ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE 
FINANCIAL SERVICES  20 JUNE 2023 
INTERNAL AUDIT REPORTS TO AUDIT AND SCRUTINY COMMITTEE 2023/2024 
1. EXECUTIVE SUMMARY 
1.1 There are ten audits being reported to the Audit and Scrutiny Committee.     
1.2 The table below provides a summary of the conclusions for the audits performed.
The full reports are included as appendices to this report. 
Audit Name Level of
Assurance
High
Actions
Medium
Actions
Low
Actions
VFM
Actions
Purchasing Cards  Reasonable 0 9 4 0
Building Standards High 0 0 1 1
Cyber Security Substantial 0 5 1 0
Management of Debt & Debt Recovery Reasonable 0 4 3 1
Burial Records  Reasonable 1 3 2 0
Counselling in Schools Substantial 0 0 2 0
Equality and Socio-Economic Impact
Assessment Substantial 0 1 4 0
Payroll Reasonable 0 5 0 0
LiveArgyll – Lochgilphead Community
Centre High 0 0 0 0
LiveArgyll – Mid-Argyll Sports Centre High 0 0 0 0 
1.3 Internal Audit provides a level of assurance upon completion of audit work. A
definition for each assurance level is documented in each audit report. 
2. RECOMMENDATIONS 
2.1 Audit and Scrutiny Committee to review and endorse this summary report and the
detail within each individual report. 
3.  DETAIL 
3.1 A high level summary of each completed audit report is noted below: 
Purchasing cards:  Our overall audit opinion for this audit is that we can take a
reasonable level of assurance. Internal control, governance and the management
of risk are broadly reliable. However, whilst not displaying a general trend, there
are areas of concern which have been identified where elements of residual risk
or weakness may put some of the system objectives at risk. At times, procurement

Page 2

procedures are not being followed and procurement teams are not consulted prior
to purchases in excess of £1,000. Testing of payments in excess of £10,000
identified transactions with a total value of expenditure with one company
exceeding £50,000. Transactional testing was unable to obtain evidence of prior
approval for 42% of transactions, some approval is verbal or via retrospective
purchase orders. There is currently no formal process in place to ensure that the
budget holder has approved amendments to card limits.  The Education
Purchasing Team (EPT) was reinstated in 2020 and has been extended to March
2025 supporting Head Teachers and central education staff to deliver an increase
in contracted spend. While the review identified that there is still work to be done
in this area there are positive indications that there is a shift in culture towards
engaging with EPT. The Procurement Team set up a Council Amazon Business
account. This process is working well and has already delivered significant savings
which are reported by Procurement Team. While the testing of the imprest account
process is not within the scope of this review, we identified situations where staff
other than the cardholder withdraw cash using their purchase card. Receipts and
invoices are not always added to the banking system. Staff working remotely, or
in non-Council networked properties may not have access to appropriate
technology or have been provided guidance on alternative ways to upload this
information.   
Building standards:  This audit has provided a high level of assurance. This
means that internal control, governance and the management of risk are at a high
standard. Only marginal elements of residual risk have been identified with these
either being accepted or dealt with.  A sound system of control designed to achieve
the system objectives is in place and being applied consistently.  There is a clear
commitment to providing a fully digital verification service with supporting
information available to the public via the Council’s website.  Staff are
appropriately trained and qualified with formal partnership arrangements in
place to provide specialist support.  Officers are allocated work on a
competence basis and are appropriately supervised.  Systems are managed by
the Council’s ICT Services and administered by Building Standards who train
and support users.  Performance information is extracted from the Building
Standards system, reported to Scottish Government and published on the
Council’s website in a timely manner, however, this employs additional software
which may be subject to additional costs in the future.  Regular meetings take
place with the finance contact and the service income is on track to exceed costs
incurred.  Areas for improvement are identified by appropriate means and
published on a log along with details of progress made.  Collaborative working
take place with other verification authorities to discuss issues and share best
practice. 
Cyber security: This audit provided a substantial level of assurance. This
means that internal control, governance and the management of risk is sound.
However, there are minor areas of weakness which put some system objectives
at risk and specific elements of residual risk that are slightly above an
acceptable level and need to be addressed within a reasonable timescale.  An
Acceptable Use Policy was updated in October 2021 and provides instructions
and guidance to employees to ensure responsible use of systems and data,
however, the Cyber Security Policy has not yet been completed.  The Council’s
Strategic Management Team (SMT) review and update cyber risks on a 6-
monthly cycle as part of the review of the Strategic Risk Register, however they
do not receive regular updates from the ICT Compliance and Security Officer
(ICT-CSO) regarding newly identified risks and statistics indicating the volume
of cyber attacks deterred by the service.  The Council has achieved compliance

