ARGYLL AND BUTE COUNCIL  AUDIT & SCRUTINY COMMITTEE   
FINANCIAL SERVICES  14 SEPTEMBER 2023  
INTERNAL AUDIT  AND COUNTER FRAUD SUMMARY OF ACTIVITIES 
1. SUMMARY  
1.1 The objective of the report is to provide the Audit and Scrutiny Committee (the
Committee) with a summary of Internal Audit activity and progress during quarter
two of 2023/24.  
1.2 Core activities together with a progress update statement are shown below: 
 2023/24 Audit Plan progress: On track subject to available resources being in
place for the full period of the approved plan. 
 2023/24 Individual Audits undertaken: Four audits have been completed
during the period and all have been assessed as providing high assurance.
(Where HSCP and LiveArgyll Audits are included these are provided for
information only). 
 Scrutiny: Planned work for 2023/24 in relation to ‘Fly Tipping’ will be scheduled
later in the calendar year. 
 Counter Fraud: The Counter Fraud Team (CFT) is continuing to rebill council
tax accounts and recovery of funds is underway.  All other aspects and referrals
are being considered, investigated and evaluated and the Counter Fraud Team
remain vigilant to protect our public purse. 
 Continuous Monitoring Programme Testing: A number of auditable units are
subject to continuous testing. There have been two new issues which have
been identified this quarter and which we have received a management
response for both cases. 
 Performance indicators: Current status is green / on track. 
2. RECOMMENDATIONS  
2.1 To review and endorse the Summary of Activities report.  
3. DETAIL  
3.1 Four audits have been completed since the previous Committee in June 2023. 
Audits Completed 
 Risk Management
 Education Maintenance Allowance
 Kintyre Community Centre – LiveArgyll

Page 2

 Victoria Hall - LiveArgyll 
Audits in Planning / in Progress
reported to a future meeting of the Committee 
 Piers and Harbours
 Pupil and Public Transport
 Hire of Vehicles
 Learning and Disability Care Packages
 Pupil Registration 
3.2 In addition to those already in progress, indicative audits planned for Quarter 3
2023/24 are: 
 Planning
 Freedom of Information Requests
 Compliance Review 
 Oban Airport  
3.3 2023/24 Audit Plan 
 Work has commenced on the approved plan and with work ongoing
outlined in paragraph 3.2.   
Scrutiny  
3.4 It was agreed in June 2023 that scrutiny work for 2023/24 will focus on the
outstanding review concerning ‘Fly Tipping’. Work had previously been postponed
until data became available to the Panel. It is now likely that this will be in the
autumn/winter of 2023 but we will keep the Panel updated. 
Counter Fraud  
3.5 “The CFT is progressing well with both team members fully CIPFA accredited
fraud investigators. Continued routine work is required to be able to accurately
track the full income recovered from the team’s work, however, based on the
amount of additional billing, even accounting for a degree of non-recovery, the
indications are that they are easily exceeding target. In addition the team are
raising awareness of the Council’s zero tolerance to fraud and this will act as a
deterrent to fraud being perpetrated in the first place. 
The team aim to visit Mull in the coming months which will likely conclude the
proactive island work this year.  The islands will be proactively reviewed
periodically for any new evidence or any further investigative requirements. 
A large review of the Helensburgh area is underway, this will be labour intensive
and will involve in depth discussions with the council tax team in order to assess
information and where appropriate re-bill any monies due as may result from the
work.

Page 3

The team now have a referral system in place from council tax teams as additional
resources through the use of summer students working has supported this
development.   
The team lead is also working directly with DWP in order to conclude a long term
investigation and will liaise with sheriff officers if successful to proceed with
recovery.  The CFT will also look at other avenues to conclude this difficult
investigation if the DWP venture is fruitless. 
The CFT are also working closely with the empty homes team to support each
other in our remits.  Work and communication between each department is key in
finding solutions and appropriate billings to enable empty homes to return to
residency or open market. 
The NFI exercise continues to be a routine work area for the CFT. 
Additional Updates from Quarter One  
3.6 Staff continue to work from home and this has proved to be successful; where on-
site visits have been required due to the specific nature of the audit work to be
undertaken, these visits have occurred in accordance with any guidance that was
in place, including lone worker best practice.  
3.7 The Public Sector Internal Audit Standards (PSIAS) require the Council’s Chief
Internal Auditor (CIA) to develop a Quality Assurance and Improvement
Programme (QAIP). The purpose of the QAIP is to enable the evaluation of
internal audit’s conformance to the PSIAS. The QAIP must include annual
internal self-assessments with a five yearly external assessment, carried out by
an independent assessor.  A programme of five yearly reviews has been
prepared by the Scottish Local Authorities Chief Internal Auditors Group
(SLACIAG) and these will be conducted by peer review. This review has been
completed and the findings were reported to the March 2023 meeting of the
Committee.  The Self-Assessment against the PSIAS for 2023 will be reported to
the September meeting of the Committee.  
3.8 A sample of data in respect of the Statutory Performance Indicators (SPI’s) that are
required to be returned by councils as part of the Local Government Benchmarking
Framework (LGBF) must be reviewed by Internal Audit for submission to the
Improvement Service by 31 August each year.  Internal audit carry out this work in
collaboration with colleagues in performance management.  Internal Audit was
provided with the full set of data from which to select indicators for review on 23
June and as large variances were reported in ‘Payment of Invoices’ and ‘Cost of
Council Tax Collection’ and there was a change in the data requirement for ‘Equal
Opportunities Policy 1’, these indicators were selected for review.   There were
also large variances reported in sport and leisure management, museum services
and use of libraries, however, the explanations provided were largely due to a
return to full service following Covid restrictions.  It was decided that these
indicators would not be reviewed for the 2022/23 reporting year as they have been
subject to review in recent years and errors in data collection and reporting had
been resolved.  Errors were identified during the course of the review and
amended by the relevant officers.  The pro-forma has been updated to reflect the
correct figures for submission to the Improvement Service.

