ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE 
FINANCIAL SERVICES  5 SEPTEMBER 2024 
STRATEGIC RISK ASSURANCE MAPPING 
1. EXECUTIVE SUMMARY 
1.1 The purpose of this report is to set out Internal Audit's assessment of the sources
of assurance for the Audit and Scrutiny Committee (the Committee) on the
management of the Council's strategic risks. 
1.2 Appendix 1 highlights the overall assessment against each of the strategic risks.
It should be noted that the assessment is based on the level of assurance that the
Committee can rely on. A 'red' assessment therefore highlights where there are
gaps in evidence of active/targeted actions/activity rather than an assessment on
the management of that risk. 
2. RECOMMENDATIONS 
2.1 To note the risk assurance map at appendix 1. 
3.  DETAIL   
3.1 Internal audit has a key role in relation to the Council’s governance to provide
assurance over the effective management of risk. 
3.2 The Chief Executive presents the Strategic Risk Register to the Committee on an
annual basis which provides the Committee the opportunity to scrutinise the
register and seek assurance from the Chief Executive that risks are being managed
appropriately.  
3.3 The CIA is of the view that the cumulative effect of these management
arrangements both contribute to positive risk management reporting within Argyll
and Bute Council while also maintaining an annual review to provide appropriate
overview and update of key emerging issues, which will be reported to the
Committee. 
3.4 The Public Sector Internal Audit Standards (PSIAS) require that Internal Audit
evaluate the effectiveness of the Council’s risk management process. However, it
does not state this needs to be an annual exercise. Furthermore it states that
Internal Audit may gather the information to support an assessment of the
effectiveness of risk management processes ‘during multiple engagements ‘and
further states that ‘The results of these engagements, when viewed together,
provide an understanding of the organisation’s risk management processes and
their effectiveness‘.  As such PSIAS does not require a full risk management audit
on an annual basis.  Additionally, The CIPFA publication “Audit
Committees: Practical Guidance for Local Authorities and Police” (2022 Edition)
requires the Audit Committee to have the option to consider risk management on a
regular basis, regardless of who has operational responsibility for it.  That option is
always available.

Page 2

3.5 Appendix 1 provides a summary of the Council’s strategic risk assurance map
which is based on the ‘three lines model’ (formerly known as the Three Lines of
Defence). 
1. The first line is the ‘functions that own and manage risks’. It is the control
environment established by day to day business operations and risk
management processes. It is formed by managers and staff who are
responsible for identifying and managing risk as part of their accountability
for achieving objectives. This requires an understanding of the Council, its
objectives, the environment in which it operates, and the risks it faces. It
includes things such as: 
• identifying risks and improvement actions
• implementing controls
• reporting on progress 
2. The second line is the ‘functions that oversee or who specialise in
compliance or the management of risk’. This provides the policies,
frameworks, tools, techniques and support to enable risk and compliance to
be managed in the first line, conducts monitoring to judge how effectively
they are doing it, and helps ensure consistency of definitions and
measurement of risk. The Council’s various committees and Strategic
Management Team are key functions in delivering this element. 
3. The third line of defence is the ‘functions that provide independent
assurance’. This is provided by internal audit. 
4. Other scrutiny is provided by external regulatory bodies which will include
External audit who offer independent challenge and provide an evaluation,
through a risk-based approach, on the effectiveness of the Council’s
governance, risk management, and internal control.

Page 3

3.6 The table below summarises the assessment against each Strategic Risk.
Strategic Risk Risk Score
(August 2024)
Assurance
Assessment
1. Population, external infrastructure
and economic decline
Red 16 Green
2. Condition and suitability of
infrastructure and asset base
Amber 12 Green
3. Financial sustainability Amber 12 Green
4. Governance & leadership Amber 8 Green
5. Engagement and understanding the
needs of the community
Amber 9 Green
6. Service delivery Amber 12 Green
7. Health & Social Care Partnership Amber 12 Green
8. Civil contingency and business
continuity arrangements are not
effective
Green 6 Amber
9. Waste management Red 16 Amber
10. Service delivery – Cyber Security Red 15 Amber
11. Cost of living crisis Amber 12 Amber
12. Impact of climate change Amber 12 Green
13. Lack of housing availability Red 20 Amber 
3.7  The assurance map has not identified an area where there may be a concerning
mismatch between the level of risk identified and the assurance provided to
Committee. 
3.8 
3.9 
3.10 
Waste Management has been subject to regular monitoring and update from the
service to the Council’s Audit and Scrutiny Committee, with the latest update in
December 2023. Additional funding is to be provided from the Scottish
Government of £1.5M to support the compliance with the BMW ban. In addition,
regular reports are being submitted to and are being monitored by the relevant
service Committee of the Council. 
In relation to ‘Service Delivery – Cyber Security’; work has been undertaken in
this area as part of the 2022/23 plan which provided a substantial level of
assurance. Going forward two planned reviews will be undertaken as part of the
2024/25 Internal audit plan putting additional audit resources into this area of
risk, specifically, Data Security and Information Security as well as the IT Risk
Register and Mitigation Processes. However, it is relevant to note that work
undertaken in 2022/23 and 2023/24 identified no significant concerns in relation
to Cyber Security or Cloud Computing. Whilst this is in part reassuring, there is
always a heightened risk to public bodies in relation to this critical area of
business activity. 
The Council declared a Housing Emergency due to the risks associated with the
Council, partner agencies and communities being unable to attract and retain
working age people due to lack of housing and pricing. A housing summit in
collaboration with housing delivery partners was held in December 2023 in order
to forge commitments aimed at tackling housing shortage which maximise
resources, pursue innovation, coordinate planning and target delivery. Plans are
underway to approach this complex and difficult issue at both a national and local
level.

Page 4

3.11 The remaining areas, where assurance has been assessed as “amber”, either
have audit reviews already undertaken, scheduled or included as part of the
ongoing audit planning process. All changes to the Strategic Risk Register from
September 2024 will be assessed in the 2025 Assurance Mapping Exercise. 
4. CONCLUSION
4.1 This exercise has again confirmed that for the majority of risks in the Council’s
strategic risk register there are either sufficient assurances in place or internal
audit have scheduled work to fill identified gaps. Nevertheless, it is important to
outline that such mitigations and assurances do not alone guarantee that an
adverse event or risk will not present itself or materialise. 
5. IMPLICATIONS 
5.1 Policy – None 
5.2 Financial – None 
5.3 Legal – None 
5.4 HR – None
5.5 Fairer Scotland Duty – None 
5.5.1 Equalities – protected characteristics – None
5.5.2 Socio-economic Duty – None
5.5.3 Islands – None
5.6 Climate Change – None 
5.7 Risk – The assurance mapping exercise has provided a satisfactory level of
assurance that the Council is managing and monitoring its strategic risks
effectively
5.8 Customer Service – None
5.9 The Rights of the Child (UNCRC) – None 
Paul Macaskill
Chief Internal Auditor
5 September 2024 
For further information contact: 
Paul Macaskill, Chief Internal Auditor, 01436 604108 
APPENDICES
Appendix 1 – Strategic Risk Assurance Map