Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
BV1.2 Develop the
transformation
agenda,
supported by an
affordable and
achievable
medium to longer
term financial
strategy 
Complete capital
strategy and
launch revised
capital process. 
Capital
Strategy and
process is
launched
May 2021
August 2022
August 2023
Head of CS An update was provided to the Policy
and Resources Committee on the 14
October 2021. 
The Executive Leadership Team
appointed in June 2022 on internal
secondment a Corporate Programme
Coordinator to undertake a holistic
review of the organisations approach to
prioritisation and phasing of capital
projects with an objective to develop a
long term ‘pipeline of projects’ which will
emerge over the coming 12 months and
significantly influence the Capital
Strategy. 
In addition, ELT completed a review of
the Strategic Asset and Group Asset
Management Plans process to improve
the value of the process and its outputs
to support Members in its decision
making. 
The Capital Strategy has gone through a
number of revisions and final draft
version will be submitted to the Council’s
Policy and Resources Committee
August 2023.

Page 2

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
BV2.3 Improve
performance
management
reporting to
provide a
balanced picture
of long-term
trends in
performance
against targets.
Review the
approach to
performance
management
reflecting:
- Clear links to
strategic
priorities
- Meaningful
indicators,
taking account
of trend data
and
benchmarking
The need for a
simple and
effective system
for recording and
presenting data
New system
procured or
developed in-
house
Dec 2021
July 2023
Head of
CSS
The project Team developed a
specification for ICT functionality which
was signed off by ELT.  A procurement
Exercise was undertaken with no
satisfactory outcome with regards to
price.   
An alternative and more holistic
approach was undertaken to seek to
develop an organisational data platform
that will provide a performance
dashboard; see BV3.3 for more
information. 
Work has commenced on building a new
dashboard for the Area Performance
Reports that are submitted to Area
Committee and will go live for FQ1
2023/24. 
BV2.5 Improve public
performance
reporting. 
Review of
public
performance
reporting
complete 
March 2022
September
2023
Head of
CSS
This will be included within a review of
the Performance Improvement
Framework with a report scheduled to
go to Council September 2023. 
BV3.3 Increase the
pace of
transformational
change to deliver
Develop data
analytics/business
intelligence as a
tool to inform
Options
appraisal on
data analytics
approach
complete
March 2021
Complete 
Head of
CSS
Initially delayed due to Covid.  Further to
learning from Aberdeen City Council on
their ‘data journey’, the Council’s
Executive Leadership Team agreed
January 2022 in principle to the

Page 3

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
the business
outcomes 
Transformation
and Improvement 
development of an in-house system
using Microsoft 365 technology.  This
initiative will allow the Council via a self-
build to take data from across various
systems into a single ‘data platform’ (i.e.
integrated set of technologies that
collectively creates the data in an
accessible format like a dashboards). 
The Executive Leadership Team (ELT)
agreed in October 2022 a business case
to develop an on-site data platform and
create capacity to commence
development of data dashboards as
directed by the Data Advisory Group (an
officer group accountable to the ELT).   
BV3.4 Implement
programme of
modernising
education
services. 
Reports on
progress to
elected
members at
appropriate
stages of
programme
Complete  Exec Dir February 2021 - Members Seminar
online learning. 
June 2021 – Education Change
Programme; report on key findings of all
10 workstreams reported to Community
Services Committee June where it was
agreed to progress with a programme of
engagement with communities, staff,
representative bodes and wider
stakeholders on the school leadership
model.

Page 4

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
Community Choices Committee agreed
in August 2022 not to progress key
recommendations and other actions will
be picked up as normal business. 
BV3.5 Implement
programme of
modernising
education
services. 
Modernisation
programme is
complete
Complete Exec Dir ‘Empowering our Educators’ community
engagement and consultation exercise
commenced 29.11.21 running through to
04.02.22 to discuss and co-develop
proposals. 
Community Choices Committee agreed
in August 2022 not to progress key
recommendations and other actions will
be picked up as normal business. 
BV3.8 Make full use of
improved
technology to
transform service
delivery and
reduce burden on
front line services 
Simplify
administrative
processes by
reducing the
number of ICT
applications in
use by 10%
March 2023 Head of
CSS
On track. Strategic context set by the
approved ICT and Digital Strategy.   
Digital by Default budget theme has
contributed to revenue budget
reductions through agile working, hybrid
meetings and significant reduction in
printing, postage and travel; 
Implementation of MS365 has
contributed to reduction of standalone
applications such as Survey Monkey
and Pyramid. Phases 2 and 3 underway
to maximise use of M365 Business Apps
and Streamline Information

Page 5

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
Management. Further reductions will be
implemented and monitored via ICT and
Digital Strategy, including via new HR
and Payroll system. Robotic Process
Automation will begin implementation in
23/24 
BV4.2 Assess the
extent to which
regeneration and
economic
development
initiatives are
delivering the
vision and
corporate
outcomes
Create inter-
departmental
Project Review
Team and scope
review of project
process to align to
BV3 Objective
Project Review
Plan to be
approved by
Capital
Investment
Board
December
2020
December
2023
Major
Project
Programme
Manager 
Key resources identified within
Programme & Project Management
Service Economic Development,
Strategic Finance and Procurement. 
Council’s response to COVID pandemic
delayed the work considerably. 
Post project evaluation is in place for
large capital projects and will be
streamlined through the Asset
Management Board.  New scoring
mechanism developed to support
evaluation. 
BV4.3 Implement
updated Project
Process for
Options &
Evaluation. 
Launch at
Capital
Investment
Board 
April 2021
August 2023
MPPM The new streamlined approach will be
launched at the August meeting of the
Capital Investment Board.
BV4.4 Training /
Mentoring for
Project
Delivery of
training
recorded
September
2021
Project
Review
Team
An external audit was undertaken to
assess training requirement.

Page 6

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
Practitioners in
updated Project
Process for
Options &
Evaluation 
September
2023 
Training now largely 75% completed
and will be completed by September
2023. 
BV5.1 Work with
communities and
community
groups to
improve
engagement
Engage with
communities to
understand and
improve levels of
satisfaction with
council services in
order to
understand and
address their
concerns 
Develop co-
ordinated
approach to
measuring
satisfaction
with
communities.
Dec 2021
Oct 2023
Head of
CSS
As part of the performance excellence
project, the project team liaised with the
Customer Engagement and
Transformation Manager to develop a
new corporate customer satisfaction
survey which will be issued October
2023.
BV5.2 Trends are
measured as
well as
individual
survey
outcomes 
Dec 2021
October 2023
Head of
CSS
The survey described above will ensure
trend data over a longer period.
BV5.4 Improve the
quality of
engagement with
our communities
and reflect this in
service
improvements
Identify
priorities for
better future
engagement
Sept 2021
June 2023
Head of
CSS
The Executive Leadership Team (ELT)
will decide in the spring 2023 a
programme of Service Co-Design where
services will be co-designing services
with stakeholders.  This will be a long
term programme informed by service
self-assessment programme.

Page 7

Best Value 3 Action Plan V4 – February 2023
Reference Theme Actions to
achieve
outcomes
Success
Measures
Key Dates Lead Progress
BV5.5 Implement a
programme to
improve
engagement skills
across the
organisation.
Training
materials
developed and
programme
rolled out
June 2022
June 2023
Head of
CSS/CPP
Manager
The Executive Leadership Team (ELT)
directed a review and agreed a new
Community Engagement Guidance
document that will be rolled out to
employees. 
The ELT also agreed to establish a
working group to further evolve the
guidance into a clear framework to
provide greater guidance, flowchart and
tools for services to engage the
community.  This activity will link to the
training for Service Design that will be
rolled out this year (2023).