ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  4 September 2025 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2025-26 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these in a database and, on a
quarterly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 30 June 2025
including information on actions where the agreed implementation date
has been rescheduled.   
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 30 June 2025. 
3.2 Appendix 1 provides further detail on actions that have been delayed and
rescheduled or superseded.

Page 2

Table 1 – Actions due by 30 June 2025
SMT/Service
Complete
Delayed/
Rescheduled
Total
Internal Audit   
DH – Education Performance & Improvement 0 2 2
DH – Legal & Regulatory Support 0 1 1
KF – Development & Economic Growth 0 3 3
KF – Roads & Infrastructure Services 0 10 10
KF – Financial Services 2 0 2
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
3 1 4
H&SCP (SW) – Children and Families and Criminal
Justice
2 0 2
LiveArgyll 1 0 1
External Audit   
Nil   
TOTAL 8 17 25 
Table 2 – Actions due after 30 June 2025
SMT/Service
Complete
Superseded
On Course
Total
Internal Audit    
DH – Commercial Services 0 0 2 2
DH – Education Performance & Improvement 0 0 5 5
DH – Legal & Regulatory Support 0 0 7 7
KF – Development & Economic Growth 0 0 1 1
KF – Roads & Infrastructure Services 1 0 3 4
KF – Financial Services 1 1 1 3
H&SCP (IJB) – Adult Services (Older Adults & Community
Hospitals
0 0 1 1
H&SCP (IJB) – Strategic Planning & Performance 0 0 8 8
H&SCP (SW) – Adult Services (Mental Health Learning
Disability, Addictions & Lifelong Conditions)
0 0 1 1
H&SCP (SW) – Adult Services (Older Adults & Community
Hospitals
1 0 1 2
H&SCP (SW) – Children and Families and Criminal
Justice
1 0 7 8
H&SCP (SW) – Finance/Transformation 0 0 3 3
H&SCP (SW) – Strategic Planning & Performance 0 0 2 2
LiveArgyll 0 0 1 1
External Audit    
Nil    
TOTAL 4 1 43 48

Page 3

4.0 CONCLUSION 
4.1 Satisfactory progress continues to be made implementing audit actions. 
5.0 IMPLICATIONS 
5.1 Policy – None
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Customer Service – None
5.6 Risk – None
5.7 Climate Change – None
5.8 Fairer Scotland Duty – None
5.9 Equalities – protected characteristics – None
5.10 Consumer Duty – None 
5.11 Island Communities – None
5.12 Children’s Rights and Wellbeing – None 
Paul MacAskill
Chief Internal Auditor
4 September 2025                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Action Plan Points Delayed & Rescheduled or superseded

Page 4

Appendix 1 - Action Plan Points - Delayed and Rescheduled or Superseded 
Action Plan Points due by 30th June 2025 
Service, Report, Plan no. & Finding Agreed Action Dates Management Comment Responsible Officer
Medium
EDUCATION PERFORMANCE & IMPROVEMENT 
SCHOOL FUNDS & MANAGEMENT OF FUNDS 
4. Practical Training   
With the exception of the LEON module, no
formal training programme or support is in
place for those involved in the management and
administration of school funds. This is in part
reflected in the inconsistent practices across
schools visited.  Practical training should be
developed and provided for head teachers,
committee members and clerical staff involved
in the management and administration of
school funds. 
Training on school fund procedures
will be carried out. Who will carry
out the training will be clarified as
part of the management circular
review. 
30/06/2025
31 Dec 2025 
The training will be developed
over the summer for
implementation with the new
School Fund Committees from
August. 
Delayed and Rescheduled 
School Services Support
Manager 
High
EDUCATION PERFORMANCE & IMPROVEMENT 
SCHOOL FUNDS & MANAGEMENT OF FUNDS 
5. Grants   
The Circular states that schools must ensure
that the Education Authority has knowledge of
any grant application for monies made to third
parties that involve the school fund.  There is no
established process for this.  
· The Circular should be updated to state that
AFAs must be consulted prior to grant
applications being submitted to ensure that the
applicant is the correct beneficiary and that
income and expenditure is accurately recorded.  
Circular will be updated to reflect
an instruction that AFAs must be
consulted prior to grant
applications being submitted. A
central grant register for grants
over £1,500, covering all schools,
will be created and maintained.
Any grants over £1,500 will have to
be reported to Finance and this will
be reflected in the updated
circular. 
30/04/2025
31 Dec 2025 
Whilst a template is in place for
a grant register, not all grants
are captured at this
stage.  Work is ongoing to
ensure all grants are registered
centrally. 
Delayed and Rescheduled 
School Services Support
Manager

Page 5

Medium
DEVELOPMENT & ECONOMIC GROWTH 
PLANNING 
1. Staff Training 
Once the incorporation of the IDOX
project is completed a training
schedule will be introduced
covering both the new system and
other relevant areas such as the
National planning for framework 4.
31/03/2024
31/12/2024
31/03/2025
30/06/2025
30 Sep 2025 
Planning staff have access to a
range of training opportunities
throughout the year.  We are
operating a flexible and
dynamic range of training
options which can be accessed
Process and
Productivity
Improvement Officer 
Service, Report, Plan no. & Finding Agreed Action Dates Management Comment Responsible Officer
· A central grant register for grants over £1,500,
covering all schools, should be created and
maintained. 
Low
LEGAL & REGULATORY SUPPORT 
Freedom of Information 
3. Publication Scheme   
The Council’s Publication scheme not updated
since May 2021, and the Council’s website was
updated in 2023.  A review of the Council’s
Publication scheme should be undertaken,
including checking that any links to information
are still working. 
Review and Update Publication
Scheme, publish on Website and
provide link to Audit. 
31/03/2025
30/06/2025
30 Sep 2025 
Report still to be considered by
ELT. Subject to approval, an
anticipated report will be
published by end of July. 
Delayed and Rescheduled 
Compliance &
Regulatory Officer 
Low
DEVELOPMENT & ECONOMIC GROWTH 
Private Sector Housing Grants & Adaptions 
3. Procedure Notes and Shared Documents
While the vast majority of requirements are
included there would be benefit to updating
these to reflect current working practices, which
have evolved due to hybrid working
arrangements and the digitalisation of records. 
Consideration should be given to creating a
checklist to ensure consistent application of
processes. 
Procedures and documents will be
reviewed and updated. Checklists
to be drawn up and introduced
when updating the procedures. 
31/12/2022
30/06/2023
31/03/2024
30/09/2024
30/12/2024
30/06/2025
31 Oct 2025 
Following approval of the
Revised Scheme of Assistance,
the documents and procedures
currently in the process of being
updated.  This is happening
slowly due to staff sickness. 
Delayed and Rescheduled 
Team Lead - Housing
Operations

Page 6

Planning do not currently have in place a
training schedule for 2023/24 for planning
officers. 
by staff, as and when is best
suited to their individual
learning needs, the needs of the
department, and individual
specific training needs that arise
as a requirement of new work
items.  Annual training events
are held that all planners are
requested to attend.  For
example, an internal Planning
conference was held focussing
on a number of topics such as
Biodiversity, the role of GIS in
Planning, Strategic
Development Frameworks, and
investment in the national grid
and its impacts on Argyll and
Bute. Staff can attend external
conferences if they wish to do
so such as the HPs’ conference
held in Kilmarnock this year. We
are also working with several
key stakeholders such as HES to
develop training modules for
Planning staff and we are
looking at how we can work
with the University of the West
of Scotland to enable staff to
access degree level Planning
courses.  In addition, staff can
access a range of digital course
specialising in Planning topics
and there is also a range of
internal courses available on
back-office systems, corporate
priorities, and other topics such
as cyber security and the use of
AI and digital tools such as

Page 7

copilot etc.  Creating a training
schedule is further complicated
by a lack of available external
courses however when staff do
attend these they are also asked
to cascade learning to other
colleagues through notes taken.
Lastly the council is also
undertaking a transformational
process and planners attend an
increasing number of
workshops and seminars that
often involve a place-based
approach working with other
council services and external
partners.  This approach is likely
to increase in the future.   
Delayed and Rescheduled 
Medium
DEVELOPMENT & ECONOMIC GROWTH 
SHORT TERM LETS 
2. Oracle – Compulsory Fields   
A number of documents of supporting evidence
must be submitted with the licence application
prior to the issuing of the licence. Oracle
currently has a number of compulsory fields
which require to be completed, this does not
include the uploading of evidence. Applications
can be submitted without all the supporting
evidence attached resulting in time-consuming
delays contacting the applicants. 
1. Upgrade to be applied to Oracle
system to ensure that applications
made without all the necessary
certification and documentation,
cannot be submitted through the
on-line system. 
2. A similar approach will be
applied to paper-based
applications 
01/05/2025
30 Aug 2025 
1. IT system changes ongoing.
Revised application
forms/processes for both New
Applications and Renewals is
currently in the testing stage. 
2. The paper form cannot be
developed until the layout of
the electronic one is finalised as
they must be the same.
Currently we have contacted all
applicants who are due for
renewal advising of the
situation and further contact
will be made once the forms are
agreed. 
Delayed and Rescheduled
Regulatory Services and
Building Standards
Manager

Page 8

High
ROADS & INFRASTRUCTURE SERVICES 
BRIDGE ASSET MANAGEMENT PLAN 
1. Performance Reporting   
There are no regular performance reporting on
the following: · Structured reporting framework
to distribute performance reports to key
stakeholders on a regular basis. · Performance
reporting into Departmental Management Team
(DMT) meetings and other relevant forums to
improve monitoring, accountability, and
decision-making. · Specific regular performance
reports for late bridge inspections, accompanied
by formal action plans and follow-up measures
to address delays and ensure compliance with
inspection schedules. 
A report setting out key
performance information in
relation to the annual programme
of bridge inspections will be
produced for review by the RIS
senior management team on a
quarterly basis. The report will be
received by the RIS senior
management team by the end of
the month following quarter end at
the latest. The first of these reports
will be produced for review during
the month of April 2025 for Q4 of
2024. A Quarterly Report on
appropriate KPIs will be generated
by WDM and can be aligned
around ABC Reporting timescales.
Currently a QR is being
implemented to report on every
bridge’s most recent inspection.
The Quarterly Report will be
accompanied by the most recent
Late Inspections report. The overall
suite of performance measures
used by RIS is currently under
review. Until such time as this
review work is completed and a
refreshed approach to service
performance reporting is
implemented the Head of Service
will provide a by exception report
to the Departmental Management
Team on a quarterly basis setting
out key metrics and risks
associated with the annual bridge
inspection programme. This
reporting will commence for the
Q4 period of 2024 and will follow
30/06/2025
30 Sep 2025 
Bridge Inspection status report
defined, and report can be
submitted in draft form for
comments from Management /
Executive. Final report to be put
in place and reporting channel
confirmed. 
Delayed and Rescheduled 
Infrastructure Design
Manager

Page 9

reporting into the RIS senior
management team and will
therefore take place as early as
possible in the month 2 months
after quarter end i.e. commencing
in June 2025.
Low
ROADS & INFRASTRUCTURE SERVICES 
BRIDGE ASSET MANAGEMENT PLAN 
4. Audit Trail re Late Inspections   
The audit found that there is currently no audit
trail within the WebSMS sysytem (WDM) to
document late inspections, including reasons for
delay, actions taken and stakeholder
communication. 
Late Inspections are currently
being recorded manually via a
report infrastructure.  Design can
export on WDM as to which
reasons are added by the
Infrastructure Design team. An
automatic report is currently being
built within WDM that will send a
late inspections report.  Late
inspections and actions needed to
ensure they are undertaken will
form part of the quarterly
reporting to RIS senior
management team. This will enable
the Infrastructure Design Team to
highlight risks, articulate
mitigations and to seek support
where required to implement
these. 
31/03/2025
30 Sep 2025 
Previously identified errors have
been rectified, and
implementation of Late
Inspections functionality has
now been further developed.
Backlog of information held
externally from WDM system
now able to be
recorded.  Currently underway.
Actions requested from
auditable to be fulfilled at this
stage, despite ongoing
refinement of WDM and data
entry.
Full implementation on track for
September 2025. 
Delayed and Rescheduled 
Infrastructure Design
Manager 
Low
ROADS & INFRASTRUCTURE SERVICES 
Burial Records 
6. Historical Register Information   
Finding;  The Burial and Cremation (Scotland)
Act 2016 (The Act) requires information to be
retained electronically although this is not
currently in force it will be at a future date.  The
BACAS system has been partially updated with
historical information recorded in burial
The service will source temporary
assistance to update records
during Summer 2024. 
30/06/2024
31/12/2024
30/06/2025
30 Sep 2025 
Still looking to recruit however
resource has been identified
within the teams to get this
project underway with an
attempt to recruit and backfill
the administrative roles. 
Delayed and Rescheduled 
Operations Manager,
Roads and
Infrastructure Services

Page 10

registers, it has not been possible to update
with all information due to the volume of work
involved.   Recommendation; Source temporary
additional resource to update historical burial
records on BACAS.
Low
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS 
2. CalMac Charges 
Calmac, the main ferry operator uses the
Council’s Piers and Harbours on a daily basis,
with administratively intensive process in place
for charging. 
Have an agreement (financial) in
place by the end of the year. 
31/12/2023
31/03/2024
30/06/2024
30/11/2024
30/06/2025
31 Dec 2025 
Being progressed with senior
management within CalMac. 
High level options appraisal to
be carried out investigating
payment mechanisms that can
be incorporated into the new
Harbour Access Agreement
(HAA) 
The draft Harbour Access
Agreement will be ready for
review by legal representatives
by December 2025 
Delayed and Rescheduled 
Marine Operations
Manager 
High
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS 
3. SLAs 
A number of companies, including large fish
farming businesses, make use of our facilities on
a regular basis, however, there are no SLAs in
place. We were advised that work is currently
being undertaken to put Harbour Access
Agreements in place. 
Any agreement must be supported
by both parties and Argyll & Bute
Council legal department. May tie
in with No 2 above. Provide a
report to Head of Service and
Director with options. 
1. Identify potential partners 
2. Negotiation period 
3. Legal support in drafting
agreement 
31/12/2023
31/03/2024
30/06/2024
30/11/2024
30/06/2025
31 Dec 2025 
Work is ongoing to identify
bridging partners 
First batch of agreements is
being developed on a priority
basis in terms of value and risk,
and will be ready by end of
December 2025 
Delayed and Rescheduled 
Marine Operations
Manager 
Low
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS 
Actionable evidence and
enforcement will continue to be an
issue where there are no Argyll &
Bute Council personnel on site.
31/12/2023
31/03/2024
30/06/2024
App being developed by
supplier to allow Harbour
Masters to monitor and enforce
at priority sites via CCTV. Report
Marine Operations
Manager

Page 11

4. Remote Piers and Harbours  
Harbourmasters based at the main piers and
harbours are able to record the use of the
facilities where they are predominantly based,
however, a number of piers, slipways and
harbours are in remote locations and are
difficult to manage in terms of use. In addition,
there are no robust procedures in place to
identify commercial tour vessels using our
facilities potentially resulting in a loss of income
for the Council. 
Investigate issues and possible
solutions with Harbour Masters
and provide options for
consideration in report to DMT. 
30/09/2024
30/11/2024
30/06/2025
31 Dec 2025 
will be ready for DMT in
December 
Delayed and Rescheduled 
Low
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS 
5. Fishing Fleet   
Fees and charges for the fishing fleet within the
Council area are managed by the fishing fleet
whereby they advise us of the value of their
landings once the catch has been sold. There is
no back up information provided to substantiate
the value, and it is generally paid through cash
receipting or by cheque. 
Investigate issues and possible
solutions with Harbour Masters
and provide options for
consideration in report to DMT. 
31/12/2023
31/03/2024
30/06/2024
30/09/2024
30/11/2024
30/06/2025
31 Dec 2025 
Work is ongoing to develop
solution for verification of value
of catches and electronic
payment of fees. Report will be
ready for DMT in December 
Delayed and Rescheduled 
Marine Operations
Manager 
Low
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS
6. Management of Debt   
The outstanding debt owed to the Council at the
end of June in respect of Piers and Harbours
amounted to £143k.  There are a number of
long-term outstanding debts, and it was noted
that in some instances there is continued use of
our facilities by vessels who have outstanding
debts dating back to 2019.
Investigate with legal department
recovery or write-off options. 
Provide a report to Head of Service
and Director with options. 
31/12/2023
31/03/2024
30/06/2024
30/09/2024
30/11/2024
30/06/2025
31 Dec 2025 
Debt reviewed by Marine
Operations Management team
and Finance on a regular basis
and pursued where possible. 
Aged debt and ability to pursue
has been identified. Where
necessary, write off to be
identified by Marine Operations
Manager and processed in
terms of the Corporate Debt
Recovery Policy 2024
Marine Operations
Manager

Page 12

Report will be ready for DMT in
December 
Delayed and Rescheduled 
Low
ROADS & INFRASTRUCTURE SERVICES 
PIERS & HARBOURS 
8. Published Pier and Harbour Dues and Fees 
Harbour fees and dues are published on the
Council website on an annual basis following
being agreed and set at the Council’s budget
setting meeting, however, these are not in a
format that can be easily downloaded. 
Produce a ‘Schedule of Harbour
Charges’ for Harbour Board
approval. 
30/11/2024
30/06/2025
31 Dec 2025 
Work is ongoing to develop
schedule that is clear and easily
understood. 
Draft for approval will be
complete by end of December
2025 and ready for approval for
first Harbour Board of 2026 
Delayed and Rescheduled 
Marine Operations
Manager 
High
ROADS & INFRASTRUCTURE SERVICES 
WARDEN SERVICES 
3. Second Bin Service Verification   
Wardens are expected to verify the veracity of
applications from customers for a second
domestic bin service. This requires the warden
to confirm that information provided by the
customer is accurate and meets the defined
criteria. The information provided to
substantiate an application can be very personal
and sometimes of a sensitive medical nature.
Wardens have been asked to provide this
service but have received no formal training in
how to ensure a customer’s dignity is
maintained or to ensure they are aware of the
requirements of General Data Protection
Regulation (GDPR) in relation to personal data
Review the process for;   
Review the second bins that are in
place and the process for
rationalising. This review to also
give consideration to composition
and identify opportunity to
increase recycling and reduce
general waste. 
31/03 2022
30/09 2022
31/12/2022
31/03/2023
30/09/2023
31/12/2023
31/03/2024
31/03/2025
30/09/2025
30/06/2025
31 Mar 2026 
The second bin review will be
part of an overall waste delivery
project including wider aspects
of the service such as assisted
pullouts, service delivery on
private roads and commercial
refuse.  Project plan currently
being agreed and will be
communicated to the RIS
review board.  Timescales for
the project and implementation
plan will require to be agreed.
This is part of a bigger review on
commercial waste contracts and
self-catering establishments. 
Delayed and Rescheduled 
Operations Manager,
Roads & Infrastructure
Services

Page 13

for this specific process. 
Due to the sensitivity of this process, and the
potential risks associated with data protection it
is recommended that the current verification
process is reconsidered to determine if it is
appropriate to maintain it in its current form. If
it is decided, it should be retained then there
should be engagement with the Council’s
Governance and Risk Manager to ensure it is
being carried out in full compliance with GDPR. 
Medium
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
CLIENT FUNDS PROGRESS REVIEW 
2. Meeting service users financial needs   
Detail Restricted. 
Detail Restricted.  30/12/2024
31/03/2025
30/06/2025
30 Sep 2025 
Detail restricted. 
Delayed and Rescheduled 
SW Admin Manager 
Action Plan Points due after 30th June 2025 
Service, Report, Plan no. & Finding Agreed Action Dates Management Comment Responsible Officer
Medium
FINANCIAL SERVICES 
CAPITAL MONITORING 
1. Capital Programme Planning & Management
Guide   
The Council’s Capital Guide has not been revised
since 2018 and requires a review to ensure it
reflects current working practices and provides
appropriate support to officers involved in the
capital monitoring process. The Council is
Capital Planning and Management
Guide to be updated once the
Capital Strategy has been approved
to ensure the two are aligned and
provide clarity. 
31/03/2022
30/09/2022
31/12/2022
31/03/2023
30/09/2023
31/12/2023
31/03/2024
31/03/2025
30/09/2025 
This action has been
superseded by a wider ‘Review
of Capital Arrangements’
approved by members, as part
of the 2025/26 budget process. 
The review requires to be
progressed by ELT during
2025/26.  A discussion paper
was considered by ELT in May,
with next steps agreed and a
further report to be brought
back to ELT in September.    
Head of Commercial
Services/Finance
Manager

Page 14

Service, Report, Plan no. & Finding Agreed Action Dates Management Comment Responsible Officer
currently developing a new Capital Strategy
which is to be presented to the Policy and
Resources Committee in August 2021 and we
recognise that a review of the Guide should be
conducted after the Strategy has been finalised
to ensure the two documents complement each
other and. The Guide could also benefit from
being linked to, or referencing, other relevant
Council processes, in particular the Project
Management section on the Hub.   
Superseded