ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 27 FEBRUARY 2025
CAPITAL PLAN 2025-28 SUMMARY REPORT 
1. EXECUTIVE SUMMARY 
1.1  This report outlines proposals for the roll forward of the current 3 year Capital
Plan 2024-27 by 1 year, incorporating updated funding assumptions, new
spending proposals, and the re-phasing of total programme spend across the 3
years of the new Capital Plan 2025-28. 
1.2 Funding constraints have put significant pressure on the ability to deliver capital
investment.  In addition, the capital programme continues to see significant price
increases, as well as disruptions to the supply chain and longer lead in times,
due to the impact of world events (Covid pandemic, UK exit from EU, Russian
invasion of Ukraine) on the global economy.  These impacts make it extremely
challenging to manage the delivery of the capital programme within available
resources and target completion timescales.   
1.3 The Local Government Finance Settlement Circular 12/2024 provided 2025-26
General Capital Grant of £9.666m, excluding effectively ring-fenced or directed
funding of £1.198m.  This represents £0.832m more than previous planning
assumptions.  However, the 2024-25 final General Capital Grant settlement was
£0.047m lower than assumed within the approved Capital Plan.  There is,
therefore, a net increase in capital resources of £2.449m overall for the 3 years
2025-28. 
1.4  The ring-fenced or directed funding of £1.198m, included within the General
Capital Grant, comprises £0.632m for Campbeltown Flood Scheme, £0.391m for
Play Parks and £0.175m for Nature Restoration Fund.  There is also a specific
grant of £0.383m available for Active Travel (formerly known as Walking Cycling
& Safer Streets).   
1.5 
1.6
The amount of capital resources effectively top-sliced from the General Capital
Grant and allocated to Private Sector Housing Grant (PSHG) is provided for at
£1.033m per annum over the 3 years 2025-28, similar to previous years’ levels,
although the funded GAE level has reduced to £0.707m in 2025-26.  In addition,
a GAE equivalent amount of £0.156m per annum is directed to flooding projects. 
The balance of the available 2027-28 General Capital Grant, assumed for
planning purposes (£7.645m), has been allocated across Priority Investment
Plans on an agreed block allocation formula basis, in line with previous years.   
The settlement also provides for additional, non-recurring capital grant funding of
£40m across Scotland in 2025-26 for Climate Emergency, to be included within
the General Capital Grant.  Given that project planning across the programme
will already take cognisance of climate change, as a key consideration, it has not

Page 2

been necessary to augment planned project expenditure in this respect.  As
such, this funding represents additional available resources for 2025-26.   
1.7 
1.8 
1.9 
1.10 
1.11
There is a rolling 3 year target for capital receipts from asset sales, forming part
of the overall funding framework for the 2025-28 Capital Plan.  The level of
receipts that may reasonably be achieved over the 3 years 2025-28 totals
£1.750m, profiled £0.750m 2025-26 and £0.500m across each of the years
2026-27 and 2027-28.  Additional unbudgeted capital receipts of £0.040m from
vehicle sales has also been achieved during 2024-25.  This represents an
overall increase of £0.640m in available funding for capital investment over the 3
years 2025-28. 
Project specific grant funding and other capital contributions are accounted for
within specific projects.  Project approved gross expenditure and income are
increased by the same amount, with no impact on project net expenditure. 
Similarly, project gross expenditure may be augmented by the level of
earmarked reserve balances used to fund programme net expenditure, with no
impact on required borrowing. 
As at 31 December 2024, there is a forecast overspend of £0.117m on the
current 2024-27 Capital Plan.  In addition, spending requirements deemed to be
essential, either critical to maintain service delivery, or to comply with legislation
or regulation (Red RAG status risks), total an estimated £0.376m. 
After taking account of budget pressures and proposed allocations, the balance
of additional capital resources, available for additional capital investment over
the 3 years 2025-28 is £3.560m.  This may be augmented by additional
borrowing for capital purposes, with the revenue consequences, in terms of debt
charges, accounted for as part of the annual revenue budget for 2025-26 and
future years.  There is also an option to redirect resources, allocated but not yet
committed, to other priorities, including in respect of the allocation to PSHG at
the historic, above GAE level.   
A range of currently unfunded investment priorities across council services have
been identified, including in respect of the Roads Maintenance programme for
2025-26, with an estimated funding shortfall of £9m to maintain current level
standards. 
1.12 
1.13
A number of known risks, specifically related to the delivery of the Capital Plan,
are documented within this report.  These risks may impact the delivery of the
plan within available resources and target timescales.   
It is recognised that there are opportunities to take a more strategic approach to
capital planning and to enhance existing governance arrangements around
capital investment activity.  This will be further explored during 2025-26.

