ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  15 SEPTEMBER 2022 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2022-23 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these in a database and, on a
monthly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 30 June 2022
including information on actions where the agreed implementation date
has been rescheduled. 
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 30 June 2022. 
Table 1 – Actions due by 30 June 2022 
DMT/Service Complete Delayed/
Rescheduled
No
Response
Evidence
Required
Total
Internal Audit
CE – Financial
Services
4 4 0 0 8
DH – Commercial
Services
1 1 0 0 2
DH – Legal &
Regulatory 
1 3 0 0 4
DH – Lifelong
Learning &
Support
0 1 3 0 4
KF – Customer
Support Services
2 3 0 0 5
KF – Development
& Economic
Growth
1 0 0 0 1

Page 2

KF – Roads &
Infrastructure
Services
3 7 0 2 12
H&SCP (IJB) –
Finance &
Transformation
2 0 0 0 2
H&SCP (IJB) –
Strategic Planning
& Performance
2 0 0 0 2
H&SCP (SW) –
Adult Services
(Mental Health
Learning Disability,
Addictions &
Lifelong
Conditions)
0 1 0 0 1
H&SCP (IJB) –
Adult Services
(Older Adults &
Community
Hospitals) 
0 1 0 0 1
LiveArgyll 1 0 0 0 1
External Audit      
TOTAL 17 21 3 2 43 
Table 2 – Actions due after 30 June 2022 
DMT/Service Complete Delayed/
Rescheduled
No
Response
On
Course
Evidence
Required
Total
Total
Internal Audit
CE – Financial
Services
0 2 0 3 0 5
DH –
Commercial
Services
0 0 0 5 0 5
DH – Learning
& Teaching
0 0 0 3 0 3
DH – Legal &
Regulatory 
0 0 0 2 0 2
DH – Lifelong
Learning &
Support
0 0 0 2 0 2
KF – Customer
Support
Services
0 0 0 4 0 4
KF –
Development
& Economic
2 0 0 1 0 3

Page 3

Growth
KF – Roads &
Infrastructure
Services
0 1 0 3 0 4
H&SCP (IJB) –
Adult Services
(Older Adults
& Community
Hospitals) 
0 0 0 3 0 3
H&SCP (IJB) –
Finance/Transf
ormation
2 0 0 1 0 3
H&SCP (IJB) –
Strategic
Planning and
Performance
0 1 0 0 0 1
H&SCP (SW)
– Adult
Services
(Mental Health
Learning
Disability,
Addictions &
Lifelong
Conditions)
0 0 0 1 0 1
H&SCP (SW)
– Children &
Families and
Criminal
Justice
1 0 0 0 0 1
H&SCP (SW)
– Strategic
Planning &
Performance
0 0 0 1 0 1
External Audit       
TOTAL 5 4 0 29 0 38 
3.2 Appendix 1 provides further detail on actions that have either been delayed
and rescheduled or for which Internal Audit have received no response
from the service to inform this follow up. 
4.0 CONCLUSION 
4.1 COVID19 continues to impact on the progress services are making to
complete audit action points.

Page 4

5.0 IMPLICATIONS 
5.1 Policy - None
5.2 Financial - None
5.3 Legal - None
5.4 HR - None
5.5 Fairer Scotland Duty - None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty - None
5.6 Climate Change – None
5.7 Risk –None 
5.8 Customer Service – None 
Paul MacAskill
Chief Internal Auditor
15 September 2022                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Action Plan Points with No Response and Delayed & Rescheduled

Page 5

Appendix 1 - Action Plan Points with No Response & Delayed and Rescheduled 
No Response 
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
LIFELONG
LEARNING &
SUPPORT - PUPIL
WORK
PLACEMENTS
Training 
There is no
training
programme to
support officers
involved in the
work placement
programme
including
ensuring
appropriate steps
are taken to
determine
whether a PVG
check is required.
Medium Conduct a training
needs analysis with
school staff leading
on work placements. 
Produce a
programme of
centrally run CPD
opportunities for
next academic year
(or include in
Education Service
Training
Programme).
30 September 21
31 December 21
30 June 22
No Response Head of
Education -
Support &
Lifelong
Learning
LIFELONG
LEARNING &
SUPPORT - PUPIL
WORK
PLACEMENTS
Self-evaluation 
Education
Scotland provides
a benchmarking
exercise which
schools can
undertake as part
of a self-
evaluation
exercise. This
provides a check
list on how things
Low CPD session to be
held on
benchmarking tool
for school staff. 
Introduce an annual
benchmarking
exercise for all
secondary schools.
31 December 21
30 June 22
No Response Head of
Education -
Support &
Lifelong
Learning

