ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  14 September 2023 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2023-24 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these in a database and, on a
monthly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 30 June 2023
including information on actions where the agreed implementation date
has been rescheduled.   
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 30 June 2023. 
3.2 Appendix 1 provides further detail on actions that have either been delayed
and rescheduled or for which Internal Audit have received no response
from the service to inform this follow up.

Page 2

Table 1 - Actions Due by 30 June 2023 
Service
Complete
Delayed/
Rescheduled
No Response
Evidence
Required
Total
Internal Audit
DH – Legal & Regulatory 1 0 0 0 1
KF – Customer Support Services 1 0 0 0 1
KF – Development & Economic Growth 1 2 0 0 3
KF – Roads & Infrastructure Services 0 5 0 0 5
KF – Financial Services 1 6 0 0 7
H&SCP (IJB) – Finance & Transformation 0 1 0 0 1
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
1 4 0 0 5
H&SCP (SW) – Finance & Transformation 0 2 0 0 2
External Audit
Nil     
TOTAL 5 20 0 0 25 
Table 2 - Actions due after 30 June 2023 
Service
Complete
Delayed/
Rescheduled
No
Response
On Course
Evidence
Required
Total
Internal Audit
DH – Commercial Services 0 0 0 3 0 3
DH – Legal & Regulatory 1 0 0 6 0 7
KF – Customer Support Services 1 1 0 11 0 13
KF – Development & Economic Growth 0 0 0 3 0 3
KF – Roads & Infrastructure Services 0 0 0 6 0 6
KF – Financial Services 1 0 0 31 0 32
H&SCP (IJB) – Adult Services (Older Adults &
Community Hospitals)
0 0 0 4 0 4
H&SCP (IJB) – Strategic Planning & Performance 0 0 0 1 0 1
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
0 0 0 2 0 2
External Audit
Nil      
TOTAL 3 1 0 67 0 71 
4.0 CONCLUSION 
4.1 Reasonable progress continues to be made implementing audit actions.

Page 3

5.0 IMPLICATIONS 
5.1 Policy – None
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Fairer Scotland Duty – None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty – None
5.6 Climate Change – None
5.7 Risk – None
5.8 Customer Service – None 
Paul MacAskill
Chief Internal Auditor
14 September 2023                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Action Plan Points Delayed & Rescheduled or with No Response

Page 4

Appendix 1 
Action Plan Points Due by 30 June 2023 - Delayed & Rescheduled/Evidence Required   
Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
VFM
DEVELOPMENT & ECONOMIC GROWTH
Building Standards 
2. KPO Reporting Finding: MS Access is used to
extract data from the IDOX system for KPO
reporting, however, a move to corporate use of MS
Office 365 means that MS Access is not included
within that licence agreement. Support for MS
Access 2013 will expire 31 March 2023 and newer
existing versions by 31 March 2026 thereafter
additional arrangements and licences will be
required. Recommendation: Building Standards
services should revisit the reporting functionality of
the IDOX system to assess if historical issues have
been addressed and raise any outstanding
anomalies with the system provider. This will
provide contingency for MS Access reporting. This
will provide contingency for MS Access reporting. 
1. Run all 7 IDOX standards
reports and compare with the
services MS Access reports 2.
Identify and investigate
differences 3. Report findings
to IDOX and request feedback
30 June 2023
01 Aug 2023
Work is ongoing to assess the
adequacy pf the IDOX standards
reports against our own MS
Access management reports.
This was delayed due to
resourcing issues and need to
carry out full testing for the
service upgrade to the UNIFORM
system.   
Delayed and Rescheduled
Building Standards
Data Systems
Technician
HIGH
DEVELOPMENT & ECONOMIC GROWTH
Planning Applications 
1. Procedure Document There are no established
written procedural documents in  place, staff
follow a series of workflow processes which  are
aligned to legislative requirements and current
guidance.
Review and update of existing
written procedures to provide
a collated procedural
document for the handling of
planning applications.
31 Dec 2022 
30 Jun 2023
31 Jul 2024
Staff availability to progress this
action has again been limited
and the requirement to prepare
a current procedure note is
being overtaken by ongoing
work to review and update
current work processes that are
linked to the IT led project for
the replacement of Civica with
the IDOX Document
Management System and
internal development of a new
Process and
Productivity 
Improvement Officer

