ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  13 June 2024 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2023-24 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these in a database and, on a
monthly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 31 March
2024 including information on actions where the agreed implementation
date has been rescheduled.   
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 31 March 2024. 
3.2 Appendix 1 provides further detail on actions that have either been delayed
and rescheduled or superseded.

Page 2

Table 1 - Actions Due by 31 March 2024 
SMT/Service
Complete
Delayed/
Rescheduled
Superseded
Evidence
Required
Total
Internal Audit
DH – Commercial Services 3 4 0 0 7
DH – Education Performance & Improvement 1 0 0 0 1
DH – Legal & Regulatory Support 1 0 0 0 1
KF – Customer Support Services 4 0 0 0 4
KF – Development & Economic Growth 0 4 0 0 4
KF – Financial Services 6 7 1 0 14
KF – Roads & Infrastructure Services 1 2 0 0 3
H&SCP (IJB) – Finance & Transformation 0 2 0 0 2
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
0 2 0 0 2
External Audit
Nil     
TOTAL 16 21 1 0 38 
Table 2 - Actions due after 31 March 2024 
SMT/Service
Complete
Delayed/
Rescheduled
No Response
On Course
Evidence
Required
Total
Internal Audit
DH – Commercial Services 0 0 0 4 0 4
DH – Education Performance & Improvement 0 0 0 1 0 1
KF – Customer Support Services 1 1 0 1 0 3
KF – Development & Economic Growth 0 0 0 3 0 3
KF – Financial Services 0 4 0 0 0 4
KF – Roads & Infrastructure Services 1 0 0 16 0 17
H&SCP (IJB) – Finance & Transformation 0 0 0 2 0 2
H&SCP (IJB) – Strategic Planning & Performance 0 0 0 2 0 2
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
2 0 0 0 0 2
External Audit
Nil      
TOTAL 4 5 0 29 0 38

Page 3

4.0 CONCLUSION 
4.1 Satisfactory progress continues to be made implementing audit actions. 
5.0 IMPLICATIONS 
5.1 Policy – None 
5.2 Financial – None 
5.3 Legal – None 
5.4 HR – None 
5.5 Fairer Scotland Duty – None 
5.5.1 Equalities – protected characteristics – None
5.5.2 Socio-economic Duty – None
5.5.3 Islands – None 
5.6 Climate Change – None 
5.7 Risk – None
5.8 Customer Service – None
5.9 The Rights of the Child (UNCRC) – None 
Paul MacAskill
Chief Internal Auditor
13 June 2024                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Action Plan Points Delayed & Rescheduled and Superseded

Page 4

Appendix 1 - Action Plan Points Delayed & Rescheduled or with Superseded 
Action Plan Points Due by 31 March 2024 
LOW
COMMERCIAL SERVICES 
Compliance Review (Period Products) 
5. Monitoring of onsite provision 
The process for auditing of sites to ensure
products remain available in an equitable way
has still be developed. There are no
records/evidence to support that checks are
carried out to ensure  that products, adequate
storage and disposal facilities and branding  are
actually on site and available in one or more of,
unisex, male, females and disabled toilets in
Council establishments. 
Monitoring process will be
implemented with an
implementation date of March
2024. 
31/03/2024
30 Sep 2024 
Location survey was carried out
- any locations that identified as
low/no stock were sent stock.
Locations that required
branding packs were sent packs.
Link to location survey form -
My Tribe Period Product
Location Survey (jotform.com)
This is an annual process. 
Delayed and Rescheduled 
Project Lead – Period 
Products 
Medium
COMMERCIAL SERVICES 
Compliance Review (Period Products) 
6. Procedure Notes 
The Project Lead post is a temporary post, until
December 2023, and with the exception of a
draft stock ordering note, there are no
procedure notes. As a priority procedure notes
should be written for all key tasks, include
detailing what the monitoring, evaluation are
reporting requirements. 
Ongoing – implemented by January
2024 
31/01/2024
30 Sep 2024 
Due to changes within the
management team, the current
process are being reviewed.
The new post of Business
Support Officer will continue to
have responsibility for the
provision of free period
products within Argyll and Bute
with Admin team support for
processing orders. 
Delayed and Rescheduled 
Project Lead – Period 
Products 
Low
COMMERCIAL SERVICES 
Compliance Review (Period Products) 
7. Engagement 
Given this is new statutory requirement there
would be benefit to engaging internally with
Engagement is ongoing, informally
but will be formalised as part of the
new monitoring process as per
point 5. 
31/03/2024
30 Sep 2024 
Engagement with partners
carried out as per point 5. Public
consultation carried out 2023.
No evidence of internal
engagement. 
Delayed and Rescheduled
Project Lead – Period 
Products

Page 5

other services and staff involved in the various
processes to establish any issues arising and
ensure procedures are efficient. 
Medium
COMMERCIAL SERVICES 
Compliance Review (Period Products) 
8. Monitoring and evaluation  
Limited evidence of monitoring and evaluation
arrangements was provided during this review.
Management should undertake a review of the
monitoring and evaluation processes to ensure
that they are in line with the Scottish
Government Evaluation Strategy. 
Annex D on SGES – Procedure
notes will be considered to cover
how to gather data as per
document. 
31/03/2024
30 Sep 2024 
Review of Annex D carried out
in relation to types of questions
to ask:
Q1: How much does delivering
access to free period products
cost? - reviewed as part of the
bid-in fund application.
Q2: What level of demand is
there for period products? -
Reviewed within bid-in fund
application.
Q3: How is access to free period
products being provided by
local authorities and education
providers? - reviewed as part of
ongoing management and via
the guidance notes of the act.
Q4: Does delivery of access to
free period products meet user
needs? - Reviewed as part of
the 2023 consultation.
Q5: What impact did the
availability of free period
products have on users? –
option to add
comments/feedback as part of
ordering process. 
Delayed and Rescheduled 
Project Lead – Period 
Products 
Low
DEVELOPMENT & ECONOMIC GROWTH
PLANNING 
3. Customer Charter 
The framework document for
2022/23 stated “A review and
update of the Development
Management Customer Service
31/12/2023
31/03/2024
30 Jun 2024 
Delayed due to other
operational pressures on staff
time during FQ4 2023/24 - in
particular the replacement of
Development Manager

Page 6

Planning have in place a customer charter,
however it was last reviewed in 2012 and
requires to be updated as it does not reflect
current practice. 
Charter will also be undertaken
during 2023/24.” 
LDP with LDP2 in Feb 2024.
Delayed until end of FQ1 24/25. 
Delayed and Rescheduled 
Low
DEVELOPMENT & ECONOMIC GROWTH
PLANNING 
4. Service level Customer User Forums
Customer User Forums have previously been
held regularly however currently customer
forums are not being undertaken. 
The Planning Performance
Framework for 2022/23 states that
“it is intended to reinitiate Service
level Customer User Forums during
2023/24”. 
31/12/2023
31/03/2024
30 Jun 2024 
Delayed due to pressures from
operational commitments, in
particular the replacement of
LDP with LDP2 during Feb 2024.
Customer engagement has
however been undertaken
during March 2024 to establish
customer appetite for a User
Forum and to ascertain what
format this will be provided in
(online/hybrid/in person) and
the content of the forum. It is
expected that the forum will be
held during FQ1 24/25. 
Delayed and Rescheduled 
Development Manager 
Low
DEVELOPMENT & ECONOMIC GROWTH 
Private Sector Housing Grants & Adaptions
2. The Scheme of Assistance 
The Councils Scheme of Assistance (SoA) which
was introduced under the duties and powers set
out in the Housing (Scotland) Act 2006, and sets
out the strategy of support for owners to
address properties which are Below Tolerable
Standard (BTS) and in disrepair does not contain
up to date information and should be updated
after the outcome of the national policy review. 
As per Local Housing Strategy
2022-2027 Action Plan; The
Scheme of Assistance, will be
revised in 2023, after the outcome
of national policy review on
adaptions. 
31/12/2022
30/06/2023
31/03/2024
30 Sep 2024 
Over the last 3 months work has
continued with updating the
Scheme of Assistance. The
Housing Team have taken the
opportunity to benchmark with
other Scottish Local Authorities
and have also worked closely
with the HSCP to ensure that all
current legislation has been
addressed within the revised
document. 
The revised Scheme of
Assistance is now at final draft
stage and is currently
undergoing scrutiny by the
Housing Team and relevant
Team Lead - Housing 
operations

Page 7

HSCP partners prior to
progressing to committee cycle
for approval. I have updated the
revised completion date to
30/09/24 to allow time for the
Scheme of Assistance to
complete the approval cycle.   
Delayed and Rescheduled 
Low
DEVELOPMENT & ECONOMIC GROWTH 
Private Sector Housing Grants & Adaptions 
3. Procedure Notes and Shared Documents
While the vast majority of requirements are
included  there would be benefit to updating
these to reflect current  working practices,
which have evolved due to hybrid  working
arrangements and the digitalisation of records. 
Consideration should be given to creating a
checklist to ensure consistent application of
processes. 
Procedures and documents will be
reviewed and updated. Checklists
to be drawn up and introduced
when updating the procedures. 
31/12/2022
30/06/2023
31/03/2024
30 Sep 2024 
Housing Officers, HSCP and Care
and Repair have progressed on
updating policies and
procedures. The HSCP are in the
final stages of updating their
Criteria and Practice Guide and
the Housing Service is currently
updating the Scheme of
Assistance. In addition, the
Housing Service has taken the
opportunity to revise all internal
admin procedures relating to
Private Sector Housing Grants. A
meeting has been scheduled for
30th May 2024 to allow relevant
Housing, HSCP and Care and
Repair staff to meet and go
through the procedure
documents. As this action links
to the action relating to the
Scheme of Assistance review
this has also been updated to
September 2024. 
Delayed and Rescheduled
Team Lead – Housing
Operations
Medium FINANCIAL SERVICES 
CAPITAL MONITORING
Capital Planning and Management
Guide to be updated once the
Capital Strategy has been approved
31/03/2022
30/09/2022
The Guide has been updated
but requires consultation with
the Head of Commercial
Head of Commercial
Services/Finance
Manager

Page 8

1. Capital Programme Planning & Management
Guide 
The Council’s Capital Guide has not been revised
since 2018 and requires a review to ensure it
reflects current working practices and provides
appropriate support to officers involved in the
capital monitoring process. The Council is
currently developing a new Capital Strategy
which is to be presented to the Policy and
Resources Committee in August 2021 and we
recognise that a review of the Guide should be
conducted after the Strategy has been finalised
to ensure the two documents complement each
other and. The Guide could also benefit from
being linked to, or referencing, other relevant
Council processes, in particular the Project
Management section on the Hub. 
to ensure the two are aligned and
provide clarity. 
31/12/2022
31/03/2023
30/09/2023
31/12/2023
31/03/2024
31 Mar 2025 
Services as it has a lot of
duplication with the new Capital
Investment Strategy and it may
be possible to streamline this
guide. 
A significant update is required
to the guide from not only
finance but other services of the
council with heavy involvement
from the Capital Investment
Board. With changes imminent
on the capital plan with new
groupings and a review of the
block allocations in the pipeline
this document will evolve over
the coming months. 
Delayed and Rescheduled 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
5. Debtors Procedure Manual and Processes
Finding:  There is insufficient evidence to
determine whether all Services receive details
of invoices being written off.  
Recommendation:  Services should be sent this
information. 
A thorough review of Sundry Debt
write-off procedure to be carried
out by the working group as part of
the overall update of the Sundry
Debt Procedures.  Reporting and
communication with stakeholders
is being reviewed by the working
group. It is anticipated that reports
of debt written off will be sent to
departments as part of a standard
suite of reporting for discussions at
quarterly meetings this will be
confirmed within the reviewed
Sundry Debt Procedure Manual. 
31/12/2023
31/03/2024
30 Sep 2024 
Departments get a list of debts
to be written off and are asked
for approval. A copy of the Q4
list 23/24 is attached and the
column on the right hand side
shows that the details are
shared. Where a debt has
prescribed as it hasn't been
collected for 5 years, we can no
longer legally pursue the
amount, departments are not
asked to approve write-off in
these circumstances because
the Council has no other option.
More evidence of the exchange
between legal services and
departments re the write-off list
can be supplied if required.
Quarter 4 is not complete as
Revenues and  Benefits
Manager

Page 9

yet, write off process still to be
completed. Departmental load
unforeseen. 
Delayed and Rescheduled 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
6. Debtors Procedure Manual and Processes
Finding: While there is a pdf version of the
authorisation and the spreadsheets containing
the individual invoices, there are concerns that
different sources of data are used during the
write off process as there is more than one
version of the write off spreadsheet.  
Recommendation:  Checks should be carried out
to ensure that Original Data is retained with
records kept of any alteration to the Source
Data. 
There must only be one version of
the write-off spreadsheet. This can
be shared between Finance and
Legal Services on MS Teams. 
Changes can be made to the
document by Legal or Finance
before it is presented to senior
management for final
consideration. 
31/12/2023
31/03/2024
30 Sep 2024 
We have been provided with
the only version of the write-off
spreadsheet. Once the
Executive Director has written
off the debt the spreadsheet
will be passed to Finance so that
the write-off can be keyed to
the Debtors system and the
departments will also get the
full list of debt written off.  Ok
to delay as per comments in
action number 5 above. 
Delayed and Rescheduled 
Revenues and  Benefits
Manager 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
11. Performance Monitoring and Reporting
Findings:  There are no performance measures
in place to monitor recovery of Sundry debt.
Quarterly meetings with Legal Services to
discuss recovery of Sundry Debtors were
postponed during the pandemic, these have not
been reinstated.  
Management information relating to Sundry
Debtors is not made widely available.  
Aged debtors reports are only sent to Services
who ask. 
Performance monitoring and
reporting will be a key part of the
Sundry Debt review undertaken by
the working group led by the Head
of Legal Services.  It is anticipated
that proposals for quarterly
meetings and the reporting suite
will be developed and
implemented by March 2024. 
31/10/2023
31/03/2024
30 Sep 2024 
Policy paper going to P&R
includes an appendix on role of
the Debt Champions covering
their duties and including
details of a data dashboard that
they will be receiving quarterly.
Once approved meetings will be
held quarterly from July 2024.
Delayed P&R and unforeseen
workload. 
Delayed and Rescheduled 
Revenues and  Benefits
Manager

Page 10

Reporting is only to the Financial Services
Management Team via Highlight Reports. 
Recommendations:  Appropriate performance
measures should be put in place to monitor
recovery of Sundry Debt.  The meetings with
Legal Services should be re-instated and
consideration given to which committees and
meetings should receive reports regarding the
management and recovery of Sundry Debtors. 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
18. Debtors Procedure Manual and Processes
Finding: Management information, detailing
outstanding invoices, should be provided on a
monthly basis to a Single Point of Contact in
each Service. This is not happening, currently
only those Services who request the
information are being sent the reports. 
Recommendation:  Reports should be provided
to all Services. 
This working group review of
Sundry Debt will include the key
issue of reporting, this aspect of
the process will be vastly improved
in the future.  A suite of reports will
be developed, the identification
departmental debt champions
reinstated and quarterly meetings
setup for all relevant stakeholders. 
31/12/2023
31/07/2024
30 Sep 2024 
On course for completion, new
policy and procedures to be
considered by P&R in May, new
Debt Champions and meetings
in place for June/July.
Delayed due to revised P&R
dated and unforeseen
workload. 
Delayed and Rescheduled 
Revenues and  Benefits
Manager 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
20. Debtors Procedure Manual and Processes
Finding: Insufficient evidence to conclude
whether supporting back up evidence of
invoices being written off is retained, leading to
concerns that full records may not be retained. 
Recommendation:  
Checks should be carried out to ensure that
appropriate back up is retained. 
Back up evidence re write-off
should be retained, the write-off
lists and any backup
documentation held together in
MS Teams group for example. This
could be further enhanced if we
can use EDMS for storage of the
information. If we can move this
onto Civica’s Electronic Document
Management System (EDMS)
Comino this will make collation of
information, document retention
and disposal so much easier and
more efficient. Discuss with Civica,
30/09/2023
30/10/2023
30/06/2024
30 Sep 2024 
Checks have been carried out
relating to items being
proposed for write-off for
2023/2024. An area of Civica
W3 has been identified and will
be used as an area to store
write-off and backup from
2024/2025 onwards in line with
our stated retention dates in
our Information Asset Register. 
Delayed until system updated
by developer. 
Delayed and Rescheduled
Revenues and  Benefits
Manager

Page 11

re the use of the Electronic
Document Management System
for these purposes and overall case
management. Improve the file
structure within the network with
the supporting documentation. 
Expected timescales for progress -
Civica EDMS System Admin
Discussion with Supplier by May
2023 - NDR and Income Manager
to review the file structure on the
network - Revenues and Benefits
Manager Evaluation of options by
July 2023 then NDR and Income
Manager to review the file
structure on the network. Revs and
Bens Manager Development and
Implementation of Solution March
2024 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
21. Performance Monitoring and Reporting
Invoices are raised using Civica Debtors system
which does not interface with the Iken System
used by Legal Services. 
The process for the raising of and
the recovery Commercial Waste
debt and Residential Care debt will
be considered as part of the
Review of Sundry Debt.  There was
efforts made previously by staff in
D&I and Finance to integrate
Commercial Waste onto the Sundry
Debt system but it failed. 
30/06/2023
31/12/2023
31/03/2024
30 Sep 2024 
No interface can be developed
between Civica Debtors and
IKen. We have decided to create
a space in Civica W3 (Comino)
which will hold all of the
relevant information. Work has
commenced on this and should
be complete in June 2024. 
Delayed until system updated
by developer. 
Delayed and Rescheduled 
Head of Legal &
Regulatory Services. 
Medium
FINANCIAL SERVICES 
Payroll Processes 
3. Processes 
Using the above process flow 
completed for action 1, conduct a 
value chain analysis exercise to 
identify points of duplication and 
any other inefficiencies in the 
31/12/2023
31 Jul 2024 
This action has now been
superseded by the planned
move from ResourceLink to the
new iTrent HR and Payroll
System. The project team is
Payroll & Pension
Officer and Team
Leader - HR Service
Centre

Page 12

Whilst there are well understood processes and
procedures in place for the management of
payroll updates, the whole process is hugely
inefficient. A new HR and payroll system is
planned for the future to replace the existing
systems. 
current process. Redesign the
process to remove the
inefficiencies identified to optimise
the use of staff and speed the
process up. 
working on the processes for
the new system which will
incorporate workflow
functionality which was not
previously available in
ResourceLink. No further work
will be undertaken to review
the ResourceLink processes as
the system is planned to be
decommissioned over the next
4 months. A review would be
recommended when the new
system is set up. 
Superseded 
VFM
ROADS & INFRASTRUCTURE SERVICES 
External Hire 
3. External hires exceeding their expected
return date  
Of the 124 current ongoing hires 101 of these
have exceeded their expected return. In
addition 29 items were over the return date by
more than 1000 days. There is no document
available that explains the reasons why these
items have substantially exceeded their
expected return date. 
Roads and infrastructure services
are currently under a review of all
services and the recommendation
will be assessed as part of the
review. 
30/06/2023
31/12/2023
31/03/2024
31 Aug 2024 
The service will put in place an
action plan with the fleet
manager to reduce the hires
exceeding 24 months. A
reporting dashboard will be
developed with triggers to
remind the service to review
the list of ongoing hires and
advise of any items that should
be taken off hire and
information will be provided to
explain the reasons for any
external hires that are
substantially over their return
date. Given the nature of
Operations works, there will
always be a requirement for
external hires to ensure the
delivery of works programmes
such as the roads
reconstruction programme.
Operations Manager,
Roads and
Infrastructure Services

Page 13

Delayed and Rescheduled 
VFM
ROADS & INFRASTRUCTURE SERVICES 
External Hire 
4. Evaluating whether long term hires should
be leased or purchased outright  
There is currently no mechanism that triggers
an exercise where “finance” considers whether
cheaper long term finance options are available
such as an operating lease or for the Council  to
purchase an item outright 
Roads and infrastructure services
are currently under a review of all
services and the recommendation
will be assessed as part of the
review. 
31/03/2024
31 Dec 2024 
This issue should be picked up
as part of the RIS review which
is currently being undertaken
and more time is required for
this action. 
Delayed and Rescheduled
Principal Accountant,
Roads and
Infrastructure Services 
High
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds 
4. Safe 
Detail Restricted 
Detail Restricted  31/03/2023
30/06/2023
31/08/2023
31/10/2023
31/03/2024
30 Jun 2024 
Delayed and Rescheduled SW Admin Manager 
High
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Client Funds 
6. Unaccounted Funds
Detail Restricted. 
Detail Restricted  30/06/2023
31/08/2023
31/12/2023
31/03/2024
30 Sep 2024 
Delayed and Rescheduled SW Admin Manager 
High
FINANCE/TRANSFORMATION 
Customer Service Centre - H&SCP
Provided by key officer HSCP
management will work with the
CET team to determine the best
way to approach the current
problem and implement the
30/06/2023
30/09/2023
31/03/2024
30 Jun 2024 
In progress updated external
sites and trialling approach with
a Dunoon based integrated
team to act as champions based
on excellent communication
Business Improvement 
Manager

Page 14

1. Failure to ensure CET have up to date Service
information 
There is concern that some teams within HSPC
are not fully engaging with CSC, despite
repeated requests from Senior Managers to
review their information. In addition, the Duty
rotas and contact details on the HSPC
SharePoint are not always up to date. HSCP
must engage with CET to review the online and
offline information available to agents and
customers to ensure it is accurate, up to date
and reflects current team structures and duty
rotas. 
correct solution agreeable by HSCP
and CSC. 
between integrated teams.
Monitoring ongoing time
commitment due to regulated
responsibilities of responsible
officers to ensure we can
prescribe a reasonable time
period for input. 
Delayed and Rescheduled 
VFM
FINANCE/TRANSFORMATION 
Customer Service Centre - H&SCP 
6. Routing of calls to the appropriate channels
Calls for HSPC represent the highest volume of
both calls handled by CSC and transferred to the
Service. The data provided detailing the teams
the calls are transferred to indicates that it may
be more appropriate for properly trained staff
to handle and manage these calls. Contact
Centre and HSCP should analyse whether it is
more efficient to route certain call types on the
HSCP Golden Number directly to HSCP for them
to manage or that specific issues which require
more specialist or detailed knowledge are dealt
directly by HSCP. 
Provided by key officer The service
will engage in discussions with
CET’s Customer Engagement
Manager to ensure that suitable
arrangements are in place which
maximises efficiency and
effectiveness of the handling of
customer contacts and enquiries
via the HSCP Golden Number. 
30/06/2023
30/09/2023
31/03/2024
30 Jun 2024 
In progress updated external
sites and trialling approach with
a Dunoon based integrated
team to act as champions based
on excellent communication
between integrated teams.
Monitoring ongoing time
commitment due to regulated
responsibilities of responsible
officers to ensure we can
prescribe a reasonable time
period for input. Note this is an
ongoing working relationship. 
Delayed and Rescheduled 
Business Improvement 
Manager

Page 15

Action Plan Points Due after 31 March 2024 
Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
Medium
CUSTOMER SUPPORT SERVICES 
Equality and Socio-Economic Impact Assessment 
1. EqSEIA  
EqSEIAs are being undertaken, however, there are
inconsistencies in practice across the Council. A
review of papers submitted to committee and
papers as part of the budget setting process
indicate that a number of EqSEIAs had been
missed. It was noted that other Councils provide
online EqSEIA toolkits for managers to assist them
with the process of completing these. 
Present options for online
EqSEIA toolkit to ELT. 
30/06/2023
31/12/2023
31/03/2024
28 Jun 2024 
This is being worked on and a
proposal for the approach will be
completed by June 2024. 
Delayed and Rescheduled 
Head of Customer
Support  Services 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
1. Corporate Debt Policy  
The Document has not been updated since 2017
and does not reflect the current Council
Organisational Structure nor current working
practices. 
The Revenues and Benefits
Manager will review the
Corporate Debt Recovery Policy
and submit it to a working
group led by the Head of Legal
Services reviewing the Sundry
Debt process for consultation.
The final document will
proceed to October P&R via the
Head of Financial Services and
Executive Director Kirsty
Flanagan’s DMT. 
31/12/2023
31/05/2024
30 Sep 2024 
Document considered by Kirsty
Flanagan's DMT Monday 8 April,
now on way to SMT in advance
of P&R in May. This will now go
to August P&R. 
Delayed and Rescheduled 
Revenues and 
Benefits Manager 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
2. Debtors Procedure Manual and Processes
Finding:  The Debtors Procedure Manual has not
been reviewed since 2017 and does not reflect the
current Council Organisational Structure or current
working practices.  
A working group (“the working
group”), led by the Head of
Legal and Regulatory Services,
will review the Sundry Debt
Procedure Manual, processes
and procedures relating to the
management and recovery of
Sundry debt.  This document
will progress through the
31/12/2023,
31/05/2024
30 Sep 2024 
Procedures will be included in
P&R report for May 2024, should
be developed in full by end of
April 2024.  As per action 1, this
will now go to P&R in August. 
Delayed and Rescheduled 
Revenues and 
Benefits Manager

Page 16

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
Recommendation:  A full review of the processes
and procedures for Sundry Debtors  relating to the
management, arrears, follow-ups and bad debt
write offs should be carried out., then the Debtors
Procedure Manual  should be updated.   
Finding: Management information, detailing
outstanding invoices, should be provided on a
monthly basis to a Single Point of Contact in each
Service. This is not happening, currently only those
Services who request the information are being
sent the reports.  
Recommendation:  Reports should be provided to
all Services.
Council’s DMT to SMT/ELT in a
similar timescale to the
Corporate Debt Recovery Policy
going to P&R (see action 1
above). 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
7. Debtors Procedure Manual and Processes
Finding: The Debtors Procedure Manual does not
mention that the keying of  the Sundry Debtors
Write Offs has two separate stages - first is the 
creating and approving of invoices as written off on
the Debtors  system and second is the manual
journals to be processed to  account for the VAT
element of the invoices written off. The journal
processed in February did not contain all of the
invoices that had been written off. This caused a
difference in the debtors’ element of the VAT
return. While this was a small value it raises
concerns as to whether there is appropriate
monitoring and oversight of the balancing of the
write off, back to the authorised invoices and
values.  
Recommendation:  Checks should be carried to
ensure that there is appropriate monitoring and
This can be added to the
revision of the procedure
manual which will be finalised
in December 2023. NDR and
Income Manager will ensure
the write-offs in the Debtors
system are fully reconciled with
the general ledger position
each quarter. 
31/12/2023
31/05/2024
30 Sep 2024 
Going to P&R in August 2024. 
Delayed and Rescheduled
Revenues and 
Benefits Manager

Page 17

Service, Report, Plan no. & Finding Agreed Action Dates Comment Responsible
Officer
oversight of the balancing of the write off, back to
the authorised invoices and values.  The Debtors
Procedure Manual should be updated to reflect all
stages of the write off. 
Medium
FINANCIAL SERVICES 
MANAGEMENT OF DEBT/DEBT RECOVERY 
8. Raising of invoices and Recovery Routes  
Finding: Invoice inappropriately raised for the
drawdown of grant monies.  Legal Services confirm
this is not a one off.  
Recommendation:  Services should be reminded
that Debtors invoices should not be raised for the
drawdown of grant monies nor to recover income. 
These examples should be
collated and used to support
some internal training that will
be delivered to launch the new
Sundry Debt Procedure
Manual. Training will be
delivered by Finance and Legal
Services to all users of the
Sundry Debt System.
Consideration will be given to
the format of the training,
mandatory e-training for all
current users and new users or
something delivered via MS
Teams. Training to be delivered
to all users by June 2024. 
31/12/2023
31/05/2024
30 Sep 2024 
E-mail issued on 15 April 2024
Email linked to action number
18. New shared storage still to
be developed by supplier. 
Delayed and Rescheduled 
Revenue and Benefits
Manager/Legal
Manager