Page 4

3.9 The Strathclyde Concessionary Travel Scheme (SCTS) is founded on the
provision of the Transport Act 1985, which allows authorities to make
concessionary travel schemes in certain circumstances.  The SCTS is
administered by Strathclyde Partnership for Transport (SPT) on behalf of the
SCTS Joint Committee consisting of 12 local authorities to issue travel cards which
entitles the holder to discounted travel by reason of age or disability, and provide
reimbursement of fare reductions on rail, subway and ferry services.  Argyll and
Bute Council operates two ferry routes that qualify for concessionary fares within
the SCTS.  Internal audit are required to provide a certificate of accuracy on an
annual basis to confirm that the details pertaining to the number of concessionary
passengers carried and the equivalent standard fares are consistent with the
quarterly claims for reimbursement of the difference between the concessionary
fare charged and the standard fare.  The data and supporting information for
quarter 4 2022/23 claim was provided to internal audit for review and found to
provide an accurate representation of the number of passengers and value of fares
charged, and the reimbursement value was found to have been calculated in
accordance with the SCTS requirements.  The certificate of accuracy was
therefore issued on 22 June 2023.   
Continuous Monitoring  
3.10 Our continuous monitoring programme is generally focused on transactional type
activity. Standard audit tests are applied which are relevant to each auditable unit.
Control design tests look at whether the controls in place adequately address the
potential risk event. There have been two new findings within the quarter that
require to be reported. 
Table 2: Continuous Monitoring Findings 
Auditable
Area
Areas Tested Issues Identified Management comment /
action
Payroll  Overtime High levels of  Overtime Service short staffed due to
sick leave and vacancies.
The use of agency staff is
being considered.
Payroll Overtime High levels of  Overtime Service short staffed with
additional shifts being picked
up by member of staff
identified. 
3.11 A follow up process is in place whereby management are advised of continuous
monitoring findings and, where appropriate, requested to take remedial action. 
There are currently no outstanding follow-up points arising from previous testing. 
Due to the volume of continuous monitoring tests carried out the decision was
made to report by exception only.     
National Reports  
3.12 A follow up process for national reports is in place whereby management are
advised of national reports published and asked to confirm what, if any, action is
planned as a result of the report.  Table 2 details the national reports issued during
quarter one 2023/24 and due to be reported in quarter two 2023/24.

Page 5

Table 3: National Reports updated 31 July 2023 
National
Report
Issued
To
Detail Management response/ Action
taken
Local
Government
in Scotland
Overview
2023
Chief
Executive
In this year’s Accounts
Commission’s overview
of local Government, it
is reported that demand
and workforce
pressures have been
deepening after the
pandemic and funding
is forecast to reduce in
real terms.
Radical change,
through greater
collaboration, is
urgently needed if
councils are to maintain
services.
ELT has noted the report and no
action is required on this occasion.
Early learning
and childcare
– Progress on
delivery of the
1,140 hours
expansion
Executive
Director
Douglas
Hendry
The Scottish
Government, councils
and partners did well to
increase early learning
and childcare provision
to 1,140 hours a year
per child, despite the
challenge of the Covid-
19 pandemic.  But the
sector remains fragile.
The Education Service has
considered the report and
recommendations contained within
for councils and are content that
we are working towards the
recommendations. The Service
has already met with Scottish
Government representatives on 23
June to discuss the data we hold
and the data that will assist us in
monitoring:- 
– the movement of the ELC
workforce between the public,
private and third sectors
– demand for both funded ELC
and childcare paid for directly by
parents 
– the extent to which children with
additional support needs are not
accessing funded ELC, the
reasons for this, and the extent of
any unmet needs.
We will welcome a more
consistent data set provided
nationally.
Fraud and
Irregularity
Annual Report
2022/23
Executive
Director
Kirsty
Flanagan
A summary of the
cases of fraud and
other irregularities at
public bodies reported
by external auditors for
A copy of the report has been
issued to all relevant staff within
the Council as an opportunity for
learning, prevention, review of
current controls in place and
where appropriate, make any

Page 6

the financial year
2022/23.
changes necessary. This email
was issued on 31 July 2023 by the
CIA. 
National Fraud Initiative (NFI)  
3.13 NFI data matching involves comparing computer records held by one body against
other computer records held by the same or another body to identify potentially
fraudulent claims and payments to be identified.  Note though that the inclusion of
personal data within a data matching exercise does not mean that any specific
individual is under suspicion. Where a match is found it indicates that there may be
an inconsistency which requires further investigation. No assumption can be made
as to whether there is fraud, error or other explanation until an investigation is
carried out.  A reminder process is in place to ensure that matches are reviewed
on a timely basis.  
3.14 The new NFI exercise has been released after some technical delays from the
Cabinet Office.  This exercise will be conducted throughout the year by officers and
matches checked and closed accordingly.  NFI have announced more data
releases in the coming month and any matches will be addressed when these
become available.  The current NFI matches are below in the NFI section of this
report. The CFT are reviewing the information received from the NFI matching
service, work has commenced to follow these up locally.  Existing users have been
reviewed and new users added where requested, all users have been informed
that matches are available for review and progress will be monitored monthly by
the Counter Fraud team and reported quarterly to the Audit and Scrutiny
Committee.   
Table 4: National Fraud Initiative Progress at 14/08/2023
Operation
al Area
Total
Matches
Recommende
d/Very High /
High Risk
Matches
Matches
Complete 
*
WIP
Match Description
CT to Elect
Register 
1155 0 1155 0 CT records to Electoral Register/
other data sets to ensure discount
awarded to only those living alone
aged over 18, taking into account
disregarded occupants.  (CT to
other Datasets will not be
progressed further due to poor
quality data)
CT rising
18s 
208 0 208 0
Housing
Benefits
20  11 19 0 HB records to records in other
authorities / other datasets
including student loans, payroll
and pensions to identify
undeclared income and capital.
Payroll 143 2 2 0 Payroll records to other datasets
including other payrolls and
pensions to ensure employee is
not receiving additional income.
Blue
Badges
238 204 184 0 Blue badge records to DWP data
to identify deceased claimant with
valid badge.

Page 7

Housing
Waiting list
233 217 179 0 Housing waiting list records to
other organisations HBCTR and
tenant data to identify
undisclosed changes in circs or
false info.
Council
Tax
Reduction
281 160 280 1 CTR records with records in other
authorities / other datasets
including; student loans, payroll
and pensions to identify
undeclared income and capital
Creditors 589 0 26 0 Analyses Creditors data to
identify possible duplicate
vendors and payments, VAT
errors or fraud and multiple
vendors sharing a bank account.
Procureme
nt
38 0 36 0 Payroll records to Companies
House and creditors data to
identify employees who appear to
have a personal interest in a
company that the authority has
traded with. 
* Work in Progress 
Overall Summary of Matches 
Matches
Complete
Work In
Progress
Cleared Frauds Errors Total
Value 
£
Recovering Recovering
Value 
£ 
1597 1 1597 0 92 0 0 0 
Internal Audit Development  
3.15 The table below details progress against the action points in our Internal Audit
development plan.  
Table 5: Internal Audit Development Key Actions: updated 22/6/23 
Area For
Improvement
Agreed Action Progress
Update
Timescale
Review Continuous
Monitoring
Programme
Continuous monitoring tests will be
reviewed following audit of Debt
recovery to assess value of existing
tests carried out. 
Consider adding test to review date
taken to process invoices from date of
receipt within the Council (not at
Creditors)
In progress October
2023
Update Internal Audit
Manual in include
evaluation of internal
audit reports against
the Local Government
(Scotland) Act 1973
exemption criteria.
Add paragraph to the IA Manual to
evaluate whether reports being
submitted to committee should be
considered for exemption under the
Local Government (Scotland) Act
1973.  
In progress March 2024

Page 8

3.16 Internal Audit scorecard data is available on pyramid. The indicators reported are
aligned to those for internal audit in the Financial Services service plan.  All
indicators are shown as currently being on track.   
Table 6: Internal Audit Team Scorecard  
Internal Audit Team Scorecard 2023– 24 – FQ1 23/24 (as at June 2023)
BO115 We Are Efficient And Cost Effective    
Internal Audit Level of Satisfaction
Actual  100% G 
Target 80%
Review of Strategic Risk register
Status On Track G 
Target On Track
Percentage of audit plan completed
Status 100% G 
Target 100%
Percentage of audit recommendations accepted by
management
Actual  100%
G
Target 100% 
4 CONCLUSION  
4.1 The 2023/24 audit plan is on track and the Counter Fraud Team is continuing with
visits and pro-active work throughout Argyll and Bute.  
5 IMPLICATIONS
5.1 Policy - Internal Audit continues to adopt a risk based approach to activity
5.2 Financial –None
5.3 Legal –None
5.4 HR – None
5.5 Fairer Scotland Duty – None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty – None
5.6 Climate Change – None 
5.7 Risk – None
5.8 Customer Service – None 
For further information please contact Internal Audit (01546 604108)
Paul Macaskill
Chief Internal Auditor
14 September 2023