Page 6

No Response 
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
are being
undertaken
against the
requirements of
the Standard.
Schools have not
completed this
exercise.
LIFELONG
LEARNING &
SUPPORT - PUPIL
WORK
PLACEMENTS
Reporting 
There are no
periodic
management
reports on pupil
work placements.
These would form
an important
understanding of
the success and
challenges of
work placements
and facilitate
discussions about
how to overcome
some of the
barriers which are
resulting in a
decreasing pool
of employers
signing up to the
scheme.
VFM Identify and agree
meaningful KPIs for
new service plan,
monitoring and
reporting. Implement
new KPI data
collection in schools.
Establish robust
reporting framework
including EMT and
CSC.
30 June 22 No Response Head of
Education -
Support &
Lifelong
Learning

Page 7

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
FINANCIAL
SERVICES - 
FIXED ASSET
REGISTER (AIRS)
Reconciliation of
AIRS to General
Ledger 
General Ledger
reports are
provided at year
end to facilitate
reconciliation of
assets to AIRS.
There is no
evidence of the
reconciliation
exercise being
reviewed for
accuracy by a
senior member of
staff.
LOW Reconciliation to be
signed off by
Finance Manager
annually.
30 June 22
31 August 22 
A match between
the AIRS and
Concerto Systems
was undertaken at
year end 21/22
which surfaced a
number of
differences between
the two systems.
Work has been done
to address the
differences but a
second system
match is required to
ensure that there are
no remaining errors
between the two
systems. This will be
done during late July
2022 with any
differences followed
up and resolved by
the end of August
2022. 
Delayed and
Rescheduled
Finance Manager
FINANCIAL
SERVICES - 
Inappropriate
authorisation of
transactions The
MEDIUM The wording of the
current monthly
email to cardholders
30 June 22
31 October 22
Delayed and
Rescheduled
Creditors
Supervisor/Creditors
Support Officer

Page 8

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
PURCHASING
CARDS
Support Officer in
the creditors’ team
approves a
considerable
number of pre-
authorised
transactions for
catering staff and
procurement staff.
Furthermore
creditors will also
approve any
outstanding
transactions for
other departments
to ensure that the
bank direct debit is
completed within
agreed timeframes.
and approvers will
be updated to
remind them of their
responsibilities.
Once available, a
one page
procurement guide
will be issued to all
purchase card
holders and
approvers.
FINANCIAL
SERVICES
SYSTEMS -
INTERFACES &
RECONCILIATIONS
General Ledger
Reconciliations
There is no
reconciliation
performed between
the source system
and the general
ledger for
ResourceLink,
PECOS, Concerto
and Tranman and
the SEEMiS
interface for
MEDIUM Data in the source
system may not be
accurately reflected
in the general
ledger.
31 March 21
31 December 21
30 June 22
30 September 22 
Further work to be
completed to
produce a report
from Resource Link
and the new Oracle
Fusion system so
that the two systems
can be reconciled.   
Delayed and
Rescheduled
Resourcelink -
Pensions & Payroll
Officer

Page 9

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
clothing grants.
COMMERCIAL
SERVICES
SYSTEMS -
INTERFACES &
RECONCILIATIONS
General Ledger
Reconciliations
There is no
reconciliation
performed between
the source system
and the general
ledger for
ResourceLink,
PECOS, Concerto
and Tranman and
the SEEMiS
interface for
clothing grants.
MEDIUM Data in the source
system may not be
accurately reflected
in the general
ledger.
31 March 21
30 September 21
31 December 21
30 June 22
31 December 22
Dialogue continues
with Strategic
Finance following
the update to Oracle
Fusion, the limited
availability of
Licenses and what
reports can be
generated. 
Delayed and
Rescheduled
Concerto - Property
Design Manager
LIFELONG
LEARNING &
SUPPORT - 
ADDITIONAL
SUPPORT NEEDS
Format of Child
Plans 
The Council do not
use a standard
format for child
plans however this
will be addressed
when all plans are
recorded on
SEEMiS. However
sample testing
highlighted that
plans do not
always include a
next review date.
LOW As child plans are
reviewed over the
coming school
session 2019-20
they will be
converted onto the
Well-being App
format, this format
contains a “Date of
Next review “field. 
Schools will be
supported to change
all plans to the new
format within the
Well-being App by
Area Principal
Teachers.  During
30 September 20
31 December 20
30 June 21
30 June 22
30 September 22
Using the drill down
facility on the Well-
being app to monitor
the number of plans
is only showing the
number of plans that
are complete.  Since
schools keep plans
open while they are
working on them this
is not a true
reflection of all the
plans that are on the
system.  The
education data team
and the ESOs have
a date planned to
Education Officer