Page 3

ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES                                          27 FEBRUARY 2025
CAPITAL PLAN 2025-28 SUMMARY REPORT 
2. INTRODUCTION 
2.1  This report outlines proposals for the roll forward of the current 3 year Capital
Plan 2024-27 by 1 year, incorporating updated funding assumptions, new
spending proposals, and the re-phasing of total programme spend across the 3
years of the new Capital Plan 2025-28. 
3. DETAIL 
3.1 Capital Funding Changes 2025-28 
3.1.1 
3.1.2 
3.1.3 
3.1.4 
The Local Government Finance Circular 10/2024, published on 12 December
2024, provides details of the provisional total capital funding allocations for
2025-26. The provisional total funding allocations form the basis for the annual
consultation between the Scottish Government and COSLA, ahead of the Local
Government Finance (Scotland) Order 2024 presented to the Scottish
Parliament.  The Finance Order was laid in Parliament on 4 February with
Stages 1-3 between 4 February and 25 February with the Finance Order
Debate taking place on 27 February.   
Funding constraints have put significant pressure on the ability to deliver capital
investment.  In addition, the capital programme continues to see significant
price increases, as well as disruptions to the supply chain and longer lead in
times, due to the impact of world events (Covid pandemic, UK exit from EU,
Russian invasion of Ukraine) on the global economy.  These impacts make it
extremely challenging to manage the delivery of the capital programme within
available resources and target completion timescales. 
The 2024-27 Capital Plan, approved in February 2024, included future year
General Capital Grant assumptions for 2025-26 and 2026-27 at the actual
2024-25 level of £8.834m.  This estimation was based on the Capital Spending
Review undertaken by Scottish Government which advised that the capital
settlements were likely to stay constant over the next five years (2021-22 to
2025-26). 
The Local Government Finance Settlement Circular 12/2024 provided 2025-26
General Capital Grant of £9.666m, excluding effectively ring-fenced or directed
funding of £1.198m.  This represents £0.832m more than previous planning
assumptions.  However, the 2024-25 final General Capital Grant settlement

