ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 22 FEBRUARY 2024
INTRODUCTORY REPORT AND RECOMMENDATIONS FOR BUDGET PAPERS 
1.  EXECUTIVE SUMMARY 
1.1 This report introduces the full package of papers included in the budget packs in
relation to the revenue and capital budget. 
REVENUE PACK 
Revenue Budget Overview
1.2 This report summarises the overall revenue budget position covering funding,
expenditure and savings.  It also sets out the assumptions and proposals around
non-pay inflation and the cost and demand pressures for inclusion in the revenue
budget. 
1.3  The Local Government Finance Circular 08/2023 was published on 21 December
2023 provides detail of the provisional total revenue and capital funding allocations
for 2024-25.  The Council’s provisional General Revenue Grant is £237.475m
(there is also £4.526m of Revenue Specific Grants).  
1.4 The Council Tax budget for 2023-24 was set at £58.896m.  The growth has been
estimated at 0.5% for 2024-25 which amounts to £0.294m.   
1.5 The budget for 2023-24 has been rolled forward into 2024-25 and the changes to the
2024-25 base budget are summarised below: 
 Removal of one-off Management/Operational savings of £1.053m
 Removal of cost pressures relating to 2023-24 only of £0.442m
 Adjustment re floral displays as agreed at EDI Committee of £0.008m
 Recognition of the 2023-24 Teachers pay award being agreed at a higher
cost than the original estimate by £3.333m 
 Recognition of the 2023-24 SJC pay award being agreed at a higher cost
than the original estimate by £2.942m 
 Adjustment to ferries budget of £0.191m following confirmation of specific
grant
 Adjustment to base of £0.024m regarding Council Tax collection rates as a
result of the Business Process Review (BPR)
 Removal of inflationary contingency of £0.058m. 
1.6 The revised payment to the Health and Social Care Partnership, reflects 2023-24 in
year adjustments and the net changes to the settlement in respect of Social Work
that we have been directed to pass over to the Health and Social Care Partnership. 
The revised payment amounts to £74.326m.

Page 2

1.7 There are a number of measures to balance the budget that have previously been
agreed at the Council’s budget meetings in 2022 and 2023 which have a net effect
of reducing the 2024-25 budget gap by £0.093m. 
1.8 
1.9
There are a number of other measures to balance the budget that are for Council
approval, summarised as follows:
 General inflationary increase of 6% to fees and charges resulting in £0.385m of
additional income.
 10% reduction to the Live Argyll Management Fee. 
 Strathclyde Pension Fund Gain totalling £2.206m.
 New management/operational savings amounting to £3.950m.
 New policy options savings amounting to £1.024m. 
The setting of Council Tax should happen on the same day as the Council sets its
revenue budget as once all proposals are considered, Council Tax is the balancing
figure. The gap noted above is based on acceptance of the Council Tax freeze with
funding from the Scottish Government equivalent to 4.8% for Argyll and Bute being
made available. In order to get to a balanced budget, Council should consider
whether to reject the Council Tax freeze and increase Council Tax by 6.04% to
balance the budget. The alternative is that Council would need to fund the gap using
reserves or other funds held, which would be a one-off fix, however, Members need
to be mindful of the significant gap within the capital programme that requires
funding. 
1.10 The budget gap in the period 2025-26 to 2028-29 across each scenario is
summarised in the table below.   
Budget Gap 2025-26
£000
2026-27
£000
2027-28
£000
2028-29
£000
Total
£000
Best Case (1,503) (1,856) (2,130) (3,185) (8,674)
Mid-Range (6,583) (12,133) (15,991) (21,191) (55,898)
Worst Case (20,351) (38,317) (55,229) (73,943) (187,840) 
1.11  Five funding requests have been received and Members are asked to give
consideration to these requests and how they would be funded.   
Fees and Charges
1.12 This report sets out proposals for increases in fees and charges and the resulting
impact on income included in the revenue budget. 
1.13 The general increase to fees and charges is proposed at 6% for 2024-25 and is
expected to generate additional income of £0.385m. 
1.14 The changes proposed to the Social Work fees and charges are noted within the
report and have been the subject of a report to the Integrated Joint Board on 31
January 2024. 
1.15 Harbour Fees have been increased by 3%. This 3% increase is ring fenced to fund
asset improvement and sustainability within the piers and harbours. This is estimated

