Argyll and Bute Council
Internal Audit Report
October 2023
Final 
High Medium Low VFM
Number of
Findings
0 0 2 3 
Fleet Management
Hire of Vehicles
Audit Opinion: Reasonable

Page 2

2 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023 
Contents 
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 4
3. Detailed Findings ............................................................................................................................ 5
Appendix 1 – Action Plan ....................................................................................................................... 9
Appendix 2 – Audit Opinion ................................................................................................................. 12 
Contact Details 
Internal Auditor: David Sullivan 
Telephone:  01546 604125 
e-mail:   david.sullivan@argyll-bute.gov.uk 
www.argyll-bute.gov.uk

Page 3

3 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
1. Executive Summary
Introduction
1. As part of the 2023/24 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2023, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal control and governance in relation to hire of vehicles.
2. The audit was conducted in accordance with the Public Sector Internal Audit Standards (PSIAS)
with our conclusions based on discussions with council officers and the information available at
the time the fieldwork was performed.  The findings outlined in this report are only those which
have come to our attention during the course of our normal audit work and are not necessarily
all the issues which may exist.  Appendix 1 to this report includes agreed actions to strengthen
internal control however it is the responsibility of management to determine the extent of the
internal control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. A review of Fleet Management – Hire of Vehicles has been planned as part of the 2023/24
Internal Audit programme. 
5. Arrangements for all vehicles and plant hired to the Council are made via the internal hire desk.
The Council owns or leases approximately 600 fleet assets and supplements this by hiring a
variety of vehicles ranging from cars to specialist trucks.  The total value of external hires for the
financial year ending 31st March 2023 was £5.6m against a budget of £4.8m.  A number of these
hires are attributed to an increased capital programme which has required additional items
necessary for operational delivery.
6. The volume of fleet vehicles, plant and equipment owned by the Council has reduced due to lack
of capital to replace items that are no longer viable to maintain, therefore spot-hire is used to
support front line service operations.  The current financial pressures on departments
necessitates that all hires must be absolutely necessary and not be used as a solution to
inadequate resource planning.
7. The Council has in place a framework arrangement with Scotland excel who negotiate
procurement contracts with vehicle/plant hire suppliers.
Scope 
8. The scope of the audit was to review the arrangements for the authorisation and use of hire
vehicles, establishing whether best value is achieved as outlined in the Terms of Reference
agreed with the Fleet performance Manager Services on 10th July 2023.

Page 4

4 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
Risks
9.  The risks considered throughout the audit were:
 Audit Risk 1: There is no guidance document in place for external hire vehicles
 Audit Risk 2: External hires are not authorised
 Audit Risk 3: Best value is not achieved
 Audit Risk 4: Appropriate arrangements are not in place for performance monitoring and
reporting
Audit Opinion
10. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
11. Our overall audit opinion for this audit is that we can take a reasonable level of assurance.  This
means that internal control, governance and the management of risk is sound.  However, there
are minor areas of weakness which put some system objectives at risk and specific elements of
residual risk that are slightly above an acceptable level and need to be addressed within a
reasonable timescale.
Recommendations
12. We have highlighted two low priority and three value for money recommendations where we
believe there is scope to strengthen the control and governance environment. These are
summarised below:
 Hire Desk Policy document to be updated and agreed to ensure the Policy reflects
current practice.
 Contractual arrangements should be recorded for all hires in the Tranman Fleet hire
system. 
 Authorisation to hire document should contain evidence that the service has checked
and confirmed that suitable fleet items under their control are not already available
prior to hire request.  
 Reporting arrangements should be introduced to provide explanations where hired
items exceed an agreed return date.
 Mechanisms for evaluating financial options such as operating lease or outright
purchase should be considered for hires substantially over their return date.
13. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1. 
2. Objectives and Summary Assessment
14. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.

