Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Customer  Services
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 605522
DX 599700 LOCHGILPHEAD
9 December 2025
NOTICE OF MEETING 
A meeting of the AUDIT AND SCRUTINY COMMITTEE will be held BY MICROSOFT TEAMS on
TUESDAY, 16 DECEMBER 2025 at 2:00 PM, which you are requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES 
2. DECLARATIONS OF INTEREST 
3. MINUTE OF PREVIOUS MEETING OF THE AUDIT AND SCRUTINY COMMITTEE
HELD ON 4 SEPTEMBER 2025 (Pages 3 - 8) 
AUDIT ITEMS 
4. INTERNAL AUDIT AND COUNTER FRAUD SUMMARY OF ACTIVITIES (Pages 9 -
18)  
Report by Chief Internal Auditor 
5. INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2025-26 (Pages 19 -
34)  
Report by Chief Internal Auditor 
SCRUTINY ITEMS 
6. PERFORMANCE REPORTING UPDATE (Pages 35 - 40)  
Report by Executive Director with responsibility for Customer Support Services 
7. 2024/25 COUNCIL ANNUAL REPORT (Pages 41 - 110)  
Report by Chief Executive 
* 8. TREASURY MANAGEMENT STRATEGY AND ANNUAL INVESTMENT
STRATEGY MID-YEAR REVIEW 2025-26 (Pages 111 - 128)  
Report by Section 95 Officer 
9. WORKPLAN (Pages 129 - 130)  
For noting and updating 
Public Document Pack

Page 2

REPORT(S) FOR NOTING 
10. ANNUAL COUNCIL BUSINESS PLAN 2024-25 OUTCOMES (Pages 131 - 178)  
Report by Chief Executive 
REPORT(S) FOR CONSIDERATION 
11. INTERNAL AUDIT REPORTS TO AUDIT AND SCRUTINY COMMITTEE 2025/2026 
(a) Covering Report and Internal Audit Reports (Pages 179 - 284) 
Report by Chief Internal Auditor 
• School Residential Trips
• Building Cleaning 
• Directed Self Support (Direct Payments)
• Oban Airport
• HSCP – Governance Arrangements (For Noting Only)
• HSCP – Partnership Working (For Noting Only)
• HSCP – Workforce Planning (For Noting Only) 
E1  (b) Exempt Internal Audit Report (Pages 285 - 306) 
• ICT Disaster Recovery 
Items marked with an “asterisk” are items, on the basis of information available at the time this
Agenda is published, on which the Committee may not have delegated powers to act, and which
may therefore require to be referred to the Council or another Committee, and that referral may
depend on the decision reached at the meeting. 
The Committee will be asked to pass a resolution in terms of Section 50(A)(4) of the Local
Government (Scotland) Act 1973 to exclude the public for items of business with an “E” on the
grounds that it is likely to involve the disclosure of exempt information as defined in the
appropriate paragraph of Part I of Schedule 7a to the Local Government (Scotland) Act 1973. 
The appropriate paragraphs are:- 
E1   
Paragraph 14   
Any action taken or to be taken in connection with the prevention, investigation or prosecution of
crime. 
Audit and Scrutiny Committee 
Janice Wason Hall (Chair) Councillor Daniel Hampsey
Councillor Graham Hardie Councillor Fiona Howard
Councillor Reeni Kennedy-Boyle Councillor Gary Mulvaney (Vice-Chair)
Councillor Andrew Vennard   
Contact: Lynsey Innis, Committee and Democratic Services Officer Tel:  01546 604338

Page 3

MINUTES of MEETING of AUDIT AND SCRUTINY COMMITTEE held ON A HYBRID BASIS IN
THE COUNCIL CHAMBERS, KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 4 SEPTEMBER 2025 
Present: Janice Wason Hall (Chair) 
Councillor Graham Hardie
Councillor Fiona Howard 
Councillor Gary Mulvaney
Councillor Andrew Vennard 
Attending: Paul MacAskill, Chief Internal Auditor
Shona Barton, Governance Manager
Iain Jackson, Governance, Risk and Safety Manager
Alison Jones, Finance Manager
Mhairi Weldon, Senior Audit Assistant
Mark Outterside, Forvis Mazars 
1. APOLOGIES 
The Chair welcomed everyone to the meeting. 
Apologies for absence were intimated on behalf of Councillors Daniel Hampsey and Reeni
Kennedy-Boyle. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest intimated.   
3. MINUTE OF PREVIOUS MEETING OF THE AUDIT AND SCRUTINY
COMMITTEE, HELD ON 12 JUNE 2025 
The Minute of the previous meeting of the Audit and Scrutiny Committee, held on 12 June
2025 was approved as a correct record. 
4. INTERNAL AUDIT AND COUNTER FRAUD SUMMARY OF ACTIVITIES 
The Committee gave consideration to a report providing a summary of Internal Audit
activity and progress during quarter one of 2025/26 against the following areas: 
Audits Completed 
• Education Maintenance Allowance (EMA)
• Music Services 
Verification Audit Work Completed 
• SPT Annual Claim 
• Local Government Benchmarking Framework 
Audits in Planning/in Progress 
• Self-Directed Support
• Payroll – iTrent
Page 3 Agenda Item 3

Page 4

• ICT Disaster Recovery
• School Residential Trips
• Capital Programme – Management and Monitoring
• Building Cleaning
• Oban Airport
• HSCP Audits 
The report also provided information on work carried out by the Counter Fraud Team; the
continuous monitoring programme and the progress of work carried out as a result of
information received from the National Fraud Initiative.   
Decision 
The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities
report. 
(Reference:  Report by Chief Internal Auditor, dated 4 September 2025, submitted) 
5. INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2025-26 
Consideration was given to a report which provided an update on all open actions as at 30
June 2025 including information on actions where the agreed implementation date had
been rescheduled. 
Decision 
The Audit and Scrutiny Committee endorsed the contents of the report. 
(Reference:  Report by Chief internal Auditor, dated 4 September 2025, submitted) 
6. INTERNAL AUDIT REPORTS TO AUDIT AND SCRUTINY COMMITTEE
2025/2026 
Consideration was given to a report containing the action plans in relation to the following
2 audits:- 
• Education Maintenance Allowance
• Music Service 
Decision 
The Audit and Scrutiny Committee reviewed and endorsed the summary report and the
detail within each individual report. 
(Reference:  Report by Chief Internal Auditor, dated 4 September 2025, submitted) 
7. EXTERNAL AUDIT PROGRESS REPORT 
The Committee considered a verbal update regarding the progress and current status of
ongoing work associated with the completion and delivery of the Annual Audit for 2024-25. 
It was noted that work remains on schedule, with the Annual Audited Accounts expected
to be delivered ahead of timescales achieved in the previous year.     
Decision
Page 4

Page 5

The Audit and Scrutiny Committee noted the information provided. 
8. INTERNAL AUDIT - ANNUAL SELF-ASSESSMENT 
Consideration was given to a report which presented the findings from the recent self-
assessment of the Council’s Internal Audit service performed by a member of the Internal
Audit team. 
Decision 
The Audit and Scrutiny Committee reviewed and endorsed the findings of the assessment
including the identified areas for improvement, where applicable. 
(Reference:  Report by Chief Internal Auditor, dated 4 September 2025, submitted) 
9. CORPORATE COMPLAINTS HANDLING - ANNUAL REPORT 2024/25 
Consideration was given to a report which provided information on how the Council dealt
with complaints during the period 1 April 2024 and 31 March 2025 and performed against
statutory indicators which have been agreed between the Scottish Public Services
Ombudsman (SPSO) and the Local Authorities Complaint Handlers Network. 
Decision 
The Audit and Scrutiny Committee:- 
1. considered and noted the content of the report; and 
2. agreed that the Chair and Vice Chair would liaise with the Governance, Risk and
Safety Manager to discuss the format of future reports to the Committee. 
(Reference:  Report by Executive Director with responsibility for Legal and Regulatory
Support, dated 4 August 2025, submitted) 
10. INFORMATION REQUESTS - ANNUAL REPORT 2024/25 
Consideration was given to a report which provided an update on the position regarding
the recording, responding to, monitoring and reporting of requests for information under
the Freedom of Information (Scotland) Act 2002 (FOISA) and the Environmental
Information (Scotland) Regulations 2004 (EIR’s) for the period between 1 April 2024 and
31 March 2025. 
Decision 
The Audit and Scrutiny Committee considered and noted the information provided. 
(Reference:  Report by Executive Director with responsibility for Legal and Regulatory
Support, dated 4 August 2025, submitted) 
11. AUDIT AND SCRUTINY COMMITTEE ANNUAL REPORT 2024/25 
The Chair presented the Committee’s Annual Report for 2024/25.  The report provided the
Chair’s annual overview of the Committee’s activity during financial year 2024/25 and a
Page 5

Page 6

summary of key developments since the commencement of 2025/26.  The report also set
out how the Committee has fulfilled its remit and provides assurances to the Council. 
Decision 
The Audit and Scrutiny Committee:- 
1. reviewed and endorsed the Chair’s Annual Report; and 
2. agreed that the Chair present the report to the Council, at their meeting scheduled to
take place on 26 November 2025. 
(Reference:  Report by Chair of the Audit and Scrutiny Committee, dated 4 September
2025, submitted) 
12. STRATEGIC RISK ASSURANCE MAPPING 
Consideration was given to a report which set out Internal Audit’s assessment of the
sources of assurance for the Audit and Scrutiny Committee on the management of the
Council’s strategic risks. 
Decision 
The Audit and Scrutiny Committee agreed to note the risk assurance map contained at
appendix 1 of the report. 
(Reference:  Report by Chief Internal Auditor, dated 4 September 2025, submitted) 
13. STRATEGIC RISK REGISTER 
The Committee gave consideration to a report which provided an update on the Council’s
Strategic Risk Register. 
Decision 
The Audit and Scrutiny Committee endorsed the updated Strategic Risk Register,
contained at appendix 1 of the report. 
(Reference:  Report by Chief Executive, dated 4 September 2025, submitted) 
14. TREASURY MANAGEMENT UPDATE - QUARTER ENDED 30 JUNE 2025 
The Committee gave consideration to a report which provided an update on the Council’s
treasury management activity during the quarter 1 April to 30 June 2025 and the overall
position as at 30 June 2025.   
Decision 
The Audit and Scrutiny Committee considered and noted the contents of the report and
the treasury activity during the period 1 April to 30 June 2025. 
(Reference:  Report by Interim Head of Financial Services, dated 8 August 2025,
submitted)
Page 6

Page 7

15. WORKPLAN 
The Audit and Scrutiny Committee Workplan was before the Committee for noting.   
Decision 
The Audit and Scrutiny Committee noted the content of the Workplan. 
(Reference:  Workplan of the Audit and Scrutiny Committee, dated 4 September 2025,
submitted) 
Page 7

Page 8

This page is intentionally left blank

Page 9

ARGYLL AND BUTE COUNCIL  AUDIT & SCRUTINY COMMITTEE   
FINANCIAL SERVICES  16 DECEMBER 2025  
INTERNAL AUDIT AND COUNTER FRAUD SUMMARY OF ACTIVITIES 
1. SUMMARY  
1.1 The objective of the report is to provide the Audit and Scrutiny Committee (the
Committee) with a summary of Internal Audit activity and progress during quarter 3
of 2025/26.  
1.2 Core activities together with a progress update statement are shown below: 
• 2025/26 Individual Audits undertaken: Eight audits have been completed
during the period, 4 have been assessed as providing high assurance, one
substantial assurance, 2 reasonable assurance and one limited assurance.
(Where HSCP and LiveArgyll Audits are included, these are provided for
information only). 
• 2025/26 Audit Plan progress: The plan is currently on track. In the event that
this position was to change, we will flag it to the Committee as part of the
quarterly updates. 
• Scrutiny: Planned work for 2025/26 has been agreed by the Committee along
with those who will serve on the Panel, and work on this will commence in
January 2026. 
• Counter Fraud: The Counter Fraud Team (CFT) is continuing to rebill council
tax accounts and recovery of funds is underway.  All other aspects and
referrals are being considered, investigated and evaluated and the Counter
Fraud Team remain vigilant to protect our public purse. All CFT team
members have completed the accredited CIPFA Fraud Specialist Course. The
team lead is currently progressing toward the completion of year 4 of a Master
in Accountancy course.   
• Continuous Monitoring Programme Testing: A number of auditable units
are subject to continuous testing. There has been one new issue identified this
quarter. 
• Performance indicators: Current status is green / on track.   
2. RECOMMENDATIONS  
2.1 To review and endorse the Summary of Activities report.   
Page 9 Agenda Item 4

Page 10

3. DETAIL  
3.1 Eight audits have been completed since the previous Committee in September
2025. 
Audits Completed 
• Oban Airport 
• ICT Disaster Recovery 
• School Residential Trips
• Self-Directed Support
• Building Cleaning 
• HSCP Governance Arrangements -for information only
• HSCP Partnership Working – for information only
• HSCP Workforce Planning  – for information only 
Verification Audit Work Completed 
• N/A 
Audits in Planning / in Progress
reported to a future meeting of the Committee. 
• Capital Programme – Management and Monitoring (awaiting management
response to draft report)
• Payroll – iTrent
• Performance Management Arrangements and Reporting
• Project Management 
• Street Lighting 
3.2 In addition to those already in progress, indicative audits planned for 2025/26
are: 
• Eclipse
• Rural Growth Deal
• Whistleblowing
• LiveArgyll Building/Property Maintenance   
2025/26 Audit Plan  
3.3 Work is ongoing and is currently on track at this point in time. Only one
amendment to the plan should be noted and that relates to the strategic
Procurement review which has been postponed to another audit plan when the
work will be more appropriate to be undertaken.   
Scrutiny  
3.4 It was agreed by the Committee that the chosen subject area for the 2025/26
scrutiny review would be on the Council’s preparedness for the Bio-Municipal
Page 10

Page 11

Waste (BMW) Landfill Ban.  A background and scoping document will be prepared
and issued to the Panel members for agreement in due course. We anticipate that
this will commence early in January 2026.   
Counter Fraud  
3.5 The CFT is progressing well with both team members fully CIPFA accredited fraud
investigators. The team now consists of 2 full time staff after completing
secondments.  Both team members are fully trained under the accredited CIPFA
fraud course. 
3.6 Routine work continues and is progressing to track the full income due and to be
recovered as part of this ongoing work. Based on the amount of additional billing,
even accounting for a degree of non-recovery, the indications are that the team are
anticipating exceeding their annual target. In addition, the team are raising
awareness of the Council’s zero tolerance to fraud and this will help act as a
deterrent to fraud being perpetrated in the first place.  
3.7 Visits continue to play a vital role in the CFTs proactive and reactive work.  Recent
visits have taken place in Mull, Campbeltown and Tarbert. Work is still underway
for Helensburgh. Further efforts toward Coll had to be delayed due to Storm Amy.
Travel to the outer islands will commence spring 2026. Both officers continue to be
proactive and make visits when information is received via the online portal and
other islands will soon be visited.  
3.8 The CFT continue to link in with Internal Audit and Debt Recovery, and where
necessary to assist, trace persons and open communication to long term debts for
recovery. Several cases have resulted in large scale rebilling.  
3.9 Second homes and Non-Domestic Rates are playing larger roles in the CFT’s 
investigations with several claims already adjusted.  These will remain proactive
areas.  
3.10 The CFT continue to work closely with the empty homes team to support each
other in our remits.  Work and communication between each department is key in
identifying and finding appropriate solutions to enable empty homes to return to
residency or open market.  
3.11 The NFI exercise continues to be a routine work area for the CFT.  The 2024/2025
exercise had extra data uploaded this September and work on this element will
commence when this has been matched and results released.  The initial part of
the matching exercise is coming to a close.  Any remedial or conclusive work will
be completed when and where appropriate.  The system is reviewed periodically
for any updates.  
3.12 Since the inception of the CFT a total of £1,553,043,262 has been rebilled and
£1,048,213 has been recovered. A recovery percentage of 68% has been
achieved at the last review of the figures. Recent large rebilling has been passed
to other agencies, and this takes time to process and progress payment plans.   
Additional Updates from Quarter Three  
3.13 The Council has entered a ten-year programme to deliver the Rural Growth Deal
(RGD) for Argyll and Bute.  The Council, as the accountable body for this
Page 11

Page 12

programme is required to allocate and account for distribution of the funding to
partners, third parties and other bodies in accordance with the approved
governance arrangements.  The Council’s Chief Internal Auditor has been
appointed to coordinate audit activity throughout the programme, this will include
liaison with partner auditors to obtain annual confirmation of regular and planned
reviews of grant funded activities and a specific review of RGD within the
Council’s Annual Audit Plan at least every two years.  Discussions regarding the
audit input required have taken place and the first review will be included within
the 2025/26 Internal Audit Plan. We will closely monitor the additional work
associated with this appointment going forward and determine whether
additional resources may be required.  
3.14 Our work as the contracted Internal Auditors for the HSCP has been progressing
well and priority has been given in this area due to staff availability, therefore, we
have been able to complete our work for 2025/26. We will continue to monitor and
report progress to the HSCP’s Audit and Risk Committee in relation to the
implementation of recommendations made in previous reports. 
3.15 Internal Audit staff continue to increase their skills and ultimately aim to complete
appropriate professional qualifications at the end of their training programmes.
Internal Audit have two staff members who are undertaking formal professional
training; training is at differing stages but is progressing as expected at this time.
The aim is to develop and retain professional staff on the completion of the
qualifications and increase resilience within the service.   
Continuous Monitoring  
3.16 Our continuous monitoring programme is generally focused on transactional type
activity. Standard audit tests are applied which are relevant to each auditable unit.
Control design tests look at whether the controls in place adequately address the
potential risk event. There has been one new finding within the quarter that
requires to be reported. 
Table 1: Continuous Monitoring Findings 
Auditable
Area
Areas Tested Issues Identified Management comment /
action
Payroll  Expenses Five out of 37 expense
claims tested were
found to have been
authorised by
managers/appropriate
persons but receipts
were either missing or
did not align with the
claim period,
additionally, there was
no evidence of
Executive Director
approval for claims over
6 months old. 
The respective
Managers/authorisers were
notified of the findings via
email and advised that the
guidance on the HUB must
be adhered to and the
importance of this. 
Four responses were
received assuring that the
guidance would be followed
in future and despite
sending 3 emails, no
response was received for
the 5th claim tested.   
3.17 A process is in place whereby management are advised of continuous monitoring
findings and, where appropriate, requested to take remedial action.    Due to the
Page 12

Page 13

volume of continuous monitoring tests carried out the decision was made to report
by exception only.     
National Reports  
3.18 A follow up process for national reports is in place whereby management are
advised of national reports published and asked to confirm what, if any, action is
planned as a result of the report.  Table 2 details the national reports issued during
quarter two of 2025/26 due to be reported in quarter three.  
Table 2: National Reports 
National Report Issued To Detail Management response/
Action taken
Delivering for
the future:
Responding to
the workforce
challenge
Executive
Director Kirsty
Flanagan
Scotland’s councils
urgently need to
make progress
with workforce
plans if they are to
protect services
and financial
sustainability.
‘Following publication of the
Workforce Challenges report in
August 2025, the Council has
been assessing our current
People Strategy and Strategic
Workforce Plan against the
Commission’s
recommendations.  This self-
assessment will be reported in
the first instance to the
Executive Leadership Team in
Spring 2026 and any
improvements identified for
inclusion in future iterations of
the Strategic workforce
documents.’
Flooding in
Communities: 
Moving towards
flood resilience
Executive
Director Kirsty
Flanagan
Flooding is getting
worse because of
changes to our
climate.  It’s likely
flooding will
happen more
often.
A request has been made to
schedule this report for
discussion at the next Scottish
Collaboration of Transportation
Specialists (SCOTS) meeting on
12 December, thereafter, a
report will be prepared for the
Council’s Environment,
Development and Infrastructure
(EDI) Committee.
The 2023/24
audit of Glasgow
City Council
Chief
Executive
The processes,
decisions and
actions that
enabled five senior
Glasgow city
Council officers to
take significant
early retirement
and redundancy
payouts fell short
of the behaviour
and standards
expected of public
servants.
A stand-alone report to be
submitted to a future meeting of
the Audit and Scrutiny
Committee. 
Page 13

Page 14

Cyber-attack
affecting
operations and
services:  The
2023/24 audit of
Comhairle nan
Eilan Siar
Executive
Director Kirsty
Flanagan
All Scottish
councils must learn
from the immediate
and ongoing
impacts of a
significant cyber-
attack on
Comhairle nan
Eilean Siar.
Argyll and Bute Council actively
manages cyber security risk
through its Strategic Risk
Register, regular reviews, and
robust IT protocols using
specialized software, while
acknowledging that absolute
prevention cannot be
guaranteed. The Council
collaborates with other
authorities, including Comhairle
nan Eilean Siar, for mutual
learning and recovery support,
and participates in the Scottish
Local Authority Information
Security Group (SLAISG) for
information sharing and best
practices. Cyber risk remains a
key focus, with efforts centred
on minimizing threats and
ensuring readiness and
preparation for potential attacks. 
National Fraud Initiative (NFI)  
3.19 NFI data matching involves comparing computer records held by one body against
other computer records held by the same or another body to identify potentially
fraudulent claims and payments to be identified.  Note though that the inclusion of
personal data within a data matching exercise does not mean that any specific
individual is under suspicion. Where a match is found it indicates that there may be
an inconsistency which requires further investigation. No assumption can be made
as to whether there is fraud, error or other explanation until an investigation is
carried out.  A reminder process is in place to ensure that matches are reviewed
on a timely basis.  
3.20 The previous NFI exercise has been completed and results published by Audit
Scotland.  This exercise was conducted by officers and matches checked and
closed accordingly.  NFI provided additional data releases over the course of the
exercise and matches were addressed when these became available.    
3.21 Existing users have been reviewed and new users added where requested, all
users have been and will continue to be informed that matches are available for
review.  Progress in investigating matches will be monitored monthly by the
Counter Fraud team and reported quarterly to the Audit and Scrutiny Committee.    
3.22 New HMRC data has been uploaded and released back to us, the respective
teams have been contacted to start matching this data.  
3.23 The NFI exercise for 2024/25 has commenced with the data uploads so far
submitted to the Cabinet office for review and therefore data matching when
released.  The new NFI matches will appear in the table below as and when they
have been released and checked. More uploads have been given to Cabinet office
during November 2025 and will be matched once released.
Page 14

Page 15

Table 4: National Fraud Initiative Progress at 16/11/2025
Operational
Area
Total
Matches
Recommended/Very
High / High/ Medium
Risk Matches
Matches
Complete 
*
WIP
Match Description
CT to Elect
Register 
2422 0 2422 0 CT records to Electoral
Register/ other data sets to
ensure discount awarded
to only those living alone
aged over 18, taking into
account disregarded
occupants.  (CT to other
Datasets will not be
progressed further due to
poor quality data)
CT rising
18s 
85 0 85 0
CT to HMRC
Household
Composition
1106 0 1106 0
Housing
Benefits
13 9 11 0 HB records to records in
other authorities / other
datasets including student
loans, payroll and pensions
to identify undeclared
income and capital.
Payroll 300 107 61 0 Payroll records to other
datasets including other
payrolls and pensions to
ensure employee is not
receiving additional
income.
Blue Badges 200 200 200 0 Blue badge records to
DWP data to identify
deceased claimant with
valid badge.
Housing
Waiting list
262 258 227  0 Housing waiting list
records to other
organisations HBCTR and
tenant data to identify
undisclosed changes in
circs or false info.
Council Tax
Reduction
638 174  206 3 CTR records with records
in other authorities / other
datasets including; student
loans, payroll and pensions
to identify undeclared
income and capital
Creditors 2340 0 1126 0  Analyses Creditors data to
identify possible duplicate
vendors and payments,
VAT errors or fraud and
multiple vendors sharing a
bank account.
Procurement 67 0 14  0 Payroll records to
Companies House and
creditors’ data to identify
employees who appear to
have a personal interest in
a company that the
authority has traded with.
Business
Rates
154  0 154 0 Business rates records
within and between
authorities to identify
those fraudulently claiming
small business bonus
scheme and grants 
Page 15

Page 16

* Work in Progress
Overall Summary of Matches 
Matches
Complete
Work In
Progress
Cleared Frauds Errors Total
Value 
£
Recovering Recovering
Value 
£ 
5612  3 5532 0 80 62,726 0 0 
Internal Audit Development  
3.24 The table below details progress against the action points in our Internal Audit
development plan.  
Table 5: Internal Audit Development Key Actions: updated 18/11/25. 
Area For
Improvement
Agreed Action Progress
Update
Timescale
Review Continuous
Monitoring
Programme
The Continuous Monitoring
Programme will be reviewed to
assess value of existing tests carried
out and establish where these can be
enhanced with greater use of data
analytics.
In progress March2026
Follow-up
Performance
Reporting
Develop performance reporting
dashboard on Power BI
In progress March 2026 
3.25 Internal Audit scorecard data provided below are aligned to those for internal audit
in the Financial Services service plan.  All indicators are shown as currently being
on track.  
Table 6: Internal Audit Team Scorecard  
Internal Audit Team Scorecard 2025– 26 – FQ2 25/26 (as at September 2025)
BO115 We Are Efficient and Cost Effective    
Internal Audit Level of Satisfaction
Actual  100% G 
Target 80%
Review of Strategic Risk register
Status On Track G 
Target On Track
Percentage of audit plan completed
Status 100% G 
Target 80%
Percentage of audit recommendations accepted by
management
Actual  100%
G
Target 100% 
Page 16

Page 17

4 CONCLUSION  
4.1 The 2025/26 audit plan is progressing as anticipated at this stage in the year,
together with the Counter Fraud Team continuing with visits and pro-active work
throughout Argyll and Bute.  
5 IMPLICATIONS
5.1 Policy – Internal Audit continues to adopt a risk-based approach to activity
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Customer Service – None
5.6 Risk – None
5.7 Climate Change – None
5.8 Fairer Scotland Duty – None
5.9 Equalities – protected characteristics – None
5.10 Consumer Duty – None 
5.11 Island Communities – None
5.12 Children’s Rights and Wellbeing – None 
For further information please contact Internal Audit (01546 604108)
Paul Macaskill
Chief Internal Auditor
16 December 2025
Page 17

Page 18

This page is intentionally left blank

Page 19

ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE                                                            
FINANCIAL SERVICES  16 December 2025 
INTERNAL AND EXTERNAL AUDIT REPORT FOLLOW UP 2025-26 
1.0 INTRODUCTION 
1.1 Internal and external audit reports include an action plan with a
management response establishing the agreed action, timescale and
responsible officer. Internal Audit record these in a database and, on a
quarterly basis, follow them up to ensure they are being progressed. 
1.2 This report updates the committee on all open actions as at 30
September 2025 including information on actions where the agreed
implementation date has been rescheduled or evidence is required to
confirm completion.   
2.0 RECOMMENDATIONS 
2.1 To endorse the contents of the report. 
3.0 DETAIL 
3.1 The two tables below provide a numerical summary of open audit actions
with a split between actions due by and due after 30 September 2025. 
3.2 Appendix 1 provides a visual representation of progress in addressing
agreed actions. 
3.3 Appendix 2 provides further detail on actions that have been delayed and
rescheduled or where evidence is required to confirm completion. 
Page 19 Agenda Item 5

Page 20

Table 1 – Actions due by 30 September 2025
Service
Complete
Delayed/
Rescheduled
Evidence
Required
Total
Internal Audit
DH – Commercial Services  1  1
DH – Education Wellbeing, Inclusion & Achievement 1   1
DH – Legal & Regulatory Support 1   1
KF – Development & Economic Growth 1 2  3
KF – Roads & Infrastructure Services 3 1  4
H&SCP (SW) – Adult Services (Mental Health Learning Disability,
Addictions & Lifelong Conditions) 
2  2
H&SCP (SW) – Adult Services (Older Adults & Community
Hospitals)
1   1
H&SCP (SW) – Finance/Transformation  1  1
H&SCP (SW) – Strategic Planning & Performance 1 1  2
H&SCP (IJB) – Adult Services (Older Adults & Community Hospitals)  1  1
H&SCP (IJB) – Finance/Transformation  2  2
H&SCP (IJB) – Strategic Planning & Performance  6  6
LiveArgyll   1 1
External Audit
Nil    
TOTAL 8 17 1 26 
Table 2 – Actions due after 30 September 2025
Service
Complete
On Course
Delayed/
Rescheduled 
Total
Internal Audit
DH – Commercial Services  1  1
DH – Education Performance & Improvement  4  4
DH – Education Wellbeing, Inclusion & Achievement  5  5
DH – Legal & Regulatory Support  6  6
KF – Development & Economic Growth   1 1
KF – Financial Services 1 2 1 4
KF – Roads & Infrastructure Services 1 7  8
H&SCP (SW) – Children & Families and Criminal Justice  7 1 8
H&SCP (IJB) – Strategic Planning & Performance  7  7
External Audit
Nil    
TOTAL 2 39 3 44 
Page 20

Page 21

4.0 CONCLUSION 
4.1 Satisfactory progress continues to be made implementing audit actions. 
5.0 IMPLICATIONS 
5.1 Policy – None
5.2 Financial – None
5.3 Legal – None
5.4 HR – None
5.5 Customer Service – None
5.6 Risk – None
5.7 Climate Change – None
5.8 Fairer Scotland Duty – None
5.9 Equalities – protected characteristics – None
5.10 Consumer Duty – None 
5.11 Island Communities – None
5.12 Children’s Rights and Wellbeing – None 
Paul MacAskill
Chief Internal Auditor
16 December 2025                                                  
For further information contact: Paul MacAskill, 01546 604108
Paul.macaskill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Visual representation of progress in addressing agreed actions 
Appendix 2 – Action Plan Points Delayed & Rescheduled or Evidence Required 
Page 21

Page 22

Appendix 1 – Visual representation of progress in addressing agreed actions as at 30 September 2025 
Page 22

Page 23

Appendix 2 – Action Plan Points - Delayed and Rescheduled or Evidence Required 
Action Plan Points due by 30th September 2025 
Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
LOW
COMMERCIAL SERVICES
Asbestos Management 
7.  Site Responsible Person Records
Services should advise Property Services of any
changes of staff nominated as SRP but in practice
this does not happen consistently meaning that
these records are not up to date. 
Property Services have in the past issued emails to
Heads of Services asking for staffing updates, but
due to a lack of response this practice was
stopped. Consideration should be given to
whether this could be reinstated and where there
is no response if this should be escalated to
DMT/SMT.
Property Services will issue
emails to Heads of Services
asking for staffing updates then
enter details into Concerto.
30/09/2025
31 Dec 2025
Extension required to 31
December 2025 to
accommodate statutory
requirements of Martyn's Law.
While the actions that will be
taken remain mostly the same,
the processes are being
updated to reflect the statutory
requirements within Martyn’s
Law. This will include increased
frequency of checking, with
Heads of Service, for changes in
site responsible persons from
annually to 6 monthly. Updated
Facility Responsible Person
Records are completed and
input on concerto.  Email to be
issued to all Heads of Service in
November 2025 with response
due by end November. 
Delayed and Rescheduled
Commercial Services
Admin Officer 
MEDIUM
DEVELOPMENT & ECONOMIC GROWTH
PLANNING 
1.  Staff Training Planning do not currently have in
place a training schedule for 2023/24 for planning
officers.
Once the incorporation of the
IDOX project is completed a 
training schedule will be
introduced covering both the 
new system and other relevant
areas such as the National
planning for framework 4.
31/03/2024
31/12/2024
31/03/2025
30/06/2025
30/09/2025
31 Mar 2026
Planning staff have access to a
full programme of training
during the year held internally,
or externally, as appropriate.  In
2025/26 a programme of
training is currently being
collated.  A formalised training
schedule has still to be
completed however action has
already been taken forward to
Process and
Productivity
Improvement Officer
Page 23

Page 24

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
deliver on several training
themes identified by staff.  This
has included an event on
considering the implications of
the grid enhancement (April
2025), and sessions during Feb
and March 2025 relating to
Trees and EIA development.  It
is confirmed that the most
pressing training needs have
been identified and are being
delivered/progressed whilst a
training plan that addresses
wider requirements remains
under production.
In addition, staff can access a
range of digital courses
specialising in Planning topics
and there is also a range of
internal courses available on
back-office systems, corporate
priorities, and other topics such
as cyber security and the use of
AI and digital tools such as
copilot etc. Creating a training
schedule is however still
complicated by a lack of
available external courses.  That
said, when staff do attend
these, they are also asked to
cascade learning to other
colleagues through notes
taken.  Lastly, the council is also
undertaking a transformational
process, and planners attend an
increasing number of
Page 24

Page 25

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
workshops and seminars that
often involve a place-based
approach working with other
council services and external
partners.  The Scottish
Government have also set up a
Planning Hub to help share
expertise with Planning
Authorities.  This approach is
likely to increase in the future. 
Delayed and Rescheduled
HIGH
DEVELOPMENT & ECONOMIC GROWTH
SHORT TERM LETS 
1.  Procedures  
Whilst policies and procedures that are in place
are comprehensive, there are some elements of
the policies which require to be completed in
parts. This includes  policies/procedures around
Enforcement and Renewals  that still require to be
brought together and circulated.  Other
developments are noted for progression on
Oracle.
1. Develop a Short-term Let
Enforcement policy  
2. Develop procedures for the
renewal of Short-term let 
Licences 
3. Secure changes to the Oracle
STL system, including a 
searchable public register, a
template licence revocation 
letter, with this status being
added to oracle and tracking
these 
4. Develop a template for
provisional licence, including
cover letter 
5. Include a new Licence type -
“Transfer Licence” and new 
application status entitled
“transferred”.
30/09/2025
31 Dec 2025
Good progress is being made to
deliver these actions. 
1. STL Enforcement - not
progressed yet. 
2. Renewal procedure
developed and in place. Revised
STL Policy approved by Council
on 26 June 2025, together with
fees. 
3. IT system being updated and
developed to accept on-line
applications and payments.
System testing ongoing but
currently cannot accept on-line
renewal applications.
Alternative arrangements in
place. 
4. IT is working on new public
register. Revocation form part
of enforcement policy and
procedures (see 1 above). 
5. IT development to process
transfers is complete.
Regulatory Services
and Building Standards
Manager
Page 25

Page 26

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer 
Delayed and Rescheduled
LOW
ROADS & INFRASTRUCTURE SERVICES
Burial Records 
6.  Historical Register Information  
Finding; The Burial and Cremation (Scotland) Act
2016 (The Act) requires information to be
retained electronically although this is not
currently in force it will be at a future date.  The
BACAS system has been partially updated with
historical information recorded in burial registers;
it has not been possible to update with all
information due to the volume of work involved.  
Recommendation;  Source temporary additional
resource to update historical burial records on
BACAS.
The service will source
temporary assistance to update
records during Summer 2024.
30/06/2024
31/12/2024
30/06/2025
30/09/2025
31 Dec 2027
The input of historical records is
progressing within the existing
Roads and Amenity
administrative support team as
it has not been possible to
obtain additional resource.  This
project is significantly more
onerous than initially
considered and is creating
pressure on the team to
complete a piece of work that is
not currently legislative.  A
more realistic timeframe has
therefore been established to
complete this work and allow
the admin team to prioritise
business as usual and progress
with this recommendation
when resources permit. 
Delayed and Rescheduled 
Operations Manager,
Roads and
Infrastructure Services
LOW
ADULT SERVICES (OLDER ADULTS & COMMUNITY
HOSPITALS) 
Adult Services - Adult Support & Protection
1.  Progress  
Whilst significant progress has been made to
address the key areas identified within the report
there remains challenges in terms of ensuring
attendance by all relevant partners at case
conferences, ensuring that chronologies and risk
assessments are completed and ensuring that the
‘three-point test’ is undertaken.
Adult services will facilitate an
ASP audit on a six monthly basis 
to determine practice and
compliance with ASP legislation
and KPIs.
30/09/2024
31/12/2024
31/08/2025
31 Dec 2025
Audit complete and report
recently shared with Senior
Leadership Team.  Due to go to
Adult Protection Committee
and Social Work governance
(Chaired by Chief Social Work
Officer).  Will also go to Chief
officer Group for Public
Protection.  Action plan in
development, evidence will be
provided once progressed
through low-level governance.
Head of Adult Services
(Mental Health, Acute
and Complex Care)
Page 26

Page 27

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer 
Delayed and Rescheduled 
MEDIUM
FINANCE/TRANSFORMATION
INFORMATION GOVERNANCE 
1.  Documentation Review
Reviews are outstanding in regard to; ·
Records Management Plan ·
Information Governance policy framework
A review of all relevant
documents will be carried out.
RMP will be reviewed and
submitted to Keeper around
February 2025.  IG policy to be
reviewed.
31/03/2025
30/09/2025
31 Dec 2025
The new date for submission of
the RMP to the Keeper is 31
December 2025. 
Delayed and Rescheduled
Governance, Risk &
Safety Manager
MEDIUM
FINANCE/TRANSFORMATION
INFORMATION GOVERNANCE 
2.  Improvement Plan
A number of improvement recommendations
made by the Keeper of Scotland were identified in
the following areas: · Business Classification ·
Retention Schedule · Destruction Arrangements ·
Archiving and Transfer · Business Continuity and
Vital Records · Audit Trail An action Plan to
address these areas should be implemented
Develop and implement an
action plan to address the
Keeper of  Scotland's
improvement
recommendations, ensuring
that all aspects of records
management are up-to-date,
compliant, and  effectively
managed. Will be reviewed as
part of RMP submission to
Keeper.
31/03/2025
30/09/2025
31 Dec 2025
The new date for submission of
the RMP to the Keeper is 31
December 2025. 
Delayed and Rescheduled
Governance, Risk &
Safety Manager
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
HSCP CULTURE 
1.  Surveys 
Recent surveys undertaken by each organisation
do not focus specifically on the HSCP in terms of
culture (how are the services working together,
communicating with each other, sharing
information), instead focussing on staff
experiences in each organisation.
HR leads within ABC and NHSH
to review survey landscape and
explore joint survey option over
and above existing employer
only surveys.  To report to SLT
and JPF.
31/03/2025
30/09/2025
31 Mar 2026 
Discussion between both
employers and Chief Officer
with conclusion that the iMatter
annual survey is for all
employees in the HSCP
regardless of employer and
therefore further survey at this
stage is not required, however,
any disbandment of the Culture
Group would need to be put to
Audit & Risk. Staff issues have
delayed this action further. 
Delayed and Rescheduled
Depute Director of
People, NHS Highland
MEDI
UM STRATEGIC PLANNING AND PERFORMANCE
HSCP CULTURE 
Refresh and review of the remit
and purpose of the Culture
31/03/2025
30/09/2025
Agreement between staffside
lead for Argyll and Bute, Chief
Depute Director of
People, NHS Highland
Page 27

Page 28

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer 
2.  Work Plan 
The work plan outlines priorities, outcomes,
responsible person and timeframes. However,
these are not specific, targeted or in some
instances easily measurable with target dates for
completion marked as ‘ongoing’.
Group.  The work plan will be
included as part of the review
to focus on  meaningful action
and timescales.
31 Mar 2026  Officer and both HR leads that
the Culture Group was no
longer required.  The JPF ToR,
standard agenda and workplan
were reviewed to include the
areas and items that had
previously been part of the
culture group remit, however,
any disbandment of the Culture
Group would need to be put to
Audit & Risk. Staff issues have
delayed this action further. 
Delayed and Rescheduled
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
HSCP CULTURE 
3.  Monitoring Progress 
There does not seem to be progress notes
assigned to the work plan therefore difficult to
assess, without reading every meeting note what
progress has made. In addition, as noted above a
number of targets dates are simply noted as
‘ongoing’.
Refresh and review of the remit
and purpose of the Culture
Group to include timescales and
progress reporting as
appropriate.
31/03/2025
30/09/2025
31 Mar 2026 
Agreement between staff side
lead for Argyll & Bute, Chief
Officer and both HR leads that
the Culture group was no longer
required.  The JPF ToR, standard
agenda and workplan were
reviewed to include the areas
and items that had previously
been part of the culture group
remit, however, any
disbandment of the Culture
Group would need to be put to
Audit & Risk. Staff issues have
delayed this action further. 
Delayed and Rescheduled
Depute Director of
People, NHS Highland
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
HSCP CULTURE 
4.  Survey Participation 
Chief Officer to communicate
commencement of surveys to
all staff via CO comms.
31/03/2025
30/09/2025
31 Mar 2026 
Agreed that the National
iMatter survey would be the
tool used. Staff issues have
delayed this action further. 
Delayed and Rescheduled 
Chief Officer
Page 28

Page 29

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
The results of surveys have demonstrated
engagement and participation by HSCP staff could
be improved.
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
HSCP CULTURE 
5.  Culture and Wellbeing Group 
Whilst the Culture Group is open to all staff across
the HSCP, there is a greater proportion of
representation of NHS staff.
As per refresh and review of
Culture Group, review
membership as a result of
revised remit and purpose.
31/03/2025
30/09/2025
31 Mar 2026  
Agreement between staff side
lead for Argyll & Bute, Chief
Officer and both HR leads that
the Culture group was no longer
required.  The JPF ToR, standard
agenda and workplan were
reviewed to include the areas
and items that had previously
been part of the culture group
remit, however, any
disbandment of the Culture
Group would need to be put to
Audit & Risk. Staff issues have
delayed this action further. 
Delayed and Rescheduled
Depute Director of
People, NHS Highland
LOW
STRATEGIC PLANNING AND PERFORMANCE
Risk Management 
3.  Training
It is noted that there is an outstanding audit
action since June 2021 covering; · Training for new
members of IJB and Audit Committee · training for
Risk leads · maintenance of training records
Recommendation accepted. A
training programme based
upon  the use of the Smartsheet
system is being developed.
31/12/2023
30/06/2024
31/12/2024
30/09/2025
31 Dec 2025
Note the agreed action is
changed, as Smartsheet will be
replaced by in Phase, which has
been delayed.  A TURAS module
in risk is available to all staff, at
present, however, uptake has
not been high.  Audit
Committee training identified
and pending funding approval. 
Delayed and Rescheduled
Business Improvement
Manager
MEDIUM
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO)
CLIENT FUNDS PROGRESS REVIEW 
2.  Meeting service users' financial needs
The HSCP will work with
Procurement  Commercial and
Contract Management Team
(PCCMT) to identify appropriate
options within each area. This
issue, which is not within the
30/12/2024
31/03/2025
30/06/2025
30/09/2025
31 Dec 2025
PCCMT has provided options
which need to be reviewed and
considered. 
Delayed and Rescheduled
SW Admin Manager
Page 29

Page 30

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
This is a restricted report, please contact Internal
Audit directly if you are responsible for updating
this action.
control of the HSCP, is likely to
recur, generating significant
additional work.
MEDIUM
ADULT SERVICES (MENTAL HEALTH LEARNING
DISABILITY, ADDICTIONS & LIFELONG
CONDITIONS/CSWO) 
Learning & Physical Disability Care Packages
3.  Case Notes
Case notes are maintained on Eclipse, the
replacement  client database for Carefirst. It was
noted that case notes  were not always
maintained and up to date.
Record keeping session (s) to be
delivered by professional lead   ·
Senior Managers to implement
case note audit within their 
respective services – this should
be linked to individual
practitioner  supervision
30/06/2024
31/12/2024
31/03/2025
30/09/2025
31 Jan 2026
Reassigned to another
Professional Team Lead, who
will revisit the case file audit
process, and peer audit case
files per team/service, per
month.  This will be tailored to
meet the requirements of
Eclipse. For record keeping
sessions, this will need time to
plan this and deliver it.
Audit practice notes for LD will
be addressed through
supervision. In addition, audit
tools to be applied to AHP, and
completed by OT and
SALT. Nurses have a different
tool, and looking to also
complete, as well as for
Psychology. 
Delayed and Rescheduled
Senior Managers
(Adult Services)
MEDIUM
FINANCE/TRANSFORMATION
Payroll Procedure for HSCP Care at Home 
1.  Processes
Payroll processes for Care at Home staff are
manually intensive involving a 3-stage process
transferring information at each stage of the
process. This increases risks of error, although
risks are mitigated through authorisation
processes and checking of information efficiencies
could be made by considering a more automated
approach.
The process for payroll will be
reviewed and any
recommendations
implemented. 
If following consultation with
the Finance Manager, it is
determined that no
improvements can be made this
action will be closed pending
purchase of a new automated
system or further development
of the iTrent system.
30/09/2025
31 May 2026
The Council are in the process
of developing a new app, Pay
Time, which, if implemented,
will address this issue.  The
Council are suggesting that
testing will begin in November
2025.  It will be rolled out to the
HSCP if the testing is
successful.  A precise
implementation date is not
within the control of the
HSCP.  It is suggested that this
SW Admin Manager
Page 30

Page 31

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
recommendation is next
reviewed in 6 months, at which
stage there should be a clear
implementation date from the
Council.   
Delayed and Rescheduled
MEDIUM
STRATEGIC PLANNING AND PERFORMANCE
Learning & Physical Disability Care Packages 
7.  Unmet Need  
Unmet need for Older People Care at Home is
collated by the resources team on a weekly basis,
this is then submitted to Performance and
Improvement Team and is reported to Scottish
Government. The data for Learning  Disability is
not currently recorded formally and not  included
in the above.
Include the data re unmet need
for those under 65 in the
weekly  reporting format
already in place for Older
People.
30/06/2024
30/09/2024
31/08/2025
31 Dec 2025
Unmet need for Homecare for
under 65's should be included in
the regular locality returns,
however, there is a variable
response in respect of persons
with MH or LD with most
localities maintaining that they
don't record this.  No separate
record is currently maintained,
and this was to be reviewed and
included in the ongoing
"Resources Services" and
commissioning practice that is
being developed. 
Delayed and Rescheduled
Head of Strategic
Planning, Performance
and Technology &
Head of Adult Services
(Health & Community
Care)
LOW
LIVEARGYLL
Disclosure Checks – PVG 
2.  Policies, Procedures & Guidance
Finding:  The Manager’s Guide to Recruitment
lacks version control to help users ensure they are
using the most current and up-to-date version and
the Safeguarding Policy requires amendment to
correct/remove errors.
Recommendation:  When updating
documentation to incorporate new legislation,
Management should ensure that version control is
applied and all errors corrected/removed.
Document control protocols in
relation to legislative updates
will be reviewed and the
process updated where needed.
31/07/2025  Version control has been added
to the Managers Guide to
Recruitment, the Safeguarding
Policy has been updated but an
error appears to remain, update
to follow. 
Evidence Required
Services and Support
Manager
Page 31

Page 32

Action Plan Points due after 30th September 2025 
Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
LOW
DEVELOPMENT & ECONOMIC GROWTH
Private Sector Housing Grants & Adaptions 
3.  Procedure Notes and Shared Documents  
While the vast majority of requirements are
included there would be benefit to updating these
to reflect current working practices, which have
evolved due to hybrid working arrangements and
the digitalisation of records.  Consideration should
be given to creating a checklist to  ensure
consistent application of processes.
Procedures and documents will
be reviewed and updated.
Checklists to be drawn up and
introduced when updating the 
procedures.
31/12/2022
30/06/2023
31/03/2024
30/09/2024
30/12/2024
30/06/2025
31/10/2025 
31 Jan 2026
Long term sickness absence
since April 2025 has prevented
any progress.  Phased return
planned for October.  Revised
timetable will need to be
agreed.
The Scheme of Assistance was
only approved by Council at its
meeting in April this year as the
February meeting agenda was
full. As a result, work on revising
the processes, procedures, and
any checklists could not be
taken forward until this point  
Delayed and Rescheduled
Team Lead - Housing
Operations
LOW
FINANCIAL SERVICES
Preparedness for IFRS16 
1.  Database Maintenance
Continuing to meet the requirements of IFRS 16 will
rely on good communication with departments and
a clear understanding of the processes involved for
updating Financial Services with new lease
arrangements or changes to existing lease
arrangements. 
Policy document and training
will be developed to provide a
framework for ongoing
compliance with IFRS16 Leases
and will be reviewed and
updated as appropriate.
31/12/2025
31 Jan 2026
Pushing back one month to
allow for competing priorities. 
Delayed and Rescheduled
Finance Manager
Page 32

Page 33

Service, Report, Plan no. & Finding Agreed Action Original and
Revised Dates
Comment Responsible Officer
LOW
CHILDREN AND FAMILIES AND CRIMINAL JUSTICE
Payroll Procedure for HSCP Care at Home 
2.  iTrent
The final stage of the payroll process involves
inputting information into iTrent which is
completed by Administration staff. There is
currently no authorisation process in place to
confirm the accuracy of information input into the
system. The iTrent Project Team are currently
looking at how the processing of timesheet data for
staff can be improved to ensure accurate and
timely information for payroll processing and more
detailed information on when and why staff are
working, particularly casual staff, for HR and service
management.
Provided by key officer for
iTrent system to enable
authorisation on system.
31/03/2026
31 May 2026
The Council are in the process
of developing a new app, Pay
Time, which, if implemented,
will address this issue.  The
Council are suggesting that
testing will begin in November
2025.  It will be rolled out to the
HSCP if the testing is
successful.  A precise
implementation date is not
within the control of the HSCP.
It is suggested that this
recommendation is next
reviewed in 6 months, at which
stage there should be a clear
implementation date from the
Council.   
Delayed and Rescheduled
iTrent Project Team 
Page 33

Page 34

This page is intentionally left blank

Page 35

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES                                   16 DECEMBER 2025 
PERFORMANCE REPORTING UPDATE 
1.0 EXECUTIVE SUMMARY 
The aim of this paper is to update the Audit and Scrutiny Committee with the
progress on the review of the Council’s Performance and Improvement
Framework (PIF) that is being undertaken as part of the Performance
Excellence Project. The main overall deliverable from this project will be an
updated PIF which includes a simplified, compliant and proportionate approach
to performance and improvement activities.    
The report highlights work completed to date on activities in Phase Two of
the project and plans for the outstanding work packages. 
It is recommended members note and consider the progress of the
Performance Excellence Project and activities to conclude Phase Two. 
Page 35 Agenda Item 6

Page 36

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES                                    16 DECEMBER 2025 
PERFORMANCE REPORTING UPDATE 
2.0 INTRODUCTION 
2.1 The performance excellence project was commenced in May 2020 with the
aim of reviewing the council’s approach to performance and improvement
activities and simplifying them where possible. The report sets out the
progress of Phase Two of the project and the planned activities to bring the
remainder to a conclusion and deliver the updated Performance and
Improvement Framework (PIF). 
3.0 RECOMMENDATIONS 
3.1 It is recommended members note and consider the progress of the
Performance Excellence Project and activities to conclude Phase Two. 
4.0 DETAIL 
4.1 The initial performance excellence project commenced in May 2020 with a
mandate to review the council’s performance management approach and
implement a simplified, proportionate and compliant approach which meets
the needs of a transforming council. Following a Best Value audit, the project
included within its scope actions to improve performance reporting to provide
a balanced picture of long term trends in performance against targets, and to
use benchmarking information to drive continuous improvement.   
4.2 The project then progressed to phase two with the overall objective to present
an updated Performance and Improvement Framework which is in alignment
with the Connect for Success Change Programme, further simplifies our
approach to performance and improvement, while maximising the use of the
technology available to us. Specifically, the project included five work streams
which are largely based on the existing elements of the Performance and
Improvement Framework.  Progress on activities contained within each
workstream is detailed below. 
4.3  Workstream One: Planning 
This workstream focused on the design and development of plans that support
delivery of the council’s strategic outcomes. As the Administration changed
during the project, a new Corporate plan was developed which had not been
Page 36

Page 37

in the original scope of the project.  The pre-existing priorities were continued
for the financial year 2024 – 2025 as the new Corporate Plan took effect within
this period.  This workstream focused on the following activities: 
- Review of corporate strategies and mapping of strategic outcomes – work
on this continues.  Sessions have taken place with senior leaders to
agree rationalisation of strategies and a template for future and reviewed
strategies.
- Development of a team plan template to manage service standards
aligned with strategic objectives – an initial pilot was undertaken by the
HR and OD team using MS planner  for non-core business, followed by
further pilots in Catering and Cleaning and Education with overall positive
feedback and most challenges coming from the behavioural shift in using
the tool as opposed to the method. At Senior Leadership Forum in
November 2024 the proposed approach using planner for non-core
business activities was shared and a survey was issued seeking
feedback.  Strategic Management Team considered this and agreed that
HROD should consider current use of MS Teams by Third Tier Managers
and assess the potential challenges of transitioning to using Planner –
this will be incorporated into ongoing work with Third Tier Managers.
- Development of an updated Corporate Improvement Plan – this has been
delivered. 
4.4 Workstream Two: Review and Evaluation 
This workstream focused on the design and development of methods to
review and evaluate performance at all levels. The aim of this work is to
replace the scorecards that were previously in pyramid with a new approach
that reduces manual input by collecting data at source wherever possible.
This work took a themes AND teams approach, seeking to use the data
platform to allow presentation of performance data in various formats for a
variety of purposes and audiences.  This workstream continues in regard to
core business.  Following a successful pilot, work is underway to implement
reporting dashboards across the remaining teams, to be in place across the
whole of the council service areas by 31 March 2026. 
4.5 Workstream Three: Reflection 
This workstream focused on the learning that informs our plans for change
and improvement. Other pieces of work took place on across the council,
such as the review of our approach to Consultation and Engagement and our
review of Service Design to embed the principles of Scottish Approach to
Service design, which inform this project. Specifically within the scope of this
work stream were 
• Self-assessment activities – a review of pilots was completed and
templates are available for self-assessment in team and thematic
approaches. 
• Annual Performance Review – a review of how we collect and reflect
on annual performance at individual, team and organisational level
took place and a revised approach to our Council Annual report is in
Page 37

Page 38

development with options to be submitted to DMTs and SMT for views. 
Finalisation of this work package is dependent on agreement of
Corporate Outcome Indicators. 
• Benchmarking – a review of our approach to the use of benchmarking
including the Local Government Benchmarking Framework (LGBF)
within our Performance and Improvement Framework.  This work
package has been delayed.  Work is taking place with managers to
explore their use of the LGBF. 
• Lessons learned – development of an approach that allows lessons
learned to be shared widely across teams.  This activity has been
descoped from the project due to parallel work in regard to
establishment of a Corporate Programme Office and will be
incorporated into that. 
4.6 Workstream 4: SPI Compliance / Public Performance Reporting 
This workstream focused on how we tell people about our performance in a
way that is proportionate and meets the requirements set out in the Accounts
Commission’s Statutory Performance Direction. The objective is for timely
and meaningful public performance reporting and scrutiny.  This workstream
was completed in respect of the December 2024 statutory direction which
covers the period up to and including 2027 – 2028.  Additionally, work has
taken place to review and update our website Performance pages which is in
the process of going live. 
4.7 Workstream 5: Updated Performance and Improvement Framework 
The final deliverable of the project will be an updated Performance and
Improvement Framework which reflects the work carried out in each of the
work streams above.  This will incorporate all the resources currently
available and in development.  The updated PIF will be presented on
conclusion of the other work packages. 
4.8 Due to unanticipated delays as a result of dependencies relating to work
requiring senior leadership involvement and direction, there is a need to
extend specific elements of this project.  It is anticipated that the outstanding
work packages will be complete by the end of March 2026 and sooner in
some cases.   
5.0 CONCLUSION 
5.1 In conclusion, this report outlines the progress made in regard to Phase Two of
the Performance Excellence Project and arrangements to bring the outstanding
work packages to a conclusion.   
Page 38

Page 39

6.0 IMPLICATIONS 
6.1 Policy   this project will deliver an updated Performance and
Improvement Framework (PIF) for the Council. 
6.2 Financial   none arising directly from this report. 
6.3  Legal    the Council has a statutory duty to ensure Best
Value and to comply with the Accounts
Commission’s SPI directive. 
6.4  HR      none arising directly from this report. 
6.5 Customer Service   delivery of Best Value through our Performance and
Improvement Framework ensures that our
customers get value for money in the services that
we provide them with. 
6.6 Risk    failure to deliver this project would result in the
Council not having performance and improvement
arrangements in place that satisfy the needs of a
transforming Council. 
6.7 Climate Change  none arising directly from this report. 
6.8  Fairer Scotland Duty  none arising directly from this report - any Integrated
Impact Assessments required will be completed as
part of the project. 
6.9 Equalities - protected  none arising directly from this report - any Integrated 
Characteristics   Impact Assessments required will be completed as
part of the project. 
6.10 Consumer Duty  none arising directly from this report. 
6.11 Island Communities   none arising directly from this report - any Integrated
Impact Assessments required will be completed as
part of the project. 
6.12 Children’s Rights and  none arising directly from this report - any Integrated 
Wellbeing    Impact Assessments required will be completed as
part of the project. 
Kirsty Flanagan
Executive Director with responsibility for Customer Support Services 
Policy Lead Councillor Mark Irvine 
28 October 2025
Page 39

Page 40

For further information contact: 
Jane Fowler, Head of Customer Support Services, jane.fowler@argyll-bute.gov.uk 
Jennifer Coyle, Senior HR Business Partner, jennifer.coyle@argyll-bute.gov.uk 
Page 40

Page 41

ARGYLL AND BUTE COUNCIL                 AUDIT & SCRUTINY COMMITTEE                                             
CUSTOMER SUPPORT SERVICES                                    16 DECEMBER 2025 
2024/25 COUNCIL ANNUAL REPORT 
1.0 EXECUTIVE SUMMARY 
1.1 This report presents to the Audit and Scrutiny Committee the 2024/25 Council
Annual Report (CAR). 
1.2 The Annual Report is one of the key ways we meet our Public Performance
Reporting responsibilities, letting the people of Argyll and Bute know what we
have delivered for our communities over the past year. 
1.3 It provides an overview of our performance against corporate outcome
indicators, along with insights from services on key activities, projects,
achievements, and challenges during the reporting period. 
1.4 Despite the challenges, there is much to celebrate. From delivering
infrastructure projects to supporting local businesses and investing in our 
young people, we have achieved a great deal together. We have also
responded to new national requirements, adapting our services and systems 
to meet evolving expectations and responsibilities. 
1.5 The increasing impact of climate events continues to test our resilience, and
we are responding with urgency and innovation. Whether through our 
climate adaptation work, investment in sustainable infrastructure, or support
for community-led initiatives, we are committed to building a greener, 
more secure future. 
Page 41 Agenda Item 7

Page 42

ARGYLL AND BUTE COUNCIL                 AUDIT & SCRUTINY COMMITTEE                                               
CUSTOMER SUPPORT SERVICES                                              16 DECEMBER 2025 
2024/25 COUNCIL ANNUAL REPORT 
2.0 INTRODUCTION 
2.1  This report presents to the Audit and Scrutiny Committee the 2024/25 Council
Annual Report (CAR). 
3.0 RECOMMENDATIONS 
3.1 The Audit and Scrutiny Committee are asked to consider the content of the
Council Annual Report. 
4.0 DETAIL 
4.1 The Council Annual Report is a key document for the Council’s statutory Public
Performance Reporting (PPR) duties and is published on the council website. It
was agreed at Council on 24 September 2025. 
4.2  It presents both our performance against our corporate outcome indicators
(COI) and information on the key activities, successes and challenges that our
services have faced during 2024/25. 
4.3  The Council Annual Report pulls together many examples of the exceptional
efforts, innovative solutions delivered by our staff and joined up working
between the Council and our partners and communities that took place during
this period. 
4.4 Despite the challenges, there is much to celebrate. From delivering
infrastructure projects to supporting local businesses and investing in our 
young people, we have achieved a great deal together. We have also
responded to new national requirements, adapting our services and systems 
to meet evolving expectations and responsibilities. 
4.5  The increasing impact of climate events continues to test our resilience, and
we are responding with urgency and innovation. Whether through our 
climate adaptation work, investment in sustainable infrastructure, or support
for community-led initiatives, we are committed to building a greener, 
more secure future. 
Page 42

Page 43

5.0 CONCLUSION 
5.1 The Annual Report is one of the key ways that the Council meets our Public
Performance Reporting responsibilities, letting the people of Argyll and Bute
know what we have delivered for our communities over the past year. Once
approved, it is published on the Council website.   
6.0 IMPLICATIONS 
6.1 Policy   All of the indicators in this report are based on 
agreed Council policy. 
6.2  Financial   All indicators with financial implications are actively     
managed through agreed budget monitoring 
processes.    
6.3  Legal All appropriate legal implications are complied
with. 
6.4  HR    All HR implications are actively managed 
through agreed Wellbeing and Management 
monitoring processes. 
6.5  Customer Service  All activities with customer feedback or insight are   
rigorously monitored for improvement. 
6.6  Risk Without this information Elected Members are less
informed of activities within their area. 
6.7  Climate Change The Council is committed to working towards net  
zero. 
6.8  Fairer Scotland Duty  None arising directly from this report. An IIA is not
required for performance reporting. 
6.9  Equalities – protected   None arising directly from this report. All activities           
characteristics  monitored in this report comply with the council’s
equality policies and obligations. An IIA is not
required for performance reporting. 
6.10  Consumer duty None arising directly from this report. An IIA is not
required for performance reporting. 
6.11  Islands Communities  None arising directly from this report. An IIA is not
required for performance reporting. 
Page 43

Page 44

6.12  Children’s Rights and   None arising directly from this report. An IIA is not        
Wellbeing  required for performance reporting. This report 
highlights examples of how the Council is
committed to and working towards reducing child
poverty and improving outcomes for every child 
Pippa Milne, Chief Executive 
Jim Lynch, Council Leader 
November 2025 
For further information contact: 
Jane Fowler, Head of Customer Support Services, jane.fowler@argyll-bute.gov.uk 
Kay Owen, Team Lead - OD Project Office, kay.owen@argyll-bute.gov.uk 
APPENDICES
Appendix 1: Council Annual Report 2024-25 
Page 44

Page 45

1 
Council Annual Report 2024 - 2025
Page 45

Page 46

1 
Contents
Forewords ................................................................................................................................................................................................... 4
Leader of the Council .......................................................................................................................................................................................... 4
Chief Executive ................................................................................................................................................................................................... 5
Introduction ............................................................................................................................................................................................... 6
Financial statement   ........................................................................................................................................................................................... 7
Council priorities ......................................................................................................................................................................................... 8
Communities ....................................................................................................................................................................................................... 8
Children and young people.................................................................................................................................................................................. 8
Environment ........................................................................................................................................................................................................ 8
Speaking up for Argyll and Bute .......................................................................................................................................................................... 8
Sustainable service delivery ................................................................................................................................................................................ 8
Transport, infrastructure and digital connectivity ................................................................................................................................................. 8
Housing, economic growth and population .......................................................................................................................................................... 9
Cross-cutting activities ................................................................................................................................................................................ 9
Connect for Success ........................................................................................................................................................................................................ 9
Our Workspace – reducing costs and increasing efficiencies ........................................................................................................................................ 10
Performance Excellence Project .................................................................................................................................................................................... 10
ICT and Digital ............................................................................................................................................................................................................... 11
Climate Change ........................................................................................................................................................................................ 12
Capital Investment and central repairs delivered ...................................................................................................................................... 13
Housing and the Housing Emergency ....................................................................................................................................................... 13
Our performance ....................................................................................................................................................................................... 15
How We Compare – Local Government Benchmarking Framework (LGBF)  ................................................................................................................ 16
Page 46

Page 47

2 
Delivering our outcomes ........................................................................................................................................................................... 18
Corporate Outcome: People live active, healthier and independent lives ................................................................................................. 18
Corporate Outcome: People will live in safer and stronger communities .................................................................................................. 21
Supporting our communities .............................................................................................................................................................................. 22
Corporate Outcome: Children and young people have the best possible start ......................................................................................... 24
Support and interventions for our care experienced children and young people ........................................................................................................... 26
Addressing non-attendance ............................................................................................................................................................................... 26
UNICEF UK’s Rights Respecting School Programme ....................................................................................................................................... 26
Children living in Poverty ................................................................................................................................................................................... 26
Award winning school meals service ................................................................................................................................................................. 28
School Counselling Service ............................................................................................................................................................................... 28
School suitability ratings .................................................................................................................................................................................... 28
Corporate Outcome: Education, skills and training will maximise opportunities for all .............................................................................. 29
Developing the young workforce .................................................................................................................................................................................... 31
Helping People into work ............................................................................................................................................................................................... 31
Literacy and Numeracy ..................................................................................................................................................................................... 32
Play on Pedals .................................................................................................................................................................................................. 32
Attainment ......................................................................................................................................................................................................... 32
Corporate Outcome: Our economy is diverse and thriving ....................................................................................................................... 34
Supporting economic recovery and our communities .................................................................................................................................................... 37
The Rural Growth Deal (RGD) ....................................................................................................................................................................................... 40
One council: property income ............................................................................................................................................................................ 43
Housing Services Partnership with Home Argyll ............................................................................................................................................... 43
Corporate Outcome: We have an infrastructure that supports sustainable growth ................................................................................... 44
Council Carbon Footprint .................................................................................................................................................................................. 45
Page 47

Page 48

3 
Flood Protection ................................................................................................................................................................................................ 46
Marine infrastructure ......................................................................................................................................................................................... 46
Ferry services .................................................................................................................................................................................................... 48
Road Condition improvements .......................................................................................................................................................................... 51
Corporate Outcome: Getting it right .......................................................................................................................................................... 54
Increasing the use of our website and self-service tools ................................................................................................................................................ 55
Improving our customer service ..................................................................................................................................................................................... 56
Award Recognition for Outstanding Innovation and Service .............................................................................................................................. 56
Supporting our Community Councils ............................................................................................................................................................................. 57
Local Government elections and supporting new elected councillors ............................................................................................................................ 57
Committee Support and Member Services ........................................................................................................................................................ 58
Looking after our financial assets  ..................................................................................................................................................................... 59
Supporting attendance ...................................................................................................................................................................................... 59
Supporting Our People: Insights and Wellbeing Initiatives ................................................................................................................................ 60
Strategic Risk Register ............................................................................................................................................................................. 60
Operational Risk Register ......................................................................................................................................................................... 61
Service delivery challenges....................................................................................................................................................................... 61
Consultations – we asked, you said, we did ............................................................................................................................................. 64 
Page 48

Page 49

4 
Forewords
Leader of the Council 
It is a privilege to introduce Argyll and Bute Council’s Annual Report for 2024-25. Within this document you will find many examples of the
achievements and successes that this council has delivered for its communities in the past year. 
The past year has also seen the council going through some changes, with a different Administration in place from April 2024. With this has come a
refreshed and renewed set of strategic Priorities for the remainder of the council term up to 2027, and these underpin the council’s decision-making,
its work and the action it takes. 
Our updated Priorities set out our aspirations for the area and our determination to see it thrive. They must, though, also frame how we tackle
challenges, and something that remains a constant for every Scottish local authority is the financial climate in which we must operate and deliver for
our communities today while seeking to plan ahead for tomorrow. 
Sometimes meeting those challenges requires making equally challenging decisions. While easy solutions or quick fixes almost never come along,
something that can help in that context of challenge is to work in partnership – whether with other agencies or with our communities. That is why
engagement is a key element of our Priorities, harnessing the knowledge and the commitment of our incredible communities where there is an
increasing understanding that councils can no longer do all that they used to do or all that they would like to do, and that different approaches are
required in today’s climate.   
Now, more than ever before, it is vital to work together where we possibly can. We may well have differing views from time to time, but we also have
much common ground to be found and there are issues on which we can not only collaborate but where we can join our voices together to speak up
and stand up for Argyll and Bute. 
I opened by saying it is a privilege to open this report. I close by saying that is an even greater privilege to represent this area, its people and its
communities. Local government in Scotland continues to cope with change and to look towards transformation. Here in Argyll and Bute we are
embracing that head-on and seeking to get ahead of the game, using the knowledge and experience we’ve had to build up in order to successfully
deliver services and investment across one of Scotland’s most unique geographic environments. That, coupled with the determination of our
workforce and the tremendous community spirit and resilience for which Argyll and Bute is renowned, stand us in good stead for as bright a future as
possible. 
Cllr Jim Lynch
Leader, Argyll and Bute Council
Page 49

Page 50

5 
Chief Executive 
Welcome to Argyll and Bute Council’s Annual Report for 2024–25. This report provides an overview of the work we’ve undertaken over the past
year, the progress we’ve made, and the challenges we continue to face. It reflects our commitment to transparency, accountability, and to delivering
the best possible outcomes for our communities. 
As we reflect on the past year and look ahead to 2025–26, I want to begin by recognising the continued dedication and resilience of our staff, who
remain at the heart of everything we do. Their commitment has enabled us to deliver vital services in the face of ongoing challenges and change.
This year, we have had to make some difficult decisions about the future of service provision. These decisions are never taken lightly, and they
reflect the complex financial landscape we continue to navigate. However, they are also part of our commitment to ensuring that we can sustain
essential services for the people of Argyll and Bute in the years to come. 
We know that the best decisions are made together. That’s why we have continued to engage with communities across the area, listening to what
matters most to them and working in partnership to shape the future. This collaborative approach is central to our vision for a stronger, more resilient
and thriving Argyll and Bute. 
Despite the challenges, there is much to celebrate. From delivering key infrastructure projects to supporting local businesses and investing in our
young people, we have achieved a great deal together. We have also responded to new national requirements, adapting our services and systems
to meet evolving expectations and responsibilities. 
The increasing impact of climate events continues to test our resilience, and we are responding with urgency and innovation. Whether through our
climate adaptation work, investment in sustainable infrastructure, or support for community-led initiatives, we are committed to building a greener,
more secure future. 
Looking ahead, we remain focused on tackling the challenges that lie before us. We will continue to work with our communities, partners, and staff to
find solutions, embrace opportunities, and deliver for Argyll and Bute. 
Together, we can shape a future that reflects the strengths, aspirations, and potential of this remarkable area. 
Pippa Milne
Chief Executive, Argyll, and Bute Council 
Page 50

Page 51

6 
Introduction 
Welcome to our annual report. This report is an opportunity to share with you how your council has performed over the past year and is part of our
public performance reporting commitment. 
Argyll and Bute Council’s vision and strategic direction is set in our Corporate Plan. Central to our corporate plan and highlighted throughout this
report is successful partnership working with our partners, stakeholders, and local communities. In 24/25 the corporate plan set out three key
priorities to fulfil our vision of a prosperous, inclusive, and sustainable Argyll and Bute. 
People and Places: our core business as a council
Potential and Growth: turning opportunities into reality
Partnership and Action: everyone has a part to play in Argyll and Bute’s success  
Our performance on these priorities over the past year was monitored via seven high-level Corporate Outcomes and a series of 47 Corporate
Outcome Indicators (COIs). These indicators are strategic in nature and are reported annually to the Audit and Scrutiny Committee and Full Council. 
Detail on our performance against these Corporate Outcome Indicators as well as further information on our key activities and areas of focus and
successes and challenges are provided within this report. 
Page 51

Page 52

7 
Financial statement  
In 2024/25 the budget gap was £10.167m prior to any measures to balance the budget and projected to rise to over £55m over a five-year period,
with decisions made to bridge the 2024/25 gap, reduce future year pressures, and protect vital services. 
When agreeing the 2024/25 budget, the Council committed to provide funding for additional leisure, tourism, regeneration, and other initiatives
totalling £0.248m which included funding for the following organisations: 
£0.010m for the International Eight Metre Association World Cup.
£0.075m for the Argyll and the Isles Tourism Co-operative.
£0.075m for the Culture, Heritage, and Arts Assembly (CHARTS).
£0.028m for the Screen Machine mobile cinema.
£0.030m for the Mid Argyll Community Pool in Lochgilphead.
£0.030m for the MacTaggart Leisure Centre on Islay. 
Over the course of 2024/25 almost £549,134 in Scottish Welfare Fund grants were paid to support vulnerable people and £968,036 of Discretionary
Housing Payments were distributed to households in need. 
During the year, the Council also continued to pay grants to cover food and fuel for people in poverty and successfully referred them for support to
advice agencies; this resulted in maximised benefit income and reduced fuel costs of over £109,920 by the end of the 2024/25
Page 52

Page 53

8 
Council priorities 
In 2024 the council administration announced our priorities for 2024-2027. Our aim is
clear: Argyll and Bute’s economy and population need to grow, and our seven
interconnected priorities contribute to that. The themes that underpin these priorities
and the actions to deliver these can be found on our website: Priorities of Argyll and
Bute Council | Argyll and Bute Council
Communities
Our communities are as diverse as our geography and have varying needs, challenges,
and opportunities. We want to harness local knowledge and work together to develop
shared priorities.
Children and young people
Giving young people the best start in life and ensuring we have the right skills for a
prosperous future, are key elements of making Argyll and Bute an ideal choice for
families to stay or to relocate. 
Environment
The Council has already declared a climate emergency continues to keep this a primary
consideration. Recognising the importance of climate change is a key factor when we
consider how we do business. We are committed to achieving 75% carbon reduction by
2030 and net zero before 2045.
Speaking up for Argyll and Bute
Collective, as well as collaborative, action is necessary to deliver growth on the scale
that Argyll and Bute needs. No single agency alone can deliver on Argyll and Bute’s
overarching aim of significant, vital population and economic growth. 
Sustainable service delivery
We want to provide the best services we can for the money and resources available – and make clear the standards that our communities can
expect. We know that this is important to local people. 
Transport, infrastructure and digital connectivity
Argyll and Bute’s mix of rural and island communities mean that transport, infrastructure, and digital connectivity are crucial in the drive for growth.
We need effective and reliable ways to bring people, goods and services to Argyll and Bute – and to carry our own products. Reliable, resilient digital
Page 53

Page 54

9 
links have a highly significant contribution to make to growing the population and the economy. They can add considerable value to Argyll and Bute’s
position as an ideal choice to locate to. 
Housing, economic growth and population
Access to housing is a factor in almost every aspect of Argyll and Bute’s crucial growth agenda. It contributes to the success of economic
development, recruitment, employment opportunities, service delivery and much more. Population growth is crucial to our economic success as
decline impacts on our ability to sustain and deliver services in the future. We value the impact and return on investment that effective, targeted
economic development can have. 
Cross-cutting activities 
Connect for Success 
This initiative is dedicated to encouraging and recognising new ways of working across the Council, to make things better for everyone. We are
looking to the future and are focused on advancing how we use technology, share resources, and collaborate because better for us is better for our
communities. 
There are 7 key areas, or principles, that we are focused on developing in how we work: 
1. One Council One Place 
2. Purpose and Mission Focus 
3. Employee Empowerment 
4. Data and Evidence Driven 
5. Learning Council 
6. Agile Mindset
7. Maximise Useful Technology 
Across the council these principles are in action and people are working on new projects and in new ways to help make things better. For example,
we have reduced bureaucracy and saved time and effort by implementing a project to streamline our internal human resources systems and speed
up the recruitment process. Connect for Success is about bringing the 7 principles to life by sharing ideas and looking for new ways to innovate to
help us do our jobs and deliver services. 
Page 54

Page 55

10 
Partnership working
As part of our Connect for Success principles we continue to work with colleagues across all teams and services, and where appropriate external
partners and stakeholders to achieve a common goal. 
This approach to partnership working assists in improving efficiencies and removing work barriers, fully utilising what we have, connecting staff
through technology, connecting services in delivering change and services, while connecting with communities and working together to improve
outcomes for Argyll and Bute. 
Our Modern Workspace – reducing costs and increasing efficiencies 
The Our Modern Workspace project is reviewing how we use our workspace, reduce costs, and increase efficiency. Six hub buildings are now
complete and under-utilised buildings under review for repurpose or to be mothballed. The entire project is being delivered through existing capital
programme budgets and Scottish Government Place Demonstrator Funding (£664K awarded to deliver Rothesay Project).
Our largest Office footprint is in Lochgilphead, and a project has been ongoing throughout 2024 and 2025 to create a new vision for the Council
headquarters at Kilmory Castle by creating a modern public sector and democratic hub. The aim is to create a better and more sustainable place to
collaborate and do business. We have been working with other public sector agencies, and an implementation plan is evolving to take the project
into development in 2025/26. 
The Project has delivered significant savings from rationalising shared offices through:
• Non-Domestic Rates relief on the buildings that have been closed.
• A reduction in utility consumption.
• A reduction in cleaning costs.
• A reduction in the number of printing devices required.
• A reduction in paper and the need to print as we adopt a more digital approach to service delivery.
• A reduction in annual ICT network charges, such as ISDN lines and broadband charges.
• Reduced ongoing cost pressures for replacement of network equipment (Wi-Fi access points / server switches etc.), where possible
network equipment has been utilised in other locations. 
These savings and ease on cost pressures will continue to grow as the Our Modern Workplace project continues to deliver town by town. 
Performance Excellence Project 
We are continuing to improve the way that we measure and report on our performance as a Council, in line with Connect for Success. We aim to
make it clearer for Councillors to scrutinise our service performance and easier for the public to see what we deliver. 
Page 55

Page 56

11 
This year we have begun to align our strategies and plans with the new council priorities and are making full use of the technology available to us
through M365. We are designing new planners and dashboards to best show the data we hold, which will support review and evaluation of our
performance so that we can ensure continuous improvement. We are designing this with a pilot group of team managers. 
Microsoft365 
With Education colleagues now being introduced to Microsoft 365 (M365) and Teams, the move to using Teams for Telephony for all staff will be
completed well before the retirement of Skype for Business in October 2025. The continued development of existing and new apps has added many
more options for staff in how they use M365, and they are now also supported by having access to a nationally resourced M365 Skills Hub. 
The Digital Champions programme is being reviewed and refreshed to ensure the most is made of our investment in M365 and that staff have the
support they need from within their own services. The opportunities that MS Copilot presents will be evaluated in a pilot of 100 staff prior to decisions
being taken on the significant additional investment that a rollout to even a proportion of staff would represent. It’s anticipated Copilot will further
enhance the benefits to staff and customers of using M365 in their daily work. 
ICT and Digital 
The Council’s ICT and Digital Strategy aims to position Argyll and Bute Council as a “digital by default” authority. The strategy resulted in the
development of an action plan containing almost 100 activities designed to lead to further efficiencies, savings, and improved services for Council
staff and customers. 
We outlined a vision to provide digital technologies and processes to support our people and our customers, to encourage collaboration, get things
done and contribute to a better organised and more efficient council.
The Accounts Commission’s April 2025 report on Best Value in Argyll and Bute Council found that “Given its remote and rural characteristics, the
council is ahead of the game in terms of achieving efficiencies, including through its use of digital technology, with exciting examples of innovation
within service areas.”
This improved position hasn’t happened by chance. Our ICT and Digital Strategy over the last 4 years has focused on delivering key outcomes for
our customers, simplifying, and improving our processes, providing secure and fit for purpose technology solutions and creating an agile culture for
our workforce. 
New ways of working with ICT and Data
Data is at the heart of key decision-making and improving outcomes for Argyll and Bute’s residents and communities. Our new Data Platform is now
live, and the Data Advisory Group and the data team are dealing with a variety of exciting new data challenges. 
Examples of data challenges in 2024/25: 
Page 56

Page 57

12 
• The Climate Change Officer produces reports to both the Scottish Government (against national targets for 2030 and 2045) and quarterly
reports to the Climate Change board. These reports require extensive data collection, analysis, and projection modelling. Using new data
models, the council’s Climate Change Board can now visualise the challenge of meeting the Scottish Government’s statutory emissions
goals. It is also now possible to perform fairly complex scenario planning to consider different strategies for reaching these goals, and aiming
to reach them sooner, based on a better understanding of the potential long-term impact of working to reduce specific carbon emission
sources more quickly.
• As part of our aim to bring as many empty business properties back into use as possible, we used our PowerBI reporting tool to extract and
analyse Non-Domestic Rates (NDR) data. This gave us information on rates of business change, business types, rateable values etc which
the Empty Business Property Officer can use to target actions to for businesses, seek inward investment or coordinate other interventions
such as a change of use for a property to make it more attractive to business in the local area.
Climate Change
The Council continues to meet its statutory duty to report on emissions and climate action through the annual Public Bodies Climate Change Duties
Report, with strategic oversight provided by the Climate Change Board. We are developing a comprehensive Net Zero Route Map to provide a
detailed pathway for Council operations to achieve net zero emissions by 2045. 
Operational Achievements
Significant progress is being made across the organisation through investments in building energy efficiency, renewable energy generation, and fleet
decarbonisation. Independent analysis confirms the Council successfully managed its energy use to outperform national benchmarks during a year
of unprecedented electricity grid challenges. 
A major milestone was reached in October 2024 with the completion of an 86kW roof-mounted solar PV system at Cardross Primary School,
representing the culmination of the Non-Domestic Energy Efficiency Framework (NDEEF) programme. The system joins the Council's expanding
renewable energy portfolio, which now includes 27 solar PV installations across the area with a combined capacity of over 1.3MWp.
Another significant achievement was the innovative stabilisation of the Grade A-listed Burnet Building in Campbeltown. The Council implemented a
cutting-edge geopolymer resin injection solution involving 250 injection points reaching depths of two metres beneath the building structure. This
non-invasive method allowed the building to remain operational throughout the works and delivered approximately 78% lower carbon emissions
compared to traditional concrete underpinning - an estimated carbon saving of 50.7 tonnes. 
The Council's LED streetlight replacement programme has achieved remarkable results, with over 14,000 luminaires replaced. Annual CO₂
emissions have dropped from 3,140 tonnes in 2015/16 to a projected 264 tonnes for the full 2024/25 financial year (based on performance to
September 2024) – a reduction of 92%. 
Page 57

Page 58

13 
Partnership and Community Leadership
The Community Planning Partnership has made substantial progress in developing the Argyll and Bute Climate Action Strategy, funded by CPP
partners including Argyll and Bute Council, with the project lead hosted by Argyll Countryside Trust. This comprehensive strategy represents a
region-wide, community-led approach to achieving net-zero and climate resilience, developed through extensive engagement with communities and
stakeholders across Argyll and Bute. The strategy establishes the vision that "We make Argyll and Bute climate ready by acting together to
understand and adapt to our changing climate". 
Carbon Neutral Islands Programme
Argyll and Bute Council supports the Scottish Government's Carbon Neutral Islands (CNI) Programme through the Local Authority Advisory Group
and accessing the Carbon Neutral Islands Capital Fund. Highlights for 2024/25 are: Governance and Alignment –Membership of the Local Authority
Advisory Group ensures island plans mesh with wider council and national policy and that good practice is shared with mainland communities.
Strategic Foundations – Community Climate Action Plans are in place for Islay, Great Cumbrae, Hoy, Raasay, and Yell. Comprehensive carbon
audits have established baseline emissions for each island. Investment and Delivery – Tailored climate-change investment strategies have been
completed to guide project selection and funding bids. £1 million of capital funding allocated for 2024/25 to kick-start priority net-zero projects. For
Islay this is supporting the installation of solar PV and battery technology across 7 community buildings as well as supporting the Islay Forestry
Initiative through the purchase of equipment for wood fuel processing and creation of a community orchard. Overall, the programme has moved from
planning to implementation, giving every island a clear emissions baseline, an agreed action plan and the first tranche of capital to put projects on
the ground—all aimed at achieving carbon neutrality by 2040, five years ahead of Scotland's national target.
Capital Investment and central repairs delivered
We have successfully delivered a programme of investment in our property assets totalling £10.5M. Included within the wide variety of investment
projects were 53 projects relating to energy efficiency, reducing fossil fuel consumption and renewable energy generation. This included solar
panels, air source heat pumps and new automated control systems in our buildings, mainly in our schools. 
As well as delivering the additional investment projects, emergency, planned and statutory maintenance programmes were successfully delivered,
resulting in improved customer satisfaction. Additionally, a separate large-scale project reviewed the water, wastewater, and drainage charges for
the Council. This project has delivered one-off refunds in the region of £570,000 and year-on-year savings of more than £160,000 per annum.
Housing and the Housing Emergency
In June 2023 the Council’s Environment, Development and Infrastructure (EDI) Committee declared a Housing Emergency due to a persistent
reduction in the supply of housing, a steady increase in demand for housing across all tenures and increasing levels of un-affordability. 
In November 2024, Members of the Scottish Government, Local Government, Housing and Planning Committee, visited Oban. They met with the
Council’s leader Jim Lynch, CEO Pippa Milne, other senior council officials, and representatives from the Link Housing Group together with a
Page 58

Page 59

14 
representative from the Colonsay Community Development Company. The day also included a visit to the Dunbeg Corridor housing development.
The Scottish Government has produced a report of the visit which can be accessed here: A report on Committee visit to Argyll & Bute Council, 25th
November 2024 
In January 2025 consultants were engaged, to develop the Strategic Development
Framework for Oban (OSDF) and Helensburgh (HSDF). Both are intended to identify
long-term 20-40 years strategic development opportunities. 
The Council has continued to develop Business Cases for the proposals for a worker
accommodation pilot on Mull, and market housing for principal home occupation on
Islay. In addition to the £3m Rural Growth Deal investment allocated to these projects,
further funding is being sought to enable housing projects. 
The Council has employed local contractors and is working with Mull and Iona
Community Trust to deliver worker housing in Tobermory. Work is underway to procure
tender costs for construction of the worker housing which will provide 12 units. It is
anticipated a site start for building construction in spring 2026. 
A Local Heat and Energy Efficiency Strategy (LHEES) was approved by Council in
November. This sets out a policy framework that assists in reducing fuel poverty in the long term. Officers will now work to identify deliverable
projects and use the LHEES to support funding applications. 
The Home Energy Efficiency Programme Scotland (HEEPS) allows homeowners and private rented tenants to reduce their energy bills, assists with
the cost-of-living crisis, and reduces energy consumption contributing to a reduction in climate change   The Council fully utilised HEEPS funding of
£1,979,827 for 24/25. 
Our Empty Homes Officer project, working with the HSCP solely to assist empty homes owners to bring back properties in to use for HSCP staff has
received national recognition through an award from the Empty Homes Network. This project is directly supporting the retention and recruitment of
the key workforce required to sustain essential services and making the best use of existing stock. The role has directly enabled homes and bed
spaces for use by HSCP workers in Coll, Connel, Tiree & Islay.” 
Page 59

Page 60

15 
Our performance 
This table presents our progress in delivering the seven Corporate Outcomes outlined in the previous Corporate Plan (2022–2027). It is followed by
detailed performance data and supporting commentary for each Corporate Outcome Indicator." 
Overall performance of our Corporate Outcome Indicators
Corporate Outcome Number of
Indicators
Number On Track /
Above Target with
Improving
Performance
Number Off Track /
Under Target / No
Data  No Target 
People live active, healthier, and independent lives 6 3 3 0
People will live in safer and stronger communities 4 3 0 1
Children and young people have the best possible start 8 5 2 1
Education, skills, and training maximise opportunities for
all 7 1 3             3
Our economy is diverse and thriving 12 0 2 10
We have an infrastructure that supports sustainable
growth 5 3 0 2
Getting it right 5 2 0 3
TOTAL 47 17 10 20 
We continue to report other indicators of importance on a quarterly basis at each of our Area Committees. Quarterly Area Performance Reports
present a suite of indicators at a local, area level with complementary narrative, and, where possible, Council-wide performance is also presented
alongside these indicators. These can be found in the Performance and Improvement section of the Council website. Performance and Improvement
| Argyll and Bute Council (argyll-bute.gov.uk) 
Page 60

Page 61

16 
How We Compare – Local Government Benchmarking Framework (LGBF) 
In addition to monitoring our corporate outcomes we use a variety of improvement tools. A key aspect of this relates to our engagement with the
Local Government Benchmarking Framework (LGBF). 
All local authorities in Scotland participate in the Local Government Benchmarking Framework (LGBF). The data is collected and presented in ways
to ensure consistency and enabling comparisons between councils to be made, as levels of performance are affected by differences in local
circumstances and local priorities. Data for the most recent year will not be complete until after the full twelve months has passed. The majority of
the 2024/25 data will be published by the end of 2025. 
The chart below shows how our performance compares relative to other Scottish local authorities; overall, our performance has improved. In the last
year, 60% of indicators for Argyll and Bute were in quartiles 1 and 2, where performance is above the Scottish average. This compares to 46% of
indicators falling in quartiles 1 and 2 in the previous year.
Between 2022/23 and 2023/24, 23 indicators (out of 99 for which direct comparisons could be made) moved to a higher quartile, 65 indicators stayed
within the same quartile, and 11 moved to a lower quartile. 
Page 61

Page 62

17 
Page 62

Page 63

18 
Delivering our outcomes
Below we provide detail on our performance against each of our Corporate Outcome Indicators and further context on the activities that have taken
place to support delivery in that area. 
Corporate Outcome: People live active, healthier, and independent lives 
Number of indicators: 6 
Number on track: 3
Number no target / no data: 3 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Maximise distribution of
Scottish Welfare Fund 95.30% 120.70% 144.00% 128.56% 119.80% G
The Scottish Welfare Fund provides vital
support to vulnerable households across our
community. During 2024/25 a total of 1,134
households were supported, enabling
individuals to remain safely in their
communities and avoid crisis situations. We
have maintained a high standard of delivery
and responsiveness.
Percentage of clients
satisfied that they are
better able to deal with
their financial problems
following our support
and intervention
90.00% 100.00% 100.00% 100.00% 97.00% G
Following their interaction with advice services,
clients are invited to participate in a customer
satisfaction survey. In the 2024/25 reporting
period, 97% of respondents indicated that they
felt better equipped to address the financial
challenges they were facing.
Maximise distribution of
Discretionary Housing
Payment (DHP) fund
96.00% 98.20% 79.00% 84.30% 89.20% R
The Discretionary Housing Payment (DHP)
fund continued to serve as a vital mechanism
for supporting low-income households facing
housing related financial hardship. Although our
actual expenditure fell short of the 96% target,
a total of 729 households were successfully
assisted in sustaining their tenancies and
avoided housing instability.  
Page 63

Page 64

19 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage of care
services graded as
'good' (4) or better in
Care Inspectorate
inspections
75.0% 80.00% 79.50% 77.30% 84.20% G
The percentage achieved is also above the
reported Scotland Rate (81.9%).
Next years target will be uplifted to 80%. 
Percentage of adults
receiving any care of
support who rated it as
excellent or good
75.30% 68.60% 68.60% 74.00% 74.00% - Data available biannually, next survey data
available 2025/26
Percentage of carers
who feel supported to
continue in their caring
role
29.70% 38.00% 38.00% 38.00%  38.00% - Data available biannually, next survey data
available 2025/26 
Helping people live active, healthier, and independent lives
We have helped residents maximise their income through additional benefits or accessing grants. This work has supported vulnerable people with
assistance with independent living, preventing homelessness and helping reduce the number of households and families living in all types of
poverty, including extreme poverty. 
• A total of £549,134 in Scottish Welfare Fund grants was paid to support 1,134 vulnerable households in our communities who are in need of
financial support. This made up of Scottish Government programme funding and funding by Argyll and Bute Council. 
• Discretionary Housing Payments totalling £968,036 were distributed to 729 households in need to prevent homelessness and assist
vulnerable members of our communities to maintain their tenancies. As a result of new guidance issued from Scottish Government, the
Council’s policy will be reviewed to maximise further use of the fund in future years. 
• We paid out £109,920 in grants to cover food and fuel for people in poverty and successfully referred them for support to advice agencies. 
Page 64

Page 65

20 
• 965 families have been supported to maximise benefit income and reduced fuel costs to the value of £1.357m. 
• The average processing time for new housing benefit claims was 14.67 days and 3.35 days for changes in circumstances against targets of
21 days and 6 days, respectively. 
• We assisted residents to claim £5.4 million in additional benefits that may have otherwise remained unclaimed, assisting independent living
and preventing homelessness. This figure included £821,127 for individuals and families affected by cancer and supported through
partnership with Macmillan Cancer Support and the Welfare Advice and Health Partnership. 
• The Welfare Rights Advice in Health Partnerships Initiative and referral pathway has built on existing links with GP practices and has made a
positive difference to these rural and island communities. Financial gain for 2024-25 for clients referred via this pathway was £418,453. 
• 98% of respondents in our welfare rights customer satisfaction survey would recommend the service. 95% rated their overall experience of
using the service as excellent or good and 96% said the time taken to respond to their initial enquiry was excellent or good. 
• In line with Scottish Government Policy, we implemented an uplift in the basic pay of carers and personal assistants who look after adults in
our communities and Early Learning and Childcare workers employed by Partner Providers to ensure payment of at least the Scottish Living
Wage. 
Page 65

Page 66

21 
Corporate Outcome: People will live in safer and stronger communities 
Number of indicators: 4 
Number on track: 3
Number no target / no data: 1 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage of groups
who say their
effectiveness has
increased as a result of
capacity building by the
community development
team
75.00% 100.00% 90.00% 100.00% 100.00% G
The results are from an annual survey of
customers and community groups engaged
with the Community Planning and Community
Development Team.  
Information provided to
our community groups,
individuals and partners
is easy to understand
75.00% 96.00% 90.00% 93.00% 93.00% G
We recognise the importance of ensuring
accessible communication when engaging
with community groups. 
Total value of
compensation
settlements for vehicle
damage/driver injury as
a result of road/bridge
faults
No target £2,807 £1,879 £1,956 £2,147 No target
Initial claims are recorded by our Roads team
using Oracle system, with a supplementary
record maintained in the designated directory
on the shared network. 
Percentage of adult
residents stating their
neighbourhood as a
'very good' place to live
70.00% - 69.00% No data 74.00% G   The figure for 2022 was 69% so the new
figure of 74% is a significant improvement. 
Page 66

Page 67

22 
Supporting our communities
In 2024/25, funding from the Supporting Communities Fund (SCF) was awarded to 64 groups across Argyll & Bute for the delivery of projects
spanning sport, transport, music, the arts, and environmental initiatives. 
Walking and Cycling in the Dark
The Community Development Team successfully secured funding through the Shaping Places
for Wellbeing Programme to support active travel initiatives in Dunoon. Darkness was identified
as a key barrier preventing children and families from choosing active travel over motorised
transport. In response, five reflective and glow-in-the-dark craft workshops were delivered in
local schools to promote safe travel during darker hours. 
A public workshop was held at Dunoon Pier
on Saturday, 5th October, coinciding with
the launch of the Dunoon Bothy. The event
attracted over 83 attendees, who shared valuable feedback on what would encourage them to
walk and cycle more. 
These insights were shared with the Active Travel Team. The project was delivered in
partnership with Community Police, Cycling UK, and the Dunoon Development Trust. 
Following the workshops, 70% of pupils reported they would be more likely to walk or cycle in the
dark. Feedback from children, staff, and parents was overwhelmingly positive. The activities were inclusive, accessible to all ages and abilities, and
fully adapted for pupils with complex needs. 
Oban Community Council – Local Place Plan & Flood Resilience
Ongoing engagement with Oban Community Council has focused on their Local Place Plan (LPP) and the work of their Flood Resilience Subgroup.
A joint meeting was facilitated between Oban Community Council and an internal colleague involved in the Oban Strategic Development Plan, to
explore opportunities for collaboration and ensure alignment of efforts, helping to avoid duplication. 
Page 67

Page 68

23 
Victory Hall, Benderloch – Community Engagement Project 
Victory Hall successfully secured SCF funding to support a local community engagement
initiative. 
A meeting was held with the group to discuss the scope and aims of their project and
guidance was provided using the VOICE Community Engagement Toolkit to help align
their approach with the National Standards for Community Engagement. 
Good practice for engaging with children and young people was also discussed and
ongoing support is being provided as the project progresses. 
Ardrishaig Community Council – Local Place Plan development
Following attendance at a community-led plans training session in December 2023, Ardrishaig
Community Council progressed their intention to develop a Local Place Plan (LPP). 
They were advised to establish a steering group and a facilitated workshop once the group was in place.
The group was signposted to relevant funding opportunities, including the Community Led Local
Development Fund and Awards for All and agreed to focus on person-to-person engagement,
recognising their own skills and capacity to lead the process. 
The group developed ideas for community outreach and proposed forming a diverse working group of
residents, with clear lines of accountability through designated representatives. 
Page 68

Page 69

24 
Corporate Outcome: Children and young people have the best possible start  
Number of indicators: 8 
Number on track: 5
Number no target / no data: 3 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Provide quality meals
within cost margins to all
pupils
+/-5.00% -0.04% -2.56% 0.48% -1.73% G  Delivered 1.2m early years, primary and
secondary school meals.
Increase the percentage
of our care experienced
young people that have
the recommended
additional tracking and
monitoring plans in
place
100.00% 100.00% 100.00% 100.00% 100.00% G 
Each care experienced child and young
person (CECYP) enrolled in an authority
school has tracking and monitoring in place
via our education management system. Data
collected includes attendance, exclusions,
progress and attainment and wellbeing
information. The Virtual School adds an
additional layer of scrutiny to this process
through a series of attainment meets and
partnership working, helping to ensure our
CECYP have the supports required. We
continue to work with partner agencies and
other local authorities to support our CECYP
hosted out with Argyll and Bute  
Percentage of children
living in poverty (after
housing costs)
No target 21.7% 23.5% No data No data   No target
Data collated by End Child Poverty, 2024/25
data not yet published. 
Last data available 2022/23.
Page 69

Page 70

25 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage rate for
attendance across all
Argyll and Bute schools
is comparable or better
than the Scottish
national average
(biennial data)
92.00% 93.30% 90.55% 92.85% 90.80% R  
Maximising attendance remains a key
strategic priority, with ongoing liaison with
Education Scotland colleagues to ensure
alignment between local policy and national
recommendations.
Support the increase in
the update of available
grants, allowance, and
entitlements
2,573 2,853 2,999 3,125 3,750 G The implementation of online grant processing
has enabled staff to exceed targets.  
A counselling service is
available in all
secondary schools
100.00% 100.00% 100.00% 100.00% 100.00% G
The service has supported 472 young people
in secondary schools and 216 children in
primary schools. The most common reasons
for referral include anxiety, low mood, family
difficulties, and emotional regulation. 83% of
young people and 81% of primary-aged
children completing support reported positive
clinical outcomes, including reduced
psychological distress and improved
emotional resilience.
Percentage of children
with no concerns across
all domains at 27-to-30-
month assessment
82.10% 87.30% 85.30% No data No data  -
No data is available for 2024/25. This
measure is taken from SOLACE LGBF
indicators but has not been reported since
2022. 
95% of schools have a
suitability rating of A or
B
95.00% 95.00% 95.00% 95.00% 98.00% G The overall position for suitability scores is
61% have a rating of A, 37% were rated as B.   
Page 70

Page 71

26 
Support and interventions for our care experienced children and young people
Each care experienced child and young person (CECYP) enrolled in an authority school has tracking and monitoring in place via our education
management system, SEEMIS. Data collated includes attendance, exclusion, progress and achievement and progress over time. Scrutiny of this
data has led to early interventions to support our CECYP, in some cases positively impacting attendance and attainment. To date we have zero
exclusions of CECYP. This is a major success that can be attributed to supportive policy, collegiate and partnership working and greater awareness
of the needs of our CECYP community. 
The Virtual Head Teacher (VHT) links to Designated Managers across settings where CECYP are enrolled to both support and challenge the
learning experience for our CECYP. We continue to explore the information arising from our data, ensuring our Health and Wellbeing Family Liaison
Officers target those most in need. We are supported by wider colleagues in education to meet this target. 
Addressing non-attendance 
Seven out of ten secondary schools have completed the Addressing Non-Attendance training programme and continue to implement this with
support from Educational Psychology Service. Training for primary school staff has been developed and implemented in some settings. Across the
authority, the Maximising Attendance policy is supporting a more consistent and data-informed approach to monitoring attendance and intervening
early to help children, young people, and families overcome barriers to school attendance. Maximising attendance remains a key strategic priority,
with ongoing liaison with Education Scotland colleagues to ensure alignment between local policy and national recommendations. 
UNICEF UK’s Rights Respecting School Programme
Apple Tree Nursery in Rothesay became the first nursery in Argyll and Bute, and only the third in Scotland, to receive a prestigious gold award from
UNICEF UK’s Rights Respecting School programme. 
Children living in Poverty
We are one of the lead players on a national level identifying those who are not in receipt of full benefit entitlement, working to identify ways of using
data to identify those in need. Work is ongoing with the Improvement Service and Scalable Approach to Vulnerability Via Interoperability (SAVVI) to
find the best approach and legal gateways to allow use. 
Reducing poverty with the power of right advice
Our Welfare Rights Team has a significant impact in the outcomes for families by helping them maximise their uptake of available benefits grants
and allowances, securing Client Financial Gain in excess of £4 million per year. Key to success is the close working of statutory and voluntary
sectors. Examples include: 
Flexible Food and Fuel Fund – our benefits team, ALI energy and the Bute Advice Centre manage this innovative scheme that sees considerable
grant aid to people every year, coupled with benefit and fuel poverty solutions advice.
Page 71

Page 72

27 
Infant Food Insecurity Pilot – a one-year pilot study is taking place to access the level of crisis need for baby formula, where there is no other
immediate solution. Supermarket vouchers are placed with Midwives and Health Visitors and a picture of the nature of this need is being identified. 
Safe homes for families who need them most
The Local Housing Strategy (LHS) aligns with the aims and objectives our Child Poverty Action Plan and outlines a series of actions to address
disadvantage and alleviate poverty. These include preventing families and young people in certain situations from incurring rent arrears, from
becoming homeless, assisting families with a disabled family member, and assisting larger families. 
In 2024/25, 476 homeless cases were closed, of which 121 involved households with dependent children (amounting to 199 children) and 86 of
these households received a positive outcome. 
There has been a slight reduction in homeless applications between the 1st of April 2024 and the 31st of March 2025. During that period, 459
homeless applications were made, a decrease of 34 applications (7% down) in the same period in the previous year.
Making life more affordable for families
Pre-loved School Uniform Project - The two-year funded pre-loved school uniform project has come to an end. The project was set up to focus on
the reuse of good quality preloved school uniform and the recycling of uniforms that are no longer fit for purpose. Working with schools, community
groups, and parent councils across all seven of our main settlements to support eco-friendly reuse school uniform schemes that cover school
uniform for Early Learning Centres, Nurseries Primary and Secondary Schools linked to each school cluster. We investigated, supported, and
promoted taking donations of uniform from parents and pupils, ways to launder them and methods of redistributing them as and when they are
required. 
The project has achieved many of the goals we envisaged and many more that developed during the project in a positive and meaningful way. It
also highlighted that more work is needed to keep this momentum moving forward. Much of the work and schemes will continue and the project has
shown that with further support and encouragement much more could be achieved. For full details of the project report, when published, will be
available from Pre-loved School uniform scheme | Argyll and Bute Council. 
My Tribe Free Period Product Initiative - our free period product initiative, plays a vital role in tackling child poverty by ensuring that no child misses
out on education due to lack of access to essential items. By providing free period products in over 150 community locations and through a user-
friendly online ordering system that delivers directly to any household in Argyll and Bute, My Tribe helps ease financial pressures faced by families. 
Schools Share and Recycle - Gigha Primary school have a community fridge, which they keep fully stocked with fresh items of food. They have been
very surprised at the uptake and need to restock very regularly. Dalmally Primary School are actively involved with the charity Mary’s Meals and
pupils fundraise and raise awareness. Most of our schools have a Uniform Bank where pupils can access pre-owned items of school uniform. Pupils,
staff, and parents spoke of the Uniform Swap Shop, with children learning that not everything needs to be bought new. 
Page 72

Page 73

28 
Award winning school meals service
We delivered 1.2m early years, primary and secondary school meals, with new menus introduced in August 2024 receiving positive feedback. The
Catering Team wowed judges at the Public Sector Catering Awards with their wild venison school meals, earning them the Sustainability Award.
Early years and primary meals were awarded a recertification for Food for Life Served Here - Bronze award. 
School Counselling Service
The service has supported 472 young people in secondary schools and 216 children in primary schools. The most common reasons for referral
include anxiety, low mood, family difficulties, and emotional regulation. 83% of young people and 81% of primary-aged children completing support
reported positive clinical outcomes, including reduced psychological distress and improved emotional resilience. This is further supported by positive
parent feedback, with 100% of parents feeling more confident in supporting their child's emotional and developmental needs and 94% observing
positive changes in their child’s wellbeing. 
School suitability ratings
Through the Capital Programme only Tobermory 2-18 school still has a C rating for suitability. There are plans for a new school on Mull through the
LEIP programme which will ensure 100% of our schools will have a suitability of A or B. The four-year planning for the new school building in
conjunction with the Hub North, will ensure that the new school have both a condition and suitability scoring of A.  Page 73

Page 74

29 
Corporate Outcome: Education, skills, and training will maximise opportunities for
all 
Number of indicators: 7 
Number on track: 1
Number no target / no data: 6 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Maintain the
percentage of all
young people leaving
school achieving a
positive destination
into further education,
training, or
employment.
*ACADEMIC YEAR
95.00% 93.50% 95.20% 94.30% No data -
The data supplied for 2024/25 will not
be available from the Scottish
Government until February 2026. 
Maintain the
percentage of
successful
examination
presentations in
Levels 4 and 5 for
literacy and
numeracy by our
senior phase pupils
*ACADEMIC YEAR
60.00% 97.00%
SCQF4
87.23%
SCQF5
66.84%
SCQF4
84.08%
SCQF5
66.59%   
64.82% G
The percentage of Argyll and Bute
school leavers who achieved Level 5
literacy and numeracy was 64.8%,
above the target of 60%
Page 74

Page 75

30 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage of
modern apprentices
that go on to a
positive destination
after completing the
Argyll and Bute
Modern Apprentice
Programme
95.00% 96.10% 96.20% 94.55% 90.00% R
The target was narrowly missed due
to a small number of applicants not
completing the programme however,
70% have successfully secured
employment within the Council.
Percentage of
children that achieve
their appropriate
developmental
milestones by
Primary 1
70.00% 64.00% 63.00% 61.00% 61.00%  R
As a result of developmental effects
of covid lockdowns, we continue to
work collaboratively with health and
allied health professionals to ensure
that we are addressing
developmental concerns as early as
possible.     
Percentage pass rate
for the National 5
qualification is
comparable or better
than the Scottish
national average
*ACADEMIC YEAR
No target 79.70% 77.39% 75.60% 77.20%   No target
The Argyll and Bute A-C pass rate of
77.2% is in line with the National
figure of 77.4%. The A-D pass rate of
89.9% is slightly above that of the
national figure 989.2%) 
Percentage pass rate
for the National
Higher qualification is
comparable or better
than the Scottish
national average
*ACADEMIC YEAR
No target 80.90% 77.35% 72.00%  73.40%  No target 
The Argyll and Bute A-C pass rate of
73.4% is slightly behind the National
pass rate of 74.8%. However, the A-
D pass rate of 89.9% is slightly above
that of the national figure (89.5%)     
Page 75

Page 76

31 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Increase the uptake
of wider achievement
opportunities which
complement
traditional SQA
awards and offer
alternative ways to
develop learning, life,
and work skills
No target - 88.00% 100.00% 9.98%   No target In 24/25, 9.98% of all senior phase
pupils completed a wider
achievement award as part of their
overall attainment profiles.               
Developing the young workforce
Analysis of 23/24 attainment data has been completed and demonstrates a continued growth in the presentation for and passing of wider
achievement awards. Data shows that the percentage of senior phase pupils who presented for a wider achievement award has grown from 7.3% in
22/23 to 9.9% in 23/24. This figure also surpasses the 5 years high of 9.8% in 2019/20. The average tariff points awarded to Argyll and Bute pupils
(52) who passed wider achievement points is also above the virtual comparator (35) and national figures (36). This average was also an increase on
the 22/23 figure (46). These two figures show that a higher proportion of our pupils are engaging with high quality wider achievement awards. We
received the Insight raw data set in November which allows us to explore at a pupil level which wider achievements were achieved, and in which
centres they were presented. Analysis of the data is underway to ensure the relevant Education Officer is equipped with the best insight possible to
support and challenge our schools. 
Further analysis of Insight leavers data, published in February 2025, shows that wider achievement made up 11.4% of all attained entries for our S6
leavers. This was the highest it had been in the last 5 years and higher than both the virtual comparator and the national figure. This data shows that
wider achievement is increasingly becoming part of a revised curriculum which complements traditional SQA awards. 
Helping People into work
Education and DYW have worked in partnership with Skills Development Scotland (SDS), the 3rd Sector and a wide and increasing range of
employer partners to develop young people’s skills, formulate personalised learning pathways and track young people’s progress, both towards and
within positive destinations. As a result, 94.8% of school leavers in 2023/24 entered positive destinations and 94.3% of all 16–19-year-olds were in
education, training or employment, which equates to Argyll and Bute ranking 9th out of Scotland’s local authorities. 
Partnerships between schools and employers have continued to increase and as a result, a total of 387 work placements – a 60% increase on
2023/34 – have supported young people to plan their individual vocational pathways and develop skills for life and work, confidence and resilience. 
Page 76

Page 77

32 
Forty Flexible Learning Plans (FLPs) have been in place across all secondary schools. FLPs have continued to provide bespoke curricula for young
people who require such provision. All secondary schools have demonstrated increased capacity for and commitment to planning individualised
curricula and timetables for young people. As a result, vulnerable young people at risk of disengagement have re-engaged with education and are
entering sustained destinations in employment and training/apprenticeships. 
Frequent and regular 16 Plus meetings are being held in secondary schools in partnership with SDS and DYW. As a result, all secondary schools
have robust frameworks for intervention to support school leavers at risk of not entering a positive destination, and to track young people post-school
to ensure positive destinations are sustained. 
Our number of Modern Apprentices employed has remained consistent over the last few years, but to improve our approach we have included
evaluation in our Growing Our Own framework. Modern Apprentices and their managers will be encouraged to provide feedback in this respect to
ensure that the programme remains fit for purpose as a pipeline into longer-term employment. 
Literacy and Numeracy
Full analysis of 23/24 literacy and numeracy data has highlighted the varying levels of attainment across all schools which will allow for interventions
to be designed and implemented. This information, along with other relevant measures, has been organised into secondary attainment meeting
packs which will be used to support improvement meetings. S3 BGE data for 23/24 shows increases at the fourth level, which should logically flow
into improvements at National 4 and 5 awards in 24/25. Insight data for leavers, which included post appeal data, was published in February 2025.
The percentage of leavers who left with Level 4 literacy and numeracy was 83.2%. The percentage of leavers who left with Level 5 literacy and
numeracy was 64.8%. Both are above the target of 60%. 
Play on Pedals 
Our Play on Pedals collaboration with Bike-ability Scotland is now operating in 3 of our 4 localities, including one island, enabling young children to
achieve their gross motor milestones, through learning to balance and pedal a bicycle. We are currently awaiting our most up to date development
data, however, initial qualitative data indicates that for children involved in the scheme, achievement of gross motor developmental milestones is
above average, and as an additional benefit, stronger parental engagement and confidence in cycling with their children has been reported. 
Attainment 
Attainment data for the 2023/24 academic year has been reviewed at both the authority and individual school levels. At the authority level, Argyll and
Bute recorded a National 5 pass rate of 75.9%, slightly below the national average of 77.2%. Notably, five out of ten secondary schools in the area
achieved pass rates above the national figure. Further analysis revealed that in 15 National 5 courses, Argyll and Bute's pass rates exceeded
national performance. 
At the Higher level, the authority-wide pass rate was 72.0%, again slightly trailing the national average of 74.9%. However, three secondary schools
outperformed the national pass rate. Additionally, Argyll and Bute achieved higher pass rates than the national average in 16 Higher courses.
Page 77

Page 78

33 
Schools have received detailed data to support targeted improvements at the subject level. Information from the results machine has been shared,
enabling schools to identify subjects that are performing above or below national averages. This insight allows for focused attention on specific
course components to enhance overall performance. 
Schools have also been provided with data on the accuracy of their grade estimates for the 2023/24 exam diet. This will support improvements in
assessment and moderation practices, helping schools more effectively track learner progress. 
Page 78

Page 79

34 
Corporate Outcome: Our economy is diverse and thriving   
Number of indicators: 12 
Number on track: 0
Number no target / no data: 12 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Maintain the
percentage of local
suppliers that benefit
from the awards of
contracts via the
procurement portal
20.00% 13.50% 19.90% 17.80% 18.70% R
During 2024/25, 183 tender/quick
quote contract awards were
placed with 203 successful
suppliers, 38 of which were local
suppliers (18.7%).
Increase the number
of community
benefits that are
delivered through the
contracts we award
locally
No target 55 73 74 75 No target
31 Community Benefits have been
achieved through Contract
Management, Contract Awards
and the Request List .44
Community Benefits have been
achieved through Contract
Management, Contract Awards,
and the Request List.
Number of business
and industry planning
applications
submitted annually
No target 19 23 21 13  No target
Although applications submitted
during 2024/25 have decreased,
these include some significant
new investments in Argyll and
Bute.
Percentage of
homeless applicants
who required
temporary
accommodation this
period
No target 40.00% 34.00% 29.00% 29.00% No target  29% of new homeless applicants
required temporary
accommodation in 2024/25. 
Page 79

Page 80

35 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Number of affordable
social sector new
builds completed per
annum
No target 145 188 70 54   No target
Registered Social Landlord (RSL)
partners completed 44 new
affordable housing units across
Argyll and Bute. 
Total number of
visitor trips to Argyll
and Bute
No target 1.5M 2.5M 2.8M 3.312M No target
Data provided by Scottish Tourism
Economic Activity Monitor
(STEAM) on an annual basis
(calendar year). The significant
increase from 2021 to 2024 is due
to the number of visitors
recovering from extremely low
numbers during the Covid-19
pandemic period. 
Total visitor spend in
Argyll and Bute
No
target   £262.5M £407.5M £461.5M  £566M No target
Data supplied by Scottish Tourism
Economic Activity Monitor
(STEAM) on an annual basis
(calendar year). The significant
increase in the total economic
impact of tourism from 2021 to
2024 is due to the number of
visitors recovering from extremely
low numbers during the Covid-19
pandemic period.
Gross Value Added
(GVA) per capita No target £23,394 £47,270 £47,270 No Data   No target
Data supplied by Office for
National Statistics (ONS). Data not
yet available.  
Page 80

Page 81

36 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Unemployment rate -
claimant count as a
%age of working age
population
No target 4.00% 2.80% 2.50% 2.70% No target
In April 2025, 2.7% of the working
age population in Argyll & Bute
were claiming unemployment
benefits – lower than the national
average for Scotland of 3.1% and
significantly below the UK average
of 4.1%. 
Unemployment rate -
claimant count as a
%age of the
population (16-24)
No target 4.30% 2.80% 0.41% 0.43% No target
As of April 2025, 0.43% of the
population aged 16-24 in Argyll &
Bute were claiming unemployment
benefit. While no target has been
set, the key focus remains to
maintain low unemployment levels
and to ensure that individuals are
engaged in sustainable and
meaningful employment, rather
being under employed. 
The number of
Business Gateway
start-ups per 10,000
of population
No target 154.3 135.7 135.0 152.0 No target 
During 2024/25, Business
Gateway successfully supported
the creation of 152 new start-ups. 
Geographical
percentage coverage
of 4/5G mobile
connectivity
95.00% 79.00% 81.00% 85.00% 89.00% R
According to latest Ofcom report
update (Jan 25), 
57% of Argyll and Bute
Geographic Area has 4G
coverage all 4 operators, this rises
to 89% coverage from at least 1
operator, however there are
geographic variations dependant
on mast locations and level of
investment, 11% of Argyll and
Bute Geographic area has no 4G
coverage from any operator. 
Page 81

Page 82

37 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Currently Argyll and Bute 0% 5G
coverage from all 4 operators,
however some operators have
started upgrading infrastructure to
incorporate 5G technology.
26% of Argyll and Bute has 5G
coverage from at least 1 operator. 
Supporting economic recovery and our communities 
During 2024/25, 183 tender/quick quote contract awards were placed with 203 successful suppliers, 38 of which were local suppliers (18.7%). From
the 53 awards that received a local bid, 37 tender/quick quote awards were awarded to a local supplier (69.8%). 31 Community Benefits have been
achieved through Contract Management, Contract Awards, and the Request List during the period from 1st April 2024 to 30th September 2024. 44
Community Benefits have been achieved through Contract Management, Contract Awards, and the Request List during the period from 1st October
2024 to 31st March 2025. 31 Community Benefits have been achieved through Contract Management, Contract Awards, and the Request List
during the period from 1st April 2024 to 30th September 2024.44 Community Benefits have been achieved through Contract Management, Contract
Awards and the Request List during the period from 1st October 2024 to 31st March 2025. 
Affordable social sector new builds
The 44 new affordable housing units completed by Registered Social Landlord (RSL) partners included 38 units for social rent and 6 properties for
New Supply Shared Equity (NSSE). 
In addition, Trust and West Highland Housing Association both acquired a property on the open market, whilst following transfer of stock to Fyne
Homes they completed the renovation works to eight affordable flats in Rothesay raising the annual completion total to 54. The challenges of
housing delivery are well-articulated in the work surrounding the Housing Emergency, particularly infrastructure constraints, construction skills
shortages, materials inflation, financial costs. 
Page 82

Page 83

38 
Business Support – case studies
Lochawe Hardwoods 
An Argyll-based business has achieved significant business growth, including a boost in turnover, after
accessing support from Business Gateway. 
Ian McAdam established Loch Awe Hardwoods in 2017 along the south shore of Loch Awe. The business
operates its own sawmill to supply a range of products to customers across the region. 
Ian’s business journey has been supported by a Business Gateway adviser, who linked him up with a digital
expert for a fully funded digital review to give guidance on growing Loch Awe Hardwoods’ digital presence to
reach new customers. Using the recommendations from the digital review, Ian plans to enhance the
company’s online presence even further, with an updated website and increased engagement on social
media platforms such as Facebook to better showcase Loch Awe Hardwoods’ products and services. 
Through Business Gateway, Ian has also accessed funding towards machinery from the UK Shared
Prosperity Fund, which has enabled the business to expand its product range, leading to an increased
customer base and improved turnover. 
Lomond Clinic, Helensburgh
A Helensburgh healthcare clinic has been given a boost after receiving digital support from Business Gateway in Argyll & Bute. The Lomond Clinic
supports locals through its range of healthcare services, which include medical and alternative treatment options encompassing health, beauty,
massage, physiotherapy, acupuncture, counselling, exercise and nutrition. 
Founder Jill Du Toit has been supporting Helensburgh residents since 2002, when she first launched her clinic with Business Gateway start-up
support. 
Page 83

Page 84

39 
Throughout her business journey, Jill has been supported by her local Business Gateway
team, who has provided expert guidance and advice as she has grown and developed The
Lomond Clinic. 
One-to-one support from Business Gateway has helped Jill to develop her business plan to
keep up with client demand. As part of recent efforts to improve The Lomond Clinic’s online
presence, Jill participated in a one-day digital review with Business Gateway, which gave her a
clear action plan on improvements to her website and social media. This has enabled Jill to
effectively reach and communicate with new customers, supporting The Lomond Clinic’s
continued development. Jill has also previously received advice on routes to funding and
accessed grants that have helped her to expand her team and secure medical diagnosis
equipment. 
Green Cup, Lochgilphead
A Ukrainian national who relocated to Scotland has brought a taste of her homeland to Lochgilphead by opening Green Cup, a coffee shop. Owner
Inna Arnautova offers specialist coffees and teas and accessed support from Business Gateway to help turn her passion for coffee into a thriving
business. 
Inna, her husband and their three children moved to the area from Ukraine in January 2023 amidst
Russia’s invasion of Ukraine. Keen to establish her roots in Argyll and Bute further, Inna had an idea
to launch her very own coffee shop and approached Business Gateway for support earlier this year.
She was soon connected with Donald Melville, a business adviser. 
Drawing on Donald’s expertise and resources, Inna successfully navigated the challenges of starting a
new venture in a foreign country. Inna benefitted from advice on taking on a new premises and routes
to funding. Through her local Business Gateway, Inna also benefited from a specialist adviser surgery
which taught her more about using social media channels such as Facebook and Instagram to market
her business to the right audience. 
Since its opening, Green Cup has proved popular with locals, and visitors alike, gaining positive
attention for its new and unique offer in the town. 
Inna told us “I’m incredibly grateful for the support I have received from Business Gateway. Starting a new business was a long haul but Donald
helped me along the way with any questions that I had. I’m looking forward to what’s to come in the future.”
Page 84

Page 85

40 
Donald Melville, Business Gateway adviser, said: “The success of Green Cup highlights the opportunities available to budding business owners
in Scotland, especially to those who bring diverse perspectives and new ideas to the local economy. Inna’s story serves as an inspiration to other
aspiring business owners looking to make their mark.” 
UK SHARED PROSPERITY FUND – Business Support Programme
Between June 2023 and March 2025 Business Gateway delivered a programme of additional support worth £516,521, fully funded through the UK
Government Shared Prosperity Fund:
• 87 small business development grants
• 16 training, trade fair, accreditation or digital grants 
• 75 start-up grants 
• 9 expert help (1 to 2 days support)
• 6 participants in intensive business support programme 
Of the 51 clients followed up to date, turnover has increased from a combined £10.7m at approval to £15.7m 12 months after the support (47%
increase). The number of employees has grown from 96 to 136 (41% increase). Across the 165 unique businesses approved for support, turnover is
predicted to grow by 32% to £32.8m and FTEs to grow by 47% to 468 within 12 months, so it is encouraging to see growth actually delivered from
the early beneficiaries. Impact data will be mature in May 2026. £200k has been secured for the UKSPF Transition phase, to continue grant and
expert help support in 2025. 
The Rural Growth Deal (RGD) 
The Rural Growth Deal (RGD) is a partnership approach to rural economic development which will deliver £50 million of investment equally funded
by the Scottish and UK Governments where it will best develop Argyll and Bute as an inclusive, sustainable, economically successful region and
driver for Scotland and the UK. Argyll and Bute Council, along with key stakeholders, will seek to contribute at least £20 million of match funding
throughout the 10-year programme to accelerate inclusive economic growth for the region. 
The RGD will provide a catalyst for inclusive economic growth that will retain and attract working-age people in the area. It will create opportunities
that can help to anchor the future prosperity of some of our key employment sectors. The programme comprises seven themes with key
interdependencies between many projects, bringing together partners from the public, private, and third sectors who are all committed to delivering
inclusive economic growth that benefits the whole region. The seven themes are: 
Page 85

Page 86

41 
• Tourism – Creating a World Class Visitor Destination
• Creating a Low Carbon Economy
• Rural Skills Accelerator Programme
• Housing to Attract Economic Growth
• Clyde Engineering and Innovation Cluster
• West Coast UAV Logistics and Training Hub
• Marine Aquaculture Programme 
Over the programme lifetime, it is estimated that the RGD will: 
• Generate over £5 million per year across its 10-year duration. This figure reflects the annual capital funding drawn down as part of the RGD,
with a total of £50 million being provided by the Scottish Government and UK Government over the full-term equating to approximately £5
million per annum. In addition to this financial investment, the deal will deliver wider economic benefits, which will be clearly mapped out as
individual projects progress.”
• Directly and indirectly create over 300 additional jobs associated with the economic benefits accrued from growth RGD projects. 
• Attract more than 70,000 tourists to the area. 
• Assist the transition towards a net zero economy. 
• Deliver skills and training opportunities to more than 6000 students / workers.
• Create an enhanced culture and leisure offering for local people to make Argyll and
Bute a more attractive place to live and work.
• Construct housing and worker accommodation in some of our remote and fragile
island communities as part of wider efforts to address our local housing emergency.
The Full Deal Agreement was signed in March 2025, at a ceremony in Rothesay, Isle of Bute signed by Cllr Jim Lynch on behalf of Argyll and Bute
Council, Kate Forbes MSP, Deputy First Minister for the Scottish Government and Ian Murray, Secretary of State for Scotland for the UK
Government. This event was a key milestone in RGD delivery and marked the beginning of the 10-year programme of investment across Argyll and
Bute. 
Page 86

Page 87

42 
Strategic Transportation
Strategic Transportation were successful in securing £100k from the SG Islands Infrastructure Fund to engage, supply and support 4 communities to
establish Digital Hubs on their Islands. The Islands were Coll (An Cridhe), Tiree (Development Trust Building), Iona (Community Hall) and Islay
(Kilarrow Hall). All 4 locations have an additional 3-year extended warranty and a direct line to the supplier for technical advice. 
Scottish Futures Trust 
Argyll, and Bute Council in partnership with Scottish Futures Trust were the first LA in Scotland to begin this full-scale area wide mobile coverage
mapping project. Several others have followed suit. The data that is being received provides an actual coverage rather the assumed coverage data
that was previously available. Data received through this ongoing project challenges the assumed data which is provided by the current 4 Mobile
Network Operator.
Page 87

Page 88

43 
One council: property income
We have generated over £956,000 from disposals and generated new annual revenue income of £40,500 driven by our strategy of divesting of
surplus property assets and generating income from our estate. 
Notable sales include: 
• Eaglesham House in Rothesay, Isle of Bute
• Housing development site at Burns Brae, Lochgilphead as part of housing emergency actions. 
Notable projects include:        
• The marketing of the Helensburgh Waterfront commercial site, with a preferred developer selected in August 2024, site investigations
completed, and utility connections secured.
• Oban Airport Business Park has seen the completion of the full business case, funding secured for the site infrastructure and first building,
Tier 1 contractor appointed, design team appointed, planning consent received, and site preparation works commenced. 
We are developing a strategic outline programme which will cover potential opportunities for the Council to develop several of its assets on a
commercial basis and will be delivered over a number of years, with the immediate focus being a new Business Park at Kilmory, Oban Airport
Business Park and commercial developments at Helensburgh’s waterfront. 
We secured ongoing commercial planning / building standards work from other local authorities. Not only is this important for us to provide a
balanced budget, but it also supports communities in these other Council areas.” 
Housing Services Partnership with Home Argyll
Housing service staff continue to work proactively with clients to offer support and identify solutions which avoid people needing to present as
homeless and require temporary accommodation. Similarly, staff are working hard to ensure Housing First Tenancies are successfully sustained,
and that Registered Social Landlords (RSLs) increase the number of offers they make to homeless clients. 
The number of tenancies created by RSLs annually has dropped and the number of offers made to homeless applicants is not reaching the agreed
levels creating a continuing need to rely on the sporadic use of unsuitable accommodation types for temporary accommodation. We continue to
engage constructively with RSLs & Scottish Government, COSLA and Highlands and Islands Regional Economic Partnership to focus on the issues
and delivery. 
Page 88

Page 89

44 
Corporate Outcome: We have an infrastructure that supports sustainable growth 
Number of indicators: 5 
Number on track: 3
Number no target / no data: 2 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage of waste
recycled, composted or
recovered
45.00% 48.30% 52.00% 58.20% 68.30% G
The figures provided represent a combined
total, with an annual rate of 68.3% for
recycling, composting and recovery. This
includes 41.5% from recycling and composting
and 26.8% from recovery. The target figure
will be revised once the landfill ban comes into
effect. 
Number of tonnes of
waste sent to landfill
(biodegradable)
21,500 18,772 18,165 17,406 14,716 G  
Since general waste from Helensburgh and
Lomond is no longer sent to landfill and is
instead processed through refuse derived fuel
and energy from waste methods, there has
been a significant reduction in the tonnage of
waste going to landfill.
Percentage of street
cleanliness 73.00% 79.00% 83.00% 84.00% 80.00% G  
The nationally recognised pass rate is 67%
The average achievement across all areas is
80%, with every team exceeding the target
set. 
Page 89

Page 90

45 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Percentage of roads in
need of maintenance as
defined by the annual
survey
No target No data 49.70% No data 50.77% No target
The latest Road Condition Index (RCI) for
2023-25 indicates a decline in network
condition. This figure is derived from the
updated two-year average of completed
survey data. Despite the recent dip, the RCI
still reflects a continued improvement since
the 2018 – 2020 period.
Carbon emissions
relating to Council
activities (Council
carbon footprint) tC02e
= tonnes of carbon
dioxide equivalent
Net Zero tC02e by 2045
No target 28,218 26,512 No data 27,515 No target
Both the Council and Scotland as a whole, are
committed to achieving Net Zero emissions by
2045. Since the baseline year, we have
achieved a 31% reduction in carbon
emissions. However, current progress – both
locally and nationally – falls short of the
trajectory needed to meet the interim target of
a 75% reduction by 2020 and the goal of Net
Zero by 2045. 
Council Carbon Footprint
Projects delivered by the Council that have contributed to the reduction in emissions include:
• LED Streetlight Replacement programme 
• Solar pv and LED lighting installations at Council assets
• Installation of low carbon heating systems (e.g. air source heat pumps 
Page 90

Page 91

46 
Flood Protection 
Campbeltown Flood Protection Scheme 
• The main works contract was certified Complete in May 2024,
• The Property Flood Resilience (PFR) element of the project is progressing through 2025 to 2026. 
As the scheme is largely complete, the only known remaining financial risk at this stage is that of the tender return costs of the Property Flood
Resilience works contract. Tender costs are expected to be available in the third quarter of 2025/26 and, if required, the adequacy of the available
£350k secured funding shall be reviewed at that stage. 
Marine infrastructure 
Oban Harbour 
For some time now there has been agreement that the Oban Bay area should be formally controlled for maritime safety, we took the step to assume
the responsibility for managing the area through an extension of its Statutory Harbour Authority area around North Pier. We are now at the end of an
extensive formal process and Transport Scotland continue to work on completing a submission and recommendation to the Cabinet Secretary for
Transport. 
Craignure Terminal 
Our Harbour Board Members met on 20 March and approved the completion of the Outline Business Case (OBC) and a continuation of the project
to the Final Business Case (FBC) pre-construction stage costing c.£3million. 
The Project Objectives include:
• Replace the existing terminal infrastructure, parts of which are in poor condition, deteriorating or have limited structural capacity.
• Increase berth capacity at the new ferry terminal to allow the full range of design vessels to be safely accommodated.
• Ensure vessels can reliably berth year-round at the new ferry terminal, including in challenging weather conditions and overnight, to
reduce weather-related cancellations and improve the winter timetable.
• Increase resilience of the new ferry terminal operations.
• Allow safe and efficient embarkation and disembarkation for both vehicles and foot passengers, including those with impaired mobility
and wheelchair users.
• Increase capacity of the new vehicle marshalling area in line with industry standards, addressing congestion on the A849.
• Provide a new terminal building with modern facilities, meeting staff and passenger requirements.
• Provide access for RNLI lifeboat, which is used for medical evacuations from Mull to mainland.
• Avoid and minimise disruption to the ferry service as far as practicable during the construction works. 
Page 91

Page 92

47 
This next stage will develop more accurate construction costing estimates as the design and methodology become more informed, with the current
construction phase projection cost estimated at c.£96 million. 
Campbeltown Old Quay
The Campbeltown Old Quay steel sheet piled walls, particularly wall ‘A,’ was showing
accelerated low water corrosion, had holes in the sheet piling, and was showing loss of infill
material behind the sheet piling wall. The pier is operational with the Royal National Lifeboats
Institute commercial /retail fishing vessels, leisure/private boats, and tourism.
The Marine Operations and Infrastructure Design
teams have been working together to facilitate the
replacement the old steel sheet piles. 
Infrastructure Design undertook outline designs
and costs of 8 Options from which a preferred
option to design and construct a deep-water berth
was selected. 
A contract was awarded in March 2024 and works
on site began in June 2024. Since then, of ground
anchors, backfilling between the old and new
sheet piles, 50 metres of cope installation. 
The remaining works are the completion of cope installation, installation of quay furniture (bollards, ladders, fenders), completion of dredging works,
site reinstatement. The completion date for the project is 04 October 2025. 
Page 92

Page 93

48 
Ferry services 
Iona Breakwater 
A contractor is now established on Iona to deliver a major infrastructure project that includes the construction of a breakwater, a new public toilet
block, and slipway enhancements. These works are designed to protect the island’s vital ferry service and prepare for the arrival of new CalMac
vessels on the route. The construction phase is expected to last approximately 17 months. 
This investment will significantly improve the reliability of ferry sailings during adverse weather conditions—an essential upgrade for a community
that depends on consistent access to medical care, education, waste collection, and business deliveries. The lack of resilient infrastructure in the
Sound of Iona has long impacted daily life for residents, with even a single day without ferry service disrupting essential services.
The breakwater will provide critical protection, enable more reliable and frequent crossings, and support broader economic development
opportunities on both sides of the Sound. 
In addition, the existing public toilet block on Iona is no longer fit for purpose. Frequently out of order and unable to meet demand—especially during
the busy tourist season—the current facility fails to serve both residents and visitors. A new, accessible, and compliant toilet block is being
constructed to provide reliable public amenities. The contract for the project was awarded in November 2024, with on-site works commencing in
February 2025. These improvements are the result of extensive local consultation and careful environmental planning, ensuring that the project
respects the unique character of this iconic location on Argyll’s coastline.
Fionnphort 
Fionnphort overnight berthing facility is progressing to follow on from the Iona works, for
c. 18 months construction. Preparation is progressing to ensure: 
• Overnight berth 
• Safe access for crew 
• Sheltered berthing 
• Charging and supply facilities 
• Traffic survey to enhance the passenger road user interface at the terminal 
An Environmental Impact Assessment (EIA) is in process including the socio-economic
assessment. 
Page 93

Page 94

49 
Port Askaig
Port Askaig has been made ready to receive the new Islay vessel being completed in Turkey and represents a collaboration between Argyll and
Bute Council and CMAL who carried out the waterside enabling works. Council works to enhance existing facilities, consisted of relining, signage,
parking allocation, CCTV and traffic access control installation. 
Campbeltown Harbour 
Campbeltown Harbour continues to be very busy commercially. Harbour improvement in the form of the replacement of ‘Wall A’ at the Old Quay is
well underway and due for completion in October this year. 
Business opportunities include using Campbeltown as a strategic supply hub for aquaculture and planned offshore wind projects are being explored.
The continuation of cruise visits as well as military traffic represent a real opportunity to develop the port and secure long-term work in and from
Campbeltown Harbour. 
Rothesay Quay 
Preparations continue for phase 3 of works, which will see a strengthening of the east roundhead and includes fendering upgrades. This work is
currently at the design stage and is planned for tender in 2025. 
Feolin 
We will be installing a passenger only access at Feolin, for those periods when the vehicular vessel is not available and the service would otherwise
be cancelled. Although these occasions are relatively rare, we have recognised the need for a replacement to the ladder access used at present. 
A plan for concrete steps between the existing dolphins following a more traditional design has been drawn up and approvals are now underway. 
Gigha and Tayinloan 
Planning is well underway to upgrade the marine infrastructure at Gigha and Tayinloan to accommodate new vessels for the CalMac route. Public
consultation has been carried out at both sites as part of the Environmental Impact Assessment process. Ground Investigation work has also been
completed at the locations, and this will help with refining the construction plans, methodology and costs. 
Page 94

Page 95

50 
Gigha Ferry Terminal
To facilitate the arrival of a new ferry as part of the Small Vessel Replacement Project (SVRP),
the Council’s Marine Operations and Infrastructure Design teams have been working to
upgrade the existing infrastructure at Gigha and Tayinloan. 
A consultant has been commissioned to produce an Environmental Impact Assessment (EIA),
design drawings, and tender documents. The designs include a new pier/breakwater at Gigha
to allow overnight berthing of the new vessel by the slipway, and an extension of the existing
breakwater at Tayinloan. 
A Ground Investigation was carried out in April 2025. This included boreholes, vibrocores, grab
samples, bathymetric surveys, and sub bottom profiling. The results of this investigation will
provide information to allow designs to progress and a Marine Directorate consent to be
secured for both construction and dredging. 
Argyll & Bute Council Ferry Services 
The first of our Ferry Stakeholder Forums held its initial meeting in June on Luing. Thanks to the enthusiasm of the local Community Council, it has
begun to shape the available resources to better fit the islands needs and to better understand the constraints the service works within. It is now our
intention to roll out this template and attend regular meetings for the remaining services for Jura, Lismore and Easdale and we look forward to
involving the local communities alongside us to get the most out of their service. 
Vessel Priority Strategy 
The lag in increasing ferry capacity through new vessels is limiting the benefit of cheaper travel costs and impeding mainland travel to islands.
New vessels and the associated marine infrastructure to accommodate them at our ports are both expensive and have lengthy lead times. It is
therefore important for us to not only have a long-term strategy for vessel replacement but also to look at the longer-term needs of the island
communities served by our ferries. A vessel strategy, which represents a realistic and Best Value approach to gain the most benefit from resources
as they become available is as follows:
1. On-site accommodation at Port Askaig. The present situation requires Officers and crew to be residents of Islay as well as suitably qualified.
Along with the market supplement and the 7-day rota, this will allow the recruitment of suitably certified crew required for resilience and new
vessel minimum manning levels.
Page 95

Page 96

51 
2. Concept design to ‘Keel Ready’ for a new Jura vessel to identify capacity levels; fuel type; crew size and infrastructure upgrade
requirements. This also allows for a more accurate assessment / estimate of build & certification costs.
3. Jura Ferry replacement and associated infrastructure at Feolin and Port Askaig.
4. Eilean Dhiura re-deployed to the Cuan / Luing route with associated slipway modifications on the route.
5. Easdale work boat replacement with landing craft type vessel.
The vessel strategy uses the available resources and maximises the return from investments on vessel life extension works. It gives a service
improvement in terms of redundancy and resilience while minimising the new build timescales. This will also allow time to assess future needs and
fixed link opportunities for each community. 
Council vehicle ferries
Major work during dry dock periods has now been completed to further extend the working lives of the Eilean Dhiura and the Belnahua. The work
continues each year as an investment in the resilience of the vessels as important links to the island communities they serve. Works included engine
replacement, extensive steel works, hydraulic and control systems as well as fire safety installations. 
Road Condition improvements
The 2024 Annual Status and Options Report sets out the benefits of continued investment in our road network and highlights the critical risk of
underinvestment.
Although our network has seen a welcome improvement in recent years, we would need to spend in the region of £11-£14million annually to
maintain a ‘standstill’ position, and significantly more to see continued improvements. Budget consultations and public feedback has shown the
importance of roads to our communities, but maintaining the required level of investment is likely to be challenging in future years given the
predicted decline in available capital funding. This brings with it significant engineering, economic, financial and reputational risks for the Council. 
We continue to deliver a range of different technical solutions that are designed to be proportionate for the use of the road and take into
consideration the island and rural geography of Argyll and Bute. 
Claoniag landslip
To facilitate the arrival of a new ferry as part of the Small Vessel Replacement Project (SVRP), the Council’s Marine Operations and Infrastructure
Design teams have been working to upgrade the existing infrastructure at Gigha and Tayinloan. A consultant has been commissioned to produce an
Environmental Impact Assessment (EIA), design drawings, and tender documents. The designs include a new pier/breakwater at Gigha to allow
overnight berthing of the new vessel by the slipway, and an extension of the existing breakwater at Tayinloan. 
Page 96

Page 97

52 
A ground investigation was carried in April 2025. This included
boreholes, vibrocores, grab samples, bathymetric surveys, and sub
bottom profiling. The results of this investigation will provide information
to allow designs to progress and a Marine Directorate consent to be
secured for both construction and dredging. 
Significant Work was carried out with SEPA and the owner of the
surrounding land, to enable improvement to a nearby old borrow pit site
using excavated material from the Works site. This helped to reduce
the impact on the environment and the roads network of transporting
large quantities of unsuitable (for engineering fill) excavated material
away from the site. Work outside the road corridor will take place during
2025 to complete aspects required by SEPA such as the topsoil and
seeding of the improved ex borrow pit area. 
Balliemore Bridge 
The original Balliemore Bridge was demolished following its partial collapse during the October 2023 severe weather event. The next critical stage in
replacing it included installing six precast, 15 metre long, concrete deck beams onto the reinforced concrete abutments. A 130 tonnes capacity crane
was required to consider the safe working radius and capacity of the lifting operations. Further work includes installing pre-cast wing walls and deck
reinforcement in preparation for the in-situ concrete deck pour. With the cooperation of Ardtaraig Estate a diversion road was put in place through a
field to the north west of Balliemore Bridge, which allowed a temporary bridge to be placed slightly upstream of the existing bridge and reopening of
the road. 
Page 97

Page 98

53 
Tigh Dearg Road in Kilcreggan. 
Civils works were completed as part of the flood alleviation scheme to
improve the surface water drainage, as well reducing sewerage
overflow into the River Clyde, at Tigh Dearg Road in Kilcreggan. 
This scheme involved de-coupling a 220m combined sewer which took
the surface water (rain runoff) and sewerage in one pipe which was
connected to the Scottish Water main sewer. This pipe lacked capacity
and was a contributor to the ongoing issues faced by locals. 
The improvements include a new much larger surface water pipe
(600mm in diameter) and a new sewer pipe connected only to
properties. Improvements have also been made in the road surfacing
which has been completely renewed – which provides a drastic visual
improvement to the area. 
To accomplish these works significant logistical and geophysical challenges had to be overcome – such as the high rock read that was present at
the site as well as the narrow nature of the street. This added complexity and time to the works but were managed and successfully overcome. 
Page 98

Page 99

54 
Corporate Outcome: Getting it right       
Number of indicators: 5 
Number on track: 2
Number no target / no data: 3 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
Increase the percentage
of all self-service and
automated contracts
70.00% 73.10% 75.00% 76.70%  79.30% G 
In FQ4 there were 190,503 interactions across
all Customer Engagement Team channels. Of
these 150,986 were digital self service, which
was 79.3%, so the target was comfortably
met.
Sickness absence days
per employee (non-
teacher)
No target 13.4 14.9 14.6 15.4 No target
Employee absence is showing an increasing
trend. This is a feature across the entire public
sector in Scotland and is concerning. The
main reasons for absence in this employee
group are Mental Health and back and neck
issues. Officers are working in partnership
with other councils to ensure we have the best
approach possible to analysing data,
managing absence and providing the most
appropriate support to staff.  Our older
workforce profile has an impact on our
absence but does not account for it all. We
continue to focus work with managers to
improve this. 
Sickness absence days
per teacher No target 5.6 7.2 9.0 9.6 No target
Absence amongst our teaching staff has
increased significantly since 2021-22. The
main reasons for absence in this employee
group are stress and infections. Workload and
pupil behaviour have been identified as
contributing factors to stress, both of which
are nationally recognised issues. Officers are
working in partnership with other councils to
Page 99

Page 100

55 
Corporate Outcome
Indicator Target 2021/22
Actual
2022/23
Actual
2023/24
Actual
2024/25
Actual Status Commentary
ensure we have the best approach possible to
analysing data, managing absence and
providing the most appropriate support
available to staff.  
Level of employee
satisfaction No target - - - 3.5 No target
Employees were asked to rate on a scale of 0-
5 stars their overall experience of working at
Argyll and Bute Council. The indicator is the
average score and will be monitored on an
annual basis.
Level of customer
satisfaction
92.5%
combined 92.00% 97.60% 96.95%  93.00% G 
FQ4 outcomes were: 97.7% Satisfied for
Customer Service Points (455 question
responses), 96.4% satisfaction for Contact
Centre (from 403 survey respondents), 100%
satisfaction with Registration Service from 85
survey respondents and 78% Web Visit
satisfaction, giving an overall satisfaction
score of 93%. 
Increasing the use of our website and self-service tools
In 2024/25 there were 638,863 customer interactions dealt with via all channels by our Customer Engagement Team (up from 661k in 23/24). Of
these 155,257 were handled in some way by Customer Service Agents (23%) and 528,606 were automated or self-service transactions (77.3%). 
This was increase of 18,000 on the previous year and so the % of digital transactions rose from 76% and thus the target was achieved. Website
page views increased by over 5%. 
Page 100

Page 101

56 
Improving our customer service
We have two main measures of customer satisfaction at a corporate level, that on satisfaction with the Customer Engagement Team (Contact
Centre, Service Points, Website, Registration) and that measured independently through the Local Government Benchmarking Framework. The
former showed high levels of success, averaging 96% for Contact Centre and Face to Face, 99% for the Registration Service and 98% for the
accessibility aspects of the website, where we now rank second highest amongst all Scottish Councils. 
It is important to note however that this reflects satisfaction with how the initial customer contacts are handled. Some services then have their own
measures for how the fulfilment of those requests are done by the back-office teams. The LGBF also measure this for some services and out of the
11 indicators four had improved, with overall satisfaction increasing from 55% in the base Year to 82% last year. 
Award Recognition for Outstanding Innovation and Service 
We’re proud to share that our teams have received prestigious recognition for their work in 2025. 
Our Housing Services Team has won the Innovation Award at this year’s Empty Homes Network (EHN)
Awards, for its project aimed at bringing properties back into use. 
Health and Social Care Partnership (HSCP) staff and were highly commended in Meeting the Challenge
Award and the Best Partnership Award, highlighting their creative and impactful approach to housing
solutions. 
Page 101

Page 102

57 
At the Scottish Local Authority Building Standards Scotland Awards,
our Building Standards Team received the Outstanding Service and
Commitment Award in recognition of their exceptional support to other
local authorities. 
Over the past nine years, the team has led commercialisation efforts on
behalf of eight partner councils, processing 3,409 building warrants for
projects with a combined works value exceeding £166 million. 
Supporting our Community Councils
We continue to support community councils both from a governance perspective and also regarding some of the more unique queries that come
directly to the Community Council Liaison Officer. We’ve seen questions about charitable status, VAT registration, issues with Service Level
Agreements which previous community councils had entered into and are supporting a community council who have a binding legal agreement
signed from the 1980s which they had no prior knowledge of as nobody involved in those contract negotiations remained on the community council.  
We successfully re-established a community council which was dormant since 2022 and commenced the necessary project planning required for our
periodic review of the Scheme for the Establishment of Community Councils to plan around key committee dates and national standards for
engagement on this piece of consultative work. 
Local Government elections and supporting new elected councillors
2024 saw a snap UK Parliamentary Election called on 4 July 2024 catching the whole electoral community by surprise. In normal circumstances we
would have commenced planning for the election at least 6 months prior to a scheduled election taking place. 
It is well documented that there are issues with the short timetable for this type of elections, and ability for specialist printers to prepare the number
of postal packs required given any person can now request a postal vote. These increasing numbers of advanced voters, ongoing issues with Royal
Mail, and the timing of the election being during Scottish school holidays caused huge pressure not only on the election team but also on wider
council resources. 
The holiday period meant we required to have new staff appointed on election contracts causing additional work for the election team and human
resources teams. Issues with delays in postal votes led to significant enquiries with our team and the contact centre staff. Bespoke arrangements
Page 102

Page 103

58 
were made to try to ensure that postal voters could collect replacement voting packs and complete these if they were going to be out of the area
when the main issue of postal votes were due to be delivered. This involved staff from the wider Legal and Regulatory team being asked to receipt
and ensure these were handled in accordance with the law. 
This election saw us taking on part of the Highland Council area within our constituency following the review of Parliamentary boundaries which
required us to work with multiple Electoral Registration Officers. It was also the first election requiring voter ID for polling station voting, and the first
election where postal votes could not be returned by hand without completion of a form. 
Committee Support and Member Services
In April 2024, a new Council Administration was formed. This required a number of additional special Council meetings and significant preparatory
work to pick up and process changes in appointments to internal committees, representation on statutory bodies and a wide range of other external
organisations at both strategic and area level, and the development and administration of a new committee and Council meetings programme. 
Alongside this sat the development and provision of dedicated support for elected members in a period of transition and for those adjusting to new
senior roles, again at strategic and area level. 
The team have also supported the Council’s election team in the administration of a by-election in July 2024 following the passing of the late Cllr
Robin Currie. Following the election, they provided induction support for the new councillor and have added to their learning and preparation for the
significant 2027 Scottish Local Government Elections administration and larger-scale councillor induction programme which will be required. 
The Elected Member Development Framework is ongoing throughout the term and includes work with individual councillors using Improvement
Service resources to identify personal development needs and potential resources. We have worked with our colleagues in Human Resources &
Organisational Development to facilitate access to the Council’s online learning platform for all Elected Members and a “Learning Community” has
been established. 
The team have also delivered another extensive Members Seminar programme over the course of the year. The programme was wide-ranging and
included topics such as renewables, tourism, islands strategy, data and technology and other focused sessions on key issues like the A83 Rest and
Be Thankful, exploring a Single Authority Model and the housing emergency. 
Building on the success of previous events and in response to member feedback, the team have supported additional externally delivered sessions
offered in partnership with the Local Government Information Unit, including seminars and workshops on advanced communication skills for elected
members, conflict resolution and mediation. 
Page 103

Page 104

59 
Following the previous year’s review of the councillors’ caseload management system and the establishment of the Member Zone self-service
system, team representatives now participate in the Member Zone Sounding Board which brings together stakeholders to look at how the system is
performing and where improvements may be possible. 
Looking after our financial assets 
The Council’s Counter Fraud Team works alongside Revenues and Benefits, Treasury, Creditors, Payroll and Corporate Debt Recovery to protect
the public purse and ensure strong financial stewardship. During 2024/25 the Counter Fraud Team contributed to the identification of £1.48m of
Council Tax that required rebilling due to fraud or error. The collection of these amounts is managed through the Council’s normal recovery
processes, led by the Corporate Debt Recovery Team. 
Key achievements across these services during the year include: 
• We collected £64.5 million in Council Tax during 2024/25, £1.2 million more than was budgeted.
• A positive External Audit report was received and presented to Council in December 2024, following completion of the 2023/24 Annual
Accounts audit.
• Financial monitoring packs and Budget Outlook were submitted to each Policy & Resources Committee.
• The average investment rate for 2024/25 was 5.07%, and the investments generated £2.549m of interest during the year.
• We processed 97.9% of invoices due within 30 days, exceeding the target of 95.5%.
• The external audit of the Council’s Non-Domestic Rates Income (NDRI) Notified Return of £45.415m for 2023/2024 was completed by the
statutory deadline with an unqualified audit certificate being received.
•  Following agreement of the 2024/25 pay awards for Teaching and Non-Teaching staff by October 2024, the Payroll Team processed the
uplifts and backdated payments during December 2024. 
Supporting attendance
The aims of the Councils Supporting Attendance policy is to support employee wellbeing and minimise sickness absence through fair, consistent,
and compassionate procedures. The policy promotes early intervention, open communication, and tailored support, including access to Occupational
Health, the Employee Assistance Programme, and wellbeing initiatives. It emphasises a preventative approach, values good attendance, and
ensures that all employees are treated individually and respectfully, in line with the Council’s core values. 
Increasing absence rates are a national trend across local government in Scotland. Since the introduction of our wellbeing strategy in 2019 the
council has improved its ranking in relation to sickness absence by 10 places. Therefore, while our absence rates are increasing and there will be
targeted work by the Human Resources & Organisational Development team to continue to tackle this, they are increasing at a slower rate than the
national picture. 
Page 104

Page 105

60 
The team are preparing to review the Supporting Attendance at Work procedures in the next 12 months to further enhance its effectiveness in
addressing high levels of staff absence and to strengthen support for employee wellbeing. 
Supporting Our People: Insights and Wellbeing Initiatives
We conducted an employee survey to gather feedback from staff across all services on their experiences working with the council. The survey
explored key areas such as leadership, workplace relationships, workload, wellbeing, and the overall working environment. Follow-up focus groups
were held to delve deeper into the findings. Analysis from these sessions has been completed and will be presented to the Senior Leadership Forum
in 2025. A comprehensive report, including recommendations and proposed actions, is currently being drafted. 
We continue to prioritise employee wellbeing. Our enhanced Employee Assistance Programme (EAP) now offers services previously unavailable
through our former provider, including physiotherapy and GP appointments. These additions are helping staff access essential support more quickly
than through traditional NHS routes. We are also reviewing our Mental Health First Aiders service to ensure it meets current needs. Once approved
the updated service will be promoted to all staff, aiming to provide timely support for mental health concerns and help reduce absence durations. 
Strategic Risk Register  
The Strategic Risk Register (SRR) details significant risks faced by the Council and the agreed approaches to manage them in the context of risk
mitigation. These can be crosscutting across all areas of the Council, although some are very specific to a service function and tend to be long-term
in nature. They each have specific interventions, subject to scrutiny at Strategic Committees, and are formally reviewed bi-annually, although the
SRR can be reviewed at any time should matters need to be placed on the register by the Strategic Management Team. A formal report is prepared
on an annual basis by the Chief Executive on risk management and is reported to the Audit and Scrutiny Committee. 
Further information can be found within the Audit and Scrutiny Committee meeting area on the council website. Audit and Scrutiny Committee -
Argyll and Bute Council (argyll-bute.gov.uk) 
Currently the SRR has 13 risks in total, 4 are red, 8 are amber and the remaining 1 is green. 
The red risks relate to: Population, External Infrastructure and Economic Decline, Waste Management, Service Delivery - Cyber Security, Lack of
Housing availability. 
The amber risks relate to: Condition and suitability of Infrastructure & Asset Base, Financial Sustainability, Governance and Leadership,
Engagement and Understanding the needs of the Community, Service Delivery, Health and Social Care Partnership, Cost of Living Crisis, Impact of
Climate Change 
The green risks relate to: Civil Contingency & Business continuity.
Page 105

Page 106

61 
Operational Risk Register  
Executive Director Kirsty Flanagan has eleven red risks which relate to: 1) Environmental Health - dealing with Public Health/infectious disease/food
related incidents and emergencies which have significant financial implications for the Council in terms of sampling/monitoring costs, employment of
experts, storage and disposal costs (food) etc; 2) Availability of Suitable Temporary Accommodation and Housing Support; 3) Road Maintenance
Culverts under 1.5m where extreme localised weather may result in loss of culvert or road loss; 4) Winter Maintenance in respect of adverse
weather conditions which require greater than budgeted number of gritting runs; 5) Waste Disposal in relation to the Biodegradable Municipal Waste
Ban (known as the BMW Ban); 6) Aging bridges and retaining wall assets which require a level of investment which is currently unaffordable, to
ensure a resilient road network; 7) Cyber Security in managing the Council’s assets to ensure they are available to users and meet the needs of the
business; 8) vulnerable roads near to the coastline; 9) vulnerability of access to and from Argyll and Bute during severe weather events and/or RTCs
where roads or routes are closed; 10) non-compliance with state subsidy regulations with regards to Council and externally funded projects dealt
with by the Transformation Projects Team; 11) Roads reconstruction capital funding will be significantly reduced in the coming financial year. 
Executive Director Douglas Hendry has nine red risk in relation to 1) Failure to maintain the school estate 2) Failure to ensure that Council offices,
depots and other properties  are improved 3) Increased utility costs 4) Resource – unavailability of Project Management, Professional Services
and/or Contractor resources 5) Finance – unavailability of internal capital funding 6) Compliance with conditions of all external funding 7) Capital
receipts targets are not met or revenue generating projects not delivered 8) Commercial Catering and Events not meeting financial targets and 9)
Challenges within HSCP in identifying budget savings within timescale due to work required to ensure service standards are being met. 
Operational Risk Registers are monitored on a quarterly basis at Departmental Management Team meetings and are managed accordingly. 
Service delivery challenges   
As well as our Strategic and Operational Risk Registers, we face a number of challenges that can impact on service delivery. This is a summary of
challenges we have encountered over the year and the actions we have identified and are putting in place to address them. 
Challenge - Allocation of the Scottish Welfare Fund
A key challenge was managing high demand within the limitations of the Scottish Government’s initial programme funding, which was insufficient to
meet local needs. 
Action 
In response to a projected overspend, the Council allocated an additional £250,000 early in the year to ensure continued support for
vulnerable residents. Through careful budget management and a focus on high and medium priority cases, we successfully reduced the
Council’s actual contribution to £90,000, maintaining a strong level of support throughout. Although a one-off additional funding allocation
Page 106

Page 107

62 
was issued by the Scottish Government in January, we did not need to use it in-year. However, the need for this additional allocation
highlighted the inadequacy of the original funding levels. This funding will be carried forward into 2025/26 to mitigate potential future
overspends. 
Challenge - Discretionary Housing Payment (DHP)
Key challenges include difficulty to identify Universal Credit (Housing Costs) claimants affected by the Bedroom Tax without direct Department of
Work and Pensions data and barriers reaching tenants in the private rented sector, where DHP take-up remains low. This resulted in DHP spend at
89.2% and below the 96% target. 
Action
Planned improvements for 2025/26 include closer collaboration with Registered Social Landlords within GDPR guidelines to proactively
identify and support vulnerable tenants and enhanced information-sharing and joint working with housing colleagues. We are planning for
greater promotion of DHP availability to private sector tenants. Introduction of a revised DHP policy, currently under consultation, to be
brought to Council in 2025/26 to improve strategic targeting and delivery. 
Challenge - Welfare Rights Advice in Health Partnerships Initiative
Through this new partnership and referral pathway we have been building links with GP practices. Due to rural locations, it was initially difficult to
identify GP practices where an adequate number of referrals could be achieved. 
Action
We have identified two additional surgeries where we will be offering this service to reach more clients. 
Challenge – Access to financial support for those that need it most
Due to the cost-of-living crisis and Welfare Reform changes some clients will continue to struggle financially even after intervention from advice
services. Some clients, particularly vulnerable individuals and families can be hard to reach and engage with and may have unmet needs. 
Action
We have planned increased community engagement with partners and community groups in 2024-25 to increase awareness of the Welfare
Rights Service and what we do. It also ensures clients and partners know how to access the service for support. 
Challenge - Achieving and sustaining positive destinations for young people
Young people across Argyll and Bute face several barriers to achieving and sustaining positive destinations. Remote rurality and transport links,
routinely involve dislocation from home to attend further and higher education establishments. Additionally, post Covid-19, a higher proportion of
young people are finding engaging with full time education or employment challenging. The requirement to develop young people's confidence,
Page 107

Page 108

63 
resilience and agency is as important as ensuring they are developing the skills to engage with Argyll and Bute's local economy and skills gaps and
the national employment landscape. 
Action
Education, Developing the Young Workforce and partners are working to identify key areas of future employment - e.g. tourism, hospitality,
renewables, construction, social care, aquaculture and inform and facilitate young people's engagement with these industries. 
Challenge - Impact of COVID on young children's speech, language and communication development
Impact of COVID lockdowns on young children's speech, language and communication development continues to be mirrored within our own data
with reports that children present in greater numbers with underdeveloped speech and reduced vocabulary than in previous years. In addition, the
number of children with underdeveloped communication and emotional regulation difficulties appear to have increased. Difficulties recruiting HSCP
allied health professionals, presents an increasing challenge for ELC staff in supporting children’s development, and for us to meet developmental
milestone targets across our authority. 
Action
We are working with health and allied health colleagues, nationally and locally, to support the development of early language and literacy
through targeted block model interventions which allows for deeper focus in the areas where it is required. 
Challenge – Modern apprenticeships with Argyll and Bute Council 
Opportunities for Modern Apprenticeships has remained consistent however there is a need to create more and varied apprenticeships and ensure
we can offer the best possible support for young people in the workplace. 
Action 
In 2024/25 we published our Growing Our Framework which outlines the organisation’s ongoing commitment to attracting the workforce of
the future and will be taking forward further activities to understand and address barriers to modern apprenticeships. 
Challenge – website customer satisfaction
Website satisfaction measures were difficult to collate and review as the tools to do this were no longer compatible with the new website. 
Action 
The web team has now fully re-engineered these to follow Govmetric principles, and we now have improved customer data to report on for
2025/26.
Page 108

Page 109

64 
Consultations – we asked, you said, we did
We want to ensure that proposed developments are what our citizens and communities want. To help us obtain your views we post our consultations
on our website. The following link will take you to the ‘closed’ consultations which relate to this reporting period. Consultation Results | Argyll and
Bute Council (argyll-bute.gov.uk)
Page 109

Page 110

This page is intentionally left blank

Page 111

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE                                                       
FINANCIAL SERVICES       16 DECEMBER 2025 
TREASURY MANAGEMENT STRATEGY AND ANNUAL INVESTMENT STRATEGY
MID-YEAR REVIEW 2025-26 
1.0 EXECUTIVE SUMMARY 
1.1 The Local Government in Scotland Act 2003 requires the council to have
regard to the CIPFA Code of Practice in Treasury Management (revised 2021),
the Code.  Key reporting requirements in this respect include an annual
Treasury Management Strategy Statement, including the Annual Investment
Strategy; a Mid-year Review Report; and an Annual Report. 
1.2  This mid-year report, prepared in compliance with the Code, covers the
following:
• An economic and interest rate update;
• A review of the approved Treasury Management Strategy and Annual
Investment Strategy;
• An update on the capital position and Prudential Indicators;
• An update on borrowing and investment activities; and
• Compliance with Treasury and Prudential Limits. 
1.3 The reports key highlights comprise the following: 
a) All borrowing and investment activity during the period 1 April to 30
September 2025 has been undertaken in accordance with the approved
2025-26 Treasury Management Strategy and Annual Investment
Strategy and the authority has operated within the treasury and
prudential limits set out therein; 
b) During the year to 30 September, the authority has continued to
maintain an under-borrowed position.  Whilst an element of new PWLB
borrowing has been undertaken during the year to date, providing a
degree of budget certainty, the significant level of internal reserve fund
balances has provided an opportunity to largely defer new external
borrowing, whilst also minimising exposure to investment risk.  This
borrowing strategy will require to be regularly reviewed to achieve
optimum value and minimise risk exposure in the longer term; 
Page 111 Agenda Item 8

Page 112

c) New PWLB borrowing of £20.000m has been undertaken in the year to
date, providing an element of certainty in respect of the underlying
borrowing requirement.  PWLB loan principal of £0.840m has also been
repaid during the year to date in respect of a 10-year loan taken on an
Equal Instalments of Principal (EIP) basis; 
d) The limit of investments has reflected the level of available reserve
balances, together with provision for managing the authority’s day to day
cash flow requirements.  The average rate of return on these
investments in the year to 30 September was 4.23%, compared to an
average benchmark overnight SONIA rate of 4.19% over this period; 
e) As at 30 September 2025, the council’s loan debt (excluding other long-
term liabilities) totalled £148.968m, while treasury investments totalled
£67.579m; and   
f) Since approval of the 2025-26 Treasury Management Strategy in
February 2025, capital planning assumptions have been updated and a
new accounting standard, IFRS 16 in respect of accounting for leases
and lease type arrangements.has been adopted.  As such, it has been
necessary to revise the Prudential Indicators set out within the approved
strategy. 
1.4 The Audit and Scrutiny Committee is asked to recommend that Council: 
• Note the report, and the treasury management activity undertaken over
the period 1 April to 30 September 2025; and,
• Approve the revised 2025-26 Prudential Indicators, as set out within
paragraph 5.2.3 of the report. 
Page 112

Page 113

ARGYLL AND BUTE COUNCIL      AUDIT AND SCRUTINY COMMITTEE 
FINANCIAL SERVICES         16 DECEMBER 2025 
TREASURY MANAGEMENT STRATEGY AND ANNUAL INVESTMENT STRATEGY
MID-YEAR REVIEW 2025/26 
2.0 BACKGROUND 
2.1 The authority operates a balanced revenue budget, which broadly means cash
raised during the year will meet its cash expenditure.  Part of the treasury
management operations ensure this cash flow is adequately planned, with
surplus monies being invested in low-risk counterparties, providing adequate
liquidity initially before considering optimising investment return.
2.2 The second main function of the treasury management service is the funding of
the authority’s capital investment plans.  These capital plans provide a guide to
the borrowing need of the authority, essentially the longer-term cash flow
planning to ensure the authority can meet is capital spending obligations.  This
management of longer-term cash may involve arranging long or short-term
loans, or using longer-term cash flow surpluses and, on occasion, existing debt
may be restructured to meet authority risk or savings objectives.
2.3 The Chartered Institute of Public Finance and Accountancy is currently
consulting local authorities in respect of potential changes to the Treasury
Management and Prudential Codes of Practice.  At this point, the key focus
appears to be in respect of non-treasury investment.  However, officers will
provide an update on any material developments or changes in due course.   
2.4 The adoption of a new accounting standard, IFRS 16 in respect of accounting
for leases, applicable from 1 April 2025, has impacted the assets and liabilities
recognised within the council’s balance sheet.  In addition, an element of
services revenue expenditure now requires to be accounted for as financing
costs.  As anticipated, the annual accounts for the year ending 31 March 2025
have been restated on this basis, as part of the audit process.  It is worth noting
that there has been no impact on the General Fund balance as at 31 March
2025 as a result of these changes.
Page 113

Page 114

2.5 Leases and lease-type arrangements, previously accounted for as revenue
activity are generally now recognised on the balance sheet as ‘Right of Use
Assets’, with associated long-term liabilities in respect lease payments, payable
over future years.  This is essentially to recognise the long-term obligations
associated with these types of arrangements.  Over two hundred assets, held
under lease-type arrangements, including fleet and property are now
represented on the council’s balance sheet.  The council’s PPP type
arrangements in respect of the school estate are also accounted for on an IFRS
16 basis. 
2.6 In addition to any required updates to the Prudential Indicators, set out within the
approved 2025-26 Treasury Management Strategy, as a result of updated
capital plan assumptions, updates will be necessary in respect of IFRS 16
accounting changes. 
3.0 INTRODUCTION
3.1 The Local Government in Scotland Act 2003, and supporting regulations,
requires the authority to have regard to the CIPFA Code of Practice on
Treasury Management (revised 2021), the Code.  The Code requires full
Council to receive an annual Treasury Management Strategy Statement,
including the Annual Investment Strategy, for the year ahead; a Mid-year
Review Report; and an Annual Report following the year end. 
3.2 The regulatory environment requires the authority to delegate responsibility
for the monitoring and scrutiny of treasury management activities, strategy
and policies to a specific named body.  For this authority, the appropriate
delegation body is the Audit and Scrutiny Committee.  Treasury management
training was delivered to members of the committee during October 2024. 
There is also a Treasury Management Toolkit, available to members, to
support this scrutiny role.
3.3 Prudential and Treasury Indicators are designed to ensure capital investment
plans are affordable, prudent and sustainable.  There are clear linkages
between the council’s capital planning and treasury management strategy,
with the financing costs arising from capital investment plans considered as
part of the overall revenue Budget Outlook.
3.4 This mid-year report, prepared in compliance with the Code, covers the
following: 
• An economic and interest rate update;
• A review of the approved Treasury Management Strategy and Annual
Investment Strategy;
• An update on the capital position and Prudential Indicators;
• An update on borrowing and investment activities; and
• Compliance with Treasury and Prudential Limits. 
Page 114

Page 115

4.0 RECOMMENDATIONS 
4.1 The Audit and Scrutiny Committee is asked to recommend that Council:
• Note the report, and the treasury management activity undertaken over
the period 1 April to 30 September 2025; and
• Approve the revised 2025-26 Prudential Indicators, as set out within
paragraph 5.2.3 of the report. 
5.0 DETAIL 
5.1 Economic and Interest Rate Update  
5.1.1 The authority’s appointed treasury advisors, MUFG Corporate Markets, provide
updates on the economic position and interest rate forecasts.  This is provided
as Appendix 1.  The first half of 2025-26 saw:
• An increase of 0.3% in GDP during the first quarter, followed by the economy
flatlining in July, with higher taxes for businesses restraining growth.
• A fall in the 3 month / year on year rate of average earnings growth, excluding
bonuses, from 5.5% to 4.8% in July.
• The Consumer Price Index (CPI) inflation ebbing and flowing but ending at 3.8%
by September.
• An easing of core inflation (excludes volatiles components such as food and
energy) to 3.6%. 
• Bank of England cut interest rates from 4.50% to 4.25% in May, and then to 4%
in August.
• The 10-year gilt yield fluctuate between 4.4% and 4.8%, ending at 4.70% as at
the end of September.
5.1.2 The 2025-26 strategy included market assumptions for long-term PWLB
interest rates and short-term interest rates (Bank Rate) during 2025-26. 
These are compared to the latest forecast in the following table:
31 March 2026 Interest Rate Forecast 
Original % Current %
Bank Rate 3.75% 3.75%  
5 Year PWLB 4.50% 4.50%
10 Year PWLB 4.70% 5.00%
25 Year PWLB 5.10% 5.70%
50 Year PWLB 4.90% 5.40%
Page 115

Page 116

5.1.3 The latest long-term PWLB and short-term interest rate forecasts, provided by
MUFG Corporate Markets, are outlined below.  This sets out a view that
medium and long-dated PWLB borrowing rates will fall back over the next
couple of years.  Bank Rate (short-term borrowing) is expected to continue to
fall steadily throughout 2026, before reaching 3.25% towards the end of 2027. 
(a) Long-term PWLB borrowing rates: 
2025-26 2026-27 2027-28
PWLB Rates
Sept 2025
%
Low
%
High
%
Low
%
High
%
5 year 4.80 4.3 4.4 4.2 4.2
10 year 5.30 4.8 4.9 4.7 4.7
25 year 6.10 5.5 5.7 5.3 5.4
50 year 5.80 5.3 5.4 5.1 5.2         
(Based on the PWLB Certainty Rate, the standard rate minus 20 bps) 
(b) Short-term borrowing rates: 
2025-26 2026-27 2027-28 
Sept 2025
%
Low
%
High
%
Low
%
High
%
Bank Rate 4.00 3.50 3.75 3.25 3.50 
5.2 Treasury Management Strategy Review
5.2.1 The 2025-26 Treasury Management Strategy was approved by Council on 27
February 2025.  The underlying strategy remains fit for purpose in terms of the
updated economic position and approved changes to the Capital Plan. 
However, the 2025-26 Prudential Indicators set out within approved strategy
require to be revised to reflect updates to capital planning assumptions and
accounting changes in respect of compliance with the new accounting
standard, IFRS 16 Leases. 
5.2.2 The council’s financial statements have been restated to reflect adoption of the
new accounting standard, IFRS 16 in respect of leases.  Whilst there is no impact
on the council’s General Fund position, the required accounting changes impact
the council’s Capital Financing Requirement and Debt calculations.  In addition,
an element of revenue expenditure previously accounted for as service
expenditure, now requires to be accounted for as financing costs.  This impacts
the calculated Ratio of Financing Costs to Net Revenue Stream indicator. 
Page 116

Page 117

5.2.3 The proposed changes to the 2025-26 Prudential Indicators are summarised in
the following table, while more detailed supporting information is provided within
section 5.3 of the report. 
Prudential Indicator Original Revised 
£m £m
Gross Capital Expenditure 71 76
Closing CFR 394 396
Operational Boundary for External Debt 394 396
Authorised Limit for External Debt 402 404
Gross Debt  321 289
Gross Debt less CFR -73 -107
Ratio of Financing Costs to Net Revenue Stream 4.9% 7.4%  
5.3 Capital Position and Prudential Indicators Update
5.3.1 This section of the report is structured to update:
• The authority’s capital expenditure plans;
• How these plans are being financed;
• The impact of the changes in the capital expenditure plans on the prudential
indicators and the underlying need to borrow; and
• Compliance with the limits in place for borrowing activity. 
Prudential Indicator for Capital Expenditure
5.3.2 The 2025-26 strategy estimated gross capital expenditure of £71.006m for the
year.  This position is monitored on an ongoing basis, as part of the Capital
Plan Monitoring, regularly reported to the Policy and Resources Committee.
The 2025-26 estimated gross capital expenditure has now been revised to
£76.308m, reflecting updated assumptions contained within the council’s
current Capital plan.  This increase mainly relates to additional expenditure
approvals, and the reprofiling of expenditure from 2024-25 into 2025-26 and
from 2025-26 into future years.  It is also worth noting that the Capital Plan
does not include assets acquired under lease or lease type arrangements.   
Financing of the Capital Plan
5.3.3 The 2025-26 strategy estimated gross capital expenditure of £71.006m for the
year, as outlined above, with £45.199m to be financed from new borrowing.  In
addition to capital expenditure updates, there have also been changes to the
capital income assumptions within the council’s current Capital Plan.  These
changes potentially impact the level of capital expenditure to be financed from
Page 117

Page 118

borrowing.  Any re-profiling of project expenditure from/to 2025-26 to/from future
years, between now and the end of the year, would also impact the underlying
borrowing requirement.  However, the Section 95 Officer will take a strategic
approach to manage the impact of capital investment on the council’s revenue
budget, including the use of earmarked reserves, to ensure that capital
investment is affordable, prudent and sustainable.  
5.3.4 The table below outlines the expected financing arrangements for the updated
capital expenditure plans.  The net financing need or borrowing element
increases the council’s underlying indebtedness (Capital Financing
Requirement), although this will be reduced in part by revenue charges for the
repayment of debt (principal repayment).  This direct borrowing need may also
be supplemented by the replacement of maturing debt and to meet other
treasury cashflow requirements.  
Capital Expenditure and Financing
Estimates 2025-26
Original Revised
£m £m
Gross Capital Expenditure 71.006 76.308
Finance by:  
Specific Project Income 8.302 12.263
General Capital Grant 11.178 11.178
Asset Sales 0.750 1.000
Earmarked Reserves / Revenue 5.577 6.668
Total Financing 25.807 31.109
Net Financing (Borrowing) Need 45.199 45.199 
5.3.5 It is worth noting that assets acquired through lease or lease-type arrangements
are not financed through direct borrowing.  These arrangements result in the
recognition of assets; and corresponding lease liabilities, repayable over the
term of the lease. 
Changes to the Prudential Indicators for the Capital Financing
Requirement (CFR), and the Operational Boundary for External Debt
5.3.6  The council’s actual CFR as at 31 March 2025 has been restated from £349m
(pre-audit) to £360m (post anticipated audit changes) to reflect IFRS 16
accounting requirements.  In approving its strategy for 2025-26, Council noted
an estimated CFR of £360m as at 31 March 2025 and £394m as at 31 March
2026 (£34m movement).  The actual CFR as at 31 March 2025 is unchanged
at £360m, while the current projected CFR as at 31 March 2026 has been
revised to £396m (£36m movement).  The estimated increased movement of
£2m in the CFR during the year largely reflects a decrease from the originally
Page 118

Page 119

estimated repayment of Other Long-term Liabilities.  The table below shows
the CFR, together with the expected debt position over the period, which is
termed the Operational Boundary.
2025-26 CFR and Operational Boundary
for External Debt
Original Revised
£m £m
Opening Capital Financing Requirement 360 360
Closing Capital Financing Requirement 394 396
Net Movement in CFR 34 36 
Prudential Indicator – the Operational Boundary for External Debt
Borrowing 293 282
Other Long-term Liabilities* 101 114
Total Debt (year-end position) 394 396 
* Includes on balance sheet PPP and lease arrangements recognised under IFRS 16. 
Limits to Borrowing Activity
5.3.7 The first key control over the treasury activity is a Prudential Indicator to ensure
that, over the medium term, net borrowing (borrowings less investments) will
only be for a capital purpose.  Gross external borrowing should not, except in
the short term, exceed the total of CFR in the preceding year plus the estimates
of any additional CFR for 2025-26 and the next two financial years.
2025-26 Estimated Debt against CFR Original Revised
£m £m
Borrowing 220 187
Other Long-term Liabilities* 101 102
Total Debt 321 289 
CFR (year-end position) 394 396
Under / (Over) Borrowing 73 107 
* Includes on balance sheet PPP and lease arrangements recognised under IFRS 16.
5.3.8 The level of ‘under-borrowing’ outlined in the table above reflects the level of
internal borrowing, as described in paragraph 5.4.5.
5.3.9 A further Prudential Indicator controls the overall level of borrowing.  This is the
Authorised Limit, representing the limit, beyond which borrowing is prohibited
and needs to be set and revised by Members.  It is the expected maximum
Page 119

Page 120

borrowing need with some headroom for short-term day to day cash flow
management requirements.  
2025-26 Authorised Limit for
External Debt
Original Revised
£m £m
Borrowing 298 287
Other Long-term Liabilities* 104 117
Total Debt 402 404         
* Includes on balance sheet PPP and lease arrangements recognised under IFRS 16.
5.4 Borrowing Activity
5.4.1 PWLB loan principal of £0.840m has been repaid in the year to 30 September
2025, with a further £0.840m due to be repaid by 31 March 2026.  These
repayments of principal relate to a 10-year PWLB loan (original principal £21m),
which was taken on a fixed Equal Instalments of Principal (EIP) basis. All other
PWLB loans will be repayable on maturity.
5.4.2 The authority has one outstanding market or LOBO loan for £5.255m, at an
interest rate of 4.75%, maturing 2048, with call dates every 6 months.  This loan
was not recalled at the 22 June 2025 call date.  There is potential for this loan to
be recalled before the end of the financial year, at the next call date of 22
December 2025.
5.4.3 New PWLB long-term borrowing of £20m has been undertaken during the year
to 30 September 2025, providing an element of certainty in respect of funding
the underlying borrowing requirement for capital.  With long-term borrowing
rates relatively high but forecast to steadily fall over the next few years, new
borrowing has been taken on a relatively short-term basis.  Details of the new
loan taken out during the period are as follows:
Lender Principal Type Interest Rate Maturity
PWLB £20.000m Fixed Rate
Maturity
4.69% 07/04/2028 
5.4.4 Any PWLB or LOBO loans maturing during the year will ultimately require
replacement borrowing to maintain the council’s cashflow position.  In addition,
the council will continue to actively monitor potential restructuring opportunities,
in order to generate savings in interest costs or to improve the balance of the
loan debt maturity profile.
5.4.5 While there is an underlying need to borrow in respect of the Capital Financing
Requirement and the replacement of maturing debt, this may involve arranging
short or long-term loans from external PWLB or market sources; or borrowing
from internal reserve fund balances on a temporary basis, dependent on fund
balance forecasts.  Although an element of new external borrowing has been
undertaken during the year to 30 September 2025, the significant level of
Page 120

Page 121

internal reserve fund balances held by the council has provided an opportunity
to largely defer new external borrowing.  The table at paragraph 5.3.7 shows the
extent to which the council has utilised internal funds in lieu of borrowing.  This is
a prudent and cost-effective approach in the current economic climate but will
require ongoing monitoring and review. 
5.4.6 As at 30 September 2025, the council’s external loan debt totalled £148.968m,
as summarised in the table below.
External Debt 
as at 30 September 2025
Amount
£000
Annual Average
Interest Rate
Share of
Total Debt
Public Works Loans Board 143,357 4.50% 96.23%
Market Loans (LOBO) 5,255 4.75% 3.53%
Temporary Loans* 356 3.56% 0.24%
Total Debt 148,968 4.50% 100.00% 
*This represents short-term borrowing from various institutions.
5.5 Debt Rescheduling
5.5.1 Debt repayment and rescheduling opportunities are considered on an ongoing
basis, either to deliver savings in interest costs or to improve the debt maturity
profile, at minimum risk.  No debt repayments or rescheduling has been
undertaken in the current financial year to 30 September 2025, however, this will
continue to be monitored in the context of changing market conditions.
5.6 Annual Investment Strategy Review
5.6.1 In accordance with the CIPFA Treasury Management Code of Practice, the
council’s approved Annual Investment Strategy sets out the council’s investment
priorities as being:
• Security of capital
• Liquidity
• Yield 
5.6.2 The authority will aim to achieve the optimum return (yield) on its investments,
commensurate with proper levels of security and liquidity, and the council’s risk
appetite.  The risk appetite of the council is low, prioritising security and liquidity.
In the current economic climate, it is considered appropriate to keep investments
short term, to cover cash flow needs, but also to seek out value available in
periods of up to 12 months with high credit quality financial institutions, using the
MUFG Corporate Markets suggested creditworthiness approach, including a
minimum sovereign credit rating and Credit Default Swap (CDS) overlay
information.
5.6.3 As outlined within the approved Annual Investment Strategy 2025-26,
investment rates were forecast to fall during the first half of 2025-26, which they
did, and expectations are that gradual but continuing reductions will follow over
the next two financial years. 
Page 121

Page 122

Creditworthiness
5.6.4 The UK’s sovereign rating has proven robust through the first half of 2025-26.
The UK Government is expected to outline in detail its fiscal proposals in the
budget scheduled for 26 November 2025. 
Investment Counterparty Criteria
5.6.5 The current investment counterparty selection criteria, approved within the
Strategy, continues to meet the requirements of the treasury management
function. 
5.7 Investment Activity
5.7.1 The council’s Section 95 Officer confirms that the principles of the Annual
Investment Strategy have been adhered to.  During the year to 30 September
2025, all investments have been made in line with the approved limits for
specific investment instruments, and in accordance with the creditworthiness
approach.  
5.7.2 Details of the council’s investments held as at 30 September 2025, totalling
£67.579m, are summarised in the table below. 
Counterparty Maturity Amount
£000
Intere
st
Rate
%
Clydesdale Bank  Instant Access 379 3.90%
Fixed Deposits:     
ANZ Banking Group 10/11/2025 15,000 4.36%   
Al Rayan Bank 20/11/2025 5,000 4.40%   
DBS Bank 26/11/2025 5,000 4.13%   
Qatar National Bank 27/11/2025 5,000 4.29%
Local Authority to Local Authority 16/02/2026 5,000 4.20%
Money Market Funds:  
Federated Call Account 15,000 4.09%
LGIM Stirling Liquidity fund Call Account 15,000 4.11%
Aviva Call Account 2,200 4.10%
Total   67,579 4.20% 
5.7.3 The weighted average rate of return on investments held during the year to 30
September 2025 was 4.23%, with an average investment duration of 17 days. 
This compares to an average benchmark SONIA overnight rate of 4.19% over
the first half of the year, while Bank Rate was lowered during the period from
4.50% to 4.25% in May, and then to 4.00% in August.   
Page 122

Page 123

5.7.4 The council is part of an Investment Benchmarking group, a service provided by
MUFG Corporate Markets, which provides monthly Investment Analysis reports.
This analysis compares the authority’s investment holdings and returns to the
other Scottish public bodies in the group, and to Scottish Unitary Authorities as a
whole.  When making investment decisions, the council prioritises security and
liquidity in that order but, when the investment options available are well within
the parameters set out in the council’s Investment Strategy, officers will also
seek to maximise yield.  The council’s investments continue to perform well and
above the benchmarks provided.
5.8 Compliance with Treasury and Prudential Limits
5.8.1 It is a statutory duty for the authority to determine and keep under review the
affordable capital expenditure limits.  In the current financial year to 30
September 2025, the authority has operated within the Treasury and Prudential
Limits set out within the approved Treasury Management Strategy for 2025-26.
All treasury management operations have also been conducted in full
compliance with the authority's Treasury Management Practices.
5.8.2 It has been necessary to revise the Prudential Indicators to reflect updated
capital planning assumptions and the adoption of IFRS 16 in respect of
accounting for leases and lease type arrangements.  The Section 95 Officer
confirms that no difficulties are envisaged in complying with the Treasury and
Prudential Limits, as revised by this report, for the remainder of the financial
year.   
6.0 CONCLUSION 
6.1 All borrowing and investment activity during the period 1 April to 30 September
2025 has been undertaken in accordance with the approved 2025-26 Treasury
Management Strategy and Annual Investment Strategy and the authority has
operated within the treasury and prudential limits set out therein.
6.2 During the year to 30 September, the authority has continued to maintain an
under-borrowed position.  Whilst an element of new PWLB borrowing has been
undertaken during the year to date, providing a degree of budget certainty, the
significant level of internal reserve fund balances has provided an opportunity to
largely defer new external borrowing, whilst also minimising exposure to
investment risk.  This borrowing strategy will require to be regularly reviewed to
achieve optimum value and minimise risk exposure in the longer term.
6.3 Since approval of the 2025-26 Treasury Management Strategy in February
2025, capital planning assumptions have been updated and a new accounting
standard, IFRS 16 in respect of accounting for leases has been adopted.  As
such, it has been necessary to revise the Prudential Indicators set out within the
approved strategy. 
Page 123

Page 124

7.0 IMPLICATIONS
7.1 Policy - None
7.2 Financial – Provides an update on 2025-26 treasury management activity and
the approved strategy
7.3  Legal  - None
7.4  HR - None
7.5 Customer Service
7.6 Risk – Provides an overview of treasury management and investment risk
7.7 Climate Change  - None
7.8  Fairer Scotland Duty - None
7.9 Equalities - protected characteristics - None
7.10 Consumer Duty - None
7.11 Island Communities – None 
7.12 Children’s Rights and Wellbeing  - None 
Kirsty Flanagan
Executive Director/Section 95 Officer
21 November 2025 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services                                                 
For further information contact: 
Carolyn Earl, Head of Financial Services (Consultant)
Carolyn.Earl@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – MUFG Economic and Interest Rate Update 
Page 124

Page 125

APPENDIX 1
Economics and Interest Rates 
Economics Update 
• The first half of 2025/26 saw: 
- A 0.3% pick up in GDP for the period April to June 2025. More recently, the
economy flatlined in July, with higher taxes for businesses restraining
growth.
- The 3m/yy rate of average earnings growth excluding bonuses has fallen
from 5.5% to 4.8% in July.
- CPI inflation has ebbed and flowed but finished September at 3.8%, whilst
core inflation eased to 3.6%.
- The Bank of England cut interest rates from 4.50% to 4.25% in May, and
then to 4% in August.
-     The 10-year gilt yield fluctuated between 4.4% and 4.8%, ending the half
year at 4.70%.
• From a GDP perspective, the financial year got off to a bumpy start with the
0.3% m/m fall in real GDP in April as front-running of US tariffs in Q1 (when
GDP grew 0.7% on the quarter) weighed on activity. Despite the underlying
reasons for the drop, it was still the first fall since October 2024 and the largest
fall since October 2023. However, the economy surprised to the upside in May
and June so that quarterly growth ended up 0.3% q/q. Nonetheless, the 0.0%
m/m change in real GDP in July will have caused some concern, with the hikes
in taxes for businesses that took place in April this year undoubtedly playing a
part in restraining growth. The weak overseas environment is also likely to have
contributed to the 1.3% m/m fall in manufacturing output in July. That was the
second large fall in three months and left the 3m/3m rate at a 20-month low of
-1.1%. The 0.1% m/m rise in services output kept its 3m/3m rate at 0.4%,
supported by stronger output in the health and arts/entertainment sectors.
Looking ahead, ongoing speculation about further tax rises in the Autumn
Budget on 26 November will remain a drag on GDP growth for a while yet. GDP
growth for 2025 is forecast by Capital Economics to be 1.3%. 
• Sticking with future economic sentiment, the composite Purchasing Manager
Index for the UK fell from 53.5 in August to 51.0 in September. The decline was
mostly driven by a fall in the services PMI, which declined from 54.2 to 51.9. The
manufacturing PMI output balance also fell, from 49.3 to 45.4. That was due to
both weak overseas demand (the new exports orders balance fell for the fourth
month in a row) and the cyber-attack-induced shutdown at Jaguar Land Rover
since 1 September reducing car production across the automotive supply
chain. The PMIs suggest tepid growth is the best that can be expected when
the Q3 GDP numbers are released.
• Turning to retail sales, and the 0.5% m/m rise in volumes in August was the
third such rise in a row and was driven by gains in all the major categories
except fuel sales, which fell by 2.0% m/m. Sales may have been supported by
Page 125

Page 126

APPENDIX 1
the warmer-than-usual weather. If sales were just flat in September, then in Q3
sales volumes would be up 0.7% q/q compared to the 0.2% q/q gain in Q2. 
• With the November Budget edging nearer, the public finances position looks
weak.  Public net sector borrowing of £18.0bn in August means that after five
months of the financial year, borrowing is already £11.4bn higher than the OBR
forecast at the Spring Statement in March. The overshoot in the Chancellor’s
chosen fiscal mandate of the current budget is even greater with a cumulative
deficit of £15.3bn. All this was due to both current receipts in August being lower
than the OBR forecast (by £1.8bn) and current expenditure being higher (by
£1.0bn). Over the first five months of the financial year, current receipts have
fallen short by a total of £6.1bn (partly due to lower-than-expected self-
assessment income tax) and current expenditure has overshot by a total of
£3.7bn (partly due to social benefits and departmental spending). Furthermore,
what very much matters now is the OBR forecasts and their impact on the
current budget in 2029/30, which is when the Chancellor’s fiscal mandate bites.
As a general guide, Capital Economics forecasts a deficit of about £18bn,
meaning the Chancellor will have to raise £28bn, mostly through higher taxes,
if she wants to keep her buffer against her rule of £10bn. 
• The weakening in the jobs market looked clear in the spring. May’s 109,000
m/m fall in the PAYE measure of employment was the largest decline (barring
the pandemic) since the data began and the seventh in as many months. The
monthly change was revised lower in five of the previous seven months too,
with April’s 33,000 fall revised down to a 55,000 drop. More recently, however,
the monthly change was revised higher in seven of the previous nine months
by a total of 22,000. So instead of falling by 165,000 in total since October,
payroll employment is now thought to have declined by a smaller 153,000. Even
so, payroll employment has still fallen in nine of the ten months since the
Chancellor announced the rises in National Insurance Contributions (NICs) for
employers and the minimum wage in the October Budget. The number of job
vacancies in the three months to August stood at 728,000. Vacancies have now
fallen by approximately 47% since its peak in April 2022. All this suggests the
labour market continues to loosen, albeit at a declining pace. 
• A looser labour market is driving softer wage pressures. The 3m/yy rate of
average earnings growth excluding bonuses has fallen from 5.5% in April to
4.8% in July. The rate for the private sector slipped from 5.5% to 4.7%, putting
it on track to be in line with the Bank of England’s Q3 forecast (4.6% for
September). 
• CPI inflation fell slightly from 3.5% in April to 3.4% in May, and services inflation
dropped from 5.4% to 4.7%, whilst core inflation also softened from 3.8% to
3.5%.  More recently, though, inflation pressures have resurfaced, although the
recent upward march in CPI inflation did pause for breath in August, with CPI
inflation staying at 3.8%. Core inflation eased once more too, from 3.8% to
3.6%, and services inflation dipped from 5.0% to 4.7%. So, we finish the half
year in a similar position to where we started, although with food inflation rising
to an 18-month high of 5.1% and households’ expectations for inflation standing
Page 126

Page 127

APPENDIX 1
at a six year high, a further loosening in the labour market and weaker wage
growth may be a requisite to UK inflation coming in below 2.0% by 2027.  
• An ever-present issue throughout the past six months has been the pressure
being exerted on medium and longer dated gilt yields. The yield on the 10-year
gilt moved sideways in the second quarter of 2025, rising from 4.4% in early
April to 4.8% in mid-April following wider global bond market volatility stemming
from the “Liberation Day” tariff announcement, and then easing back as trade
tensions began to de-escalate. By the end of April, the 10-year gilt yield had
returned to 4.4%. In May, concerns about stickier inflation and shifting
expectations about the path for interest rates led to another rise, with the 10-
year gilt yield fluctuating between 4.6% and 4.75% for most of May. Thereafter,
as trade tensions continued to ease and markets increasingly began to price in
looser monetary policy, the 10-year yield edged lower, and ended Q2 at 4.50%. 
• More recently, the yield on the 10-year gilt rose from 4.46% to 4.60% in early
July as rolled-back spending cuts and uncertainty over Chancellor Reeves’
future raised fiscal concerns. Although the spike proved short lived, it
highlighted the UK’s fragile fiscal position. In an era of high debt, high interest
rates and low GDP growth, the markets are now more sensitive to fiscal risks
than before the pandemic. During August, long-dated gilts underwent a
particularly pronounced sell-off, climbing 22 basis points and reaching a 27-
year high of 5.6% by the end of the month. While yields have since eased back,
the market sell-off was driven by investor concerns over growing supply-
demand imbalances, stemming from unease over the lack of fiscal
consolidation and reduced demand from traditional long-dated bond
purchasers like pension funds. For 10-year gilts, by late September, sticky
inflation, resilient activity data and a hawkish Bank of England have kept yields
elevated over 4.70%. 
• The FTSE 100 fell sharply following the “Liberation Day” tariff announcement,
dropping by more than 10% in the first week of April - from 8,634 on 1 April to
7,702 on 7 April. However, the de-escalation of the trade war coupled with
strong corporate earnings led to a rapid rebound starting in late April. As a
result, the FTSE 100 closed Q2 at 8,761, around 2% higher than its value at
the end of Q1 and more than 7% above its level at the start of 2025. Since then,
the FTSE 100 has enjoyed a further 4% rise in July, its strongest monthly gain
since January and outperforming the S&P 500. Strong corporate earnings and
progress in trade talks (US-EU, UK-India) lifted share prices and the index hit
a record 9,321 in mid-August, driven by hopes of peace in Ukraine and dovish
signals from Fed Chair Powell. September proved more volatile and the FTSE
100 closed Q3 at 9,350, 7% higher than at the end of Q1 and 14% higher since
the start of 2025. Future performance will likely be impacted by the extent to
which investors’ global risk appetite remains intact, Fed rate cuts, resilience in
the US economy, and AI optimism. A weaker pound will also boost the index as
it inflates overseas earnings. 
MPC meetings: 8 May, 19 June, 7 August, 18 September 2025
• There were four Monetary Policy Committee (MPC) meetings in the first half of
the financial year. In May, the Committee cut Bank Rate from 4.50% to 4.25%,
while in June policy was left unchanged. In June’s vote, three MPC members
(Dhingra, Ramsden and Taylor) voted for an immediate cut to 4.00%, citing
Page 127

Page 128

APPENDIX 1
loosening labour market conditions. The other six members were more
cautious, as they highlighted the need to monitor for “signs of weak demand”,
“supply-side constraints” and higher “inflation expectations”, mainly from rising
food prices. By repeating the well-used phrase “gradual and careful”, the MPC
continued to suggest that rates would be reduced further. 
• In August, a further rate cut was implemented.  However, a 5-4 split vote for a
rate cut to 4% laid bare the different views within the Monetary Policy
Committee, with the accompanying commentary noting the decision was “finely
balanced” and reiterating that future rate cuts would be undertaken “gradually
and carefully”.  Ultimately, Governor Bailey was the casting vote for a rate cut
but with the CPI measure of inflation expected to reach at least 4% later this
year, the MPC will be wary of making any further rate cuts until inflation begins
its slow downwards trajectory back towards 2%.
• The Bank of England does not anticipate CPI getting to 2% until early 2027,
and with wages still rising by just below 5%, it was no surprise that the
September meeting saw the MPC vote 7-2 for keeping rates at 4% (Dhingra
and Taylor voted for a further 25bps reduction).
• The Bank also took the opportunity to announce that they would only shrink its
balance sheet by £70bn over the next 12 months, rather than £100bn. The
repetition of the phrase that “a gradual and careful” approach to rate cuts is
appropriate suggests the Bank still thinks interest rates will fall further but
possibly not until February, which aligns with both our own view and that of the
prevailing market sentiment.   
Interest Rate Forecasts 
The Authority has appointed MUFG Corporate Markets as its treasury advisors and
part of their service is to assist the Authority to formulate a view on interest rates. The
PWLB rate forecasts below are based on the Certainty Rate (the standard rate minus
20bps) which has been accessible to most authorities since 1 November 2012. 
MUFG Corporate Markets’ latest forecast on 11 August sets out a view that short,
medium and long-dated interest rates will fall back over the next year or two, although
there are upside risks in respect of the stickiness of inflation and a continuing tight
labour market, as well as the size of gilt issuance. 
MUFG Corporate Markets Interest Rate View 11.08.25
Sep-25 Dec-25 Mar-26 Jun-26 Sep-26 Dec-26 Mar-27 Jun-27 Sep-27 Dec-27 Mar-28 Jun-28 Sep-28
BANK RATE 4.00 4.00 3.75 3.75 3.50 3.50 3.50 3.50 3.25 3.25 3.25 3.25 3.25
3 month ave earnings 4.00 4.00 3.80 3.80 3.50 3.50 3.50 3.50 3.30 3.30 3.30 3.30 3.30
6 month ave earnings 4.00 3.90 3.70 3.70 3.50 3.50 3.50 3.50 3.30 3.30 3.40 3.40 3.40
12 month ave earnings 4.00 3.90 3.70 3.70 3.50 3.50 3.50 3.50 3.30 3.40 3.50 3.60 3.60
5 yr   PWLB 4.80 4.70 4.50 4.40 4.30 4.30 4.30 4.20 4.20 4.20 4.20 4.10 4.10
10 yr PWLB 5.30 5.20 5.00 4.90 4.80 4.80 4.80 4.70 4.70 4.70 4.70 4.60 4.60
25 yr PWLB 6.10 5.90 5.70 5.70 5.50 5.50 5.50 5.40 5.40 5.30 5.30 5.30 5.20
50 yr PWLB 5.80 5.60 5.40 5.40 5.30 5.30 5.30 5.20 5.20 5.10 5.10 5.00 5.00
Page 128

Page 129

Audit & Scrutiny Committee Work Plan 2025 
This is an outline plan to facilitate forward planning of reports to the Audit & Scrutiny Committee 
Report  Lead Service Regularity
16 December 2025 Reports to Committee Services by 21 November 2025
Internal Audit and Counter Fraud Summary of Activities Chief Internal Auditor Quarterly
Internal and External Audit Report Follow Up  Chief Internal Auditor Quarterly
Internal Audit Reports to Audit and Scrutiny Committee 2025/26 Chief Internal Auditor Quarterly
Verbal Update by Chair(s) of Scrutiny Panel Chair and Vice Chair of Audit & Scrutiny Committee   Quarterly
Performance Reporting Update (to include reference to LGBF) Chief Executive/Head of Customer Support Services/HR
& OD Manager – Carolyn Cairns/Jennifer Coyle
Annual
Council Annual Report 2025/26 Head of Customer Support Services Annual
Annual Council Business Plan 2024-25 Outcomes Head of Customer Support Services Annual
Treasury Management Strategy and Annual Investment Strategy –
Mid-year Review Report 2025/26 
Head of Financial Services Annual
Special Meeting – 26 January 2026 Reports to Committee Services by 16 January 2026
Annual Auditors Report Forvis Mazars – Mark Outterside Annual
Draft Thematic Review Forvis Mazars – Mark Outterside Annual
2024-25 Audited Annual Accounts Forvis Mazars – Mark Outterside/Section 95 Officer/Head
of Financial Services
Annual
12 March 2026 Reports to Committee Services by 16 February 2026
Internal Audit and Counter Fraud Summary of Activities Chief Internal Auditor Quarterly
Internal and External Audit Report Follow Up Chief Internal Auditor Quarterly
Internal Audit Reports to Audit and Scrutiny Committee 2025/26 Chief Internal Auditor Quarterly
Verbal Update by Chair(s) of Scrutiny Panel Chair and Vice Chair of Audit & Scrutiny Committee   Quarterly
External Audit Progress Report Forvis Mazars – Mark Outterside Quarterly 
RIPSA Annual Report Governance and Risk Manager Annual
Internal Audit 2025/26 Plan and Internal Audit Strategy 2025-2028 Chief Internal Auditor Annual
2025/26 Unaudited Annual Accounts Preparation Plan and
Timetable
Head of Financial Services Annual
2025-26 Treasury Management Update as at 31 December 2025 Head of Financial Services Annual
2026-27 Treasury Management Strategy and Annual Investment
Strategy
Head of Financial Services Annual
Page 129
Agenda Item
9

Page 130

Audit & Scrutiny Committee Work Plan 2025 
Internal Audit Charter and Internal Audit Manual Chief Internal Auditor Annual
Scrutiny Manual and Framework Annual Review  Chief Internal Auditor Annual
11 June 2026 Reports to Committee Services by 18 May 2026
Internal Audit and Counter Fraud Summary of Activities Chief Internal Auditor Quarterly
Internal and External Audit Report Follow Up Chief Internal Auditor Quarterly
Internal Audit Reports to Audit and Scrutiny Committee 2026/27 Chief Internal Auditor Quarterly 
Verbal Update by Chair(s) of Scrutiny Panel Chair and Vice Chair of Audit & Scrutiny Committee   Quarterly
External Audit Progress Report Forvis Mazars – Mark Outterside Quarterly
Internal Audit 2025-26 Annual Report  Chief Internal Auditor Annual
Scrutiny report on the Monitoring and Managing of Complaints Chief Internal Auditor (Scrutiny Panel) from March A&SC Annual
Annual Audit Plan for year ending 31 March 2026 Forvis Mazars – Mark Outterside Annual
Local Government in Scotland – Financial Bulletin 2024/25 
(Accounts Commission publication – timing will be subject to change, as this is
dependent on publication date)
Head of Financial Services Annual
Local Government Benchmarking Framework Report Head of Customer Support Services/OD Project Manager
(Chris Carr)
Annual
Unaudited Annual Accounts for year ending 31 March 2026 Head of Financial Services Annual
Treasury Management Annual Report 2025/26 Head of Financial Services Annual
Statement of Governance and Internal Control Governance, Risk and Safety Manager Annual
XX September 2026  Reports to Committee Services by XX August 2026
Internal Audit and Counter Fraud Summary of Activities Chief Internal Auditor Quarterly
Internal and External Audit Report Follow Up  Chief Internal Auditor Quarterly
Internal Audit Reports to Audit and Scrutiny Committee 2026/27 Chief Internal Auditor Quarterly
External Audit Progress Report Forvis Mazars – Mark Outterside Quarterly
Verbal Update by Chair(s) of Scrutiny Panel Chair and Vice Chair of Audit & Scrutiny Committee   Quarterly
2026-27 Treasury Management Update as at 30 June 2026 Interim Head of Financial Services Annual
PSIAS Self-Assessment  Chief Internal Auditor Annual
Corporate Complaints Annual Report 2025-26  Governance, Risk and Safety Manager Annual
Freedom of Information Annual Report 2025-26  Governance, Risk and Safety Manager Annual
Audit & Scrutiny Committee 2025/26 Annual Report  Audit & Scrutiny Committee Chair Annual
Strategic Risk Assurance Mapping Chief Internal Auditor Annual
Strategic Risk Register Update  Chief Executive Annual 
Page 130

Page 131

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES            16 DECEMBER 2025 
ANNUAL COUNCIL BUSINESS PLAN 2024-25 OUTCOMES 
1.0 EXECUTIVE SUMMARY 
In June 2023 the Council agreed a Corporate Plan covering the years 2023 –
2027.  It was intended that there would be annual updates on the progress
against outcomes in the form of Annual Business Plans and a new Business
Plan created for each year of the life of the Corporate Plan.  As the
Administration changed, the priorities were reviewed and a new Corporate Plan
was developed to align with these, coupled with a new suite of Annual Business
Plans.  This report provides an update on progress for the Annual Business Plan
2024 – 2025 which closes off the previous corporate priorities reporting, for the
Committee’s information. 
The report recommends that the Committee:   
• Notes the progress made against the outcomes specified in the 2024 – 2025
Annual Business Plan and
• Notes that an Annual Business Plan for 2025 - 2026 will be created in
regard to the current Council priorities 
Page 131 Agenda Item 10

Page 132

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES                   16 DECEMBER 2025 
ANNUAL COUNCIL BUSINESS PLAN 2024-25 OUTCOMES 
2.0 INTRODUCTION 
2.1 In June 2023 the Council agreed a Corporate Plan covering the years 2023 –
2027.  It was intended that there would be annual updates on the progress
against outcomes in the form of Annual Business Plans and a new Business
Plan created for each year of the life of the Corporate Plan.  As the
Administration changed, the priorities were reviewed and a new Corporate Plan
was developed to align with these, coupled with a new suite of Annual Business
Plans.  This report provides an update on progress for the Annual Business Plan
2024 – 2025 which closes off the previous corporate priorities reporting, for the
Committee’s information.  The report was presented to Council on 26 November
2025.   
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Committee: 
3.1.1 Notes the progress made against the outcomes specified in the 2024 –
2025 Annual Business Plan and 
3.1.2 Notes that an Annual Business Plan for 2025 - 2026 will be created in
regard to the current Council priorities 
4.0 DETAIL 
4.1 Members agreed the Council priorities at its meeting in November 2022. Those
priorities were captured within the Corporate Plan for the period 2023 – 2027. 
The Administration changed during the life of this plan and a new set of priorities
were agreed in September 2024.  These were incorporated into a new
Corporate Plan, agreed by Committee in May 2025.  Consequently, the previous
Annual Business Plan outcomes were carried forward to the financial year 2024
– 2025.  Details on activity for the financial year 2024 - 2025 against those
priorities are set out in the Council’s Annual Business Plan Annual Update 2024
– 2025 which brings more focus and scrutiny on the delivery and performance of
the organisation against its priorities. 
Page 132

Page 133

4.2 An assessment against the performance contained within the Business Plan for
2024 – 2025 is appended.  Where available, the updates cover the period to
October 2025 although the key reporting period covered by the Annual Business
Plan is the financial year 2024 – 2025.  This was submitted to Council on 26
November 2025 as part of an annual cycle of review, correction and
implementation.  The report and update is now also submitted to Audit and
Scrutiny Committee. 
5.0 CONCLUSION 
5.1 Members are asked to review the update on progress for the second year of the
Council’s Corporate Plan, 2024 – 2025 and note progress against outcomes
identified, in consideration of the Council’s current priorities. 
6.0 IMPLICATIONS 
6.1 Policy - None arising directly from this report. 
6.2 Financial - None arising directly from this report. 
6.3  Legal - None arising directly from this report. 
6.4  HR - None arising directly from this report. 
6.5 Customer Service - None arising directly from this report however outcomes in
the Business Plan may impact.  These have been addressed in Integrated
Impact Assessments for relevant activities. 
6.6 Risk - None arising directly from this report. 
6.7 Climate Change - None arising directly from this report however outcomes in
the Business Plan may impact.  These have been addressed in Integrated
Impact Assessments for relevant activities. 
6.8  Fairer Scotland Duty - An EqSEIA for the Corporate Plan 2023 - 2027 is
available on the Council website. 
6.9 Equalities - protected characteristics 
Socio-economic - Duty None arising directly from this report however
outcomes in the Business Plan may impact.  These have been addressed in
Integrated Impact Assessments for relevant activities. 
6.10 Consumer Duty - None arising directly from this report however outcomes in
the Business Plan may impact.  These have been addressed in Integrated
Impact Assessments for relevant activities. 
Page 133

Page 134

6.11 Island Communities - None arising directly from this report however outcomes
in the Business Plan may impact.  These have been addressed in Integrated
Impact Assessments for relevant activities. 
6.12 Children’s Rights and Wellbeing - None arising directly from this report
however outcomes in the Business Plan may impact.  These have been
addressed in Integrated Impact Assessments for relevant activities. 
Pippa Milne, Chief Executive 
Jim Lynch, Council Leader 
28 October 2025                                                  
For further information contact: 
Pippa Milne, Chief Executive, pippa.milne@argyll-bute.gov.uk 
Jane Fowler, Head of Customer Support Services, jane.fowler@argyll-bute.gov.uk 
Jennifer Coyle, Senior HR Business Partner, jennifer.coyle@argyll-bute.gov.uk 
APPENDICES 
Appendix 1  Annual Business Plan 2024 to 2025 Annual Update October 2025   
Page 134

Page 135

Argyll and Bute Council
Annual Business Plan 2024 – 2025
Update Report 
Page 135

Page 136

Council Priorities Action Plan 2024 - 2025 
Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
People and places, our core business as a council    
Attaining and achieving at all stages; we will improve outcomes for our children and young people  
Improve educational
attainment,
achievement and
outcomes for our young
people within Argyll and
Bute to Scotland’s
upper quartile.
• Continue to challenge and support
schools proportionately. Further
refine criteria for support and
ensure increased focus on
secondary schools.
• Continue to work in close
partnership with Developing the
Young Workforce (DYW) team to
ensure young people successfully
develop the skills for life and work
required to attain sustained positive
destinations post-school.
• Continue to track young people’s
pathways within school and in the
period after leaving school, to
ensure appropriate support,
guidance and opportunities are in
place to gain and sustain positive
destinations.
• Improved levels of
attainment across
the Senior Phase
where attainment
is in line with
national data. 
• Extended range of
learning pathways
on offer for all
learners. 
• 96% of 16–19-
year-olds are in
Education,
Training or
Employment.
• We are continuing to
strengthen our
approaches to
supporting and
challenging secondary
schools to raise levels
of attainment for all. All
schools now have
more robust tracking
systems in place which
are leading to
improvement. A few
schools are continuing
to receive intensive
support around
improving attainment.
In 2 (out of 3) of these
schools, senior phase
predictions for August
2025 are showing
signs of some
improvement.
Page 136

Page 137

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
• In 2024/25, Education
has further developed
its work with
Community Learning to
introduce an increased
range of wider
achievement
opportunities across
secondary schools. As
a result, 614 young
people have engaged
across seven
accredited awards,
while 718 young
people have accessed
eight non-accredited
learning activities,
including dedicated
primary-secondary
transition support.
• Skills Development
Scotland Annual
Participation Measure
published Aug 24:
94.3% of 16-19 year-
olds in Education,
Training or
Employment.
Page 137

Page 138

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Educational Attainment
and Wider Achievement
– Developing the use of
all the available data
and intelligence on
each of our educational
establishments to focus
on and drive
improvement, achieving
our stretch aims (goals
to improve
opportunities and
outcomes for young
people) as agreed with
the Scottish
Government.
• Strengthen focus on learning,
teaching and assessment with
increased emphasis on secondary
sector. Continue to build staff
capacity in the interrogation and
use of data for improvement.
• Develop further use of range of
data dashboards in order to provide
accessible and meaningful data for
all schools and settings.
• Deliver targeted and universal
literacy and numeracy support for
establishments in order to raise
attainment with specific focus on
pupils residing in Quintile 1.
• Continue to support schools to
rigorously track and monitor pupil
progress and plan measurable
interventions and initiatives to raise
attainment for all whilst closing the
poverty related attainment gap.
• Stretch aims are
achieved: 
Literacy 73.5%,
Numeracy 80.5%
School Leavers
with 1 or more
pass at SCQF
Level 5 92.25%.
• School Leavers
with 1 or more
pass at SCQF
Level 6 67.75%.
Improved levels of
attainment across
the Senior Phase
where attainment
is in line with
national data. 
• Stretch Aims 23/24: 
ACEL: 
Literacy - 72.2% (up
from 67.7%) Numeracy
- 80.1% (up from
76.4%) 
Based on recent ACEL
attainment data
tracking, we are on
track to achieve our
overall stretch aims for
P1/4/7 at June 2025. 
• School Leavers: 
School Leavers with 1
or more pass at SCQF
Level 5 - 85.7% School
Leavers with 1 or more
pass at SCQF Level 6 -
66.7% (Amongst S6
leavers only, the
percentage leaving
with 1+ At level 6
increased from 85.5%
to 90.6%. Increase in
S4 leaving rates
created downward
pressure on cohort
performance).
Page 138

Page 139

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Developing a broader
curriculum offer to
augment current
opportunities with a
range of wider
achievement awards
and
accreditations.  This will
have a positive impact
on leaver destinations
through inclusive, skills
- based programmes in
each secondary school.
• Schools will be supported and
challenged to develop their
curricula, underpinned by a robust
rationale taking account of place-
based resources and local labour
market data.
• Support secondary schools via UK
Shared Prosperity Funding to
ensure accredited wider
achievement opportunities exist for
every pupil at each stage of their
secondary education.
• Strengthen partnerships with
Community Learning, UHI Argyll
and Third Sector agencies to
increase wider achievement
opportunities for young people at
each stage of their secondary
education.
• Young People in
every secondary
school have the
opportunity to
engage in 1
accredited wider
achievement
programme at
each stage of their
secondary
education.
An extended
range of pathways
are in place and
opportunities for
partnership
working are
maximised. 
• All secondary schools
are now in a position to
offer young people at
least 1 wider
achievement
opportunity.
• The use of UKSPF has
been monitored
robustly to ensure best
value and appropriate
use. All schools are on
track to have utilised
this funding by the
deadline. In addition,
we will receive an
allocation next session.
We were initially
informed that this
funding stream was
coming to an end.
• Community Learning
(CL) have extended
partnership with
secondary schools. CL
active in all secondary
schools offering wider
achievement/skills
development courses.
To date in 2024-25,
there have been 198
Page 139

Page 140

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
accreditations. 359
young people engaged
in either accredited or
non-accredited wider
achievement activities.
• 39 Flexible Learning
Plans (FLPs) are in
place across
secondary schools to
support disengaged
learners as a result of
partnerships with
employers and UHI
Argyll (2023-24 34
FLPs)
• Partnerships between
schools and employers
have continued to
increase in 2024-25.
As a result, a total of
380 work placements
have supported young
people to plan their
individual vocational
pathways.
Page 140

Page 141

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Continuing to promote
the teaching and use of
Gaelic as set out in the
council’s emerging
Gaelic Plan for 2023.
• Education Officer and Principal
Teacher will continue to support and
challenge establishments to build
staff capacity and help to establish
Gaelic as an L2 or L3.
• Continue to signpost schools to
ESgoil support and support and
materials from other agencies such
as Education Scotland and
Storlann. Continue to work in
partnership with Ed Scot to
challenge and support schools. EO
and PT will continue to challenge
and support schools to improve the
quality of Gaelic Medium Education
and attainment for all pupils.
• Principal Teacher will continue to
deliver online language lessons
with colleagues from other
authorities. 
• Number of schools
offering Gaelic as
L2 or L3 to 80%
(dependent on
Scottish
Government).
• Through the work of
the PT, including the
additional development
of Live Lessons, 71%
of primary schools in
A&B are currently
delivering Gaelic as L2
or L3. This is an
increase of 3% since
October 2024 when
68% of schools
delivered Gaelic
Learner Education. The
Live Lessons support
schools to continue
their development of
Gaelic as L3, enabling
pupils to progress their
learning beyond the
‘beginner’ stage. The
Live Lessons enable
schools to continue
their delivery of Gaelic
as L2 and L3, thus
supporting the
Education Service to
reach our target of 80%
of all primary schools. 
• All A&B teaching staff
have regular updates
Page 141

Page 142

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
from the PT to inform
staff of educational
resources and support
from partners including
eSgoil and Education
Scotland.
• Education Scotland’s
Senior Education
Officer (SEO) for
Gaelic has visited
almost all GMPE
settings to support
Learning Teaching and
Assessment (LTA).
Positive impact on
pupil attainment in
Gaelic Literacy is being
evidenced. 
• Almost all GMPE
settings have been
trained in QI Writing
strategies. This
methodology is
resulting in a positive
impact on pupil
attainment in Gaelic
writing.  
• Almost all GMPE
settings received in-
person support from
Page 142

Page 143

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
the Furan Gaelic
Centre administrator.
This has had a positive
impact on pupil fluency. 
• All GMPE practitioners
now have access to the
wide range of Highland
Literacy Project
materials in Gaelic for
use in LTA. This work is
starting to have a
positive impact on pupil
attainment in GME.
Learning estate now and in the future; we will ensure our schools are effective, sustainable learning environments  
Progress a bid to the
Scottish Government to
establish a new
campus on Mull. 
• Continue to develop the business
case, undertake engagement and
site selection process for a new
Campus on Mull.
• Robust business
case in place,
communities feel
involved and
engaged in
process, site
selected and plans
progressed in line
with identified
timescales.
• LEIP application was
successful and was
accepted to LEIP
phase 3 programme in
October 2023.
Community
engagement activities
took place in
September 2024
informing the project
site selection.
Special Council
Committee meeting on
March 7th agreed the
preferred site
Page 143

Page 144

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
‘Tobermory South’
(southern edge of
Tobermory with the
western boundary
adjacent to the A848).A
group called Mull
Campus Working
submitted a Judicial
Review against the
Council which was
heard in Court of
Session on 13th
October.  Work on the
project has ceased
pending outcome of
JR.
Develop the next
generation of capital
investment plan and
priorities for our school
estate.
• Service Asset Management Plan
(SAMP) for Education and delivery
of Programme by Feb 2024.  
• All programmed
work completed by
the specified date
and in line with the
allocated capital
budget.
• All capital works
completed on budget
and to timescale to
programme with
notable investment in
John Logie Baird
Primary School and
Tobermory / Hermitage
ASN Units.
Supporting children and young people with additional needs    
Page 144

Page 145

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Reducing the number
of children and young
people who have to
travel out-with the area
to access services by
enhancing provision
where gaps currently
exist.
• Progress planning for and set up of
four Learning Centres in areas as
identified in the ASN review of
2021/22.
• Continue to increase the number of
staff within educational settings
being CALM trained.
• Continue to offer opportunities for
staff to further develop their skill in
meeting the needs of all learners.
• Continue to
Increase the
number of children
accessing high
quality enhanced
provision within
Argyll and Bute.
• All new Learning
Centres will be
operational by August
2025 with places
allocated to children
through the ERG
allocation process.
• All schools are able to
access CALM training
and there has been
increased uptake
during session
2024/2025 from the
previous academic
session. By June 2025,
there will be an
increased number of
CALM trainers in Argyll
and Bute. This will
support educational
settings in becoming
CALM trained and
moderate the effective
application of this
training.
• All primary and
secondary schools
have been able to
access CIRCLE and
GIRFEC training.
Page 145

Page 146

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Working to improve and
secure equity of
specialist provision
across Argyll and Bute
by addressing gaps
where they exist across
the education estate.
• Continue to progress plans
accordingly including recruitment of
staff.
• Continue to
increase the
number of children
accessing high
quality specialist
provision within
Argyll and Bute.
• Most new Learning
Centres already have
teaching staff in post
prior to August 2025
opening. The
remaining posts are
currently being
advertised.
• Support staff
recruitment is
underway and all
learning Centres are on
track to be fully
resourced by August
2025.
• Leaders from all
Learning Centres are
participating in the
development of a
Strategic Leadership
network for specialist
provision. The network
has identified
improvement priorities
and will be
collaborating to
develop shared
understanding on
effectively supporting
learners and how to
Page 146

Page 147

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
develop high quality
specialist provision
appropriate for their
context. 
Maintaining the current
staffing complement
who support ASN in line
with our nurture stretch
aim agreed with
Scottish Government.
• Current complement of central staff-
1 Principal Teacher and 2 Teachers
will be maintained through
maintaining teacher numbers. The
number of schools engaging with
Our Children Their Nurture
Education will increase to 35.
• Stretch aims are
achieved: Literacy
73.5%, Numeracy
80.5% School
Leavers with 1 or
more pass at
SCQF Level 5
92.25%.School
Leavers with 1 or
more pass at
SCQF Level 6
67.75%.Core plus
stretch aim nurture
measure is 67%.
• There are currently 58
settings engaged with
OCTNE (52 schools
and 6 ELC providers),
with 12 of these
settings joining during
session 24/25,
exceeding the stretch
aim of 35 schools and
reflecting a growing
commitment to trauma-
informed, nurture-
based education.”
• The current
complement of central
staff – 1 Principal
Teacher and 2
Teachers – continues
to provide targeted
ASN support, aligned
with the nurture stretch
aim.
• In session 24/25,
Nurture Teachers
delivered training in
Boxall Profiles, Block
Page 147

Page 148

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Based Therapy, and
PACE to staff across
multiple settings,
directly contributing to
the professional
capacity of ASN
support staff.
• The 5th cohort of
leadership training
began February 2025
with 32 participants
from 22 settings,
helping schools
prepare for OCTNE
accreditation and
sustain nurturing
practices at a strategic
level.
• Targeted nurture
intervention and
coaching has been
delivered to 8 schools
via the Coach and
Consult model,
strengthening the ASN
support network and
helping staff address
SEMH needs.
Roads and pathways; connecting to, from and within Argyll will be supported  
Page 148

Page 149

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Reviewing our
approach to road repair
prioritisation to make
the most effective use
of resources in the
context of budget
pressures and to
achieve the best
possible balance in
terms of strategic,
operational and
member input.
• Implement actions to increase
member input in process 
• Members seminar  • Officers have agreed a
process plan which
include an annual
members input for the
capital roads plan of
works so that a local
perspective can be
introduced.  Members
seminar took place
October 2024. 
Initiating plans for a
20mph speed limit by
working in partnership,
and in line with national
legislation, on the
rollout and delivery of a
20mph limit where that
will work best for our
communities.
• Review potential for implementing
20mph speed limits in accordance
with national priorities. 
• Number of
engagement
sessions
• Number of 20mph
schemes
introduced
• Officer appointed to
post funded by Scottish
Government and is
developing a
programme of
engagement with
stakeholders including
elected members and
community groups.
Completing a review of
parking and traffic
management/enforcem
ent to reshape
arrangements that
reflect community
needs and ambitions.
• TRO review in line with members
requests to support their
communities’ needs. 
• Report through
December 2025
EDI Committee to
obtain agreement
on proposed
review and
methodology.
• Report to EDI
committee on 18
• Report through EDI
Committee 18
December 2025 the
proposed Traffic
Regulation Orders for
the whole ABC area. 
• TRO Business day with
members October
2025 to outline
Page 149

Page 150

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
December 2025 to
obtain agreement
on proposed
review and
methodology
• Review
commences.
• Start of
consultation
period.
• Statutory
consultation takes
place.
• TRO Business day
with members .
• New TROs
agreed.
proposed approach
and obtain member
feedback. Proposals
now being developed
to reflect this.
Piers and harbours  
Upgrading the council’s
harbour infrastructure
to ensure it is capable
of receiving existing
and planned new
ferries (including at
Craignure,
Fionnphort/Ruahaich,
Port Askaig, Dunoon,
Kilcreggan and
• Iona
Start work on new breakwater at Iona. 
o Capital dredging to improve
navigational access
o Replacement of the public toilet block
o Slipway repairs 
• Craignure
Complete OBC
Start preparation of FBC
• Campbeltown
• Iona
All necessary marine
licences granted
Tender go live for
management consultant
Project start
• Craignure
Complete OBC
• Campbeltown
Open new quay 
• Iona 
All necessary marine licences
have been granted, including: 
o Rock Armour Breakwater
Licence
o Capital Dredging Licence
o European Protected
Species Licence
o Basking Shark Licence. 
• A Seagrass Mitigation
and Monitoring Plan
Page 150

Page 151

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Campbeltown,
Tayinloan - Gigha).
Open new quay     was approved in July
2025, with ongoing
environmental
monitoring throughout
construction
• Site mobilisation began
in March 2025. Over
120,000 tonnes of
granite rock are being
used, sourced from
Glensanda Quarry,
Ireland, and Norway.
21,000 tonnes of 1–3
tonne rock have
already been delivered
and placed to form the
base and core of the
breakwater. 
• The new toilet block is
nearing completion,
with mechanical and
electrical installations
underway.
• Craignure
• A tender for
management
consultants to lead this
next phase is expected
to go live in November
2025, with an
Page 151

Page 152

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
appointment
anticipated in January
2026. 
• The cost of the project
is now  projected at
£96 million
• Gigha / Tayinloan
• The ferry terminals at
Gigha and Tayinloan
are undergoing
significant upgrades as
part of Transport
Scotland’s Small
Vessel Replacement
Project This will
modernise
infrastructure to
support new hybrid
ferries. These are two
separate but
coordinated projects
being managed by
Argyll and Bute Council
with support from RPS
Tetra Tech.
Creating a new
municipal harbour
authority in Oban,
ensuring that proposals
are submitted to
• HRO to be submitted to and agreed
by Scottish Government
• New HRO in place • The council has
submitted a Harbour
Revision Order (HRO)
to Transport Scotland
to establish a Municipal
Page 152

Page 153

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Scottish ministers as
soon as possible
following consideration
by the Harbour Board in
December 2022, and
putting preparations in
place to commence
operations upon
approval by ministers.
Harbour Authority that
would cover most of
Oban Bay, excluding
the area around the
ferry terminal (which
remains under CMAL).
• The HRO is now with
Scottish Government
Ministers for
consideration. When
approved, Argyll and
Bute Council would
become the Statutory
Harbour Authority for
the newly defined area
of Oban Bay.
Seeking funding for the
procurement of new
council-operated
vessels including
Islay/Jura, Luing and
Easdale.
• Carry out assessment, specification
and costing of new vessels.  
• Request funding from Scottish
Government and/or explore other
funding opportunities.   
• Secure funding for
new vessels
based on priority
requirement.  
• Funding for new ferries
serving Jura, Luing,
and Easdale is
progressing through a
combination of local
authority planning,
regional transport
partnerships, and the
Scottish Government’s
Small Vessel
Replacement
Programme (SVRP).
• Jura Ferry
Page 153

Page 154

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
The Council is actively
pursuing funding for
the design and
construction of a new
ferry for Jura
• HITRANS has
committed £1.5 million
to support planning and
infrastructure
improvements for Jura
and Luing.
• The Council is lobbying
for full funding from the
Scottish Government
and exploring options
for capital investment
through Transport
Scotland and
HITRANS. 
• Jura, Luing, and
Easdale are not
included in Phase 1 of
SVRP, which covers
seven electric ferries
for other routes (e.g.,
Gigha, Iona). However,
future phases may
include these
Finalising the demand,
economic impact and   
Page 154

Page 155

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
business case
assessment for the
Helensburgh Pier
strategy in 2023.
Waste and recycling services; reduce our carbon emissions  
Delivering a solution
that enables the council
to divert its
biodegradable waste
from landfill, within
2026, while seeking a
short-term derogation
to allow the PPP
contract to expire.
• Identify route to market for contract
to replace PPP
• Develop variation to existing PPP
contract to divert residual waste
away from landfill
• Procure off take and haulage
contracts for island sites
• New offtake
contracts for
landfill waste
• End of MBT at
Oban, Dunoon
and Lochgilphead
PPP sites
• Multi disciplinary
working group
established with
representatives of the
council’s legal,
procurement, financial
and waste services to
develop legally
compliant solution to
landfill ban
• Agreement reached
with current contractor,
Biffa, to alter existing
Public / Private
Partnership to allow for
closure of landfill sites
at Dunoon and
Lochgilphead, and
ending of Mechanical
and Biological
Treatment of landfill
waste
• New waste disposal
contract in place to
Page 155

Page 156

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
divert waste from MAKI
and OLI to energy from
waste facilities
Encouraging
households to increase
use of recycling
services to reach at
least the Scottish
average (with service
exploring options to
stretch targets where
possible).
• Carry out marketing and publicity
campaign – e.g. Food Waste
Awareness campaign, Green July
(which will also include waste). 
• Officers review the
recycling rate to
see if the
campaign has had
an impact.  
• The Council worked
with Zero Waste
Scotland to refresh the
recycling section of our
website to streamline
our messaging and
reflect best practice. 
• A second social media
campaign took place in
June which focussed
on behaviour changes
which would help
reduce the amount of
waste going to landfill
and pointed customers
to supporting
information, either on
the council website or
third-party sites.
• Marketing will continue
with regular posts, and
campaigns, throughout
the year. 
Housing
Page 156

Page 157

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25  
Supporting the
provision of over 1,000
affordable homes by
2027 (247 in 2022/23
plus at least 750
additional homes over
the life of the Strategic
Housing Investment
Plan).
• Continue to monitor housing
completions and produce annual
housing land audit.
• Deliver 247
affordable
completions in
22/23
• 107 affordable housing
units were completed
in 23/24 so less than
the programmed
delivery, but this
reflects a natural
variation and is the
latest period for which
data is available.
Exploring additional
options to increase the
availability of all tenures
of housing - mid market
rents, shared equity,
affordable by design
and other
developments - in the
area.
• Explore title burdens and phase 1
site investigations for possible Rural
growth Deal Funded housing for
sale and principal home occupancy
• Complete site
investigations.
• Establish
satisfactory title.
• Phase 1 site
investigations are
complete.  Title
investigations involving
Church of Scotland are
ongoing.
Considering the
implementation of short
term lets control zones
to open up more
housing availability.
• Short-term let licensing regime and
policy in place. 3308 applications
received to be determined.
• 100% of
applications
determined or
deemed granted.
STL applications
mapped on GIS,
to support
consideration of
planning control
areas.
• Draft policies being
devised
Page 157

Page 158

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Continuing to support
households to improve
energy efficiency and
tackle rising living costs
through annual
investment through and
implementation of the
Home Energy Efficiency
Programme in Argyll
and Bute.
• Renew contractors and manage
delivery of HEEPS:ABS
programme.
• Complete delivery
of 24/25 HEEPS
ABS allocation.
• 24/25 HEEPS ABS
allocation was 100%
spent.
Developing the
opportunity for the
council to become a
Rural Housing Body -
where it would be more
directly involved in the
delivery of housing or
land for housing.
• Council has already been awarded
Rural Housing Body status.   
Communities; we will build and strengthen our communities as attractive, vibrant places to live, work and do business  
Creating area plans for
all our communities,
reflecting investment
opportunities and local
service prioritisation.
• Launch Aspiring Places platform
• Comprehensive support to be
provided by the Community
Development team to local
community bodies to facilitate the
development of Local Place Plans.
• Evaluation of
engagement of
platform
undertaken and
reported to Policy
and Resources
Committee
• Development of
support package
for communities,
• Further to Members
agreement in
September 2024, the
‘Aspiring Places –
Community Projects in
Argyll and Bute’ digital
platform was
successfully launched
in March 2025 and
over 150 community
Page 158

Page 159

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
including
webinars, master
classes and a
dedicated web
page with links to
resources,
enabling
communities to
develop Local
Place Plans.
groups registered, and
over 100 project
proposals have been
published.
• An evaluation has been
completed and will be
reported to the Policy
and Resources
Committee on the 04
December 2025.
• Close working between
Development Planning
and Community
Development teams to
prepare a
comprehensive support
page for communities
developing Local Place
Plans, complementing
the Local Development
Plan 3
process.  Support to
communities included
master classes and
webinars, development
of a newsletter and
community of practice.
Page 159

Page 160

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Seeking ways of
securing more
community wealth
building opportunities
across Argyll and Bute
and supporting
communities to gain
maximum benefit from
developments in their
area.
• Arrange community wealth building
meeting with anchor organisations
within Argyll and Bute. Share
Council’s contract plan with them to
determine if any collaborative
opportunities, publish our contract
plan on website. Share our
community benefit guidance, and
wishlist with them to enable best
practice to be rolled out across all
of Argyll and Bute public sector
organisations. Invite our anchor
organisation colleagues to
collaborate with us on appropriate
contracts/frameworks.
• Contracts
awarded to local
suppliers (%) –
Target 20%. 
For 2023/24 the %
was 17.8%. For
2024/25 (Q1&Q2)
– 18.3%
As this % includes
all contracts,
whether a local bid
was submitted or
not we also report: 
-Tenders won by a
local supplier
where a local
supplier has
placed a bid (%) -
no target.
For 2023/24 the %
was 59.5%. For
2024/25 (Q1&Q2)
– 65.2%
-Local suppliers
bidding for
business with the
council (% of bids
received) - Target
20%.
For 2023/24 the %
• Community wealth
building event took
place.  A Community
Wealth Building Action
Plan is currently being
prepare by specific
partner organisations
within the Argyll and
Bute Community
Planning Partnership
aligned to the key
content within the draft
CWB Bill published on
20th March 2025 by the
Scottish Government
which was out for
consultation until 23rd
May 2025 on whether it
should become an Act
of Parliament.
• Our contract plan was
shared and as a result
collaborative contracts
are taking place with
our partner
organisations. Our
contract plan is
published on the
website to allow local
Page 160

Page 161

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
was 15.2%.  For
2024/25 (Q1&Q2)
– 14.4%
-Increase the
number of
community
benefits that are
delivered through
contracts we
award locally – no
target.
For 2023/24 – 74
community
benefits achieved. 
For 2024/25
(Q1&Q2) – 31
-Local spend – no
target.
For 2023/24 local
spend was 35.8%.
For 2024/25 (Q1)
– 28.4%
businesses to see what
we are looking to buy
in the coming year
ahead. Our community
benefit guide has been
shared with our
community wealth
building partners along
with a link to our
wishlist. Further
engagement has taken
place at area
community planning
partnership meetings.
• Contracts awarded to
local suppliers (%) –
Target 20%. 
2024/25:18.7%
As this % includes all
contracts, whether a
local bid was submitted
or not we also report: 
-Tenders won by a
local supplier where a
local supplier has
placed a bid (%) - no
target.  2024/25:69.8%
Page 161

Page 162

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
-Local suppliers
bidding for business
with the council (% of
bids received) - Target
20%.  2024/25:13.5%
-Increase the number
of community benefits
that are delivered
through contracts we
award locally – no
target.   89 community
benefits were delivered
via our council
contracts in 2024/25
compared to 74 in
2023/24 which is an
increase of 15. 
-Local spend – no
target. The total
Procurement-related
spend with known local
suppliers in 2024/25
was £72.7m. The local
procurement-related
spend has increased
from the previous two
years, (£65.7m in
2023/24 and £60.8m in
2022/23).
Page 162

Page 163

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Seeking to maximise
scope for community
involvement and
participation, including
exploring the role that
community transfers
can play. 
•  Argyll and Bute Community
Planning Partnership to agree the
actions for the ABOIP priority
outcome of Community Wellbeing,
which has a long-term objective to:
support community cohesion, the
sustainability of community services
and a voice in collective decision
making. 
• Explore the potential to have the
Community Development Team
work in collaboration with Estates
Team to ensure effective
Community Asset Transfer, dealing
with requests from community
groups in a timeous manner and
providing comprehensive support.
• An Engaging Communities
Framework will be developed and
launched to facilitate and support a
corporate approach to community
engagement, including the
development of training and support
materials
• Members of the Community
Planning and Community
Development team will undertake
training in Art of Hosting techniques
to enable a suite of practical
methods of community engagement
•  Community
Planning
Partnership
agreement and
endorsement of
Community
Wellbeing actions. 
• Community Asset
Transfer requests
will be considered
and processed
according to the
requirements of
section 5 of the
Community
Empowerment
(Scotland) Act
2015. The
Community Asset
Transfer web page
will be updated as
required with an
annual report
produced and
uploaded for
2024/25.
• Launch of the
Engaging
Communities
Framework with
• In December 2024, the
CPP agreed a set of 6
actions under the
priority outcome of
Community Wellbeing. 
• Successful trial project
of Community
Development team and
the Estates team
collaboration
throughout 2024-25
ensuring the
Community Asset
Transfer process
worked effectively
ensuring requests from
community groups
were dealt with
timeously with
comprehensive
support. The
Community Asset
Transfer web page has
been updated with
detailed information on
the process for
Community Transfer
Bodies and an annual
report has been
produced for 2024/25.
Page 163

Page 164

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
to be incorporated into professional
practice.
appropriate
training and
support materials
developed to
enable a corporate
approach.
• Members of the
Community
Planning and
Community
Development
team will
successfully
undertake training
in Art of Hosting
techniques, will
cascade learning
to the full team
and will use these
techniques in
community
engagement
practice.
• Engaging Communities
Framework developed,
launched in January
2026 with online
training on LEON for
staff.
• Staff members have
successfully trained in
Art of Hosting,
contributing to the
development of a
Community of Practice
in Argyll and Bute.
Skills developed for
use in community and
partnership settings
shared with colleagues
i.e. Heretohearyou, and
practical application of
techniques has
encouraged new forms
of community
participation.
Potential and growth; turning opportunities into reality    
Economic development    
Page 164

Page 165

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Achieving sign-off of the
Rural Growth Deal
business and cases
and begin delivering
priority projects like The
Marine Industry
Training Centre, UAV
Drone Hub and
Seaweed Academy. 
• Deal signed on
10th March 2025.
Conditional
endorsement of
Rothesay Pavilion
FBC achieved;
FQ4 grant claims
submitted to
Central
Government.
• Rural Growth Deal
signed on 10th March
2025.  Drawdown of
2024/25 Q4 funding to
support Rothesay
Pavilion.  Most OBC’s
now endorsed and
FBC’s being
progressed for KSS
and Tobermory
Housing projects. 
Further work
necessary to deliver
Action Plan and
achieve full
endorsement of
Rothesay Pavilion
FBC.
Securing of Levelling
Up funding for projects,
including Argyll and
Bute Western Seaboard
Marine Gateways
Initiative, Whisky
Islands and Lorn
Economic Growth
Zone.
• Funding re-branded as Community
Regeneration Partnership following
change in UK Government. 
£20.3m of funding committed to
Argyll and Bute and negotiations
are on-going with UKG and
external partners to agree final
priority projects.  All funding
requires to be committed by
2026/27 and as such, projects
require to demonstrate
deliverability within these
• Confirmation of
funding via
Community
Regeneration
Partnership;
Support UKG
fieldwork visits.
Identify a long-list
of project options.
• These applications
were not successful,
but Community
Regeneration
Partnership funding,
circa £20m, was
secured by Argyll and
Bute Council.
Page 165

Page 166

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
timescales.  UKG will undertake a
business case for Ministerial sign
off.
Implement £4.5m Argyll
and Bute UK Shared
Prosperity Fund
Investment Plan.    
• The Argyll and Bute
UK Shared Prosperity
Fund (UKSPF)
Investment Plan,
2022-2025 has now
been concluded; all
project spend had to
be completed by the
end of March 2025
and all final claims to
the UK Government
need to be submitted
by the 1st May 2025.
• A final transition year
of UKSPF has been
agreed for 2025/26.
The Transition Year
UKSPF Investment
Plan (further additional
activity for current
projects in the 2022-25
plan) was approved by
the Policy and
Resources Committee
on 20th February 2025
and the MOU was
signed between the
Page 166

Page 167

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
UK Government and
Argyll and Bute
Council mid-March
2025.
Complete site
development of
Helensburgh Waterfront
project securing long-
term economic benefit.
• Development of site. • Completion of
Helensburgh
Waterfront
Development.
• Marketing of the site
completed and
preferred developer
selected. Site
investigations
completed and utility
connections secured.
Awaiting outcome of
Judicial Review which
was heard in Court of
Session on 4th July –
cannot proceed until
verdict passed.   
Deliver the £15m
Campbeltown Flood
Prevention Scheme.
• A multi-element £15–15.9m
Flood Protection Scheme for
Campbeltown to reduce risk
from
the Millknowe and Balgreggan B
urns and from local surface-
water flooding. To be delivered
as four main work packages: 
1. Millknowe flood storage
reservoir (flood-storage
basin/earthworks). 
2. Upsizing/renewal of
the Dalaruan Street culvert. 
•  Delivered
as
designed: the
key engineered
elements (flood
storage
at Millknowe,
culvert
upsizing, SuDS
at The
Meadows, and
the Burnside
• The Campbeltown
Flood Protection
Scheme was complet
ed and certified in
May 2024, transitioning
into the defects and
monitoring phase. 
• The Property Flood
Resilience
(PFR) programme
continues into 2025–
26, focusing on
Page 167

Page 168

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
3. Surface Water Management
/ SuDS at The Meadows. 
4. Works at Burnside Square
(public-realm + flood
interventions). 
In addition, some property-level
flood protection measures to be
provided to selected
properties. Argyll and Bute
Council+1 
• Programme / timing:
construction phases to be
completed through 2023–early
2024 with the council reporting
the project on course to be
complete around February
2024, with additional requested
works and follow-up items into
later 2024. 
Square
interventions).
• Hydraulic
modelling and
design quality
• Communit
y / co-
benefits.  
property-level
protection. 
• Revised total cost:
£15.925 million (up
from £15.215 m). 
• Main works
delivered: Millknowe fl
ood
storage, Dalaruan culv
ert, Burnside Square
improvements,
and SuDS at The
Meadows. 
• Benefits noted:
reduced flood risk,
environmental
resilience, and
community economic
benefit. 
• AECOM’s detailed
hydraulic modelling
was used to design the
fluvial and surface
water elements, and
sources indicate the
design intent was
aligned with delivering
improved flood
resilience for the town.
That modelling
Page 168

Page 169

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
supports the
expectation that the
interventions will
materially reduce flood
risk from Millknowe/
Balgreggan and from
surface water. (Note:
modelling = projected
performance; real-
world success is best
judged after significant
storm events and
monitoring.) Institution
of Civil Engineers
(ICE)+1 
• Community-benefit
activities were reported
in Sept 2024 Argyll and
Bute Council+2Argyll
and Bute Council+2 
•  Funding & cost:
original secured
funding was
~£15.215m with 80%
Scottish Government
support and 20%
council contribution;
later estimates in 2024
put the projected cost
slightly higher (c.
Page 169

Page 170

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
£15.9m) and an extra
~£710k was listed
for additional works
Regenerate the
waterfront of Ardrishaig.
•  • Support on-going
negotiations with
potential
developers of
Gleaner Oil Site.
Ardrishaig North Public Realm
works were completed April
2023. Negotiations are on-
going with potential developer
at former Gleaner Oil Site. 
Note this site is owned by
Scottish Canals. £250k of
funding available via Tarbert
and Lochgilphead
Regeneration fund to support
remedial works at Gleaner
site subject to an endorsed
business case.
Driving forward
additional strategic
economic development
projects including
progression of the
Dunbeg housing,
commercial and
infrastructure projects
and the North Lorn
Economic Growth Zone
through the Lorn Arc
Tax Incremental
Finance (TIF) scheme.
• Multiple planning applications
submitted for Housing /
infrastructure and commercial area
at Dunbeg. Determination expected
by spring 2026.
• Planning Applications submitted
and approved for business
development and infrastructure at
Oban Airport.
• TIF infrastructure element of FBC at
Oban Airport Approved by Council
and Scottish Gov. 
•   Agreement
reached with
Scottish Gov to
both extend the
TIF income stream
period by 10years
and allow for the
retention of
income prior to
project initiation. 
• This significantly
derisks the TIF
projects and gives
confidence to the
• Oban Airport TIF
element of business
park agreed – awaiting
finalised costs for non
TIF elements to be
agreed by Full Council
in Nov 2025. Once that
takes place the project
will move into the
implementation phase.
• Dunbeg once planning
applications have been
determined, assuming
approval, the
Page 170

Page 171

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Council to make
investments.
infrastructure design
and detailed costing
phase will begin. This
will inform the final
FBC which is expected
to be presented to
Council’s P&R
Committee early to mid
2027.
Implement
Conservation Area
Regeneration Scheme
(CARS) Projects in
Dunoon, Lochgilphead,
Tarbert and
Helensburgh.
• Proposed Heritage and Place
scheme being developed for
Tarbert.  This will require Council
match funding of circa £635k over 5
years. Development phase
currently being progressed with
formal bids scheduled to be
submitted in August 2025.
Lochgilphead CARS in delivery
stages and due to complete in
March 2026.  At least 4 priority
buildings will be completed in
Lochgilphead.  Helensburgh CARS
is also in the delivery stages and
works to the first two priority
buildings commenced in September
2024. 
• Dunoon now complete.
• Continued
delivery of
Lochgilphead and
Helensburgh
CARS schemes;
• Complete Dunoon
CARS
• Progress Tarbert
HPP
Development
Phase.
• Lochgilphead in final
stages of delivery with
works to priority
buildings complete. 
Helensburgh is
ongoing with all priority
buildings now on-site. 
Funding bids have
been submitted to
NHLF and HES for an
HPP scheme in Tarbert
and funding
announcements will be
made in early 2026.
Maximising community
economic and
employment
The Council’s role is a consultee in this
project which is being led by Scottish
Power Renewables.  
This is led by Scottish Power
Renewables and is going
through consultation stage. 
Page 171

Page 172

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
opportunities from the
Islay Scotwind offshore
wind project.
The Council continues to
engage with the developer via
forums such as ABRA.  The
Council are also continuing to
monitor community benefit
opportunities linked to
renewable developments.  We
have also been engaging with
developers around potential
operations and maintenance
opportunities aligned with this
development.
Preparing an options
appraisal for
implementation of a
transient visitor levy.  
• A draft Visitor Levy
(VL) Scheme will
be supported by
impact
assessments align
to the impact on
businesses
providing
accommodation,
communities,
visitors and the
council who will
need to collect a
levy if as VL
Scheme is
introduced in
across Argyll and
Bute. The options
• The formal consultation
on a draft Visitor Levy
(VL) Scheme for Argyll
and Bute will
concluded on
Thursday, 10th April
2025. 
It is a statutory
requirement to prepare
a Consultation Report,
which will include
updated impact
assessments as
outlined in Appendix 2
of the Special Council
paper, 20th December
2024.
Page 172

Page 173

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
are to introduce a
levy or not, further
to a formal 12-
week consultation
period from
January to March
2025, again if the
consultation is
approved by
elected members.
The content of this
Consultation Report, to
be prepared by
external consultants,
will provide
recommendations if a
VL Scheme should be
introduced across
Argyll and Bute based
on the evidence
gathered during the 12-
week public
consultation.
Commercial services; making assets work now    
Increasing commercial
development of
business and retail
space, including the
Kilmory Industrial Park,
and identifying other
opportunities wherever
possible.
• Develop business cases for 
* Kilmory Industrial Park 
* Kilarrow House, Bowmore 
* Lorn House, Oban
• Complete
construction of
Kilmory Business
Park.
Completion of
business cases for
Lorn House and
Kilarrow House.
• Kilmory Business Park
under construction with
forecast completion in
Quarter 1 2026
• Killarow and Lorn
House being
considered for housing
delivery options.
Exploring additional
commercial
opportunities at Oban
Airport.
• Develop business case, apply for
planning consent for business units.
• Completion of
Detailed Business
Case for Oban
Airport.
• FBC (contractor
verified costs)
completed, planning
consent received, , Tier
1 contractor appointed,
design team appointed,
Page 173

Page 174

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
TIF & Community
Regeneration
Partnership funding
approved.
• 26th November Council
meeting for Full
Business Case
approval and award of
contracts.
Delivering the Our
Modern Workspace
project (OMW),
rationalising the council
estate and facilitating
hybrid working
solutions.
• Progress delivery of OMW project
in Lochgilphead, Oban and
Rothesay.
• Completion of
physical works at
Rothesay and
Oban
Production of an
approved by ELT
Phasing Plan for
changes to offices
in Lochgilphead
and Ardrishaig.
• Works at Rothesay and
Oban are complete.
• Dunoon works are
underway at Argyll
House with completion
forecast February
2026.
• Design work at
Lochgilphead and
Ardrishaig progressing
Leading the
development and
creation of
Craigendoran Business
Park as a business,
engineering and
innovation hub.
• Site investigations to be completed.
Site infrastructure and utilities to be
designed and costed.
• Completion of the
pre-development
investigative
works to confirm if
the site is suitable
and viable for
development
• Site investigations
completed,
infrastructure and
utilities designed and
costed. Outcome has
identified challenges
with site utilities and
flood risk requiring
further investigation.
Page 174

Page 175

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Exploring opportunities
for sharing services
where possible - both to
help grow our income
through providing our
expertise and
enhancing service
delivery in communities
where we need to
source options from
elsewhere.
• Implementation of new shared
management structure with HSCP
in relation to Hostels and care
homes for catering and cleaning.
• Completion of 1
year review of
shared
management
structure.
• The HSCP Shared
Management Project
concluded at the end of
June 2025. While
elements of the project
were successful, HSCP
SLT made the decision
that a return to pre-pilot
arrangements would be
more sustainable.
Driving down further
our own carbon
emissions, achieving
net zero by 2045 and
exceeding our target of
a 75% reduction by
2030, building on our
good track record in
relation to combatting
climate change,
through the delivery of
our Decarbonisation
Plan.
• Progress Argyll and Bute
Decarbonisation Plan for 2022-
2025.
• Commission new
Decarbonisation
Plan (Routemap to
Net Zero).
• Draft under
development with
Climate Change Board
Securing Carbon
Literate Organisation
status by the end of
2023, including
completion of the rollout
of carbon literacy
• Securing Carbon Literate
Organisation by the end of 2023
Deliver more training - application
of Carbon Literate Organisation
submitted and await outcome.
• Completed  • Complete.  Exploring
renewal and
enhancement options
Page 175

Page 176

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
training to all
councillors. 
Partnership and Action - everyone has a part to play in Argyll and Bute’s success 
In our Priorities for the Council Term 2022 to 2027, we set out our areas for action to deliver our vision for Argyll and Bute. There
are elements of that vision which require action from other agencies at all levels - from our communities right up to national
government. We will commit to working in partnership wherever we need to as well as calling on others, with responsibility, to take
the action that is required to safeguard Argyll and Bute’s success. This included: 
1. Continuing to build up our strong track record in partnership working and seeking new ways of working with communities,
other organisations, and the third and private sectors.  
2.  Continuing to work in partnership with further education and higher education providers in Argyll and Bute to ensure young
people have access to high quality innovative educational opportunities that support local employers and the Argyll economy.
3.  Lobbying for support for the higher-than-average energy costs faced by Argyll and Bute communities.  
4.  Pressing the case for retaining delivery of care services locally, where community knowledge, relationships and experience
are best placed to identify and meet local needs and local accountability.  
5.  Calling for funding support to tackle challenges in local social care delivery - including recruitment, retention and
development of care staff in communities - rather than centralisation of services.  
6.  Continuing to call for planning, construction and opening of the replacement route at the Rest and Be Thankful within the life
of this Scottish Parliament. 
7.  Working in partnership with the Rothesay Pavilion Charity Trust to lobby for funding to complete the refurbishment of the
Pavilion.  
8.  Seeking additional funding support to address the unprecedented severe weather damage to the sea defences supporting
Bute’s main island roadway at Ardbeg.  
9.  Working with the Community Planning Partnership to develop a Climate Change Strategy for the region as a whole.  
10.  Adding our voice to those of our local government colleagues across Scotland to call on national government for fair funding
settlements which enable councils to deliver the services that matter to communities and reinforcing the need for recognition
of the vital contribution that local government makes to national priorities and Scotland’s overall success.   
Page 176

Page 177

11.  Delivering the Argyll and Bute Employability Partnership Delivery Plan for 2024-25 through working in partnership with third
sector delivery partners. – Update October 2025 – The ABEP Delivery Plan has concluded with hard stop spend at the end
of March 2025.  The No One Left Behind (NOLB) grant offer letter for 2025/26 has been received from the Scottish
Parliament and a revised Annual Investment Plan, which will include third sector partner delivery, was submitted by 30th April
2025.  There was no Scottish Government requirement to prepare a more detailed ABEP Delivery Plan for 2025/26 (just an
Investment Plan).  However, the ABEP members still wanted to put in place a local and shortened ABEP Delivery Plan,
which was prepared further to an ABEP workshop session on 20th May 2025 and will hopefully be endorsed by the Argyll and
Bute CPP Management Committee on 5th December 2025.   
Page 177

Page 178

This page is intentionally left blank

Page 179

ARGYLL AND BUTE COUNCIL  AUDIT AND SCRUTINY COMMITTEE 
FINANCIAL SERVICES  16 DECEMBER 2025 
INTERNAL AUDIT REPORTS TO AUDIT AND SCRUTINY COMMITTEE 2025/2026 
1. EXECUTIVE SUMMARY 
1.1 There are eight audits being reported to the Audit and Scrutiny Committee.     
1.2 The table below provides a summary of the conclusions for the audits performed.
The full reports are included as appendices to this report. 
Audit Name Level of
Assurance
High
Actions
Medium
Actions
Low
Actions
VFM
Actions
School Residential Trips Limited 4 2 0 0
Building Cleaning  High 0 0 1 0
Directed Self Support (Direct
Payments) Reasonable 0 6 0 0
ICT Disaster Recovery Substantial 1 3 2 0
Oban Airport High 0 0 0 0
HSCP – Governance Arrangements High 0 0 2 0
HSCP – Partnership Working High 0 0 3 0
HSCP – Workforce Planning  Reasonable 0 7 0 0 
1.3 Internal Audit provides a level of assurance upon completion of audit work. A
definition for each assurance level is documented in each audit report. 
2. RECOMMENDATIONS 
2.1 Audit and Scrutiny Committee to review and endorse this summary report and
the detail within each individual report. 
3.  DETAIL 
3.1 A high level summary of each completed audit report is noted below: 
School Residential Trips: this audit provided a limited level of assurance. 
This means that internal control, governance and the management of risk are
displaying a general trend of unacceptable residual risk and placing system
objectives at risk. Weakness must be addressed within a reasonable timescale
with management allocating appropriate resources to the issues raised.  The
Council has procedures in place supported by a suite of Education
Management Circulars (EMCs) for school residential trips, however, these
require to be updated to incorporate the Scottish Government’s best practice
Page 179 Agenda Item 11a

Page 180

“Going Out There” framework and address some identified gaps. Head
Teachers or nominated deputies check and approve arrangements for school
residential trips and ensure staff are supported when organising, additionally,
clerical staff maintain records of trips and carry out limited checks, it was noted
that limited monitoring arrangements are in place.  Some schools have used
external companies to help with the provision and planning of school trips
without consulting the Procurement, Commercial and Contract Management
Team (PCCMT).  A training needs analysis and suitable training are required
to be provided when undertaking school trips, however, this has not been fully
undertaken.  All school staff receive the required child protection information
and training and individuals in regulated roles hold the required level of
Disclosure Checks, however, testing identified that during home stay trips,
PVG checks of hosts were not undertaken in line with Council procedures. 
Building Cleaning: this report provided a high level of assurance. This means
that Internal control, governance and the management of risk are at a high
standard. Only marginal elements of residual risk have been identified with
these either being accepted or dealt with. A sound system of control designed
to achieve the system objectives is in place and being applied consistently.
The Council’s Cleaning Service has arrangements in place to carry out regular
cleaning of establishments where this has been requested. Each
establishment has specific cleaning staff allocated to undertake a pre-planned
schedule of cleaning at an agreed frequency.  Casual staff are retained in
locations to provide cover for staff annual leave and absence.  Changes to the
Disclosure Checks requirements affect some cleaning staff who work in what
are deemed regulated roles e.g. schools and nurseries.  The induction pack
should be reviewed to ensure that it contains up to date links to key
documents/ policies, reflects current working practices and if applicable, any
changes to processes required as a result of the change to the PVG scheme.
There are detailed cleaning schedules and standards to support the cleaning
of council premises, these are based on industry standards. Monitoring of
cleaning in premises is undertaken by the cleaning services manager who
conducts regular reviews and audits of cleaning practices against established
benchmarks such as the British Institute of Cleaning Science (BICS) cleaning
standards. Reporting of performance and issues for the cleaning services are
discussed at the Commercial Services Teams meetings. No reports are
currently provided to Council Committees. 
Directed Self Support (Direct Payments): this report provided a reasonable
level of assurance. This means that Internal control, governance and the
management of risk are are broadly reliable. However, whilst not displaying a
general trend, there are areas of concern which have been identified where
elements of residual risk or weakness may put some of the system objectives
at risk. Policies and procedures are in place and are up to date.  A policy and
procedural document – Self Directed Support, Direct Payments Option 1,
Policy and Procedural Guidance for Staff and Managers is available, the most
recent version, V2.5 and is dated May 2025.  A leaflet – Option 2 Individual
Service Funds (ISF) provides an outline guide to the four options available to
clients, providing further details for Option 2 which allows the client to direct
Argyll and Bute Council to commission services from a support provider on
their behalf.  Information is available on the Council website. Policies,
procedures, guidance documents and other relevant information is available
for staff on the HSCP SharePoint site. Training is provided by the Self-
Directed Support Officer.  Processes and procedures are in place for the
checking of financial records which require to be maintained by those in
Page 180

Page 181

receipt of Direct Payments.  A review timetable has been established and the
Finance Administration Officer (AWI) has responsibility for undertaking these
reviews.  We identified that there was a need to make clearer within the
agreement that funds may be required to be returned in certain circumstances.
The Guidance document does not provide clear guidance on the
circumstances which would give rise to the requirement to ‘top up’ the Direct
Payment bank account or circumstances whereby accumulated funds require
to be returned. Supported Person’s financial records highlighted that financial
reviews had not been undertaken in accordance with the agreed timetable and
there remains a significant backlog of cases to review. Care plans require to
be reviewed timeously and to make sure that the supported persons needs are
being met. 
Oban Airport: Our overall audit opinion for this audit is that we can take a
high level of assurance. This means that internal control, governance and the
management of risk are at a high standard. Only marginal elements of residual
risk have been identified with these either being accepted or dealt with. A
sound system of control designed to achieve the system objectives is in place
and being applied consistently. The audit covered 6 of the 25 airport operating
instructions within the aerodrome operating manual (AOI 16-20 & 24) and all
were found to be satisfactory. The Manual is updated on an annual basis, and
no audit issues were raised. 
Information and Communication Technology (ICT) Disaster Recovery
(Exempt): This report is exempt from publication under paragraph 14 of part 1
to schedule 7A of the Local Government (Scotland) Act 1973 – “Any action
taken or to be taken in connection with the prevention, investigation or
prosecution of crime”. 
Health and Social Care Partnership (HSCP) Governance Arrangements
(For Noting Only): this audit provided a high level of assurance.  This means
that Internal control, governance and the management of risk are at a high
standard. Only marginal elements of residual risk have been identified with
these either being accepted or dealt with. A sound system of control designed
to achieve the system objectives is in place and being applied consistently, in
particular the report highlights the following strengths and areas for
improvement. The HSCP governance framework is well-documented, formally
approved, and reviewed in accordance with statutory and good practice
standards, additionally, it promotes transparency, stakeholder accessibility,
and clear documentation of decisions. The governance structure and
responsibilities within the HSCP are clearly laid out in governance documents
and reflect good practice.  Strategic plan performance and audit
recommendations are actively monitored. Governance interactions between
the Integrated Joint Board (IJB), Council, and National Health Service (NHS)
Highland are well-established. While role clarity is strong, additional
improvements could be made by enhancing accessibility and communication
of these responsibilities and training expectations. A governance roles guide
and organisational chart should be developed to clarify officer responsibilities
and committee reporting lines. Information on IJB member training and
induction should be published to enhance transparency for stakeholders and
potential board members. 
Health and Social Care Partnership (HSCP)  Partnership Working (For
Noting Only): this audit provided a high level of assurance.  This means that
Page 181

Page 182

Internal control, governance and the management of risk are at a high
standard. Only marginal elements of residual risk have been identified with
these either being accepted or dealt with. A sound system of control designed
to achieve the system objectives is in place and being applied consistently, in
particular the report highlights the following strengths and areas for
improvement. Argyll and Bute HSCP operate within a clear and effective
governance framework established by the Integration Scheme, which defines
statutory responsibilities, decision-making structures, and operational
processes between Argyll and Bute Council and NHS Highland. Evidence from
recent Integrated Joint Board (IJB) minutes, Chief Officer reports, and the
Direction Log confirms active participation, structured collaboration, and
compliance with legislative expectations across both partners. IJB meeting
records and the Direction Log demonstrate transparent, documented, and
jointly actioned decision-making. The approval process for the Joint Strategic
Plan further confirms collaborative planning and shared accountability. Argyll
and Bute HSCP and Council demonstrate strong alignment through shared
strategic goals embedded in key planning documents such as the Joint
Strategic Plan, Commissioning Strategy, and Digital Modernisation Strategy.
Joint planning is facilitated by statutory structures like the Strategic Planning
Group and Locality Planning Groups, with clear partner and stakeholder
involvement. Performance against shared objectives is actively monitored
using structured reporting and risk management frameworks. Argyll and Bute
HSCP have robust governance arrangements for dispute resolution, with
clearly defined escalation procedures set out in the Integration Scheme and
Standing Orders. HSCP should continue to develop existing workforce
performance monitoring arrangements so that key performance indicators
(KPIs) and red, amber and green (RAG) assessments remain clearly linked to
strategic objectives and risks that IJB developed in partnership with both
employing bodies. To strengthen assurance, the HSCP should consider
embedding awareness of escalation and dispute resolution routes from the
Integration Scheme into induction for senior managers and key officers to
ensure consistent understanding across the partnership and with wider
partners. HSCP should capture and review recurring themes or patterns from
informal partnership challenges to support organisational learning and provide
assurance to the IJB that risks are being managed proactively. 
HSCP Workforce Planning (For Noting Only): this report provided a
reasonable level of assurance. This means that Internal control, governance
and the management of risk are are broadly reliable. However, whilst not
displaying a general trend, there are areas of concern which have been
identified where elements of residual risk or weakness may put some of the
system objectives at risk. Workforce Plan 2022–2025 aligns clearly with
Scottish Government guidance DL (2022)09, the Joint Strategic Plan, Digital
Modernisation Strategy, and National Workforce Strategy. Workforce planning
responsibilities are well embedded within the Integration Scheme and
committee Terms of Reference. Routine reporting of workforce matters occurs
through quarterly workforce reports and IJB papers. Workforce risks such as
recruitment/retention and remote/rural challenges are clearly reflected in the
Strategic Risk Register, reviewed biannually by Audit and Risk Committee and
Integrated Joint Board. Multi-agency involvement is strong (ABC, NHSH and
third sector) in committees and planning groups. There is currently no
standalone annual Workforce Plan progress/refresh report is produced,
meaning the IJB lacks a clear annual overview aligned to SG guidance DL
(2024)33. A concise “workforce at a glance” KPI summary is not currently
provided, limiting quick visibility of key workforce indicators for decision-
Page 182

Page 183

makers. There is no single consolidated Workforce Plan action tracker,
resulting in inconsistent ownership, missing baselines/targets, and difficulty
monitoring progress. The Scottish Government Appendix 1 ‘Indicative Content
Checklist’ (DL 2022/09) is not currently completed or retained, and should be
fully completed and documented as part of future Workforce Plan refreshes.
There is currently no costed funding map jointly across NHS Highland and
Argyll & Bute Council Finance/HR, setting out estimated costs, named funding
sources/budget codes, phasing, and expected benefits/savings for each
priority action. There is no consolidated agency and supplementary staffing
dashboard integrating service-level spend, FTE, trends, key drivers and
ownership, meaning workforce reporting does not provide the level of
oversight required by the IJB. There is no consolidated Finance–HR
dashboard bringing together agency and supplementary staffing data (service-
level spend, FTE, trends, key drivers and named owners), limiting the clarity of
reporting and oversight available to the IJB. 
4. CONCLUSION 
4.1 Management has accepted each of the reports submitted and have agreed
responses and timescales in the respective action plans. 
5. IMPLICATIONS 
5.1 Policy – None 
5.2 Financial – None 
5.3  Legal – None 
5.4  HR – None 
5.5 Customer Service – None 
5.6 Risk – The implementation of recommendations contained in audit reports
may help mitigate the risk to the Council  
5.7 Climate Change – None 
5.8  Fairer Scotland Duty – None 
5.9 Equalities - protected characteristics – None 
5.10 Consumer Duty – None 
5.11 Island Communities – None 
5.12 Children’s Rights and Wellbeing – None 
Paul Macaskill
Chief Internal Auditor
16 December 2025 
For further information contact: 
Paul Macaskill, Chief Internal Auditor
Tel:  01546 604108
Email: paul.macaskill@argyll-bute.gov.uk 
APPENDICES 
1. School Residential Trips
2. Building Cleaning
3. Directed Self Support (Direct Payments)
4. Oban Airport
Page 183

Page 184

5. HSCP – Governance Arrangements (For Noting Only)
6. HSCP – Partnership Working (For Noting Only)
7. HSCP – Workforce Planning (For Noting Only) 
Page 184

Page 185

Argyll and Bute Council
Internal Audit Report
November 2025
FINAL
High Medium Low VFM
Number of
Findings
4 2 0 0
Process for School
Residential Trips
Audit Opinion: Limited
Page 185

Page 186

2
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
Contents
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Key Dates ................................................................................................................................................ 4
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 5
3. Detailed Findings ............................................................................................................................ 8
Appendix 1 – Action Plan ..................................................................................................................... 15
Appendix 2 – Audit Opinion ................................................................................................................. 18
Contact Details
Internal Auditor: Annemarie McLean
Telephone: 01700 501354
e-mail: annemarie.mclean@argyll-bute.gov.uk
www.argyll-bute.gov.uk
Page 186

Page 187

3
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2025, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal control and governance in relation to the process for school residential visits.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with council officers and the information available at the time
the fieldwork was performed. The findings outlined in this report are only those which have
come to our attention during the course of our normal audit work and are not necessarily all the
issues which may exist. Appendix 1 to this report includes agreed actions to strengthen internal
control however it is the responsibility of management to determine the extent of the internal
control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy, and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. Scotland’s outdoor environment offers motivating, exciting, varied, relevant and easily
accessible activities from pre-school years through to college and beyond. Through Curriculum
for Excellence, and Learning for Sustainability, the Scottish Government endorses the value of
children and young people enjoying positive learning and play experiences in a wide variety of
settings from galleries and museums to woodlands, parks and wild natural spaces, as well as
planned adventure and residential experiences.
5. An enjoyable, creative, challenging learning journey helps children and young people learn by
experience and grow as confident and responsible citizens who value and appreciate their local
area and the wider environment of Scotland, which includes spectacular landscapes, rich natural
heritage and a diverse built environment including landmarks of international significance, as
well as further afield.
6. Excursions and educational visits are an important and valuable part of our educational system.
Getting more children and young people out of the traditional classroom and into the real world,
by giving access to cultural experiences and outdoor learning and play opportunities provides
invaluable life experiences.
7. A residential experience can be an extremely valuable learning opportunity and may be part of
the progressive outdoor learning or cultural experiences provided for young people. Residential
visits include any form of overnight stay regardless of the type of accommodation.
Scope
8. The scope of the audit was to determine if the current processes are embedded prior to the
expansion of residential trips which will be available to all children, as outlined in the Terms of
Reference agreed with the Head of Education: Performance and Improvement on 03 July 2025.
9. It was agreed that the purpose of the audit was to identify areas for process improvement, its
applicability to be applied consistently across the Council’s school estate rather than highlighting
Page 187

Page 188

4
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
specific issues at an individual school level. A detailed list of issues arising will be provide to the
Service and the recommendations for improvement contained within it, reflects this agreed
focus on aiding the Council’s preparations for the expansion of residential trips. 
10. The Legislation regarding this expansion is still being considered and the timescales agreed for
completing the recommendations takes cognisance of this.
Key Dates
11. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below.
Exhibit 1 – Key Dates
Stage Actual Date
Terms of Reference agreed 03 July 2025
Fieldwork Commencement 12 August 2025
Draft Report issued 10 November 2025
Management Comments received 18 November 2025
Final Report issued 18 November 2025
Audit and Scrutiny Committee 16 December 2025
Risks
12.  The risks considered throughout the audit were:
• Audit Risk 1: Processes and procedures for school residential trips are not effective.
• Audit Risk 2: Monitoring arrangements do not provide sufficient oversight of school
residential trips.
• Audit Risk 3: Staff have not been provided with appropriate information, instruction and
training regarding their responsibilities related to school residential trips.
Audit Opinion
13. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
14. Our overall audit opinion for this audit is that we can take a limited level of assurance.  This
means that internal control, governance and the management of risk are displaying a general
trend of unacceptable residual risk and placing system objectives are at risk. Weakness must be
addressed with a reasonable timescale with management allocating appropriate resources to
the issues raised.
Recommendations
15. We have highlighted four high priority recommendations and two medium priority
recommendations where we believe there is scope to strengthen the control and governance
environment. These are summarised below:
Page 188

Page 189

5
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
• Education Management Circular 3.25 and its appendices, should be reviewed, clarified
and updated to contain a flow chart and checklist section on key tasks which can be used
to document and evidence compliance with relevant legislation. 
• Education Management Circular 3.14 and its appendix should be reviewed and updated
with the assistance of Legal Services.
• Education Management Circular 1.26 and its appendices, should be reviewed, clarified
and updated to ensure it takes cognizance of best practice contained in the “Going Out
There” Framework.
• Appropriate corporate monitoring arrangements should be established and
implemented.
• Consideration should be given to the Procurement and Commercial Contract
Management Team (PCCMT) being consulted prior to making bookings/ entering into an
agreement with external providers for school residential trips.
• A training needs analysis should be undertaken, and suitable training provided, for Head
Teachers and staff, including clerical, involved in the processes of planning and
undertaking of school residential trips. 
16. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
17. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.  
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to Risk Assessment Summary Conclusion
1 Procedures for
school residential
trips are in place, up
to date and take
cognisance of best
practice.
Audit Risk 1 Reasonable • The Council has procedures in
place for school residential trips.
These are not all up to date and
the Council has not yet adopted
the Scottish Government best
practice “Going Out There”
framework.  
• There are five Education
Management Circulars (EMCs) that
provide guidance and instruction
relating to the procedures for
planning and undertaking of school
residential trips. 
• The Service is aware that the EMCs
require updating and has
established a working group to
facilitate the Council’s adoption of
the “Going Out There” best
practice framework.
• Three of the EMCs need updating
to reflect current working practices
and identified gaps in the
Page 189

Page 190

6
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
procedures. The roles and
responsibilities of all staff involved
in the process are not stated and
linkages between the circulars
could be clearer. 
• There are no record retention
periods stated for key documents
which has led to inconsistent
record keeping. 
• When enquiring with schools about
the trips that they have
undertaken, some have used
external companies to help with
the provision and planning of the
trips. Consideration should be
given to PCCMT being consulted
prior to making bookings and/or
entering into an agreement with
external providers for school
residential trips.
• Procedures are not easily
accessible to staff as the end-to-
end process for planning school
residential trips are not contained
in one document. When updating
the circulars there would be
benefit to considering including a
flow chart providing a visual
overview and a checklist as these
could help streamline and
standardise the processes, whilst
aiding better overall understanding
and improving consistency of
approach.  
2 There are
appropriate
oversight and
monitoring
arrangements in
place for schools
undertaking
residential trips.
Audit Risk 2 Limited • The EMCs provide information and
instruction to schools to assist staff
in planning and approval processes
for school residential trips, there is
no mention of monitoring
arrangements in contained in these
documents. Testing and overview
have established that out with
schools, there is insufficient or
limited monitoring arrangements
in place for schools undertaking
residential trips.
• In schools, Head Teachers, or their
nominated deputies, as Head of
the establishment, are responsible
for checking and approving
arrangements for school residential
Page 190

Page 191

7
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
trips and are expected to ensure
staff are supported in organising
school trips.
• Clerical staff in School Support
Teams, record details of trips and
carry out limited checks, so that
the information is available on
request, but nothing else is done
with this information. We would
expect that, for example, this is
used to inform, monitoring,
feedback and training. 
3 Staff involved in
school residential
trips have been
provided with
appropriate
information,
instruction and
training regarding
their
responsibilities.
Audit Risk 3 Limited • The EMCs provide information and
instruction but as noted above,
these require updating. 
• The Council’s Corporate Health and
Safety policy states that a training
needs analysis should be
undertaken, and suitable training
be provided. This has not been
undertaken for school residential
trip processes; No corporate
practical training is made available
to staff regarding their
responsibilities and staff are not
directed to the LEON Risk
Assessment module. 
• Other basic training suggested is
First Aid training. Testing identified
a first aid trained member of staff
was not present on some school
residential trips. In some instances,
this is covered by the facility being
visited, however, this should not be
relied upon.
4 Adults participating
in school trips have
received the
required child
protection
information/basic
training and
evidence of this is
retained.  
Audit Risk 2 Reasonable  • The Council has well established
processes and arrangements in
place to ensure that all school staff
receive the required child
protection information and training
with records kept to evidence this. 
• Legislation regarding the Disclosure
Checks - Protecting Vulnerable
Groups (PVG) scheme changed in
April 2025. 
• The Council carried out an
organisation wide check of
regulated roles and took steps to
ensure that the individuals in those
roles undertook the required level
Page 191

Page 192

8
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
of Disclosure Checks and
appropriate evidence retained.
• Testing identified that during home
stay trips PVG checks were not
undertaken in line with Council
procedures. 
• The revised PVG scheme
requirements should be considered
both, when updating the EMCs and
when developing monitoring
arrangements.
18. Further details of our conclusions against each control objective can be found in Section 3 of this
report.
3. Detailed Findings
Procedures for school residential trips are in place, up to date and take cognisance of best
Practice.
19. The Scottish Government developed the “Going Out There” Framework which relates to outdoor
experiences and off-site visits in a wide variety of settings from galleries and museums to
woodlands, parks and wild natural spaces, as well as planned adventure and residential
experiences. It is expected that ‘Going Out There’ should be adopted as a common framework
across Scotland by all those managing or organising visits or providing activities and venues. 
20. The aims include to increase confidence and co-operation and that by adoption of the good
practice exemplified in the framework allows Employers to fulfil their responsibilities under the
Health and Safety at Work Act 1974 for outdoor experiences and off-site visits for all
participants.
21. The Scottish Advisory Panel for Outdoor Education (SAPOE) is the forum where Scotland’s
outdoor learning community collaborates to develop best practice in the design and safe
delivery of outdoor learning for all children and young people in Scotland. It is member led, and
representatives include Local Authorities. One of its key aims is: “promote and develop
consistent good practice across Scotland for off-site visits through the implementation of the
framework Going Out There”.
22. Not all Councils have chosen to adopt the “Going Out There” best practice yet. The Service has
made the decision to adopt the best practice guidance and has established a working group to
undertake this. The group comprises one Education Manager, two Headteachers (one being the
SAPOE representative) and a representative from school support team.
23. This group has already identified the school trips and outdoor learning management circulars
requiring updating as they need to reflect the decision to adopt the national guidance.
24. The Council’s Education Service have a suite of Education Management Circulars (EMCs) which
collectively form the current policies and procedures issued to schools. There are five EMCs that
provide guidance and instruction relating to the procedures for planning and undertaking of
school residential trips, these are: 
Page 192

Page 193

9
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
• EMC 3.25 School Trips -is the main circular, containing most of the procedures, it directs
staff read EMC 3.14, EMC 1.26 and EMC 3.23 and was last reviewed in 2017.
• EMC 3.14 Insurance – provides details of the three insurance policies available to cover
school trips and procedures for notifying and liaising with Insurance Services and was
also last reviewed in 2017.
• EMC 1.26 Outdoor Education - gives overarching guidance for individual activities, last
reviewed 2023 – although this appears to be incomplete.
• EMC 3.23 Child Protection and Safeguarding - is a core Council policy document which is
supported by annual training provided to all school staff, it was updated in July 2023.
• EMC 1.10 School Funds – provides guidance and instructions relating to the financial
aspects of school residential trips, this was updated in May 2025, in response to internal
audit recommendations.
25. The circulars reviewed in detail as part of this audit were, School Trips, Insurance and Outdoor
Education. The information in these was used to test procedures in nine schools which included,
one joint campus, two 2-18 schools and six primary schools.  
26. The School Trips circular is the main source of guidance and instruction for staff involved in the
planning and undertaking of school trips, including residential trips and contains three
appendices.
27. The School Trips circular has not been updated since 2017 and does not reflect current working
practices and contained gaps which we have identified including:
• No record retention period for any of the documents, which has led to inconsistent
record keeping among the different schools.
• There is no formal or consistent process for P7 transition trips. These require co-
ordination between multiple schools with staff in different schools carrying out tasks.
Lack of guidance has resulted in school support not been notified by all schools involved
in the trips. 
• There is no tailored approval form for home stay trips.
• There are missing links to documents and contact details.
• Post trip reports are now verbal and are mostly lessons learned. It is unclear whether
this is the current way of working or if reports no longer required.
28. The circular sets out the roles and responsibilities for four key roles involved but not all roles and
responsibilities are included.
• Head Teacher/Campus principles /nominated delegate – as Head of the Establishment
has overall responsibility for all trips and approval.
• Leaders In Charge – the teacher (s) planning and leading the school residential trip.
• Supervising staff – accompanying the trip.
• School liaison officer – the in-school contact for those on the trip.
29. Clerical staff in the schools have an active role, performing tasks related to the administration
for school trips but this is not detailed in the circular and has led to differing practices and
inconsistency within schools. In some small primary schools, clerical staff organise the trips while
in other larger schools, teachers undertake more of the administration. 
Page 193

Page 194

10
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
30. The School Support Team is the corporate support team which consists of the School Support
Manager, the Admin and Finance Officers and clerical staff. Schools are advised to send a copy of
the approval forms to school support for them to record. The tasks carried out by theses staff
are not detailed in the circular. 
31. When updating the circulars there would be benefit to reviewing the tasks at each stage of the
process and clarifying the roles and responsibilities of the staff involved.
Action Plan 1
32. As noted above, EMC 3.14 Insurance provides details of the insurance policies in place for school
trips and procedures for notifying and liaising with Insurance Services, it was last reviewed 2017.
33. The Council has four policies available to schools’ undertaking trips, the costs of these are
apportioned into school budgets:
• Public Liability & Employers Liability insurance automatically covers all employees and all
activities officially approved by school, outdoor centre, youth club etc are covered.
Cover is automatic and insurance documents are published on the Hub.
• Group personal accident policy - applicable to staff only, cover is automatic.
• School journey policy is available for trips involving overnight stays, it covers
participants, teachers and other adults, whether employees or not, who accompany
them. Examples of cover include medical expenses, cancellation expenses, personal
effects and legal liability. 
o This policy is optional, and cover is supplied only when schools complete the School
Travel Insurance Policy Proposal form (appendix 1) and submit this to Insurance
Services, before the event.
34. Schools are not directly provided with copies of the policies where there is automatic cover and
there are no links in the circular to these, rather it states that it is the Head Teachers
responsibility to “ensure that all staff who may be involved in organising school journeys are
made aware of the content”. 
35. When Insurance Services receive Appendix 1 requests from schools, they record this so that they
have the details in the event of a claim and provide schools with a copy of the School Journey
policy.  
36. The guidance contained in the Insurance circular could be clearer, and some gaps were identified
which create the potential that trips are booked without fully checking the existing cover
available. These include:
• Appendix 1 - staff are advised to submit this before the event, there are no minimum
timescales within which schools should submit this form to Insurance Services nor any
retention period for this. 
• Appendix 1 - asks for minimal details only and does not require to be signed by the Head
Teacher/ person approving the trip.
• The School Journey Policy schedule is only provided to schools after Appendix 1 has
been submitted, this has some exclusions, e.g. maximum age covered is 70 and
limitations on winter sports, which are not reflected in the Insurance circular. 
Page 194

Page 195

11
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
37. The Insurance Circular and its appendix should be reviewed and updated with the assistance of
Legal Services to ensure it reflects current working practices and requirements. 
Action Plan 2
38. Residential trips are classified as all school journeys involving an overnight stay, these should be
notified to Insurance Services and as the School Journey Policy cover is an extensive policy
additional insurance is not normally required. 
39. Testing of processes within schools found that there are occasions when schools do not advise
Insurance Services of residential trips and pay for insurance cover with external parties,
examples included an outdoor centre being visited and a company organising an overseas trip.
The costs of this are included in the total trip costs, either some or all of which are paid by for
mostly by families of those participating in the trips.
40. Insurance Services maintain a record of all insurance claims. In the past five years there have
only been twelve claims, six of which related to cancellations due to lockdown.
41. The Outdoor Education circular gives overarching guidance for individual activities. In
recognition that many heads of educational establishments and staff involved in the planning of
outdoor education and activities are not specialists in these areas and so may have difficulty in
the exercise of judgements on certain outdoor activities. To provide support with this, the
Council has engaged the services of a technical adviser, who is kept on retainer, and is available
to provide advice. 
42. The Outdoor Education circular was reviewed in 2023, but this document appears incomplete as
there are missing sections, specifically those relating to the Scottish Government “Going Out
There” best practice framework/toolkits.
Action Plan 3
43. Both the School Trips and Outdoor Education circulars provide some guidance on the use of
external providers, requiring that Head Teachers/Head of Establishment should be fully satisfied
as the capability of the external provider, e.g. travel or activity provider. 
44. When enquiring with schools about the trips that they have undertaken, some have used
external companies to help with the provision and planning of the trips. There has been no
direct instruction from Senior Managers that advice should be sought from Procurement and
Commercial Contract Management Team (PCCMT).  
45. Some providers have been engaged with via PCCMT, but this has only happened when the team
having become aware, via their overview and monitoring of spend, that providers are being used
or will be used on a regular basis for school trips. PCCMT have then followed procurement
processes and put appropriate arrangements in place. Consideration should be given to PCCMT
being consulted prior to making bookings/ entering an agreement with external providers for
school residential trips.
Action Plan 5
46. Education Maintenance Circulars are all published on the Council’s website but procedures are
not easily accessible to staff as the end-to-end process for planning school residential trips and
are  not contained in one document. 
Page 195

Page 196

12
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
47. School offices tend to keep copies of school trip packs which contain forms that are required,
with some schools developing a covering checklist with key tasks. Staff planning trips are
provided with copies of these packs from the offices, however, these do not always contain a
copy of the circular and similarly do not always read the School Trip and Insurance circulars in
full; most were unaware of the linkages to the Outdoor Education circular. 
48. When reviewing and updating the circulars there would be benefit to considering including a
flow chart providing a visual overview and a checklist as these could help streamline and
standardise the processes.  This may help navigate the process more effectively and support
consistency of approach.
Action Plan 1,2 and 3
There are appropriate oversight and monitoring arrangements in place for schools undertaking
residential trips.
49. The Education Management Circulars provide information and instruction to schools to assist
staff in planning and approval processes for school residential trips.  There is no mention of
centralised monitoring arrangements in these documents and our testing established that out
with schools there are no monitoring arrangements in place. 
50. In schools, Head Teachers, or their nominated deputies, as Head of the establishment, are
responsible for checking and approving arrangements for school residential trips and are
expected to ensure staff are supported in organising school trips.
51. The School Trips circular appendix 2 – Residential Trips is the approval form that Leaders in
Charge complete with the main details of the proposed trip. This form is passed to the Head
Teacher for review and approval. Copies of this should be retained in the office and emailed to
the School Support Team for recording. A review of forms found most are completed and signed
but there are other examples that were incomplete, some unsigned and some were out of date
forms from 2013.
52. Clerical staff within the school support team file the documents received from schools and
record some of the information on the Master School Trip spreadsheet.  Limited checks are
carried out e.g. there is a formula built into the spreadsheet to check the ratios of pupils to
teachers. This information is available on request but nothing else appears to be done with the
information. 
53. Schools do not receive any acknowledgement nor feedback, unless the ratios need queried.
Discussions with Head Teachers and staff in schools established that the assumption is that no
response or feedback means that there are no issues with the forms and processes. 
54. A sample of available Appendix 2 Approval forms, from schools and from the school support
records were reviewed and compared with the Master School Trip spreadsheet, this found that
not all trips undertaken were notified to school support, some schools submitted copies of risk
assessments, others did not. 
55. The lack of sufficient monitoring of both schools and school support processes has meant that
there are no mechanisms for providing feedback to staff. As a result, staff are unaware where
procedures could be improved. 
Page 196

Page 197

13
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
56. Appropriate corporate monitoring arrangements should be established and implemented. There
would be benefit to updating the School Trips Master spreadsheet to ensure that it capture all
the information required to support monitoring arrangements.
Action Plan 4
Staff involved in school residential trips have been provided with appropriate information,
instruction and training regarding their responsibilities.
37. The EMC’s provide written information and instruction to staff, outlining responsibilities for
Head Teachers and Leaders in Charge, but as noted above, these require updating.
38. No corporate/ practical training is made available to staff involved in the planning and
undertaking of school residential trips, rather Head Teachers are expected to follow the
management circular and ensure staff are supported to organise school trips.  Head Teachers
can contact the Education Managers for support, but this is not detailed in either the School Trip
or Outdoor Learning circulars. 
39. Feedback during testing highlights that staff would like some formal or tailored training to help
them feel more confident planning and undertaking school residential trips.  Most go to other
teachers who have undertaken trips previously for advice.
40. School excursions and educational visits can involve an element of risk, and the School Trips
circular instructs staff to carry out a risk assessment at the planning stage. A review of the
circulars and wider testing established that:
• There are no arrangements in place to provide training on the completion of risk
assessments to Leaders in Charge/ staff planning school trips and those expected to
approve school trips. 
• The circulars do not refer staff to the Council’s LEON Risk Assessment training module.
• No risk assessment template is included in any of the circulars.
• The further information section on P19 of the School Trips circular provides a link to  The
Health and Safety Executive leaflet Five steps to risk assessment
• Some schools had been provided with a risk assessment template by the Council’s
Health and Safety Team.
• There is no retention period stated for completed risk assessments.
• There is no monitoring of risk assessments carried out.
41. EMC 1.26 Outdoor Education states the “First Aid certificate - requirements “the level of first aid
training required by the authority for all activities is the 'standard' first aid course”. There is no
mention of First Aid requirements in EMC 3.25 School Trips. 
Action Plans 1 and 3
42. Testing highlighted that there is not always a First Aid trained member of staff participating in all
school residential trips. In some instances, like trips to outdoor centres, this is covered by the
facility being visited. 
Page 197

Page 198

14
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
43. The Council’s Corporate Health and Safety plan states that Services should “undertake a training
needs analysis and provide suitable training to staff, taking into account risk assessments for
work activities and the need to provide appropriate Health and Safety induction and refresher
training, in line with the relevant policies and local risk assessment”. This has not been carried
out for school trips processes. 
44. A training needs analysis should be undertaken, and suitable training provided, for Head
Teachers and staff, including clerical, involved in the processes of planning and undertaking of
school residential trips. This should consider, making the LEON Risk Assessment Module
compulsory and requirements for First Aid Training. 
Action Plan 5
Adults participating in school trips have received the required child protection information/basic
training and evidence of this is retained.   
45. The Council has well established processes and arrangements in place to ensure that all school
staff receive the required child protection information and training with appropriate records
kept for evidence of this occurring.
46. Prior to the start of each new academic year, schools have two in-service days, child protection
training is provided to all staff and records maintained by schools of this.
47. From 1 April 2025, it is a legal requirement for individuals to be a member of the Disclosure
Checks – Protecting Vulnerable Groups (PVG) scheme when carrying out a regulated role with
children, protected adults, or both. Organisations had to ensure that individuals who are to carry
out a regulated role (paid or voluntary) have PVG scheme membership from 1 April 2025
onwards. 
48. To comply with this legislation the Council carried out an organisation wide check of regulated
roles and took steps to ensure that the individuals in those roles undertook the required level of
Disclosure Checks and evidence of this is retained. 
49. Testing identified that during home stay trips PVG checks were not undertaken in line with
Council procedures.
50. The revised PVG scheme requirements should be included when updating the guidance and
instructions within the EMCs, including EMC 1.56 Disclosures, and considered when developing
monitoring arrangements. 
Action Plans 1, 3 and 4
Page 198

Page 199

Appendix 1 – Action Plan
No Finding Risk Agreed Action Responsibility / Due Date
High 1
EMC 3.25 School Trips and its appendices are not up to
date and gaps have been identified. 
The School Trips circular should be reviewed, clarified and
updated. There would be benefit to including a flow chart
providing a visual overview and a checklist as these could
help streamline and standardise the processes, improving
consistency of approach while helping document and
evidence compliance with relevant legislation and Scottish
Government best practice contained in the “Going Out
There” Framework.
Processes and procedures for
school residential trips are
not effective and record
keeping arrangements may
not provide sufficient
evidence of compliance with
relevant legislation. 
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework, will lead the review of
the circular.
Education Officer
30 August 2026
High 2
EMC 3.14 Insurance and its appendix have not been
updated since 2017. 
The circular could be clearer, and some gaps were
identified which create the potential that trips are booked
without fully checking the cover available.
This circular should be reviewed and updated with the
assistance of Legal Services. 
There is the potential that
trips are booked without
fully checking exclusions
within the cover available.
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework will lead the review of
the circular, with the assistance of
Legal Services. 
Education Officer
30 August 2026
High 3
EMC 1.26 Outdoor Learning and its appendices, do not take
account of best practice “Going Out There” framework.
The circular should be reviewed, clarified and updated to
ensure it takes cognisance of the best practice contained in
the “Going Out There” Framework.
The Councils current
processes are not as efficient
and effective as they could
be if they were following
best practice guidance in
relation the planning of
school residential trips.
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework will lead the review of
the circular.
Education Officer
30 August 2026
High 4
Insufficient oversight of schools undertaking residential
trips. 
The lack of monitoring of both schools and school support
processes has means there is no mechanism for providing
feedback to staff. As a result, there are inconsistent
Monitoring arrangements do
not provide sufficient
oversight of school
residential trips.
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework will determine
appropriate corporate monitoring
Education Officer
30 August 2026
Page 199

Page 200

16
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
No Finding Risk Agreed Action Responsibility / Due Date
approaches, and staff are unaware where procedures could
be improved. 
Appropriate corporate monitoring arrangements should be
established and implemented.
arrangements which will be
implemented.
Medium
5
Insufficient guidance on use of external providers.
Guidance on the use of external providers places
responsibility for checks on those approving school
residential trips. When enquiring with schools about the
trips that they have undertaken, some have used external
companies to help with the provision and planning of the
trips.
Consideration should be given to the Procurement and
Commercial Contract Management Team (PCCMT) being
consulted prior to making bookings with external providers
for school residential trips. 
Staff have not been provided
with appropriate
information, instruction and
training regarding their
responsibilities related to
school residential trips.
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework, in consultation with
Procurement and Commercial
Contract Management Team
(PCCMT), will consider this.
Education Officer
30 August 2026
Medium
6
Staff involved in school residential trips have not been
provided with training regarding their responsibilities.
No training analysis has been undertaken, and no
corporate/ practical training is made available to staff; gaps
include the completion of risk assessments and first aid
training. Head Teachers are expected to follow the circular
and ensure staff are supported to organise school trips.  
A training needs analysis should be undertaken, and
suitable training be provided, for Head Teachers and staff,
including clerical, involved in the processes of planning and
undertaking of school residential trips. This should consider:
• making the LEON Risk Assessment Module compulsory.
• requirements for First Aid training.
Staff have not been provided
with appropriate
information, instruction and
training regarding their
responsibilities related to
school residential trips.
The Education working group
established to facilitate the
Council’s adoption of the “Going
Out There” best practice
framework will consider the
training needs analysis and what
training should be provided for
those involved in the processes of
planning and undertaking of
school residential trips.
Education Officer
30 August 2026
Page 200

Page 201

17
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows:
Grading Definition
High A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error.
Medium
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.
Low Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives.
VFM An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).
Page 201

Page 202

18
Argyll and Bute Council – Internal Audit Report –Process for School Residential Trips November 2025 
Appendix 2 – Audit Opinion
Level of Assurance Definition
High Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk.
Limited Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 202

Page 203

Argyll and Bute Council
Internal Audit Report
November 2025/6
FINAL
High Medium Low VFM
Number of
Findings
0 0 1 0
Building Cleaning
Audit Opinion: High
Page 203

Page 204

2
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
Contents
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Key Dates ................................................................................................................................................ 3
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 4
3. Detailed Findings ............................................................................................................................ 6
Appendix 1 – Action Plan ..................................................................................................................... 10
Appendix 2 – Audit Opinion ................................................................................................................. 12
Contact Details
Internal Auditor: Annemarie McLean
Telephone: 01700 501354
e-mail: annemarie.mclean@argyll-bute.gov.uk
www.argyll-bute.gov.uk
Page 204

Page 205

3
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2025, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal control and governance in relation to building cleaning.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with council officers and the information available at the time
the fieldwork was performed. The findings outlined in this report are only those which have
come to our attention during the course of our normal audit work and are not necessarily all the
issues which may exist.  Appendix 1 to this report includes agreed actions to strengthen internal
control however it is the responsibility of management to determine the extent of the internal
control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy, and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. The purpose of the Cleaning Service is to provide a clean and safe working and learning
environment for Council employees and for pupils and staff in schools and nurseries across the
Council area. Cleaning is provided to 46 Council offices and buildings, and to the 36 larger
schools across the Council: the remainder of cleaning in very small schools is carried out by
janitor/cleaners who are directly managed by Education.
5. The cleaning service employs around 220, part time and term time staff, the majority of which
are female.  Cleaning staff often work out of hours and are employed on the lowest SLGE grades.
These are entry level jobs that offer meaningful and valuable employment opportunities to a
range of people, including to young people with no work experience elsewhere.
6. The cleaning team provides commercial cleaning services to Argyll Community Housing
Association (ACHA) and the Valuation Joint Board, generating income for the council via this
approach.  Services are provided to ACHA offices and sheltered housing facilities across the
Council area. 
Scope
7. The scope of the audit was to review and assess the arrangements for cleaning across the
Council establishments, as outlined in the Terms of Reference agreed with the Head of
Commercial Services on 02 September 2025.
Key Dates
8. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below.
Page 205

Page 206

4
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
9. Exhibit 1 – Key Dates
Stage Actual Date
Terms of Reference agreed 02 September 2025
Fieldwork Commencement 22 September 2025
Draft Report issued 18 November 2025
Management Comments received 26 November 2025
Final Report issued 26 November 2025
Audit and Scrutiny Committee 16 December 2025
Risks
10.  The risks considered throughout the audit were:
• Audit Risk 1: Arrangements for the cleaning of Council establishments are adversely
impacted due to insufficient staff cover in each location.
• Audit Risk 2: Monitoring and reporting of the quality of cleaning is not undertaken.
Audit Opinion
11. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
12. Our overall audit opinion for this audit is that we can take a high level of assurance.  This
means that Internal control, governance and the management of risk are at a high standard.
Only marginal elements of residual risk have been identified with these either being accepted
or dealt with.  A sound system of control designed to achieve the system objectives is in place
and being applied consistently.
Recommendations
13. We have highlighted one low priority recommendations where we believe there is scope to
strengthen the control and governance environment.  This is summarised below:
• The Induction Pack contains out of date links and should be reviewed to ensure it
reflects current working practices, and if applicable, reflect changes to the PVG scheme.
14. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
15. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective. 
Page 206

Page 207

5
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to Risk Assessment Summary Conclusion
1 The Council has
arrangements in
place to carry out
regular cleaning
of Council
establishments.
Audit Risk 1
Audit Risk 2
Substantial • The Council’s Cleaning Service has
arrangements in place to carry out
regular cleaning of establishments
where this has been requested. 
• Each establishment has specific cleaning
staff allocated to undertake a pre-
planned schedule of cleaning at an
agreed frequency.
• Cleaning staff do not have access to
Council computers, so all training
records, including Induction training, are
manual records. These are stored at
each premises in the on-site Health and
Safety folders, except for GDPR training
which is collated by Operational Delivery
Managers. 
• New employees are provided with an
induction pack with contains links to key
Council policies. These links do not work.
• Casual staff are retained in locations to
provide cover for staff annual leave and
absence.  Changes to the Disclosure
Checks requirements affect some
cleaning staff who work in what are
deemed regulated roles e.g. schools and
nurseries.  
• The induction pack should be reviewed
to ensure that it contains up to date
links to key documents/ policies, reflects
current working practices and if
applicable, any changes to processes
required as a result of the change to the
PVG scheme.
2 Cleaning
standards are
being utilised, and
the quality of
cleaning is
monitored and
reported
regularly.
Audit Risk 2 High • There are detailed cleaning schedules
and standards to support the cleaning of
council premises, these are based on
industry standards.
• Monitoring of cleaning in premises is
undertaken by the cleaning services
manager who conducts regular reviews
and audits of cleaning practices against
established benchmarks such as the BICs
standards. The Operations Officers or
Managers carry out ad- hoc spot check
on premises on a regular basis. No
documentation relating to this was
reviewed as part of the audit. 
Page 207

Page 208

6
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
• Building users are sent surveys
requesting feedback but these are rarely
returned, instead any issues are raised
with the Operational Delivery Managers,
who discuss these at weekly catch up
meetings with the Senior Manager -
Catering, Cleaning, Events and Food
Strategy. 
• Reporting of performance and issues for
the cleaning services are discussed at
the Commercial Services Teams
meetings. No reports are currently
provided to Council Committees.
16. Further details of our conclusions against each control objective can be found in Section 3 of this
report.
3. Detailed Findings
The Council has arrangements in place to carry out regular cleaning of Council establishments.
17. The Council’s Cleaning Services has arrangements in place to carry out regular cleaning of
Council establishments where this has been requested.  Each establishment has specific cleaning
staff allocated to undertake a pre-planned schedule of cleaning at an agreed frequency. 
18. The service has recently gone through changes to the management structure.  To support
delivery of cleaning services across the geographic area of the Council, the Commercial Services
current structure is:
• Senior Manager - Catering, Cleaning, Events and Food Strategy
• two Operational Delivery Managers, one East and one West
• four Operational Officers, one for each Council area, have responsibility for both
catering and cleaning staff for the establishments within the areas.
19. Cleaning Services maintain the Cleaning Premises spreadsheet which has a list of premises
where cleaning has been requested.  This list is not compared to a Council premises list as it is
the responsibility of the Service occupying the building to request cleaning arrangements and to
notify any changes to cleaning services.
20. Specific arrangements for each premises and the assessed/measured area to be cleaned, are
detailed on the Cleaning Template which is maintained by the Operational Delivery Managers
who updates the template as changes occur.  For each establishment, this lists:
• The assessed/measured area to be cleaned
• The number of staff allocated to clean that premises
• The weekly hours per post and the working pattern of these hours.
21. Education Service has a central process for notifying changes to the cleaning requirements in
schools and, for other services, the Building Responsible Person for that establishment, will
contact the Operation Delivery Managers for that area. 
Page 208

Page 209

7
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
22. There are location-based arrangements in place to cover for staff annual leave and absence.
Each area has a list of casual staff to cover absences.  Cleaning services advised that they often
have difficulty recruiting cleaners for several different reasons, e.g. usually the hours are very
small, it is very hard physical work, the Council only advertise posts on My Job Scotland, and
many people don't actively look on this for cleaning jobs.  Cleaning staff often work out of hours
and are employed on the lowest pay grades and external cleaning companies may have more
enhanced benefits. 
37. Commercial Services maintain the Cleaning Manual, last updated August 2023.  This is a working
guide for managers and employees, it outlines the roles and responsibilities for cleaning, within
Commercial Services.  It is a practical reference tool to aid training and support compliance with
clearly defined cleaning procedures.  The manual sets out the health and safety standards and is
the overarching document that other cleaning service processes and documents are sourced.
38. New employees are given an induction pack which contains:
• Contact telephone numbers
• Council Health and Safety Policies -links and overview, how to report incidents
• General Health and Safety policies
• HR procedures including holiday entitlement
• Training Record card which should be signed by both the employee and the trainer
• Details “toolbox talks” available.
39. Operations Officers provide induction training to all new employees and existing staff moving
either location or changing type of establishment:
• Explanations of all sections within the induction pack
• Control of Substances Hazardous to Health Regulations (COSHH) training
• A walk though of the establishment explaining the requirements on the cleaning
schedule and materials to be used and location of the onsite Health and Safety folder.
40. Additional training after initial Induction training is only carried out if there have been changes
to legislation, cleaning schedules, or products used.  As cleaners undertake manual tasks that do
not require access to the Council computer network, they are classed as non-network staff and
have manual training records.
41. The On-Site Health and Safety folder contains employee training records.  This folder is reviewed
and updated biannually.  All updates must be read and signed off by all cleaners.  Operational
Delivery Managers also collate a manual record of GDPR training as a check that non-networked
staff have completed the training.  No documentation was checked during this review. 
42. From 1 April 2025, it is a legal requirement for individuals to be a member of the Disclosure
Checks – Protecting Vulnerable Groups (PVG) scheme when carrying out a regulated role with
children, protected adults, or both.  This includes cleaning staff who work in schools and
nurseries etc.  
43. To comply with this legislation the Council carried out an organisation wide check of regulated
roles and took steps to ensure that the individuals, currently employed, in those roles undertook
the required level of Disclosure Checks and evidence of this is retained. The Council bore the
costs associated with this exercise. 
Page 209

Page 210

8
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
44. The Cleaning Services Induction pack should be reviewed to ensure that it contains up to date
links to key documents/ policies, reflects current working practices and if applicable, any
changes to processes required as a result of the change to the PVG scheme.
Action Plan 1
Cleaning standards are being utilised, and the quality of cleaning is monitored and reported
regularly.
23. The cleaning service operates under a structured cleaning methodology that aligns with industry
standards and best practices.  This methodology outlines the processes, equipment, and
materials to be used for different areas and ensures that all cleaning activities are carried out
effectively and consistently. 
24. The British Institute of Cleaning Science (BICs) is responsible for producing standards and
educational frameworks for the cleaning industry.  All cleaning staff and management undergo
regular training and professional development, including BICSc -accredited training, to maintain
high levels of competency and stay up to date with the latest cleaning techniques, health and
safety requirements, and quality assurance standards. 
25. Appropriate cleaning schedules and standards are in place to support the cleaning of council
establishments where this is requested.  The schedules vary depending on the Service occupying
the establishment, examples include Pre 5 Nursery, Schools and offices. 
26. Schedules are based on the structure cleaning methodology and are reviewed annually or as
required and detail:
• area to be cleaned, restricted to those that are accessible
• description of what should be cleaned and frequency i.e. daily/weekly
• description of cleaning activity that should be carried out
• acceptable standards
• description of what is not acceptable.
27. The cleaning service significantly reduced its cleaning specification in 2012 following the service
choices exercise that was undertaken in 2010 and was subject to an independent review in
2016/17 as part of the Catering and Cleaning Service Choices review.  This review noted that
“the current hours and standards are at the lower end of acceptable, but meet the basic
minimum requirements expected”.  We have been advised by the service that this remains the
case.
28. The current cleaning arrangements in schools and offices across the Council are historical,
although, plans have been developed to review this going forward.  Currently, in some cases,
cleaning is carried out based on the customer request, i.e. 2 hours, 1 day per week.
29. Cleaning services have implemented a review of these historical arrangements.  Plans are being
developed to re-measure all cleaning premises and re-calculate the cleaning requirements to
ensure the required standards are met.  To facilitate this re-measure, it was necessary for some
managers to have undertaken and completed the required BICs training.  
30. In addition to the above, cleaning services are working together with the Education
Management Team to update the cleaning schedules for Janitors and day cleaners, as this aspect
Page 210

Page 211

9
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025
of the service sits within Education. In order to prevent confusion regarding roles and
responsibilities, it was agreed that job descriptions get reviewed at the same time.
31. To ensure that the Council’s cleaning schedules continue to meet industry standards, cleaning
services managers conduct regular reviews and audits of cleaning practices against established
benchmarks such as the BICs standards.  The Operations Officers or Managers carry out ad- hoc
spot check on premises on a regular basis.  No documentation relating to this was reviewed. 
32. The opportunity to feedback on the performance of the cleaning service is available to building
users via customer satisfaction questionnaire forms.  Responses are rarely received from internal
clients e.g. schools or offices, as they usually email or phone if there is a problem and the
operations officer or manager resolves any issues that have been highlighted.  Any issues arising
are discussed with the Senior Manager, Catering, Cleaning, Events and Food Strategy during the
weekly catch up meetings with the two Operational Delivery Managers.
33. Due to the lack of returns of the current customer satisfaction questionnaire forms, this has not
been included in the new performance dashboard.  To try and boost engagement, cleaning
services are considering the introduction of an online survey using MS Forms to capture
feedback. 
34. Commercial services submit data on the delivery of the cleaning service to an Annual Public
Sector Excellence Building Cleaning (APSE) benchmarking exercise.  APSE use this data and other
benchmarking information to create an annual benchmarking report. The results of this are used
to monitor performance year on year.  The Council benchmark against similar Local Authorities
but due to the logistical and unique issues in Argyll and Bute, benchmarking with another
authority can be more complex.
35. Reporting of performance and issues for the cleaning servicers are discussed at the Commercial
Services Teams meetings. No reports are currently provided to Council Committees.
Page 211

Page 212

Appendix 1 – Action Plan
No Finding Risk Agreed Action Responsibility / Due Date
Low 1
Induction Pack
The Induction Pack contains out of date links and should
be reviewed to ensure it reflects current working
practices, and if applicable, reflect changes to the PVG
scheme.
New employees are not
provided with access to
relevant current Council
policies and procedures.
Induction pack to be reviewed and
all links updated.
Information on PVG changes will
be added when available.
Operational Delivery
Manager
30 March 2026
Page 212

Page 213

11
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows:
Grading Definition
High A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error.
Medium
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.
Low Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives.
VFM An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).
Page 213

Page 214

12
Argyll and Bute Council – Internal Audit Report – Building Cleaning, November 2025 
Appendix 2 – Audit Opinion
Level of Assurance Definition
High Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk.
Limited Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 214

Page 215

Argyll and Bute Council
Internal Audit Report
November 2025
FINAL
High Medium Low VFM
Number of
Findings
0 6 0 0
Self-Directed Support
Audit Opinion: Reasonable
Page 215

Page 216

2
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
Contents
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 4
Key Dates ................................................................................................................................................ 4
Risks ........................................................................................................................................................ 5
Audit Opinion ......................................................................................................................................... 5
Recommendations ................................................................................................................................. 5
2. Objectives and Summary Assessment ........................................................................................... 6
3. Detailed Findings ............................................................................................................................ 8
Appendix 1 – Action Plan ..................................................................................................................... 12
Appendix 2 – Audit Opinion ................................................................................................................. 15
Contact Details
Internal Auditor: Moira Weatherstone
Telephone: 01546 604146
e-mail: moira.weatherstone@argyll-bute.gov.uk
www.argyll-bute.gov.uk
Page 216

Page 217

3
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Scrutiny Committee in
March 2025, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal control and governance in relation to Self-Directed Support (Direct Payments)
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with council officers and the information available at the time
the fieldwork was performed. The findings outlined in this report are only those which have
come to our attention during the course of our normal audit work and are not necessarily all the
issues which may exist. Appendix 1 to this report includes agreed actions to strengthen internal
control however it is the responsibility of management to determine the extent of the internal
control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy and appreciation is due for the cooperation and assistance received from all
officers over the course of the audit.
Background
4. The Social Care (Self-directed Support) (Scotland) Act 2013 (the Act) which came into force on 1
April 2014, makes legislative provisions relating to the arrangement of care and support
(“community care services” and “children’s services”) in order to provide a range of options to
individuals as to how they are to be provided with their support. 
5. After an assessment has been completed and if an individual meets the eligibility criteria, the
allocated worker will discuss ways of meeting the assessed need and will explain the 4 options
available under Self Directed Support. These are:
• Option 1 – Direct Payment;
• Option 2 – Direct your own support;
• Option 3 – Services arranged for you by the Local Authority;
• Option 4 – Mixture of the three above.
6. A Direct Payment (Self Directed Support) is an amount of money paid by Argyll & Bute Health &
Social Care Partnership (HSCP) to enable individuals who meet the eligibility criteria to source
their own care and support.  Self-directed support is where a person takes responsibility for
managing their own support, it is about giving people more choice on how their support services
are designed and making sure they receive support that meets their needs.  It allows people to
choose how their support is provided to them by giving them as much ongoing control as they
want over the money spent on their support.  This can be by means of employing a personal
assistant or an agency.
7. Self-directed support (SDS) aims to give individuals more flexibility, choice and control over their
health and social care support and is based on five key principles: respect, fairness, freedom,
safety and independence. Where an assessment has been undertaken and support needs
Page 217

Page 218

4
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
identified, Social Work will discuss the support needs with the client and a support plan will be
agreed and any financial contribution by the client will be discussed.
8. SDS can be used in many ways.  A client can get support to live in their own home, such as help
with having a bath or getting washed and dressed.   Out of the home it could be support to go to
college, to continue in employment or take a job, or to enjoy leisure pursuits more. Instead of
relying on activities run at a day centre for example, the client could arrange for a personal
assistant to help them attend local classes, go swimming, or be a volunteer helping others. It
could also be used to provide respite or for equipment and temporary adaptations.
9. If a client has been assessed as being eligible for certain support needs, four options on how to
receive services through SDS are available:
• A direct payment that you can use to organise and pay for your own support;
• SW can make arrangements for the support the client has chosen and if it is provided by
someone other than the HSCP, the HSCP will pay the relevant contribution;
• The HSCP can choose the best support for the client, make arrangements to set it up and
if it is provided by someone other than the HSCP, the HSCP will pay the relevant
contribution;
• A combination of any of the above.
10. Within the Council area the HSCP currently provide around 200 Self Directed Support payments
through a budget of £4,170,908 for 2024/25.  This includes payments for supported living,
respite, homecare and children with disabilities. The projected outturn at the end of March 2025
was £4,614,447.
Scope
11. The scope of the audit was to review the assessment of processes in place for the checking of
evidence, receipts and accounts for payment   as outlined in the Terms of Reference agreed with
the Chief Officer – HSCP on 18 June 2025. 
Key Dates
12. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below.
Exhibit 1 – Key Dates
Stage Actual
Date
Terms of Reference agreed 18 June 2025
Fieldwork Commencement 19 June 2025
Draft Report issued 5 August 2025
Management Comments received 12 November 2025
Final Report issued 13 November 2025
Audit and Scrutiny Committee 16 December 2025
Page 218

Page 219

5
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
Risks
13.  The risks considered throughout the audit were:
• SRR07:  Failure of the HSCP to deliver on its Strategic Priorities results in deteriorating
health and wellbeing outcomes for the population and / or reduced access to appropriate
health and social care services. This could also result in financial and reputational risk to
the Council.
• Audit Risk 1: failure to ensure that staff are provided with support and training to manage
Self-Directed Support packages (Direct Payments)
• Audit Risk 2: failure to have processes in place for checking documentation and accounts in
respect to Direct Payments made
Audit Opinion
14. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
15. Our overall audit opinion for this audit is that we can take a reasonable level of assurance.  This
means that internal control, governance and the management of risk are broadly reliable.
However, whilst not displaying a general trend, there are areas of concern which have been
identified where elements of residual risk or weakness may put some of the system objectives at
risk.
Recommendations
16. We have highlighted six medium priority recommendations where we believe there is scope to
strengthen the control and governance environment.  These are summarised below:
• Guidance within the Agreement document should be updated to include further
information on the management of Direct Payments in terms of accumulated fund or
the requirement to top up of funds, including details of the circumstances that would
give rise to the repayment of funds.
• The Self-Directed – ‘Option 1 Direct Payments Information – Supported Persons
Guidance’ should be strengthened to include the statement that following financial
review funds may be requested to be returned to the authority and in what
circumstances.
• Financial reviews should be completed in a timely manner with consideration being
given to providing additional assistance to the Finance Officer – AWI to clear the
outstanding backlog.
• Process should be put in place to ensure Care Managers follow through and complete
the recommendations in financial review memos.
• Care Plans should be reviewed and kept up to date to ensure the Direct Payment
remains appropriate.
• A robust ‘single’ recording system should be put in place to ensure that there is a
complete overview of when financial reviews are undertaken, when Care Plans are
Page 219

Page 220

6
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
reviewed and when requests contained in the Memos following a financial review are
completed. 
17. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
18. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective. 
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to Risk Assessment Summary Conclusion
1 Policies and
procedures are in
place for the
management of Self-
Directed Support
(Direct Payments)
SRR07 Substantial Policies and procedures are in place
and are up to date.  A policy and
procedural document – Self Directed
Support, Direct Payments Option 1,
Policy and Procedural Guidance for
Staff and Managers is available, the
most recent version, V2.5 and is dated
May 2025.  The purpose of the policy is
to reflect the provisions of The Self-
directed Support (Direct Payment)
(Scotland) Regulations 2014 which
came into force on the 1st of April
2014 following the enactment of the
Social Care (Self-directed Support)
(Scotland) Act 2013.  In addition, the
policy informs the procedures outlined
in Part B of the document which are
applicable to all Social Work service
users (“supported person”) and should
be adopted by all staff.
A leaflet – Option 2 Individual Service
Funds (ISF) provides an outline guide to
the four options available to client,
providing further details for Option 2
which allows the client to direct Argyll
and Bute Council to commission
services from a support provider on
your behalf.  Information is available
on the Council website.  In addition,
when supported people are being
assessed they are provided with
information on independent advice,
advocacy, Community Contacts and
Carers Centres. During the course of
the audit, new guidance came into
Page 220

Page 221

7
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
effect in July 2025 for the financial
review of Direct Payments – ‘Staff
Guidance – Direct Payment Finance
Reviews’.  This guidance is to be read
in conjunction with the Self-Directed
Support Direct Payments Option 1
Policy and Guidance.
2 Policies and
procedures have
been distributed to
staff and training
provided for the
management of Self-
Directed Support
(Direct Payments)
Audit risk 1 Substantial Policies, procedures, guidance
documents and other relevant
information is available for staff on the
HSCP SharePoint site. Training is
provided by the Self-Directed Support
Officer.  Training was previously
undertaken face to face as group
sessions with the Self-Directed Support
Officer attending all areas and Islands
throughout Argyll & Bute to deliver
training for staff.  As working from
home practices have developed,
training is now provided through the
TEAMS platform.
3 Processes are in
place for the
checking of
evidence, receipts
and accounts
relating to Self-
Directed Support
(Direct Payments)
Audit Risk 2 Reasonable Processes and procedures are in place
for the checking of financial records
which require to be maintained by
those in receipt of Direct Payments.  A
review timetable has been established
and the Finance Administration Officer
(AWI) has responsibility for
undertaking these reviews. From a
sample size of 205, testing was
undertaken of thirteen Supported
Person’s financial records and this
highlighted that financial reviews had
not been undertaken in accordance
with the agreed timetable and there
remains a significant backlog of case to
review. It should be noted that the
backlog of reviews is historical and that
the Finance Administration Officer AWI
inherited this work.  Work is well
underway, however, at the time of
reporting there were 172 client
financial records which have been
received but were waiting to be
reviewed.
19. Further details of our conclusions against each control objective can be found in Section 3 of this
report.
Page 221

Page 222

8
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
3. Detailed Findings
Policies and procedures are in place for the management of Self-Directed Support (Direct
Payments)
20. Policies and procedures are in place for the management of Self-Directed Support (Direct
Payments). A policy and procedural document – Self Directed Support, Direct Payments Option
1, Policy and Procedural Guidance for Staff and Managers is in place, the most recent version,
V2.5, dated May 2025.  This is a two-part document with Part A being Option 1 – Direct Payment
Policy (a payment which is made to a supported person which can be used to purchase support.
The supported person can do this on their own or get help from family, friends and support
organisations).  Part B is the Direct Payment Procedural Guidance.
21. The purpose of the policy is to reflect the provisions of The Self-directed Support (Direct
Payment) (Scotland) Regulations 2014 which came into force on the 1st of April 2014 following
the enactment of the Social Care (Self-directed Support) (Scotland) Act 2013.  In addition, the
policy informs the procedures outlined in Part B of the document which are applicable to all
social work service users (“supported person”) and is required to be adopted by all staff. The
document should be read in conjunction with all other supporting documentation which is
available on the Social Work SharePoint site. Roles and responsibilities are outlined in the
document in the form of a flow chart.
22. The process for referral, determining eligible needs, support plan agreement and review are as
per departmental processes and procedures for assessment, care management and eligibility
criteria.  
23. Option 1 Direct Payments Information Supported Person’s Guidance details background
information, including the 4 Options available to those assessed with eligible needs. It explains
what Direct Payments are, advises about the scheme, outlines the necessity to open a bank
account for the specific purpose of receiving the payment and details how the payments can be
used. It outlines that all bank statements, letters and cheque books for the account must be kept
and that there is an expectation that these are made available to Social Work Services for the
purpose of monitoring the account. It further clarifies that the account will be reviewed regularly
at intervals designated by the HSCP and that if funds in the Direct Payment account total more
than the 2 months’ contingency allowed, the excess funds will require to be returned to Argyll &
Bute HSCP.
24. During the course of the audit, new guidance came into effect in July 2025 for the financial
review of Direct Payments – ‘Staff Guidance – Direct Payment Finance Reviews’.  This guidance is
to be  read in conjunction with the Self-Directed Support Direct Payments Option 1 Policy and
Guidance.
25. Information is available on the Council website.  In addition, when a supported person is being
assessed they are provided with information on independent advice, advocacy, community
contacts and Carers Centres. Two documents and a leaflet are provided to individuals which give
comprehensive guidance on Self-Directed Support, including the management of the payment.  
The Self-Directed Support Officer provides comprehensive information on Self Directed Support
Page 222

Page 223

9
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
at an ‘in person’ or online meetings with anyone considering a Direct Payment option.   Ongoing
support is provided, as necessary by the Self-Directed Support Officer. 
Policies and procedures have been distributed to staff and training provided for the
management of Self-Directed Support (Direct Payments)
26. Policies, procedures, guidance documents as detailed above, along with other relevant
information is available for staff on the HSCP SharePoint site. A staff survey was undertaken to
gauge the understanding, awareness and accessibility of documents relating to Direct Payments
and although the survey response rate was low there was some assurance that staff know where
to access information or get support from the results produced.  
27. Training is provided by the Self-Directed Support Officer.  Training was previously undertaken
face to face as group sessions with the Self-Directed Support Officer attending all areas and
Islands throughout Argyll & Bute to deliver training for staff.  As working from home practices
have developed, training is now provided through the TEAMS platform.
Processes are in place for the checking of evidence, receipts and accounts relating to Self-
Directed Support (Direct Payments)
28. Everyone in receipt of a Direct Payment is required to sign a legally binding Direct Payment
Agreement. The agreement places responsibility and obligations upon the supported person and
the HSCP to ensure that appropriate funding is provided regularly to meet the needs of the
individual and that they spend the funding they receive appropriately and in terms of their Care
Plan. The Supported Person is accountable to the HSCP for how the Direct Payment money is
spent and are expected to provide evidence they have spent the funding as agreed.  If in any
circumstances the Direct Payment stops and it is assessed there has been an overpayment of
monies, then there is an obligation that the supported person will be required to repay the
overpayment to us. 
Action Plan 1
29. Supported Persons are provided with a document ‘Option 1 Direct Payments Information –
Supported Persons Guidance’.  This document provides comprehensive information on Self-
Directed Support and the management of payments.   It details the responsibilities in terms of
Argyll & Bute HSCP being accountable for public funds and its responsibilities to monitor direct
payments to ensure they are spent appropriately and that they represent cost effective use of
resources.   The Guidance provides clarity in terms of the requirement to keep a range of
financial documentation and provide the HSCP with financial information on their Direct
payments at designated intervals. The guidance also states that if the Direct Payment agreement
is terminated either by the supported person or by Argyll & Bute HSCP or if the supported
person is deceased all unspent funds must be returned to Argyll & Bute HSCP. 
Action Plan 2
30. For financial and monitoring purposes, the Supported Person must record of all income and
expenditure on the Direct Payment bank account statements. All items of expenditure must be
recorded separately on a template Financial Return Form, which is provided.  For each separate
payment made: 
Page 223

Page 224

10
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
• the date of payment;
• person/organisation to whom the payment is being made (payee)
• the nature of the payment;
• cheque number (if appropriate) and
• the total amount must be recorded.
In addition, for each item of expenditure recorded there must be an invoice or a receipt to
support the payment made, this must be kept up to date. A financial review timetable has been
established with clear timeframes published.
31. Where appropriate employment records (PAYE, National Insurance, Liability Insurance etc.) for
all the carers/ personal assistants employed or contracted by supported person must be kept.
Time sheets (or rotas) indicating the days and times carers have worked should be submitted
when a financial review is requested.  However, a number of Supported Persons use the services
of a payroll company who maintains responsibility for the management of employment,
including managing timesheets and payroll. 
32. Statutory guidance to accompany the Social Care (Self-directed Support) (Scotland) Act 2013
states that depending on the circumstances surrounding any decision to terminate a direct
payment the local authority may need to decide if it is appropriate to seek recovery of unspent
funds. The legislation enables the authority to require some or all of the money they have paid
out to be repaid if it is not satisfied that it has been used to secure the support to which it
relates. The Council is required to take into account hardship considerations in deciding whether
to seek repayments.  In addition, the Social Work Finance Team will review bank balances prior
to the end of the financial year, or at any reasonable time, and may seek to reclaim any excess
funds held. 
33. From a sample size of 205, testing was undertaken of thirteen Supported Person’s financial
records and this highlighted that financial reviews had not been undertaken in accordance with
the agreed timetable and there remains a significant backlog of case to review. Work is well
underway, however, at the time of reporting there were 172 client financial records which have
been received but were waiting to be reviewed.    The testing of records identified there were
instances where: 
• Supported persons’ not using their full assessed hours resulting in accumulation of funds in
the Direct Payment bank account;
• Supported Persons paying over the agreed hourly rate for a service and whereby this is
acceptable, additional funds must be repaid to the Direct Bank Account by the Supported
Person.  Testing of records showed that additional funds were not being paid to cover the
additional costs and that advanced payments provided by the Council were used to cover
the deficit;
• One record highlighted that there was unauthorised use of the Self-Directed Support
payment which was being used to fund everyday bills;
• Supported persons paying over the agreed hourly rate for services, whilst not using the full
assessed hours resulting in accumulation of funds in the Direct Payment bank account;
Page 224

Page 225

11
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025
• Overspending on agreed hourly rates and above assessed hours whilst not topping up the
Direct Payment bank account, placing reliance on advance payments to cover ongoing costs.       
Action Plan 3
34. If, during the review of the Supported Persons financial records it is identified that there is an
accumulation of funds, funds not being used as agreed in the care plan or funds not being
‘topped up’ in the bank account to cover additional care costs, a memo is sent to the Care
Manager to action and follow up.  During the process of testing of records, it was noted that
there was evidence that recommendations in Memos issued to the Care Mangers had not been
followed up. 
Action Plan 4
35. The Direct Payment Policy and Guidance document states that reviews will be undertaken to
ensure that the supported person’s needs are being met and that the Direct Payments
arrangements continue to be appropriate and that it is essential the Care Manager
communicates directly with the supported person where possible to ensure that they are happy
with the arrangements.  Of the records reviewed, four records were recently set up with up-to-
date Care Plans, four records Care Plans had been reviewed in 2025, two records were due for
review and two records were overdue. 
Action Plan 5
36. We were unable to establish if all Direct Payment Care Plans had been reviewed and were up to
date.  All Direct Payment service agreements continue to be updated and recorded in Carefirst
with any Direct Payment financial reviewing taking place off system and uploaded and recorded
in CIVICA (there is nothing is updated in ECLIPSE, the replacement for Carefirst). Any updates to
Direct Payment Care Plans are recorded and updated in CIVICA. ECLIPSE Finance Module (EFM)
processes have not been embedded in the Council and EFM has not yet been adopted. Once live,
this would allow for the linkage of referrals, assessments, reviews to care plans and care service
agreements and financial reviews as the Finance Summary screens would have the relevant EFM
worklists, forms and tasks populated.   
Action Plan 6
Page 225

Page 226

Appendix 1 – Action Plan
No Finding Risk Agreed Action Responsibility / Due Date
Medium
1
Direct Payment Agreement
Everyone in receipt of a Direct Payment is required to sign
a legally binding Direct Payment Agreement. The
agreement places responsibility and obligations upon the
supported person and the HSCP to ensure that appropriate
funding is provided regularly to meet the needs of the
individual and that they spend the funding they receive
appropriately and in terms of their Care Plan. However,
the Agreement is not clear enough what funds require to
be returned in certain circumstances.
Supported Persons may not
be fully aware of the
obligation to return funds
The Direct Payment guidance
relating to the section on unspent
funds will be updated and the
new guidance will be available on
SharePoint and the website.
Self-Directed Support
Officer
Date: 31 December 2025
Medium
2
Guidance Document
Supported Persons are provided with a document ‘Option
1 Direct Payments Information – Supported Persons
Guidance’.  This document provides comprehensive
information on Self-Directed Support and the
management of payments.  However, the Guidance
document does not provide clear guidance on the
circumstances which would give rise to the requirement to
‘top up’ the Direct Payment bank account or
circumstances whereby accumulated funds require to be
returned.
Supported Person may not be
aware that the Direct
Payment bank account
requires to be topped up or
that accumulated funds would
need to be returned
The Direct Payment guidance
relating to information on the
topping up of funds will be
updated to ensure clarity and the
new guidance will be available on
SharePoint and the website.
Self-Directed Support
Officer
Date: 31 December 2025
Medium
3
Financial Reviews
From a sample size of 205, testing was undertaken of
thirteen Supported Person’s financial records and this
highlighted that financial reviews had not been
undertaken in accordance with the agreed timetable and
there remains a significant backlog of case to review. 
Recovery of funds delayed, or
Direct Payment bank accounts
are not topped up as required
Discussions to be held with Head
of Finance about what extra
resource can be provided to clear
back log of cases.  
Since issuing the draft audit report
an additional temporary member
of staff has been appointed for
one year.
Social Work Amin
Manager
Date: Completed
Page 226

Page 227

13
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
No Finding Risk Agreed Action Responsibility / Due Date
Medium
4
Follow up Actions
During the process of testing of records, it was noted that
there was evidence that recommendations in Memos
issued to the Care Mangers had not been followed up. 
Where recommendations or
advice from practice
leads/team managers are not
followed there is a risk that
inaccurate information is
provided to individuals or
actions not carried out which
could result in the Legislation
not being implemented
placing the organisation at
risk.
This finding will be highlighted
and shared with Service Managers
and Team Managers to ensure
that the message is
communicated clearly to Social
Work staff to take account of any
advice and guidance in a complex
area of practice and are fully
aware of their responsibility to
collaborate with practice leads
and senior staff to ensure their
practice is to the standard
expected and achieves the best
outcomes for the individual.
Head of Hospitals and
Community Care
Date: 31 December 2025
Medium
5
Care Plans
The Direct Payment Policy and Guidance document states
that reviews will be undertaken to ensure that the
supported person’s needs are being met. Of the records
reviewed, four records were recently set up with up-to-
date Care Plans, four records Care Plans had been
reviewed in 2025, two records were due for review, and
two records were overdue.
Care Plans do not align with
the Direct Payments
A process of self-evaluation,
through case file reviews, twice
yearly, will be implemented by
each locality to monitor
performance and benchmark
against other localities.
Head of Hospitals and
Community Care
Date: 31 December 2025
Medium
6
Supported Persons Records
We were unable to establish if all Direct Payment Care
Plans had been reviewed and were up to date due to the
multiple ways in which the Supported Persons’s records
are maintained. 
Care Plans and financial
reviews are at greater risk of
not aligning, this can also
result in excessive build-up of
unused funds and greater risk
of money not being used as
intended. 
A process of self-evaluation,
through case file reviews, twice
yearly, will be implemented by
each locality to monitor
performance and benchmark
against other localities.
Head of Hospitals and
Community Care
Date: 31 December 2025
Page 227

Page 228

14
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained.  The definitions
of each classification are as follows:
Grading Definition
High A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error.
Medium
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.
Low Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives.
VFM An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the council to achieve
better value for money (VFM).
Page 228

Page 229

15
Argyll and Bute Council – Internal Audit Report – Self-Directed Support, November 2025 
Appendix 2 – Audit Opinion
Level of Assurance Definition
High Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk.
Limited Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 229

Page 230

This page is intentionally left blank

Page 231

Argyll and Bute Council
Internal Audit Report
November 2025
FINAL
High Medium Low VFM
Number of
Findings
0 0 0 0
Oban Airport
Audit Opinion: High
Page 231

Page 232

2
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
CContentss
1. Executive Summary........................................................................................................................3
Introduction............................................................................................................................................3
Background.............................................................................................................................................3
Scope.......................................................................................................................................................4
Risks........................................................................................................................................................4
Audit Opinion.........................................................................................................................................4
2. Objectives and Summary Assessment...........................................................................................4
3. Detailed Findings............................................................................................................................6
Appendix 1 –Audit Opinion...................................................................................................................9
Contactt Detailss 
Internal Auditor: Leanne Rennie
Telephone: 01369 708516
e-mail: Leanne.rennie@argyll-bute.gov.uk
www.argyll-bute.gov.uk
Page 232

Page 233

3
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
11. Executivee Summaryy
Introductionn
1. As part of the 2025/26 Internal Audit Plan, approved by the Audit & Scrutiny Committee in
March 2025, we have undertaken an audit of Argyll and Bute Council’s (the Council) system of
internal controland governance in relation to Oban Airport.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with council officers and the information available at the time
the fieldwork was performed. The findingsoutlined in this report are only those which have
come to our attention during the course of our normal audit work and are not necessarily all the
issues which may exist. Appendix 1 to this report includes agreed actions to strengthen internal
control however it is the responsibility of management to determine the extent of the internal
control system appropriate to the Council.
3. The contents of this report have been agreed with the appropriate council officers to confirm
factual accuracy and appreciation is due for the cooperation and assistance received from all
officers overthe course of the audit.
Backgroundd
4. Oban Airport is one of three aerodromes operated by the Council, and licensed under Article 211
of the ANO 2009 by the Civil Aviation Authority (CAA). Deemed as a Public Service Obligation
(PSO),scheduled services, and scholar flights for island school children, operate from Oban
airport to Coll, Colonsay, Islay and Tiree. Additionally, the airport deals with chartered traffic and
military flights as well as general aviation traffic such as medevacs, coastguard operations,
training flights and scenic tours by private operators.
5. Prior to the grant of a licence and for continued licensing, the CAA requires the Aerodrome
Operator to meet the minimum standards detailed in CAP168 Licensing of Aerodromes. CAP 168
setsout the standards required at UK national licensed aerodromes relating to management
systems, operational procedures, physical characteristics, assessment and treatment of
obstacles, visual aids, rescue and fire-fighting services and medical services.
6. The Oban Airport Aerodrome Manual (the Manual) provides information about the airport, its
systems for managing safety and the required operational procedures.  The Airport Rescue &
Fire Fighting Service (RFFS) manual provides guidance on the agreed policy and procedures
designed to achieve an effective and efficient RFFS. Both manuals are derived from CAP168.
7. Oban Airport operate the ‘Redkite Equipment Management system’ which is used in all UK
airports to help ensure they meet the requirements of the CAA in regard to RFFS personnel and
equipment.
8. The overall remit of internal audit is to provide assurance over compliance with the 25 airport
operating instructions (AOIs) established by the Manual and the further procedures established
by the RFFS manual.
Page 233

Page 234

4
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
SScopee 
9. The scope of the audit was to provide assurance over compliance with six of the airport
operating instructions (AOIs) established by the Manual and the further procedures established
by the RFFS manual as outlined in the Terms of Reference agreed with the Oban Airport Station
Manager. The operating instructions audited on 18th September 2025 are as follows:
x AOI 16 – Aerodrome Safeguarding
x AOI 17 –Recovery of Disabled Aircraft
x AOI 18 –Recording Aircraft Movements
x AOI 19 – Accident, Incident and Occurrence Reporting
x AOI 20 – Aerodrome Ground Maintenance
x AOI 24 –Cranes & Tall Equipment in vicinity of Aerodrome
Riskss
10. The risks considered throughout the audit were:
x Audit Risk 1 - Failure to comply with operating instructions could result in increased risk
of accidents and/or the airport losing its CAA licence
Auditt Opinionn
11. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work. Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
12. Our overall audit opinion for this audit is that we can take a HIGH level of assurance.  This means
that internal control, governance and the management of risk are at a high standard. Only
marginal elements of residual risk have been identified with these either being accepted or dealt
with. A sound system of control designed to achieve the system objectives is in place and being
applied consistently.
2. Objectivess andd Summaryy Assessmentt
13. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective
Exhibit 1 – Summary Assessment of Control Objectives
Control Objective Link to
Risk
Assessment Summary Conclusion
CO1 The Manual, setting
out the operational
procedures of the
airport, is up to date,
appropriate and
accessible to all
relevant staff.
Audit Risk
1
High The Manual is updated annually and
is available to appropriate officers
and published on the Council’s
intranet site, the Hub. The document
was found to be comprehensive with
each section outlining the Council
policy for compliance with regulations
and procedures.
Page 234

Page 235

5
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
Control Objective Link to
Risk
Assessment Summary Conclusion
CO2 AOI16 – Aerodrome
Safeguarding -
reasonable steps are
taken to keep the
airport and its
airspace safe at all
times for use by
aircraft.
Audit Risk
1
High There is a safeguarding map which
details the specific area which fall
under the safeguarding requirements,
and external contractors are issued
with guidance when working within
the safeguarding area.
CO3 AOI17 – Recovery of
Disabled Aircraft -
measures are in place
to remove disabled
aircraft without
disrupting the safety
of the airport.
Audit Risk
1
High It is the responsibility of aircraft
owners to remove disabled aircraft to
a safe area. The Council has facilities if
the owner requires assistance.
CO4 AOI18 – Recording
Aircraft Movements –
the airport complies
with operating
instruction to record
movements.
Audit Risk
1
High Aircraft movements are compiled by
the Aerodrome Flight Information
Service Officer (AFISO), or during busy
periods by another crew member and
are recorded appropriately.
CO5 AOI19 – Accident,
Incident and
Occurrence Reporting
- the airport complies
with the operating
instructions to report
accidents, incidents
and occurrences.
Audit Risk
1
High Accidents, incidents and occurrences
associated with the operation of an
aircraft are reported appropriately
internally and externally. All reports
are recorded internally on the airport
database.
CO6 AOI20 – Aerodrome
Ground Maintenance
- the airport complies
with the ground
maintenance
programme.
Audit Risk
1
High Ground maintenance procedures
have been designed to ensure there is
a system in place to maintain the
airfield to a suitable standard.
CO7 AOI24 – Cranes & Tall
Equipment in vicinity
of Aerodrome –the
airport complies with
the operating
instructions regarding
tall equipment &
cranes.
Audit Risk
1
High Tall Equipment and Cranes must apply
for a permit 14 days prior to the
planned operation.
14. Further details of our conclusions against each control objective can be found in Section 3 of this
report. 
Page 235

Page 236

6
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
33. Detailedd Findingss
The Manual, setting out the operational procedures of the airport, is up to date, appropriate and
accessible to all relevant staff
15. The Manual is available to all relevant personnel onthe Council HUB with a hard copy held
onsite atthe airport. Each section within the Manual sets out:
x the Council’s policy and established procedures to ensure compliance with relevant rules
and/or regulations
x appropriate monitoring arrangements (where applicable)
x roles and responsibilities of relevant personnel.
16. The Manual is reviewed annually by the Station Manager and was last updated in July 2025.  The
updated version is submitted to the CAA who have 28 days to highlight any queries on the
Manual’s content. If no response is received in 28 days, then the revised Manual is adopted. The
current Manual is version 8.7.
17. The CAA document CAP 168 sets out the standards required at UK National licensed aerodromes
relating to management systems, operational procedures, physical characteristics, assessment
and treatment of obstacles, visual aids, rescue and fire-fighting services and medical services.
18. When updating the Manual, the Station Manager ensures that it reflects any updates or
revisions as published by the CAA. A check of the CAA website found that there has been no
alterations, other than formatting, to the CAP 168 document since January 2022.
19. The CAA carry out periodic on-site audits to verify continued compliance with national licensing
requirements. The latest inspection was June 2025; we have been provided with findings and
responses to date.
All reasonable steps are taken to always keep the airport and its airspace safe for use by aircraft.
20. The CAA requires that the airport and its airspace are always safe for use by aircraft. This is
detailed in CAP 738 “Safeguarding of Aerodromes”. The station manager is responsible for
aerodrome safeguarding.
21. Oban airports all have a safeguarding map which has been lodged with planning services which
details the specific area which falls within the safeguarding requirements. All planning
applications within this area should meet the CAP 738 requirements and must be notified to
relevant airport personnel. We have been provided with a copy of the latest planning
application.
22. External contractors have been issued with guidance when working within the safeguarding area
to ensure that the requirements of CAP 738 are met.
Measures are in place to remove disabled aircraft without disrupting the safety of the airport.
23. In the event of an aircraft becoming disabled it is the responsibility of the aircraft owner to
remove the aircraft to a safe distance. To facilitate this, the airport has a “tug” or if this not
suitable they can advise the owner of a suitable contractor. If the aircraft is disabled in a
hazardous area,the airport will ensure that the aircraft is removed as soon as possible. If the
runway is required to be closed, then a NOTAM will be issued. There have been no recordings of
disabled aircraft for several years.
Page 236

Page 237

7
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
The airport complies with the operating instructions to record Aircraft movements
24. CAP168 Licensing of Aerodromes requests that all aircraft movements are to be recorded. The
following is recorded:
x aircraft type and registration
x flight number
x type of flight
x destination or departure aerodrome
x time of departure/arrival
x aircraft operator
x number of persons on board
25. Aircraft movements are compiled by the Aerodrome Flight Information Service Officer (AFISO),
or during busy periods by another crew member.  Aircraft movements are recorded
appropriately on the airport database.
The airport complies with the operating instructions to report accidents, incidents and
occurrences
26. The Aerodrome Safety Management System outlines the principle and purpose of accident and
incident reporting.  Additionally, there are mandatory requirements for reporting accidents and
incidents.
27. The Manual states that the Station Manager is responsible for:
x all incidents are investigated
x a no blame philosophy is pursued
x all mandatory reporting procedures are followed in a timely manner
x radio transmission frequencies (RTF) are retained
x appropriate steps are taken to circulate the findings of accident/incident investigations
28. The Manual requires the duty AFISO to make verbal and written reports. All reports are recorded
internally on the airports database. External reports are made directly to the UK Aircraft
Accident Investigation Branch (AAIB). All matters reported to the AAIB/CAA culminate in formal
reports which are available to the public and staff.
The Airport complies with the ground’s maintenance programme
29. Ground Maintenance procedures are in place to ensure there is a system to maintain the airfield
to a suitable standard, incorporating:
x grass cutting
x strimming
x weed and moss control
x perimeter fence maintenance
x egress gate access
30. The Manual states that prior to operating any item of equipment, sufficient training must be
carried out on each item, and the Station Manager must be satisfied with the competence of the
operator before allowing them to operate the equipment.  Personnel are suitably trained by
colleagues and are permitted to use the tractor and attachments once proficient. 
Page 237

Page 238

8
Argyll and Bute Council – Internal Audit Report –Oban Airport, November2025
31. The Manual states that knapsack sprayersmust only be used by personnel in possession of the
relevant PA1 and PA6 certification, two members of staff currently hold this certification.
Cranes & Tall Equipment in vicinity of Aerodrome –the airport complies with the operating
instructions regarding tall equipment & cranes.
32. Operators intending to use cranes or tall equipment within 6 kilometers of an aerodrome
boundary, where the height exceeds 10 meters above ground level (AGL) or the height of
surrounding structures or trees, must apply for a Crane/Tall equipment permit using ‘Crane
Permit FM01’ within the stated time frame.
33. The Manual states that the Station Manager is responsible for assessing all crane/tall equipment
requests and has the right to refuse applications that are not submitted within the time frame
and/or are deemed a hazard to the aerodrome.  Appropriate documentation was retained in
compliance with this requirement.
Page 238

Page 239

9
Argyll andBute Council –Internal Audit Report –Oban Airport, November2025
AAppendixx 11 –– Auditt Opinionn
Level of Assurance
Definition
High
Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system
of control designed to achieve the system
objectives isin place and being applied consistently.
Substantial
Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system
objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale.
Reasonable
Internal control, governance and the management of risk are broadly reliable. However, whilst notdisplaying a general trend,
thereare areas of concern which have been identified where elements of residual riskor weakness may put some of the system
objectives at risk.
Limited
Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptablelevel andplacing system
objectives are at risk. W
eakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised.
No Assurance
Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system
open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues.
Page 239

Page 240

This page is intentionally left blank

Page 241

Argyll & Bute Health & Social Care Partnership
Internal Audit Report
September 2025
FINAL 
High Medium Low VFM
Number of Findings 0 0 2 0 
Review Of Governance
Arrangements 
Audit Opinion: High 
Page 241

Page 242

2 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025 
Contents 
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Key Dates ................................................................................................................................................ 3
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 4
3. Detailed Findings ............................................................................................................................ 5
Appendix 1 – Action Plan ....................................................................................................................... 9
Appendix 2 – Audit Opinion ................................................................................................................. 11 
Contact Details 
Internal Auditor: David Sullivan 
Telephone:  01546 604125 
e-mail:   David.sullivan@argyll-bute.gov.uk 
www.argyll-bute.gov.uk
Page 242

Page 243

3 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Risk Committee in February
2025, we have undertaken an audit of Argyll & Bute Health & Social Care Partnership (HSCP)
system of internal control and governance in relation to Review of Governance arrangements.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with Health & Social Care Partnership officers and the
information available at the time the fieldwork was performed. The findings outlined in this
report are only those which have come to our attention during our normal audit work and are
not necessarily all the issues which may exist. Appendix 1 to this report includes agreed actions
to strengthen internal control however it is the responsibility of management to determine the
extent of the internal control system appropriate to the HSCP.
3. The contents of this report have been agreed with the appropriate Health & Social Care
Partnership officers to confirm factual accuracy, and appreciation is due for the cooperation and
assistance received from all officers over the course of the audit.
Background
4. The purpose of this audit is to ensure that the governance framework remains fit for purpose,
complies with good practice standards, and is reviewed regularly.
5. The governance structure of the HSCP includes the Integration Joint Board (IJB), sub-
committees, and partnership arrangements with NHS Highland and Argyll & Bute Council. This
audit supports the HSCP’s commitment to continuous improvement, transparency, and
accountability in decision-making processes.
Scope 
6. The scope of the audit was to provide assurance that the HSCP’s governance arrangements are
periodically reviewed and fit for purpose as outlined in the Terms of Reference agreed with the
Head of Service and Transformation on 12th May 2025.
Key Dates 
7. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted in Exhibit 1 below.
Exhibit 1 – Key Dates 
Stage
Actual
Date
Terms of Reference agreed 12th May 2025
Fieldwork Commencement 15th June 2025
Draft Report issued 11th July 2025
Management Comments received 18th July 2025
Final Report issued 8 September 2025
Audit and Risk Committee 23 September 2025
Page 243

Page 244

4 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
Risks
8.  The risks considered throughout the audit were:
• SRR04:  Governance and Leadership – risk that governance arrangements are not
conducive to effective working.
• Audit Risk 1: Governance documents are not reviewed regularly or are outdated.
• Audit Risk 2: Roles and responsibilities of key decision-makers are unclear or
inconsistently understood.
• Audit Risk 3: Governance decisions are not transparent or appropriately documented.
• Audit Risk 4: The Integration Joint Board (IJB) make decisions that are out with its legal
powers (ultra vires), potentially leading to legal or financial repercussions.
Audit Opinion
9. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
10. Our overall audit opinion for this audit is that we can take a high level of assurance.  This means
that Internal control, governance and the management of risk are at a high standard. Only
marginal elements of residual risk have been identified with these either being accepted or dealt
with. A sound system of control designed to achieve the system objectives is in place and being
applied consistently.
Recommendations
11. We have highlighted 2 low priority recommendations where we believe there is scope to
strengthen the control and governance environment. These are summarised below:
• A governance roles guide and organisational chart should be developed to clarify officer
responsibilities and committee reporting lines.
• Information on IJB member training and induction should be published to enhance
transparency for stakeholders and potential board members.
12. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1. 
2. Objectives and Summary Assessment
13. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.   
Page 244

Page 245

5 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
Exhibit 2 – Summary Assessment of Control Objectives 
Control Objective Link to Risk Assessment Summary Conclusion
CO1 Governance
documents are
reviewed
periodically and
updated accordingly
SRR04 /
Audit Risk 1
Audit Risk 4
High The HSCP governance framework is
well-documented, formally approved,
and reviewed in accordance with
statutory and good practice
standards. Evidence from IJB minutes
confirms oversight and review activity
has been performed. The existence of
formal schedules and version controls
supports ongoing governance
arrangements.
CO2 Roles and
responsibilities
within the
governance
structure are clearly
defined and
understood.
Audit Risk 2 High The governance structure and
responsibilities within the Argyll &
Bute HSCP are clearly laid out in
governance documents and reflect
good practice. While role clarity is
strong, additional improvements
could be made by enhancing
accessibility and communication of
these responsibilities and training
expectations
CO3 Governance
meetings are
properly
documented, and
decisions are
transparent and
traceable.
Audit Risk 3 High The HSCP’s governance framework
promotes transparency, stakeholder
accessibility, and clear
documentation of decisions. Strategic
plan performance and audit
recommendations are actively
monitored. Governance interactions
between the IJB, Council, and NHS
Highland are well-established.
The IJB prepares an Annual
Governance Statement. 
14. Further details of our conclusions against each control objective can be found in Section 3 of this
report.  
3. Detailed Findings
Governance documents are reviewed periodically and updated accordingly
15. The Joint Strategic Plan (2022–2025) sets out the HSCP’s vision, priorities, and integrated service
delivery objectives over a three-year period. Developed following a formal consultation process,
it defines governance principles, planning cycles, and performance expectations. The document
outlines the governance responsibilities of the Integration Joint Board, the Chief Officer, and
strategic partners, and is aligned with national health and social care integration policy and the
Public Bodies (Joint Working) (Scotland) Act 2014.
16.  The HSCP has a well-documented governance framework comprising all key components
expected under statutory and good practice standards. These include the IJB Standing Orders
Page 245

Page 246

6 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
(v3.4, approved January 2025), committee Terms of Reference (v2.4), the Integration Scheme,
and the 2022–2025 Joint Strategic Plan. Collectively, these documents define governance
procedures, membership structures, delegated authority, and partnership responsibilities. They
are subject to regular review, include version control, and are publicly accessible, supporting
transparency and accountability.
17. The Standing Orders (v3.4, January 2025) provide a comprehensive and up-to-date procedural
framework for the Integration Joint Board. They clearly define the governance structure,
including the distinction between voting and non-voting members, and outline key
responsibilities for the Chair, Vice Chair, and Chief Officer. The document includes detailed
provisions on decision-making, quorum, delegation of functions, and the conduct of meetings.
The inclusion of version control and regular review cycles further demonstrates alignment with
national policy and good governance practice.
18. The key governance documents of the HSCP have all been formally reviewed and approved
within appropriate statutory and operational timeframes. The Standing Orders (v3.4) were
reviewed and approved in May 2025, with version control confirming a biennial review cycle.
The Strategic Plan 2022–2025 was approved in 2022 and remains current, with provisions for a
mid-cycle review if required. The Integration Scheme was last reviewed in 2021 and approved by
Scottish Ministers, with the next review due by 2026. The Terms of Reference for IJB committees
(v2.4) were reviewed and approved in March 2025. These approvals are documented in official
IJB minutes, and all documents contain version controls and embedded review schedules,
evidencing structured and compliant governance oversight.
19. All core governance documents include version control and scheduled review cycles. These align
with statutory expectations: five years for the Integration Scheme, three years for the Strategic
Plan, and annual review for committee Terms of Reference. 
Roles and responsibilities within the governance structure are clearly defined and understood.
20. The audit reviewed the governance framework, key documentation, and training provisions to
assess whether the roles and responsibilities of key officers and committees are clearly defined
and communicated.
21. The roles and responsibilities of key officers within the HSCP are clearly defined and consistently
communicated through core governance documents, including the Standing Orders (v3.4),
Strategic Plan 2022–2025, and Integration Scheme. The Chief Officer is designated as the lead
accountable officer, with responsibilities covering strategic delivery, operational oversight, and
liaison with partner bodies. The Standing Orders also outline the duties of the Chair and Vice
Chair, including meeting leadership and adherence to procedural standards, as well as the
functions of the Standards and Monitoring Officers in relation to conduct and compliance. These
responsibilities are further reinforced through board appointments and formal reporting. These
arrangements promote transparency, accountability, and clarity of governance roles. A
summarised governance roles guide or organisational chart could further improve accessibility
for stakeholders and new members.                         
Action Plan 1
22. The structure of the IJB and its subcommittees is clearly defined and aligned with good
governance practice. The Standing Orders detail the governance framework, including
Page 246

Page 247

7 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
membership composition, quorum rules, decision-making processes, and provisions for
establishing subcommittees. Key roles and delegation arrangements are stated, supporting
accountable leadership and operational delivery. The Strategic Plan further reinforces this
structure, highlighting the roles of strategic and operational committees, such as the Finance
and Audit Committee. The governance model reflects best practice, with defined
responsibilities, clear reporting lines, and a Chief Officer accountable to both partner
organisations. To enhance accessibility, a visual governance chart showing committee
relationships and officer accountabilities could be developed to support stakeholder
understanding.    
Action Plan 1
23. The governance structure is well defined, comprising strategic oversight by the IJB, operational
delegation to the Chief Officer, and supporting subcommittees for finance, audit, clinical
governance, and strategic planning.
24. Subcommittees have documented Terms of Reference, reviewed and approved by the IJB in
March 2025, outlining purpose, responsibilities, membership, and reporting lines.
25. The IJB has established appropriate arrangements for the induction and ongoing development of
its members. New members are supported through structured induction programmes and board
development sessions to ensure they understand their roles and responsibilities within the
governance framework. The Strategic Plan confirms that Performance Development and Review
(PDR) schemes are in place through each partner agency, promoting individual growth aligned
with organisational objectives. In addition, the HSCP offers a range of accessible training courses
on key topics such as mental health and suicide prevention, which are open to both staff and IJB
members. These arrangements reflect a strong commitment to maintaining effective
governance participation. Publishing further detail on induction and training provisions via the
IJB’s website could enhance visibility and support stakeholder engagement.
Action Plan 2 
Governance meetings are properly documented, and decisions are transparent and traceable.
26. The audit reviewed whether governance decisions of the HSCP are transparent, accessible to
stakeholders, and supported by clear reporting, oversight structures, and assurance
mechanisms.
27. Governance documentation, including IJB agendas, reports, and minutes, are routinely published
via the Argyll and Bute Council website. Reports typically include background, options, decisions,
and recommendations in full, supporting public accountability. Agendas, reports, and approved
minutes are routinely published on the Argyll and Bute Council website in a dedicated IJB
section, ensuring that stakeholders can access key decisions, background papers, and
recommendations in a timely manner. The Standing Orders reinforce this approach by explicitly
supporting open meetings, in line with statutory obligations under the Public Bodies (Joint
Working) (Scotland) Act 2014. Examples such as the 27 March 2024 meeting confirm that
governance decisions are documented and presented in an accessible format. These practices
promote visibility, trust, and effective stakeholder engagement.
28. Governance arrangements between the HSCP, Argyll and Bute Council, and NHS Highland are
underpinned by the Integration Scheme and Standing Orders, which clearly define the statutory
Page 247

Page 248

8 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance
arrangements, September 2025
delegation of functions and responsibilities. The Chief Officer is jointly accountable to the IJB and
both partner organisations, ensuring that strategic decisions are implemented across NHS and
Council structures. While the IJB determines strategic direction and budget allocations,
operational delivery remains with the parent bodies. This model is supported by joint oversight
mechanisms and shared reporting through audit and governance structures.
29. The IJB complies with statutory requirements by preparing, reviewing, and publishing an Annual
Governance Statement (AGS) as part of its audited annual accounts. The 2023–24 AGS, approved
on 26 March 2025, provides a comprehensive summary of the IJB’s governance arrangements
and internal control environment. It is subject to both internal review and external audit
scrutiny, with the auditor confirming that the statement fairly reflects the IJB’s risk assurance
and governance framework. This process offers assurance to stakeholders regarding the
effectiveness and transparency of governance practices within the HSCP.
30. The HSCP has established governance arrangements to support strategic risk management. The
Strategic Risk Register (SRR) was formally reviewed and approved by the Leadership Team and
the Audit & Risk Committee in December 2024, with subsequent scrutiny by the Integration Joint
Board in January 2025. The SRR is actively aligned to the Joint Strategic Plan through a
structured mapping exercise, demonstrating how key risks relate to strategic objectives. Overall,
the risk governance framework is compliant, well-documented, and subject to regular review,
reinforcing effective risk-informed decision-making at a strategic level. 
Page 248

Page 249

Appendix 1 – Action Plan 
No Finding Risk Agreed Action Responsibility / Due Date
Low
1 A summarised governance guide, including an
organisational chart that outlines officer responsibilities
and committee reporting lines, would improve
accessibility for new members and external stakeholders.
Without a clear and
accessible governance
guide, there is a risk
that new members,
staff, and stakeholders
may lack a full
understanding of roles,
accountability
structures, and
decision-making
processes.
HSCP will develop a
concise governance
summary guide,
including officer
responsibilities and
reporting lines.
Business Improvement
Manager 
30th April 2026
Low
2 While training provisions are evident, details of IJB
member training and induction are not currently published
publicly. This limits transparency for stakeholders and
potential board members.
The absence of publicly
available information on
IJB member training and
induction may reduce
stakeholder confidence
in governance capability
and discourage
potential candidates
from engaging with the
IJB.
HSCP will on an ongoing
basis publish a summary
of the training and
induction programme
provided to IJB
members, including any
development
opportunities
Business Improvement
Manager 
30th April 2026 
Page 249

Page 250

10 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance arrangements, September 2025
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained. 
The definitions of each classification are as follows: 
Grading    Definition
High  A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error. 
Medium 
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.  
Low  Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives. 
VFM  An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the HSCP to achieve better
value for money (VFM). 
Page 250

Page 251

11 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Review of Governance arrangements, September 2025
Appendix 2 – Audit Opinion 
Level of Assurance  Definition 
High  Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial  Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable 
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk. 
Limited  Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance  Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 251

Page 252

This page is intentionally left blank

Page 253

Argyll & Bute Health & Social Care Partnership
Internal Audit Report
August 2025
FINAL 
High Medium Low VFM
Number of Findings 0 0 3 0 
Partnership Working
Audit Opinion: High 
Page 253

Page 254

2 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26 
Contents 
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Key Dates ................................................................................................................................................ 3
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 4
3. Detailed Findings ............................................................................................................................ 7
Appendix 1 – Action Plan ..................................................................................................................... 12
Appendix 2 – Audit Opinion ................................................................................................................. 15 
Contact Details 
Internal Auditor: David Sullivan 
Telephone:  01546 604125 
e-mail:   David.sullivan@argyll-bute.gov.uk 
www.argyll-bute.gov.uk
Page 254

Page 255

3 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Risk Committee in February
2025, we have undertaken an audit of Argyll & Bute Health & Social Care Partnership (HSCP)
system of internal control and governance in relation to Partnership Working.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with Health & Social Care Partnership officers and the
information available at the time the fieldwork was performed. The findings outlined in this
report are only those which have come to our attention during the course of our normal audit
work and are not necessarily all the issues which may exist. Appendix 1 to this report includes
agreed actions to strengthen internal control however it is the responsibility of management to
determine the extent of the internal control system appropriate to the HSCP.
3. The contents of this report have been agreed with the appropriate Health & Social Care
Partnership officers to confirm factual accuracy, and appreciation is due for the cooperation and
assistance received from all officers over the course of the audit.
Background
4. This audit focused on the effectiveness of joint working between the HSCP and its main partner,
Argyll and Bute Council, to deliver integrated services.
5. The integration of health and social care services requires strong and effective collaboration
between partner organisations. This promotes clarity of roles, shared objectives, and effective
decision-making processes which are essential to achieving successful outcomes for service
users. This review supports assurance against Strategic Risk Register item SRR05.
Scope 
6. The scope of the audit is to provide assurance that partner organisations, primarily Argyll and
Bute Council, are working effectively with HSCP as outlined in the Terms of Reference agreed
with the Head of Finance and Transformation, Health and Social Care Partnership on 28th April
2025.
Key Dates
7. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted in Exhibit 1 below. 
Exhibit 1 – Key Dates
Stage Actual
Date
Terms of Reference agreed 28th April 2025
Fieldwork Commencement 1st May 2025
Draft Report issued 5th August 2025
Management Comments received 11th August 2025
Final Report issued 8 September 2025
Audit and Risk Committee 23 September 2025
Page 255

Page 256

4 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
Risks
8.  The risks considered throughout the audit were:
• SRR05:  Partnership working risk that inadequate relationships with key partners lead to
service delivery failure.
• Audit Risk 1: Partnership roles and responsibilities are unclear or poorly communicated.
• Audit Risk 2: Decision-making arrangements do not support effective joint working.
• Audit Risk 3: There is limited evidence of shared goals or integrated planning processes.
• Audit Risk 4: Disputes or misalignment between partners are not effectively managed.
Audit Opinion
9. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion is provided in Appendix 2 to this report.
10. Our overall audit opinion for this audit is that we can take a high level of assurance.  This means
that Internal control, governance and the management of risk are at a high standard. Only
marginal elements of residual risk have been identified with these either being accepted or dealt
with.  A sound system of control designed to achieve the system objectives is in place and being
applied consistently.
Recommendations
11. We have highlighted 3 low priority recommendations where we believe there is scope to
strengthen the control and governance environment. These are summarised below:
• HSCP should continue to develop existing workforce performance monitoring
arrangements so that KPIs and RAG assessments remain clearly linked to strategic
objectives and risks that IJB developed in partnership with both employing bodies.
• To strengthen assurance, the HSCP should consider embedding awareness of escalation
and dispute resolution routes from the Integration Scheme into induction for senior
managers and key officers to ensure consistent understanding across the partnership
and with wider partners.
• HSCP should capture and review recurring themes or patterns from informal partnership
challenges to support organisational learning and provide assurance to the IJB that risks
are being managed proactively.
12. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
13. Exhibit 2 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective. 
Page 256

Page 257

5 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
Exhibit 2 – Summary Assessment of Control Objectives 
Control Objective Link to Risk Assessment Summary Conclusion
CO1 There is a clear
framework
governing
partnership roles
and responsibilities.
SRR05 /
Audit Risk 1
High Argyll and Bute HSCP operate within a
clear and effective governance
framework established by the
Integration Scheme, which defines
statutory responsibilities, decision-
making structures, and operational
processes between Argyll and Bute
Council and NHS Highland. The
Integration Joint Board (IJB) provides
central oversight, supported by
subcommittees and management
teams that ensure joint
accountability, financial governance,
and strategic planning. Evidence from
recent IJB minutes, Chief Officer
reports, and the Direction Log
confirms active participation,
structured collaboration, and
compliance with legislative
expectations across both partners.
CO2 Governance and
decision-making
structures facilitate
joint working and
accountability.
Audit Risk 2 High Argyll and Bute HSCP operate under a
well-defined governance framework,
with the Integration Joint Board (IJB)
and its supporting committees
actively overseeing strategic,
financial, and clinical functions.
Governance documents — including
the Integration Scheme, Standing
Orders, and Terms of Reference —
clearly define roles and
responsibilities between NHS
Highland and Argyll and Bute Council,
ensuring accountability and
minimising duplication. IJB meeting
records and the Direction Log
demonstrate transparent,
documented, and jointly actioned
decision-making. The approval
process for the Joint Strategic Plan
further confirms collaborative
planning and shared accountability. 
CO3 The HSCP and Argyll
and Bute Council
work to shared
goals with
integrated planning.
Audit Risk 3 Substantial Argyll and Bute HSCP and Council
demonstrate strong alignment
through shared strategic goals
embedded in key planning
documents such as the Joint Strategic
Plan, Commissioning Strategy, and
Digital Modernisation Strategy. Joint
planning is facilitated by statutory
Page 257

Page 258

6 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
structures like the Strategic Planning
Group and Locality Planning Groups,
with clear partner and stakeholder
involvement. Performance against
shared objectives is actively
monitored using structured reporting
and risk management frameworks. To
enhance transparency and support
decision-making, the partnership
should consider developing existing
workforce performance monitoring
arrangements so that KPIs and RAG
assessments remain clearly linked to
strategic objectives and risks. This
should be done in collaboration with
both employing bodies.
CO4 Disagreements
between partners
are managed
constructively
through defined
processes.
Audit Risk 4 Substantial Argyll and Bute HSCP have robust
governance arrangements for dispute
resolution, with clearly defined
escalation procedures set out in the
Integration Scheme and Standing
Orders. While no formal disputes
were recorded during the audit
period, evidence suggests that
challenges are addressed
collaboratively at operational levels.
However, the absence of
documented informal disagreements
or outcomes limits transparency and
learning. To strengthen assurance,
the HSCP should consider embedding
awareness of escalation and dispute
resolution routes from the
Integration Scheme into induction for
senior managers and key officers to
ensure consistent understanding
across the partnership and with wider
partners. In addition, the HSCP should
consider capturing recurring themes
or patterns from partnership
challenges (rather than logging every
issue) to support organisational
learning and provide assurance to the
IJB that risks are being managed
proactively. 
14. Further details of our conclusions against each control objective can be found in Section 3 of this
report.  
Page 258

Page 259

7 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
3. Detailed Findings
There is a clear framework governing partnership roles and responsibilities
15. The Argyll and Bute Integration Scheme provides the statutory foundation for partnership
working between Argyll and Bute Council and NHS Highland through the Integration Joint Board
(IJB), as required under the Public Bodies (Joint Working) (Scotland) Act 2014. The audit
reviewed the current Integration Scheme alongside key supporting documents, including the
Chief Officer’s Report (May 2025) and the IJB Direction Log. The Integration Scheme remains up
to date following its scheduled 5-year review in June 2025 and continues to define governance
structures, financial responsibilities, clinical and care governance, and dispute resolution
mechanisms. Evidence from the Direction Log and Chief Officer’s reporting confirms that the
scheme is not only active but embedded in operational practice. These documents illustrate
effective delegation, accountability, and cross-organisational planning, supporting the
conclusion that the partnership framework is robust and functioning in accordance with
legislative expectations.
16.  Partnership working across Argyll and Bute HSCP is underpinned by a well-defined governance
and operational framework. The Integration Joint Board (IJB) remains the central oversight body,
bringing together voting members and representatives from both Argyll and Bute Council and
NHS Highland. Operational delivery is coordinated through the Strategic Leadership Team (SLT)
or Joint Management Team (JMT), which ensures the alignment of Council and NHS functions
under the leadership of the Chief Officer. Subcommittees such as the Clinical and Care
Governance Group, Finance and Policy Committee, and Audit and Risk Committee provide
structured assurance across key areas. Supporting evidence from the Chief Officer’s Report (May
2025), Direction Log, and Annual Audit Report 2023–24 confirms that roles, responsibilities, and
communication channels are clearly established and routinely utilised. Wider partnership
engagement is also facilitated through forums involving the third sector, independent providers,
and locality planning groups, reflecting a broad-based, integrated approach to service planning
and delivery.
17. Argyll and Bute Council plays a central role within the Health and Social Care Partnership (HSCP)
governance framework. As a statutory partner under the Public Bodies (Joint Working)
(Scotland) Act 2014, the Council jointly developed and approved the Integration Scheme
alongside NHS Highland, which underpins the partnership’s governance and delivery model.
Council representation on the Integration Joint Board (IJB), through appointed elected members,
ensures that local authority priorities are directly reflected in strategic decisions. In addition,
senior Council officers actively participate in IJB subcommittees such as the Audit and Risk
Committee and Finance and Policy Committee, providing input into financial oversight,
performance management, and risk assurance. Joint accountability is reinforced through the
dual reporting line of the Chief Officer to both parent bodies. Operational coordination is further
evidenced through the IJB’s Directions Log, which confirms that services are jointly instructed
and delivered across Council and NHS functions. This reflects a partnership model with shared
governance and delivery arrangements.
18. A review of minutes of the Integration Joint Board (IJB) meetings such as on 29 January and 26
March 2025 confirm that Argyll and Bute Council and NHS Highland are actively fulfilling their
joint responsibilities for the governance of the Health and Social Care Partnership (HSCP). The IJB
serves as the primary forum for strategic oversight and decision-making, with documented
discussions on key areas such as renewal of the Joint Strategic Plan, financial reporting, and
Page 259

Page 260

8 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
performance monitoring. The review of minutes also confirmed active participation from both
partner organisations, with voting members in attendance and evidence of collaborative input
into service planning and accountability processes. The consistent presence of updates from the
Chief Officer and financial oversight items further demonstrates that the Integration Scheme is
being conducted effectively through structured and transparent governance meetings. 
Governance and decision-making structures facilitate joint working and accountability
21. Review of the Integration Scheme, IJB Standing Orders, Chief Officer’s Report (May 2025), and
IJB meeting minutes confirms that the governance structures described in the Integration
Scheme are fully established and operational. The Integration Joint Board (IJB) is functioning as
the central governance body, with documented evidence of regular meetings and strategic
oversight activity. Supporting committees — including the Audit and Risk Committee, Finance
and Policy Committee, and Clinical and Care Governance Group — are actively engaged in
providing assurance over financial, clinical, and operational matters. Direction-setting processes
and the role of the Strategic Leadership Team (SLT) further demonstrate that governance is not
only structured but also embedded in day-to-day delivery. The presence and activity of these
structures, with participation from both Argyll and Bute Council and NHS Highland, confirms that
the HSCP governance model is aligned with statutory requirements and is being implemented in
practice. 
22. Review of IJB meeting agendas and minutes from January and March 2025, alongside the
Direction Log and Chief Officer’s Report (May 2025), confirms that decision-making processes
within the Argyll and Bute Integration Joint Board are transparent, well-documented, and
actioned in line with good governance standards. Meeting papers are publicly available in
advance, with agendas covering strategic, financial, and operational matters. Minutes clearly
record decisions, approvals, and issued directions, demonstrating accountability and follow-
through. The Direction Log provides further assurance that agreed decisions are implemented
across both NHS Highland and Argyll and Bute Council. 
23. The approval process for the Joint Strategic Plan 2022–2025 demonstrates effective joint
decision-making and accountability between Argyll and Bute Council and NHS Highland. Review
of the Integration Joint Board (IJB) meeting minutes from 25 May 2022 confirms that the plan
was formally adopted by the IJB, with voting members from both statutory partners present and
engaged in the decision. The development of the plan itself was a collaborative process involving
input from both partners, wider stakeholders, and the local community. The inclusive approach,
as reflected in the plan’s introduction and supporting documentation, provides strong evidence
that both partners’ priorities were considered. This confirms that key strategic decisions within
the HSCP are made jointly, in line with the governance principles set out in the Integration
Scheme.
24. A review of the Integration Joint Board (IJB) Standing Orders (January 2025), the Integration
Scheme, and the Terms of Reference for relevant governance structures confirms that roles and
responsibilities between Argyll and Bute Council and NHS Highland are clearly defined and
consistently applied. The Standing Orders outline procedural rules for IJB operations, including
voting rights and delegated authority, distinguishing the responsibilities of Council and NHS
representatives. The Integration Scheme remains the statutory foundation of the partnership,
setting out governance arrangements, accountability for strategic planning, and delivery
Page 260

Page 261

9 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
responsibilities. Subcommittee Terms of Reference (e.g., for Audit and Risk and Clinical and Care
Governance) reinforce these roles by identifying specific oversight functions assigned to each
partner. Collectively, these documents ensure that duties such as budget management, clinical
governance, and operational delivery are allocated without duplication, promoting a structured
and accountable governance model within the Health and Social Care Partnership (HSCP). 
The HSCP and Argyll and Bute Council work to shared goals with integrated planning.
25. A review of key strategic documents—including the Joint Strategic Plan 2022–2025, the Joint
Strategic Commissioning Strategy, and the Digital Modernisation Strategy 2022–2025—confirms
that shared objectives are clearly embedded within the Health and Social Care Partnership’s
(HSCP) planning framework. These documents articulate joint priorities aligned to national
outcomes and demonstrate collaborative input from Argyll and Bute Council, NHS Highland, and
wider stakeholders. The Joint Strategic Plan outlines strategic goals supported by annual
progress reporting and oversight from the Strategic Planning Group. The Commissioning Strategy
reflects joint delivery intentions and locality-based planning, while the Digital Modernisation
Strategy outlines shared commitments to transformation. Further evidence from the Chief
Officer’s Report and the 2025 Integration Scheme Review highlights continued alignment and
consultation between partners in setting and refreshing strategic direction. Collectively, these
documents demonstrate a strong foundation of joint planning, monitoring, and accountability. 
26. A review of governance documents, strategic plans, and meeting records confirms that formal
joint planning processes are well established and functioning effectively within the Argyll and
Bute Health and Social Care Partnership (HSCP). The Strategic Planning Group (SPG), established
in accordance with statutory requirements, includes wide representation from both statutory
partners as well as the third sector, carers, professionals, and the public. Minutes from the SPG
meeting held on 13 March 2025, along with the Joint Strategic Plan 2022–2025 and its Year
Three Progress Report, evidence structured engagement and review processes involving all
service areas. Forward planning is supported by documents such as the March 2025 update on
the renewal of the strategic plan, which outlines a clear engagement timetable for the new plan
due in September 2025. The role of Locality Planning Groups and the senior leadership
engagement described in the Chief Officer’s Report (May 2025) further confirm that joint
planning is embedded in both operational and strategic activity. The 2025 Integration Scheme
Review complements this by illustrating a functioning partnership-led structure, with clear
evidence of shared strategic planning, priority setting, and review across all partners.
27. A review of performance reports and supporting documentation confirms that joint priorities
within the Argyll and Bute HSCP are actively monitored and reviewed through established
performance management arrangements. The Year Three Progress Report (May 2025), aligned
with the Joint Strategic Plan, includes RAG-rated assessments and service-level commentary
from across key areas such as mental health, community care, and children's services. This
structured reporting process allows the Integration Joint Board (IJB) to track progress, identify
challenges, and reprioritise as needed. Supporting evidence from the Strategic Risk Register and
Internal Audit Reports further demonstrates the integration of performance and risk monitoring,
with alignment to strategic objectives such as workforce and digital transformation. The Chief
Officer’s Report (May 2025) provides additional high-level narrative insight, reinforcing the
HSCP’s approach to joint performance assurance. Overall, this indicates that joint strategic
Page 261

Page 262

10 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
priorities are not only documented but are subject to consistent and multi-layered review across
the partnership.
28. To further strengthen performance assurance and stakeholder communication, the HSCP should
consider developing existing workforce performance monitoring arrangements so that KPIs and
RAG assessments remain clearly linked to strategic objectives and risks. This should be carried
out in collaboration with both employing bodies.
Action Plan 1 
Disagreements between partners are managed constructively through defined processes.
29. The Argyll and Bute Health and Social Care Partnership (HSCP) operates within a structured
governance framework that includes decision-making and escalation procedures, as set out in
the Integration Joint Board (IJB) Standing Orders and the Integration Scheme. These documents
establish transparent processes for meetings, voting, and formal dispute resolution, including a
clear three-stage escalation route involving senior officers, Chief Executives, and potential
referral to the Scottish Government. The absence of recent escalations suggests that informal
and operational mechanisms are functioning effectively. Supporting structures such as the Audit
& Risk Committee and Strategic Planning Group also provide forums for addressing emerging
concerns at an early stage. Furthermore, the 2025 Integration Scheme Review process itself
reflects practical use of collaborative decision-making and escalation pathways across both
partner organisations.
Although formal escalation has not been necessary during the audit period, the Chief Officer
should consider embedding this in induction for senior managers and key officers on the
escalation routes set out in the Integration Scheme, to ensure a consistent understanding across
the partnership and with wider partners. 
Action Plan 2
30. A review of relevant records, including IJB minutes (29 January 2025), the Chief Officer’s Report
(May 2025), and supporting internal audit documentation, found no evidence of formal or
informal disputes between Argyll and Bute Council and NHS Highland during the audit period.
Operational challenges, such as workforce capacity and financial constraints, are documented
and discussed openly, but appear to have been managed collaboratively without escalation.
While this may reflect effective communication and resolution at officer or committee level, the
lack of recorded disagreements limits transparency and makes it difficult to assess how issues
are consistently handled or whether patterns of concern exist. Without a mechanism to track
informal disputes or significant challenges, assurance over the practical operation of dispute
resolution procedures remains limited.
Recognising that operational issues are routinely resolved, the HSCP should consider capturing
recurring themes or patterns from partnership challenges (rather than logging every issue) to
support organisational learning and provide assurance to the IJB that risks are being managed
proactively. This would complement existing public reporting, not replace it.           
Action Plan 3
31. The Strategic Risk Register Review (January 2025) provides clear evidence that partnership-
related risks are actively identified, assessed, and monitored by the Argyll and Bute HSCP. A total
Page 262

Page 263

11 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working,
August 2025-26
of 21 strategic risks are recorded, including six categorised as ‘Very High’, such as financial
sustainability, workforce recruitment and retention, and dependencies on both NHS Highland
and Argyll and Bute Council for support services and infrastructure. Risks are explicitly mapped
to the HSCP’s Strategic Objectives (Appendix 2), ensuring alignment between risk and planning.
The register is reviewed biannually by both the Integration Joint Board (IJB) and the Audit & Risk
Committee, supporting dynamic and informed oversight. Partnership interdependencies—such
as reliance on NHS cyber security and Council HR services—are transparently documented, with
corresponding mitigations identified. This demonstrates an integrated approach to risk
governance across organisational boundaries. 
Page 263

Page 264

Appendix 1 – Action Plan 
No Finding Risk Agreed Action Responsibility / Due Date
Low
1 Performance Monitoring and Reporting 
The HSCP should continue to develop the existing
workforce performance monitoring arrangements so that
KPIs and RAG assessments remain clearly linked to
strategic objectives and risks, and reporting continues to
provide meaningful assurance to the IJB developed in
partnership with both employing bodies. 
If workforce KPIs and
RAG ratings are not
clearly aligned with
strategic objectives and
risks, there is a danger
that reporting to the IJB
will not provide
meaningful assurance.
HSCP will further
develop its performance
dashboard or scorecard
that visually aligns key
performance indicators
(KPIs) and RAG statuses
with the HSCP’s
strategic objectives and
risks.
Business Improvement
Manager 
30th April 2026
Low
2 Dispute Resolution Awareness 
The Chief Officer should embed this in induction for senior
managers and key officers on the escalation routes set out
in the Integration Scheme, to ensure a consistent
understanding across the partnership and with wider
partners 
Without embedding
awareness of escalation
routes set out in the
Integration Scheme into
senior management
induction, there is a risk
that disputes may not
be handled consistently
or effectively.
The Chief Officer will
ensure that induction
materials for senior
managers and key
officers to include a
dedicated section on
dispute resolution
processes and
escalation routes as set
out in the Integration
Scheme.
Business Improvement
Manager 
30th April 2026
Page 264

Page 265

13 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working, August 2025-26 
No Finding Risk Agreed Action Responsibility / Due Date
Low
3 Informal Issue Themes & Learning 
Recognising that operational issues are routinely resolved,
the HSCP should consider capturing recurring themes or
patterns from partnership challenges (rather than logging
every issue) to support organisational learning and provide
assurance to the IJB that risks are being managed
proactively. This would complement existing public
reporting, not replace it.
If recurring operational
issues and partnership
challenges are not
captured at a thematic
level, there is a risk that
patterns of concern may
go unnoticed.
HSCP will establish a
confidential action log
to capture informal
disputes or significant
partnership challenges,
including those resolved
without formal
escalation. 
Business Improvement
Manager (vacant) / Head
of Strategic Planning,
Performance and
technology 
30th April 2026 
Page 265

Page 266

14 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working, August 2025-26
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained. 
The definitions of each classification are as follows: 
Grading    Definition
High  A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error. 
Medium 
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.  
Low  Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives. 
VFM  An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the HSCP to achieve better
value for money (VFM). 
Page 266

Page 267

15 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – HSCP: Partnership Working, August 2025-26
Appendix 2 – Audit Opinion 
Level of Assurance  Definition 
High  Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial  Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable 
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk. 
Limited  Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance  Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 267

Page 268

This page is intentionally left blank

Page 269

1 
Argyll & Bute Health & Social Care Partnership
Internal Audit Report
November 2025
Final 
High Medium Low VFM
Number of Findings 0 7 0 0 
HSCP: Workforce Planning
Audit Opinion: Reasonable 
Page 269

Page 270

2 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL 
Contents 
1. Executive Summary ........................................................................................................................ 3
Introduction ............................................................................................................................................ 3
Background ............................................................................................................................................. 3
Scope ....................................................................................................................................................... 3
Key Dates ................................................................................................................................................ 3
Risks ........................................................................................................................................................ 4
Audit Opinion ......................................................................................................................................... 4
Recommendations ................................................................................................................................. 4
2. Objectives and Summary Assessment ........................................................................................... 5
3. Detailed Findings ............................................................................................................................ 7
Appendix 1 – Action Plan ..................................................................................................................... 11
Appendix 2 – Audit Opinion ................................................................................................................. 16 
Contact Details 
Internal Auditor: David Sullivan
Telephone:  01546 604125
e-mail:   David.sullivan@argyll-bute.gov.uk
www.argyll-bute.gov.uk
Page 270

Page 271

3 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
1. Executive Summary
Introduction
1. As part of the 2025/26 internal audit plan, approved by the Audit & Risk Committee in February
2025, we have undertaken an audit of Argyll & Bute Health & Social Care Partnership (HSCP)
system of internal control and governance in relation to Workforce Planning.
2. The audit was conducted in accordance with the Global Internal Audit Standards (GIAS) with our
conclusions based on discussions with Health & Social Care Partnership officers and the
information available at the time the fieldwork was performed. The findings outlined in this
report are only those which have come to our attention during our normal audit work and are
not necessarily all the issues which may exist. Appendix 1 to this report includes agreed actions
to strengthen internal control however it is the responsibility of management to determine the
extent of the internal control system appropriate to the HSCP.
3. The contents of this report have been agreed with the appropriate Health & Social Care
Partnership officers to confirm factual accuracy, and appreciation is due for the cooperation and
assistance received from all officers over the course of the audit.
Background
4. Workforce planning aligns changing organisational needs with people strategy by analysing
demand and supply for skills, identifying gaps, and translating these into actions that sustain the
workforce required to deliver HSCP priorities.  In line with Scottish Government guidance DL
(2022)09, plans should be structured around the national approach (e.g. the five pillars) and
aligned to the Joint Strategic Plan. 
5. This audit was carried out amid ongoing recruitment and retention pressures, rural capacity
challenges, and workforce risks on the Strategic Risk Register.  We reviewed the Strategic
Workforce Plan and the related management reports. We also assessed arrangements mainly
against DL (2022)09 (Scottish Government guidance), using the National Audit Office (NAO)
Government workforce planning framework (Sept 2025) as an external reference.
6. The scope of workforce planning for the IJB appropriately encompasses staff employed by both
Argyll & Bute Council and NHS Highland, as both groups deliver services within the HSCP and are
integral to meeting strategic objectives. Workforce risks and performance data are reported
jointly to the IJB.
Scope 
7. The scope of the audit was to provide assurance over the arrangements for workforce planning
as outlined in the Terms of Reference agreed with the Chief Officer of the HSCP on 8th
September 2025. 
Key Dates
8. The Terms of Reference provided provisional timescales for the review to take place, the actual
dates are noted below. 
Page 271

Page 272

4 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
Exhibit 1 – Key Dates
Stage Actual
Date
Terms of Reference agreed 8th September 2025
Fieldwork Commencement 8th September 2025
Draft Report issued 5TH November 2025
Management Comments received 19TH November 2025
Final Report issued 2nd December 2025
Audit and Scrutiny Committee 8th December 2025
Risks
9.  The risks considered throughout the audit were:
• SRR11 – Workforce Recruitment & Retention (Very High Risk): Inability to retain and
recruit required workforce because of Local and National Workforce shortages
• SRR16 – Support Services (very High Risk): Risk that support services do not adequately
support front line service delivery
• Audit Risk 1: Governance and oversight arrangements are not in place
• Audit Risk 2: HSCP does not provide workforce data and performance indicators on a
regular basis
• Audit Risk 3: partnership roles and responsibilities for workforce planning are not clearly
defined
• Audit Risk 4: Insufficient HR support capacity undermines the delivery and oversight of
workforce planning.
Audit Opinion
10. We provide an overall audit opinion for all the audits we conduct. This is based on our
judgement on the level of assurance which we can take over the established internal controls,
governance and management of risk as evidenced by our audit work.  Full details of the five
possible categories of audit opinion are provided in Appendix 2 to this report.
11. Our overall audit opinion for this audit is that we can take a Reasonable level of assurance.  This
means that Internal control, governance and the management of risk are broadly reliable.
However, whilst not displaying a general trend, there are areas of concern which have been
identified where elements of residual risk or weakness may put some of the system objectives at
risk.
Recommendations
12. We have highlighted seven medium priority recommendations where we believe there is scope
to strengthen the control and governance environment.  These are summarised below:
• Prepare an annual Workforce Plan progress and refresh paper, aligned to Scottish
Government guidance DL (2024)33, and present it to the IJB each autumn.
• Provide a concise “workforce at a glance” KPI summary through the most appropriate
reporting route, with management determining where this is best placed, ensuring
alignment with existing workforce reporting.
Page 272

Page 273

5 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
• Develop and maintain a single consolidated Workforce Plan action tracker, with named
owners, baselines/targets, milestones, RAG status and funding source.  Management will
agree the appropriate reporting frequency to the IJB.
• HSCP should ensure that the Scottish Government Appendix 1 ‘Indicative Content
Checklist’ (DL 2022/09) is completed and retained for the Workforce Plan.
• Develop a costed funding map jointly across NHS Highland and Argyll & Bute Council
Finance/HR, setting out estimated costs, named funding sources/budget codes, phasing,
and expected benefits/savings for each priority action.
• Develop an agency and supplementary staffing report that can be consolidated into a
single Finance–HR dashboard showing service-level spend, FTE, 12-month trends, key
drivers and named owners, with the dashboard cross-referenced within the Workforce
Report to strengthen IJB oversight.
• Undertake a joint review of HR support capacity and recruitment timeliness, led by NHS
Highland HR and Argyll & Bute Council HR in partnership with the HSCP, to clarify
service-level expectations, constraints, and improvement actions.
13. Full details of the audit findings, recommendations and management responses can be found in
Section 3 of this report and in the action plan at Appendix 1.
2. Objectives and Summary Assessment
14. Exhibit 1 sets out the control objectives identified during the planning phase of the audit and our
assessment against each objective.  
Exhibit 2 – Summary Assessment of Control Objectives 
Control Objective Link to Risk Assessment Summary Conclusion
C01 The HSCP has a
clear and up-to-
date Workforce
Plan aligned to
national and local
strategic priorities.      
SRR11
SRR16
Reasonable We reviewed the Strategic Workforce
Plan 2022–2025 and related IJB
reporting. The jointly developed plan
(Argyll & Bute Council / NHS
Highland) was produced as per
Scottish Government guidance DL
(2022)09. It follows the National
Workforce Strategy’s five pillars and
aligns with the Joint Strategic Plan,
financial planning, the Digital
Modernisation Strategy, and the JSNA
(including remote/island challenges).
It was approved by the IJB in Nov
2022 and supported by routine
quarterly workforce reports.
However, as of October 2025 no
standalone 2024 refresh/consolidated
progress report was identified despite
the Plan’s annual review
commitment: future versions
Page 273

Page 274

6 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL 
should align to the latest Scottish
Government guidance namely DL
(2024)33.
CO2 Governance and
oversight
arrangements are in
place to monitor
implementation and
progress of
workforce planning
objectives
Audit risk 1 Reasonable Governance for workforce planning is
clearly set out (Integration Scheme
and committee Terms of Reference),
workforce risks are routinely
reviewed by the Audit and Risk
committee and Integrated Joint Board
(A&RC/IJB), and multi-agency input is
evident; however, the Chief Officer’s
report lacks a simple KPI’s “at-a-
glance” and progress mapping to Plan
actions, and action tracking is
inconsistent (no single consolidated
tracker.  We also found no retained
SG DL (2022)09 Appendix-1 checklist,
and costing/funding is not shown at
action level.
CO3 Workforce data and
performance
indicators are
systematically
monitored and used
to inform planning. 
Audit Risk 2 Reasonable Quarterly reports evidence
progresses but remain high-level and
aren’t consistently tied to plan
actions, owners or milestones; several
KPIs lack targets/benchmarks and
there’s no single RAG-tracked action
tracker visible to the IJB.  While
targeted investment is evident,
there’s no consolidated, action-level
costing/funding map, and agency
spend/FTE is absent from the Q4 pack
despite ongoing reliance on
supplementary staffing.
CO4 Partnership roles
and responsibilities
for workforce
planning are clearly
defined and
coordinated across
NHS Highland and
Argyll & Bute
Council
Audit Risk 3 High Partnership roles and responsibilities
for workforce planning are clearly
defined and embedded through the
IJB, Strategic Planning Group, Clinical
& Care Governance Committee, and
Audit & Risk Committee.
CO5 HR support capacity
and arrangements
are sufficient and
effective to enable
workforce planning,
with clear
mitigations and
escalation where
gaps exist
Audit Risk 4 Reasonable Recruitment timeliness pressures are
evident, but current reporting does
not define HR support capacity,
Service Level Agreements (SLAs)
interim cover or a joint escalation
route—so links between HR capacity
and recruitment are not obvious. 
Page 274

Page 275

7 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
15. Further details of our conclusions against each control objective can be found in Section 3 of this
report. 
3. Detailed Findings
The HSCP has a clear and up-to-date Workforce Plan aligned to national and local strategic
priorities.
16. The Argyll & Bute HSCP Strategic Workforce Plan 2022–2025 was produced under Scottish
Government guidance DL (2022)09 and explicitly references the National Workforce Strategy for
Health and Social Care (2022).  It is structured around the Strategy’s five pillars—Plan, Attract,
Train, Employ, Nurture—and aligns workforce priorities with the Joint Strategic Plan and
financial planning.  The Plan was developed jointly by NHS Highland and Argyll & Bute Council
and approved by the IJB in November 2022.
17. The Plan states it will be reviewed annually in line with strategic planning cycles, however, a
standalone 2024 refresh/consolidated progress report was not identified at the time of audit. 
Future versions should align to the updated guidance DL (2024)33 issued December 2024 by the
Scottish Government.                    
Action Plan 1
18. The Plan explicitly references and aligns with the National Workforce Strategy for Health and
Social Care (2022) as recommended in DL (2022)09.  It translates national priorities—workforce
growth, wellbeing, and stronger workforce-planning capacity—into local objectives and actions
for Argyll & Bute.  A subsequent workforce planning update summarises progress against those
actions and shows how they contribute to the HSCP’s strategic priorities.
19. The Plan is clearly integrated with local strategic planning and national guidance. As
recommended under Scottish Government guidance DL (2022)09, it aligns workforce priorities
to the Joint Strategic Plan 2022–2025 and service-transformation objectives and cross-
references the Digital Modernisation Strategy with commitments on digital skills, remote/hybrid
service delivery, and technology-enabled care.  Locality needs are informed by the Joint Strategic
Needs Assessment, recognising remote and island challenges and related workforce
implications, which are translated into targeted actions.  Taken together, this shows workforce
planning is embedded within the HSCP’s overarching strategy   
Governance and oversight arrangements are in place to monitor implementation and progress
of workforce planning objectives
20. Review of governance documentation—Integration Scheme and Terms of Reference for IJB
Committees (Jan 2025, pp. 6–18)—confirms that workforce planning responsibilities are
embedded within the partnership.  The Strategic Planning Group incorporates workforce
considerations into the Strategic Plan; the Clinical & Care Governance Committee oversees
workforce factors affecting quality and safety (staffing levels, capacity, skill mix); and the Audit &
Risk Committee monitors workforce-related risks on the Strategic Risk Register, escalating to the
IJB as required.  The Integration Scheme assigns the IJB, through the Chief Officer and HR/OD
workstreams, responsibility to produce and maintain a Workforce and Organisational
Development Plan covering delegated functions.  These arrangements indicate clear
responsibilities, defined reporting routes, and regular oversight.
Page 275

Page 276

8 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
21. Review of IJB minutes and papers confirms that workforce planning is reported routinely—
typically via quarterly workforce performance reports and within wider performance/planning
updates.  A formal update was provided in May 2023; however, as of September 2025 we found
no standalone 2024 annual refresh/consolidated progress report on delivery of the Strategic
Workforce Plan, as envisaged by DL (2022)09.  Future refreshes should be prepared in line with
the updated Scottish Government guidance DL (2024)33.                        
Action Plan 1
22. Review of the Strategic Risk Register (January 2025) confirms that workforce-related risks—such
as recruitment and retention, specialist skill shortages, and challenges in attracting staff to
remote and rural areas—are recorded, graded (with several at Very High residual level), and
mapped to the HSCP’s Strategic Objectives.  Each risk sets out current mitigations (e.g. targeted
recruitment, partnerships with education providers, flexible working), and the register is
reviewed on a biannual cycle by both the Audit & Risk Committee and the Integration Joint
Board with updates provided through formal reporting.  Mitigations and residual risk levels are
tracked over time, indicating a structured process for monitoring and oversight. 
23. Review of the Terms of Reference for the IJB committees confirms multi-agency representation
(Argyll & Bute Council, NHS Highland and third sector) through the Integration Joint Board,
Strategic Planning Group and Clinical & Care Governance Committee, supporting cross-partner
oversight of workforce matters.  IJB minutes and Chief Officer reports show workforce topics
discussed with partner input.  Staff engagement is evident during development of the 2022–
2025 Workforce Plan (e.g., joint staff-side representation and consultation).
24. The Chief Officer’s Report to the IJB (28 May 2025) references several workforce-relevant
items—leadership changes and recruitment to stabilise the senior team, interim coverage for
Primary Care while a permanent Head is recruited, and training initiatives (e.g., UHI’s care-home
training to address remote and rural access).  It also notes wider context (financial pressures,
demographics) and stakeholder briefings.  The Chief Officer reporting provides the IJB with
valuable narrative updates on workforce-related pressures and initiatives.  However, it does not
present headline workforce KPIs (e.g., vacancy, time-to-hire, sickness, agency) or progress
against the Strategic Workforce Plan.  Including a brief “workforce at a glance” KPI paragraph
(with a signpost to the full Workforce Report) would give members concise, high-level
assurance. 
Action Plan 2
25. The Strategic Workforce Plan 2022–2025, developed under Scottish Government guidance DL
(2022)09, sets clear workforce priorities (recruitment and retention, succession planning,
wellbeing, training/development, accommodation/digital) and identifies material risks (ageing
profile, remote/rural recruitment, specialist shortages, sickness).  It includes a themed Strategic
Workforce Action Plan with SMART-style elements (e.g., % increase in under-25 profile, Investors
in Young People accreditation by July 2023, succession-planning toolkit with review dates,
actions to reduce placement losses via accommodation).  However, coverage is uneven, and
some actions lack explicit KPIs/baselines, named owners, timelines and funding sources.  Future
versions should align to the latest Scottish Government guidance i.e. DL (2024)33 and ensure
every risk-linked action has measurable indicators with targets, milestones/due dates, a named
owner and funding source, all maintained in a single consolidated tracker reported to the IJB.
Action plan 3
Page 276

Page 277

9 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
26. The Scottish Government guidance DL (2022)09 includes an Appendix 1 “Three-Year Workforce
Plan – Indicative Content Checklist” intended to assure completeness and alignment
(methodology used; partner engagement; quantified gap analysis; linkage to service and
financial plans; and actions structured under the five pillars).  We found no evidence that this
checklist was completed or retained when the Plan was produced.       
Action Plan 4
Workforce data and performance indicators are systematically monitored and used to inform
planning
27. Review of the Strategic Workforce Plan 2022–2025 and management reporting (including the Q4
2024/25 Workforce Report, the September 2025 Workforce Report, and IJB/SLT papers) shows
progress on several priorities—for example targeted recruitment to hard-to-fill posts, expansion
of flexible working, and delivery of digital skills training.  The September pack adds
targets/benchmarks for some KPIs (e.g., time-to-fill and sickness) and notes recruitment stage
metrics are being finalised; however, reporting remains largely high-level and is not consistently
linked to the Plan’s actions, named owners, milestones or KPIs, and coverage of
targets/benchmarks is still inconsistent.  There is still no single consolidated tracker with action-
level RAG/status visible to the IJB, and agency usage (spend and FTE) is not provided in the
workforce pack despite reliance on supplementary staffing being flagged elsewhere. 
Consequently, members lack a clear line of sight from performance data to delivery of the
Strategic Workforce Plan and associated risk mitigation.       
Action Plan 3
28. Review of the Workforce Plan and management reporting evidences investment in several
workforce priorities—such as recruitment/retention activity, leadership development, and staff
training (e.g. the UHI care-home training supported via the Care Home Collaborative Group)—
with activity funded primarily from partner core budgets and, where applicable, national
programmes (e.g. Primary Care Improvement Plan, Vaccination Transformation Programme,
Recovery & Renewal).  However, neither the Plan nor the quarterly workforce reports provide a
consolidated, action-level breakdown of costs or named funding sources for many priorities;
costs are recorded “as appropriate”, limiting assurance that all initiatives are fully and
sustainably resourced.      
Action Plan 5
29. Review of documents confirms an ongoing reliance on supplementary staffing (bank/agency)
driven by vacancies and sickness; the Workforce Plan explicitly notes this under “Supplementary
Staffing”.  While the FQ4 2023/24 Performance Report records a 21% (£50k per month)
reduction in agency nursing costs in Argyll & Bute hospitals, the 2024/25 workforce reporting set
does not provide a consolidated, service-level view of agency spend and FTE with 12-month
trends, targets and named owners.  These limits targeted action, benefits tracking and
committee oversight.       
Action Plan 6  
Page 277

Page 278

10 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning,
November 2025
Classification: OFFICIAL
Partnership roles and responsibilities for workforce planning are clearly defined and coordinated
across NHS Highland and Argyll & Bute Council
30. Partnership roles and responsibilities are evident within the Integration Scheme (Section 7),
committee Terms of Reference (IJB, Strategic Planning Group, Clinical & Care Governance, Audit
& Risk Committee), and the governance sections of the Strategic Workforce Plan 2022–2025.
They indicate that roles are clearly defined at the governance level: the IJB sets direction and
receives assurance; the Strategic Planning Group embeds workforce within the Strategic Plan;
the Clinical & Care Governance Committee oversees workforce factors affecting quality and
safety (staffing levels, capacity, skill mix); and the Audit & Risk Committee monitors workforce
risks via the Strategic Risk Register and escalates as required.  The Workforce Plan describes
oversight arrangements and workstreams supporting delivery. 
HR support capacity and arrangements are sufficient and effective to enable workforce planning,
with clear mitigations and escalation where gaps exist
31. Review of the Strategic Workforce Plan 2022–2025, the Q4 2024/25 Workforce Report, the Chief
Officer’s Report (May 2025) and the January 2025 Strategic Risk Register (SRR) evidence ongoing
recruitment timeliness pressures.  However, the documents do not define Human Resources
(HR) support capacity or service levels (SLAs), set out interim cover arrangements, or show a
joint escalation route to the IJB when HR capacity constraints arise.  As such, links between HR
capacity and recruitment timeliness / employee-relations (ER) support are not transparently
evidenced in routine reporting.             
Action Plan 7 
Page 278

Page 279

11 
Appendix 1 – Action Plan 
No Finding Risk Agreed Action Responsibility / Due Date
Medium
1 Annual Workforce Plan refresh 
The Plan commits to an annual refresh; however, as at
September 2025 no standalone 2024
refresh/consolidated progress paper was identified. 
Workforce updates appear within routine reports
rather than a single progress report.  Future refreshes
should align to updated SG guidance DL (2024)33 (Dec
2024).
If there’s no Annual
refresh, the Integrated
Joint Board can’t easily
see what’s on track, and
therefore problems may
be missed.
A standalone Workforce
Plan progress and refresh
paper will be prepared
annually, summarising
delivery against the
Strategic Workforce Plan
2022–2025 (and its
successor) and aligning to
Scottish Government
guidance DL (2024) 33. The
paper will be presented to
the IJB for approval each
autumn to maintain
visibility and assurance. 
People Partner: HSCP 
April 2026 
Medium
2 Chief Officers Report 
The Chief Officer’s Report provides valuable narrative
updates but does not include headline workforce KPIs
(e.g., vacancy, time-to-hire, sickness, agency) or a
summary link to progress against the Strategic
Workforce Plan. A brief “workforce at a glance” KPI
summary would give IJB members clear, high-level
assurance and help identify emerging issues quickly
Without a concise KPI
summary, members
may miss emerging
workforce pressures,
reduce visibility of
progress and slowing
decision-making.
Management will agree the
most appropriate reporting
mechanism for providing a
concise “workforce at a
glance” KPI summary,
ensuring alignment with
existing workforce
reporting arrangements
and avoiding duplication. 
People Partner: HSCP 
April 2026 
Page 279

Page 280

12 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning, November 2025
Classification: OFFICIAL 
No Finding Risk Agreed Action Responsibility / Due Date
Medium
3 Workforce Plan action tracker (quarterly to IJB) 
The 2022–2025 Plan includes SMART-style actions, but
coverage is inconsistent, and some actions lack explicit
KPIs/baselines, named owners, timelines and funding
sources. Future refreshes should align to DL (2024)33
and maintain a single consolidated action tracker
visible to the IJB.
Without clear
measures, ownership,
dates and funding,
actions may drift,
benefits may not be
delivered, and the IJB
cannot easily monitor
progress or hold
services to account.
A single consolidated
Workforce Plan action
tracker will be developed
to capture all agreed
workforce actions across
the HSCP. Each action will
include a named owner,
baseline/target,
milestones, RAG status,
and identified funding
source, in line with Scottish
Government guidance DL
(2024)33.
Management will
determine the appropriate
reporting frequency to
ensure the tracker provides
suitable visibility and
assurance to the IJB 
Head of Strategic
Planning, Peformance and
Technology: HSCP 
People Partner: HSCP 
April 2026 
Medium
4 Appendix 1 checklist 
Scottish Government guidance DL (2022)09 includes an
Appendix 1 “Three-Year Workforce Plan – Indicative
Content Checklist” to assure completeness
(methodology, partner engagement, gap analysis,
linkage to service/finance plans, and actions under the
five pillars). No evidence was found that this checklist
was completed or retained when the Plan was
produced/refreshed.
At the next Workforce Plan refresh, complete the
Appendix 1 checklist in full.
Without the checklist,
important requirements
can be missed, the
Integrated Joint Board
has less assurance that
the Plan is complete,
and therefore it may fall
short of Scottish
Government
expectations.
The Appendix 1 “Three-
Year Workforce Plan –
Indicative Content
Checklist” from Scottish
Government guidance DL
(2022) 09 will be fully
completed and retained as
part of the documentation
for the next Workforce
Plan refresh.
Head of Strategic
Planning, Performance
and Technology: HSCP 
People Partner: HSCP 
April 2026 
Page 280

Page 281

13 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning, November 2025
Classification: OFFICIAL 
No Finding Risk Agreed Action Responsibility / Due Date
Medium
5 Funding for Workforce Plan actions 
The Strategic Workforce Plan and quarterly workforce
reports show targeted investment (e.g., recruitment
and retention initiatives, leadership programmes, UHI
care-home training). However, they do not provide a
consolidated, action-level breakdown of estimated
costs or named funding sources. Costs are referenced
only “as appropriate,” limiting assurance that priority
actions are fully resourced and sustainable.
Without clear costs and
funding sources, priority
actions may be under-
resourced or delayed
and overspends may
occur. It also becomes
harder for the IJB to
assess value for money
and ensure the
Workforce Plan is
deliverable.
A costed funding map will
be developed jointly by
NHS Highland Finance/HR
and Argyll & Bute Council
Finance/HR, working in
partnership with the HSCP.
The map will set out, for
each priority action, the
estimated cost, named
funding source or budget
code, phasing, and
expected benefits or
savings. 
NHS Highland Finance and
HR / Argyll and Bute
Council Finance and HR 
June 2026 
Medium
6 Agency Costs 
Reliance on supplementary staffing (bank and agency)
is acknowledged in the Workforce Plan and risk
documentation. However, the 2024/25 reporting does
not provide a consolidated, service-level view of
agency spend and FTE with 12-month trends, targets,
or named owners. These limits targeted action,
benefits tracking, and IJB oversight.
Without clear,
consolidated reporting
of agency usage, costs
may rise without
prompt intervention,
and it becomes harder
to demonstrate savings
or understand the
drivers of
supplementary staffing.
Existing agency and
supplementary staffing
reporting will be
consolidated and expanded
into a single dashboard,
developed jointly with
Finance and HR. The
dashboard will provide
service-level spend and
FTE, 12-month trends, key
drivers (e.g., vacancy,
sickness), and named
owners. It will be cross-
referenced within the
regular Workforce Report
to the IJB to support
clearer oversight. 
HR Business Partner /
Finance Business Partner
(Argyll and Bute Council)
in partnership with HSCP 
April 2026 
Page 281

Page 282

14 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning, November 2025
Classification: OFFICIAL 
No Finding Risk Agreed Action Responsibility / Due Date 
7 HR and Support Services 
Recruitment timeliness pressures are evident in the
Workforce Plan, the Q4 2024/25 Workforce Report, the
Chief Officer’s Report (May 2025), and the January
2025 Strategic Risk Register. However, the documents
do not define HR support capacity, service levels (SLAs),
interim cover arrangements, or escalation routes. As a
result, the link between HR capacity and workforce
planning delivery is not clearly evidenced.
Without clear
expectations regarding
HR support capacity and
service levels,
recruitment and
employee-relations (ER)
processes may be
delayed or inconsistent,
agency costs may rise,
and the IJB has weaker
assurance that
workforce plans are
adequately supported.
NHS Highland HR and Argyll
& Bute Council HR will
jointly review HR support
capacity, recruitment
timeliness, and service-
level expectations, working
in partnership with the
HSCP. The review will
identify current
constraints, the minimum
level of support required,
and any improvement
actions or escalation routes
needed to strengthen
assurance to the IJB. 
Deputy Director of People
(NHS Highland) and Head
of Customer Support
Services (Argyll & Bute
Council), in partnership
with the HSCP 
June 2026 
Page 282

Page 283

15 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning, November 2025
Classification: OFFICIAL
In order to assist management in using our reports a system of grading audit findings has been adopted to allow the significance of findings to be ascertained. 
The definitions of each classification are as follows: 
Grading    Definition
High  A major observation on high level controls and other important internal controls or a significant matter relating to the critical success of the
objectives of the system.  The weakness may therefore give rise to loss or error. 
Medium 
Observations on less significant internal controls and/or improvements to the efficiency and effectiveness of controls which will assist in meeting
the objectives of the system.  The weakness is not necessarily substantial however the risk of error would be significantly reduced if corrective
action was taken.  
Low  Minor recommendations to improve the efficiency and effectiveness of controls or an isolated issue subsequently corrected.  The weakness does
not appear to significantly affect the ability of the system to meet its objectives. 
VFM  An observation which does not highlight an issue relating to internal controls but represents a possible opportunity for the HSCP to achieve better
value for money (VFM). 
Page 283

Page 284

16 
Argyll & Bute Health & Social Care Partnership – Internal Audit Report – Workforce Planning, November 2025
Classification: OFFICIAL
Appendix 2 – Audit Opinion 
Level of Assurance  Definition 
High  Internal control, governance and the management of risk are at a high standard. Only marginal elements of residual risk have
been identified with these either being accepted or dealt with. A sound system of control designed to achieve the system
objectives is in place and being applied consistently. 
Substantial  Internal control, governance and the management of risk is sound. However, there are minor areas of weakness which put some
system objectives at risk and specific elements of residual risk that are slightly above an acceptable level and need to be
addressed within a reasonable timescale. 
Reasonable 
Internal control, governance and the management of risk are broadly reliable. However, whilst not displaying a general trend,
there are areas of concern which have been identified where elements of residual risk or weakness may put some of the system
objectives at risk. 
Limited  Internal control, governance and the management of risk are displaying a general trend of unacceptable residual risk above an
acceptable level and placing system objectives are at risk. Weakness must be addressed with a reasonable timescale with
management allocating appropriate resources to the issues raised. 
No Assurance  Internal control, governance and the management of risk is poor. Significant residual risk and/or significant non-compliance with
basic controls exists leaving the system open to error, loss or abuse. Residual risk must be addressed immediately with
management allocating appropriate resources to the issues. 
Page 284

Page 285

Document is Restricted
Page 285 Agenda Item 11bNOT FOR PUBLICATION by virtue of paragraph(s) 14
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 286

This page is intentionally left blank

Page 287