Argyll and Bute Council
Internal Audit Report
March 2025
Final
High Medium Low VFM
Number of
Findings
1 1 2 0
Bridge Asset Management
Plan 
Audit Opinion: Reasonable

Page 2

2
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
Contents
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 4
Key Dates ................................................................................................................................................ 4
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 5
2. Objectives and Summary Assessment ........................................................................................... 5
3. Detailed Findings ............................................................................................................................ 7
Appendix 1 – Action Plan ..................................................................................................................... 11
Appendix 2 – Audit Opinion ................................................................................................................. 15
Contact Details
Internal Auditor: David Sullivan 
Telephone: 01546 604125 
e-mail: david.sullivan@argyll-bute.gov.uk
www.argyll-bute.gov.uk

Page 3

3
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
1. Executive Summary
Introduction
1. As part of the 2024/25 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2024, we have undertaken an audit of Argyll and Bute Council’s (the Council / ABC)
system of internal control and governance in relation to Bridge Asset Management Plan.
2. The audit was conducted in accordance with the Public Sector Internal Audit Standards (PSIAS)
with our conclusions based on discussions with council officers and the information available at
the time the fieldwork was performed. The findings outlined in this report are only those which
have come to our attention during the course of our normal audit work and are not necessarily
all the issues which may exist. Appendix 1 to this report includes agreed actions to strengthen
internal control however it is the responsibility of management to determine the extent of the
internal control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. The Infrastructure Design team is responsible for the oversight of 903 bridges within Argyll and
Bute Council. The Infrastructure Design team’s approach is to follow the 'Well-managed Highway
Infrastructure' Code of Practice and the Standards for Highways/Design Manual for Roads and
Bridges (DMRB) CS 450 - Inspection of Highway Structures.
5. These national Codes of Practice and Standards categorise bridge inspections into three types:
General Inspections, Principal Inspections, and Special Inspections and set out the frequency of
inspections that should be undertaken. General Inspections should be conducted every 24
months, encompassing visual assessments from ground level without additional access
equipment. Principal Inspections are more comprehensive, requiring close examinations within
touching distance of all accessible parts of a structure, and are recommended every 72 months.
Special Inspections are performed as needed to address specific concerns raised by various
stakeholders.
6. The Infrastructure Design team recently transitioned the structures' asset management system
to the cloud-based WebSMS platform by WDM, replacing the previous server-based version of
the WDM system maintained by Argyll and Bute Council. This system migration aimed to
enhance the accessibility of bridge inventory data. Inventory validation is being integrated into
WebSMS through tablet input by Bridge Inspectors or manually via desktop entries. Additionally,
ad-hoc validation is performed by Bridge Inspectors and Engineers as required.
7. This audit will aim to provide an analysis of the data integrity within the WebSMS system and
evaluate the effectiveness and compliance of the cyclic bridge inspection process with the
national Code of Practice and Standards.

Page 4

4
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
Scope
8. The scope of the audit was to review the data held in the bridges asset management system
together with a review of the cyclic bridge inspection process as outlined in the Terms of
Reference agreed with the Head of Roads and Infrastructure Services on July 24th 2024.
Key Dates
9. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below.
Exhibit 1 – Key Dates
Stage Actual
Date
Terms of Reference agreed 24th July 2024
Fieldwork Commencement 24th July 2024
Draft Report issued (Information
required for the review was
delayed)
25th November
2024
Management Comments received 17th March
2025
Final Report issued 19th March
2025
Audit and Scrutiny Committee 12th June 2025
Risks
10. The risks considered throughout the audit were:
 SRR02:  Infrastructure and Asset Base does not meet future requirements
 Audit Risk 1: There are no procedures in place for Bridge inspections
 Audit Risk 2: Information within the Bridge Asset Management system is not complete
and accurate
 Audit Risk 3: Bridge Inspections are carried out as per agreed policies
 Audit Risk 4: Reputational damage to the Council
 Audit Risk 5: There are no procedures in place for mitigating the risk of late inspections
 Audit Risk 6: Monitoring and reporting of inspections is not in place
Audit Opinion
11. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
12. Our overall audit opinion for this audit is that we can take a Reasonable level of assurance.  This
means that Internal control, governance and the management of risk are broadly reliable.
However, whilst not displaying a general trend, there are areas of concern which have been
identified where elements of residual risk or weakness may put some of the system objectives at
risk.

Page 5

5
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
Recommendations
13. We have highlighted one high priority recommendation, one medium priority recommendation
and two low priority recommendations where we believe there is scope to strengthen the
control and governance environment. These are summarised below:
 The Council should ensure a structured performance reporting framework is established
to distribute reports to key stakeholders, include performance updates to Departmental
Management Team (DMT) meetings,
 The Council should develop its own documented procedure for bridge inspections to
ensure and document the process for compliance with the Well-managed Highway
Infrastructure Code of Practice and DMRB CS 450, to enhance clarity, accountability, and
adaptability while aligning inspection activities with external standards and the Council’s
specific operational requirements.
 The Council should ensure formal records are maintained for all training completed by
Bridge Inspectors, including certification courses and in-house training on the WebSMS
asset management system, to enhance accountability and ensure compliance with
training requirements.
 The Council should establish an audit trail within the WebSMS system to document late
inspections, including reasons for delays, actions taken, and stakeholder communication,
to enhance transparency and accountability.
14. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
15. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to Risk Assessment Summary Conclusion
CO1 There are
Procedures in place
for Managing Bridge
Inventory Data
which are
Documented and
communicated to
appropriate
personnel
Audit Risk 1 Reasonable The Infrastructure Design team
oversees 903 bridges, operating
within a legislative and procedural
framework that includes the Roads
(Scotland) Act 1984 and the DMRB
standards.
The Infrastructure Design team lacks
a documented procedure to ensure
compliance with the relevant national
Codes of Practice relying instead on
national Codes of Practice and
Standards categorise and the
WebSMS system. This reliance could
result in reduced adaptability to local
conditions, potential accountability
gaps, and inconsistent processes.
Additionally, while inspectors are
trained, there is no formal record to

Page 6

6
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
verify this, highlighting the need for
documented procedures and training
records to enhance accountability
and transparency.
CO2 All bridge inspection
are carried out in
accordance with
General, Principal,
and Special
Inspections per the
recommended
frequencies and
standards as
outlined in the
'Well-managed
Highway
Infrastructure' Code
of Practice and the
DMRB CS 450.
Audit Risk 2
Audit Risk 3
Audit Risk 4
Substantial A review of inspection reports from
the WebSMS system confirmed that
inspections are comprehensive and
adhere to the 'Well-managed
Highway Infrastructure' Code of
Practice and DMRB CS 450 standards.
The reports include calculated
Condition Indicators & Scores,
inspection of each bridge element,
estimated costs of repairs and
summary of work required.
CO3 There are
procedures in place
for identifying and
mitigating risks
associated with late
inspections,
particularly for high-
priority structures.
Audit Risk 5 Reasonable The audit found gaps in WebSMS for
managing late bridge inspections, as
the system lacks a formal reporting
mechanism to document delays,
actions taken, and risk mitigation.
Currently, inspectors manage this
manually, though plans for an
automated email report are
underway. While risks for high-
priority structure delays are
addressed as needed, no formal
procedures or records exist within
WebSMS for these mitigation
strategies or resource reallocation.
CO4 There are regular
performance
reports generated
and reviewed by
relevant
stakeholders and
reports include key
performance
indicators in
relation to
inspection
schedules and late
inspections
Audit Risk 6 Limited The audit identified gaps in
performance reporting, including the
absence of a structured framework to
distribute reports to key stakeholders
on a regular basis. Additionally,
performance reports are not
routinely included in Departmental
Management Team (DMT) meetings
or other forums, limiting
opportunities for enhanced
monitoring, accountability, and
informed decision-making.
Furthermore, there are no specific
regular reports addressing late bridge
inspections, nor are there formal
action plans or follow-up measures to
ensure compliance with inspection
schedules.

Page 7

7
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
16. Further details of our conclusions against each control objective can be found in Section 3 of this
report.
3. Detailed Findings
There are Procedures in place for Managing Bridge Inventory Data which are Documented and
communicated to appropriate personnel.
17. The cyclic bridge inspection process, recorded within WebSMS, follows established standards
including the 'Well-managed Highway Infrastructure' Code of Practice and the Standards for
Highways/Design Manual for Roads and Bridges (DMRB) CS 450 - Inspection of Highway
Structures. The Infrastructure Design team is responsible for the oversight of 903 bridges within
Argyll and Bute Council. Management within Infrastructure Design follow a framework of
legislative, procedural, and operational documents to ensure effective and compliant
management of highway structures. This includes the Roads (Scotland) Act 1984, adherence to
the Code of Practice: Well-Managed Highway Infrastructure, and implementation of design
standards as outlined in the DMRB - Highway Structures and Bridges Series. Furthermore, the
team operates in alignment with the Council's strategic objectives as detailed in the Roads Asset
Management Plan (RAMP) - June 2017, providing a structured approach to maintaining and
managing bridge infrastructure.
18. The audit found that the Council does not have its own documented service procedure for
ensuring that bridge inspections are conducted in line with the national codes of practice.
Instead, the Management complies with 'Well-managed Highway Infrastructure' Code of
Practice and the Standards for Highways/Design Manual for Roads and Bridges (DMRB) CS 450 -
Inspection of Highway Structures and records asset management information within WDM
WebSMS. The sole reliance on national Codes of Practice and Standards and the WebSMS
(WDM) system without agreed internal procedures tailored to the Councils operational
requirements may result in
 Reduced adaptability to address specific local requirements or unique structural
conditions
 Potential gaps in accountability and clarity for staff responsible for inspections
 Inconsistent application of inspection processes, especially when relying solely on
system outputs
 Vulnerability to interruption in service of the WebSMS (WDM) system including: failures
by the provider, cyber-attack or other long duration ICT outage requiring reversion to
“manual / paper based” approaches to bridge inspection and associated data collection.
The Council should consider developing its own documented service procedure for bridge
inspections setting out how compliance with the national codes of practice will be achieved in
the context of Argyll and Bute Council. This would enhance clarity, accountability, and
adaptability, ensuring that all inspection activities align with both external standards and the
Council’s specific operational requirements.  
Action Plan 2

Page 8

8
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
19. Council officers advised that Bridge Inspectors have completed comprehensive training under
the Bridge Inspector Certification Scheme, ensuring they are qualified to conduct inspections in
line with established standards. Inspectors follow the Inspection Manual for Highway Structures,
Volumes 1 and 2, which guides inspection procedures. Additionally, training on the WDM
WebSMS asset management system is provided internally by the Infrastructure Design team, as
the system was developed specifically to meet the team's unique operational needs. This in-
house, tailored training equips inspectors with the necessary skills to effectively manage bridge
inventory data in the WebSMS system. While the client has indicated that Bridge Inspectors have
completed relevant certification courses and received in-house training on using the WebSMS
asset management system, there is no formal record of training maintained on file.
Action Plan 3
20. Special Inspections are recorded within the WebSMS system, the current limitation is the
inability to export these reports. The client was already aware of this issue and had instructed
WDM to enhance the system's functionality to allow for exporting Special Inspection data in
future for full Inspection History reports. This enhancement will facilitate more efficient audits
and improve accessibility to inspection data.
All bridge inspection are carried out in accordance with General, Principal, and Special
Inspections per the recommended frequencies and standards as outlined in the 'Well-managed
Highway Infrastructure' Code of Practice and the DMRB CS 450.
21. A sample of inspection reports from the WebSMS system were viewed via a desktop exercise.
The review found inspections were comprehensive and aligned with 'Well-managed Highway
Infrastructure' Code of Practice and the DMRB CS 450 standards. Checked carried out detailed
within Inspections reports include:
 Calculated Structural Condition Indicators and Condition indicator scores indicating the
average and critical condition of each bridge,
 Inspection of each bridge element including deck, sub structure, safety elements, and all
other structural elements of each bridge,
 Estimated costs of repairs for each inspected bridge element which requires work,
 Work required section indicating where structures require works, including immediate
attention (High Priority) where applicable.
22. The audit found that 38 bridges have inspections late by 26 months or more. While the report
provided details on the late status, it did not specify the risk category of these bridges. This lack
of information limits the Council’s ability to prioritise and address inspections based on the
potential risk level associated with each structure.
23. The audit found that inspection resources for bridge inspections, particularly for high-priority or
urgent matters, are allocated on an ad hoc basis, according to immediate needs. Consideration
should be given to establishing a more structured approach for allocating inspection resources,
particularly for high-priority or urgent inspections, to ensure that critical inspections are
consistently prioritised and adequately resourced.

Page 9

9
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
24. Concerns raised by the public are addressed through the same process as those initiated by
Inspectors' recommendations following General Inspections. While Special Inspections are
primarily triggered by Inspectors' observations, any inspections prompted by public concerns are
handled consistently within the established inspection framework.
There are procedures in place for identifying and mitigating risks associated with late
inspections, particularly for high-priority structures.
25. The Code of Practice states that there should be a formal and traceable documentation process
in place to manage and report on late inspections. This ensures accountability and continuous
monitoring of inspection schedules and compliance with the 'Well-managed Highway
Infrastructure' Code of Practice and the DMRB CS 450 standards.
26. The audit found that there is currently no audit trail within the WebSMS system (WDM) to
document late inspections, including reasons for delays, actions taken, and stakeholder
communication. Instead, this process is managed manually by inspectors outside of the system.
Council officers noted that steps are underway to develop an automated report from WDM to
capture and record this information formally via email. Establishing an integrated, automated
audit trail within WebSMS would enhance transparency, accountability, and ease of access to
records related to late inspections, providing a more robust system for tracking and managing
inspection compliance.
Action plan 4
27. The audit found that while council officers confirmed that risks associated with late inspections
of high-priority structures are addressed as they arise, there is no formalised documentation of
specific risk mitigation plans within the WebSMS system. To strengthen oversight, it is
recommended that a formal process for documenting these risk mitigation strategies within the
WebSMS system be implemented, ensuring consistent and transparent management of
inspection delays.
28. The audit found that resources are reallocated as needed in response to inspection delays,
including prioritisation for high-priority structures. This flexible approach helps to mitigate risks
associated with inspection delays and ensures that high-priority structures receive attention
promptly. However, formalising this process with documented procedures could enhance
consistency and transparency in resource reallocation, providing clearer guidance for staff and
further supporting effective risk management.
There are regular performance reports generated and reviewed by relevant stakeholders and
reports include key performance indicators in relation to inspection schedules and late
inspections. 
29. The Council's Annual Report highlights key data on the condition of bridge stock and associated
challenges. The Bridge Stock Condition is now evaluated using a weighted average per span, with
recent cyclic assessments showing a decline in condition over time. In the most recent cycle
(2022-24), the Average Bridge Stock Condition was reported as 87.86 (out of 100), and the
Critical Element Stock Condition as 79.08 (out of 100), both showing a significant drop compared
to earlier cycles, such as 2016-18 when these figures were 89.46 and 82.40, respectively. A

Page 10

10
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
backlog of maintenance works currently amounts to £32.4 million, exacerbating the declining
condition trend. Additionally, the report identifies specific weak bridges within the Council's
network, which are subject to weight restrictions ranging from 3 tonnes to 18 tonnes. Examples
include Laggan Old Bridge (10T, Islay), Glendaruel Bridge (3T, Cowal), and Kilbride Bridge (10T,
Cowal). In the near term it is unlikely that significant increases in capital budget allocation will
enable a meaningful programme of works to address this backlog maintenance liability. These
findings underscore the need for prioritised maintenance to address the growing infrastructure
deficit and ensure public safety and functionality while recognising that difficult decision may be
required that prioritizes the limited available resources to maximise the preservation of
transport network functionality on the more highly used / critical road routes.
30. The audit found that no key performance indicators (KPIs) are currently established for the
bridge inspection process, resulting in an absence of KPI-based performance reporting.
Introducing relevant KPIs and incorporating them into regular performance reporting would
enhance transparency, facilitate better decision-making, and support the timely identification
and resolution of potential issues in bridge inspections.
Action plan 1
31. The audit found that no performance reports are currently generated within the WebSMS
system for distribution to relevant stakeholders. Without a structured reporting process, key
stakeholders lack critical information needed to monitor inspection performance and allocate
resources effectively. It is recommended that the Council establish a clear reporting framework
to ensure that key stakeholders receive regular performance updates, enhancing oversight and
accountability in bridge management.
Action Plan 1
32. The audit determined that performance reports are not forwarded to Departmental
Management Team (DMT) meetings or other relevant forums. Establishing regular performance
reporting and including these in DMT meetings would strengthen monitoring practices, foster
accountability, and enable timely decision-making regarding the bridge inspection management.
Action plan 1
33. The audit revealed that no regular performance reports generated specifically for late bridge
inspections, and consequently, no formal action plans or follow-up measures are developed to
address these delays. Implementing a structured reporting process focused on late inspections,
along with associated action plans to resolve identified issues, would improve oversight and help
ensure that inspection schedules are adhered to, thereby enhancing the safety and reliability of
the bridge infrastructure.
Action Plan 1
34. Regular team meetings are held to discuss bridge inspection matters, ensuring ongoing oversight
and coordination. A review of the meeting minutes confirmed that these discussions address key
issues related to inspection schedules, prioritisation of high-risk structures, and any arising
concerns regarding bridge maintenance and safety.

Page 11

Appendix 1 – Action Plan
No Finding Risk Agreed Action Responsibility / Due Date
High 1
Performance Reporting
There are no regular performance reporting on the
following:
 Structured reporting framework to distribute
performance reports to key stakeholders on a
regular basis.
 Performance reporting into Departmental
Management Team (DMT) meetings and other
relevant forums to improve monitoring,
accountability, and decision-making.
 Specific regular performance reports for late
bridge inspections, accompanied by formal action
plans and follow-up measures to address delays
and ensure compliance with inspection schedules.
The absence of regular
performance reporting also
restricts visibility for relevant
stakeholders, which may lead
to delays in addressing late
inspections and hinder
proactive maintenance
planning.
A report setting out key
performance information in
relation to the annual programme
of bridge inspections will be
produced for review by the RIS
senior management team on a
quarterly basis. The report will be
received by the RIS senior
management team by the end of
the month following quarter end
at the latest. The first of these
reports will be produced for
review during the month of April
2025 for Q4 of 2024.
A Quarterly Report on appropriate
KPIs will be generated by WDM
and can be aligned around ABC
Reporting timescales.  Currently a
QR is being implemented to
report on every bridge’s most
recent inspection.  The Quarterly
Report will be accompanied by
the most recent Late Inspections
report.
The overall suite of performance
measures used by RIS is currently
under review. Until such time as
this review work is completed and
a refreshed approach to service
performance reporting is
implemented the HoS will provide
a by exception report to the
Infrastructure Design
Manager 
30th June 2025

Page 12

12
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
No Finding Risk Agreed Action Responsibility / Due Date
Departmental Management Team
on a quarterly basis setting out
key metrics and risks associated
with the annual bridge inspection
programme. This reporting will
commence for the Q4 period of
2024 and will follow reporting into
the RIS senior management team
and will therefore take place as
early as possible in the month 2
months after quarter end i.e.
commencing in June 2025.
Medium
2
Procedures
The Council should consider developing its own
documented procedure for bridge inspections which sets
out how the Council will achieve and ensure compliance
with Well-managed Highway Infrastructure Code of
Practice and DMRB CS 450. This would enhance clarity,
accountability, and adaptability, ensuring that all
inspection activities align with both external standards and
the Council’s specific operational requirements.
Reliance on national Codes of
Practice and Standards
without internalised
procedures may reduce
adaptability to local
requirements, create gaps in
accountability, and result in
inconsistent application of
inspection processes.
A service manual will be
developed setting out how the
Council implements and assures
compliance with Well-managed
Highway Infrastructure Code of
Practice and DMRB CS 450. This
will not seek to replace the
national Code of Practice but
rather to articulate how the
Council ensures compliance with
it.
Infrastructure Design
Manager
30th September 2025
Low 3
Training
While the client has indicated that Bridge Inspectors have
completed relevant certification courses and received in-
house training on using the WebSMS asset management
system, there is no formal record of training maintained
on file.
The absence of documented
training records creates a gap
in verifying staff competency,
which could lead to potential
compliance issues and hinder
accountability.
Records shall be stored on
Infrastructure Design network
drive until instructed otherwise.
Infrastructure Design
Manager 
31st March 2025

Page 13

13
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
No Finding Risk Agreed Action Responsibility / Due Date
Low 4
Audit Trail Re late Inspections
The audit found that there is currently no audit trail within
the WebSMS system (WDM) to document late inspections,
including reasons for delays, actions taken, and
stakeholder communication.
Without an integrated,
automated audit trail, there is
limited transparency and
accountability in tracking late
inspections.
Late Inspections are currently
being recorded manually via a
report Infrastructure.
Design can export on WDM as to
which reasons are added by the
Infrastructure Design team.
An automatic report is currently
being built within WDM that will
send a late inspections report. 
Late inspections and actions
needed to ensure they are
undertaken will form part of the
quarterly reporting to RIS senior
management team. This will
enable the Infrastructure Design
Team to highlight risks, articulate
mitigations and to seek support
where required to implement
these.
Infrastructure Design
Manager
31st March 2025

Page 14

14
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows:
Grading Definition
High A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error.
Medium
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.
Low Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives.
VFM An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).

Page 15

15
Argyll and Bute Council – Internal Audit Report – Bridge Asset Management, March 2025
Appendix 2 – Audit Opinion
Level of Assurance Definition
High
Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently.
Substantial
Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale.
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk.
Limited
Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised.
No Assurance
Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues.