989 2,461 105 0 11,555

Page 18

CAPITAL PLAN 2023 - 2027 APPENDIX 3
ICT
Category Service Project
2023-24      
£000s
2024-25      
£000s
2025-26      
£000s
2026-27     
£000s
Total
£000s
Asset Sustainability ICT Block Allocation - ICT 0 132 0 688 820
PC Replacement 518 648 669 0 1,835
Server Sustainability 352 425 400 0 1,177
Telecomms Network 256 72 152 0 480
Asset Sustainability Total 1,126 1,277 1,221 688 4,312
Service Development ICT Applications Projects 348 316 0 0 664
Service Development Total 348 316 0 0 664
Overall Total 1,474 1,593 1,221 688 4,976

Page 19

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Roads and Infrastructure Services
Category Service Project
2023-24     
£000s
2024-25    
£000s
2025-26   
£000s
2026-27    
£000s
Total
£000s
Asset Sustainability RIS Block Allocation 0 0 4,268 3,823 8,091
Bridge Strengthening 373 1,313 0 0 1,686
Bute Sea Wall Repairs 59 621 0 0 680
Coastal Change Adaptation 41 246 0 0 287
Coastal Protection 6 193 0 0 199
Environmental Projects 200 821 0 0 1,021
EV Quick Chargers 62 0 0 0 62
Footway Improvements 450 300 0 0 750
Glengorm - Cell and Transfer Station (PB) 89 0 0 0 89
Helensburgh CHORD - Signage etc 10 0 0 0 10
Helensburgh Flood Mitigation 1 427 0 0 428
Investment in Active Travel 189 200 0 0 389
Lighting 440 600 0 0 1,040
Local Bridge Maintenance Fund 173 4,827 203 0 5,203
Play Park Renewal 0 547 391 0 938
Public Convenience Upgrades 282 0 0 0 282
Roads Reconstruction 7,419 8,000 0 0 15,419
Roads Reconstruction - Helensburgh CHORD 47 0 0 0 47
Roads Reconstruction - Oban CHORD 3 0 0 0 3
Tobermory Car Park 96 0 0 0 96
Asset Sustainability Total 9,940 18,095 4,862 3,823 36,720
Service Development RIS Fleet Management 325 1,180 0 0 1,505
Fleet Management - Prudential Borrowing 1,941 246 0 0 2,187
Lismore Ferry Replacement 15 20 0 0 35
Lochgilphead Depot Rationalisation 33 0 0 0 33
Oban Depot Development 9 0 0 0 9
Preliminary design for  Regional Transport projects (tif) 16 0 0 0 16
Service Development Total 2,339 1,446 0 0 3,785
Strategic Change RIS Harbour Investment Programme PB 3,200 24,110 39,000 17,585 83,895
Street Lighting LED Replacement 61 613 0 0 674
Strategic Change Total 3,261 24,723 39,000 17,585 84,569
Overall Total 15,540 44,264 43,862 21,408 125,074

Page 20

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Development and Economic Growth
Category Service Project
2023-24    
£000s
2024-25   
£000s
2025-26    
£000s
2026-27     
£000s
Total
£000s
Service Development DEG Ardrishaig North Active Travel 112 13 0 0 125
Cycleways - H&L (FSPT) 300 290 0 0 590
Dunoon Cycle Bothy 292 12 0 0 304
Dunoon STEM Hub 713 1,750 0 0 2,463
Gibraltar Street Public Realm Improvements 222 0 0 0 222
Helensburgh Public Realm - Arts Strategy Fund 50 0 0 0 50
Hermitage Park 26 0 0 0 26
Rural Growth Deal 162 0 0 0 162
SPT - bus infrastructure 0 25 0 0 25
Town Centre Funds 718 0 0 0 718
Service Development Total 2,595 2,090 0 0 4,685
Strategic Change DEG 01 TIF - Lorn/Kirk Road 1 0 0 0 1
09 TIF - Oban Airport Business Park 56 45 0 0 101
TIF - Halfway House Roundabout 56 518 0 0 574
Strategic Change Total 113 563 0 0 676
Overall Total 2,708 2,653 0 0 5,361

Page 21

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Health & Social Care Partnership
Category Service Project
2023-24   
£000s
2024-25   
£000s
2025-26   
£000s
2026-27    
£000s
Total
£000s
Asset Sustainability HSCP Ardfenaig 27 0 0 0 27
Block Allocation 0 1,058 184 382 1,624
Capital Property Works 79 0 0 0 79
Digitalising telecare 100 0 0 0 100
East King Street Childrens Home 58 0 0 0 58
Glencruitten Hostel 81 36 143 0 260
Gortonvogie 1 0 0 0 1
Greenwood/Woodlands 216 0 0 0 216
Lochgilphead Resource Centre 16 0 0 0 16
Shellach View 144 0 0 0 144
Struan Lodge Boiler 59 0 0 0 59
Tigh An Rudha HFE 109 991 150 0 1,250
Tobermory Top Flat 28 0 0 0 28
Asset Sustainability Total 918 2,085 477 382 3,862
Service Development HSCP Dunclutha Childrens Home 54 0 0 0 54
Service Development Total 54 0 0 0 54
Overall Total 972 2,085 477 382 3,916

Page 22

CAPITAL PLAN 2023 - 2027 APPENDIX 3
Live Argyll
Category Service Project
2023-24    
£000s
2024-25    
£000s
2025-26    
£000s
2026-27   
£000s
Total
£000s
Asset Sustainability Live Argyll Aqualibrium 343 48 40 0 431
Capital Property Works 52 317 213 382 964
Corran Halls Gaelic Centre 113 46 84 0 243
Kintyre Community Education Centre - Lift Shaft Refurbishment 2 0 0 0 2
Lochgilphead Community Ed Centre 122 200 40 0 362
Lochgilphead Library Relocation 14 0 0 0 14
Riverside Leisure Centre - Health Suite Upgrade 204 0 0 0 204
Riverside Leisure Centre - Spa Pool Upgrade 17 0 0 0 17
Rothesay Swimming Pool 40 25 50 0 115
The Moat Centre 77 0 0 0 77
Victoria Halls, Helensburgh 78 0 0 0 78
Asset Sustainability Total 1,062 636 427 382 2,507
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1 0 0 0 1
Service Development Total 1 0 0 0 1
Strategic Change Live Argyll Carbon Management 21 0 0 0 21
Strategic Change Total 21 0 0 0 21
Overall Total 1,084 636 427 382 2,529

Page 23

APPENDIX 4 
1.0    EXECUTIVE SUMMARY 
1.1 The purpose of this report is to update Committee on the Council’s Learning
Estate Investment Programme (LEIP) project to deliver a New Campus on Mull. 
Mull was chosen to be the Council’s sole bid to LEIP and priority for strategic
investment due to being the only secondary school in our region to be graded
as ‘Poor’ in terms of learning suitability.   
1.2 The successful LEIP announcement was made on 30th October, approximately
a year later than the Scottish Government (SG) had originally outlined that they
would make a decision.  Since the announcement the project delivery team
have been re-mobilised to commence the initial stages of the project and
respond to the SG offer of LEIP funding. 
1.3 This report provides an update in terms of the project and importantly the new
financial environment and economic considerations that must be considered. 
Currently, there is no site selected for a new campus on Mull and extensive
community engagement, design development and a full options appraisal would
be required to progress with the project to an Outline or Full Business Case
position.   This would be an intensive pre-construction phase taking place
during 2024 and most of 2025.   
1.4 The project team have been working closely with Hub North and the Northern
Alliance – who also supported the original bid.  These organisations,
jointly owned by the Council’s (and other public sector partners) and private
sectors, are responsible for working collaboratively and delivering community
infrastructure in our region. This partnership is particularly relevant to LEIP
given 5 of the 10 national projects have been earmarked for the ‘North’ and
there are significant collaboration opportunities with working inter-authority with
partners in Orkney, Moray, Shetland and Aberdeen City in developing our LEIP
projects.  A programme approach is currently being considered for these
Council’s to deliver efficiency in terms of design development, purchasing
materials, economies of scale, contract labour and sharing best practices.   
1.5 Even with regional collaboration, the delivery of a new campus on Mull will be
one of the most significant projects in terms of cost and complexity the Council
has delivered for many years.  The funding offered by the SG is not a grant nor
is it for the full cost of the building – it will cover up to 50% of eligible costs and
SG will then offer financing for this sum over 25 years.  This means the entire
design, land acquisition (if required) and build costs will require to be met -up
front - by the Council with up to 50% being recouped in coming years.  Building
modern schools to high digital and environmental standards comes at a cost 
ARGYLL AND BUTE COUNCIL  COUNCIL BUDGET 
COMMERCIAL SERVICES /
EDUCATION / FINANCE 
22nd FEBRUARY  2024 
Learning Estate Investment Programme (LEIP) – Mull Campus Update

Page 24

APPENDIX 4 
premium and this increases when island weighting is applied due to logistical
challenges of getting labour and materials to site.  Overall affordability of the
project must be considered closely by Members and is referred to in this report. 
1.6 Affordability of this project was a key consideration when the bid was submitted
in October 2022 and at that point was already stretching upper tolerance levels. 
The updated cost plan and programme that has been worked on since the
October 2023 announcement indicates that overall cost will have increased by
around 10% and forecast opening of October 2028.  Through a combination of
the increased costs / timescales caused by the funding announcement,
increased construction inflation, worse than anticipated budget settlement and
other capital budget pressures Officers are of the view that the project would
only remain affordable if Members are prepared to take hard decisions to
reduce other Council areas of capital and / or revenue spend.   
1.7 It is acknowledged if a decision is taken to not proceed with the LEIP Project
this would be disappointing for many on Mull and surrounding islands however
as an alternative, a package of significant upgrading works to the existing
Tobermory Primary and High School would be required. These would be
funded from the £9m previously earmarked for LEIP and works are likely to
include: 
A. Works to enhance Building Fabric improving condition and prolonging life
of the asset
a. Partial re-roof
b. Roughcast improvements
c. Solar Panels and energy efficiency works
d. Drainage works
e. Partial rewire
f. LED Lighting
g. Ventilation upgrades
h. Address remedial damp areas 
B. Minimum works to enhance learning and teaching spaces to improve
suitability
a. Partial redecorations in areas
b. Additional Support Needs (ASN) upgrades
c. Home economics lab refurbishment
d. Science Lab refurbishment
e. Technical lab refurbishment
f. External landscaping for social / learning space 
2.0    RECOMMENDATION 
As per the recommendations in the Introductory Report of Budget Pack, the
Council are recommended to:- 
2.1.1  Note the successful award of a major bid funding bid; 
2.1.2  Note the funding provided by Scottish Government is not a capital grant
for full cost of project – in summary SG will provide up to 50% of eligible

Page 25

APPENDIX 4 
costs over a 25 year period following completion.  The Council will
require to pay the total cost up front; 
2.1.3  Note due to the 1 year time delay of LEIP announcement the requirement
to open the new Campus by December 2027 (which was the original
timescale) cannot be met – now forecast for October 2028 at earliest; 
2.1.4  Note the updated timescale programme forecast as outlined at
Appendix A + B; 
2.1.5  Consider overall affordability of project as outlined at Appendix C and
determine whether: 
(A) Proceed with the LEIP Project in the knowledge that Members will be
required to take hard decisions to reduce other Council areas of capital
and / or revenue spend, in future revenue budgets / capital programmes. 
Or 
(B) Not to proceed with the current LEIP Project based on current capital
affordability considerations and as an alternative deliver a programme
of significant building fabric upgrade works to (a) prolong the operational
life and (b) enhance learning and teaching spaces of the existing school
buildings (Primary and Secondary) at Tobermory using £9m of
previously earmarked funds.

Page 26

APPENDIX 4 
3.0    INTRODUCTION 
3.1 In June 2022 the Scottish Government (SG) invited bids from Local
Authorities for funding from their Learning Estate Investment Programme
(Phase 3).  This is the SG main investment programme for improving
education buildings and there is unlikely to be any new funding in the lifetime
of this current government.   
3.2 Argyll and Bute Learning Estate Strategy identified Tobermory High School as
its number one priority to pursue strategic change / investment and submitted
a bid for A New Campus on Mull on 31 October 2022.  The school in its
current condition is lowest scoring of all secondary schools in terms of its
suitability to provide modern learning facilities.  Investment – LEIP or
otherwise is required for this school.   
3.3 The Mull bid was one of thirty-six (36) made by other Local Authorities across
Scotland.  The announcement was received on 30 October 2023 confirming
Mull was one of the ten successful bids investing approximately £400m in the
Learning Estate across the country. Other successful island bidders included
Orkney and Shetland.   
4.0    RECOMMENDATION 
As per the recommendations in the Introductory Report of Budget Pack, the
Council are recommended to:- 
4.1.1  Note the successful award of a major bid funding bid; 
4.1.2  Note the funding provided by Scottish Government is not a capital grant
for full cost of project – in summary SG will provide up to 50% of eligible
costs over a 25 year period following completion.  The Council will
require to pay the total cost up front; 
4.1.3  Note due to the 1year time delay of LEIP announcement the requirement
to open the new Campus by December 2027 (which was the original
timescale) cannot be met – now forecast for October 2028 at earliest; 
4.1.4  Note the updated timescale programme forecast as outlined at
Appendix A + B; 
ARGYLL AND BUTE COUNCIL  COUNCIL BUDGET 
COMMERCIAL SERVICES /
EDUCATION / FINANCE 
22nd FEBRUARY  2024 
Learning Estate Investment Programme (LEIP) – Mull Campus Update

Page 27

APPENDIX 4 
4.1.5  Consider overall affordability of project as outlined at Appendix C and
determine whether: 
(A) Proceed with the LEIP Project in the knowledge that Members will be
required to take hard decisions to reduce other Council areas of capital
and / or revenue spend, in future revenue budgets / capital programmes. 
Or 
(B) Not to proceed with the current LEIP Project based on current capital
affordability considerations and as an alternative deliver a programme
of significant building fabric upgrade works to (a) prolong the operational
life and (b) enhance learning and teaching spaces of the existing school
buildings (Primary and Secondary) at Tobermory using £9m of
previously earmarked funds.   
5.0 DETAIL 
5.1  Since the LEIP announcement of 30th October the Council have been moving at
pace to mobilise the Project Delivery Team and update the project details and
forecasts.  Consideration needs to be given to the following:- 
A – Conditions of funding
5.2 Unlike previous and other funding delivery models, LEIP is not a grant nor does
it address total cost of a project. The LEIP funding will cover up to 50% of
eligible costs and SG will then offer financing for this sum over 25 years.  This
means the entire design, land acquisition (if required) and build costs will
require to be met -up front - by the Council with up to 50% being recouped in
coming years.  Building modern schools to high digital and environmental
standards comes at a cost premium and this increases when island weighting is
applied due to logistical challenges of getting labour and materials to site. 
Overall affordability of the project must be considered closely by Members and
is referred to in this report at Section C.  Given the nature of the LEIP funding
structure, this will be one of highest value projects the Council has ever
delivered in terms of up-front costs so strong commitment to the project and its
resourcing is required.   
5.3 The LEIP funding model is also predicated on achieving a number of quality,
environmental, space, function and condition standards.  In effect, this will
create a high standard of building that should be sustainable and flexible – this
is a higher benchmark standard to any new buildings (including schools) the
Council has delivered in recent years.  Ensuring the buildings are digitally
enabled and support local economic development is also encouraged.  The full
list of conditions is as follows:- 
 Internal Environmental Quality (suitable internal environment for building
users is vital for their health, wellbeing and learning. 
 Internal Monitoring (use of sensors to ensure the highest quality internal
environment is delivered as a response to Covid 19 in terms of ventilation and
CO2 levels)

Page 28

APPENDIX 4 
 Zero Emissions Heating
 Electrical Vehicle Charging
 Healthier Learning Environments
 Infrastructure Technology 
Scottish Government (SG) funding will be available through the Outcomes Based
Funding (OBF) model.  The outcomes include: 
 Condition - Local authorities must provide evidence, through their annual
returns that the facility is kept in condition A or B for a period of 25 years. 
 Energy Efficiency 
 Digitally Enabled Learning
 Economic Growth
 Construction Embodied Carbon 
5.4 It should be noted that not all costs are LEIP ‘eligible’.  It therefore needs to be
considered during the design development phases and in context of overall
affordability that spend on ‘non-eligible’ costs such as purchasing of land (if
required), creation of non -learning space (for example Customer Contact
Point) or Hostel would not be funded by LEIP and therefore would need to be
met solely by Council or other funding source.   
5.5 Despite the approx. 1-year delay on announcement of LEIP one of the core
funding criteria has been to open the new campus to learners by the original
December 2027 timeframe.  The programme outlined in the Mull Campus bid
was already ambitious and the additional announcement delay has added
significant pressure to meet this timescales.  Our updated Programme indicates
that a Mull bid would now be unable to make this December 2027 timescale
and now forecasting an opening of October 2028.  This is a risk to the project
but one the Government and Scottish Futures Trust have indicated they would
be willing to have dialogue with Council’s on their ability to adhere to this or
other criteria.   
5.6 The SG and Scottish Futures Trust (SFT) have also intimated that a project on
Mull may be eligible for additional funding due to island locational factors. 
Whilst this additional ‘locational uplift’ is not currently written into the
conditions of funding or LEIP agreement they have confirmed there is
precedent with other rural and island LEIP projects and it is likely these would
be available to this project on Mull.  Locational factors would cover the known
additional costs that relate to construction in island or rural areas such as cost
of raw materials, costs of labour, travel, extra build time, extreme weather and
waste disposal.  If successful in agreeing terms, the locational uplift would not
cover the entire ‘island weighting’ factor but it would meet 50% of it.  At present
we forecast this locational uplift could be up to £3.5m (max) but this figure
cannot be confirmed or accounted for in full until more detailed design work is
completed due in 2025 and agreement with SG is reached at that time.   
B- Programme

Page 29

APPENDIX 4 
5.7 Given the approximate 1 year delay in funding announcement the team have
updated the project delivery plan can be found at Appendix A – Proposed
Programme Business Case to Delivery and Appendix B – Tracker / Gant
with key milestones being as follows:- 
 Q1/ Q2 2024 – Consultations begin (community / statutory)
 Q2 2024 – Site Selection process begins
 Q2 – 2025 – Design development, cost plan begins (RIBA Stage 2)
 Q4 – 2025 – Planning, detailed cost, contracts to construct (RIBA Stage 4)
 Q4 2026 to Q4 2028 – Construction 
 October 2028 new campus open 
5.8 The Programme also includes the close and partnership working with Hub
North and the Northern Alliance – who also supported the original bid.  There is
an agreed ‘Northern Programme Approach’ where there will be inter-authority
collaboration with partners from Orkney Island Council, The Moray Council,
Shetland Island Council and Aberdeen City Council in developing our LEIP
projects.  The Northern programme approach is currently being developed and
anticipate working with these Council’s will deliver efficiency and good practice
in terms of design development, purchasing materials, economies of scale,
contract labour and sharing best practices.  For example – joint commissioning
of architectural is being looked at and input and purchasing of high value
generic items like doors or windows.   
C – Cost and affordability 
5.9 Creating modern schools has traditionally been some of highest value projects
the Council delivers.  Building modern schools to high digital and environmental
standards as required by LEIP comes at a cost premium and this increases
when island weighting is applied due to logistical challenges of getting labour
and materials to site.  Overall affordability of the project must be considered
closely by Members and is referred to in this report.   
5.10 The full Council made an express decision to support the bid for LEIP at their
meeting on 29 September 2022.  This included commentary from the Council’s
Section 95 Officer.  Given the passage of time and updated financial landscape
an update of this advice is contained at Appendix C. 
5.11 Affordability of this project was a key consideration when the bid was submitted
in October 2022 and at that point was already stretching upper tolerance levels. 
Following an update forecast in December 2023, the total forecast project
cost now sits at £39.12m.  It must also be noted that this £39.12m is a
justified projection based on the information currently available and the
timescales linking construction to inflation.  The forecast price and proportion
the Council will be responsible for funding will fluctuate depending on a number
of material factors:- 
 What site is selected – some sites may be more or less
expensive to develop (eg is there power, water, rock, roads,
peat)

Page 30

APPENDIX 4 
 Is a land purchase or compulsory purchase required (SG wont
fund land purchase)
 Design and function of new campus – materials and variety of
uses will influence cost and SG funding
 Scottish Government funding is ‘up to’ 50% of eligible costs
(lower offer than 50% of total project cost may be made)
 Efficiencies driven from Regional Programme Approach or
Uplift in metrics from Scottish Government (additional funding)
due to ‘Locational Factors’ – cannot quantify or account for
these at this stage until detailed design completed 
5.12 Notwithstanding these variable factors the £39.12m is a justified cost based
on experience developing LEIP Projects across the Country plus addition of a
‘island weighting’ factor.  The LEIP3 Projects in Orkney and Shetland that are
similar in scope and stage to Mull, and both currently forecast over the £40m
mark.   It should therefore be considered this is the region of total cost and
total outlay by our Council.   
5.13 The recently updated cost plan and programme that has been worked on
since the October 2023 announcement indicates that overall cost has
increased by around 10% since the forecast provided at the time of the bid (1
year delay in announcement).   Through a combination of the increased costs
/ timescales caused by the funding announcement, increased construction
inflation, worse than anticipated budget settlement and other capital budget
pressures Officers are of the view that the project would only remain
affordable if Members prepared to take hard decisions to reduce other Council
areas of capital and / or revenue spend.   
5.14 Progressing to Outline Business Case or Full Business Case would require
investment of several million pounds and require high degree of consultation
and engagement with the community which if not progressed to construction
would be abortive costs and unrealistically raise expectations. 
D – Alternative Learning Estate Improvements     
5.15 It is acknowledged if a decision is taken to not proceed with the LEIP Project
this would be disappointing for many on Mull and surrounding islands however
as an alternative a package of significant upgrading works to the existing
Tobermory Primary and High School would be required. These would include: 
A. Works to enhance Building Fabric improving condition and prolonging life of
the asset
a. Partial re-roof
b. Roughcast improvements
c. Solar Panels and energy efficiency works
d. Drainage works
e. Partial rewire
f. LED Lighting
g. Ventilation upgrades
h. Address remedial damp areas

Page 31

APPENDIX 4 
AND 
B. Minimum works to enhance learning and teaching spaces to improve suitability
a. Partial redecorations in areas
b. Additional Support Needs (ASN) upgrades
c. Home economics lab refurbishment
d. Science Lab refurbishment
e. Technical lab refurbishment
f. External landscaping for social / learning space 
5.16 The value of this work will be in the region of £9m.  These can be funded by
existing earmarkings previously allocated for LEIP.   
6.0 CONCLUSIONS 
6.1 The successful bid for LEIP funding has been a welcomed opportunity to closely
consider the development of new learning estate on Mull.  The Council has a
strong track record of building new schools over the past 15 years however for
reasons set out in Para 1.6 above, the overall increased costs / timescales
caused by the funding announcement, increased construction inflation, worse
than anticipated budget settlement and other capital budget pressures Officers
are of the view that the project would only remain affordable if Members are
prepared to take hard decisions to reduce other Council areas of capital and / or
revenue spend.   
6th February 2024 
For further information contact: 
Policy Lead for Education – Councillor Yvonne McNeilly 
Policy Lead for Commercial Services & Finance – Councillor Gary Mulvaney 
Executive Director with Responsibility for Commercial Services & Education – 
Douglas Hendry 
Executive Director for Financial Services + S95 Officer –
Kirsty Flanagan 
Head of Commercial Services – Ross McLaughlin
Head of Education and Lifelong Learning + Chief Education Officer – Jen Crocket
Head of Education – Learning and Teaching - Wendy Brownlie
Head of Financial Services – Anne Blue 
Appendices 
Appendix A – Proposed Programme Business Case to Delivery
Appendix B – Tracker / Gant Programme
Appendix C – Finance / Affordability Update

Page 32

No embedded text on this page.

Page 33

APPENDIX B
LEIP 3 Programme New Schools
Draft Tracker Programme Rev 01
30th November 2023            
Summary Programme
Briefing
New Mull Campus
KEY:
OBC APPROVAL
FBC APPROVAL
SSPS Briefing: hub North Development brief, consultation, vision, RIBA Stage 1 design
STAGE 1: hub North Stage 1 (incl RIBA Stage 2 design and developed cost plan)
STAGE 2: hub North Stage 2 (RIBA Stage 4 design and contract signature)
Q1 Q2 Q3 Q4Q3 Q4 Q1 Q2 Q3 Q4
2027
Q1 Q2 Q3 Q4 Q1
2028
Q2
2029
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2023 2024 2025 2026
Consultations/Site Agreement STAGE 1 STAGE 2 CONSTRUCTION DEMO & PITCHES