Page 4

3.1.5 
3.1.6 
3.1.7 
was £0.047m lower than assumed within the approved Capital Plan.  There is,
therefore, a net increase in capital resources of £2.449m overall for the 3 years
2025-28. 
The ring-fenced or directed funding of £1.198m, included within the General
Capital Grant, comprises £0.632m for Campbeltown Flood Scheme, £0.391m
for Play Parks and £0.175m for Nature Restoration Fund.  There is also a
specific grant of £0.383m available for Active Travel (formerly known as
Walking Cycling & Safer Streets).  Project expenditure plans, matched by these
funding streams, will be built into the capital programme. 
The amount of capital resources effectively top-sliced from the General Capital
Grant and allocated to Private Sector Housing Grant is provided for at £1.033m
per annum over the 3 years 2025-28.  This amount has remained at the same
level since 2016-17, however, the GAE level, included within the 2025-26
General Capital Grant is now £0.707m.  Members may wish to review the
amount allocated to PSHG and this is explored further within Section 3.5 of this
report.  In addition, a GAE equivalent amount of £0.156m per annum is directed
to flooding projects. 
The settlement also provides for additional, non-recurring capital grant funding
of £40m across Scotland in 2025-26 for Climate Emergency, to be included
within the General Capital Grant.  Whilst the distribution across individual
authorities has yet to be confirmed, based on the expected distribution formula,
additional funding of £0.964m has been assumed within the Capital Plan for
2025-26.  Given that project planning across the programme will already take
cognisance of climate change, as a key consideration, it has not been
necessary to augment planned project expenditure in this respect.  As such,
this funding represents additional available resources for 2025-26.  
3.1.8 
3.1.9
There is a rolling 3 year target for capital receipts from asset sales, forming part
of the overall funding framework for the 2025-28 Capital Plan.  This is based on
an assessment undertaken by Commercial Services on potential sales
opportunities, now extending another year through to 2027-28.  There is an
estimated overall increase in capital income across the programme of £0.600m
in this respect.  The level of receipts that may reasonably be achieved over the
3 years 2025-28 totals £1.750m, profiled £0.750m 2025-26 and £0.500m
across each of the years 2026-27 and 2027-28.  The assets available for sale
are listed in Appendix 1.  Additional unbudgeted capital receipts of £0.040m
from vehicle sales has also been achieved during 2024-25.  This represents an
overall increase of £0.640m in available funding for capital investment over the
3 years 2025-28. 
Project specific grant funding and other capital contributions are accounted for
within specific projects.  Project approved gross expenditure and income are
increased by the same amount, with no impact on project net expenditure. 
Similarly, project gross expenditure may be augmented by the level of
earmarked reserve balances used to fund programme net expenditure, with no
impact on required borrowing. Details of project specific capital income, totalling
£13.302m and reserve balances earmarked to fund capital expenditure,
totalling £10.607m over the 3 years 2025-28 are outlined within Appendix 2.

Page 5

3.2 
3.2.1 
3.2.2
New Capital Commitments and Resource Allocations 
As at 31 December 2024, there is a forecast overspend of £0.117m on the
current 2024-27 Capital Plan.  In addition, spending requirements deemed to be
essential, either critical to maintain service delivery, or to comply with legislation
or regulation (Red RAG status risks), total an estimated £0.376m (£0.305m
Riverside Leisure Centre and £0.071m ICT).  Members are requested to
approve the allocation of additional resources totalling £0.493m in respect of
these items. 
In order to support early capital planning, an indicative block allocation from the
General Capital Grant for a further year, 2027-28 was provided, allowing the
development of Priority Investment Plans across a range of service categories. 
After allowing for an allocation to Private Sector Housing Grant and flooding
projects, a 2027-28 balance of £7.645m, assumed for planning purposes, has
been allocated across Priority Investment Plans (PIPs).  This is based on an
agreed block allocation formula, in line with previous years.  PIPs outline
spending proposals to meet service priorities and also provide details of
currently unfunded service aspirations.  Details of the 2027-28 General Capital
Grant block allocations are outlined in the table below.  Members are requested
to approve these resource allocations. 
Service % Share £000 
Education 26% 1,988
Customer Services - IT 9% 688
Customer Services - Facilities 5% 382
Roads & Infrastructure Services 50% 3,823
Social Work (HSCP) 5% 382
LiveArgyll 5% 382
Total 2027/28 GCG Block Allocation 100% 7,645
Private Sector Housing Grant (Top-sliced)  1,033
Flooding – General (Top-sliced)  156
Total 2027/28 GCG (Planning Assumption)  8,834

Page 6

3.3 
3.3.1 
3.3.2 
Updated Capital Plan 
As part of the capital planning process, services have reviewed project costs
and spending profiles and re-profiled total resources, comprising existing
approvals and new 2027-28 block allocations, across the 3 years of the Capital
Plan 2025-28. 
The table below provides a summary of the updated Capital Plan 2025-28
planned investment or gross expenditure, subject to member approval of new
spending commitments and block allocations outlined within Section 3.2 of this
report, while a more detailed breakdown is given within Appendix 3.  This is
prior to the allocation of any additional resources, explored within Section 3.5 of
this report.   
2025-26
£m
2026-27
£m
2027-28
£m
Total
£m
Executive Directorate (Douglas
Hendry):        
Education 2.946 1.988 1.988 6.922
Facility Services - Shared Offices 3.681 0.667 0.382 4.730
Major Projects/CHORD 10.865 10.018 0.000 20.883         
Executive Directorate (Kirsty
Flanagan):       
ICT 1.352 0.820 0.688 2.860
Roads and Infrastructure 48.500 39.110 33.979 121.589
Development and Economic
Growth 1.104 0.000 0.000 1.104         
Health and Social Care
Partnership 2.084 0.000 0.382 2.466         
Live Argyll 0.474 0.468 0.382 1.324         
Total 71.006 53.071 37.801 161.878 
3.3.3  After accounting for project specific capital income of £13.302m, as outlined at
paragraph 3.1.9, the net expenditure on the capital programme that requires to
be funded totals £148.576m over the 3 years 2025-28.  This funding framework
comprises General Capital Grant, capital receipts from asset sales and capital
funded from current revenue or earmarked reserves, with the balance to be met
from borrowing.

Page 7

3.3.4 
Details of the funding framework for capital net expenditure over the 3 years
2025-28 is set out in the table below. 
2025-26
£m
2026-27
£m
2027-28
£m
Total
£m
Net Capital Expenditure 62.704 48.071 37.801 148.576
Funded by:        
General Capital Grant 11.178 8.633 8.633 28.444
Asset Sales 0.750 0.500 0.500 1.750
Earmarked Reserves/Revenue 5.577 5.030 0.000 10.607
Borrowing 45.199 33.908 28.668 107.775
Total Funding 62.704 48.071 37.801 148.576 
3.3.5 
3.3.6 
3.4 
3.4.1 
There are a number of projects where the annual debt charges are expected to
be fully offset by revenue budget savings, either through increased income or
reduced expenditure, over the useful life of the project deliverables, with no
impact on Council Tax.  This is generally referred to as prudential borrowing and
accounts for £100.593m of the overall borrowing requirement in the above table,
largely in respect of the Harbour Investment Programme. 
The estimated gross capital expenditure and borrowing requirement over the 3
years 2025-28, arising from the 2025-28 Capital Plan, are reflected within the
Capital and Prudential Indicators 2025-28, set out within the council’s 2025-26
Treasury Management Strategy.  Revenue implications of borrowing in respect
of future debt repayments are provided for within the council’s revenue budget
forecasts for 2025-26 and future years.   
Unfunded Priorities 
The priority investment planning process has identified a number of currently
unfunded priorities, broadly comprising the following: 
• An estimated funding shortfall in Roads Maintenance of £9m.  This is the
estimated additional level of investment that would be required to
maintain roads to the current level standard (steady state), based on an
estimated cost of £11m at current prices, compared to a planned level of
investment from the block allocation of £2m for 2025-26; 
• An estimated funding shortfall in Footway Maintenance of £950k, on a
similar basis to that of Roads Maintenance; and 
• Indicative cost estimates that require to be refined, and profiled over
2025-26 and future years, in respect of a number of other identified
service priorities.  These are largely in respect of Asset Sustainability and
include investment in Sports Facilities, Fleet, Waste, Airports, Flood Risk
Management, and Bridges and Coastal Protection. 
More detailed information on the Priority Investment Plans (PIPs) is contained
within a separate report on the Corporate Asset Management Strategy and
Plan.

Page 8

3.4.2 
3.5 
3.5.1 
Members may wish to consider additional investment for currently unfunded
service priorities.  Funding options and considerations in this respect are
outlined in the following section. 
Additional Investment Considerations 
After taking account of new planned spending commitments and block
allocations, the balance of additional capital resources, available for further new
capital investment over the 3 years 2025-28 is £3.560m, as detailed in the table
below.     
£000
Decrease to 2024-25 GCG (47)
Increase to 2025-26 GCG  832
Increase to 2026-27 and 2027-28 GCG Assumption 1,664
2027-28 GCG Assumption (2024-25 level) 8,678
2027-28 PSHG Allocation (1,033)
2027-28 Block Allocation (PIP Process) (7,645)
Climate Emergency Fund (One-off – will go into
GCG)
964
Current Capital Plan Forecast Overspend (117)
Red Risks (Regulatory, Critical) (376)
Additional Asset Sales  640
Net Total Available Resources 3,560 
3.5.2 
3.5.3 
Council requires to consider the allocation of available resources of £3.560m, in
light of the unfunded investment priorities set out within paragraph 3.4.1.  This
available resource reflects the balance remaining from the estimated additional
capital income, after providing for planned spending commitments and
allocations, over the 3 years 2025-28.  There is, therefore, no impact on the
revenue budget in this respect. 
As set out at paragraph 3.1.6 of this report, the level of resources top-sliced
from the GCG and allocated to PSHG is currently planned at the historic level of
£1.033m.  However, it should be noted that the indicative GAE level, funded
from within General Capital Grant, has reduced to £0.707m in 2025-26, while
the average annual spend in recent years equates to circa £0.820m.  A
reduction to the average spend level over each of the 3 years would result in
additional resources of £0.640m being made available for redirection.  There is

Page 9

3.5.4
also an option to redirect resources, allocated through the block allocation but
not yet committed, to other council priorities. 
There is also an opportunity to fund additional capital investment through
additional borrowing.  However, the revenue consequences, in terms of
increased debt charges, would require to be accounted for as part of the annual
revenue budget for 2025-26 and across future years.  For illustrative purposes,
every £1m of additional borrowing for capital purposes creates an annual
revenue budget pressure of circa. £0.065m, on average. 
3.6 
3.6.1 
3.6.2 
3.6.3 
3.6.4 
Capital Plan Risks 
The finance circular received on 12 December 2024 provided details of
government grant funding for 2025-26.  There is, therefore, a degree of certainty
in respect of General Capital Grant and available specific capital grant funding
for 2025-26.  However, there is a risk that future years grant settlements will be
below the 2025-26 level, assumed in the Capital Plan for 2026-27 and 2027-28. 
Also, at the time of writing, the council’s share of an additional £40m Climate
Emergency Fund, to be paid as General Capital Grant, has still to be confirmed. 
The Capital Plan has assumed additional funding of £0.964m in this respect. 
Any variation in the final allocations from these assumptions will require to be
managed within the overall Capital Plan resources. 
The funding framework for the approved Capital Plan includes capital receipts
from asset sales, estimated at £0.750m in 2025-26 and £1.750m over the 3
years 2025-28.  This is based on an assessment provided by the Estates Team
in January 2025, however, is subject to changing market conditions.  The level
of receipts that may reasonably be achieved will be kept under review, to reflect
changing market conditions and due diligence undertaken on asset condition. 
Any variation from this assumption will require to be managed within the overall
Capital Plan resources. It is generally the case that the capital programme
experiences slippage throughout the year and as such, this risk is expected to
be manageable. 
As capital project approvals are based largely on early indicative cost estimates,
there is a risk that actual costs will be more than originally planned, particularly
in the current economic climate and where there has been unavoidable project
delays.  The capital programme continues to see significant price increases, as
well as disruptions to the supply chain and longer lead in times, due to the
impact of world events (Covid pandemic, UK exit from EU, Russian invasion of
Ukraine) on the global economy. Additional funding of £11m, made available to
manage these impacts to date, has now been fully allocated.  There are likely to
be other significant cost pressures in respect of projects, where contracts have
yet to be entered into, which are not quantifiable, at this stage.  It will be
challenging to manage these impacts within available resources and target
completion timescales. 
The Capital Plan monitoring report, as at 31 December 2024, outlines a forecast
overspend on the 2024-27 Capital Plan of £0.117m.  Members are requested to
approve additional resources in this respect, as part of the 2025-26 budget
process, as outlined in Section 3.2 of this report.

Page 10

3.6.5 
3.6.6 
3.6.7 
3.6.8 
3.7 
3.7.1 
The council’s funding bid to the Scottish Government’s Learning Estate
Investment Programme (LEIP) for a new school campus on Mull was
successful. While this is good news and will provide welcome investment in the
school estate, it will not meet the full cost of the project.  The funding gap
requires to be met by the council and presents a financial pressure. The
Scottish Government will fund up to 50% of eligible costs, with the balance of
circa. £20m to be funded by the council.  No specific provision has been
included within the 2025-28 Capital Plan in this respect, at this stage. 
There is a risk of further severe weather incidents, requiring both revenue and
capital expenditure to be incurred.  Whilst there may be additional funding
available through the Bellwin Scheme, this is limited to eligible revenue
expenditure only.  There is no provision for potential additional costs in this
respect within the 2025-28 Capital Plan.  This risk is considered as part of the
council’s policy on the level of the general contingency balance held within the
unallocated General Fund reserve. 
Following the weather event in October 2023 a temporary emergency road was
constructed at the A816 Bealach Mor, Kintraw, Ardfern.  Due to the future stability
of the hillside, the plan is for permanent diversion onto a widened alignment of
the emergency route.  Funding of £1.1m is already provided for within the capital
plan however this may not be sufficient.  A feasibility options report is being
prepared and a preferred option will be presented for approval following which
ground investigation and consultations with stakeholders will take place to inform
the design and build contract.  A design and build contract shall be prepared and
tendered and any shortfall in budget will be determined.   
The monitoring and review of these risks will continue to be undertaken on an
ongoing basis, with actions put in place to continue to mitigate or manage these
risks, as far as possible.  Actions to manage financial risk within available
resources may include re-profiling; project redesign, re-engineering or
curtailment, and the re-prioritisation of uncommitted resources across the
programme.  An update on risks will be reported regularly to Policy and
Resources Committee, as part of future capital programme monitoring reports. 
Opportunities for Improvement 
It is recognised that there are opportunities to take a more strategic approach to
capital planning and to enhance existing governance arrangements around
capital investment activity.  The Executive Leadership Team is committed to
undertaking a future review and recommendations will be reported to members
during 2025-26 in this respect.  Whilst the detailed specification of requirements
of the review has still to be developed, at this stage, it is anticipated that the
review will include the following: 
▪ Enhanced governance arrangements, including greater member
involvement in the allocation of capital resources.  This would include a
review of current Priority Investment Plans and whether they remain fit
for purpose in their current format and provide Members with sufficient
information for decision making;

Page 11

4.
▪ Longer term financial planning, including longer term Capital Plan (5-10
years); 
▪ Integrated capital forecasting, treasury strategy and debt charges
(revenue budget) modelling; 
▪ A review of the capacity within the current debt charges budget for
additional investment, reflecting capital planning and treasury borrowing
assumptions; and 
▪ An updated Capital Strategy, to help ensure that we are investing in our
infrastructure, to support council key strategic priorities. 
CONCLUSIONS 
4.1 
4.2 
4.3 
4.4
The 3 year Capital Plan has been rolled forward another year, now covering the
period 2025-28.  Funding assumptions; planned spending commitments,
including block allocations across services; and profiling across 2025-26 and
future years have been updated for the Capital Plan period 2025-28.   
Subject to member approval of planned spending commitments and block
allocations, there is a balance of £3.560m additional capital resources available,
to be allocated to increase levels of planned investment in service priorities. 
There are opportunities to augment the level of additional resources available
for increased investment in the highest priorities, through review and redirection
of planned resource allocations, not yet committed, and from additional
borrowing, as set out at paragraphs 3.5.4 and 3.5.4 of the report.   
There are a number of specific capital programme risks that require to be
monitored and reviewed on an ongoing basis, and which will require to be
managed within available resources.   
Opportunities to enhance current capital arrangements will also be explored,
with recommendations to be reported to members, following a review to be
undertaken during 2025-26. 
5. IMPLICATIONS 
5.1 Policy – Sets out the approach to capital planning. 
5.2 Financial – Outlines the planned capital investment and funding for the capital
planning period 2025-28. 
5.3 Legal - Statutory and Regulatory requirements in relation to Health and Safety
have been provided for within capital spending plans.   
5.4 HR - There are risks that the funding available will have an impact on the
sustainability of the Property Design Team and the design team within Roads and
Amenity Services. 
5.5 Fairer Scotland Duty:

Page 12

5.5.1
5.5.2
5.5.3
Equalities – Impacts will be considered as appropriate.
Socio-Economic Duty – Impacts will be considered as appropriate. 
Islands Duty – Islands duty is considered as part of the Equality and Socio-
Economic Impact Assessments 
5.6 Climate Change – The council is committed to addressing climate change, within
the available budget resources. 
5.7 Risk - There are a number of risks impacting the delivery of the Capital Plan within
available resources and target timescales, which require to be monitored on an
ongoing basis. 
5.8 Customer Service – None. 
5.9 The Rights of the Child (UNCRC) - None   
Kirsty Flanagan
Executive Director/Section 95 Officer
13 February 2025 
Councillor Ross Moreland - Policy Lead for Finance and Commercial
Services 
APPENDICES:
Appendix 1 - Proposed Asset Disposals
Appendix 2 -  Project Specific Capital Income and Earmarked Reserves
Appendix 3 - Proposed Capital Investment 2025-28 
For further information please contact:
Carolyn Earl, Acting Head of Financial Services 
carolyn.earl@argyll-bute.gov.uk

Page 13

Appendix 1 - Proposed Asset Disposals 2025-28
Property
Shop, 3 Montague Street
Ardchonnel Primary School
Skipness Primary School
Hill Street office
Achaleven Primary School
Minard Primary School
Southend Primary School
Former Registrar Office, Witchburn Road
Witchburn Road site, former Finance Office
Ground at 125 Frederick Street
Former Lochgilphead Primary School
Area of ground adjoining Pier House Fionnphort, Isle of Mull
Land at Broom Road,
Former Girl Guide Hut, Dunclutha Lane
Luing Primary School
Kilchrenan Primary School
Dunclutha Children's Home
Blairvadach site, Shandon, Helensburgh (Phase 2)
Note: Estimated sale values are not separately disclosed due to
commercial sensitivity.

Page 14

Appendix 2 - Project Specific Capital Income and Earmarked Reserves
Project Specific Capital Grants and Contributions
2025-26
£m
2026-27
£m
2027-28
£m
Total
£m
HSCP
Scottish Government Island Funding - Tigh Na Rhuda 0.050 0.000 0.000 0.050
HSCP - Kintyre Care Home 0.650 0.000 0.000 0.650
HSCP - General Funding 0.260 0.000 0.000 0.260
HSCP Total 0.960 0.000 0.000 0.960
CHORD
Rothesay Pavilion - HIE/HES/HLF 2.700 0.000 0.000 2.700
Rothesay Pavilion - Rural Growth Deal 4.000 5.000 0.000 9.000
CHORD Total 6.700 5.000 0.000 11.700
Roads & Infrastructure Services
Coastal Change Adaptation 0.142 0.000 0.000 0.142
Roads & Infrastructure Services Total 0.142 0.000 0.000 0.142
Development & Economic Growth
Coastal Communities Funding (Crown Estate) 0.500 0.000 0.000 0.500
Development & Economic Growth Total 0.500 0.000 0.000 0.500
Total 8.302 5.000 0.000 13.302
Earmarked Reserve Balances
2025-26
£m
2026-27
£m
2027-28
£m
Total
£m
Cimate Change Programme / NDEEF 0.550 0.000 0.000 0.550
RAAC - John Logie Baird 0.600 0.000 0.000 0.600
Red Risk - ICT 0.120 0.000 0.000 0.120
Rothesay Pavilion 3.371 5.000 0.000 8.371
Crown Estates 0.390 0.000 0.000 0.390
SG Islands Fund 0.157 0.000 0.000 0.157
Inflationary Increases - ICT 0.279 0.000 0.000 0.279
Inflationary Increases - Fleet Road Marking Machine 0.028 0.000 0.000 0.028
Inflationary Increases - Claonaig Landslip 0.000 0.030 0.000 0.030
Inflationary Increases - RAAC - John Logie Baird 0.082 0.000 0.000 0.082
Total 5.577 5.030 0.000 10.607

Page 15

Appendix 3 - Capital Investment 2025-28
Service Category Project
2025-26                
£000s
2026-27                 
£000s
2027-28                
£000s
Total
£000s
Education Asset Sustainability Block Allocation - Education 0 1,988 1,988 3,976
Digital Inclusion 20-21 0 0 0 0
Free School Meals 434 0 0 434
Preliminary RAAC Investigation 1,006 0 0 1,006
Primary Schools 1,280 0 0 1,280
Secondary Schools 226 0 0 226
Asset Sustainability Total 2,946 1,988 1,988 6,922
Education Total 2,946 1,988 1,988 6,922
Shared Offices Asset Sustainability 5-7 East Clyde Street - Coastal Communities Fund 390 0 0 390
Block Allocation 427 382 382 1,191
Kilmory Castle 1,545 0 0 1,545
Asset Sustainability Total 2,362 382 382 3,126
Strategic Change Clean Energy - NDEEF1 208 0 0 208
Clean Energy - NDEEF2 855 285 0 1,140
Net Zero 256 0 0 256
Strategic Change Total 1,319 285 0 1,604
Shared Offices Total 3,681 667 382 4,730
CHORD Strategic Change CHORD - Oban 79 0 0 79
Rothesay Pavilion 10,000 10,000 0 20,000
Kilmory Business Park Phase 2AA 786 18 0 804
Strategic Change Total 10,865 10,018 0 20,883
CHORD Total 10,865 10,018 0 20,883
ICT Asset Sustainability Block Allocation - ICT 0 820 688 1,508
PC Replacement 669 0 0 669
Server Sustainability 400 0 0 400
Telecomms Network 223 0 0 223
Asset Sustainability Total 1,292 820 688 2,800
Service Development Applications Projects 60 0 0 60
Service Development Total 60 0 0 60
ICT Total 1,352 820 688 2,860
RIS Asset Sustainability Block Allocation -222 3,823 3,823 7,424
Bridge Strengthening 1,498 0 0 1,498
Bute Sea Wall Repairs 359 0 0 359
Claonaig Landslip 42 0 0 42
Coastal Change Adaptation 299 0 0 299
Coastal Protection 500 0 0 500
Environmental Projects 100 0 0 100
EV Quick Chargers 0 0 0 0
Flood Prevention 500 0 156 656
Helensburgh Flood Mitigation 427 0 0 427
Lighting 369 0 0 369
Local Bridge Maintenance Fund 4,777 0 0 4,777
Play Park Renewal 391 0 0 391
Public Convenience Upgrades 109 0 0 109
Roads Reconstruction 2,000 0 0 2,000
Asset Sustainability Total 11,149 3,823 3,979 18,951
Service Development Fleet Management - Prudential Borrowing 500 0 0 500
Weather Incident October 2023 1,100 0 0 1,100
Service Development Total 1,600 0 0 1,600
Strategic Change Campbeltown Flood Scheme 24 387 0 411
Harbour Investment Programme PB 35,406 34,900 30,000 100,306
Street Lighting LED Replacement 321 0 0 321
Strategic Change Total 35,751 35,287 30,000 101,038
RIS Total 48,500 39,110 33,979 121,589
DEG Service Development Helensburgh Public Realm - Arts Strategy Fund 25 0 0 25
Nature Restoration Fund 409 0 0 409
Safe Streets, Walking and Cycling (CWSS) 383 0 0 383
Service Development Total 817 0 0 817
Strategic Change TIF - Halfway House Roundabout 287 0 0 287
Strategic Change Total 287 0 0 287
DEG Total 1,104 0 0 1,104
HSCP Asset Sustainability Block Allocation 0 0 382 382
Capital Property Works 9 0 0 9
Eadar Glinn 25 0 0 25
Kintyre Care Home 673 0 0 673
Struan Lodge Boiler 566 0 0 566
Thomson Home Rothesay 776 0 0 776
Tigh An Rudha HFE 35 0 0 35
Asset Sustainability Total 2,084 0 382 2,466
HSCP Total 2,084 0 382 2,466
Live Argyll Asset Sustainability Aqualibrium 104 0 0 104
Capital Property Works 0 382 382 764
Corran Halls Gaelic Centre 0 86 0 86
Riverside Leisure Centre 305 0 0 305
Rothesay Swimming Pool 65 0 0 65
Asset Sustainability Total 474 468 382 1,324
Live Argyll Total 474 468 382 1,324
Overall Total 71,006 53,071 37,801 161,878