Page 10

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
the year there will be
checks to see how
many plans have
been converted and
to check if the date
of review field has
been completed.
amend the training
materials to ensure it
clear to staff in
schools how to mark
the plans as
complete.  Further
training sessions will
be scheduled in the
new academic
session. In the MAKI
area 61% of schools
are showing as
having plans on the
WBA.  In the H+L
area 62% of schools
have plans on the
WBA.  In B+C 81%
of schools have
plans on the WBA. 
In the OLI area 65%
of the schools have
plans on the WBA.
Further training and
individual support
will be offered to
Head Teachers by
the I+E ESOs in the
coming school
session to help them
to transfer more
plans onto the WBA.

Page 11

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
Delayed and
Rescheduled
CUSTOMER
SUPPORT
SERVICES - 
ICT Remote
Working 
Wellbeing
information  
The Wellbeing
Strategy and some
links to further
guidance and
information are not
provided on
MyCouncilWorks
and one link does
not work.
HIGH Wellbeing Strategy
will be added to the
MyCouncilWorks
page and the
addiction link
repaired.
31 May 22
31 August 22
Vacancies within the
team have delayed
implementation of
this action. This will
be completed in
August. 
Delayed and
Rescheduled
HR Service Centre
Team Leader
CUSTOMER
SUPPORT
SERVICES
ORGANISATIONAL
CULTURE & 2019 -
EMPLOYEE
SURVEY ACTION
PLAN
Involvement in
change
N/A Use new approach
of online exit
questionnaires to
help identify root
causes for
departures and
assess the potential
additional benefit of
exit interviews.
31 March 20 
31 December 20
31 March 21
30 September 21
31 March 22
1 June 22
Final testing is
underway for the
new approach and
process maps are
being redrawn to
include a link to the
new online exit
questionnaire.
Target date for
implementation is
August 2022. 
Delayed and
Rescheduled
Head of Customer
Support Services
ROADS &
INFRASTRUCTURE
SERVICES
CONTRACT
MANAGEMENT -
Contract
Monitoring
Monitoring of
contracts has not
been undertaken
HIGH Contract manager to
be identified for each
contract, key dates
to be agreed
including pre-start
30 June 22
30 September 22
N+S have set up the
contracts and Ops
are now managing
same. 
Operations Manager
and Network and
Standards Manager

Page 12

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
ROADS AND
AMENITY
SERVICES
as required by the
‘Contract and
Supplier
Management
Toolkit’,
specifically: : · no
contract managers
have been
identified · contract
and Supplier
management plans
have not been
completed · formal
supplier review
meetings have not
been undertaken ·
key performance
indicators have not
been identified ·
contracts have not
been subject to
formal annual
review and risk
assessments
and review meeting,
KPIs to be
developed which
include formal
annual review and
risk assessment.
Delayed and
Rescheduled
ROADS &
INFRASTRUCTURE
SERVICES
CONTRACT
MANAGEMENT -
ROADS AND
AMENITY
SERVICES
Roles and
Responsibilities 
No clearly defined
roles and
responsibilities
have been
identified for
HIGH Contract manager to
be identified for each
contract which will
work to the contract
monitoring
requirements
detailed in action
plan number 1.
30 June 22
30 September 22
Delayed and
Rescheduled
Operations Manager
and Network and
Standards Manager