Page 5

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
workflow system using IDOX
Enterprise. The IDOX DMS
project has been delayed as a
result of matters out with the
direct control of the DM Service
and is currently expected to be
completed by Summer 2024, it is
recommended that the updated
procedure notes be produced to
align with the introduction of the
new system environment
(Summer 2024). 
Delayed and Rescheduled 
LOW
ROADS & INFRASTRUCTURE SERVICES
FLEET MANAGEMENT 
3. Driving Hours Compliance 
Fleet drivers not subject to EU legislation maintain
manual driving records which are handed to
supervisors on a weekly basis to check and sign.
This is a resource intensive process which is subject
to human error. There would be clear process
efficiency gains and less risk of error if the Council
adopted the system already in place for fleet
drivers subject to EU legislation and rolled out
electronic driver cards to all fleet drivers. 
The key officer will ensure that
all drivers hold and use
tachograph cards to move
away from the paper book
records.
31 Dec 2020 
31 Mar 2021 
30 June 2021
31 Mar 2022
30 June 2022
31 Aug 2022 
31 Mar 2023 
31 May 2023
31 Aug 2023
Meeting was held 15 June where
it was agreed to roll out the
Digital Tachograph to one area
(Helensburgh) starting in August,
on a trial basis. A review will take
place with roll out in other
locations thereafter. The reason
for progressing on a trial basis is
down to new information
coming to light relating to the
council having implemented a
tachograph system
approximately 15 years ago
following which VOSA made
changes which allowed councils
to continue to use log books for
activities where drivers are only
driving for a part of the working
day. The Helensburgh trial will
help to determine the suitability
of tachographs vs logbooks. Also
Procurement/
Technical Officer

Page 6

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
at the June meeting it was
agreed that enhanced logbook
information will be produced
which can also be compared
with timesheets to ensure that
we have a definitive record of
driving activity. Note the existing
use of tachographs, where
drivers drive full time, will
continue during the trial period. 
Delayed and Rescheduled 
VFM
ROADS & INFRASTRUCTURE SERVICES
FLEET MANAGEMENT 
6. Management of Pool Cars A high level analysis of
the use of pool cars suggests the Council could
generate considerable savings through more
efficient use of pool cars. Fleet Services should
explore this further via a more detailed review
which should consider the potential benefits of: 
 a more centralised approach to the
administration and booking of pool cars
 better promotion of the use of pool cars
 providing greater visibility of bookings and
destinations to encourage pool car sharing
 implementing or developing a pool car
booking system
 identifying ways of transferring the balance
of pool car usage from shorter journeys to
longer ones 
The pool car module will be
released through Tranman. 
The pool car module offers a
centralised approach to
bookings and visibility. The
Council’s internal
communications department
will be contacted to highlight
the use of the pool cars. Work
will be undertaken to increase
usage.
30 Sep 2020 
31 Dec 2020
30 June 2021
31 Dec 2021 
30 Apr 2022
29 Jul 2022 
30 Sep 2022 
31 Dec 2022
30 Apr 2023
31 Aug 2023
Digital team contacted regarding
procedure for system switch-
over and comms to council staff.
Revised go live date 1/8/23. 
Delayed and Rescheduled
Procurement/
Technical Officer

Page 7

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
LOW
ROADS & INFRASTRUCTURE SERVICES
STREET CLEANING 
4. Updating of ELM Local Environment Teams
(LETs) are not currently using tablet devices to
indicate that work allocated has been completed.
Supervisors are updating the system in some areas
but this is not consistent across the Council. 
Reintroduce use of handheld
devices subject to ongoing
Covid restrictions etc. to allow
efficient updates to ELM.
31 July 2022
31 Dec 2022
31 Mar 2023
30 Sept 2023 
Refresher training for
supervisors is nearing
completion.  Reintroduction of
the tablet devices has not yet
been fully implemented as issues
have been identified in the
performance of the devices and
their usage is considered
challenging for some employees. 
Further consideration will be
taken to progress this action. 
Delayed and Rescheduled 
Operations Manager,
Roads &
Infrastructure
Services
HIGH
ROADS & INFRASTRUCTURE SERVICES
WARDEN SERVICES 
3. Second Bin Service Verification 
Wardens are expected to verify the veracity of
applications from customers for a second domestic
bin service. This requires the warden to confirm
that information provided by the customer is
accurate and meets the defined criteria. The
information provided to substantiate an
application can be very personal and sometimes of
a sensitive medical nature. Wardens have been
asked to provide this service but have received no
formal training in how to ensure a customer’s
dignity is maintained or to ensure they are aware
of the requirements of General Data Protection
Regulation (GDPR) in relation to personal data for
this specific process. 
Due to the sensitivity of this process, and the
potential risks associated with data protection it is
Review the process for; 
Review the second bins that
are in place and the process for
rationalising. This review to
also give consideration to
composition and identify
opportunity to increase
recycling and reduce general
waste.
30 Sep 2022 
30 Dec 2022 
30 Jun 2023
30 Sep 2023
The list for the second domestic
bins has been compiled as have
the draft letters for both second
domestic bins and assisted pull
outs to send to residents to see if
they still require this service. 
These letters will be sent out by
Friday 28th July 2023 with a
return date of Friday 1st
September 2023. 
Delayed and Rescheduled
Operations Manager,
Roads &
Infrastructure
Services

Page 8

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
recommended that the current verification process
is reconsidered to determine if it is appropriate to
maintain it in its current form. If it is decided it
should be retained then there should be
engagement with the Council’s Governance and
Risk Manager to ensure it is being carried out in full
compliance with GDPR. 
HIGH
ROADS & INFRASTRUCTURE SERVICES
WARDEN SERVICES 
2. Second Bin Service Verification 
Wardens are expected to verify the veracity of
applications from customers for a second domestic
bin service. This requires the warden to confirm
that information provided by the customer is
accurate and meets the defined criteria. The
information provided to substantiate an
application can be very personal and sometimes of
a sensitive medical nature. Wardens have been
asked to provide this service but have received no
formal training in how to ensure a customer’s
dignity is maintained or to ensure they are aware
of the requirements of General Data Protection
Regulation (GDPR) in relation to personal data for
this specific process. 
Due to the sensitivity of this process, and the
potential risks associated with data protection it is
recommended that the current verification process
is reconsidered to determine if it is appropriate to
maintain it in its current form. If it is decided it
should be retained then there should be
engagement with the Council’s Governance and
Review the process for -  
Dealing with requests for new
and replacement bins.
30 June 2022 
30 Sep 2022 
31 Dec 2022 
30 Jun 2023
31 Jul 2023
Work is still ongoing on the
waste policy and a draft
procedure is with the Operations
Manager for sign off.  As per
previous comment those
customers who require a second
bin for medical requirements will
automatically receive their bin. 
The Wardens have received
confidentiality training from KSB
and the service receives annual
training with regards to RIPSA
from the Governance and Risk
Manager. 
Delayed and Rescheduled
Operations Manager,
Roads &
Infrastructure
Services

Page 9

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
Risk Manager to ensure it is being carried out in full
compliance with GDPR. 
MEDIUM
FINANCIAL SERVICES
FIXED ASSET REGISTER (AIRS) 
3. Asset Record Maintenance 
There are inconsistencies in descriptions when
recording Council assets across the various systems
and asset references are not always available to aid
cross referencing. This results in difficulties
reconciling assets held in service records to the
fixed asset system AIRS. 
Work with Property Services
and Fleet to ensure systems
record the same assets and
refer to references on other
systems.
31 Dec 2022 
31 Mar 2023
30 June 2023
30 Sep 2023
The bulk of the work for this has
been completed, however, the
information has not been
transferred over to AIRS due to
issues with the AIRS system
requiring supplier support and
also staff resources. 
Delayed and Rescheduled
Accountant - Capital
MEDIUM
FINANCIAL SERVICES
MANAGEMENT OF DEBT/DEBT RECOVERY 
10. Raising of invoices and Recovery Routes
Finding:  Legal Services recovery is hampered due
to lack of customer telephone and email contact
details being entered when the Debtors records
are created by Services.  Recommendation:  Phone
number and email fields should be mandatory 
Speak to System supplier about
making these fields mandatory
for users to complete if raising
a debtor account.
30 June 2023
31 Dec 2023
We have spoken to the System
supplier and this is still under
investigation with the supplier.     
Delayed and Rescheduled
NDR &  Income
Manager
VFM
FINANCIAL SERVICES
Management of Debt/Debt Recovery 
17. Sharing of good practice Consideration should
be given to whether it is possible to issues text
message reminders for Non Domestic Rates missed
payments.
The service would like to look
at the possibility of E-billing
and text reminders for NDR in
the future.  There will be a cost
to this, given that NDR income
is pooled by the government it
has never been our highest
priority. That being said it
would introduce improvements
for our businesses. We will
approach the systems supplier,
30 June 2023
31 Dec 2023
Action regarding E-billing had
been progressing but was stalled
around March due to Annual
Billing and revaluation.   We are
looking to establish if this is
possible to do in-house, or if we
require to purchase 3rd party
software. We have also still to
approach the systems supplier
(Northgate) about the possibility
of using a text reminder service.  
NDR & Income
Manager

Page 10

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
Northgate (Orbis) and get
quotes for this work.  At that
point a business case will need
to be considered before any
other progress can be made. 
Delayed and Rescheduled
MEDIUM
FINANCIAL SERVICES
CAPITAL MONITORING 
1. Capital Programme Planning & Management
Guide The Council’s Capital Guide has not been
revised since 2018 and requires a review to ensure
it reflects current working practices and provides
appropriate support to officers involved in the
capital monitoring process. The Council is currently
developing a new Capital Strategy which is to be
presented to the Policy and Resources Committee
in August 2021 and we recognise that a review of
the Guide should be conducted after the Strategy
has been finalised to ensure the two documents
complement each other and. The Guide could also
benefit from being linked to, or referencing, other
relevant Council processes, in particular the Project
Management section on the Hub. 
Capital Planning and
Management Guide to be
updated once the Capital
Strategy has been approved to
ensure the two are aligned and
provide clarity.
31 Mar 2022 
30 Sep 2022 
31 Dec 2022
31 Mar 2023
30 Sep 2023 
The completion of this action is
dependent upon the agreement
of the revised capital strategy.
The latest update from the Head
of Commercial Services is that
the strategy is currently being
refined and it is planned that it
will be presented to the Policy
and Resources Committee in
June 2023. 
Delayed and Rescheduled
Head of Commercial
Services/Finance
Manager
MEDIUM
FINANCIAL SERVICES
CAPITAL MONITORING 
2. Capital Programme Training   
There is no training programme to support officers
involved in the management of the Council’s
capital programme. It would be beneficial to
engage with project managers to identify training
needs and address these through the development
of a training programme to help ensure a
Training documentation to be
created that project managers
can refer to. Refresher training
to be provided for existing
Project Managers and a plan
put in place for training for any
new staff that have capital
budget monitoring
responsibilities.
30 Jun 2022
30 Sep 2022 
31 Mar 2023
30 Jun 2023
30 Sep 2023
The completion of this action is
dependent upon the agreement
of the revised capital strategy.
The latest update from the Head
of Commercial Services is that
the strategy is currently being
refined and it is planned that it
will be presented to the Policy
and Resources Committee in
June 2023. 
Finance Manager

Page 11

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
consistent and robust approach to capital project
management. In particular this should include
training on capital project profiling. 
Delayed and Rescheduled
HIGH
FINANCIAL SERVICES
FOLLOWING THE PUBLIC POUND 
1. Guidance on Following the Public Pound (FtPP)
Although the Council has an approved process to
manage external funding requests it is limited in
detail, is not closely aligned to the Code of
Guidance on Funding External Bodies and
Following the Public Pound and there is a general
lack of awareness amongst officers that it exists.
Audit testing identified a number of areas of good
practice within the Council and overall compliance
with the principles of FtPP however there were
examples of inconsistent practice. A more
comprehensive guidance document should be
established which provides a more standardised
and tiered approach providing greater clarity over
roles and responsibilities and standardised
templates for key stages in the process including
funding assessments and post award monitoring
and reporting. The audit team researched a
number of examples of FtPP guidance which had
been created by other councils during the planning
phase of the audit and can make these available to
inform the creation of an Argyll and Bute
equivalent. 
Following the Public Pound
guidance will be drafted to
provide a consistent approach
to managing the award of
external funds.
30 Jun 2020
31 Dec 2020
30 Jun 2021
31 Dec 2021
30 Sep 2022 
31 Dec 2022 
31 Mar 2023 
30 Jun 2023
30 Sep 2023
This cannot be completed until
the Capital Investment Strategy
has been completed. The latest
update from the Head of
Commercial Services is that the
strategy is currently being
refined and it is planned for it to
be presented to the Policy and
Resource Committee in June
2023. Currently waiting on the
new asset management strategy
being completed and ratified to
complete. 
Delayed and Rescheduled
Head of Financial
Services

Page 12

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
LOW
FINANCE/TRANSFORMATION
H&SCP - Complaints Handling 
3. Training 
Training should be provided in the complaints
handling  procedures for the IJB
Complaints Handling  Training
will be  incorporated into staff 
training processes
30 Sep 2022 
30 Nov 2022 
30 Jun 2023
30 Sep 2023 
Training took place in person on
9th June.  
Single agency training has been
delivered with a plan to move
towards joint training in the
coming months- the plan is still
being developed. Complaint
handlers, investigators and
responsible managers are also
encouraged to access the SPSO
online resources for training on
complaints handling and
investigations. 
Delayed and Rescheduled 
Chief Nurse-NHS
Highland
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds
2.  Detail restricted. 
Detail restricted. 30 Jun 2023
31 Aug 2023
Detail restricted. 
Delayed and Rescheduled
SW Admin Manager
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds
4.  Detail restricted. 
Detail restricted. 31 Mar 2023 
30 Jun 2023
31 Aug 2023
Detail restricted. 
Delayed and Rescheduled
SW Admin Manager
HIGH
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds
6.  Detail restricted.
Detail restricted. 30 Jun 2023
31 Aug 2023
Detail restricted. 
Delayed and Rescheduled
SW Admin Manager

Page 13

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
MEDIUM
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds
9.  Detail restricted. 
Detail restricted. 30 Jun 2023
31 Jul 2023
Detail restricted. 
Delayed and Rescheduled
SW Admin Manager
HIGH
FINANCE/TRANSFORMATION
Customer Service Centre 
1. Failure to ensure CET have up to date Service
information There is concern that some teams
within HSPC are not  fully engaging with CSC,
despite repeated requests from  Senior Managers
to review their information. In addition, the Duty
rotas and contact details on the HSPC SharePoint
are not always up to date. HSCP must engage with
CET to review the online and offline information
available to agents and customers to ensure it is
accurate, up to date and reflects current team
structures and duty rotas.
Provided by key officer HSCP
management will work with the
CET team to determine the
best way to approach the
current problem and
implement the correct solution
agreeable by HSCP and CSC.
30 Jun 2023
30 Sep 2023
A meeting with senior staff and
service centre management is
arranged for 20 July to review
the information requirement and
partnership working to address
concerns.  Highlighted evidence
from CSC has been forwarded to
management and action taken to
ensure staff are responding
appropriately.  Some ongoing
staffing issues suspended duty
rotas in some areas which was
not communicated. Other duty
rotas are confirmed as up to
date. If this is not operating as
required it will be reviewed at
the meeting. 
Delayed and Rescheduled
Business
Improvement 
Manager
VFM
FINANCE/TRANSFORMATION
Customer Service Centre 
6. Routing of calls to the appropriate channels Calls
for HSPC represent the highest volume of both calls
handled by CSC and transferred to the Service. The
data provided detailing the teams the calls are
transferred to indicates that it may be more
appropriate for properly trained staff to handle
and manage these calls.  Contact Centre and HSCP
Provided by key officer The
service will engage in
discussions with CET’s
Customer Engagement
Manager to ensure that
suitable arrangements are in
place which maximises
efficiency and effectiveness of
the handling of customer
30 Jun 2023
30 Sep 2023
This action will be a focal point
of the forthcoming meeting on
20 July. Contact centre staff are
regularly provided with training
in public protection and this can
be arranged as required.  As
noted previously we have
responded to protection
concerns by ensuring staff are
directed to respond to CSC
Business
Improvement 
Manager

Page 14

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
should analyse whether it is more efficient to route
certain call types on the HSCP Golden Number
directly to HSCP for them to manage or that
specific issues which require more specialist or
detailed knowledge are dealt directly by HSCP. 
contacts and enquiries via the
HSCP Golden Number.
appropriately. 
Delayed and Rescheduled

Page 15

Action Plan Points Due after 30 June 2023 - Delayed & Rescheduled 
Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer / Status
LOW
CUSTOMER SUPPORT SERVICES
Customer Service Centre 
3. Performance Indicators Information gather using
the Avoidable and Non Avoidable  categories do not
match real time concerns or trends  identified by
staff regarding arising issues as these are  lagging
indicators.  Customer Service Centre should , with
Services, review the  definitions of the Avoidable
and Non Avoidable Contacts  with a view to
gathering actionable data on the volume of  repeat
contacts due to lack of follow up, availability of 
information and establishing whether there is an
issue  with customers being unable to reach staff
who have been  named as a key contacts.
Provided by key officer 1. CET
will engage with Service Leads
to review Avoidable Contact
measures and reporting.  2. CET
will send a report with
Improvement
Recommendations to DMT and
ELT for approval by July 2023.
31 Jul 2023
30 Sep 2023
CET has been liaising with
Govmetric regarding the latest
thinking around Avoidable
Contact and the potential to use
it for efficiencies. A
presentation on this was given
to Budget Working Group on
26/6 where it was recognised as
having longer term potential
(see attachment item 6). The
Avoidable Contact Consultation
will now be integrated to the
wider Customer Service
Strategy Consultation, hence
the completion date of this task
will slip. 
Delayed and Rescheduled
Customer
Engagement
Manager