Appendix 3
SUMMARY OF OFF-TRACK PERFORMANCE 
The following six KPIs are currently off-track and performance has decreased since the last
reporting period. All four KPIs were noted in the previous performance report as off Track
and Decreasing. 
EDU107_05-Maintain the percentage of all young people leaving school achieving a
positive destination into further education, training or employment.
Target: 95.0%
Actual: 93.5%
The Annual Participation Measure for 2020-21 was released on 31st August 2021. In Argyll
and Bute 93.5% of young people aged 16-19 were participating (in work, training or
education). This figure is 1.3% above the national average. 3.2% were not participating,
which is equal with the national average. 3.3% were unconfirmed, which is 1.3% below the
national average. 
LRS110_02-Maintain the percentage of local suppliers that benefit from the awards of
contracts via the procurement portal.
Target: 20.0%
Actual: 13.5%
FQ4 saw a performance of 13.5%. This is a decrease from the previous quarter due to the
nature of the contracts. However, of the 6 bids made by local contractors, 5 were awarded
the contract (83.3%) with a total value of over £911k. A summary of all contracts awarded in
FQ4 is available on Pyramid. The Procurement, Commercial and Contract Management
Team (PCCMT) continue to support local suppliers by providing useful information on the
Council’s website, ie: pre-recorded webinars on how to bid for Council contracts, hints and
tips for tendering as well as our contract plan, details of upcoming supplier development
events and our category officer’s contact details all of which enable local suppliers to be
able to bid for our contracts. The YTD % is 26.1% (above target). 
FIS102_04a-All new benefit claims are processed promptly. 
Target: 21 Days
Actual: 25.19 Days
Performance at an average processing time of 25.19 days to process as at 31 March 22 does
not meet the target of 21 days in the service plan. From August to March 2022 the increase
in Self Isolation Support Grant (SISG) applications aligned with staff shortages has meant an
increase to monthly processing times to between 26 and 27 days per month on average. 
This has caused the increase in the cumulative average processing times for the full year to
25.19 days. Benefit Assessors were redeployed to support the administration of the Scottish
Government's Self Isolation Support Grant programme. We have tried to recruit Benefit
Assessors to temporary posts using admin funding provided by the Scottish Government but
have been unsuccessful. Some staff are currently working overtime in order to limit the
delays in processing new claims.

Page 2

Appendix 3 
RIS113_05-The percentage of street lighting fault repairs are completed within 10 working
days.
Target: 75%
Actual: 28%
The Street lighting Team were affected by Covid absences in the final quarter with all staff
being off at some point due to Covid. This has been reflected in the performance figures
which has dipped to 28% of faults being repaired within the 10 day period across the ABC
area. A total of 241 faults are still outstanding at this time with staff prioritising where
appropriate. In prioritising faults, staff will review the timescale of reported faults (i.e. clear
oldest ones first) and review sections where there may be more than one light fault
reported (i.e. a stretch of 5 lights as opposed to 1 light outage) 
Early indications show that the backlog of outstanding faults is being addressed for FQ1
2022/23 however this continues to be monitored. 
FIS115_02-Maintain the high rate of collecting Non-Domestic Rates [NDR]. 
Target: 97.30%
Actual: 96.37%
As at 31 March 2021 Non Domestic Rates collected is 96.37% which is slightly less than the
council target of 97%. This is mainly attributed to changes in legislation for certain reliefs,
mainly Small Business Bonus Scheme Relief (SBBS) which was previously available to
unoccupied properties who now no longer qualify for 100% relief. 
Coronavirus Retail, Hospitality and Leisure Relief (RHL) which had previously been
automatically granted now requires business to make an application and eligibility has been
tightened. Therefore the net NDR due increased and additional work is required to collect
the monies due. 
LRS102_01-Advice and assistance from Welfare Rights is provided to Clients to ensure they
maximise their income.
Target: £2,750,000
Actual: £2,728,847
Although the year to date figure is below target, the figure for income generated by Welfare
Rights in FQ4 is £993,251. This figure is in excess of the quarter target as there has been an
increased number of closed cases. 
The volume of referrals received overall has reduced due to Covid-19 as there was an uplift
in Universal Credit.

Page 3

Appendix 3
The following KPI is currently off-track however performance has improved since the last
reporting period. 
DEG110_03-The time it takes to determine 'local' planning applications is no longer than 10%
above the National Average. 
Target: 11.0 Weeks
Actual: 15.5 Weeks 
The Development Management Team continues to operate with reduced resource. During
FQ4 several legacy applications were finalised and determined, the majority of which were
in the OLI team, a team which has carried vacancies and experienced staff turnover in posts
over a prolonged period. 
The headline performance figure of an average of 15.5 weeks to determine these
applications is badly skewed by 6 applications which took between 1 and 3 years to
determine. Those taking in excess of a year can be broken down into areas, as follows:- OLI
3 applications varying between 1 year and 3 years; H&L 2 applications which took between 1
and 2 years; BAC 1 application which took 1.5 years. 
Steps are being taken to address vacancies across the Service and attempts are being made
to recruit to vacant posts. The Service has also identified the likelihood of additional
pressure on staff resource/capacity arising during 2022/23 through a significantly higher
than normal caseload of major planning applications and consultations with many of these
items being delayed as a result of the pandemic but are now ready to be progressed. 
The Service will shortly be seeking to increase its professional staff resource by 2fte in
response to expected demands upon the Major Applications Team.