Page 13

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
contract monitoring
between the
Network and
Standards services
and Operational
Services within
Development and
Infrastructure.
ROADS &
INFRASTRUCTURE
SERVICES
CONTRACT
MANAGEMENT -
ROADS AND
AMENITY
SERVICES
Performance
Reporting 
No formal
performance
monitoring and
reporting
arrangements are
in place for any of
the 20 contracts
currently in
operation.
MEDIUM As detailed in action
1 and 2 above, the
designated contract
manager will be
responsible for all
performance
monitoring and
reporting for specific
contracts.
30 June 22
30 September 22
Delayed and
Rescheduled
Operations Manager
and Network and
Standards Manager
ROADS &
INFRASTRUCTURE
SERVICES - 
STREET
CLEANING
Partnership
Agreement 
Oban Business
Improvement
District (BID) has
agreed to fund an
additional seasonal
street sweeper
employed by the
Council. The street
sweeper has been
HIGH Formalise
arrangements with
Oban BID for the
funding of the
seasonal street
sweeper
30 April 22
30 September 22
Delayed and
Rescheduled
Operations
Manager, Roads &
Infrastructure
Services

Page 14

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
appointed through
the Council’s
recruitment
process, however
no formal
agreement is in
place and income
from BID has not
been received.
ADULT SERVICES
(MENTAL HEALTH
LEARNING
DISABILITY,
ADDICTIONS &
LIFELONG
CONDITIONS/CSW
O)
H&SCP - IMPACT
OF NEW
LEGISLATION
NMAHP
Implementation
Group reporting 
The NMAHP
Implementation
Group is
accountable to the
NMAHP Workforce
Planning &
Development
Group, which in
turns reports to
NMAHP
Professional
Leadership
Committee and the
Programme Board. 
Risk 
There is a risk that
compliance with
HIGH Recommendation 
The NMAHP
Implementation
Group should
provide a work plan
and update reports
to the NMAHP
Workforce Planning
& Development
Group in accordance
with its Terms of
Reference. Required
actions arising from
the reports should
be clearly recorded
on the NMAHP
Implementation
Group’s action plan. 
Management Action. 
The NMAHP
31 May 21
30 June 22
There are staffing
pressures
throughout the NHS
so no point in
implementing safe
staffing legislation
when there are not
enough qualified
staff in the economy
to comply with it. 
Delayed and
Rescheduled
Lead Nurse -
Contact

Page 15

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
the Staffing Act is
not being
monitored and
reported on with
sufficient
frequency, and
appropriate actions
are not being taken
where necessary. 
The NMAHP
Implementation
Group’s Terms of
Reference states
that the group will
provide an annual
work plan and bi-
monthly update
reports to the
NMAHP Workforce
planning &
development group
in respect of: 
• Adherence to the
Common Staffing
Methodology 
• Completion of
establishment
reviews (following
SOP for
Implementation
Group has been
disbanded. All
actions will be
picked up by the
NMAHP Oversight
Group. This group
will report on actions
to the IJB to provide
the requisite
assurance.

Page 16

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
establishment
reviews) for all
clinical areas with
access to validated
tools by February
2020 
• Develop schedule
for annual tool run
to be implemented
from 2020 
• Development of a
Risk Register 
• Development of
an Issues Log 
• Monitoring
monthly any
change to current
establishments 
However, whilst
some oral updates
have been
provided at
meetings of the
NMAHP Workforce
Planning &
Development
Group, the reports

Page 17

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
have not been
provided to the
group.
FINANCIAL
SERVICES - 
PURCHASING
CARDS
Procurement
procedures Forty
five purchase
cardholders (25%)
were invited to take
part in a survey,
with twenty nine
responses
received. The
responses received
highlighted a
general lack of
awareness of
procurement
procedures.
MEDIUM A review of the
guidance for spend
within the lowest
threshold of £0-£999
will be undertaken
and a one page
procurement guide
will be produced for
issue to all purchase
card holders and
approvers.
30 June 22
30 September 22
Partially completed.  
Discussions have
been completed with
the majority of Head
Teachers as the bulk
of purchase card
spend is within the
schools.   This has
helped us
understand why they
are using the cards
in the first place (and
not PECOS) to
ensure the new
guidance addresses
these issues.  
Remaining meetings
to be completed on
return from school
summer holidays
and guidance note
circulated &
appended to the
council’s
procurement
manual.     
Delayed and
Rescheduled
Category
Management
Officer/Procurement
& Contract
Management Team

Page 18

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
LEGAL &
REGULATORY
SUPPORT -
INFORMATION
ASSET
REGISTERS
Periodic Review
and Agreement of
Information Asset
Registers 
For four of the 12
IARs there was no
evidence they had
been agreed by the
relevant DMT.
Furthermore IARs
need to be
reviewed to ensure
they are aligned to
the new Corporate
structure. The RMP
requires that IAR’s
should have a
complete action
plan to document
required changes.
Two of the 12 IARs
had an action plan,
two had action
plans that did not
fully meet the
requirements of the
RMP and eight had
no action plan.
MEDIUM Obtain annual
approval from DMTs
for all completed
IARs
30 September 20
31 March 21
30 September 21
31 December 21
30 June 22
31 December 22
Delayed and
Rescheduled
Governance, Risk &
Safety Manager
LEGAL &
REGULATORY
SUPPORT - 
Periodic Review
and Agreement of
Information Asset
MEDIUM Action plans for all
IARs to be put in
place and agreed by
30 September 20
31 March 21
30 September 21
Delayed and
Rescheduled
Governance, Risk &
Safety Manager

Page 19

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
INFORMATION
ASSET
REGISTERS
Registers 
For four of the 12
IARs there was no
evidence they had
been agreed by the
relevant DMT.
Furthermore IARs
need to be
reviewed to ensure
they are aligned to
the new Corporate
structure. 
The RMP requires
that IAR’s should
have a complete
action plan to
document required
changes. Two of
the 12 IARs had an
action plan, two
had action plans
that did not fully
meet the
requirements of the
RMP and eight had
no action plan.
management teams 31 December 21
30 June 22
31 December 22 
LEGAL &
REGULATORY
SUPPORT - 
INFORMATION
Information Asset
Registers 
The two Social
HIGH Social Work IARs to
be completed and
approved by
appropriate
31 December 20
30 June 21
30 September 21
31 December 21
Delayed and
Rescheduled
Governance, Risk &
Safety Manager

Page 20

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
ASSET
REGISTERS
Work IARs were
not available for
review or located
on the designated
SharePoint site. Of
the remaining ten,
four require to be
updated to reflect
the latest GDPR
requirements. 
Clarity over
whether the Live
Argyll IAR comes
under the remit of
the Governance,
Risk & Safety
Manager’s
responsibility is
required.
management teams 30 June 22
31 December 22
CUSTOMER
SUPPORT
SERVICES - 
SICKNESS
ABSENCE 
Attendance Review
Meetings 
Procedures
stipulate that
attendance review
meetings should be
carried out by the
employee’s line
manager to
facilitate the
employees return
Medium HR will review the
mechanism for
documenting content
of attendance review
meetings and
recommend a
preferred option for
automatically
populating the
documentation into
the MyView system. 
31 December 21
30 April 22
30 June 22
31 October 22 
Delayed and
Rescheduled
HR Development
Team Lead

Page 21

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
to work. No
evidence of review
meetings being
carried out was
available for any of
a sample of eight
long term
absences.
Procedures should
be updated to
ensure that all
attendance review
meetings are
properly recorded
in the MyView
system in the same
way that return to
work interviews are
recorded in
MyView.
ROADS &
INFRASTRUCTURE
SERVICES - 
WARDEN
SERVICES 
Warden Service
Coverage 
The four
environmental
wardens that are
expected to cover
the whole of the
Council area,
including the
islands, are not
geographically
High Consider
opportunities to
either restructure/
review overall
service delivery to
provide additional
warden cover or
alternatively look to
generate additional
income to facilitate
additional FTEs and
a more equitable
30 June 2022
31 December 22 
It has been agreed
that the Warden
Service is
transferring to N & S
and will be
combined with the
Car Parking
wardens and also
the staycation
wardens, this will
provide additional
resilience and better
Operations
Manager, Roads &
Infrastructure
Services

Page 22

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
spread to ensure
there is efficient
cover across the
four Council
administration
areas. In particular,
since 2018, there
has been no
warden based in
the MAKI area
which has resulted
in: 
· disproportionately
low level of warden
service in MAKI
compared to the
other
administrative
areas 
· where work is
required in MAKI
the majority of the
warden’s time is
spent commuting
rather than
delivering the
required services. 
spread of resource. 
This will help inform
any input into the
2022 budget
process. 
coverage of the area
and also working
towards a 7 day
warden service for
all taks once training
has been completed. 
Delayed and
Rescheduled 
ROADS &
INFRASTRUCTURE
Second Bin
Service Verification
HIGH Review the process
for:
30 June 22
30 September 22
Further to
discussions with the
Operations
Manager, Roads &

Page 23

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
SERVICES -
WARDEN
SERVICES 
Wardens are
expected to verify
the veracity of
applications from
customers for a
second domestic
bin service. This
requires the
warden to confirm
that information
provided by the
customer is
accurate and
meets the defined
criteria. The
information
provided to
substantiate an
application can be
very personal and
sometimes of a
sensitive medical
nature. Wardens
have been asked
to provide this
service but have
received no formal
training in how to
ensure a
customer’s dignity
is maintained or to 
· Dealing with
requests for new
and replacement
bins. 
Governance, Risk
and Safety Manager
it has been
suggested that the
review of the
process considers
that the service take
the customers at
their word when they
make the application
and provide the
second bin without
any further checks,
and for the assisted
uplift only check that
the distance from
the kerb is under 30
metres.   
Delayed and
Rescheduled 
Infrastructure
Services

Page 24

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
ensure they are
aware of the
requirements of
General Data
Protection
Regulation (GDPR)
in relation to
personal data for
this specific
process. 
Due to the
sensitivity of this
process, and the
potential risks
associated with
data protection it is
recommended that
the current
verification process
is reconsidered to
determine if it is
appropriate to
maintain it in its
current form. If it is
decided it should
be retained then
there should be
engagement with
the Council’s
Governance and
Risk Manager to

Page 25

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
ensure it is being
carried out in full
compliance with
GDPR.
ROADS &
INFRASTRUCTURE
SERVICES - 
STREET
CLEANING 
Recharging for
sweeping of
Council car parks 
The Council’s
income generating
car parks are
recharged for
street sweeping
according to
information
retained in work
schedules rather
than actual work
taking place,
additionally the
Council’s non-
income generating
car parks are not
recharged for
sweeping.
VFM Ensure that timely
and accurate
recharges are
carried out and a
system in place to
ensure that this is
regularly taking
place. 
31 March 22
30 June 22
30 September 22 
Discussions are
ongoing with N & S
colleagues with
regards to the
frequency of street
sweeping for car
park maintenance. 
A reduction in
frequency at certain
locations has been
agreed and the work
schedules are being
amended and an
indicative value will
be given to N & S for
their approval. 
Delayed and
Rescheduled 
Operations
Manager, Roads &
Infrastructure
Services 
Adult Services
(Older Adults &
Community
Hospitals) HSCP –
Care Programme
Approach
CPA Procedures 
There are no
agreed CPA written
procedures,
including client
assessment
High Processes and
procedures will be
developed across
Argyll & Bute to
improve consistency
and ensure service
provision is
30 June 22
31 December 22
Not complete. CPA
post has been out to
advert however did
not attract any
applicants on this
occasion, being re-
advertised.
Consultant Nurse

Page 26

Action Plan Points Due by 30 June 2022 – Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer 
processes, to
ensure a consistent
approach to CPA
service provision
across the HSCP.
appropriate across
the region. This is
subject to the
recruitment of key
posts within the
service which are
currently vacant. 
Delayed and
Rescheduled 
Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
FINANCIAL
SERVICES -
CAPITAL
MONITORING
Capital Programme
Planning &
Management
Guide The
Council’s Capital
Guide has not
been revised since
2018 and requires
a review to ensure
it reflects current
working practices
and provides
appropriate support
to officers involved
in the capital
monitoring
process. The
Council is currently
developing a new
MEDIUM Capital Planning and
Management Guide
to be updated once
the Capital Strategy
has been approved
to ensure the two
are aligned and
provide clarity.
31 March 22
30 September 22
31 December 22
This cannot be completed
until the Capital Strategy is
complete which the Head
of Commercial Services
has advised will be
towards the end of the
calendar year. 
Delayed and
Rescheduled
Head of
Commercial
Services/Finan
ce Manager

