Argyll and Bute Council – Corporate Governance Action Plan 2021/2022 - Updated 
Ref Improvement actions  Success measures Key dates Lead
CG-1 Continue to engage with the
Scottish Government and other
local authorities to determine
the most efficient and effective
way of ensuring the Council
can provide a waste solution
which complied with the 2025
Bio-degradable Municipal
Waste Ban
Progress made in
identifying appropriate
solution 
Update: Specialist
economic consultants
now engaged on an
options appraisal
exercise to help inform
the decision. This is to
be reported to
September’s ED&I
committee. 
Included in plan for
22/23 
31 March 2022  Head of R&I
CG-2 Further develop the Council’s
Counter Fraud Team
2 year pilot successful
and SMT agree to it
becoming a permanent
feature of the Councils’
establishment 
Update: The Counter
Fraud Team (CFT) have
submitted a report to the
ELT which outlines the
actions, rebilling and
recovery to date with a
31 March 2022
Complete
Head of FS

Page 2

Appendix 1
proposal for
permanency.  
CG-3 Progress the project to
upgrade the Council’s general
ledger system with an
anticipated go live of 1 April
2022
System in place and
monitoring of
effectiveness
undertaken 
Update: This has now
been pushed back to
the 6 June 2022 at the
earliest due to issues
which have surfaced
during the
implementation of the
automated interface
between Concerto and
Oracle. 
Included in plan for
22/23 
31 March 2022 Head of FS
CG-4 Complete the development of
the automated interface
between the Property
Management System
(Concerto) and the Financial
System (Oracle) to process
contractor payments 
Interface in place and
monitoring of
effectiveness
undertaken 
Update: The capital
Oracle/Concerto
interface has been
completed. The revenue
interface has been
delayed because of the
30 September
2021
Head of CS

Page 3

Appendix 1
need for Oracle to be
updated as advised at
CG-3 
Included in plan for
22/23 
CG-5 Review of the scheme of
delegation in relation to
property matters to ensure
decisions are taken at the
correct level
Appropriate delegations
agreed and monitoring
of effectiveness
undertaken 
Update: Further review
of property delegations
will be included in the
next review of the
constitution. 
31 March 2022
Complete
Head of CS 
CG-6 Enhance reporting of
workforce planning to the
Strategic Management Team
and Elected Members
Reporting process in
place and working well 
Update: Operational
Workforce plans are
reviewed on a six
monthly basis and each
team in the council are
assigned a WFP risk
rating. Data from these
discussions are collated
and analysed in a report
which is presented to
SMT. HROD team
highlight any common
31 March 2022
Complete 
Head of CSS

Page 4

Appendix 1
themes that would
benefit from a revised
corporate approach.
Quarterly health of the
organisation reports are
presented to DMT and
SMT which cover a
number of workforce
indicators. 
CG-7 Further progress the work to
digitalise all document and
evidence exchanges for Local
Development Plan 2
‘Examination in Public’
Digitalised system in
place and monitoring of
effectiveness
undertaken 
Update: complete and
DPEA have
complimented D&EG on
the provision of
information in the
required format
31 March 2022
Complete
Head of D&EG 
CG-8 Respond to the findings of the
Scrutiny Review of the
Strategic Housing Fund which
is to be reported in June 2021 
All actions identified are
progressed – 
Update: Complete
31 March 2022
Complete
Head of D&EG 
CG-9 Continue to improve quality
and accuracy of asset
information which will benefit
asset valuations, calculations
for utilities costs and asset
management
System in place and
monitoring of
effectiveness
undertaken 
Update: Contract let and
31 March 2022 Head of CS

Page 5

Appendix 1
work underway to
gather updated asset
information for major
buildings – new plans
being drawn. Estates
has continued to
improve records with the
property measurement
contract providing new
plans for properties. As
part of the asset
valuation process
Estates also building up
property records and will
use the details for the
insurance valuation
updates to be
completed in 2022/23. 
Include in plan for 22/23 
CG-10 Further progress the
implementation of a self-billing
approach using CareFirst for
payments to social care
providers 
Processes and
procedures in place and
monitoring of
effectiveness
undertaken 
Update: This action has
been suspended
pending the
implementation of two
new key systems which
31 March 2022 Head of FS

Page 6

Appendix 1 
would be integral to the
revised process: The
Oracle Fusion Financial
Management System
and the Eclipse Social
Work Management
System. Once the two
systems are up and
running and we know
what the Eclipse system
can do – the vendor is
still writing the software
- we’ll be able to
determine the actions
necessary to implement
this process. 
Included in plan for
22/23