Page 3

to generate additional income of £0.279m. No general inflationary increase has been
proposed for piers and harbours dues in order that the service is cost neutral. 
Financial Risks Analysis 2024-25
1.16 This report set out the risks identified as part of preparing the revenue budget and
makes an assessment of the potential financial impact of these.  The financial risks
are monitored routinely throughout the year and actions put in place to mitigate
risks. 
1.17 There are 6 Council wide revenue risks identified for 2024-25 currently amounting
to £6.833m.  One of these risks have been classified as likely and four as possible
as follows:
- The pay award exceeding 3% has been categorised as likely although the
expectation is that additional funding would be forthcoming from Scottish
Government for an enhanced pay award, which has been the case for the
last 2 years. 
- Energy costs increasing by more than 20% greater than projected has been
categorised as possible due to ongoing rising costs;
- The IJB referring to the Council for additional funding should they have
insufficient reserves has been categorised as possible; 
- A 1% variation in council tax income which is uncertain due to the current
cost of living crisis impacting collection rates has been categorised as
possible; 
- A 1% variation of general inflation risk is categorised as possible. 
1.18 There are currently 38 departmental risks totalling £5.080m.  Five of the 38
departmental risks are categorised as likely with no risks categorised as almost
certain. 
Reserves and Balances
1.19 This report summarises the reserves and balances, sets out an analysis of risk
around the adequacy of reserves and balances and proposes a level of
contingency to be held in the General Fund Reserve.   
1.20 The Council had a total of £93.828m usable reserves as at 31 March 2023.  Of this
balance, £2.916m relates to the Repairs and Renewals Fund, £4.503m relates to
Capital Funds and the remainder of £86.409m is held in the General Fund, with
£79.466m of this balance earmarked for specific purposes. 
1.21 The General Fund contingency level remains at 2% of net expenditure.  This
monetary level has been adjusted to take account of the revised net revenue
expenditure proposed for 2024-25.  The revised contingency at 2% of net
expenditure amounts to £6.120m. 
1.22 Due to the pressure on the capital programme, officers have conducted a review of
the earmarked balances and have agreed release of earmarkings totalling £2.212m
which could assist with some of the gap in the capital programme.

Page 4

1.23 The table below summarises the position of the unallocated General Fund balance. 
Heading Detail £000 £000
Unallocated
General Fund as
at 31 March 2023
This is the balance that is
unallocated over and above the
2% contingency which amounts to
£5.691m 
1,252
Allocation to
General Fund for
2023-24 budget
Per Budget Motion at Council on
23 February 2023 
19
Earmarked
Balances no
longer required
Amounts previously earmarked
that can be released back to the
General Fund 
2,316
Transfer of
contingency to
maintain 2% level  
(429)
Forecast Outturn
for 2023-24 as at
31 December 2023  
(91)
Allocation from
unallocated
general fund
balance during the
year  
(8)
Estimated costs
associated with
weather incident
not claimable
through Bellwin
scheme  
(839)
Estimated
Unallocated
General Fund
Balance as at 31
March 2024  
2,220 
CAPITAL PACK 
Capital Plan Summary
1.24 This report details the revisions proposed to the capital plan approved in February
2023 for the period 2024-25 to 2025-26 and extends the capital plan for a further
year to 2026-27. The revisions are based on updated capital funding assumptions,
phasing and cost changes. 
1.25 The annual General Capital Grant for 2024-25 was estimated when the plan was
agreed last year to be £9.771m. This estimation was based on the Capital Spending
Review undertaken by Scottish Government which advised that the capital
settlements were likely to stay constant over the next five years. The updated
General Capital Grant based on the settlement is £8.834m and is therefore a

