Argyll and Bute Council
Scrutiny Report
March 2025
FINAL 
Complaints Process

Page 2

2 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
Contents 
1. Executive Summary ........................................................................................................................ 3
2. Detail ............................................................................................................................................... 4
Introduction ............................................................................................................................................ 4
Objectives ............................................................................................................................................... 4
Background ............................................................................................................................................. 5
Scrutiny Initiation Briefings – 30 November 2022 ................................................................................ 7
Exhibit 1 – Scrutiny Meetings Attendees and Key Areas for Discussion ............................................. 8
3. Scrutiny Meetings ........................................................................................................................... 8
Scrutiny Panel Meeting – Council Officers – 02 & 24 February 2023 ................................................... 8
Exhibit 2 – Scrutiny Meetings – Council Officers - Key Messages ....................................................... 9
4. Overall Conclusion and Findings .................................................................................................. 12
Exhibit 3 – Findings ........................................................................................................................... 12
APPENDIX 1........................................................................................................................................... 14 
Contact Details 
Chair: Martin Caldwell (Independent Chair of Audit and Scrutiny Committee)
Chief Internal Auditor: Paul Macaskill (paul.macaskill@argyll-bute.gov.uk)
www.argyll-bute.gov.uk

Page 3

3 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
1. Executive Summary
1. In January 2024, Elected Members requested that a scrutiny review of the Council’s Complaints
Process take place as part of Argyll and Bute Council’s (the Council) 2024/25 scrutiny plan.  The
Audit and Scrutiny Committee (the Committee) agreed to progress with this review and work
should commence to define the scope of the work to be carried out.
2. A briefing paper was prepared by the scrutiny officer and passed to the panel to provide
background information.  Discussion took place to establish the scope of the review which
resulted in the following themes of enquiry:
• The Council’s complaints process is aligned to the national guidance provided by the
Scottish Public Services Ombudsman (SPSO).
• Sufficient comprehensive guidance has been prepared and made available to assist
officers conduct complaints investigations and provide adequate responses to the
complainant within the stipulated timelines.  
• Suitable oversight is in place to ensure the complaints process is operating as intended.
• Sufficient measures are in place to assess satisfaction with the complaints process
separately from dissatisfaction with specific outcomes relating to the subject matter of
the complaint to exclude undue/subjective negativity.
• Improvements identified as a result of learning from complaints are shared equitably
throughout the Council to avoid recurrence in other service areas.
• Sufficient, comprehensive training and guidance is in place to assist Members and
Officers decide when to progress communications as complaints, expressions of
dissatisfaction or an enquiry. 
3. Research took place to establish legislative requirements and examples of good practice to form
a basis for assessing the Council’s complaints handling process.  An extensive examination
followed to measure compliance with the established assessment basis and identify any areas
for improvement.  The findings of this review formed the basis of discussions held with key
officers involved, the full details of which are included in Exhibit 2.  
4. The panel reviewed and discussed a large suite of documents obtained over the course of the
review to reach its conclusions, these can be summarised as follows:
• The Council’s Complaints Handling Procedure is based on the SPSO’s Model Complaints
Handling Procedure.
• The Complaints Handling Procedure is comprehensive and readily available to all Council
employees, supplementary information and templates provide additional support.
• Monthly, quarterly and annual reporting provides senior management with oversight of
the complaints handling process.  This information is made available to DMTs and
separately to Heads of Service and service single points of contact for complaints, 
however, there is no evidence of this information being cascaded to operational levels
to share learning and improvement actions. 
• Customer satisfaction is subjective and difficult to assess, satisfaction surveys may be
biased and return rate is low. 
• Training and guidance materials help Members and officers understand what is and is
not a complaint.

Page 4

4 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
The full conclusions reached are included in paragraph 33 with findings and recommendations
outlined in exhibit 3.
2. Detail
Introduction
5. As part of the Council’s 2024/25 scrutiny plan, approved by the Committee in March 2024, we
have undertaken a scrutiny review of the Council’s complaints process. 
6. Throughout this report references to ‘the panel’ refers to the former independent Chair of the
Committee (to provide guidance to new panel members), the new independent Chair and three
Committee Elected Members who conducted this review. They were:
• Martin Caldwell (panel chair)
• Janice Wasson-Hall (Chair)
• Councillor Mulvaney
• Councillor Vennard 
• Councillor Howard
7. The panel was supported by council officers who gave willingly of their time to help deliver the
review.  We would like to extend our appreciation for the co-operation and assistance received
from all attendees invited to provide evidence over the course of the review.
Scope
8. Consider whether the Complaints Handling Procedure provides sufficient clarity over service
expectations, what does and does not constitute a complaint and whether services are learning
lessons from complaints feedback to inform continuous improvement.  As social Work Servies
are the responsibility of the HSCP, the Panel should exclude this service area from
considerations.
Objectives
9. The agreed objectives of the scrutiny review were to:
• Ensure the Complaints Handling Procedure contains clear guidance defining what can
and cannot be considered as a complaint, it is well communicated and referenced within
key council documentation:
o In constitution, governance statement and Council policies
o In guidance to Members, line managers and officers
• Ensure the Council’s procedure is aligned with national guidance and best practice:
o Scottish Public Services Ombudsman
o Identified best practice within public service
o Robust sources of evidence are used in arriving at complaints resolutions
• Ensure performance data is captured, reported and used to inform senior management
of areas for improvement and share good practice
o Surveys to gather information
o Reports to senior management and committees
o Submissions to appropriate partner organisation for monitoring and
benchmarking

Page 5

5 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
o Information published on Council website
• Assess methods of identifying and sharing improvement actions
o Improving complaints handling process
o Informing service performance improvements
o Information sharing across Council Services
• Development and final agreement of improvement actions
Background
10. Within the Council’s website and Complaints Handling Procedure, a complaint is defined as “the
expression of dissatisfaction with an organisation’s procedures, charges, employees, agents or
quality of service”, and “an expression of dissatisfaction about the Council’s action or lack of
action, or about the standard of service provided by or on behalf of the Council”.  
11. Complaints may relate to the following examples:
• failure or refusal to provide a service 
• inadequate quality or standard of service, or an unreasonable delay in providing a
service 
• dissatisfaction with one of our policies or its impact on the individual 
• failure to properly apply law, procedure or guidance when delivering services 
• failure to follow the appropriate administrative process 
• conduct, treatment by or attitude of a member of staff or contractor (except where
there are arrangements in place for the contractor to handle the complaint themselves:
see Complaints about contracted services); or 
• disagreement with a decision, (except where there is a statutory procedure for
challenging that decision, or an established appeals process followed throughout the
sector).
12. The above complaint definition is broad, but not every concern raised with the Council is a
complaint. For example, a complaint is not: 
• a request for information or an explanation of policy or practice 
• a request under the Freedom of Information Act or Data Protection legislation.    
13. There are also some matters we can’t deal with under the Complaints Procedure. These include: 
• A first time request for a service e.g. a request for a street-lighting repair 
• A request for compensation only 
• Where there is a statutory or other formal right of appeal e.g. decision on housing or
council tax benefit or in regard to formal enforcement action 
• Insurance claims or potential claims concerning injury to people or damage to property,
however if they are also complaining about the cause of the injury/damage this part
should be dealt with as a complaint
• Matters which are currently subject to court proceedings or have already been heard in
court or at a tribunal 
• Complaints regarding the conduct of a Councillor 
• Disagreement with decisions or conditions that are based upon social work
recommendations, but determined by a court or other statutory body, for example
decisions made by a children's panel, parole board or mental health tribunal

Page 6

6 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
• A concern about a child or an adult’s safety 
• A complaint which has already been investigated and a final decision given.
14. The Council Constitution states that “Citizens have the right to complain to the Council under its
complaints procedure about any service failure”.  The Council is committed to providing high
quality services for the people in Argyll and Bute, however, sometimes services may fail to fully
meet their objectives, and when this happens, the Council needs to know so that weaknesses
can be addressed and lessons are learned from the actions taken. 
15. The Council has developed a formal complaints procedure to help those wishing to raise a
complaint to do so either in person at any of the Council’s customer service points, or by
telephone, in writing, by email or via the Council’s or Health and Social Care Partnership’s
(HSCP) websites.
16. The Council has a dedicated area on its website providing information about complaints.  This
includes an explanation of what a complaint is, the Council’s aims and commitments regarding
the complaints procedure, how to raise a complaint, what can and cannot be complained about,
who can complain, how long a customer has to make a complaint, a link to what happens when
complaints have been submitted and performance information.  
17. The Complaints Handling Procedure operated by the Council and the HSCP is comprehensive
and was developed by local government complaints handling experts working closely with the
SPSO.  The Model Complaints Handling Procedure (MCHP) was revised in 2019, combining both
local authority and social work procedures into one containing core text applicable to all public
services in Scotland with some additional text specific to local authorities and HSCPs handling
social work complaints.    
18. The procedure sets out what constitutes a complaint, the complaints handling process and what
is expected from employees during the complaints process, it also provides some examples and
guidance with regard to issues raised.  
19. The Complaints procedure consists of two stages:
• Stage one: Frontline Response
• Stage two: Investigation
20. Complaints will be resolved wherever possible and this may happen at any point within the
process.  Action taken, if any, to resolve the complaint will be agreed between the complainant
and the Council/HSCP.  Where a complaint is resolved, it is not usually necessary to continue
investigating, although it may be useful to do so e.g. to identify learning opportunities to
prevent recurring complaints.  All investigations will be undertaken by a senior officer
independent of the service area under review and a clear record of how the complaint was
resolved will be maintained, noting what action was agreed and the customer’s agreement to
the final outcome.
21. The Council welcomes and indeed values complaints as the feedback received can be used to
inform service improvements and ensure that customers are treated fairly.  Where appropriate,
action will be taken to improve services on the basis of complaints findings.  The outcomes and
actions taken are recorded for all complaints and this data is used to analyse trends and
themes.  Complaints data is used to analyse and improve services and learning is shared
throughout the Council/HSCP as relevant.

Page 7

7 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
Scrutiny Preparatory Meeting – 02 October 2024 
22. In October 2024 the Panel Chair and scrutiny officers met with key service officers to gather
information and discuss possible focus areas for the review.   
23. The attendees recognised the nature of this briefing and discussion noted the following :
• The definition of a complaint is provided by the SPSO, however there may be benefit in
further explaining “expectations”
• We follow the SPSO Model Complaints Handling Process to progress complaints, it is not
useful to step outside of this guidance
• Complaints should focus on service provision and not overarching policy
• The Member’s Portal is not a conduit for submitting a complaint, anything that looks like
a complaint should be passed to relevant officers to progress through the appropriate
channels if deemed appropriate
• Members have been provided with induction training
• It is important to understand the difference between a complaint and a disagreement 
• The complaints procedure includes issue of a survey upon completion
• Survey return rate is low and more commonly returned by those who are unhappy with
the outcome rather than the complaint process, this has an impact on the annual
complaints report
• Services use feedback inconsistently for learning and benchmarking purposes, there is
no mechanism across the Council to share improvement actions e.g. to provide more
timeous responses to complaints
• Heads of Service are provided with monthly complaints reports and SMT quarterly,
however, there is no evidence of this being cascaded to operational management to
highlight need for improvement
24. The scrutiny officer thereafter prepared and circulated a “Background and Scoping Document”
to the Panel which contained a great deal of information to help inform the review.  As well as
providing the scope (para 8), Objectives (para 9) and background information (paras 10-21
above) the document also contained a briefing paper providing a summary of the contents of
the Council’s Complaints Handling Procedure and performance reporting mechanisms.
25. Attendees agreed that a panel meeting be held to consider the following:
• SPSO Model Complaints Handling Guidance is communicated within Council guidance
and training provided to Members and officers and helps provide a clear understanding
of what can and cannot be considered a complaint
• performance data is captured and shared with management to inform improvement
actions and where relevant share information across the Council
• benchmarking arrangements are in place to learn from other Councils
26. The panel agreed that they should meet with appropriate representatives of the groups set out
in Exhibit 1.

Page 8

8 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
Exhibit 1 – Scrutiny Meetings Attendees and Key Areas for Discussion
Group Key Areas for Discussion
Council
Officer(s)
SPSO guidance is communicated within Council procedures and training to
provide clear understanding of what is and what is not a complaint 
• In Complaints Handling Procedure
• In Council website
• In service information 
Performance data is captured, reported and shared sufficiently to inform
improvement actions
• Survey feedback
• KPI reporting
• Information sharing across services 
Benchmarking Arrangements
• Local Authorities Complaints Handlers Network (LACHN)
• How improvements are shared within other Councils
• How improvements are shared between Councils 
3. Scrutiny Meetings 
Scrutiny Panel Meeting – Council Officers – 29 November 2024
27. The Panel meeting consisted of Panel Chair, Chair of the Audit and Scrutiny Committee,
Councillor Vennard, Councillor Howard, Head of Legal and Regulatory Support and the
Compliance and Regulatory Officer.    
28. The scrutiny officer undertook a review of the Council’s procedure document on complaints
handling against the SPSO Model Complaints Handling Procedure to assess their alignment. 
This revealed that the Council’s guide is clearly based on this document with additional details
advising of how the procedure should be applied locally within services.  This is a lengthy
document and a summary was provided for the convenience of the Panel.   
29. Against this finding and building on the overall purpose of the review that had been agreed
within the Background and Scoping document following the first meeting, the six themes
identified in paragraph 2 were agreed by the panel as the final scope of the review.
30. Scrutiny officers thereafter reviewed the Council’s procedure against these themes and
considered improvements. (See conclusions at Paragraph 33) 
31. The panel focussed on how satisfaction with the complaints process is assessed, learning from
complaints and what is and is not considered to be a complaint.  
32. The panel met with Council Officers at a single panel meeting. The Exhibit 2 lists the themes in
order and the key messages emerging from each theme representing the respective views of
the panel and the Officers.

Page 9

9 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
Exhibit 2 – Scrutiny Meetings – Council Officers - Key Messages 
Theme  Detail 
The Council’s complaints
process is aligned to the
national guidance provided by
the Scottish Public Services
Ombudsman (SPSO). 
The SPSO Model Complaints Handling Procedures has been
adopted by the Council with some additional detail around
how to apply the requirements at a local level. 
When we consider aspects of the complaints process, we
will not be able to deviate away from what the SPSO
expects of a local authority. 
The Complaints Handling Procedure is considered to be
comprehensive and useful. 
The definition of a complaint used by the Council is derived
from the SPSO.   
Sufficient comprehensive
guidance has been prepared
and made available to assist
officers conduct complaints
investigations and provide
adequate responses to the
complainant within the
stipulated timelines.   
The Complaints Handling Procedure is available to all
members of staff with a Council email address on the HUB
intranet resource website. 
The complaints process is underpinned by best practice. 
The Council uses a suite of templates provided by the
Compliance and Regulatory Team, including examples of
what is and is not a complaint.   
Suitable oversight is in place to
ensure the complaints process
is operating as intended. 
Annual report is published and passed to the Audit and
Scrutiny Committee. 
Heads of Service are passed monthly reports detailing how
many complaints were received in the period, how many
were dealt with within the required timeframe, how many
were late, number of issues arising and any lessons learned. 
Each Service has a Complaints Representative (Rep) who
coordinates the response to complaints within that Service. 
The Rep liaises with the Compliance and Regulatory Team
for advice and assistance and attends regular meetings held
by the team for all Reps to discuss matters related to
performance, current issues and advice related to that.   
Strategic Leadership Team (SLT) are passed quarterly
summaries of the above.  The format of this report is
undergoing development to provide an easier to
understand graphic summary.  The SPSO will be interested
to see this development. 
There is no evidence of information being cascaded to
operational management to implement improvements at
front-line service delivery.

Page 10

10 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
No complaints were required to be investigated by the SPSO
in 2023/24, our performance is considered to be very good. 
Most teams/services have a single point of contact for
complaints and regular discussions take place, especially
where issues arise. 
We do not publish the content of individual complaints but
we do publish  a high level overview of the number of
complaints and our complaints performance. 
Stage two complaints are investigated by someone
completely independent to the situation and is usually a
Head of Service.  The investigating officer cannot have had
any involvement in the specific situation that the complaint
relates to. 
Sufficient measures are in
place to assess satisfaction
with the complaints process
separately from dissatisfaction
with specific outcomes relating
to the subject matter of the
complaint to exclude
undue/subjective negativity. 
The Panel may wish to consider how we assess satisfaction
with the complaints process.  This can often be difficult as
there is a distinct difference between someone being happy
with the process but not necessarily happy with the
outcome.  One option would be to benchmark what other
Council’s do and see if there are any learning points to
consider in terms of improving. 
Customer satisfaction is difficult to gauge, it is subjective,
often closely linked to whether the complainant agrees or
disagrees with the outcome. 
Customer satisfaction survey response rate is low and this is
comparable with other Councils across the Local Authorities
Complaints Handlers Network (LACHN). 
Improvements identified as a
result of learning from
complaints are shared
equitably throughout the
Council to avoid recurrence in
other service areas. 
The Panel may wish to consider how the Council learns from
complaints.  The most important element to emerge from a
complaint is learning and using that information to inform
improvements.  Identified improvements may be relevant in 
more than one area of the Council, therefore the Panel may
wish to consider how this learning is cascaded equitably
throughout the Council and if there are any ways that this
can be improved.   
It is not a quantitative assessment but a quality assessment
on how we are improving and what we can do to continue. 
We publish an Annual Report on complaints which includes
some examples of lessons learned and improvements made
as a result, “You said and We did”.  It was suggested that it
might be useful to draw this out further e.g. to the website.

Page 11

11 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
It is important to admit that we make mistakes.  The Council
is on a journey for continuous improvement along with the
members of the public. 
This information is made available to DMTs and separately
to Heads of Service and Service single points of contact for
Complaints.  It is important that services share successful
improvements to managing complaints.  It would be useful
and of value if the Panel were able to suggest areas for
improvement to help cascade information across the
Council.  It may be beneficial to undertake a benchmarking
exercise to establish what measures are taken within other
Councils.  (This exercise was undertaken but received only 4
responses that were of very limited use, these can be
viewed within Appendix 1.) 
How do we translate what we say in terms of good
governance and meeting the needs of the SPSO into
relaying that to our community so they have an
understanding on how we use complaints to improve. 
Making changes as a result of complaints shows that we are
listening and taking notice, two examples were provided
regarding email system failure and use of acronyms within
Council reports.   
Stage 1 complaints can be resolved relatively informally and
as a result the outcome might not necessarily require to be
recorded. 
Sufficient, comprehensive
training and guidance is in
place to assist Members and
Officers decide when to
progress communications as
complaints, expressions of
dissatisfaction or an enquiry. 
The Panel may wish to consider whether there is clear
distinction and understanding regarding what is and is not a
complaint.  There may, at times, be confusion when a
communication is received, as to whether it should be
treated as a formal complaint or is an expression of
dissatisfaction.  Would further guidance, training and
support help develop a more consistent approach. 
People may disagree with the Council on a number of areas
but the mere fact there is a disagreement is not the basis
for a complaint.  The manner of how a disagreement may
have arisen may be the basis of a complaint.   
Members induction slides contain useful information with a
lot of focus on how we use the complaints data for
improvements and other aspects on governance that may
arise.

Page 12

12 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
4. Overall Conclusion and Findings 
33. Based on the information obtained over the course of the review the panel has concluded that:
• The Council’s Complaints Handling Procedure is a useful, comprehensive document that
is based on the Scottish Public Sector Ombudsman’s (SPSO) Model Complaints Handling
Procedure with additional guidance on local application.
• Sufficient comprehensive guidance is available to all Council employees via the Council’s
intranet resource, the “HUB”.  This guidance is supported by a suite of templates
provided by the Compliance and Regulatory Team, including some useful examples.  
• The most important element to emerge from a complaint is learning and using that
information to inform improvements.  Suitable oversight is in place via monthly,
quarterly and annual reporting mechanisms.  This information is made available to DMTs
and separately to Heads of Service and Service single points of contact for Complaints,
however, there is no evidence of information being cascaded to operational
management from senior management.
• Customer satisfaction is subjective and difficult to assess, the return rate for surveys is
low and those that are returned are often biased by those who are unhappy with the
outcome as opposed to the complaints process.
• New elected Members are provided with induction training promptly after elections
take place as well as regular development sessions to explain what is and is not
considered to be a complaint and how these matters should be addressed.
34. The review has identified 2 findings which have been discussed with management. These, and
the management responses, are detailed in Exhibit 3.
Exhibit 3 – Findings
No. Recommendations Management Response
1 Satisfaction with the complaints process 
It is difficult to gauge satisfaction due to
the poor return rate of surveys issued
upon completion.   
The complaints system administrator may
wish to consider whether there would be
any benefit in having a further stage in the
reminder process, given the current level
of engagement from complainers.   
Noted 
This can be investigated, however, this
may be additional work for no guaranteed
benefit.  Most people respond, based on
the outcome of their complaint, not
necessarily in terms of the spirit of the
survey, i.e. on the process.  This is
reflected in the limited benchmarking. 
2 Learning from Complaints 
There is insufficient evidence of lessons
learned identified being implemented as a
result of the complaints process despite
having been cascaded within and across
the Council’s Service areas. 
Noted 
Improvement actions are identified and
shared with Heads of Service and Service
Reps.  There is a current requirement for
Heads of Service to ensure that

Page 13

13 
Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
No. Recommendations Management Response
Whilst lessons learned are discussed at
senior management level and details
cascaded to ensure that improvements
should be identified and can be used to
inform improvements across all Council
service areas, this is not always evident in
terms of process within individual service
areas/teams. 
As part of the cascade arrangements,
Heads of Service should confirm to Legal
and Regulatory Services how identified
improvement actions which have been
shared with them and with their Service
Representatives have been or will be
implemented in practice for inclusion in
the annual report. 
Management should consider cascading
learning to all Council employees via
periodic bulletins where it is deemed that
there is sufficient benefit for wider
circulation (linked to monthly/ quarterly
reporting) to share insights with all
involved in service delivery. 
improvement actions have been
completed, and this is confirmed to L&RS
by the Service Rep updating the Oracle
case form – this is simply not always done. 
Most improvement actions relate to the
individual complaint and actions taken to
reduce the likelihood that a similar issue
will arise again for that individual, where it
is something that affects other areas of
the Service, then they should be discussed
at DMT and cascaded as appropriate. 
Services already have “Service Reps” and
they fill that champion role – but issues
with getting confirmation that
improvement actions have been
completed and the case file updated
continue.

Page 14

Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
APPENDIX 1
Review of Argyll and Bute Council’s Learning from Complaints compared to other Councils
The Scrutiny officer prepared four questions for submitting to other councils to assess if there are any lessons we
can learn to share improvement ideas across the Council.  The Compliance and Regulatory Officer issued these
questions to the Local Authority Complaints Handlers Network on behalf of the Panel with a view to reach across as
may local authorities as possible, unfortunately, only 4 responses were received despite an additional reminder
being sent.  The response from one Council indicated that they receive a good return rate in relation to feedback
surveys and were contacted to obtain further information, unfortunately they did not respond.  The limited
information received is detailed below:
Responses to questions submitted to other Councils
No. Question Responses
1 Surveys requesting feedback on
satisfaction with the complaints
handling process have a low
return rate, have you taken or are
you planning to take any
additional action to encourage a
greater responses rate?  
If so, what are those actions?
We stopped surveys a number of years ago as we had to do manually,
and response was little.  We are in the process of getting a new system
and hoping that it will be able to issue a survey once complaint is
complete. 
Ours are over 50% and we are happy with that. 
We ask customers to opt into our surveys.  If they do, they get one.  We
review the feedback and incorporate it into our annual report, but
beyond that we don’t do anything with it.  If we had time, we would do
more with it, but we just don’t have the resource. 
We have not taken any action to encourage a greater response rate. 
We are aware that the return rate is low and is skewed towards those
who are unhappy. 
2 Have you considered any
alternative means of gauging
satisfaction with the complaints
process within your Local
Authority?  
If so, what are these?
As an authority we are looking at customer satisfaction across services
and how best to capture. 
No 
No, we haven’t considered any alternative methods.  Again, this is a
resource issue. 
No, we haven’t but it is something that we should look at in the future. 
3 By addressing complaints
received, services are able to
identify improvements, can you
please advise if these
improvements are shared across
other service areas within your
Local Authority?
If so, how are these
improvements communicated
and is there any information
gathered to evidence successful
implementation?
Improvements are shared within Management Teams within Services
only unless they have implications for all Services. 
Only shared in our annual report, we include some “stories”. 
This is an area for improvement for us.  Sharing learning is not
happening in the way it should. 
We do not communicate this directly with Services, however, we do
share it with our Information Management Group and publish it in our
Quarterly and Annual Complaints Monitoring report.  We are currently
looking at developing a Power BI dashboard to make this more widely
accessible and introducing shared learning across Services at our
internal Complaint Handlers and Co-ordinators Network.

Page 15

Argyll and Bute Council – Scrutiny Report – Complaints Process 2024/25 
No. Question Responses
4 Is improvement information
currently shared across other
Local Authorities?
If so, how is this communicated?
No. 
No. 
Beyond looking at the benchmarking and considering anything that
comes up at LACHN meetings, we don’t share improvement
information. 
No