ARGYLL AND BUTE COUNCIL COUNCIL
CAPITAL INVESTMENT BOARD 27 FEBRUARY 2025
CORPORATE ASSET MANAGEMENT STRATEGY AND PLAN 
1.  EXECUTIVE SUMMARY  
1.1 Asset management is a structured and systematic approach to managing fixed
assets on an ongoing basis. The Council has a large and varied collection of
assets including buildings, vehicles, transport infrastructure (roads / bridges /
piers), ferries, parks, cemeteries to information technology hardware and
software.  Assets are essential to the operation of the Council and ensuring they
evolve and remain fit for their intended purpose is key to the function of the
organisation and service delivery.  Successful asset management addresses all
phases of an asset's life cycle, from pre-acquisition through to retirement. 
Effective asset management planning means knowing what you own, where it's
located, what it costs you, what it will cost you in the future, whether it will support
current and future service delivery and who is responsible for it.   
1.2  The Council adopts a systematic approach to asset management and this paper
sets out the principles, polices and summary priorities for 2025-26.  The Strategy
and Plan are consistent with the Prudential Code for asset management and the
outcomes of the Best Value 2 review.  This report in conjunction with appendices
and wider Budget Pack forms our Corporate Asset Management Strategy and
Plan.  Asset Management is delivered by all departments and teams of the Council
and overseen by the Capital Investment Board.   
The underlying principles of the Council’s Asset Management Strategy and Plan
are:- 
• The Council’s commitment to sound asset management;
• All Council assets are required for operational, regeneration, economic and
commercial development purposes;
• There are clear links between asset management, the Corporate Plan, the
Argyll and Bute Outcome Improvement Plan (ABOIP), Live Argyll and the
Argyll and Bute Health and Social Care Partnership (HSCP);
• Asset Management is linked to available resources and budgetary
considerations;
• There are sound Governance arrangements for asset management; and
• Asset management requires to be forward looking to deliver the assets the
Council requires for future service delivery.

Page 2

ARGYLL AND BUTE COUNCIL COUNCIL
CAPITAL INVESTMENT BOARD 27 FEBRUARY 2025
CORPORATE ASSET MANAGEMENT STRATEGY & PLAN  
2. INTRODUCTION 
2.1  The Corporate Asset Management Strategy and Plan establishes the Council’s
overall approach to management of its asset base. In particular it sets out: 
• The Council’s commitment to sound asset management;
• All Council assets are required for operational, regeneration, economic and
commercial development purposes;
• There are clear links between asset management, the Corporate Plan, the
Argyll and Bute Outcome Improvement Plan (ABOIP), Live Argyll and the
Argyll and Bute Health and Social Care Partnership (HSCP);
• Asset Management is linked to available resources and budgetary
considerations;
• There are sound Governance arrangements for asset management; and
• Asset management requires to be forward looking to deliver the assets the
Council requires for future service delivery. 
3. DETAIL 
Core Values of Asset Management 
3.1 Asset management is a structured and systematic approach to managing fixed
assets on an ongoing basis. This approach addresses all phases of an asset's life
cycle, from pre-acquisition through to retirement. Effective asset management
planning means knowing what you own, where it's located, what it costs you, what it
will cost you in the future, whether it will support current and future service delivery
and who is responsible for it.   
3.2 It is recognised that these general guiding principles can also be applied to the
management of non-fixed, or less permanent, assets such as vehicles, plant and
equipment. 
3.3 The Council will ensure that the assets it provides are used in a fair, consistent,
efficient and effective way, taking into account their social and environmental impact
and the needs and aspirations of our people, communities, areas and organisation. 
3.4 Asset management is the process of ensuring that the Council’s Assets are: 
• fit for purpose
• used efficiently
• maintained on a sustainable basis
• matched in investment terms to service needs.

Page 3

Approach and Commitment to Sound Asset Management 
3.5 The Local Government in Scotland Act 2003 provides the legal framework for both
the Prudential Code and the Best Value arrangements.  Under the Prudential Code
local authorities are authorised to make capital investments where it can be
demonstrated that these investments are affordable, prudent and sustainable.  A
local authority, which secures Best Value, is one, which promotes continuous
improvement in the performance of its functions. 
3.6 Asset management is a key element of achieving Best Value. Councils have a
statutory duty to deliver Best Value. This has significant implications for asset
management as Councils must:  
• ensure that management arrangements secure continuous improvement 
• balance quality and cost in relation to the procurement of assets 
• ensure asset management decisions contribute to sustainable development. 
3.7 Asset management has potential to contribute to achievement of efficiency savings. 
3.8 The Best Value 2 Asset Management templates published by Audit Scotland
essentially set out the direction of travel for asset management within the Council.
The desired outcomes of good practice contained within these templates have been
fully adopted and are being actively promoted and progressed by the Strategic Asset
Management Board. 
3.9 In line with Best Value Guidance: “Sound Management of Resources” the Council will
manage its assets to deliver the Council’s corporate and ABOIP objectives, by
providing the basis for corporate challenge and a focus on the future asset
requirements in respect of service delivery.   
Current Governance Arrangements for Asset Management 
3.10 Council governance of asset management by elected members is on the basis of the
Council directing the work of the Council through the Strategic Management Team.   
3.11  Responsibility for Council assets is held by the two Departments:
• Executive Director Douglas Hendry
• Executive Director Kirsty Flanagan 
3.12 These Departments are headed by an executive director reporting to the Chief
Executive and supported by heads of service who are responsible for day to day
service provision and the effective and efficient use of assets. Assets owned by the
Council but operated by the HSCP and Live Argyll continue to be the responsibility of
the Council.   
3.13 The Head of Commercial Services is the Chair of the Capital Investment Board and
is responsible alongside Section 95 Officer for the development of the Corporate
Asset Management Strategy, production of the Corporate Asset Management Plan,
and preparation of the Capital Plan – referred to as the Councils Priority Investment
Plans (PIPS).

Page 4

Council Current Asset Base 
3.14 The table below summarises the main operational and infrastructure assets of the
Council. 
Description Number  Description Number
Shared Accommodation
(Offices)
25  Roads (km) 2,286
Operational Depots 19  Public Road Bridges 903
Primary Schools (in use) 65  Car Parks 118
Secondary Schools 5  Marine Structures 41
2-18 Schools 4  Public Road Coastal
Protection (km estimated)
200
Joint campuses 1  Public Road Retaining Wall
(estimated)
1,000
Youth Centres 1  Public Conveniences 85
Adult Learning Centres 2  Waste Disposal facilities 12
Early Learning Centres 2  Ferries 6
School Houses 19  Airports 3
Special School for pupils
with complex additional
support needs
1  Cemeteries 131     
Homes for the Elderly 7  Children’s Homes 5
Hostel 3  Resource Centres 3
Leisure Centres 5  Crematoria 1
Community Centres 4  Lighting Units 14,642
Halls 5  Vehicles and Plant 634
Libraries 10  IT Systems and Devices
(estimated)
16,955 
Corporate Asset Management Plan and Priority Investment Plans (PIPS) 
3.15 Each year the Corporate Asset Management Plan is prepared on the basis of the
underlying principles of the Corporate Asset Management Strategy referred to above. 
The aim of the Corporate Asset Management Plan is to ensure that capital and
revenue expenditure is directed efficiently and effectively for the coming year.  The
Asset Management Plan is made up of a collective of Priority Investment Plans
(PIPs). 
3.16 In preparing this Asset Management Plan & PIPs services ensure that the
opportunity cost of financial resources tied up in assets is minimised and that there
is: 
• an integrated corporate approach towards asset management, capital
planning and budgeting process for both capital and revenue 
• a process for changing the Council’s asset portfolio consistent with the
Corporate Plan and ABOIP  
• a process for asset decision making which is consistent with services’
requirements

Page 5

• an identification of opportunities for innovation, asset investment or disposal 
• provision of a context for capital project evaluation helping to prioritise
decisions on spending. 
3.17 Each Executive Director is responsible for the completion of their respective PIPs. 
Service asset managers prepare the PIP Summary templates, which, when approved
by the Departmental Executive Director, are submitted to Capital Investment Board
and also discussed as part of scheduled Policy Lead Meetings.   The Capital
Investment Board evaluates each PIP prior to being discussed with respective Policy
Lead (including Asset Management Plans prepared by the HSCP and Live Argyll). 
3.18 
3.19 
3.20 
In preparing PIPs, service asset managers must consider the following guiding
criteria: 
• maximise the impact of all capital and revenue expenditure on assets  
• apply asset performance indicators and benchmarking (Condition,  Suitability
and Risk ) to ensure robust planning and decision making 
• maximise the utilisation of assets 
• reduce the unit costs of service delivery through smarter and more efficient
asset management 
• dispose of underperforming, unsuitable assets and assets which are at risk
and invest in “fit for purpose” assets  
• share assets with Community Partners and Third Sector to maximise public
benefit. 
Asset Management Plan and Priorities for 2025-26 
This Corporate Asset Management Plan for 2025-26 reflects the Council's strategic
objectives contained in the Argyll and Bute Outcome Improvement Plan (ABOIP) and
Corporate Plan to support Strategic Change, Service Development and Asset
Sustainability projects in 2025-26 and beyond. These projects have been developed
taking account of the future service delivery requirements of the Council, the Argyll
and Bute Health and Social Care Partnership (HSCP) and Live Argyll. 
On an ongoing basis all services assess the risk arising from the condition and
suitability of the assets they have responsibility for. This enables the prioritisation of
projects for inclusion within the capital plan.  The continued reduction in available
capital budgets and revenue maintenance budgets has had an impact on planned
maintenance programmes. This in turn increases the rate of deterioration in asset
condition across the Council leading to increasing demand for capital investment in
the asset base to maintain service delivery.  
3.21 
3.22
The Priority Investment Plans (PIPs) that outline the proposed resource allocation,
condition and prioritisation of capital expenditure are outlined at Appendix 1.   
It is clear from the PIPs that the real terms reduction of available capital resources
year to year plus recent unprecedented increases in inflation and global events is
resulting on the majority of investment towards Asset Sustainability – i.e. ensuring
our current assets remain fit for purpose.  There is minimal service development,
transformation or strategic change mainly due the higher value of such projects.   
High Risk Assets Not Addressed within Capital Plan Proposals for 2025-26

Page 6

3.23 The Capital Programme for 2025-26 has been structured to address the majority of
foreseen Council’s high risk assets.  High risk unfunded assets requiring attention in
2025/26 totalling £376k are note below. 
• ICT Network Equipment - £71k
• Riverside Leisure Centre, Dunoon – Structural Repair Works - £305k. 
Opportunities for Improvement 
3.24 It is recognised that there are opportunities to take a more strategic approach to
capital planning and to enhance existing governance arrangements around capital
investment activity.  The Executive Leadership Team is committed to undertaking a
future review and recommendations will be reported to members during 2025-26 in
this respect.  Whilst the detailed specification of requirements of the review has still
to be developed, at this stage, it is anticipated that the review will include the
following: 
• Enhanced governance arrangements, including greater member involvement in
the allocation of capital resources.  This would include a review of current Priority
Investment Plans and whether they remain fit for purpose in their current format
and provide Members with sufficient information for decision making; 
• Longer term financial planning, including longer term Capital Plan (5-10 years); 
• Integrated capital forecasting, treasury strategy and debt charges (revenue
budget) modelling; 
• A review of the capacity within the current debt charges budget for additional
investment, reflecting capital planning and treasury borrowing assumptions; and 
• An updated Capital Strategy, to help ensure that we are investing in our
infrastructure, to support council key strategic priorities. 
4. CONCLUSION 
4.1 The aim of this Corporate Asset Management Strategy & Plan including summarised
Priority Investment Plans (PIPs) is to ensure that asset management takes place in a
systematic and well governed manner taking cognisance of corporate policies, plans,
systems and processes.   
5. IMPLICATIONS 
5.1 Policy – The report sets out the Council’s policy and
prioritisation in respect of Asset Management. 
5.2 Financial -  This strategy and plan follows Prudential Code and
outlines the planned capital investment and funding
for the capital planning period 2025-28..