Page 5

£0.937m reduction on the previous estimate. This creates a gap of £1.782m across
the life of the capital programme. 
1.26 The amount of capital resources allocated to Private Sector Housing Grant (PSHG)
is £1.033m per annum, similar to previous years. 
1.27 In addition to the £8.834m general capital grant there is ring-fenced funding of
£0.379m for Walking Cycling & Safer Streets which will also be built into the capital
programme. 
1.28 The restricted capital funding of £5.122m is noted within Appendix 2 of the Capital
Plan Summary Report.  This relates to income which is restricted to specific
projects and this has been matched with expenditure against the projects, thereby
showing the gross cost of the projects.   
1.29 A comparison between the capital plan as at December 2023, including the new
block allocation for 2026-27, has been compared to the estimated funding and
there is gap up to 2026-27 of £2.076m. After adjusting for further anticipated
pressures the total gap within the capital programme is £29.843m.  Borrowing
could be taken out to cover the gap in the programme however this creates a
revenue cost. Every £1m of borrowing for the capital programme creates a revenue
pressure of circa £0.064m on average per annum which has not been built into the
revenue budget overview report. 
1.30 There are four significant areas contributing towards the total gap of £29.384m
which are detailed within the capital report and are as follows: 
 Removal of Reinforced Autoclaved Aerated Concrete (RAAC) from the
Council’s Learning Estate - £3m
 Weather event not claimable through Bellwin scheme - £4.348m
 Rothesay Pavilion - £8.859m
 Learning Estate Investment Programme (LEIP) - £11.560m 
While the costs associated with RAAC and the weather incident are unavoidable,
Members will be required to make decisions regarding the proposals relating to
Rothesay Pavilion and LEIP. 
1.31  Although the direct impact of COVID on most local services has reduced or even
ceased altogether over the last 12 months, COVID-19 in conjunction with the UK
exit from the European Union and the Russian invasion of Ukraine, continues to
affect worldwide supply chains. This has the impact of reducing the availability of
supplies and materials resulting in significant cost increases through a combination
of higher prices and longer materials delivery lead times. 
Corporate Asset Management Strategy and Plan
1.32 This report outlines the overall principles, policies and priorities within the Councils
Asset Management Strategy and Plan.

Page 6

1.33 This report identifies key issues for this planning cycle in managing the asset base,
the proposed actions and any risk assets not addressed through the proposed
Capital Plan.  It includes the Group and Service Asset Management Plan summary
templates.  
2. RECOMMENDATIONS 
2.1 It is recommended that the Council: 
a) Approve the revenue estimates for 2024-25 and that consequently the local
tax requirement estimated at £63.114m is funded from Council Tax. 
Approve the following rates and charges for the year, 2024-25: 
1. Council Tax to be paid in respect of a chargeable dwelling in Band “D”
of £1,568.54 representing a 6.04% increase.
2. Council Tax to be paid in respect of a chargeable dwelling in each of
the other valuation bands in accordance with Section 74(1) of the Local
Government Finance Act 1992 as amended.
3. Business Rates as determined by Scottish Ministers. 
b) Approve the revenue budget for 2024-25 as set out in the revenue budget
overview report. 
c) In respect of the gain received from the reduction in the Strathclyde Pension
Employer’s Contribution rate between 17.5% and 6.5% over 2024-25 and
2025-26:  
1. Note that £2m is proposed to be used towards the Council revenue
budget each year over the next 4 years (see management/
operational savings).  
2. Agree that the balance remaining attributable to all Council
employees is transferred to the General Fund and set aside for
transformational/spend to save projects.   
3. Agree that HSCP projects that fit the above criteria (point 2 above) be
eligible for funding up to the value of £6.106m with the release of any
funding delegated to the Chief Executive and the Executive Directors
of the Council.
4. Note that reports on the drawdowns from the General Fund balance
will be submitted to Policy and Resources Committee as part of the
monitoring pack.   
d) Approve a base allocation to the Health and Social Care Partnership of
£74.326m for 2024-25.  Approve indicative base allocations for 2025-26 of
£74.326m and 2026-27 of £77.379m.  The level of future years funding is
subject to the level of Scottish Government funding and the Council’s overall
financial position in future years. 
e) Endorse the new management/operational savings as outlined in Appendix
5 of the revenue budget overview report and approve the policy savings
options as outlined in Appendix 6 of the revenue budget overview report.

Page 7

f) Consider the five funding requests received as set out within Appendix 8 of
the Revenue Budget Overview Report.  
g) Approve the following in relation to fees and charges with effect from 1 April
2024 unless otherwise noted: 
1. Approve the proposals for the fees and charges inflationary increase
of 6% and approve the charges that are over and above inflation.  Note
that this would generate additional income of £0.385m in total.   
2. Approve no increase to school meal charges in 2023-24 as detailed in
section 3.6.2 of the Fees and Charges report.
3. Approve the changes proposed to the Social Work fees and charges.
4. Approve all other charges as noted within the Fees and Charges
Schedule. 
h) Note the financial risks analysis. 
i) Approve the contingency level for the General Fund balance at a level of 2%
of net expenditure, equivalent to £6.120m and note the report on reserves
and balances. 
j) Approve the capital plan as set out in Appendix 3 of the capital plan
summary report, noting that consideration needs to be given as to how to
fund the £29.384m gap. 
k) In respect of LEIP: 
1. Note the successful award of a major bid funding bid;
2. Note the funding provided by Scottish Government is not a capital grant
for full cost of project – in summary SG will provide up to 50% of eligible
costs over a 25 year period following completion.  The Council will
require to pay the total cost up front; 
3. Note due to the 1year time delay of LEIP announcement the requirement
to open the new Campus by December 2027 (which was the original
timescale) cannot be met – now forecast for October 2028 at earliest;
4. Note the updated timescale programme forecast as outlined at
Appendix A + B;
5. Consider overall affordability of project as outlined at Appendix C and
determine whether: 
1. Proceed with the LEIP Project in the knowledge that Members will be
required to take hard decisions to reduce other Council areas of
capital and / or revenue spend, in future revenue budgets / capital
programmes.
Or
2. Not to proceed with the current LEIP Project based on current capital
affordability considerations and as an alternative develop a
programme of significant building fabric upgrade works to (a) prolong
the operational life and (b) enhance learning and teaching spaces of

Page 8

the existing school buildings (Primary and Secondary) at Tobermory
using £9m of previously earmarked funds. 
l) In respect of Rothesay Pavilion note that a further paper will be available for
Members at the Special Meeting of the Council prior to the budget meeting
which will provide detailed information on the project and recommendations
for consideration.    
m) Approve the Corporate Asset Management Strategy and Plan including the
Asset Group Summaries. 
3.  IMPLICATIONS 
3.1 Policy – There are policy implications associated with proposals to balance the
revenue budget as well as the policy options that have been subject to employee
consultation.   
3.2 Financial – The report outlines the revenue budget position over 2024-25 to 2028-
29 and the funding and commitments for the capital plan 2024-27. 
3.3 Legal – Any legal implications have and will be considered when developing the
savings options required for the revenue budget.  The funding for new capital
expenditure may not address all the statutory and regulatory requirements in
relation to health and safety. 
3.4 HR – Any HR implications have and will be considered when developing savings
options required for the revenue budget.  There are risks that the capital funding
available will have an impact on the sustainability of the property design team and
the design team within Roads and Amenity Services. 
3.5 Fairer Scotland Duty – See Below 
3.5.1 Equalities - Equality and Socio-Economic Impact Assessments have been carried
out where appropriate for savings options already agreed or developed. Equality
and Socio-Economic Impact Assessments will be a key consideration in developing
future savings proposals. These assessments can be found on the Councils
website here: Equality and Socio-Economic Impact Assessments (argyll-
bute.gov.uk) 
3.5.2 Socio-Economic Duty - Equality and Socio-Economic Impact Assessments have
been carried out where appropriate for savings options already agreed or
developed. Equality and Socio-Economic Impact Assessments will be a key
consideration in developing future savings proposals. 
3.5.3 Islands Duty – Islands duty is considered as part of the Equality and Socio-
Economic Impact Assessments

Page 9

3.6 Climate Change – The Council is committed to addressing climate change and
reviews of how Services are delivered is ongoing within the available budget
resources. 
3.7 Risk – There is a separate report assessing financial risks and there is also an
overall assessment of risk included within the separate report on Reserves and
Balances. In respect of the capital programme, there are risks around the level of
capital receipts, ongoing cost increases, grant funding, future pressures and there
are a number of other risks highlighted within the corporate asset management
plan. 
3.8 Customer Service – There may be some customer service implications arising from
previously agreed savings options and the new policy options.   Future customer
service implications will be considered when developing savings options. 
3.9 The Rights of the Child (UNCRC) - None 
Kirsty Flanagan
Executive Director/Section 95 Officer
6 February 2024 
Policy Lead for Finance and Commercial Services: Councillor Gary Mulvaney 
For further information please contact Anne Blue, Head of Financial Services