Page 27

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
Capital Strategy
which is to be
presented to the
Policy and
Resources
Committee in
August 2021 and
we recognise that a
review of the Guide
should be
conducted after the
Strategy has been
finalised to ensure
the two documents
complement each
other and. The
Guide could also
benefit from being
linked to, or
referencing, other
relevant Council
processes, in
particular the
Project
Management
section on the Hub.
FINANCIAL
SERVICES - 
FOLLOWING THE
PUBLIC POUND
Guidance on
Following the
Public Pound
(FtPP) Although
the Council has an
HIGH Following the Public
Pound guidance will
be drafted to provide
a consistent
approach to
30 June 20
31 December 20
30 June 2021
31 December 21
30 September 22
This cannot be completed
until the Capital Strategy is
complete which the Head
of Commercial Services
has advised may be
Head of
Financial
Services

Page 28

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
approved process
to manage external
funding requests it
is limited in detail,
is not closely
aligned to the Code
of Guidance on
Funding External
Bodies and
Following the
Public Pound and
there is a general
lack of awareness
amongst officers
that it exists. Audit
testing identified a
number of areas of
good practice
within the Council
and overall
compliance with
the principles of
FtPP however
there were
examples of
inconsistent
practice. A more
comprehensive
guidance
document should
be established
managing the award
of external funds.
31 December 22 towards the end of the
calendar year. 
Delayed and
Rescheduled

Page 29

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
which provides a
more standardised
and tiered
approach providing
greater clarity over
roles and
responsibilities and
standardised
templates for key
stages in the
process including
funding
assessments and
post award
monitoring and
reporting. The audit
team researched a
number of
examples of FtPP
guidance which
had been created
by other councils
during the planning
phase of the audit
and can make
these available to
inform the creation
of an Argyll and
Bute equivalent.

Page 30

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
ROADS &
INFRASTRUCTURE
SERVICES - 
FLEET
MANAGEMENT 
Management of
Pool Cars A high
level analysis of
the use of pool
cars suggests the
Council could
generate
considerable
savings through
more efficient use
of pool cars. Fleet
Services should
explore this further
via a more detailed
review which
should consider the
potential benefits
of: · a more
centralised
approach to the
administration and
booking of pool
cars 
· better promotion
of the use of pool
cars 
· providing greater
visibility of
bookings and
VFM The pool car module
will be released
through Tranman.
The pool car module
offers a centralised
approach to
bookings and
visibility. The
Council’s internal
communications
department will be
contacted to
highlight the use of
the pool cars. Work
will be undertaken to
increase usage. 
30 September 20
31 December 20 
30 June 21
31 December 21
30 April 22
29 July 22 
On-going delay in
implementation due to
staff absence and staff
training for temporary
posts. New
implementation date
September. 
Delayed and
Rescheduled 
Procurement/T
echnical
Officer

Page 31

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
destinations to
encourage pool car
sharing 
· implementing or
developing a pool
car booking system 
· identifying ways
of transferring the
balance of pool car
usage from shorter
journeys to longer
ones 
Strategic Planning
and Performance –
HSCP – Risk
Management –
Risk Management
Training
There is no formal
proactive
programme of risk
management
training. Whilst we
understand some
training has been
provided where
requested by the
Clinical
Governance
Manager (and
tailored to whom it
is being delivered)
there is no
requirement for
Medium A formal programme
of risk management
training should be
developed and
delivered to all key
personnel involved
in the management
of risk. 
30 June 21
30 June 22
30 December 22
Development sessions
have been held with
groups of staff which
included raising
awareness of the risk
register process and
support to update
registers. The aim now is
to offer sessions to each
Head of Service and their
direct reports to review
their service registers and
agree the process by
which they will keep their
service registers current.
These sessions include
Clinical
Governance
Manager

Page 32

Action Plan Points Due After 30 June 2022 - Delayed & Rescheduled/Evidence Required
Service / Report Finding Priority Agreed Action Dates Comment Responsible
Officer /
Status
Risk Leads to have
training and
training records are
not maintained.
There is also no
dedicated training
programme in
place for new
members of the IJB
or Audit
Committee, such
as within induction
training.
full training in use of the
risk registers, the risk
register process, the types
of risks that should be
recorded and escalation of
risks Due to two members
of the Clinical Governance
Team leaving end of May
resourcing this work is
very challenging, leading
to timescales slipping,
therefore it is suggested
that this is revised to the
end of March 2023. 
Delayed and
Rescheduled