ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  20 June 2023 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2022-23 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these on SharePoint and, on a
quarterly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 31 March
2023 including information on actions where the agreed implementation
date has been rescheduled.   
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 31 March 2023. 
3.2 Appendix 1 provides further detail on actions that have either been delayed
and rescheduled or for which Internal Audit have received no response
from the service to inform this follow up.

Page 2

Table 1 - Actions Due by 31 March 2023 
Table 2 - Actions due after 31 March 2023 
Service
Complete
On Course
Delayed
&
Rescheduled
Total
INTERNAL AUDIT
CE – Financial Services   0 2 0 2
DH – Commercial Services 0 2 1 3
DH – Legal & Regulatory 1 1 0 2
KF – Customer Support Services 0 4 0 4
KF – Development & Economic Growth 0 2 0 2
KF – Roads & Infrastructure Services 0 4 0 4
H&SCP (IJB) – Adult Services (Older Adults & Community Hospitals) 0 0 1 1
H&SCP (IJB) – Finance & Transformation 0 1 0 1
H&SCP (SW) – Adult Services (Mental Health Learning Disability,
Addictions & Lifelong Conditions)
0 4 0 4
H&SCP (SW) – Finance & Transformation 0 2 0 2
EXTERNAL AUDIT
Nil 0 0 0 0
TOTAL 1 22 2 25 
Service
Complete
Delay &
Reschedule
Evidence
Required
No Response 
Total
INTERNAL AUDIT
CE – Financial Services   3 2 0 0 5
DH – Commercial Services 1 0 0 0 1
DH – Legal & Regulatory 0 3 0 0 3
KF – Customer Support Services 1 0 0 0 1
KF – Development & Economic Growth 1 1 0 0 2
KF – Roads & Infrastructure Services 2 0 1 0 3
H&SCP (IJB) – Adult Services (Older Adults & Community Hospitals) 0 3 0 0 3
H&SCP (IJB) – Strategic Planning & Performance 2 1 0 0 3
H&SCP (SW) – Adult Services (Mental Health Learning Disability,
Addictions & Lifelong Conditions)
3 4 0 0 7
LiveArgyll 1 0 0 0 1
EXTERNAL AUDIT     
Nil 0 0 0 0 0
TOTAL 14 14 1 0 29

Page 3

4.0 CONCLUSION 
4.1 Satisfactory progress continues to be made implementing audit actions. 
5.0 IMPLICATIONS 
5.1 Policy - None
5.2 Financial - None
5.3 Legal - None
5.4 HR - None
5.5 Fairer Scotland Duty - None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty - None
5.6 Risk –None 
5.7 Customer Service – None 
Paul MacAskill
Chief Internal Auditor
20 June 2023                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Action Plan Points Delayed & Rescheduled or with No Response

Page 4

Appendix 1 
Action Plan Points Due 31 March 2023 - Delayed & Rescheduled/Evidence Required 
Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
MEDIUM
FINANCIAL SERVICES
FIXED ASSET REGISTER (AIRS)
3. Asset Record Maintenance 
There are inconsistencies in descriptions when
recording Council assets across the various systems
and asset references are not always available to aid
cross referencing. This results in difficulties
reconciling assets held in service records to the
fixed asset system AIRS.
Work with Property Services
and Fleet to ensure systems
record the same assets and
refer to references on other
systems.
31 Dec 2022 
31 Mar 2023
30 Jun 2023
The data matching exercise
between both systems has been
completed and the Concerto
reference numbers harvested
and assigned to the
corresponding AIRS records. A
data upload has been prepared
to physically add the Concerto
references to the records in
AIRS and discussions are
ongoing with the AIRS system
supplier to confirm how to
upload the reference data to
AIRS. Completion of this work
has been delayed by recent
sickness absence but will be
finished at the earliest
opportunity. 
Delayed and Rescheduled
Accountant - Capital
MEDIUM
LEGAL & REGULATORY SUPPORT
CIVIL CONTINGENCIES
2. Civil Contingencies Duties   
Civil Contingencies officers are trained to comply
with all duties of the Act, however, the Council’s
business continuity duties are managed out with
the Unit.
A review of Business Continuity
arrangements across the
Council is to be progressed
during 22/23 and part of that
will be to integrate Business
Continuity duties within the
Civil Contingencies Unit as part
of their wider resilience
responsibilities.
31 Mar 2023
31 Mar 2024
An invitation to quote for the
first part of the process, ie, a
review of our current BCM
programme and systems to
ensure the council’s BCM
programme is effective and
robustly maintained has been
issued to a number of
consultants. 
Delayed and Rescheduled
Governance, Risk and
Safety Manager

Page 5

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
MEDIUM
LEGAL & REGULATORY SUPPORT
Heritage Assets
1. Valuations, Insurance & Fixed Assets Register 
Finding:  Civic chains, archive documents and
museum exhibits are not included within the
Council’s programme of valuations.    
Finding:  There is no inclusion of valuable archive
documentation within the Council’s All Risks
insurance policy.    
Finding:  Civic chains, Museum exhibits and
valuable archive documents are not included within
the Council’s Fixed Asset Register, AIRS.   
Recommendation:  Officers representing the
various services involved should meet to discuss the
requirements for valuation, insurance and inclusion
within the Council’s Annual Accounts and nominate
responsible officer(s) to take forward any actions
identified as a result. 
Officers representing the
various services involved will
meet to discuss the
requirements for valuation,
insurance and inclusion within
the Council’s Annual Accounts
and nominate responsible
officer(s) to take forward any
actions identified as a result.
31 Mar 2023
30 Jun 2023
Civic Chains are included on the
Council’s insurance but
arrangements are being made
for further valuation to update
on individual basis; inclusion of
Museum exhibits and archive
documents on AIRs is being
explored and actions planned to
be complete by 30 June 2023. 
Delayed and Rescheduled
Head of Legal and
Regulatory Support
HIGH
LEGAL & REGULATORY SUPPORT
ICT Remote Working 
2. GDPR Training and annual refresher 
21.4% of employees with a user accounts have
completed the mandatory or refresher GDPR
modules in 2021, falling below the target of 90%.
An email will be issued to all
networked employees
reminding them of the
requirement to complete the
mandatory or refresher GDPR
modules on LEON by 31 March
2023.
31 Mar 2023
30 Sep 2023
The mandatory module is
undertaken as part of a new
employee’s induction. The
refresher training module has
been revised/updated and sent
to Organisational Development
to build. Reminder email will be
sent once confirmation is
received that it is available in
LEON. 
Delayed and Rescheduled
Governance and Risk
Manager

Page 6

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
LOW
DEVELOPMENT & ECONOMIC GROWTH
Private Sector Housing Grants & Adaptions
3. Procedure Notes and Shared Documents 
While the vast majority of requirements are
included there would be benefit to updating these
to reflect current working practices, which have
evolved due to hybrid working arrangements and
the digitalisation of records.  Consideration should
be given to creating a checklist to ensure consistent
application of processes. 
Procedures and documents will
be reviewed and updated.
Checklists to be drawn  up and
introduced  when updating the 
procedures
31 Mar 2023
30 Sep 2023
Meeting will be arranged with
HSCP, Care and Repair and
Housing Officers to update
procedures and documents. 
This is scheduled to take place
in early June 2023 due to staff
shortages etc.   
Delayed and Rescheduled
Team Lead - Housing 
operations
LOW
ROADS & INFRASTRUCTURE SERVICES
STREET CLEANING
4. Updating of ELM 
Local Environment Teams (LETs) are not currently
using tablet devices to indicate that work allocated
has been completed. Supervisors are updating the
system in some areas but this is not consistent
across the Council.
Reintroduce use of handheld
devices subject to ongoing
Covid restrictions etc. to allow
efficient updates to ELM.
31 July 2022
31 Dec 2022
31 Mar 2023 
Handheld devices reintroduced
across the teams, supervisors
have received refresher training
and are now delivering
training/toolbox talks to
frontline staff to enable updates
to be completed to the ELM
system. 
Evidence Required
Operations Manager,
Roads &
Infrastructure
Services
HIGH
ADULT SERVICES (OLDER ADULTS & COMMUNITY
HOSPITALS)
HSCP - CARE PROGRAMME APPROACH (CPA)
1. CPA Procedures 
There are no agreed CPA written procedures,
including client assessment processes, to ensure a
consistent approach to CPA service provision across
the HSCP.
Processes and procedures will
be developed across Argyll &
Bute to improve consistency
and ensure service provision is
appropriate across the region. 
This is subject to the
recruitment of key posts within
the service which are currently
vacant.
30 June 2022
31 Dec 2022
28 Feb 2023
30 Sep 2023
April 2023 - CPA administrator
and co-ordinator in post,
benchmark of clients on CPA
completed and CPA process and
criteria written, currently going
through clinical quality group
for ratification and roll out. 
Delayed and Rescheduled
Consultant Nurse

Page 7

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
HIGH
ADULT SERVICES (OLDER ADULTS & COMMUNITY
HOSPITALS)
HSCP - CARE PROGRAMME APPROACH (CPA)
2. CPA Training 
There is no programme of CPA training available to
relevant HSCP staff to ensure a consistent approach
to CPA service provision across the HSCP.
A training programme will be
developed once key service
staff are recruited.
30 Sept 2022 
28 Feb 2023
31 Dec 2023
April 2023, process for CPA
awareness initiated, soft roll out
to begin the process of
understanding need and levels
of understanding, both post
holders able to and currently
supporting teams to implement
and progress supported CPA 
and are able to support training
where needed across A&B. 
Delayed and Rescheduled 
Service Manager
MEDIUM
ADULT SERVICES (OLDER ADULTS & COMMUNITY
HOSPITALS)
HSCP - CARE PROGRAMME APPROACH (CPA)
4. Carefirst 
Carefirst does not have a specific identifier category
for clients on the CPA programme.  Carefirst will be
replaced by the system Eclipse system in June 2022. 
Service is moving to Eclipse on
June 2022, an identifier
category will be included.
30 June 2022
30 Sept 2022 
31 Mar 2023
30 Sep 2023
The go live date for Eclipse has
been further delayed to June
2023. This will result in another
delay in implementing this
recommendation. 
Delayed and Rescheduled
Service Manager/
Eclipse Project
Manager
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
HSCP - RISK MANAGEMENT - Risk Management
Training
6. There is no formal, proactive programme of risk
management training. Whilst we understand some
training has been provided where requested by the
Clinical Governance Manager and her team (and
tailored to whom it is being delivered), there is no
requirement for Risk Leads to have training and
training records are not maintained. There is also
no dedicated training programme in place for new
members of the IJB or Audit Committee, such as
within induction training. 
A formal programme of risk
management training should be
developed and delivered to all
key personnel involved in the
management of risk.
30 June 2021
30 June 2022 
30 Dec 2022
31 Mar 2023 
30 Sep 2023
The following actions are being
taken -  
• Reviewing partner risk
management online training
resources. There has been a
significant change of personnel
within the team and we are
keen to support a longer term
approach to embedding risk
management and this will be
updated through the
contingency risk and resilience
group which is the appropriate
internal governance. 
Clinical Governance
Manager

Page 8

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
Risk management may be impaired due to
insufficient risk training and support amongst key
personnel.
• Implementing a programme of
system training (immediate) 
• Co-opting support from HR
and the Business Improvement
manager to support completion
of the task at an integrated
organisational level.   
Due to the review action an
update will be provided by the
next quarterly reporting period
which indicates an actual
completion date but the activity
is started.   
Delayed and Rescheduled 
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO)
Client Funds
3. Procedures 
This is a restricted report, content removed.
The facility to set up  individual
bank  accounts for each client 
will be made available to all
Social Work  Offices
31 Mar 2023
30 Jun 2023
Restricted Report, content
removed. 
Delayed and Rescheduled
Finance Manager 
Departmental
Support
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO)
Client Funds
4. Procedures 
This is a restricted report, content removed. 
A  new safe will be  installed 31 Mar 2023
30 Jun 2023
Restricted Report, content
removed. 
Delayed and Rescheduled
SW Admin Manager

Page 9

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO)
Client Funds
8. Procedures 
This is a restricted report, content removed.
Local banking facilities  will be
set up for each  Social Work
Office
31 Mar 2023
30 Jun 2023
Restricted Report, content
removed. 
Delayed and Rescheduled
Finance Manager 
Departmental
Support
VFM
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO)
SW - CHARGING FOR NON-RESIDENTIAL CARE
SERVICES
4. Service Uptake Data 
Records held on Carefirst do not allow for an
analysis of the level of service uptake compared to
those assessed as having a need. If this analysis
could be performed it would help inform
discussions and decisions in relation to service
uptake, charges and barriers to uptake.  It would be
advisable to progress this issue in conjunction with
the CareFirst replacement programme which is
scheduled to be complete by April 2022.
Recommendation accepted.
Further discussion will be held
with supplier to include service
uptake functionality and
reporting capabilities on new
system from April 2022.
31 Mar 2022
30 Sept 2022
31 Mar 2023
30 Jun 2023 
Eclipse go live has now been
further delayed to June 2023.
Some further delay to the
implementation of this
recommendation is now
expected 
Delayed and Rescheduled
Deputy Head of
eHealth HSCP

Page 10

Action Plan Points Due After 31 March 2023 - Delayed & Rescheduled/Evidence Required 
Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
LOW
COMMERCIAL SERVICES
Externally Funded Projects - Rothesay Pavilion
3. Resources 
Consideration should be given to reviewing the
extensive use of outside contractors and
consultants as opposed to investing in in-house
resources in regard to major capital projects
especially in light of the projected overspend on
the project.
As part of the End Project
Report, Lessons Learned, a
review of the decision
pertaining to project resourcing
will be undertaken, and
recommendations made to
Head of Service with respect to
the on-going efficient resourcing
of projects.  In developing
future projects the Council will
continue to give consideration
to the most efficient resourcing
model.
30 Jun 2023
30 Jun 2024
In approving the Staged
Approach to Project Completion
on 23 February 2023, the
Council has accepted the
resourcing structure for the
delivery of the Stage 2a works,
which are to be delivered
between 1 May 2023 and 14
June 2024. How the subsequent
stages of works are to be
resourced will be determined by
a number of factors, including:
securing the additional funding
necessary to take those works
forward; the procurement route
for securing the services of a
suitably qualified and
experienced principal
contractor; the availability of
the existing Design Team and
Cost Consultants to support the
delivery of the later stages of
implementation; and the
availability, experience and
capacity of internal technical
resources to provide support to
the project through the next
stages of implementation.
These will all be considered in
the interim period to arrive at a
preferred implementation
strategy for Stage 2b and Stage
2c, which will be submitted to
the Policy and resources
Project Manager

Page 11

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
Committee and full Council for
consideration and approval at
the appropriate juncture, but
realistically this may not be fully
determined prior to completion
of the Stage 2a works on 14
June 2024. 
Delayed and Rescheduled 
HIGH
ADULT SERVICES (OLDER ADULTS & COMMUNITY
HOSPITALS)
HSCP - CARE PROGRAMME APPROACH
3. Client Records 
There is no consistent agreed process for
maintaining client records, including the recording
and sharing of information.
HSCP expect to transition to
new Eclipse system.
Implementation of the new
system and associated
processes and procedures will
address this recommendation
and the Data Officer will be
involved in the development of
processes and procedures.
30 June 2022
30 Sept 2022
31 Mar 2023
30 June 2023
30 Sep 2023
The Eclipse go live date has
been further delayed to June
2023 by the project board.
Further delay in implementing
this recommendation is one of
the implications of this.   
Delayed and Rescheduled
Service Manager/
Eclipse Project
Manager