Page 7

5.3 Legal -  Statutory and Regulatory requirements in relation to
Health and Safety have been provided for within
capital spending plans.   
5.4 HR -  There are risks that the funding available will have an
impact on the sustainability of the Property Design
Team and the design team within Roads and Amenity
Services. 
5.5
5.5.1
5.5.2
5.5.3
Fairer Scotland Duty -
Equalities - 
Socio-Economic Duty -
Islands Duty - 
Will be considered as appropriate.
Will be considered as appropriate. 
Islands duty is considered as part of the Equality and
Socio-Economic Impact Assessments
5.6 Climate Change As outlined in the Policy, Plan and PIPs there is
specific funding being allocate to investment relating
to dealing with the impacts of climate change and
reducing the Council’s carbon footprint.   
5.7 Risk -  None. 
5.8 Customer Service -  Investing in assets will continue to ensure access and
sustainability of services.   
5.9 The Rights of the Child
(UNCRC)
None. 
Kirsty Flanagan, Section 95 Officer
Douglas Hendry, Executive Director with responsibility for Commercial
Services
Ross McLaughlin, Head of Commercial Services
13 February 2024 
Policy Lead for Financial Services and Commercial Services:  Councillor
Ross Moreland 
APPENDICES:-
Appendix 1 – Service Priority Investment Plans (PIPS)

Page 8

PRIORITY IMPROVEMENT PLAN – ASSET GROUP SUMMARY 
Asset Group Education  3rd Tier Manager Susan Tyre / Wendy Brownlie
Description of
Asset Group
and Condition
Assessment 
ABC Learning Estates Strategy – Learning Environments in all schools should have a suitability grading A or B
A=good; B=satisfactory; C=poor; D=bad 
Asset Group No
and
/or
val
ue.
Condition Suitability
A B C D A B C D
Primary Schools (in use) 65 4 61 0 0 38 27 0 0
2-18 schools 4 1 3 0 0 1 2 1 0
Joint Campus 1 1  0 0 1  0 0
Secondary Schools 5 4 1 0 0 4 1 0 0
Complex addition needs schools 1  1 0 0 1  0 0
Adult learning centres, and a Youth
Centre
2  1 1 0  1 1 0
Early Learning and Childcare Centres 2  2 0 0  2 0 0
School Houses 19   0 0   0 0
Investment
(current and
planned)    Funding source Current Year Anticipated Investment (£m)  
2024-25 (£m) 2025-26 2026-27 2027-28
Block Allocation
Scottish
Government 2.226 2.219 1.988 1.988
Block Allocation
Carried Forward
Scottish
Government 2.160 (0.279)  
New Schools
Scottish
Government 0.710   
1140 Hours
Scottish
Government 0.243   
Gaelic Grant
Scottish
Government 0.038   
CO2 Grant  0.113   
RAAC - Capital
Allocation
Council
Reserves 3.200     
8.690 2.946 1.988 1.988 
2024-25 Overview 
Investment Strategy
 The Investment Asset strategy for Education in 2023-24 was to focus on undertaking major maintenance and
keeping assets that we have wind, watertight & safe ensuring schools remain in a minimum B category and avoid
slippage into C 
 In 2023-24 work was done to maintain or improve the suitability of several schools including scoring of;
Dalintober Primary, Castlehill Primary, Garelochhead Primary, Kilninver Primary, Islay High,  Iona Primary,
Kilchattan Primary, Port Charlotte Primary, Bowmore Primary, Dalmally Primary, Kilmodan Primary, Sandbank
Primary, St Muns Primary, St Andrews, North Bute, Tiree High School
 Works to create a high quality learning environment internal and external at our early learning and childcare
settings: Clyde Cottage Nursery, Park Primary, Dunbeg, Easdale and Kilchattan
 Works to create new Learning Centres in Campbeltown (Castlehill Primary) and Islay High along with design work
for new Learning Centres Tobermory and Hermitage Academy 
Risks
Asset sustainability

Page 9

 Significant backlog of maintenance work includes roof repairs, rewiring, damp repairs, heating upgrades and
suitability works. Failure to invest in planned capital maintenance in a timeous manner will see a reduction in the
condition scores and could result in component failure and building closure. 
 Council agreeing to progress with LEIP funding following Business Case.
 Diminishing level of investment coupled with increased costs (inflation and construction costs) mean many
buildings and building elements are deteriorating at a rate which may not be able to be addressed via revenue
(maintenance / reactive) expenditure.   This is beginning to impact on the use of buildings, capacity of the school,
flexibility to deliver the curriculum, health & safety standards, support for pupils with complex needs and our
inspection ratings.  This will continue unless the number of properties are reduced or the capital and revenue
budget is increased.
Service Development
 Updated Business Case being prepared for LEIP funding for Tobermory will result in significant investment to
address condition and suitability (service development project)
 Discovery of RAAC within John Logie Baird Primary resulted in significant investment identified for repairs to
replace (service development project)
 Scottish Government roll out of Universal Free School Meals (UFSM). The UFSM has identified works to be
carried out in identified schools to support the roll out of free school meals to all primary pupils within Scotland.
Unknown if this will be back on the agenda for Scottish Government during 24-25. 
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
 At current funding levels within the block allocation the focus will remain on high and medium risk Asset
Sustainability priority projects – therefore no funding is allocated to ‘service development’ projects
 John Logie Baird works ongoing to remove RAAC and reinstate learning spaces
 Continued development of Business Case as part of LEIP to bring new Campus to Mull
 The aim is to improve condition scorings at the following schools: Tobermory 3-18
 suitability scores in the following schools: Lochgoilhead Primary, Keills Primary, Tarbert 2-18
 As per decision of Community Services Committee in August 2023, Capital works relating to new Additional
Support Needs provision by way of new learning centres in, Mull and Hermitage Academy.
 £2.219M reserved for Asset Sustainability will be used to undertake major maintenance and keeping assets that
we have wind, watertight & safe ensuring schools remain in a minimum B category and avoid slippage into C 
Unfunded Investment Priorities 
None identified that would cause Health and Safety risk 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26
Asset Sustainability Gaelic – See below nil
Service Development  Climate Change - See below Climate Change - See below
Strategic Change Bid for Learning Estate Investment
Programme (LEIP) Funding
Climate Change - See below
Major opportunity to access Government flagship investment programme Learning Estate Investment Programme
(LEIP) for new campus on Mull.  
In relation to climate change, opportunities for external funding will continue to be explored to allow delivery of
projects similar to the Non-Domestic Energy Efficiency Framework (NDEEF). These opportunities could offer low
carbon solutions throughout the wider Argyll and Bute area, which would not only assist the Council in its journey to
Net Zero Carbon (NZC) but would also result in financial benefit through revenue savings or additional income. The
delivery of these types of project which fall into a spend-to-save category will also consider Prudential Borrowing as a
funding source i.e. where simple payback breaks even in relatively short timeframes.

Page 10

Links to relevant strategies
Corporate Asset Management Strategy
Learning Estates Strategy 
ASN provision across Argyll and Bute
CO6: We have an infrastructure that supports sustainable growth

Page 11

PRIORITY IMPROVEMENT PLAN – ASSET GROUP SUMMARY 
Asset Group Council Owned
Buildings 
Group Lead / 3rd
Tier Manager
Ross McLaughlin & Craig Houston 
Description of
Asset Group
and Condition
Assessment 
This is a new Asset Grouping for 2025/26 as specified in the newly adopted Capital Investment
Strategy.  The majority of Council owned buildings are part of this grouping that includes Offices,
Health and Social Care Buildings, hostels, LIVE Argyll Properties and Depot Buildings.  It excludes
Education Buildings (schools) and operational specific buildings like public toilets, airport buildings
and crematoria.   
Building condition and suitability is measured in accordance with the Local Government
Benchmarking Framework (LGBF). The condition rating of buildings is measured through an
assessment of the main elements of the building (roof, walls, windows, doors, services etc.) via a
weighted scoring matrix. Suitability is measured in a similar manner but instead of building
elements, assesses themes including: location; accessibility; building facilities; the working
environment; and ICT infrastructure etc. These assessment methodologies have recently changed
and in moving forward will require more input/assessment for each property. 
All information is recorded within the Council’s property management system, Concerto, and
LGBF returns are made on an annual basis
SHARED OFFICES 
Group No. Condition  Suitability 
A B C D A B C D
Owned 24 2 22 0 0 9 11 4 0
Leased 1 0 1 0 0 0 0 0 0 
LIVE ARGYLL
Group No. Condition  Suitability 
A B C D A B C D
Community Centres 4 0 2 2 0 0 3 1 0
Leisure Centres 4 1 3 0 0 0 3 1 0
Halls 5 1 4 0 0 1 3 1 0
Libraries 11 4 7 0 0 2 7 2 0
Museums 1 0 0 0 0 0 1 0 0
Archives 1 0 1 0 0 0 1 0 0
Sandbank HQ 1 0 1 0 0 0 1 0 0
Sport Centre 1 1 0 0 0 0 1 0 0
Campbeltown
Pavilion
1 1 0 0 0 0 1 0 0 
HOSTELS
Group No. Condition  Suitability 
A B C D A B C D
Hostels 2 0 2 0 0 0 2 0 0 
HSCP BUILDINGS
Group No. Condition  Suitability 
A B C D A B C D
Elderly Persons Homes 7  5 2   5 2 
Children’s Homes 5 3 2   3 2  
Resource Centres 3  3   1 1 1 
Offices 8 3 5   1 6 1 
Other 6  6   2 3 1