Page 5

5 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
Exhibit 1 – Summary Assessment of Control Objectives 
Control Objective Link to Risk Assessment Summary Conclusion
CO1 There is appropriate
arrangements/guidance
in place for external
hires
Audit Risk 1 Reasonable Fleet services have in place a Hire
Desk Policy that outlines
guidance/procedures that should
be followed in regard to hire of
vehicles/plant. The document was
last reviewed in 2010 and should
therefore be updated to ensure it
reflects current practice.
CO2 All external hires are
properly authorised
and best value is
achieved
Audit Risk 2
Audit Risk 3
Reasonable External hires have been properly
authorised prior to hire. Checks
that items are not already available
for use within the service should
be evidenced on authorisation
document. Where appropriate,
hires are contracted for using the
Scotland Excel contractual terms
and conditions. Mechanisms for
evaluating financial options such as
operating lease or outright
purchase should be considered for
hires substantially over their
expected return date.
CO3 Appropriate
arrangements are in
place for performance
monitoring and
reporting
Audit Risk 4 Substantial Reporting on reasons where hires
substantially exceed their expected
return date should be
implemented. Monthly
reconciliations are carried out to
ensure that all hires captured on
Tranman are properly recorded in
the financial ledger.
15. Further details of our conclusions against each control objective can be found in Section 3 of this
report.  
3. Detailed Findings
There is appropriate arrangements/guidance in place for external hires
16. Fleet services have in place a Hire Desk Policy that outlines guidance/procedures that
should be followed in regard to hire of vehicles/plant.  The Policy outlines
recommendations such as :
 only authorised personnel can request the hire
 departments should ensure that the item requested for hire isn’t already
available within the organisation

Page 6

6 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
17. The Hire Desk Policy was last reviewed in 2010.  The current Policy should be reviewed
and agreed to ensure it reflects current arrangements. 
Action Plan 1
All external hires are properly authorised and best value is achieved
18. All external hires are initiated via an authorisation form signed by the authorised
manager.  The largest percentage of hires originate from Roads and Infrastructure
services i.e. accounting for approximately 95% of all hires. 
19. A desktop exercise was carried on a sample of 30 hires chosen at random to ensure that: 
 all hires have been properly authorised
 prior to initiating the hire, services establish whether the required item is already
under their control and available to use (as required in the current Policy
document).
All hires had been properly authorised prior to hire, however, there was no evidence
that services had established if the item required was already under their control and
available to carry out the work required as recommended in the Hire Desk Policy.
Consideration should be given to amending the hire authorisation document to include a
section that confirms the necessary checks have been carried out.
Action Plan 3
20. Once approved, external hires are initially captured on the Tranman Fleet Management
System.  The system captures a range of data concerning the hire including:
 contract reference
 description of item hired
 start of hire date
 expected length of hire in days
 date when hire actually ended
 cost centre
 supplier name
 responsible person within Council
 cost of hire
 contract details e.g. Scotland excel
21. At the time of the review, there were 124 ongoing hires recorded on Tranman, each
with a start date and expected return date recorded.  A review of these ongoing hires
noted that 101 are over their expected return date.  Of the 101: 
 30 were less than 500 days over 
 42 were between 500 and 1000 days over 
 29 were 1000 days or greater over

Page 7

7 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
There is currently no information available that explains the reasons why external hires
are substantially over their expected return date.             
Action Plan 4
22. It is a requirement under the International Financial Reporting Standards (IFRS) that
from 2024 all items on hire over 365 days must be transferred to the balance sheet and
depreciated over their useful life.  A review of all ongoing hires currently over 365 days
was carried out and those items are summarised below:
Year initially hired Example of items hired  Total ongoing hire
cost to Council 
2013 2 Telehandlers £207,767
2014 Excavators £262,549
2015 Excavator/Lorry £419,462
2016 Small Excavator £86,345
2017 None £0
2018 5 Tippers>3,500 kg £217,760
2019 6 Tippers> 3,500kg £161,168
2020 Welfare Vans £480,930
2021 Panel Vans<=3,000kg, 
7 Tippers>3,500kg, 2 Telehandlers
£217,596
2022 Panel Van, Tipper, Sweeper £47,914
Total cost to the
Council 
£2,101,491 
There is currently no mechanism that triggers an exercise where Financial Services
considers whether cheaper long term options are available such as an operating lease or
to purchase the item outright.        
Action Plan 5
23. The Council participate in the Scotland Excel Fleet Hire Framework agreement for
vehicle and plant hire.  The framework covers a complete range of vehicles and plant
which meet the council’s hiring needs and where possible the hire desk will use suppliers
who are signed up to this Framework.  The benefits are for example :
 agreed hire rates for a wide range of plant and equipment used by the Council
such as refuse collection vehicles, Gritters, plant excavation and sweepers
 Scotland Excel terms and conditions (T&C’s)
 added value benefits agreed with individual suppliers
24. All hires taking place over the last 18 months were reviewed to identify what percentage
used the Scotland Excel Framework, the information provided shows that approximately
64% by value of all hires take place utilising this Framework.  In cases where the
Framework was not applied, discussions with management confirmed that these cases
arose where the local supplier was not signed up to the Framework and best value
would not be achieved by sourcing elsewhere.  In these instances the general Council

Page 8

8 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
terms and conditions are applicable.  It was noted a small number of hires on Tranman
did not indicate which contractual arrangement had been applied to a particular hire.          
Action Plan 2
Appropriate arrangements are in place for performance monitoring and reporting
25. All relevant departments are sent a list of ongoing hires and it is the responsibility of the
service to review the list and advise the internal hire desk of any item that should be
taken off hire.  Internal audit confirmed that whilst departments are sent a list of
ongoing hires there is no reporting arrangement in place for departments to explain why
hires exceed expected return dates, e.g. hires exceeding 500 days as detailed in
paragraph 21 above. 
Action Plan 4
26. Hire of vehicles, plant and equipment for roads contracts is charged directly from
Tranman to the specific contract via the TOTAL Costing System (as well as the financial
ledger).  Where items are unused but still on hire for roads contracts, the downtime is
charged directly to an overhead account.  In the financial year 2022/23 roads contracts
were charged £2.3m in fleet hire charges, £100k of this related to time where the hire
was not utilised directly against roads contracts and was therefore charged to an
overhead account.  This relates to an efficiency of 95.7%. 
27. External hires are initially recorded within Tranman, from where a weekly feeder file is
generated and electronically transferred to the general ledger.  Monthly reconciliations
take place to ensure that all hire costs are properly reflected in the financial ledger.
Internal audit confirmed that the monthly reconciliation is properly carried out.

Page 9

Appendix 1 – Action Plan 
No Finding Risk Agreed Action Responsibility / Due Date
Low 1
Hire Desk Policy 
The Hire Desk Policy was last reviewed in 2010.  The
current Policy should be reviewed and agreed to
ensure it reflects current arrangements. 
Current practices may no
longer be aligned to the
content of the agreed Hire
Desk Policy.
Fleet Services confirm that the
Policy document will be
reviewed and updated where
appropriate.
Performance Manager,
Fleet , Roads and
Infrastructure Services 
31st December 2023
Low 2
Contractual arrangements 
A number of hired items on Tranman did not indicate
which contractual arrangement had been applied to
the hire. 
Failure to note which
contractual terms and
conditions apply to a hire
may lead to best value not
being achieved
Going forward all hires will
reflect the contractual
arrangements agreed.
Performance Manager,
Fleet , Roads and
Infrastructure Services 
31st December 2023
VFM 3
Checking of availability of items within Council prior
to externally hiring. 
There was no evidence that services had established
that an item already under their control was available
within the Council prior to hiring.
Consideration should be given to amending the hire
authorisation document to include a section that
confirms this check has been carried out. 
Failure to check the
availability of
items/vehicles within the
council prior to externally
hiring may lead to best
value not being achieved.
Fleet Services will amend the
document and advise relevant
departments of the change.
Performance Manager,
Fleet , Roads and
Infrastructure Services 
31st December 2023
VFM 4
External hires exceeding their expected return date 
Of the 124 current ongoing hires, 101 have exceeded
their expected return, 29 items were over the return
date by more than 1000 days. 
There is no document available that explains the
reasons why these items have substantially exceeded
their expected return date. 
Failure to report on why
hires exceed their expected
return date may lead to
best value not being
achieved
Roads and infrastructure
services are currently under a
review of all services and the
recommendation will be
assessed as part of the review.
Operations Manager,
Roads and
Infrastructure Services 
31st March 2024

Page 10

10 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023 
No Finding Risk Agreed Action Responsibility / Due Date
VFM 5
Evaluating whether long term hires should be leased
or purchased outright 
There is currently no mechanism that triggers an
exercise where Financial Services considers whether
cheaper long term finance options are available such
as an operating lease or for the Council to purchase
an item outright.
In cases of long term hires
failure to assess possible
cheaper financial hire
arrangements may lead to
best value not being
achieved. 
Roads and infrastructure
services are currently under a
review of all services and the
recommendation will be
assessed as part of the review.
Principal Accountant,
Roads and
Infrastructure Services 
31st March 2024

Page 11

11 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows: 
Grading    Definition
High  A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error. 
Medium 
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.  
Low  Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives. 
VFM  An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).

Page 12

12 
Argyll and Bute Council – Internal Audit Report, External Hire, October 2023
Appendix 2 – Audit Opinion 
Level of Assurance  Definition 
High 
Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial 
Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable 
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk. 
Limited 
Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance 
Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues.