Argyll and Bute Council
Internal Audit Report
February 2025
FINAL
High Medium Low VFM
Number of
Findings
0 1 0 0
Data and Information
Security – Data Platform
Audit Opinion: Substantial

Page 2

2
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
Contents
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 4
Key Dates ................................................................................................................................................ 4
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 5
Recommendations ................................................................................................................................. 5
2. Objectives and Summary Assessment ........................................................................................... 5
3. Detailed Findings ............................................................................................................................ 6
Appendix 1 – Action Plan ..................................................................................................................... 10
Appendix 2 – Audit Opinion ................................................................................................................. 12
Contact Details
Internal Auditor: Mhairi Weldon 
Telephone: 01546 604294 
e-mail: mhairi.weldon@argyll-bute.gov.uk
www.argyll-bute.gov.uk

Page 3

3
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
1. Executive Summary
Introduction
1. As part of the 2024/25 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2024, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal control and governance in relation to data and information security – data platform.
2. The audit was conducted in accordance with the Public Sector Internal Audit Standards (PSIAS)
with our conclusions based on discussions with council officers and the information available at
the time the fieldwork was performed. The findings outlined in this report are only those which
have come to our attention during the course of our normal audit work and are not necessarily
all the issues which may exist. Appendix 1 to this report includes agreed actions to strengthen
internal control however it is the responsibility of management to determine the extent of the
internal control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. The Council’s Data Strategy and Action Plan 2024-28 (the Strategy) was endorsed by the Policy
and Resources Committee in August 2024 and, alongside Principle 4 of the Council’s “Connect
for Success” programme, notes the importance of data in evidence driven decision-making.  The
Strategy notes that Council data combined with data from other reliable sources provides a solid
foundation from which to assess the needs and demands of residents and communities and is
reflected in the mission statement “Improving outcomes for our residents and communities
through better combination and use of data”.
5. The Data Advisory Group (DAG) was established in March 2022 with representatives from across
Council Services to create a one-council, service-led forum for data and delivery of the Strategy.
Reporting to the DAG, the Data Technical Groups (DTGs) are multiple short-life working groups
with service representation, each of which have been tasked to deliver the specific required
outputs including bespoke reports and dashboards.
6. Towards the end of 2022, the Scottish Government’s Data Maturity Assessment Programme
rated the Council as “developing” maturity, the Strategy seeks to drive change and progress to
the “mastering” stage.
7. The Council collects, stores, uses and shares a large amount of data across various line of
business systems to inform service delivery, monitor performance and provide essential
business information, however, this data is split across multiple service areas within systems
which no not readily interact with each other, resulting in significant challenge when analysis is
required at an overarching strategic level of the Council.
8. The establishment of a data platform to help manage, store and analyse multiple data sets in a
single centralised environment, with the intent to deliver real-time information and insights to
develop and inform strategic objectives, is a key element within the Council’s data programme

Page 4

4
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
which has been prepared to advance data maturity.    Services, working alongside the DAG and
working groups, also intend to harness this data to build detailed reports to meet their specific
service requirements.
9. The Council has appointed a consultancy partner to assist with the design and implementation of
the data platform and support handover to the Council’s ICT Applications Team who will
continue with its day-to-day support and maintenance, and future development.
10. Data is one of the council’s most important assets and should be protected accordingly, it is
essential that a robust control framework is in place to ensure its confidentiality, integrity and
ongoing availability, and as a large amount of this data is personal, the Council must also comply
with data protection legislation.
Scope
11. The scope of the audit was to assess the arrangements for the deployment of the data platform,
paying particular attention to access permissions, controls and security as outlined in the Terms
of Reference agreed with the ICT and Digital Manager on behalf of the Head of Customer and
Support Services on 13 December 2024.
Key Dates
12. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below.
Exhibit 1 – Key Dates
Stage Actual
Date
Terms of Reference agreed 13 December 2024
Fieldwork Commencement 8 January 2025
Draft Report issued 10 February 2025
Management Comments received 12 February 2025
Final Report issued 12 February 2025
Audit and Scrutiny Committee 13 March 2025
Risks
13. The risks considered throughout the audit were:
• SRR10:  Service Delivery – Cyber Security
• KF ORR35: Cyber Security Breach and associated Cyber Attack
• Audit Risk 1:  failure to comply with requirements of the Data Protection Act 2018 and
General Data Protection Regulation (GDPR)
• Audit Risk 2:  failure of consultancy partner to fulfil contractual obligations
• Audit Risk 3:  failure to continue development of data platform following completion
of consultancy arrangement
• Audit Risk 4:  failure to maintain integrity of data from source systems
• Audit Risk 5:  data platform is unable to deliver intended information and insights