Page 12

DEPOTS 
Asset Type No. Condition Suitability  
A B C D A B C D
Depots/Workshops 22 1 12 6 3 1 12 8 1 
A=good; B=satisfactory; C=poor; D=bad
Investment
(current and
planned) 
Funding  Funding source 
Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Block allocation
Scottish
Government 1.374 1.281 1.146 1.146
Block allocation
Carried Forward
Scottish
Government 3.049 2.267 (0.011) 0.000
Non Domestic
Energy
Efficiency
Framework
(NDEEF)
Scottish
Government
0.124 1.063 0.00 0.00
Islands
Programme
Scottish
Government 0.400 0.050  
Partner
contribution 
HSCP
0.881   
Strategic
Housing Fund
Council
0.080   
Totals  5.908 5.934 1.135 1.146 
2024-25 Overview 
Investment Strategy 
This is a new asset category however there has been notable projects delivered or planned during 2024-25 by LIVE
Argyll, Shared Offices, Health and Social Care Partnership and Depots.  
LIVE Argyll have completed renovation works at Lochgilphead CEC, upgrades to Health Suite at Aqualibrium.  Moat
Centre, Rothesay re-wired.  New reception and windows at Rothesay Leisure Centre.  During upgrade works to
Riverside Leisure Centre Dunoon significant structural corrosion was identified.  All works have paused and strategic
approach to address the structural issues are now required.  
Shared Officers – continued rationalisation of assets, mothballing of Whitegates, leasing out of Helensburgh and
Lomond Civic Centre.  Planning for redesign of Kilmory and rewire.  
Depot Buildings – Demolition of dangerous building and erection of temporary building at Bishopton Road
Lochgilphead.  
Health and Social Care Partnership – Tigh A Rudha, Tiree upgrade remains ongoing.  The recently acquired Kintyre
Care Home has also required several capital investments to upgrade fabric and energy efficiency.  
Hostels – Window investment at Oban Hostel and roofing repairs at Dunoon.  
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
Principles are:-
1. Asset Sustainability
Building assets require to be safe and health and safety compliant to remain operational.  Due to the size of Council
portfolio and increasing cost of construction and maintenance substantial investment is required to simply maintain
our current building stock.   Property condition and suitability assessments are reviewed on a 5 year cycle to prioritise
investment. Work is required to maintain the facilities in a wind and water tight condition and to ensure compliance
to legislative and regulatory requirements. Work will include, roof refurbishment, boiler replacement, re-wire of

Page 13

ageing buildings, remedial work to emergency lighting and fire prevention systems and this will include other building
plant equipment. Notable Asset Sustainability projects that are planned are Struan Lodge (Dunoon) re-wire (currently
out to tender and subject to review) and similar full re-wire required of Kilmory which will form part of wider
redesign project.  Works to investigate structural issues at Riverside, Dunoon and solutions will be a significant
project that requires strategic overview.  
It is also notable that Care Inspectorate inspect Hostels and Care Homes and substandard buildings may be subject to
enforcement and potential closure.  
2. Business Development
The asset group managed by differing departments is ageing and requires more capital investment to ensure it
remains in an operable state. Year-on-year the Capital Investment is becoming less which in turns places greater
strain on an already insufficient central repairs budgets. Underinvestment of Capital funds will lead to facilities that
will further deteriorate in condition and suitability and inevitably reach a stage where they are deemed not fit for
purpose. Failure to maintain assets and ensure they are fit for purpose will adversely impact on Council and partners
ability to deliver agreed service specification requirements and fulfil charitable objectives. Business Development
activity may assist teams or partners delivering services in another way that may reduce or eliminate need for
buildings – can be a precursor to Principle 3 (Disinvestment) Notable Business Development projects being
progressed in 2025/26 include review of Corran Halls business model, Care Home Programme and Library Services in
partnership with HSCP and Live Argyll.  Thomson Court Care Home on Rothesay expanded bed spaces to meet
increased demand.  
Although Capital funding is very limited, it is important for liveArgyll to be aspirational in its business planning and
strategic thinking. Being responsive to changing customer needs and usage trends, liveArgyll would propose business
case development of Corran Halls, Ramsay Hall, Sandbank Building and several Libraries.
Investment in depots to create inspection or 3rd Party MOT Stations is also considered to be a business development
opportunity particularly in Campbeltown, Helensburgh and Lochgilphead.  
Construction has commenced on new Business Parks at Kilmory and Oban Airport.  Business development could
include the construction of business / industrial units for commercial lease to create income that can be reinvested
into other priorities.  
3. Disinvestment, Disposal or Repurpose Buildings not fully utilised
Success has been demonstrated with maximising efficiency of our building stock via Our Modern Workspace
Programme where 10no office buildings have been mothballed or repurposed.  More emphasis will be placed on this
in coming year with focus on Kilmory HQ and Live Argyll + HSCP Properties.  Notably in Lochgilphead and Oban.  The
depot rationalisation board will also continue.  
Reducing the number of buildings reduces operational costs such as utilities, non domestic rates, maintenance and
cleaning.   
UNFUNDED PRIORITIES 
Service Priority Cost (£) Are costs
indicative
or
calculated)
Estimated
funding
shortfall
Asset category (asset sustainability,
service development, strategic
change)
Riverside Leisure Centre
(Dunoon)  – temporary
structural works 
£305,000  Calculated £305,000 Asset Sustainability  (ESSENTIAL)
Riverside Leisure Centre
(Dunoon)  – RIBA Stage 0
- Business Case
Development for new
Leisure Centre 
£200,000  Indicative  £200,000  Strategic Change 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26

Page 14

Islands Programme
Funding  Part funding Tigh A Rudha, Tiree Islands Programme Funding – Thomson
Court Care Home Rothesay
Scottish Government
Funding – Bairns Hoose
Grant award Development of Bairns Hoose project for
HSCP
Place Based investment
Funding
Our Modern Workspace funding for
office rationalisation in Rothesay 
Strategic Housing Fund For Housing related enabling works or
delivery 
Links to relevant strategies
Capital Investment Strategy
Local Development Plan 2
Council Corporate Plan
De-carbonisation Plan

Page 15

PRIORITY INVESTMENT PLAN – ASSET GROUP SUMMARY 
Asset Group ICT 3rd Tier Manager Gerry Wilson
Description of
Asset Group
and Condition
Assessment 
Asset Group No
and/or
value.
Condition Suitability
A B C D A B C D
Server Infrastructure
Overall 1,941k 859k 890k 24k 469k 859k 890k 24k 469k
PC, Laptops and
Tablet Devices -
Corporate
£906k 276k 213k 226k 190k 276k 213k 226k 190k
PC, Laptops and
Tablet Devices -
Education
2,496k 987k 516k 478k 514k 987k 516k 478k 514k
Communications
Equipment incl
network devices and
Broadband
2,492k 811k 962k 496k 223k 811k 962k 496k 223k
Supported Business
Software
Applications(Number)
75 54 12 9 0 50 14 11 0 
Investment
(current and
planned) 
Funding  Funding
source 
Current
Year Anticipated Investment (£m)
2024-25
(£m) 2025-26 2026-27 2027-28
Block Allocation Scottish
Gov  0.771 0.768 0.688 0.688 
Block Allocation
Carry forward
Scottish
Gov 0.043 0.060 0.132 0.000  
Additional Council
Funding
Council
Reserves 0.605 0.453 0.000 0.000 
Total    1.419 1.281 0.820 0.688 
2025-26 Overview 
Investment Strategy 
Asset Sustainability – All of the Council’s ICT assets are replaced on a rolling cycle. PCs and Laptops are
replaced on a 4 year (corporate) or 5 year (education) cycle. Major infrastructure assets such as servers,
firewalls, and network routers and switches are replaced every 6 years. This is an industry standard
approach to the maintenance of critical infrastructure designed to minimise the risk of service failure which
would otherwise result in poor system reliability, the unavailability of major systems, and a consequential
failure to deliver front line services.  The expected lifespan of ICT infrastructure assets is determined by
manufacturer support availability, age, or fitness for purpose. 
The ICT Service normally apportions part of the ICT Block Allocation each year to cover the annual PC
Replacement and network infrastructure asset costs. Every six years we also have to prioritise our spend on
our two data centres (the heart of the ICT environment) which normally means we have to allocate the
majority or all of the block allocation for that year to servers and network equipment. The data centres
continue to host several hundred council applications as the true cost of migrating to the cloud remains

Page 16

unaffordable for many systems. The data centre upgrades started this year and will continue through
2025/26.
We face enormous inflationary pressures on the ICT Capital Programme as the post pandemic global supply
crisis impacts on technology equipment pricing. The current need to prioritise investment in critical server
and network assets for the data centres means there would have been little or no funding available for PC
replacement or other service development projects without the additional capital agreed at the last budget
meeting or without drawdowns from the Capital Contract Increases Earmarking fund to cover some of the
inflationary and exceptional cost increases. Our strategy is therefore based on the proposed drawdowns
from those two funding sources being allocated to the affected asset replacement projects before the block
allocation is then distributed across the remaining sustainability projects – IT Network and Server
infrastructure and PC Replacement.
Service Development and Strategic Change - The ICT Development framework establishes a consistent and
transparent method for the evaluation of ICT business case based proposals being presented to the Capital
Investment Board.  The framework allows competing demands for Council resources to be compared like for
like with the purpose of establishing an ICT Development Plan that includes a mix of small and significant ICT
developments that are both affordable and deliverable.  The ICT Development Plan determines the ICT
Asset service development priorities and the levels of funding required to meet them. No new business
cases have been approved at the Capital Investment Board for new business application systems or
replacement of existing business application systems
Risks
1. All ICT Assets - Failure of key infrastructure supporting technology components that are critical for day to
day service delivery across all services of the Council. The severity and the reach of the impact will very
much depend on which components fail and consequences for individual services but could also be cross
Council affecting.  As technology components age and move out of support, the Council risks non-
compliance with PSN, Cybersecurity and PCI DSS obligations.
2. PCs and laptops are currently replaced on a 4 year Corporate and 5 year Education cycle with no
warranty or maintenance on PCs after the first 3 years. This has consequences for the reliability of
desktop equipment. On warranty expiry, the Council is required to effectively self-insure against failure. 
3. Service Development - In addition to impacting our ability to comply with our security obligations, the
risk of underinvestment for key business application systems will result in missed opportunities for
greater efficiencies and service improvements across council services. 
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
Please Note – anything identified as RED RISK is unfunded.
Server Sustainability 
Replacement of Server equipment in Kilmory and GWITC so that our infrastructure is robust, supported and
fit for purpose for at least 6 years.  Major investment on the data centre servers is underway to ensure that
the servers will require minimum investment over the following 5 years. The funding requirement for
servers and associated software has been met from a combination of the block allocation and drawdown
from the Capital Contract Increases Earmarking fund and will continue through 2025/26. NO RED RISK FOR
2025/26 
PC Replacement 
 Replacement of Corporate PCs due to become red risk assets (> 4 years old) in 2025/26, with 3 years
of warranty.
 Replacement of Education PCs that either are already red risk assets or due to become red risk
assets (> 5 years old) in 2025/26, with 3 years of warranty.

Page 17

Note – the PC replacement programme is based on a continuous cycle of investment. One quarter of all
corporate PCs were expected to be replaced each year alongside one fifth of Education PCs each year.
Exceptional price rises in secondary school device equipment this year means that the original budget of
669k is insufficient to cover the replacement of devices at a cost of £704k in 2025/26. The additional funding
requirement of 35k has been met from existing block allocation. NO RED RISK FOR 2025/26
IT Network
Replacement of IT Network Infrastructure technologies which are either due to become or are already end
of life assets in 2024/25. This investment will result in these assets being fit for purpose for potentially 6
years.  This includes replacing end of life network switches at our Kilmory and GWITC datacentres, as well as
replacement of network routers and switches across a number of our schools and offices.  More network
equipment will need to be replaced in 2026/27 and we are expecting a large amount of RED RISK assets
(approx. £405k) in 2026/27. For 2025/26 we have an immediate shortfall as follows:
Due to greater increases in pricing of equipment than anticipated and short notice of equipment
reaching end of life, the existing funding (£152k) is insufficient to meet the replacement of
equipment at a cost of £223k in 2025/26. This results in a RED RISK emerging for Network
equipment in 2025/26 of 71k. 
Key Business Applications
No business application red risks have been identified definitively beyond 2024/25 at this time. 
Unfunded Capital Pressures  
The ICT Management team follows an industry best practice approach for the replacement of key
technology assets based around the age and condition of each asset type. This is required as part of our
statutory membership of the PSN where we are obligated by the Cabinet Office to maintain our network of
servers and devices at current supported levels. The PSN in turn allows us access to their private network to
collaborate and share data with other public sector partners such as the National Registrars for Scotland,
HMRC, and DWP in a safe, secure, and trusted manner. Our investment priorities are therefore based on
sustaining our complex network of circuits, routers, servers, pcs, and applications and this is reflected in our
three priorities for 2025/26. Funding from the block allocation, coupled with contributions from previously
agreed Capital Contract Increases Earmarking fund will allow us to only partially replace red risk critical IT
server and infrastructure assets for 2025/26. 
This is illustrated in the following table for 2025/26: 
Service Priority Expected
Cost in
2025/26
Budget
available
Are costs
indicative or
calculated)
Estimated
funding
shortfall
Asset category 
(asset sustainability, 
service development, 
strategic change)
1.  IT Networks 223k 152k calculated 71k Asset Sustainability (ESSENTIAL)
TOTAL ADDITIONAL
FUNDING REQUIRED   
£71k 
Match funding Opportunities/External Funding 
Achieved 2023-24 Opportunities 2024-25

Page 18

Asset Sustainability 
Service Development   
Strategic Change   
Links to relevant strategies
ICT and Digital Strategy 2021 -24

Page 19

PRIORITY INVESTMENT PLAN – ASSET GROUP 2 SUMMARY 
Asset Group Road and Footways 3rd tier
Managers
Hugh O’Neill and Tom Murphy 
Description of
Asset Group
and Condition
Assessment 
Asset Group
Road and Footway
Condition
No and
or/Value*
CONDITION
(Percentages based on total asset value)
Green Yellow Amber Red
Roads
*See below comments £2.09Billion 50.24% 9.36% 26.64% 13.76%
Footways  £78.3Million * * * * 
This can be further broken down to road classification as per below table: 
* There is no similarly automated footway condition survey mechanism. 
A Safety Inspection programme, with a frequency of annual to monthly visits, based on
the hierarchy of the footway, is carried out by the inspection team. Generally, footways
are considered safe and fit for purpose with maintenance works undertaken in response
to identified defects or public complaints as investment and resources permit. 
The externally delivered Road Condition Survey was not fully carried out in 2023 and
missed most of our island roads, we have therefore had to use the previous year’s RCI for
the purpose of this document Capital Programme, as such the above table also refers to
last years RCI results.

Page 20

Parking: 
Argyll and Bute have 118 off street car parks ranging from formally laid out urban car
parks to less formal more rural car parks. 
There is no fixed scoring mechanism for our car parks, although safety inspections are
carried out to a standard similar to those carried out on the road network. 
Asset Group No. Condition                                    Suitability
Car parks 118 A          B       C      D       A            B          C          D  
42       53      22      1      N/A    N/A     N/A    N/A 
Argyll and Bute Council has 29 Pay and display car parks. 
There is no capital funding for car parks – the car park maintenance budget money is
funded from income raised from fees and charges. 
Investment
(current and
planned)  Funding Roads 
Funding
source 
Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Block
Allocation
Scottish
Government
3.412 2.000 3.823
RIS Total
3.823 
RIS Total
Block
Allocation
Carried
Forward
Scottish
Government
0.610 (0.222) 0.00 0.00
Additional
Roads
Reconstruction
Council 4.588 0.000 0.000 0.000

Page 21

Weather
Incident 2023
Council 3.208 1.100 0.000 0.000
Claonig
Landslip
Council 1.570 0.030 0.000 0.000
CHORD
Funding
Council 0.060 0.000 0.000 0.000  
13.448 2.908 3.823 3.823 
Funding (Car
Park) Funding source Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
TOTAL  0.000 0.000 0.000 0.000 
2024-25 Overview 
Investment Strategy
Prioritisation of Asset Sustainability:
Road condition is measured by the Scottish Road Maintenance Condition Survey (SRMCS) which assesses
parameters such as surface texture and cracking, smoothness and rutting. This provides an indication of
the residual life of the road structure. 
It should be noted that the flooding and road closures experienced in October 2023 due to excess rain are
likely to continue due to climate change. It is therefore imperative that appropriate road maintenance
including drainage and ditch clearance is carried out to alleviate flood and land slip risks on our Council
roads. More consideration needs to be given to climate change adaptation regarding roads and transport
infrastructure. 
CAPITAL RESURFACING INVESTMENT OPTIONS 
Argyll and Bute Council take part in the Scottish Roads Maintenance Condition Survey (SRMCS) contract
which generates the road asset condition data presented in this report. Further detail on this methodology
can be found in the Annual Status and Options Report produced each year. This methodology provides the
Council with road condition deterioration modelling based on our proposed investment levels. For the
2025/26 financial year investment levels of £2m, £3M and £11M have been used for modelling purposes
to determine the effects of these levels of investment on the condition of the road carriageway. 
The Scottish Statutory Performance Indicator (SPI) for road condition is the percentage of a road network
that has an RCI of 40 or more (ie is in the ‘Red’ or ‘Amber’ categories). 
The below lists 3 options where direct comparison can be made with investment against a 20 year profile
for road condition. Further budget modelling for £5M and £8M are available in the ASOR. 
OPTION 1— £2M 
An annual investment of £2m would lead to very substantial deterioration on overall RCI, this would
significantly increase risk to road users safety and may well leave the council open to criticism.  The
volume of reactive temporary repairs would steadily rise, year on year as would public liability claims.
Customer satisfaction levels can be expected to decrease dramatically.

Page 22

OPTION 2— £3M    
An annual investment of £3m would lead to a substantial deterioration on overall RCI, this would
significantly increase risk to road users safety.  The volume of reactive temporary repairs would steadily
rise, year on year as would public liability claims. Customer satisfaction levels can be expected to steadily
decrease. 
OPTION 3— £11M  
An annual investment of £11m (based on 2024/25 costs) would largely maintain the current condition of
the road carriageway network. 
Prioritisation of Strategic Change:
The value of undertaking adequate preventative maintenance works cannot be overstated. It is the most
vital and fundamental function required to extend infrastructure service life, strengthen network
resilience, and minimise demand for capital investment. 
Over the last 10 years, where we have seen average investment of at least £8 Million on Roads
Reconstruction, RIS have been able to improve our road condition which in turn improves visitor
numbers/local businesses as well as supporting our communities daily commute. However we have seen
recently rises in the costs of materials and vehicles etc which has now increased investment from £8M to
£11M to keep over 50% of our roads in the good condition category. The initial improvement to over 50%
was purely down to investment and the support provided by members allowing RIS officers to manage the
network effectively. 
Footways
Footways investment of £1m over previous 3 years has tackled some of the worst identified sections of the
network aimed at reducing reactive maintenance demands. There is no planned capital footway
investment for 2025/26.
Our footways have a depreciation cost of approximately £1M per annum, as calculated by SCOTS,
therefore a steady annual investment required to prevent the footways from deteriorating and maintained
safe and proportionate for use. 
Risks
1. Increase in third party insurance claims. This would be due to an increase in potholes and road defects
as funding was not sufficient to treat roads properly.
2. Restricted traffic and the possibility of some roads having to be closed on safety grounds. Failure to fully
deliver the duty to maintain, through limited funding as a Roads Authority and a lack of funding will
require prioritisation of routes which may well restrict vehicular sizes on certain roads to prevent further
decline/damage. This would include consideration of weight, width and length limits on our roads as well
as restricted speed limits and ultimately road closures if roads were to become unsafe due to damage. The
practicality to deliver on road closures or restrictions also imposes a cost on the council funds to provide
traffic management and Temporary Traffic Regulation Orders.
3. Detriment to business and tourism should the road network deteriorate to a point that its condition is
not convenient for the travelling public.
4. Increased risk of flooding and land slips should drainage and ditch clearance works not be carried out
regularly. This was highlighted in the flooding from October last year where land slides closed off several
of our roads with a cost in excess of £10m for the clear up of the roads and surrounding area.

Page 23

Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
Asset Sustainability:
Carry out a mix of surface dressing, edge strengthening, resurfacing works.  The surfacing works will
include proportionate drainage works.  Works will be identified from condition surveys, collision data, and
known development activity and reports from the public.  Final programmes may be adjusted to take
account of any winter deterioration. 
Strategic Change:
An annual investment of approximately £11M would maintain the overall RCI provided there was no real
change to inflation, however as inflation and costs increase the steady state budget must also be
increased. Without this inflationary adjustment, the volume of reactive temporary repairs would steadily
rise, year on year as would public liability claims. Customer satisfaction levels can be expected to steadily
decrease.  
Unfunded Capital Pressures: 
Service Priority Cost (£) Are costs
indicative or
calculated)
Estimated
funding
shortfall
Asset category (asset
sustainability, service
development, strategic change)
1. Road Maintenance £11M to
retain
steady
state
Calculated as
per agreed
methods
£9M (if £2M is
allocated to
Roads Capital
from the Block
Allocation)
Asset Sustainability
2. Footway
Maintenance 
£950k to
retain
steady
state
Estimation of
condition
calculated as
three percent
of gross
replacement
cost of the
asset.   
£950k  Asset Sustainability 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26
Asset Sustainability   Active Travel Funding 
 Road Safety Improvement Fund
£144,653.
 STTS
 Crown Estates Funding
 RTIF (not available for
2024/25, therefore may not be
available for 2025/26)
 Road Safety Improvement
Fund

Page 24

Service Development    Community Regeneration
Fund
 Islands Infrastructure Fund
Strategic Change   
Links to relevant strategies
Item No 7 ASOR EDI Report
The road infrastructure is also covered by the Roads Asset Management Plan (RAMP) which has been
carried out as part of a national project steered by SCOTS. This means that the roads asset infrastructure’s
condition can be compared not only across Argyll and Bute, but across the whole of Scotland.