Page 3

with the Public Sector Network (PSN) code of connection as well as Cyber
Essentials+ reaccreditation.  Networking takes place with other local authorities
to share information and conferences are attended to learn from subject experts. 
The ICT-CSO holds the CompTIA Security+ certification and is responsible for
cyber security in addition to other duties and is designated as manager in the
cyber incident response plan.  There is no depute appointed to cover in the
absence of the ICT-CSO and with the increasing workload advised by the
National Cyber Security Centre (NCSC) it would appear that the Council is
under-resourced in this high risk field of expertise in comparison to other local
authorities where the majority contacted have teams in place.  Periodic
reminders of safe cyber practices are issued to employees and brief training
videos are issued monthly, however, these are not completed by all users.  A
comprehensive Cyber Incident Response Plan, Playbooks and Disaster
Recovery Plans have been prepared and tested with positive feedback recorded
following a corporate exercise in March 2022. 
Management of debt and debt recovery: This audit provided a reasonable
level of assurance.  This means that internal control, governance and the
management of risk are broadly reliable. However, whilst not displaying a
general trend, there are areas of concern which have been identified where
elements of residual risk or weakness may put some of the system objectives
at risk. This review covered the management and recovery of debt over four
areas – Council Tax, Non Domestic Rates, Housing Benefit Over Payments and
Sundry Debtors, which are invoices raised by Services. We found no significant
issues in relation to processes and procedures for Council Tax, Non Domestic
Rates and Housing Benefit Over Payments, most of which are covered by
legislation and are working well. The contents of this report largely covers
findings regarding the management and recovery of Sundry Debtors. The
Corporate Debt Policy and the Debtors Procedure Manuals have not been
updated since 2017 and do not reflect the current Council organisational
structure nor current working practices. A Business Process Review (BPR) is
currently being undertaken, this includes a review of debt management and
recovery policies and procedures. Our overall conclusion is that debt
management and arrears follow-up procedures relating to Sundry Debtor
invoices are not carried out in accordance with procedures. Testing identified a
number issues which are detailed in the body of report. A full review of the
processes and procedures for Sundry Debtors relating to the management,
arrears, follow-ups and bad debt write offs should be carried out. 
There are no performance measures in place to monitor recovery of Sundry
debt. Quarterly meetings with Legal Services to discuss recovery of Sundry
Debtors were postponed during the pandemic, these have not been re-instated.
The value of debt being actively managed is not easily quantifiable.
Management information relating to Sundry Debtors is not made widely
available. Provisions for Bad Debt are set in accordance with procedures. 
Burial Records: This audit has provided a reasonable level of assurance. 
This means that internal control, governance and the management of risk are
broadly reliable. However, whilst not displaying a general trend, there are
areas of concern which have been identified where elements of residual risk or
weakness may put some of the system objectives at risk.  Policies and
procedures are in place, however, these require to be reviewed on a regular
basis, additionally, there is no procedure for managing records resulting in
some inconsistencies across the service area locations.  The BACAS
electronic burial register is updated promptly upon receipt of details and

Page 4

traditional registers updated soon afterwards.  There is no record of private
home burials and documentation in support of exhumations was not available
at the time of the review.  The BACAS system is installed on a terminal server
that is accessed remotely by users via network credentials, however, there is
no further authentication required to logon to the system to prevent
unauthorised access.  Traditional registers are stored safely in locked rooms,
safes and filing cabinets, saved electronic forms are securely managed on
shared drives and printed documents are managed by the Council’s secure
printing service.  Burial registers are not made available to the public to view to
maintain compliance with GDPR, however, extracts of information can be
provided upon request and payment of the appropriate fee. 
Counselling in schools: this audit provided a substantial level of assurance.
This means that internal control, governance and the management of risk is
sound. However, there are minor areas of weakness which put some system
objectives at risk and specific elements of residual risk that are slightly above
an acceptable level and need to be addressed within a reasonable timescale.
Temporary funding provided to the Council was utilised to develop a counselling
in schools service which has been in place since January 2021. The Council did
not have an existing counselling service therefore there were delays in the
commencement of the service resulting in Year 1 funding being underspent.
After discussions with partners and careful consideration it was agreed that the
counselling service would be delivered by the HSCP with funding transferring
from Education to the NHS. There are no records to support the appraisal and
decision making process for the delivery of counselling services. Over 729
young people engaged with the service during the period of funding to
December 2022. Whilst we can draw a substantial level of assurance that young
people have benefited from the delivery of an effective counselling service
based on the outcomes measured against the ten nationally agreed core
principles, the funding provided by the Scottish Government was not fully
utilised and has carried forward an underspend to a new project. The impact of
counselling is assessed using the Strengths and Difficulties Questionnaire
(SDQ) and the Young Persons CORE 10 (YP-CORE 10) which are both
assessment tools used to evaluate progress. The outcomes set were in line with
the Scottish Governments Core Principles and reporting requirements. Councils
were required to submit regular reports on a six monthly basis to the Scottish
Government detailing outcomes over the period, this was done on a standard
template. 
Equality and Socio-economic impact assessments: this audit provided a
substantial level of assurance.  This means that internal control, governance
and the management of risk is sound. However, there are minor areas of
weakness which put some system objectives at risk and specific elements of
residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. Equality and Socio-Economic Impact
Assessment processes are in place which reflect current legislative and
regulatory requirements.  The Council have published guidance for staff entitled
‘Argyll and Bute Equality and Socio-Economic Impact Assessment (2020)
Guidance’.  This guidance sets out the council’s Equality and Socio-Economic
Impact Assessment (EqSEIA) process, why we have one, and how it is used.
EqSEIAs are being undertaken, however, there are inconsistencies in practice
across the Council. We reviewed papers submitted to Committees for decision
and the budget pack, specifically looking to ensure that when required the
EqSEIAs had been completed.  The review of papers submitted indicate that a
number of EqSEIAs had been missed by the responsible service. The Council

Page 5

is required to publish, at intervals of not more than two years, a report on the
progress it has made to make the general equality duty integral to the exercise
of its functions. The Council have published and made available on the Council’s
website the ‘Equalities Mainstreaming Report and Equality Outcomes’ every two
years since 2013, the most recent report in 2021. 
Payroll: This audit has provided a reasonable level of assurance.  This means
that internal control, governance and the management of risk are broadly
reliable. However, whilst not displaying a general trend, there are areas of
concern which have been identified where elements of residual risk or weakness
may put some of the system objectives at risk.  Payroll are dependent on the
systems and processes in place which inform them of additions or changes
within the payroll system.  The efficiency of the whole process is heavily reliant
on managers within the services inputting the correct information and uploading
all the relevant paperwork in a timely manner.  Whilst there are well understood
processes and procedures in place for the management of payroll updates, the
whole process is hugely inefficient.  Each step of the process requires
considerable amounts of manual intervention with the same basic information
requiring to be keyed in separately by HR&OD and payroll, increasing the risk
of error.  A combination of the challenges that can be experienced at times,
include payroll not being updated in a timely manner.  Payroll have established
timetables which are available on the HUB for staff to view. The number of
payroll errors and late submissions to payroll are tracked on a spreadsheet and
reported each quarter.  Reliance was placed on work undertaken as part of the
continuous monitoring process. Staff are restricted from certain areas of the
systems and can only access data/areas that fall within their job remit.  User
lists and access right are reviewed on a monthly basis and are updated as and
when Payroll are notified of any leavers. 
LiveArgyll – Lochgilphead Community Centre: This audit has provided a
high level of assurance. This means that internal control, governance and the
management of risk are at a high standard. Only marginal elements of residual
risk have been identified with these either being accepted or dealt with. A sound
system of control designed to achieve the system objectives is in place and
being applied consistently. Audit testing on LiveArgyll establishments are
predominantly observational, therefore, any issues that are highlighted are
based on what was witnessed on the day of the visit. Recommendations are not
included in the reports and LiveArgyll management determine whether any
corrective action is required. Under any ‘areas for consideration’ management
will take appropriate action. (For Information only) 
LiveArgyll – Mid-Argyll Sports Centre: This audit has provided a high level of
assurance. This means that internal control, governance and the management
of risk are at a high standard. Only marginal elements of residual risk have been
identified with these either being accepted or dealt with. A sound system of
control designed to achieve the system objectives is in place and being applied
consistently. Audit testing on LiveArgyll establishments are predominantly
observational, therefore, any issues that are highlighted are based on what was
witnessed on the day of the visit. Recommendations are not included in the
reports and LiveArgyll management determine whether any corrective action is
required. Under any ‘areas for consideration’ management will take appropriate
action. (For Information only)

Page 6

4. CONCLUSION 
4.1 Management has accepted each of the reports submitted and have agreed
responses and timescales in the respective action plans. 
5. IMPLICATIONS 
5.1 Policy - None
5.2 Financial - None
5.3 Legal - None
5.4 HR – None
5.5 Fairer Scotland Duty - None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty – None
5.6 Climate Change – None 
5.7 Risk – The implementation of recommendations contained in audit reports may
help mitigate the risk to the Council. 
5.8 Customer Service – None 
Paul Macaskill
Chief Internal Auditor
20 June 2023 
For further information contact: 
Paul Macaskill, Chief Internal Auditor
Tel:  01546 604108
Email: paul.macaskill@argyll-bute.gov.uk 
APPENDICES 
1. Purchasing Cards
2. Building Standards
3. Cyber Security
4. Management of Debt/Debt Recovery
5. Burial Grounds
6. Counselling in Schools
7. Equality and Socio-Economic Impact Assessment
8. Payroll
9. LiveArgyll – Lochgilphead Community Centre
10. LiveArgyll – Mid-Argyll Sports Centre