Page 34

APPENDIX C
Financial and Budget Position 
Part of the Council Report of 13 September 2022, requested agreement to move ahead with
a bid to the Scottish Government LEIP funding programme to deliver a new Campus on Mull. 
The Council was advised on 30 October 2023, that the bid was successful. This fund would
contribute up to 50% of the eligible costs of the project over a 25 year period, and the paper
included a financial report at Appendix B.  
The forecast cost of a new campus at that time was £35.5m, which did not include any land
purchase costs, if required.  Table below shows funding options presented at that time as
well as an updated position: 
Original 
Option A
£000
Original
Option B
£000
Updated
Position
£000
Assumptions
Cost of Construction* 35,500 35,500 39,120 As per estimates. 
Estimated Cost of Land   1,000 As per estimates
LEIP earmarking (1,000) (1,000) (1,000) Agreed as part of February 2022
budget.
Capital Grant Saving
over 5 years (estimate) 
(3,000)  This amount would need to be
top-sliced from the general
capital grant – for illustrative
purposes only, would require a
Council decision.
Use of Service
Concessions one-off
gain in 22-23 
(6,750) (8,000) Updated – using full amount of
one-off Service Concession gain
allocated for learning estate –
for illustrative purposes only,
would require a Council
decision.
Net capital after
funding options
applied
34,500 24,750 31,120 
Cost of borrowing Net
Capital Cost over 60
years
1,853 1,330 1,672 Based on 31,120 over 60 years
Revenue Saving in
Energy Costs
(35) (35) 0 Estimated saving in energy
costs due to more efficient
building.
LEIP Income (25 years) (710) (710) (782) Assumed 50% paid equally over
25 years.
Net Cost of Borrowing
(first 25 years)
1,108 585 890 
Net Cost of Borrowing
(remaining 35 years)
1,818 1,295 1,672 
*The cost of construction does not include any fixtures and fitting, IT and equipment. Costs
associated with any additional staffing resource for the project are also not included. 
The delay in the decision from the Scottish Government on the bid has meant that the cost
of the project has risen to £39.120m, excluding any land purchase costs.  Additionally, the
following negative fiscal issues have arisen since the original report was presented:

Page 35

 The General Capital Grant from Scottish Government for 2024-25 was £0.937m
lower than the previous year. As we set a 3 year capital programme this impact is
doubled for years 1 and 2 where the budget has already been set therefore causes a
gap in the capital programme of almost £1.9m. Note that due to this reduction we
have removed the £3m capital grant skimming detailed in the original option shown in
the table above, therefore increasing the pressure further. 
 Construction Sector Inflation has slowed from the unprecedented rises we saw
through 2020-2023 which were at times around 15%.  Construction cost inflation in
Scotland has been rising around 5% per annum in the past 12 months however some
forecasters predict there may be a stabilising of around 3.5% in future
years.  However as we have seen, this can fluctuate greatly due to global or external
factors linked to supply of material, energy and labour.  Notwithstanding this, given
this project would take some time to complete there is a high risk that costs will
increase beyond the latest figures noted in the table above;
 Recently there have been a number of pressures on the Capital Budget: 
o Surveys of the Councils Learning Estate have identified RAAC in one building
which must be removed. Estimated costs associated with this are £3m. 
o As a result of a significant weather event on 7 October 2023, Argyll and Bute
the Council activated the Bellwin scheme in relation to the recovery costs
associated with the incident. Capital expenditure does not qualify therefore
any long term replacements to infrastructure such as bridges cannot be
claimed through the scheme resulting in an estimated pressure of £4.348m. 
o As a result on ongoing rises in inflation the costs associated with Rothesay
Pavilion continue to rise. It is uncertain at this stage the full financial impact
this is estimated to be circa £8.425m. 
Should the Scottish Government fund 50% of the project then based on the updated figures
above the Council would need to fund £11.560m (this would be subject to any locational
uplift being applied by Scottish Government). Through a combination of the increased costs /
timescales caused by the funding announcement, increased construction inflation, worse
than anticipated budget settlement and other capital budget pressures Officers are of the
view that the project would only remain affordable if Members are prepared to take hard
decisions to reduce other Council areas of capital and / or revenue spend.   
If Members decided not to proceed with the LEIP project, it should be noted that while this
will reduce the pressure on the capital programme there will still be a requirement to utilise
the £9m earmarking for a package of significant upgrading works to the existing Tobermory
Primary and High School.