Page 25

PRIORITY INVESTMENT PLAN
Asset Group Street lighting 3rd Tier Manager Tom Murphy
Description of
Asset Group
and Condition
Assessment 
Gross street lighting stock replacement cost (new replacement) from the current Asset
Register is £47m. 
We have 13,616 Street Lighting Columns. It is estimated that 35-45% of these columns
have exceeded their expected service life of 25-30 years, with some in the region of 70
years. 
Significant benefits in terms of energy efficiency and public amenity have been delivered
over recent years through the programme of replacing old luminaires with efficiency LED
units and associated targeted dimming of lights. Carbon emissions have greatly reduced
as a result of the project. 
Service Standards: To ensure that our asset is maintained properly, electrical certification
/ testing is required every 6 years with column condition and ranking carried out every 4
years as part of scheduled planned maintenance. The next round of testing (Categorised
as planned maintenance) is due 2025/26. Inspections undertaken of columns as part oif
the LED programme has provided a prioritisation of columns due for replacement with
the residual funding from the LED project together with other capital allocations that
have been received. 
Investment
(current and
planned) -
Updated by
Finance for
2025-26 
Funding  Funding source 
Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Block
Allocation
Scottish
Government
0.150  0.000  
Block
Allocation
Carried
Forward
Scottish
Government
0.175 0.369  
LED Project -
Prudential
Borrowing
Council 0.300 0.321    
0.625 0.690 0.000 0.000 
2024-25 Overview
Investment Strategy
The LED Upgrade Project funded by Prudential Borrowing is nearing completion in terms of luminaire
upgrades, we are still looking to finalise this within financial year 2025/26
To date 290 columns have been identified in the poorest condition category and will be replaced through
the LED Upgrade Project. 
In addition, with the extra capital funding received during 2023/24, a number of improvements schemes
have have been completed delivering a further upgrade the lighting stock. 
The Carry Over and the capital budget of £150k for 2024/25 9as per the table above) will see this column
and cable replacement works continue. 
Risks
1. Insufficient investment may lead to column and or systems failure with the possibility/risk of damage to
individuals/property.

Page 26

2. Health and safety concerns re columns that are old and rusted with the potential to fall down in adverse
weather.
3. Lack of reliability and increased outages would lead to a corresponding increase in customer
contact/complaints and a negative impact on the Council’s reputation. 
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above 
Lighting has benefited from investment to change luminaires to low energy LED. This has approximately
halved our energy consumption and has provided benefits with significantly reduced light pollution and
which benefits dark skies. 
Without continued investment for an aged cabling and column inventory, we will only be able to plan to
improve a small percentage of lighting assets. We prioritise funding through a study of any planned
maintenance findings, analysis of fault records and reliability, light level meter checks for inadequacies,
column condition scores – all will be considered to compile and prioritise programs of work. 
Possible Savings Proposals Currently Being Considered.
Argyll and Bute could consider switching lights off between midnight and 05:00hrs. Potential savings if
street lighting is switched off between midnight and 5am are significant. The figures have been calculated
using the current inventory with any non-street lighting equipment (signals, beacons, sign lights,
controllers etc) excluded.  When calculating the switch off kWh’s, any item that currently operates on a
dimmed profile has been calculated as being in the appropriate dimmed state outside of the switch off
period.
It’s estimated that around 30% of the Street Lighting Inventory is switched on/off by Photocells fitted to
the Luminaires. Photocells react to natural light levels and bring lights on at dusk and switch them off at
dawn. 70% of the network is controlled by Time Clocks where we’d currently be able to set times for
specific or altered burning regimes. Time clocks would need to be introduced across the whole of the
network to set any new switching regime so there would need to be a spend to save approach applied. 
Top three service/asset group priorities 
Service Priority Cost (£) Are costs
indicative
or
calculated)
Estimated
funding
shortfall
Asset category (asset sustainability,
service development, strategic
change)
1. Completion of
LED installation
programme
LED Business
Case
Calculated 0 Asset sustainability
2. Column
replacement and
cabling works
£854k Calculated * Asset sustainability
3. Continue asset
sustainability
works
tbc Indicative
– value tbc
* Asset sustainability
 The review of the LED, column and cabling requirements for street lighting will identify funding
requirements for future lighting works. 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26

Page 27

Asset Sustainability  
Service Development   
Strategic Change   
Limited opportunities for match funding/external funding. Historically Scottish Futures Trust have
provided interest free loans for lighting however it is understood that this funding stream is no longer
available. 
Links to relevant strategies
LED strategy for converting low efficiency luminaires to LED.
Climate Change strategy.

Page 28

PRIORITY INVESTMENT PLAN – ASSET GROUP 3 SUMMARY 
Asset Group Amenity  3rd Tier Manager Hugh O’Neill and Tom Murphy
Description of
Asset Group
and Condition
Assessment 
Argyll and Bute Council has 131 Cemeteries with 68 Closed for the sale of lairs. They are however
still being opened for interments as well as the Council being responsible for the upkeep of the
Cemetery. They have been listed as Suitability D in the above Table. 
63 Cemeteries are open for the sale of lairs, however they have been broken down in the
condition table to whether they have 20+ years Condition A, 10-20 years Condition B, 5-10 years
Condition C and 0-5 years capacity Condition D. 
Argyll and Bute Council have 30 Play parks which are listed as D in urgent need of repair, C in need
of repair, B minor repairs needed and A in good order.
Argyll and Bute Council have 25 Sports pitches parks which are listed as D in urgent need of repair,
C in need of repair, B minor repairs needed and A in good order. 
Argyll and Bute Council have 60 Public Conveniences are listed as D in urgent need of repair, C in
need of repair, B minor repairs needed and A in good order from the condition survey.
- Sports Fields - We have 25 Sport Fields which cater for a mix of football/shinty and rugby. We
have listed them as A=Good condition/B=Reasonable Condition/C=Poor Condition. Most
require drainage work as well as work to improve the playing surfaces of the pitches and
update/replace fencing.
- Stadiums – We have 3 stadiums which are listed as 2 in good condition and 1 in poor
condition
- Toilets – 16 high footfall public conveniences are in the process of having charging
infrastructure installed through a £300,000 scheme [£100,000 Council capital; £200,000
Coastal Communities]. Income received can be used to meet previously unachieved income
targets. Depending on the level of income received, information from these 16 sites following
the fitting of the charging infrastructure can be used in a business case to consider extending
the number of public conveniences where charges are made. 
Asset Group No and/or value. Condition Suitability
A B C D A B C D
Cemetery 131 47 8 3 5 0 0 0 68
Parks and Open Spaces 30 Play Parks 6 4 18 2 4 6 16 4
Parks and Open Spaces Sports Fields 5 6 14 0 3 6 9 7
Parks and Open Spaces Stadium 2 0 1 0 0 3 0 0
Toilet facilities 55 7 20 27 6 6 15 20 19
Investment
(current and
planned)  Funding  Funding source 
Current Year Anticipated Investment (£m)
2024-25 (£m)    2025-26 2026-27 2027-28
Block Allocation Scottish
Government
0.100 0.100 0.000 0.000
Block Allocation
Carried Forward
Scottish
Government
0.029   
Capital Grant
(Play Parks)
Scottish
Government
0.547 0.391  
Coastal
Communities
Fund
Crown Estate 0.400 0.109  
Additional
Allocation -
Cemeteries 
Council 0.310   
1.386 0.600 0.000 0.000 
2024-25 Overview

Page 29

Investment Strategy
Cemeteries
Officers are reviewing the capacity of cemeteries, those with less than 5 years capacity are prioritised in line with
budget availability. Cemeteries are either extended or when this is not possible then nearby land is identified where
possible within Council ownership and if not then land owners are approached to purchase land. To support
cemeteries with less than 5-10 years capacity, the EDI Committee has agreed a policy in regards to lair availability,
whereby the pre-sale of lairs is stopped when capacity is less than 5-10 years. There is currently funding within the
Capital Budget which at this time will cover the immediate requirements. However this is dependent on whether
officers can purchase land at a reasonable cost as well as abiding by SEPA rules which have been tightened around
water courses. Further to this, although predicted in the listed years this again is dependent on work with land
owners where delays are outwith officers control.
Play Parks 
Play Parks have been reviewed by trained officers to identify defective equipment and surfaces. Previously no
funding has been available and defective equipment has either been removed or fenced off. On occasion funding
sources have been identified to locally refurbish equipment and play parks such as Atlantis in Oban. Engagement has
concluded with elected members to agree a suitable spend for the budget locally. Play park funding will be covered
by the Scottish Govt budget for another two years. There are no further plans to develop play parks further than this.
Pitches 
Most pitches are in need of drainage work as well as work to improve the playing surfaces of the pitches and
update/replace fencing. Several pitches have previously had drainage works carried out and now at least 6 need
urgent drainage works to enable sports to be played on the pitches following wet periods.
In regards to Rothesay Stadium, this requires extensive drainage works as well as building works to ensure health and
safety is not compromised. Work is also required to continue to improve the mobile stand, to alleviate this issue and
support the Bute Games Operations staff have made this a permamnent structure rather than a temporary stand.
This works but requires an annual application for planning.
Public Conveniences
Various public conveniences (PC) are undergoing improvements and general upgrades. At the P&R Committee
meeting on 13/10/22 additional funding was approved subject to SG confirming the anticipated level of Coastal
Communities funding being received.  16 high footfall public conveniences are in the process of having charging
infrastructure installed through a £300,000 scheme. 16 PCs are being upgraded to door entry systems which will
generate an income, through door payment systems, for the council which will contribute towards the asset
sustainability and general day to day maintenance of the PCs.
The service has developed a number of robust partnerships with community groups to assist with the opening,
closing, stocking and maintenance of public conveniences. This partnership approach, whilst fostering a collaborative
arrangement with the community, it also helps to reduce direct costs to the Council. As a general rule the Council
maintain full responsibility for the maintenance of the fabric of the building with the community groups carrying out
the day to day servicing and cleaning duties. The locations with partnerships in place are:
Ardentinney
Tayinloan
Pensioners Row
Calgary
Scaranish 
Officers are waiting on the proposed partnership with MICT being approved (Internally). This will allow MICT to open
their facility as a Public Convenience and the Council to remove the existing toilet block which is in poor condition.
Reservoirs 
The Council is defined as Reservoir Manager for 2 assets at Kirk Dam, Rothesay and Bishops Glen, Dunoon.  There is a
requirement to regularly inspect these structures and undertake any remedial works that are specified in the interest
of safety and enforceable by SEPA.  
Risks of insufficient funding to carry out asset sustainability and asset improvement works:

Page 30

1. As a Burial Authority, the Council will risk being in breach of legislation should there not be sufficient funding
for cemetery expansion and development. Further, this will damage the council’s reputation should more
cemeteries close and cause negative feedback from deceased relatives etc.
2. Sports pitches would become unfit for purpose which would be detrimental to the council’s objective of a
healthy community. This would also see clubs using all weather facilities at the council’s High schools, this
has recently been raised as an issue with clubs being unable to book the pitches due to over subscription.
Officers have also experienced sports clubs taking their bookings to neighbouring authorities.
Ongoing discussions with the local sports group regarding the development of Mossfield stadium in Oban
have paused pending sufficient information to satisfy external funders/grant organisations.
Discussions are ongoing with Oban rugby club around improvement to the pitch the club use adjacent to
Mossfield stadium.
3. Breach of Health and Safety legislation if toilets are not maintained in a good condition and reputational
damage to the Council. Not maintaining our public conveniences also limits the opportunities for the council
to engage with potential third sector partners. It is interesting to note that there is no financial allocation
through the GAE settlement for public conveniences. 
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
1. Cemetery investment continues to be prioritised on extending cemeteries with limited life as per the asset
cemetery plan considered by EDI Committee in November 2023. 
2. Sports field investment will be prioritised towards proportionate works which ensure that the sports facilities are
available and fit for purpose for both young people and adults. Much of this work would include drainage of the
playing surface, boundary fencing and any lighting together with changing rooms and associated buildings etc. All of
these works effectively falling within the asset sustainability category.
3. Investment in playing fields would be prioritised where third party external funding can also be secured
encouraging community groups to secure investment and work in partnership with the Council where this can be
demonstrated to be sustainable long term.
4. Public convenience investment will be used to ensure we meet statutory requirements in terms of health and
safety and public health. 
5. Where business cases stack up, further investment over and above the 16 currently funded, will be made to
generate income and a self-financing model through additional charging infrastructure being installed.
Unfunded Capital Pressures 
Service Priority Cost (£) Are costs
indicative
or
calculated)
Estimated
funding
shortfall
Asset category (asset sustainability,
service development, strategic
change)
1. Sports facilities/playing
fields areas
£938k Indicative  £938 Asset Sustainability – carrying out
proportionate works to ensure
sports areas/playing field are
available and fit for purpose. Works
will be prioritised base on health and
safety, facility use and value for
money.
Experience of previous expansion and land purchase timescales highlights that at least 5 years are required in some
cases to identify, source, purchase and prepare the land for use as a cemetery. This continues annually with work
ongoing to estimate further budget costs.
Match funding Opportunities/External Funding 
Achieved 2025-26 Opportunities 2026-27
Asset Sustainability  £391k from Scottish Govt Play Park
Fund

Page 31

Service Development   Currently ongoing partnership discussions
with sports clubs in Oban around attracting
local investment to improve Mossfield
Stadium and other sports fields in the Oban
and Lorn area.
Potential opportunities which are being
pursued with the local sports group
regarding the development of Mossfield
stadium in Oban have paused due to the
committee requiring to obtain certain
aspects to satisfy potential funders.
Discussions are ongoing with Oban rugby
club around improvement to the pitch the
club use adjacent to Mossfield stadium. 
Strategic Change   
Links to relevant strategies:
Play Park and Cemeteries: December EDI (Items 5 and 7).

Page 32

PRIORITY INVESTMENT PLAN – ASSET GROUP 2 SUMMARY 
Asset Group Bridges and Coastal
Protection
3rd tier
Manager
Elsa Simoes 
Description of
Asset Group
and Condition
Assessment 
BRIDGES:
903 Bridges (over 1.5m span)
Increase of 1 since March 2023
Culverts under 1.5m span arenot classified as bridge structures and so are ot included the figure
above.
677 Retaining Walls (over 1.35m retained height) recorded on Council systems, however it is
recognised that a gap in data is likely to exist and this figure is therefore regarded to represent
circa  80% of the total number of retaining walls. 
Retaining walls under 1.35m retained height are not included within this figure.
Bridge Condition is calculated through Structural Inspections carried out by Bridge Inspectors and
are rcorded on bespoke Asset Management Software.
Structural condition is measured through inspection of assets which considers each element of a
structure.  National guidance documents are utilised as well as a standardised Asset Management
system. 
The Bridge Stock Condition is now reported on a weighted average per span figure.  The recent
results are shown in the table below: 
Average
Bridge Stock
Condition
(out of 100)
Critical
Element Stock
Condition
(out of 100)
2022-24 Cycle 87.86 79.08
2020-22 Cycle 89.03 80.44
2018-20 Cycle 89.73 82.24
2016-18 Cycle 89.46 82.40
Over recent years there has been a slow decline in bridge stock condition.
There is an estimated backlog of maintenance liability totalling £32.4m. With the following bridges
subject to weight restrictions.
Bridge No. & Name Area
Restriction
(MGW)
A846-239 LAGGAN OLD (Weak Bridge) Islay 10T
B8025-020 ISLAND ADD (Weak Bridge) Mid Argyll 3T
B866-020 GLACHAVOIL (Weak Bridge) Cowal 7.5T
C012-050 MILINDRY SCHOOL (Weak Bridge) Islay 13T
C038-010 BRIDGEND (Weak Bridge) Mid Argyll 18T
C038-050 BARMOLLOCH (Weak Bridge) Mid Argyll 18T
C057-010 OLD BALLIEBEG (Weak Bridge) Cowal 18T
U010-090 LEACAINN (BRENACHOILLE) (Weak Bridge) Mid Argyll 7.5T
U010-100 BRANDON STREET (Weak Bridge) Cowal 7.5T
U021-020 IRON (Weak Bridge) Islay 3T
U022-050 GLENDARUEL (Weak Bridge) Cowal 3T
U027-010 MILLHOUSE (Weak Bridge) Cowal 18T
U031-010 NEWTON BURN (Weak Bridge) Cowal 10T
U042-100 AIRDS HOTEL (Weak Bridge) Lorn 10T
U046-010 KILBRIDE (Weak Bridge) Cowal 10T

Page 33

Investment
(current and
planned)  Funding 
Funding
source 
Current Year Anticipated Investment (£m)
2024-25 (£m)
2025-26
(£m)
2026-
27(£m)
2027-
28(£m)
Block
Allocation
Scottish
Government 0.000 0.750 0.000 0.000
Block
Allocation
Carried
Forward
Scottish
Government 0.315 1.248 0.000 0.000
Local Bridge
Maintenance
Fund
Scottish
Government   0.230 4.777 0.000 0.000
Capital Coastal
Change
Adaption 
Scottish
Government 0.255 0.299 0.000 0.000
Bute Sea Wall Council 0.274 0.359 0.000 0.000
Total  1.074 7.433 0.000 0.000 
2024-25 Overview 
Investment Strategy
BRIDGES and COASTAL PROTECTION:
Investment Strategy
Bridge Inspections are carried out every 24 months in accordance with Well Managed Highways
Infrastructure Code of Practice and DMRB Standards.
Principal Inspections / Structural Reviews / Bridge Assessments are undertaken to determine
priority of strengthening/improvement works.
Capital Bridge Strengthening and Replacement Programme is prioritised using a risk-based
methodology which considers overall condition and risk of structure, extent and severity of defects,
usage of structure and engineering judgement.  This methodology has been modified in recent
years to take account of new SCOTS guidance.
Revenue Structural Maintenance is currently prioritised using a risk-based methodology which
considers overall condition of structure, extent and severity of defects, usage of structure and
engineering judgement.  
Structures Investment:
1) Capital Bridge Strengthening and Replacement Programme (including LBMF)
a. Strengthening & Replacement of Bridges & Retaining Walls
2) Revenue Structural Maintenance
a. Bridge & Wall Inspections
b. Bridge & Wall Maintenance Repairs 
c. Technical Approval 
d. Asset Management
3) Revenue Structural Assessment
a. Assessment of Bridges and Retaining Walls
b. Management of Abnormal Load Notifications 
Coastal Protection Investment:

Page 34

1) Capital Coastal Protection
a. Repair, Strengthening & Replacement of Coastal Protection Assets
2) Revenue Coastal Protection:
a. Coastal Protection Inspections
b. Coastal Protection Maintenance Repairs 
c. Asset Management 
Risks
The current level of capital & revenue funding is expected to result in an ongoing decline in the
overall condition of bridge and coastal protection assets and an increase in the number of bridges
subject to weight and other restrictions. This will be reflected in a reduction in the overall Bridge
Condition indicator (BCi).
1. Increase in risk of bridge/road weight restrictions or closures thereby decreasing the overall
functionality of the local road network. 
2. Potential for communities being left isolated should any single access areas have closures or
restrictions imposed. For example Seil, Easdale and Luing communities will be severely affected if
Kilninver bridge had to have a restriction.
3. Inspections, assessments and works are prioritised to best manage the risks versus available
funding and the Council’s responsibilities for its assets.
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above
Top three service/asset group priorities 
Service Priority Cost (£) Are costs
indicative or
calculated)
Estimated
funding shortfall
Asset category (asset
sustainability, service
development, strategic
change)
Bridges
Bridge Strengthening
and Replacement
28m indicative 21m Asset sustainability
Structures
Maintenance
4.366m indicative 4.066m Asset sustainability
Coastal Protection 25m indicative 23.4m Asset sustainability 
The above table illustrates the total estimated backlog maintenance liability in relation to bridges and
coastal protection. Assuming a 10-year programme of increased pro-active maintnenance to improve the
condition of these asset groups and remove the backlog maintenance liability the funding shortfall for the
2025/26 financial year would be:
Service Priority Cost (£) Are costs
indicative or
calculated)
Estimated
funding shortfall
Asset category (asset
sustainability, service
development, strategic
change)
Bridg Bridge Strengthening
and Replacement
£2.8m indicative £2.1m Asset sustainability

Page 35

Structures
Maintenance
£0.437m indicative £0.407m Asset sustainability
Coastal Protection £2.5m indicative £2.34m Asset sustainability 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26
Asset Sustainability  COASTAL CHANGE ADAPTATION
 £60k Coastal Change
Adaptation funding
secured for and donated to
Luing Community.
 £129,690 Coastal Change
Adaptation Capital Grant
2024-25.
COASTAL PROTECTION
COASTAL CHANGE ADAPTATION
 Dynamic Coast Project funding
(coastal change)
 Coastal Change Adaptation
(£250k secured) 
BRIDGES
 Any future rounds of Scottish
Government’s Local Bridge
Maintenance Fund
Service Development   
Strategic Change   
Links to relevant strategies
BRIDGES:
 LEGISLATION - Roads (Scotland) Act 1984
 CODE OF PRACTICE - Code of Practice 'Well-managed highway infrastructure'
 DESIGN STANDARDS - DMRB - Highway Structures & Bridges Series 
 PLAN - Argyll and Bute Council - Roads Asset Management Plan (RAMP) - June 2017 
COASTAL PROTECTION:
 LEGISLATION - Coast Protection Act 1949
 POLICY - Argyll and Bute Council - Coast Protection Policy and Strategy - March 2015

Page 36

PRIORITY INVESTMENT PLAN – ASSET GROUP 2 SUMMARY 
Asset Group Flood Risk Management 3rd tier
Manager
Elsa Simoes 
Description of
Asset Group
and Condition
Assessment 
FLOOD PROTECTION INFRASTRUCTURE:
Designed flood protection schemes in Rothesay (coastal), Dunoon (two no. fluvial
alleviation schemes; Milton Burn and Kilbride Road).  No formal condition rating. 
Concerns about Rothesay FPS are known. Investigations and studies are ongoing
to determine future maintenance requirements.
Kilcreggan SWMP identified Tigh Dearg Road and foul drainage issues –
construction works ongoing and scheduled for completion in late 2024.
Helensburgh surface water drainage has also been identified and designs are in
abeyance. 
Other informal structures which provide flood protection to population centres
would require to be documented in order to quantify the asset, owner, and
condition.  This is in part the purpose of the Local Flood Risk Management Plan
2022-2028, to assess risk in those areas affected by flooding.
Watercourse assessments to be carried out and a schedule of clearance and
repair works to be programmed. 
A Surface Water Management Plan has been incorporated into the Campbeltown
Flood Protection Scheme and the Council aims to prioritise other areas
respectively.
Revenue funded temporary mitigation scheme in Oban is being progressed which
includes watercourse inspections, clearance of obstructions, topographic and
Bathymetric surveys, hydrologic study, repair of an existing pumping system at
Lochavullin car park, consultations with SEPA on consents (for protected
amphibians, invasive species and other matters under their remit) and securing
of quotes for proposed works to identify if funding can be secured from available
budgets or otherwise.
Coastal Change Adaptation Plans are a requirement from the Flood Risk
Management Plans.  The Council is progressing Plans for the first selected areas
with a specialist consultant. 
The current focus of delivery are the two Local Flood Risk Management Plans
which relate to Argyll and Bute as described in this document (Highland and
Argyll, Clyde and Loch Lomond).
The maintenance backlog on designed flood protection assets is currently
minimal (Rothesay and Dunoon) as these assets are relatively new.  Current flood
alleviation assets are maintained under a combination of flood, coastal, and
roads budgets depending upon the context. 
On a wider scale there are under and un-designed flood protection assets
throughout Argyll and Bute which are not formally recognised as such and may
not be owned by the Council but serve this purpose e.g. the banks of the Black
Lynn through Oban.  There is an unknown backlog on such assets but would
certainly run to tens of millions of pounds of investment to bring to an ideal
condition.
Scottish Government recently advised that there is no prospect of any future
funding for Flood Protection Schemes in the near term.

Page 37

Investment
(current and
planned)  Funding 
Funding
source 
Current Year Anticipated Investment (£m)
2024-25
(£m)
2025-26
(£m)
2026-27
(£m)
2027-28
(£m)
Block
Allocation
Scottish
Government 0.306 0.656 0.156 0.156
Block
Allocation
Carried
Forward
Scottish
Government 0.907 (0.156) (0.156) 0.000
Helensburgh
Flood
Mitigation
Council 0.000 0.427 0.000 0.000
Campbeltown
Flood Scheme 
Scottish
Government
& Council 
1.780  0.010 0.387 0.000
Totals  2.993 0.937 0.387 0.000 
2024-25 Overview 
Investment Strategy
FLOOD PROTECTION INFRASTRUCTURE:
Investment Strategy
On a strategic scale this is through the Local Flood Risk Management Plan(s) and the SEPA led
National Flood Risk Assessment process to consider local history and impact of flooding as well as
national flood risk based on climate change predictions – all in accordance with Flood Risk
Management (Scotland) Act 2009. 
The cost of implementing flood protection schemes has to be less than the damages avoided i.e. a
benefit cost ratio of greater than one. Non-economic benefits are also being considered by SEPA.
However, the weighting this has on its prioritisation is being considered by the Scottish
Government and COSLA.
Risks
1. A key risk is the now confirmed loss of further investment from Scottish Government. There was
a defined process currently for assessing flood risk and prioritising investment across Scotland. 
2. Road closures and loss of assets – Several population centres in Argyll and Bute will be at
significant risk of more frequent flooding in the future with climate change. Communities living
along lifeline roads may be cut off temporarily. This will lead to considerable financial impact to
properties and businesses. Ultimately, significant flooding events can lead to loss of life.
Summary of Planned 2025-26 investment
Investment Strategy at funding levels indicated above 
Top three service/asset group priorities 
Service Priority Cost (£) Are costs
indicative or
calculated)
Estimated
funding shortfall
Asset category (asset
sustainability, service
development, strategic
change)

Page 38

1. Flood Protection
Delivering cycle two
and three schemes as
per the Local Flood
Risk Management Plan
cycle one and two
flood studies.
41.290m
(based on
2019 flood
study
costs)
2019
indicative
costs 
Strategic Change. The
Council is not under an
obligation to deliver these
schemes and no approval
for them has been
received. 
Carrying out works as
identified under
section 18 scheduled
of clearance and
repair. 
TBC TBC TBC. Asset Sustainability
Carry out emergency 
and urgent reactive
works punctually
Unknown N/A Unknown Asset Sustainability 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26
Asset Sustainability  
Service Development   
Strategic Change FLOOD PROTECTION
INFRASTRUCTURE:
 £12.172m (80%)
contribution for
Campbeltown Flood
Protection Scheme FPS
from Scottish Government. 
Links to relevant strategies
FLOOD RISK MANAGEMENT:
 LEGISLATION - Flood Risk Management (Scotland) Act 2009
 ADOPTED PLANS:
o Highland & Argyll Local Flood Risk Management Plan (Cycle 2)
o Clyde and Loch Lomond Local Flood Risk Management Plan (Cycle 2)
 ADOPTED POLICY - Argyll and Bute Council - Flood Risk Management Policy – March 2015
 NOTIFIED FLOOD PROTECTION SCHEME - Campbeltown Flood Protection Scheme

Page 39

PRIORITY INVESTMENT PLAN – ASSET GROUP SUMMARY 
Asset Group Fleet Services 3rd Tier Manager John Blake
Description of
Asset Group
and Condition
Assessment 
Fleet services have reviewed market costs for petrol/ diesel vehicles and the cost of alternatively
fuelled vehicles, e.g. electric vehicles to comply with the changes imposed by Scottish
Government which prevent public bodies from purchasing small vehicles (cars and small vans)
with internal combustion engines post 2025. The figures below are based on a replacement values
for this part of the Councils fleet with alternatively fueled vehicles. 
Asset Group No and
or/Value*
CONDITION
(percentages based on total asset value)
Green
/
Purple
Yellow Amber Red
Cars and Small vans:
Changes to legislation
within the public sector
informs us that from 2025
no petrol or diesel cars or
light vans can be purchased
Suitable replacements will
be electric vehicles. 
Circa £8m to
replace the
existing Fleet
which are 7
years or
older with
compliant
alternatively
fueled
vehicles. 
40% 20% 20% 20.00% 
Fleet Services No. Condition Suitability
A B C D A B C D
Fleet vehicles & plant equipment 504        
TOTAL 504        
Investment
(current and
planned) 
Funding  Funding source Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Block Allocation
Scottish
Government 0.000 0.500 0.000 0.000
Prudential
Borrowing
Council
2.152 0.000 0.000 0.000
Earmarked
Reserves
Capital
0.258 0.000 0.000 0.000
Community Bus
Fund
Scottish
Government 0.233 0.000 0.000 0.000 
Total  2.643 0.500 0.000 0.000  
2023-24 Overview 
Summary of Planned 2024-25 investment
Investment Strategy at funding levels indicated above
Asset sustainability - The Council has a duty to ensure vehicles are fit for purpose and comply with current legislation. 
Due to increasing repair and maintenance costs, an essential vehicle replacement programme continues when
funding is made available. Capital and revenue savings have been identified in the procurement of new vehicles. With
smaller vehicles having to be replaced with zero emission vehicles/electric vehicles beyond 2025. There is an
anticipated increase in vehicle replacement costs associated with climate friendly alternatives. The cost of replacing
cars and small vans beyond 2025 is £8.23m in capital expenditure over a 5-year replacement programme period or

Page 40

revenue expenditure of £1.5m per annum in revenue costs.  Over a 5-year period the capital cost of undertaking this
replacement programme would be £1.646m p.a.
Vehicle replacements will be programmed ensuring that suitable, reliable fleet vehicles and plant equipment are
available for service users, and with limited capital investment this will possibly be achieved through prudential
borrowing. 
This will also contribute to climate change with more modern vehicles purchased and reduced CO2 emissions
contributing to the wider council net zero ambitions. 
A full replacement of the Councils entire fleet would be at a cost of £18m i.e. an additional £10m over and above the
cost of replacing the cars and small vans. The remainder of the vehicle replacement programme would ideally be
undertaken over a 7-year period. Over a 7-year period the cost per annum of replacing this remaining part of the
Councils fleet would be £1.429m p.a.
UNFUNDED PRIORITIES 
Service Priority Cost (£) Are costs
indicative or
calculated)
Estimated
funding
shortfall
Asset category (asset
sustainability, service
development, strategic change)
1. Cars and small vans:
Changes to legislation
within the public
sector informs us that
from 2025 no petrol
or diesel cars or light
vans can be
purchased as suitable
replacements. Electric
vehicles will be
required to be
procured. This will
represent a higher
purchase cost than at
present. Based on age
and condition of the
existing vehicle stock
a 5-year replacement
programme is
recommended at a
total cost of £8.23m.
This results in an
annual programme of
£1.646m
1.646m Calculated  £1.146m  Asset sustainability (like for like
service will be the outcome).
Improved C02 emmisisons.
2. All other vehicles and
plant: Based on a 7-
year average vehicle
replacement period
for the remaining
proportion of the
Councils fleet and
plant and an
estimated total
replacement cost of
£10m the annual
replacement cost is
estimated at £1.429m
£1.429m Indicative £1.429m Asset sustainability (like for like
service will be the outcome) 
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26

Page 41

Asset Sustainability  None identified None identified
Service Development  None identified Funding sources relating to roll out of
petrol / diesel phase out beyond 2025
Strategic Change None identified None identified 
Links to relevant strategies

Page 42

PRIORITY INVESTMENT PLAN – ASSET GROUP SUMMARY
Asset Group Waste Services 3rd Tier Manager John Blake
Description of
Asset Group
and Condition
Assessment 
SEPA condition surveys and site monitoring to ensure compliance with environmental
legislation. The sites are permitted by SEPA to operate the sites. Biffa through a Waste
PPP contract manage sites on behalf of the Council.  The sites include civic amenity and
landfill sites at the one locus, mixed waste, recycling etc. is managed on site. Biffa
manage Moleigh, Dalinlongart, Lingerton, Westland’s, Roading and Bogleha. The Council
manage sites on Islay, Mull, Tiree and small civic amenity site on Coll and Colonsay.
Officers monitor the requirements for each site. Biffa have the responsibility for
infrastructure within the Waste PPP sites. 
Investment is required at Dalinlongart, Lingerton, Council operated sites – Gartbreck and
Glengorm, there is likely to be a requirement for capital investment of £6m (estimate) for
cell capping, environmental monitoring, annual surveys, additional boreholes for gas
related equipment, replacements pumps, leachate monitoring points, relining of leachate
lagoons and reed beds beyond the contract term in financial years 2026-27. This
investment would be made through capital funds. However, if revenue funding is
available this could be used to undertake the required works.  
Asset Group No and
or/Value*
CONDITION
(percentages based on total asset value)
Green/
Purple Yellow Amber Red
Moleigh, Dalinlongart,
Westland’s and Lingerton.  £6.0million 0% 0% 0% 100.00% 
Investment
(current and
planned) 
Funding  Funding source  Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Block Allocation  Scottish
Government 0.279 0.000 0.000 0.000
Earmarked
Reserves Council 0.250 0.000 0.000 0.000  
0.529 0.000 0.000 0.000 
2024-25 Overview 
Investment Strategy
Assessment and review is conducted by officers. Property have the responsibility for assessing any
requirements or maintenance to the sites. Asset Sustainability is the primary driver for investment,
however, there is a lack of investment made at sites. 
Risks
1. Future ongoing investment will be required to meet the site licence requirements that are regulated
by SEPA. An estimated £6.0m is required beyond the Biodegradable Municipal Waste (BMW) Ban for
site works and the requirement for on-going capital costs. Funding to achieve compliance has not been
identified. This funding will be required to cap and restore all landfill sites as no waste material will be
landfilled as per SEPA regaulations. 
2. Non-compliance with statutory requirements and likely prosecution by SEPA if compliance is not met. 
Summary of Planned 2025-26 investment

Page 43

Investment Strategy at funding levels indicated above
Funding is in place to convert the MBT sheds which are currently part of the PPP contract with Biffa to
transfer stations and also to provide a waste transfer station in Helensburgh.
Investment is required on all sites within the next 30-60 years, the Council sites will require investment at
varying stages, the lower level cost for the management of the sites are £10.929m – higher level costs are
£16.085m. The investment will be required under Asset Sustainability to ensure that the conditions of the
site licences are met. Licence conditions are monitored by the regulator SEPA. The works will include but
not be limited to reed bed restoration, leachate monitoring equipment, landscaping, perimeter fencing,
building maintenance, access roads etc.  No immediate investment is required, this should however be
noted within any horizon planning. 
UNFUNDED PRIORITES 
Service Priority Cost (£) Are costs
indicative
or
calculated)
Estimated
funding
shortfall
Asset category (asset sustainability,
service development, strategic
change)
1. Dalinlongart,
Lingerton, Moliegh,
Council sites –
Gartbreck and
Glengorm site
maintenance.
Capping and
restoration  of sites. 
£6.0m Indicative £6.0m
post BMW
Ban 
Asset sustainability, service
development, strategic change,
2026-27
2.    
3.     
Match funding Opportunities/External Funding 
Achieved 2024-25 Opportunities 2025-26
Asset Sustainability N/A N/A
Service Development  Compliance with SEPA
requirements and site
management. 
Recycling Infrastructure
Fund (RIF) Bid – Island +
Helensburgh – approx.
£891k. Infrastructure
improvements at Council
operated sites. 
Waste Transfer Station –
funds of £3.0m have been
allocated for the
development of a waste
transfer station in H&L. A
further £0.5m has been
allocated to convert the
existing MBT plants located
at Renewi sites Dalinlongart,
Lingerton and Moleigh.
Strategic Change N/A N/A

Page 44

Links to relevant strategies
Argyll and Bute Council’s Waste Strategy.

Page 45

PRIORITY INVESTMENT PLAN – 9. Piers & Harbours 
Asset Group Transport Infrastructure: Piers & Harbours 3rd Tier
Managers
Scott Reid
Marine Operations Manager 
Description of
Asset Group
and Condition
Assessment 
Asset Group 
Piers and Harbours
CONDITION
Green Yellow Amber Red
Marine Asset Management Plan (MAMP):
Argyll and Bute Council is a Statutory Harbour Authority
at 8 locations and a marine asset owner at a further 29
marine facilities located throughout the Council area.
Marine infrastructure is developed through a capital
investment Marine Asset Management Plan for the
Marine Capital Investment Board and ultimately
approved by elected Members of the Argyll and Bute
Council Harbour Board.
This supports infrastructure upgrades for CalMac ferry
service upgrades but also includes Argyll & Bute Council
ferry infrastructure upgrades and required
modifications for legislative changes. 
80% 10% 5% 5% 
Investment  Funding
Funding source  Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Marrine Asset
Management
Plan
Prudential
borrowing 17.693 35.406 34.900 30.000 
2024-25 Overview
Investment Strategy
Technical condition surveys, inspections and assurance audits inform condition assessments.
Regular reports are made to the Marine Capital Board and the Council’s Harbour Board.
In the MAMP, priority is determined considering lifeline ferry services and required modifications or upgrades to
support new vessels deployments and national strategies like the Islands Connectivity Plan. Priorities are confirmed
by investment boards and Harbour Board.
Marine Risks
1. Impact to Island Community Connectivity.
2. Potential increase in claims for vessel damage and reputational risk to the Council.
3. Potential increase in funds required to repair infrastructures following underinvestment. 
Summary of Planned 2024-2025 investment
Investment Strategy at funding levels indicated above
Top service priorities alongside the Capital Plan
None
Match funding Opportunities/External Funding 
Achieved 2023-24 Opportunities 2024-25
Service Development   Islands Programme application for
funding for Port Askaig crew
accommodation and concept design for

Page 46

ferry. This was ultimately unsuccessful
(Nov 24).
Potential ex-SPT funds via HITRANS to
fund aspects of Jura and Luing services.
Strategic Change  Community Regeneration Fund 
Links to relevant strategies: Islands Connectivity Plan

Page 47

PRIORITY INVESTMENT PLAN – ASSET GROUP 6 SUMMARY 
Asset Group Transport Infrastructure: Council Ferries 3rd Tier
Managers
Scott Reid
Marine Operations Manager 
Description of
Asset Group
and Condition
Assessment 
Asset Group
Vessels
CONDITION
(percentages based on total asset value)
Green Yellow Amber Red
MV Lady of Lismore (2022) Passenger service only,
linking Port Appin & Lismore. 100% 0% 0% 0%
Eilean Dhiura (1998) Vehicle Ro-Ro & passenger
service, linking Islay & Jura 0% 75% 25% 0%
MV Belnahua (1972) Vehicle and passenger service,
linking Seil & Luing 0% 75% 25% 0%
ML Torsa (1996) Open workboat passenger service
only, linking Seil & Luing 0% 25% 0% 75%
ML Fladda (1994) Open workboat passenger service
only, linking Easdale & Seil 0% 25% 0% 75%
ML Easdale (1992) Open workboat passenger service
only, linking Easdale & Seil  0% 25% 0% 75% 
Investment  Funding
Funding source  Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Lismore Ferry
Scottish
Government 0.035 0.000 0.000 0.000 
2024-25 Overview
Investment Strategy
External investment from Scottish Government has been requested.
The life extension works for the vehicle carrying vessels has been covered by grant allocation to date.
Marine Risks
1. Impact to Island Community Connectivity. 
Summary of Planned 2024-2025 investment
Investment Strategy at funding levels indicated above
Top service priorities alongside the Capital Plan
Ferry Service and supporting Infrastructure Priorities
Vessel Priority Description Benefits
1 On-site accommodation at Port Askaig.
Present situation requires Officers and
crew to be residents of Islay as well as
suitably qualified.
Along with the market supplement and the 7-
day rota, this will allow the recruitment of
suitably certified Officers required for
resilience and new vessel minimum manning
levels.
2 Funding for concept design to ‘Keel Ready’
for the new Jura vessel.
To identify capacity levels; fuel type; crew
size and infrastructure upgrade
requirements. Also allows for a more
accurate assessment / estimate of build &
certification costs.
3 Jura New Build (and associated
infrastructure at Feolin & Port Askaig).
Fit for purpose and the future vessel to
support the Jura community for the next 20 –
30 years.

Page 48

4 Eilean Dhiura is re-deployed to the Cuan /
Luing route (and associated slipway
upgrades on the route).
Capable of refuse collection, HGV and
capacity increase from c.15t to c.40t.
Due to life extension on Belnahua (2024) and
Eilean Dhiura (2022) service expects to
make savings by utilising Belnahua as relief
vessel (for Dry dock) etc.
Match funding Opportunities/External Funding 
Achieved 2023-24 Opportunities 2024-25
Service Development   Islands Programme application for
funding for Port Askaig crew
accommodation and concept design for
ferry. This was ultimately unsuccessful
(Nov 24).
Potential ex-SPT funds via HITRANS to
fund aspects of Jura and Luing services.
Strategic Change  UK levelling Up Fund 
Links to relevant strategies: Islands Connectivity Plan

Page 49

PRIORITY INVESTMENT PLAN – ASSET GROUP 6 SUMMARY 
Asset Group Transport Infrastructure: Airports 3rd Tier
Managers
Moya Ingram 
Description of
Asset Group
and Condition
Assessment 
Asset Group
Airports  
CONDITION
Green Yellow Amber Red
Oban, Coll and Colonsay airports. Oban runway
length 1200m, Coll and Colonsay runway lengths
500m. Both Coll and Colonsay have a small terminal
facility comprising of office, waiting area and integral
garage. Oban airport has a larger terminal building
comprising of office, crew commander room, meeting
room, waiting area, drying area and integral double
garage. Oban airport also has a tower from which a
Flight Information Service is offered. The facilities and
runways are now circa 15 years old. 
75% 10% 10% 5% 
Investment  Funding
Funding source  Current Year Anticipated Investment (£m)
2024-25 (£m) 2025-26 2026-27 2027-28
Airports
Crown Estates 0.000 0.000 0.000 0.000
Regulators
Pioneer Fund 0.000 0.000 0.000 0.000
Rural Growth
Deal 0.000 0.000 0.000 0.000 
2024-25 Overview
Investment Strategy
Technical condition surveys, runway inspections and regulator audits inform condition assessments.
Priorities are determined by investment boards and national strategies like the Islands Connectivity Plan. 
Previous Airport Risks
1. Risk for unknown maintenance failure due to inclement weather e.g. fence damage, sign damage and
flooding. (The perimeter fence at Colonsay has been identified as failed and is no longer stock proof, animal
fouling has been noted within the airfield boundary.) Status – undertaken.
2. CAA audit inspections findings are unknown and will require to be addressed Argyll and Bute Council
operate three licensed aerodromes at Oban, Coll and Colonsay. These aerodromes are licensed by the Civil
Aviation Authority as required by law to allow scheduled passenger flight services (for use by paying
members of the public) to land and take off. The licence stipulates the required safety standards and fire
cover required for each aircraft movement. Operations at the licensed aerodromes are audited on a regular
basis by the CAA and require the appropriate level of resource. 
(The foam dispensers at Oban Airport have been identified as not running to the correct pressure deeming
them non-compliant with regulations. These require to de sent to manufacturer for
recalibration/replacement) Status – undertaken.
3. The spare island fire appliance is no longer operational and cannot be repaired. In the event of the main
appliance failing this will result in airport operations having to cease for a significant length of time due to
lack of fire cover until repairs can be undertaken. Status – undertaken.
Several other operational requirements will require future funding.
 Oban Airport Visual Control Room (VCR) equipment replacement – circa £50k
 Surfacing access road to Colonsay Airport - £250k
 Removing vegetation limiting line of site from Oban Airfield Control Tower -£10k
 Replacement of white linings/markings at 3 airports
 Clearing of Drainage at Coll Airfield
 Training revalidation of Full/Part time/Relief staff - £60k
 Replacement of grass cutting equipment and add-ons Oban Airfield - £35k

Page 50

 Operational Radio Replacement at Coll and Colonsay Airport 
Summary of Planned 2024-2025 investment
Investment Strategy at funding levels indicated above
Top service priorities alongside the Capital Plan
Airport Service and supporting Infrastructure Priorities 
Airport Service Priority Cost (£) Are costs
indicative
or
calculated)
Estimated
funding
shortfall
Asset
category
(asset
sustainability,
service
development,
strategic
change)
1. Upcoming Costs Oban
Resurfacing Echo and Foxtrot Taxiway £28,765.19
Resurface Golf Taxiway £56, 280.28
Control Tower Equipment Ageing £50k+
PPE £5k
FODBoss equipment £ unknown
£150k Indicative £150k 
2. Upcoming Costs Colonsay
Runway line painting £4k
Fire fighter PPE £10k
Replacement of MET Equipment £2,500
£16,500k Indicative £16,500k 
3. Upcoming Costs Coll
Runway line painting £4k
Fire fighter PPE £10k 
£14k Indicative £14k 
4. Staff Training Costs £30k Indicative £30k 
Match funding Opportunities/External Funding 
Achieved 2023-24 Opportunities 2024-25
Asset Sustainability  
Service Development   
Strategic Change  UK Levelling Up Fund/Islands Connectivity
Funding 
Links to relevant strategies: Islands Connectivity Plan