Page 5

5
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
Audit Opinion
14. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
15. Our overall audit opinion for this audit is that we can take a substantial level of assurance.  This
means that “internal control, governance and the management of risk is sound. However, there
are minor areas of weakness which put some system objectives at risk and specific elements of
residual risk that are slightly above an acceptable level and need to be addressed within a
reasonable timescale”.
Recommendations
16. We have highlighted one medium priority recommendation which is summarised below:
• The data challenge proposal document should include a requirement to identify how
long datasets are to be held to inform capacity management.
17. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
18. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to Risk Assessment Summary Conclusion
1 Contract/SLAs are in
place and include
security and
performance
monitoring
arrangements.
All risks Substantial A comprehensive business case and
procurement exercise were followed to
engage consultants for delivery of the
data platform, however, they were not
as responsive as anticipated in
commencing work.  Documentation
reviewed contained detailed technical
specifications as well as security and
access arrangements.  Arrangements
for and progress in delivery receives
sufficient management oversight from
the ITMT, DMT and SMT.
2 Access to the data
platform and its
contents is properly
authorised,
managed and
maintained.
SRR10
KF ORR35
Audit Risks
1 & 2
High The data platform and its data are
subject to robust physical,
environmental and logical access
controls and routine maintenance and
update schedules.  There is sufficient
capacity to host current and proposed
datasets with options available to
expand in the future should it be
required.

Page 6

6
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
3 Data uploaded
retains its integrity
and outputs are
relevant, reliable
and useful.
Audit Risks
2 - 5
Substantial A business need must be demonstrated
via an agreed Data Challenge Proposal
prior to uploading to the data platform,
a Data Protection Impact Assessment
must also be carried out where
personal information is included. 
Appropriate mechanisms are in place
to transform data upon upload to the
platform to ensure operability whilst
preserving integrity.  End-user access is
on a read-only basis via appropriate
analysis and reporting tools.  The need
to remove data for GDPR purposes is
detailed, however, there is no evidence
of consideration to remove general
data once no longer useful to preserve
capacity availability or minimise future
expansion costs.
4 Business
continuity/disaster
recovery
arrangements are in
place.
SRR10
KF ORR35
Audit Risk 5
Substantial Well-established processes are in place
for the underlying technology in use to
ensure data is backed up and available
for disaster recovery purposes. 
Additional, specific details are planned
to be documented alongside ongoing
development of the platform.
19. Further details of our conclusions against each control objective can be found in Section 3 of this
report.
3. Detailed Findings
Contract/SLAs are in place and include security and performance monitoring arrangements
20. A comprehensive Outline Business Case (OBC) was prepared and details of the preferred model
submitted to the Department Management Team (DMT) and Strategic Management Team (SMT)
in September 2022 and was approved.  The Information and Communication Technology (ICT)
service, experienced subsequent difficulty in recruiting an officer to take the project forward,
and therefore, in collaboration with the Council’s procurement officers, launched a procurement
exercise in November 2023 to identify a suitable consultancy partner to assist the applications
team implement the solution.
21. An officer was successfully recruited in January 2024 and a working prototype of the data
platform developed by the ICT applications team was demonstrated to the Data Advisory Group
in March 2024.  It became apparent, however, that there were significant complexities involved
in further development and maintenance of the data platform and that there would be greater
value achieved if the Council were to proceed with the consultancy arrangement and benefit
from the knowledge and expertise of consultants with experience in implementing similar
solutions.  A further OBC, was therefore submitted to DMT and SMT in June 2024 reflecting on
the updated position and was subsequently approved.

Page 7

7
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
22. The procurement process commenced with a formal Invitation to Quote (ITQ) in November 2023
which received ten responses, six of these met the minimum requirements and were evaluated
in terms of quality and price by experienced officers to identify the preferred consultancy
partner.  The quotation from the preferred consultant was accepted on 23 July 2024 via a formal
email from the Senior Procurement Officer noting that the Council’s general terms and
conditions apply.
23. The contract was awarded following the Council’s robust procurement process including due
diligence reviews of the preferred consultant’s financial standing, insurance cover and feedback
from other clients who had completed a similar exercise with the consultant.  No concerns were
raised as a result of this review.
24. We understand that the appointed consultant has not been as responsive as had been
anticipated, this is considered to have been an exceptional circumstance, due to them acquiring
another company from where resources were subsequently allocated to fulfil the contract with
the Council.  A detailed statement of work to be completed has now been provided and
discussions confirm that the delivery team are effective and professional.  Weekly catchups are
taking place to discuss progress and work planned for the week ahead with a firm commitment
in place to complete delivery by the end of the financial year.   The response to the ITQ stated
that the engagement was expected to take place over 12 weeks, inclusive of 25 days technical
support and 10 days project management.  Dates to commence a consultancy arrangement are
not provided at this stage as this will be agreed when the mobilisation meeting takes place and
the programme of work is agreed.
25. The information provided within the ITQ response states that permissions to access the data
platform and its contents will be linked to existing access and identity management controls
operated within the Council.  These controls have previously been reviewed by internal audit
and found to be robust.  Additional security measures are to be designed and implemented in
the early stages of the data platform delivery to provide row and column level security in
preparation for integration with analysis and reporting tools used within the Council.
26. Data held on the platform will be accessed on a read-only basis and is designed to comply with
General Data Protection Regulation and other relevant security standards accreditations held by
the Council.  A draft security assessment has been completed by Council officers with detailed
provision of information in terms of security arrangements, the consultants were asked to
review and confirm the content of the assessment, and the consolidated responses from both
the Council officers and the consultants have been incorporated within the agreed Project Plan
and completed GDPR appendix.
27. Should any changes be required within the development of the data platform, provision for this
has been included within the Council’s terms and conditions which form part of the agreed
contract of work.  Any technical changes required post implementation will be undertaken
following the Council’s change management process where there are separate development,
test and production environments for changes to transition through and undergo testing and
quality control prior to being made available to users.
28. There is no specific project board assigned to provide oversight of the data platform
development, however, there are regular update reports submitted to the Information
Technology Management Team, DMT and SMT providing details of progress made and funding
status.

Page 8

8
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
29. There is no specific reference to disaster recovery within the ITQ response provided by the
consultant, however, it is noted within the security assessment and other planning documents
that business continuity and disaster recovery arrangements are provided for within existing
processes.
Access to the data platform and its contents is properly authorised, managed and maintained
30. Physical access to the data platform is restricted to authorised personnel only.  Environmental
warnings and controls are in place to ensure that temperatures do not exceed acceptable levels
for optimum operational requirements and provisions have been made for emergency power
supply should it be required.
31. Logical access to the data platform and its contents is managed via the Council’s identity and
access management controls, access to the platform itself is only achievable by ICT
administrators.  The data within the platform will be accessible on a needs-only basis via the
Council’s analysis and reporting tools in accordance with user defined roles and requirements.  A
leavers process is in place to remove former employees from the network which also controls
access to the data platform.
32. There is sufficient capacity available to store the information required to operate the data
platform at this current time, it is difficult to define what the full capacity requirement may be in
the longer term as this will depend on what datasets are added on a case-by-case basis.  Should
a need for expansion be identified in the future, there is potential for a secondary business case
to be brought forward to consider options available at that time.
33. The data platform host environment is supported via maintenance schedules, application of
appropriate software and regular security updates, there are also monitoring and alerting
mechanisms in place to bring matters to the attention of designated officers should an issue
arise.
Data uploaded retains its integrity and outputs are relevant, reliable and useful
34. When a service identifies a business need for data to be uploaded to the platform, they will
require to complete a data challenge proposal for submission to the DAG.  Each proposal is
evaluated on a case-by-case basis and where personally identifiable information is included a
Data Protection Impact Assessment (DPIA) will also be required.
35. Data extracted from line of business systems is subject to some transformation to help datasets
link with each other within the platform and provide desired results for the end-user, this has no
detrimental effect on the integrity of the data and may include the following:
• Data cleansing – removing duplicates, correcting errors/missing values
• Normalising data – standardising data format for consistency e.g. date format
• Enrichment – adding related data or calculated values in additional columns
• Aggregation – summarisation of data from larger data sets to simplify usage
36. End-user access to the data platform is on a read-only basis using analysis and reporting tools.
Data held in the platform cannot be edited using these tools and there is no transfer of
information back into the main line of business systems from the platform.

Page 9

9
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform,
February 2025 
37. Training to enable ongoing operation and development of the data platform following delivery is
a key requirement and is clearly stated within contract and planning documents.  This
knowledge transfer element of the consultancy arrangement is scheduled to take place in March
2025.
38. Training in the use of the Council’s analysis and reporting tools required to view information
held on the data platform is beyond the scope of the contract, however, it is planned that
appropriate training resources will be made available to support authorised users gain access to
the content of the platform.
39. The quality of report content from the data platform is the responsibility of the end-user via
their report writing criteria and output testing.  Discussions with current report-builders
confirmed that where unexpected results are returned, the report criteria are carefully checked
and outputs verified against data in the relevant main line of business system.  Once operational,
the same process will be followed for users of the data platform, if, however, in the event of
reporting criteria being  accurate and incorrect results persist, the Council’s ICT Applications
team, as part of their support and maintenance function for the data platform, will be able to
confirm that data extracted from the line of business system has been uploaded correctly or
reperform the task if necessary.
40. Throughout documentation reviewed, there is cognisance of the need to remove personally
identifiable information when no longer required for GDPR purposes, however, there is no other
reference to removal of general data once obsolete to preserve capacity availability and
minimise any future costs in relation to data storage expansion.
Action Plan 1
Business continuity/disaster recovery arrangements are in place
41. The data platform and the underlying data are backed up in accordance with existing well-
established arrangements to facilitate restoration in the event of a disaster scenario.  These
arrangements have been subject to prior internal audit review with all actions completed.
Additional documentation specific to the data platform will be prepared alongside the
development of the solution, however, sufficient measures are currently in place covering the
underlying technologies in use to manage disaster recovery efforts.
42. Back up and recovery testing takes place in accordance with an agreed schedule and includes the
underlying technologies used to support the data platform.  Testing results are recorded, signed
off and comments noted for future reference where relevant.

Page 10

Appendix 1 – Action Plan
No Finding Risk Agreed Action Responsibility / Due Date
Medium
1
Removal of general data once obsolete
Finding:  whilst there has been consideration for removal
of personally identifiable information when no longer
required for GDPR purposes, there has been no further
documentation of the need to remove general data to
preserve capacity availability/minimise potential future
costs for expansion.
Recommendation:  include a section within the data
challenge proposal to state how long the data should be
retained within the platform.
The data platform may be
limited in terms of capacity to
hold data or subject to
increased costs for expansion.
The data challenge form is due to
be fully revised at the conclusion
of the current consultancy and the
form will include a section within
the data challenge proposal for
the service to state how long the
data should be retained within the
platform.
Data Programme
Manager
Date 30/4/2025

Page 11

11
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform, February 2025 
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows:
Grading Definition
High A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error.
Medium
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.
Low Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives.
VFM An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).

Page 12

12
Argyll and Bute Council – Internal Audit Report – Data and Information Security – Data Platform, February 2025 
Appendix 2 – Audit Opinion
Level of Assurance Definition
High Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk.
Limited Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues.