Democracy Spraffa

Internal Audit and Counter Fraud Summary of Activities

Argyll and Bute Council · 4 September 2025
Back to Audit and Scrutiny Committee — 4 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  AUDIT & SCRUTINY COMMITTEE   
FINANCIAL SERVICES  04 SEPTEMBER 2025  
INTERNAL AUDIT AND COUNTER FRAUD SUMMARY OF ACTIVITIES 
1. SUMMARY  
1.1 The objective of the report is to provide the Audit and Scrutiny Committee (the
Committee) with a summary of Internal Audit activity and progress during quarter
one of 2025/26.  
1.2 Core activities together with a progress update statement are shown below: 
• 2024/25 Audit Plan progress: The plan is complete and all items reported to
the Committee. 
• 2025/26 Individual Audits undertaken: Two audits have been completed
during the period, one has been assessed as providing high assurance and
one substantial assurance. In addition, two pieces of audit verification work
were undertaken relating to the SPT claim and Local Government
Benchmarking Framework (LGBF). (Where HSCP and LiveArgyll Audits are
included, these are provided for information only). 
• 2025/26 Audit Plan progress: The plan is currently on track. In the event that
this position was to change, we will flag it to the Committee as part of the
quarterly updates. 
• Scrutiny: Planned work for 2025/26 has been agreed by the Committee along
with those who will serve on the Panel, and work on this will commence later
in the calendar year. 
• Counter Fraud: The Counter Fraud Team (CFT) is continuing to rebill council
tax accounts and recovery of funds is underway.  All other aspects and
referrals are being considered, investigated and evaluated and the Counter
Fraud Team remain vigilant to protect our public purse. The established CFT
team member is on secondment to Housing for career and personal
development for a two year period.  The CFT have obtained a member of
staff, again on secondment for the same time period who has recently
completed the CIPFA Fraud Specialist Course. The team lead is currently
progressing toward the completion of year 3 of a Master in Accountancy
course.   
• Continuous Monitoring Programme Testing: A number of auditable units
are subject to continuous testing. There have been two new issues which we
have identified this quarter. 
• Performance indicators: Current status is green / on track.

Page 2

2. RECOMMENDATIONS  
2.1 To review and endorse the Summary of Activities report.   
3. DETAIL  
3.1 Two audits have been completed since the previous Committee in June 2025. 
Audits Completed 
• Education Maintenance Allowance (EMA)
• Music Services 
Verification Audit Work Completed 
• SPT Annual Claim – See section 3.6 for further details
• Local Government Benchmarking Framework – See section 3.7 for further
details 
Audits in Planning / in Progress
reported to a future meeting of the Committee. 
• Self-Directed Support (Draft Report – awaiting management response)
• Payroll – iTrent
• ICT Disaster Recovery
• School Residential Trips
• Capital Programme – Management and Monitoring
• Building Cleaning
• Oban Airport
• HSCP Audits  
3.2 In addition to those already in progress, indicative audits planned for Q3 2025/26
are: 
• Street Lighting
• Performance Management Arrangements and Reporting   
2025/26 Audit Plan  
3.3 Work is ongoing and is currently on track at this point in time.   
Scrutiny  
3.4 It was agreed by the Committee that the chosen subject area for the 2025/26
scrutiny review would be on the Council’s preparedness for the Bio-Municipal
Waste (BMW) Landfill Ban.  A background and scoping document will be prepared
and issued to the Panel members for agreement in due course. We anticipate that
this will commence towards the end of the calendar year.

Page 3

Counter Fraud  
3.5 The CFT is progressing well with both team members fully CIPFA accredited fraud
investigators. The current investigator has taken on a 2 year secondment to empty
homes for further skills development and this is due to come to an end in
September 2025 with discussions ongoing regarding transitional arrangements. 
The backfill of the investigator post was again on a secondment basis which is also
coming to an end.  The seconded member of staff has completed and passed the
CIPFA Fraud Specialist course. Efforts are underway to maintain service delivery
for the terminations of both secondments. 
Routine work continues and is progressing to track the full income due and to be
recovered as part of this ongoing work. Based on the amount of additional billing,
even accounting for a degree of non-recovery, the indications are that the team are
anticipating exceeding their annual target. In addition, the team are raising
awareness of the Council’s zero tolerance to fraud and this will help act as a
deterrent to fraud being perpetrated in the first place. 
Visits continue to play a vital role in the CFTs proactive and reactive work.  Recent
visits have taken place in Islay, Dunoon, Tarbet and surrounding villages. 
Investigations and visits will take place in the outer islands toward the autumn. 
Both officers continue to be proactive and make visits when information is received
via the online portal and other islands will soon be visited. 
The CFT continue to link in with Internal Audit and Debt Recovery, and where
necessary to assist, trace persons and open communication to long term debts for
recovery. Several cases have resulted in large scale rebilling. 
Second homes and Non-Domestic Rates are playing larger roles in the CFT’s 
investigations with several claims already adjusted.  These will remain proactive
areas. 
The CFT now have an established referral system in place from council tax teams
and have already liaised with this team going forward into 2025 for the review of
the second and holiday home tax changes.  The aim is to assist with the single
person discount review within 2025. 
The CFT continue to work closely with the empty homes team to support each
other in our remits.  Work and communication between each department is key in
identifying and finding appropriate solutions to enable empty homes to return to
residency or open market. 
The NFI exercise continues to be a routine work area for the CFT.  The 2024/2025
exercise has extra data to be uploaded this September and work on this element
will commence when this has been matched and released.  The initial part of the
matching exercise is coming to a close.  Any remedial or conclusive work will be
completed when and where appropriate.  The system is reviewed periodically for
any updates 
Since the inception of the CFT a total of £1,514,262 has been rebilled and
£950,168 has been recovered. A recovery percentage of 62% has been achieved

Page 4

at the last review of the figures. Recent large rebilling has been passed to other
agencies, and this takes time to process and progress payment plans. 
Additional Updates from Quarter Two  
3.6 The Strathclyde Concessionary Travel Scheme (SCTS) is founded on the
provision of the Transport Act 1985, which allows authorities to make
concessionary travel schemes in certain circumstances.  The SCTS is
administered by Strathclyde Partnership for Transport (SPT) on behalf of the
SCTS Joint Committee consisting of 12 local authorities to issue travel cards which
entitles the holder to discounted travel by reason of age or disability, and provide
reimbursement of fare reductions on rail, subway and ferry services.  Argyll and
Bute Council operates two ferry routes that qualify for concessionary fares within
the SCTS.  Internal Audit are required to provide a certificate of accuracy on an
annual basis to confirm that the details pertaining to the number of concessionary
passengers carried and the equivalent standard fares are consistent with the
quarterly claims for reimbursement of the difference between the concessionary
fare charged and the standard fare.  The data and supporting information for
quarter 4 2024/25 claim was provided to Internal Audit for review and found to
provide an accurate representation of the number of passengers and value of fares
charged, and the reimbursement value was found to have been calculated in
accordance with the SCTS requirements.  The certificate of accuracy was
therefore issued on 11 June 2025.  
3.7 A sample of data in respect of the Statutory Performance Indicators (SPI’s) that are
required to be returned by councils as part of the Local Government Benchmarking
Framework (LGBF) must be reviewed by Internal Audit for submission to the
Improvement Service by 31 August each year.  Internal audit carry out this work in
collaboration with colleagues in performance management.  Internal Audit was
provided with data from which to select indicators for review on 25 June and as
large variances were reported in ‘Other Local Government Employees – Sickness
Absence – including Covid, ‘Sport and Leisure Management’, and ‘Museum
Services’ these indicators were selected for review.  ‘Teachers – Sickness
Absence – including Covid’ was also reviewed alongside Teachers data due to
large numbers involved. ‘Council Tax Collection’ was selected as this has risen in
both the past two years and ‘Council Tax Income’, as this has slightly dipped this
year and both indicators use similar data sources. Some minor errors were
identified in the Sport and Leisure Management, and Museum Services, these
were immaterial and did not require to be amended prior to submission to the
Improvement Service. The supporting data were found to contain a known issue
and an incorrect calculation. The relevant officers are progressing with plans to
ensure this is not repeated in future.  Therefore, Internal Audit are offering a
substantial level of assurance for all 6 of the indicators reviewed.  
3.8 The Council has entered a ten-year programme to deliver the Rural Growth Deal
(RGD) for Argyll and Bute.  The Council, as the accountable body for this
programme is required to allocate and account for distribution of the funding to
partners, third parties and other bodies in accordance with the approved
governance arrangements.  The Council’s Chief Internal Auditor has been
appointed to coordinate audit activity throughout the programme, this will include
liaison with partner auditors to obtain annual confirmation of regular and planned
reviews of grant funded activities and a specific review of RGD within the
Council’s Annual Audit Plan at least every two years.  Discussions regarding the
audit input required have taken place and the first review will be included within

Page 5

the 2025/26 Internal Audit Plan. We will closely monitor the additional work
associated with this appointment going forward and determine whether
additional resources may be required.  
3.9 Our work as the contracted Internal Auditors for the HSCP has been progressing
well and priority has been given in this area due to the availability of staff, work has
completed for 2024/25 and commenced for 2025/26. We will continue to monitor
and report progress to the HSCP’s Audit and Risk Committee in relation to the
implementation of recommendations made in previous reports. 
3.10 Internal Audit staff continue to increase their skills and ultimately aim to complete
appropriate professional qualifications at the end of their training programmes.
Internal Audit have two staff members who are undertaking formal professional
training; training is at differing stages but is progressing as expected at this time.
The aim is to develop and retain professional staff on the completion of the
qualifications and increase resilience within the service.   
Continuous Monitoring  
3.11 Our continuous monitoring programme is generally focused on transactional type
activity. Standard audit tests are applied which are relevant to each auditable unit.
Control design tests look at whether the controls in place adequately address the
potential risk event. There has been two new findings within the quarter that
require to be reported. 
Table 2: Continuous Monitoring Findings 
Auditable
Area
Areas Tested Issues Identified Management comment /
action
Budgeting Engagement
logs for cost
centres
Engagement records
not maintained 
Staff will ensure that an
appropriate record is
maintained going forward.
This is a minor issue but will
be rectified.
Payroll Overtime High levels of overtime Management have advised
that an error had been made
in the overtime payment and
details have now been
passed to Payroll who will
make arrangements to
recover the overpayment
element in full.   
3.12 A follow up process is in place whereby management are advised of continuous
monitoring findings and, where appropriate, requested to take remedial action. 
There are currently no outstanding follow-up points arising from previous testing. 
Due to the volume of continuous monitoring tests carried out the decision was
made to report by exception only.     
National Reports  
3.13 A follow up process for national reports is in place whereby management are
advised of national reports published and asked to confirm what, if any, action is

Page 6

planned as a result of the report.  Table 2 details the national reports issued during
quarter four of 2024/25 due to be reported in quarter one of 2025/26.  
Table 3: National Reports 
National Report Issued To Detail Management response/
Action taken
Sustainable
Transport:
Reducing car
use
Executive
Director Kirsty
Flanagan
A lack of
leadership has
meant the Scottish
Government has
made minimal
progress towards
its challenging
climate change
goal of reducing
car use.
All councils in
Scotland have seen
an increase in car
kilometres driven.
The Council works closely with
Hi Trans and a new Regional
Transport Strategy has been
approved that promotes the use
of public transport and active
travel. The council is about to
consult on a new active travel
strategy to inform how new
active travel routes will be
delivered in future years.  At the
moment the majority of funding
to deliver active travel
improvements comes through
competitive bids and we have
been successful in relation to
projects in Kintyre, Roseneath
and Islay.  Further bids have
been made. The council has
also approved a further
consultation on transport issues
that will inform a new local
transport strategy.  The issue of
reducing car usage will be
examined through this however
given we are a predominately
rural authority with limited public
transport options reducing car
usage will be a challenging task
going forward. 
National Fraud Initiative (NFI)  
3.14 NFI data matching involves comparing computer records held by one body against
other computer records held by the same or another body to identify potentially
fraudulent claims and payments to be identified.  Note though that the inclusion of
personal data within a data matching exercise does not mean that any specific
individual is under suspicion. Where a match is found it indicates that there may be
an inconsistency which requires further investigation. No assumption can be made
as to whether there is fraud, error or other explanation until an investigation is
carried out.  A reminder process is in place to ensure that matches are reviewed
on a timely basis.  
3.15 The previous NFI exercise has been completed and results are being compiled by
Audit Scotland.  Any follow up matches will be addressed if necessary.
This exercise was conducted throughout the year by officers and matches checked
and closed accordingly.  NFI provided additional data releases over the course of
the exercise and matches are addressed when these become available.

Page 7

Existing users have been reviewed and new users added where requested, all
users have been and will continue to be informed that matches are available for
review and progress will be monitored monthly by the Counter Fraud team and
reported quarterly to the Audit and Scrutiny Committee.
New HMRC data has been uploaded and released back to us, and teams have
been contacted to start matching this data.    
3.16 The new NFI exercise for 2024/25 has commenced with the data uploads so far
submitted to the Cabinet office for review and therefore data matching when
released.  The new NFI matches will appear in the table below as and when they
have been released and checked. 
Table 4: National Fraud Initiative Progress at 03/08/2025
Operational
Area
Total
Matches
Recommended/Very
High / High/ Medium
Risk Matches
Matches
Complete 
*
WIP
Match Description
CT to Elect
Register 
2422 0 2422 0 CT records to Electoral
Register/ other data sets to
ensure discount awarded
to only those living alone
aged over 18, taking into
account disregarded
occupants.  (CT to other
Datasets will not be
progressed further due to
poor quality data)
CT rising
18s 
85 0 3 0
CT to HMRC
Household
Composition
1106 0 0 0
Housing
Benefits
13 9 9 0 HB records to records in
other authorities / other
datasets including student
loans, payroll and pensions
to identify undeclared
income and capital.
Payroll 300 107 51 0 Payroll records to other
datasets including other
payrolls and pensions to
ensure employee is not
receiving additional
income.
Blue Badges 200 200 183 0 Blue badge records to
DWP data to identify
deceased claimant with
valid badge.
Housing
Waiting list
262 259 199  0 Housing waiting list
records to other
organisations HBCTR and
tenant data to identify
undisclosed changes in
circs or false info.
Council Tax
Reduction
638 174  87 2 CTR records with records
in other authorities / other
datasets including; student
loans, payroll and pensions
to identify undeclared
income and capital
Creditors 2340 0 1126 0  Analyses Creditors data to
identify possible duplicate
vendors and payments,
VAT errors or fraud and

Page 8

multiple vendors sharing a
bank account.
Procurement 67 0 14  0 Payroll records to
Companies House and
creditors’ data to identify
employees who appear to
have a personal interest in
a company that the
authority has traded with.
Business
Rates
154  0 154 0 Business rates records
within and between
authorities to identify
those fraudulently claiming
small business bonus
scheme and grants 
* Work in Progress
Overall Summary of Matches 
Matches
Complete
Work In
Progress
Cleared Frauds Errors Total
Value 
£
Recovering Recovering
Value 
£ 
4248  2 4173 0 75 58,756 0 0 
Internal Audit Development  
3.17 The table below details progress against the action points in our Internal Audit
development plan.  
Table 5: Internal Audit Development Key Actions: updated 31/3/25. 
Area For
Improvement
Agreed Action Progress
Update
Timescale
Review Continuous
Monitoring
Programme
The Continuous Monitoring
Programme will be reviewed to
assess value of existing tests carried
out and establish where these can be
enhanced with greater use of data
analytics .
In progress December
2025 
3.18 Internal Audit scorecard data provided below are aligned to those for internal audit
in the Financial Services service plan.  All indicators are shown as currently being
on track.

Page 9

Table 6: Internal Audit Team Scorecard  
Internal Audit Team Scorecard 2025– 26 – FQ1 25/26 (as at June 2025)
BO115 We Are Efficient and Cost Effective    
Internal Audit Level of Satisfaction
Actual  100% G 
Target 80%
Review of Strategic Risk register
Status Complete G 
Target Complete
Percentage of audit plan completed
Status 100% G 
Target 80%
Percentage of audit recommendations accepted by
management
Actual  100%
G
Target 100% 
4 CONCLUSION  
4.1 The 2025/26 audit plan is progressing as anticipated at this stage in the year,
together with the Counter Fraud Team continuing with visits and pro-active work
throughout Argyll and Bute.  
5 IMPLICATIONS
5.1 Policy – Internal Audit continues to adopt a risk based approach to activity
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Customer Service – None
5.6 Risk – None
5.7 Climate Change – None
5.8 Fairer Scotland Duty – None
5.9 Equalities – protected characteristics – None
5.10 Consumer Duty – None 
5.11 Island Communities – None
5.12 Children’s Rights and Wellbeing – None 
For further information please contact Internal Audit (01546 604108)
Paul Macaskill
Chief Internal Auditor
4 September 2025