ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE 
FINANCIAL SERVICES  5 SEPTEMBER 2024 
SCRUTINY – ESTABLISHMENT OF A PANEL FOR THE REVIEW 2024-25 
1. INTRODUCTION  
1.1 The objective of the report is to provide the Audit and Scrutiny Committee
(the Committee) with an update arising from the recent change in
administration, outline the potential options in order to increase resilience
within the Committee for undertaking scrutiny reviews, and to ask the
Committee to identify a Panel. In addition, to take forward the review of
Complaints in the context of the Scrutiny Manual and Framework as part of
the Committee’s scrutiny role for 2024-25.  
2. RECOMMENDATIONS  
2.1 The Audit and Scrutiny Committee is asked to:  
2.1.2 Establish a Panel for the agreed scrutiny review relating to the Council’s
complaints process. (The previous arrangements agreed by the Committee, in
terms of identifying the Chair to lead the review, have been superseded by the
change of Administration and composition of Members within the Audit and
Scrutiny Committee).  
2.1.3 
2.1.4
In the event that the Committee are minded to proceed with this approach,
appoint a Panel Chair and three further Members to form a Scrutiny Panel for
the review, which will commence within financial year 2024-25. It is suggested
that this would consist of the Chair and Vice-Chair of the Committee and a
further two members to be identified. (This approach would allow a basis for
the wider development of skills within the Committee to undertake and
participate in future scrutiny reviews). 
In support to the Membership of the Panel, the former Chair of the Committee,
Martin Caldwell, will provide mentoring support to the new Panel in order to
build up experience and skills in undertaking scrutiny work. Officer support will
be provided as required.  
3 DETAIL  
3.1 The development of the scrutiny function has progressed successfully, and in
in the new format, a total of three reviews have been undertaken. The
Committee have found such reviews helpful in discharging their role in relation
to scrutiny and the Committee agreed in March 2024 that one review would
be undertaken in 2024-25 and a review of Complaints would be taken forward
as the preferred choice which would be of benefit to the Council. It is also
important to balance the Committee’s work in relation to scrutiny with its
primary duty, which is to seek the successful delivery of the agreed Internal
Audit Plan.

Page 2

3.2 The change of Administration within the Council, and the composition of the
Council’s Committees has resulted in changes within the make up of the Audit
and Scrutiny Committee, together with a new Chair and Vice-Chair.
Experience within the Committee to undertake scrutiny review is now limited.
In order to build experience and facilitate mentorship of the Chair and Vice-
Chair, in respect of leading such scrutiny reviews, it is proposed that the
former independent Chair, Martin Caldwell support the Panel Chair and Vice-
Chair by facilitating this scrutiny review. This would provide members with the
appropriate skills and experience to confidently undertake such reviews going
forward. A significant amount of staff resource can be expended on scrutiny
reviews. As a section we need to balance this work with available staff
resources to keep within the allocated resource envelope to complete the
scrutiny review without affecting the core primary function of undertaking the
approved Internal Audit Plan for 2024-25.       
Approach to Scrutiny previously agreed by the Committee– Context and
Background 
3.3 In order to provide further context to the development of ‘scrutiny reviews’; a
Development Session was held to establish the process to be adopted by the
Committee to identify and prioritise potential scrutiny topics and of the overall
approach adopted to scrutiny reviews which has been a combination of panel
reviews and ‘scrutiny lite’ where relevant officers have been asked to present
at Committee or at Development Sessions on topics of interest to the
Committee. 
3.4 In particular the Chief Internal Auditor (the CIA) asked the Committee to
consider some key questions. These, and the Committee responses, are
summarised in the table below.  
3.5 Question Committee Response
Should Scrutiny topics
originate from all members
and senior officers or from
Committee members?
There needs to be a degree of flexibility to
change topics and to be able to react quickly
to an ever changing environment. 
It is for the Committee to determine scrutiny
topics. 
If topics originate from the
committee should this be
via discussions at
Committee or development
sessions? 
We may need to meet as a Committee more
often however these could be less formal
meetings and held virtually. Further thought
can be given to this as to some extent it will
depend on the number of emerging topics to
be considered for scrutiny. 
Do we still need an annual
scrutiny plan or should
topics for scrutiny ‘emerge’
as the year goes by?
We don’t need a plan we should allow items
to emerge. 
Do we still need the detailed
prioritisation process? 
The prioritisation process is there as a tool if
we need it but we don’t need to use to
assess every scrutiny topic.

Page 3

Do we have the right
balance between ‘full blown’
panel approach vs Scrutiny
Lite? 
There has been value in having the full
panels but these are resource intensive and
we should look to make use of a scrutiny lite
approach where appropriate.  Once a topic
is decided then the Committee can decide
what the best Scrutiny approach to adopt is. 
3.6 The CIA has reviewed and updated, where identified, the Scrutiny Framework
and Manual in 2023/24 and will do so on an annual basis in order that the
approach to scrutiny work is both focused, appropriate and reflects the best
approach taking cognisance of the Committee’s views. 
4. CONCLUSION  
4.1 The recent changes at Chair and Vice-Chair level have resulted in a gap in
experience of leading and undertaking scrutiny reviews. To improve
resilience, knowledge and experience within the Committee to undertake and
lead scrutiny reviews, the Committee should accept the offer of mentoring and
overview from an experienced person in order to facilitate the next review
along with support from officers. 
5 IMPLICATIONS  
5.1 Policy – None
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Fairer Scotland Duty – None
5.5.1 Equalities – protected characteristics – None
5.5.2 Socio-economic Duty – None
5.5.3 Islands – None
5.6 Climate Change – None
5.7 Risk – None
5.8 Customer Service – None
5.9 The Rights of the Child (UNCRC) – None 
Paul Macaskill 
Chief Internal Auditor
5 September 2024                                                  
For further information contact: 