Argyll and Bute Council
Annual Business Plan 2024 – 2025
Update Report

Page 2

Council Priorities Action Plan 2024 - 2025 
Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
People and places, our core business as a council    
Attaining and achieving at all stages; we will improve outcomes for our children and young people  
Improve educational
attainment,
achievement and
outcomes for our young
people within Argyll and
Bute to Scotland’s
upper quartile.
• Continue to challenge and support
schools proportionately. Further
refine criteria for support and
ensure increased focus on
secondary schools.
• Continue to work in close
partnership with Developing the
Young Workforce (DYW) team to
ensure young people successfully
develop the skills for life and work
required to attain sustained positive
destinations post-school.
• Continue to track young people’s
pathways within school and in the
period after leaving school, to
ensure appropriate support,
guidance and opportunities are in
place to gain and sustain positive
destinations.
• Improved levels of
attainment across
the Senior Phase
where attainment
is in line with
national data. 
• Extended range of
learning pathways
on offer for all
learners. 
• 96% of 16–19-
year-olds are in
Education,
Training or
Employment.
• We are continuing to
strengthen our
approaches to
supporting and
challenging secondary
schools to raise levels
of attainment for all. All
schools now have
more robust tracking
systems in place which
are leading to
improvement. A few
schools are continuing
to receive intensive
support around
improving attainment.
In 2 (out of 3) of these
schools, senior phase
predictions for August
2025 are showing
signs of some
improvement.

Page 3

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
• In 2024/25, Education
has further developed
its work with
Community Learning to
introduce an increased
range of wider
achievement
opportunities across
secondary schools. As
a result, 614 young
people have engaged
across seven
accredited awards,
while 718 young
people have accessed
eight non-accredited
learning activities,
including dedicated
primary-secondary
transition support.
• Skills Development
Scotland Annual
Participation Measure
published Aug 24:
94.3% of 16-19 year-
olds in Education,
Training or
Employment.

Page 4

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Educational Attainment
and Wider Achievement
– Developing the use of
all the available data
and intelligence on
each of our educational
establishments to focus
on and drive
improvement, achieving
our stretch aims (goals
to improve
opportunities and
outcomes for young
people) as agreed with
the Scottish
Government.
• Strengthen focus on learning,
teaching and assessment with
increased emphasis on secondary
sector. Continue to build staff
capacity in the interrogation and
use of data for improvement.
• Develop further use of range of
data dashboards in order to provide
accessible and meaningful data for
all schools and settings.
• Deliver targeted and universal
literacy and numeracy support for
establishments in order to raise
attainment with specific focus on
pupils residing in Quintile 1.
• Continue to support schools to
rigorously track and monitor pupil
progress and plan measurable
interventions and initiatives to raise
attainment for all whilst closing the
poverty related attainment gap.
• Stretch aims are
achieved: 
Literacy 73.5%,
Numeracy 80.5%
School Leavers
with 1 or more
pass at SCQF
Level 5 92.25%.
• School Leavers
with 1 or more
pass at SCQF
Level 6 67.75%.
Improved levels of
attainment across
the Senior Phase
where attainment
is in line with
national data. 
• Stretch Aims 23/24: 
ACEL: 
Literacy - 72.2% (up
from 67.7%) Numeracy
- 80.1% (up from
76.4%) 
Based on recent ACEL
attainment data
tracking, we are on
track to achieve our
overall stretch aims for
P1/4/7 at June 2025. 
• School Leavers: 
School Leavers with 1
or more pass at SCQF
Level 5 - 85.7% School
Leavers with 1 or more
pass at SCQF Level 6 -
66.7% (Amongst S6
leavers only, the
percentage leaving
with 1+ At level 6
increased from 85.5%
to 90.6%. Increase in
S4 leaving rates
created downward
pressure on cohort
performance).

Page 5

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Developing a broader
curriculum offer to
augment current
opportunities with a
range of wider
achievement awards
and
accreditations.  This will
have a positive impact
on leaver destinations
through inclusive, skills
- based programmes in
each secondary school.
• Schools will be supported and
challenged to develop their
curricula, underpinned by a robust
rationale taking account of place-
based resources and local labour
market data.
• Support secondary schools via UK
Shared Prosperity Funding to
ensure accredited wider
achievement opportunities exist for
every pupil at each stage of their
secondary education.
• Strengthen partnerships with
Community Learning, UHI Argyll
and Third Sector agencies to
increase wider achievement
opportunities for young people at
each stage of their secondary
education.
• Young People in
every secondary
school have the
opportunity to
engage in 1
accredited wider
achievement
programme at
each stage of their
secondary
education.
An extended
range of pathways
are in place and
opportunities for
partnership
working are
maximised. 
• All secondary schools
are now in a position to
offer young people at
least 1 wider
achievement
opportunity.
• The use of UKSPF has
been monitored
robustly to ensure best
value and appropriate
use. All schools are on
track to have utilised
this funding by the
deadline. In addition,
we will receive an
allocation next session.
We were initially
informed that this
funding stream was
coming to an end.
• Community Learning
(CL) have extended
partnership with
secondary schools. CL
active in all secondary
schools offering wider
achievement/skills
development courses.
To date in 2024-25,
there have been 198

Page 6

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
accreditations. 359
young people engaged
in either accredited or
non-accredited wider
achievement activities.
• 39 Flexible Learning
Plans (FLPs) are in
place across
secondary schools to
support disengaged
learners as a result of
partnerships with
employers and UHI
Argyll (2023-24 34
FLPs)
• Partnerships between
schools and employers
have continued to
increase in 2024-25.
As a result, a total of
380 work placements
have supported young
people to plan their
individual vocational
pathways.

Page 7

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Continuing to promote
the teaching and use of
Gaelic as set out in the
council’s emerging
Gaelic Plan for 2023.
• Education Officer and Principal
Teacher will continue to support and
challenge establishments to build
staff capacity and help to establish
Gaelic as an L2 or L3.
• Continue to signpost schools to
ESgoil support and support and
materials from other agencies such
as Education Scotland and
Storlann. Continue to work in
partnership with Ed Scot to
challenge and support schools. EO
and PT will continue to challenge
and support schools to improve the
quality of Gaelic Medium Education
and attainment for all pupils.
• Principal Teacher will continue to
deliver online language lessons
with colleagues from other
authorities. 
• Number of schools
offering Gaelic as
L2 or L3 to 80%
(dependent on
Scottish
Government).
• Through the work of
the PT, including the
additional development
of Live Lessons, 71%
of primary schools in
A&B are currently
delivering Gaelic as L2
or L3. This is an
increase of 3% since
October 2024 when
68% of schools
delivered Gaelic
Learner Education. The
Live Lessons support
schools to continue
their development of
Gaelic as L3, enabling
pupils to progress their
learning beyond the
‘beginner’ stage. The
Live Lessons enable
schools to continue
their delivery of Gaelic
as L2 and L3, thus
supporting the
Education Service to
reach our target of 80%
of all primary schools. 
• All A&B teaching staff
have regular updates

Page 8

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
from the PT to inform
staff of educational
resources and support
from partners including
eSgoil and Education
Scotland.
• Education Scotland’s
Senior Education
Officer (SEO) for
Gaelic has visited
almost all GMPE
settings to support
Learning Teaching and
Assessment (LTA).
Positive impact on
pupil attainment in
Gaelic Literacy is being
evidenced. 
• Almost all GMPE
settings have been
trained in QI Writing
strategies. This
methodology is
resulting in a positive
impact on pupil
attainment in Gaelic
writing.  
• Almost all GMPE
settings received in-
person support from

Page 9

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
the Furan Gaelic
Centre administrator.
This has had a positive
impact on pupil fluency. 
• All GMPE practitioners
now have access to the
wide range of Highland
Literacy Project
materials in Gaelic for
use in LTA. This work is
starting to have a
positive impact on pupil
attainment in GME.
Learning estate now and in the future; we will ensure our schools are effective, sustainable learning environments  
Progress a bid to the
Scottish Government to
establish a new
campus on Mull. 
• Continue to develop the business
case, undertake engagement and
site selection process for a new
Campus on Mull.
• Robust business
case in place,
communities feel
involved and
engaged in
process, site
selected and plans
progressed in line
with identified
timescales.
• LEIP application was
successful and was
accepted to LEIP
phase 3 programme in
October 2023.
Community
engagement activities
took place in
September 2024
informing the project
site selection.
Special Council
Committee meeting on
March 7th agreed the
preferred site

Page 10

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
‘Tobermory South’
(southern edge of
Tobermory with the
western boundary
adjacent to the A848).A
group called Mull
Campus Working
submitted a Judicial
Review against the
Council which was
heard in Court of
Session on 13th
October.  Work on the
project has ceased
pending outcome of
JR.
Develop the next
generation of capital
investment plan and
priorities for our school
estate.
• Service Asset Management Plan
(SAMP) for Education and delivery
of Programme by Feb 2024.  
• All programmed
work completed by
the specified date
and in line with the
allocated capital
budget.
• All capital works
completed on budget
and to timescale to
programme with
notable investment in
John Logie Baird
Primary School and
Tobermory / Hermitage
ASN Units.
Supporting children and young people with additional needs

Page 11

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Reducing the number
of children and young
people who have to
travel out-with the area
to access services by
enhancing provision
where gaps currently
exist.
• Progress planning for and set up of
four Learning Centres in areas as
identified in the ASN review of
2021/22.
• Continue to increase the number of
staff within educational settings
being CALM trained.
• Continue to offer opportunities for
staff to further develop their skill in
meeting the needs of all learners.
• Continue to
Increase the
number of children
accessing high
quality enhanced
provision within
Argyll and Bute.
• All new Learning
Centres will be
operational by August
2025 with places
allocated to children
through the ERG
allocation process.
• All schools are able to
access CALM training
and there has been
increased uptake
during session
2024/2025 from the
previous academic
session. By June 2025,
there will be an
increased number of
CALM trainers in Argyll
and Bute. This will
support educational
settings in becoming
CALM trained and
moderate the effective
application of this
training.
• All primary and
secondary schools
have been able to
access CIRCLE and
GIRFEC training.

Page 12

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Working to improve and
secure equity of
specialist provision
across Argyll and Bute
by addressing gaps
where they exist across
the education estate.
• Continue to progress plans
accordingly including recruitment of
staff.
• Continue to
increase the
number of children
accessing high
quality specialist
provision within
Argyll and Bute.
• Most new Learning
Centres already have
teaching staff in post
prior to August 2025
opening. The
remaining posts are
currently being
advertised.
• Support staff
recruitment is
underway and all
learning Centres are on
track to be fully
resourced by August
2025.
• Leaders from all
Learning Centres are
participating in the
development of a
Strategic Leadership
network for specialist
provision. The network
has identified
improvement priorities
and will be
collaborating to
develop shared
understanding on
effectively supporting
learners and how to

Page 13

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
develop high quality
specialist provision
appropriate for their
context. 
Maintaining the current
staffing complement
who support ASN in line
with our nurture stretch
aim agreed with
Scottish Government.
• Current complement of central staff-
1 Principal Teacher and 2 Teachers
will be maintained through
maintaining teacher numbers. The
number of schools engaging with
Our Children Their Nurture
Education will increase to 35.
• Stretch aims are
achieved: Literacy
73.5%, Numeracy
80.5% School
Leavers with 1 or
more pass at
SCQF Level 5
92.25%.School
Leavers with 1 or
more pass at
SCQF Level 6
67.75%.Core plus
stretch aim nurture
measure is 67%.
• There are currently 58
settings engaged with
OCTNE (52 schools
and 6 ELC providers),
with 12 of these
settings joining during
session 24/25,
exceeding the stretch
aim of 35 schools and
reflecting a growing
commitment to trauma-
informed, nurture-
based education.”
• The current
complement of central
staff – 1 Principal
Teacher and 2
Teachers – continues
to provide targeted
ASN support, aligned
with the nurture stretch
aim.
• In session 24/25,
Nurture Teachers
delivered training in
Boxall Profiles, Block

Page 14

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Based Therapy, and
PACE to staff across
multiple settings,
directly contributing to
the professional
capacity of ASN
support staff.
• The 5th cohort of
leadership training
began February 2025
with 32 participants
from 22 settings,
helping schools
prepare for OCTNE
accreditation and
sustain nurturing
practices at a strategic
level.
• Targeted nurture
intervention and
coaching has been
delivered to 8 schools
via the Coach and
Consult model,
strengthening the ASN
support network and
helping staff address
SEMH needs.
Roads and pathways; connecting to, from and within Argyll will be supported

Page 15

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Reviewing our
approach to road repair
prioritisation to make
the most effective use
of resources in the
context of budget
pressures and to
achieve the best
possible balance in
terms of strategic,
operational and
member input.
• Implement actions to increase
member input in process 
• Members seminar  • Officers have agreed a
process plan which
include an annual
members input for the
capital roads plan of
works so that a local
perspective can be
introduced.  Members
seminar took place
October 2024. 
Initiating plans for a
20mph speed limit by
working in partnership,
and in line with national
legislation, on the
rollout and delivery of a
20mph limit where that
will work best for our
communities.
• Review potential for implementing
20mph speed limits in accordance
with national priorities. 
• Number of
engagement
sessions
• Number of 20mph
schemes
introduced
• Officer appointed to
post funded by Scottish
Government and is
developing a
programme of
engagement with
stakeholders including
elected members and
community groups.
Completing a review of
parking and traffic
management/enforcem
ent to reshape
arrangements that
reflect community
needs and ambitions.
• TRO review in line with members
requests to support their
communities’ needs. 
• Report through
December 2025
EDI Committee to
obtain agreement
on proposed
review and
methodology.
• Report to EDI
committee on 18
• Report through EDI
Committee 18
December 2025 the
proposed Traffic
Regulation Orders for
the whole ABC area. 
• TRO Business day with
members October
2025 to outline

Page 16

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
December 2025 to
obtain agreement
on proposed
review and
methodology
• Review
commences.
• Start of
consultation
period.
• Statutory
consultation takes
place.
• TRO Business day
with members .
• New TROs
agreed.
proposed approach
and obtain member
feedback. Proposals
now being developed
to reflect this.
Piers and harbours  
Upgrading the council’s
harbour infrastructure
to ensure it is capable
of receiving existing
and planned new
ferries (including at
Craignure,
Fionnphort/Ruahaich,
Port Askaig, Dunoon,
Kilcreggan and
• Iona
Start work on new breakwater at Iona. 
o Capital dredging to improve
navigational access
o Replacement of the public toilet block
o Slipway repairs 
• Craignure
Complete OBC
Start preparation of FBC
• Campbeltown
• Iona
All necessary marine
licences granted
Tender go live for
management consultant
Project start
• Craignure
Complete OBC
• Campbeltown
Open new quay 
• Iona 
All necessary marine licences
have been granted, including: 
o Rock Armour Breakwater
Licence
o Capital Dredging Licence
o European Protected
Species Licence
o Basking Shark Licence. 
• A Seagrass Mitigation
and Monitoring Plan

Page 17

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Campbeltown,
Tayinloan - Gigha).
Open new quay     was approved in July
2025, with ongoing
environmental
monitoring throughout
construction
• Site mobilisation began
in March 2025. Over
120,000 tonnes of
granite rock are being
used, sourced from
Glensanda Quarry,
Ireland, and Norway.
21,000 tonnes of 1–3
tonne rock have
already been delivered
and placed to form the
base and core of the
breakwater. 
• The new toilet block is
nearing completion,
with mechanical and
electrical installations
underway.
• Craignure
• A tender for
management
consultants to lead this
next phase is expected
to go live in November
2025, with an

Page 18

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
appointment
anticipated in January
2026. 
• The cost of the project
is now  projected at
£96 million
• Gigha / Tayinloan
• The ferry terminals at
Gigha and Tayinloan
are undergoing
significant upgrades as
part of Transport
Scotland’s Small
Vessel Replacement
Project This will
modernise
infrastructure to
support new hybrid
ferries. These are two
separate but
coordinated projects
being managed by
Argyll and Bute Council
with support from RPS
Tetra Tech.
Creating a new
municipal harbour
authority in Oban,
ensuring that proposals
are submitted to
• HRO to be submitted to and agreed
by Scottish Government
• New HRO in place • The council has
submitted a Harbour
Revision Order (HRO)
to Transport Scotland
to establish a Municipal

Page 19

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Scottish ministers as
soon as possible
following consideration
by the Harbour Board in
December 2022, and
putting preparations in
place to commence
operations upon
approval by ministers.
Harbour Authority that
would cover most of
Oban Bay, excluding
the area around the
ferry terminal (which
remains under CMAL).
• The HRO is now with
Scottish Government
Ministers for
consideration. When
approved, Argyll and
Bute Council would
become the Statutory
Harbour Authority for
the newly defined area
of Oban Bay.
Seeking funding for the
procurement of new
council-operated
vessels including
Islay/Jura, Luing and
Easdale.
• Carry out assessment, specification
and costing of new vessels.  
• Request funding from Scottish
Government and/or explore other
funding opportunities.   
• Secure funding for
new vessels
based on priority
requirement.  
• Funding for new ferries
serving Jura, Luing,
and Easdale is
progressing through a
combination of local
authority planning,
regional transport
partnerships, and the
Scottish Government’s
Small Vessel
Replacement
Programme (SVRP).
• Jura Ferry

Page 20

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
The Council is actively
pursuing funding for
the design and
construction of a new
ferry for Jura
• HITRANS has
committed £1.5 million
to support planning and
infrastructure
improvements for Jura
and Luing.
• The Council is lobbying
for full funding from the
Scottish Government
and exploring options
for capital investment
through Transport
Scotland and
HITRANS. 
• Jura, Luing, and
Easdale are not
included in Phase 1 of
SVRP, which covers
seven electric ferries
for other routes (e.g.,
Gigha, Iona). However,
future phases may
include these
Finalising the demand,
economic impact and

Page 21

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
business case
assessment for the
Helensburgh Pier
strategy in 2023.
Waste and recycling services; reduce our carbon emissions  
Delivering a solution
that enables the council
to divert its
biodegradable waste
from landfill, within
2026, while seeking a
short-term derogation
to allow the PPP
contract to expire.
• Identify route to market for contract
to replace PPP
• Develop variation to existing PPP
contract to divert residual waste
away from landfill
• Procure off take and haulage
contracts for island sites
• New offtake
contracts for
landfill waste
• End of MBT at
Oban, Dunoon
and Lochgilphead
PPP sites
• Multi disciplinary
working group
established with
representatives of the
council’s legal,
procurement, financial
and waste services to
develop legally
compliant solution to
landfill ban
• Agreement reached
with current contractor,
Biffa, to alter existing
Public / Private
Partnership to allow for
closure of landfill sites
at Dunoon and
Lochgilphead, and
ending of Mechanical
and Biological
Treatment of landfill
waste
• New waste disposal
contract in place to

Page 22

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
divert waste from MAKI
and OLI to energy from
waste facilities
Encouraging
households to increase
use of recycling
services to reach at
least the Scottish
average (with service
exploring options to
stretch targets where
possible).
• Carry out marketing and publicity
campaign – e.g. Food Waste
Awareness campaign, Green July
(which will also include waste). 
• Officers review the
recycling rate to
see if the
campaign has had
an impact.  
• The Council worked
with Zero Waste
Scotland to refresh the
recycling section of our
website to streamline
our messaging and
reflect best practice. 
• A second social media
campaign took place in
June which focussed
on behaviour changes
which would help
reduce the amount of
waste going to landfill
and pointed customers
to supporting
information, either on
the council website or
third-party sites.
• Marketing will continue
with regular posts, and
campaigns, throughout
the year. 
Housing

Page 23

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25  
Supporting the
provision of over 1,000
affordable homes by
2027 (247 in 2022/23
plus at least 750
additional homes over
the life of the Strategic
Housing Investment
Plan).
• Continue to monitor housing
completions and produce annual
housing land audit.
• Deliver 247
affordable
completions in
22/23
• 107 affordable housing
units were completed
in 23/24 so less than
the programmed
delivery, but this
reflects a natural
variation and is the
latest period for which
data is available.
Exploring additional
options to increase the
availability of all tenures
of housing - mid market
rents, shared equity,
affordable by design
and other
developments - in the
area.
• Explore title burdens and phase 1
site investigations for possible Rural
growth Deal Funded housing for
sale and principal home occupancy
• Complete site
investigations.
• Establish
satisfactory title.
• Phase 1 site
investigations are
complete.  Title
investigations involving
Church of Scotland are
ongoing.
Considering the
implementation of short
term lets control zones
to open up more
housing availability.
• Short-term let licensing regime and
policy in place. 3308 applications
received to be determined.
• 100% of
applications
determined or
deemed granted.
STL applications
mapped on GIS,
to support
consideration of
planning control
areas.
• Draft policies being
devised

Page 24

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Continuing to support
households to improve
energy efficiency and
tackle rising living costs
through annual
investment through and
implementation of the
Home Energy Efficiency
Programme in Argyll
and Bute.
• Renew contractors and manage
delivery of HEEPS:ABS
programme.
• Complete delivery
of 24/25 HEEPS
ABS allocation.
• 24/25 HEEPS ABS
allocation was 100%
spent.
Developing the
opportunity for the
council to become a
Rural Housing Body -
where it would be more
directly involved in the
delivery of housing or
land for housing.
• Council has already been awarded
Rural Housing Body status.   
Communities; we will build and strengthen our communities as attractive, vibrant places to live, work and do business  
Creating area plans for
all our communities,
reflecting investment
opportunities and local
service prioritisation.
• Launch Aspiring Places platform
• Comprehensive support to be
provided by the Community
Development team to local
community bodies to facilitate the
development of Local Place Plans.
• Evaluation of
engagement of
platform
undertaken and
reported to Policy
and Resources
Committee
• Development of
support package
for communities,
• Further to Members
agreement in
September 2024, the
‘Aspiring Places –
Community Projects in
Argyll and Bute’ digital
platform was
successfully launched
in March 2025 and
over 150 community

Page 25

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
including
webinars, master
classes and a
dedicated web
page with links to
resources,
enabling
communities to
develop Local
Place Plans.
groups registered, and
over 100 project
proposals have been
published.
• An evaluation has been
completed and will be
reported to the Policy
and Resources
Committee on the 04
December 2025.
• Close working between
Development Planning
and Community
Development teams to
prepare a
comprehensive support
page for communities
developing Local Place
Plans, complementing
the Local Development
Plan 3
process.  Support to
communities included
master classes and
webinars, development
of a newsletter and
community of practice.

Page 26

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Seeking ways of
securing more
community wealth
building opportunities
across Argyll and Bute
and supporting
communities to gain
maximum benefit from
developments in their
area.
• Arrange community wealth building
meeting with anchor organisations
within Argyll and Bute. Share
Council’s contract plan with them to
determine if any collaborative
opportunities, publish our contract
plan on website. Share our
community benefit guidance, and
wishlist with them to enable best
practice to be rolled out across all
of Argyll and Bute public sector
organisations. Invite our anchor
organisation colleagues to
collaborate with us on appropriate
contracts/frameworks.
• Contracts
awarded to local
suppliers (%) –
Target 20%. 
For 2023/24 the %
was 17.8%. For
2024/25 (Q1&Q2)
– 18.3%
As this % includes
all contracts,
whether a local bid
was submitted or
not we also report: 
-Tenders won by a
local supplier
where a local
supplier has
placed a bid (%) -
no target.
For 2023/24 the %
was 59.5%. For
2024/25 (Q1&Q2)
– 65.2%
-Local suppliers
bidding for
business with the
council (% of bids
received) - Target
20%.
For 2023/24 the %
• Community wealth
building event took
place.  A Community
Wealth Building Action
Plan is currently being
prepare by specific
partner organisations
within the Argyll and
Bute Community
Planning Partnership
aligned to the key
content within the draft
CWB Bill published on
20th March 2025 by the
Scottish Government
which was out for
consultation until 23rd
May 2025 on whether it
should become an Act
of Parliament.
• Our contract plan was
shared and as a result
collaborative contracts
are taking place with
our partner
organisations. Our
contract plan is
published on the
website to allow local

Page 27

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
was 15.2%.  For
2024/25 (Q1&Q2)
– 14.4%
-Increase the
number of
community
benefits that are
delivered through
contracts we
award locally – no
target.
For 2023/24 – 74
community
benefits achieved. 
For 2024/25
(Q1&Q2) – 31
-Local spend – no
target.
For 2023/24 local
spend was 35.8%.
For 2024/25 (Q1)
– 28.4%
businesses to see what
we are looking to buy
in the coming year
ahead. Our community
benefit guide has been
shared with our
community wealth
building partners along
with a link to our
wishlist. Further
engagement has taken
place at area
community planning
partnership meetings.
• Contracts awarded to
local suppliers (%) –
Target 20%. 
2024/25:18.7%
As this % includes all
contracts, whether a
local bid was submitted
or not we also report: 
-Tenders won by a
local supplier where a
local supplier has
placed a bid (%) - no
target.  2024/25:69.8%

Page 28

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
-Local suppliers
bidding for business
with the council (% of
bids received) - Target
20%.  2024/25:13.5%
-Increase the number
of community benefits
that are delivered
through contracts we
award locally – no
target.   89 community
benefits were delivered
via our council
contracts in 2024/25
compared to 74 in
2023/24 which is an
increase of 15. 
-Local spend – no
target. The total
Procurement-related
spend with known local
suppliers in 2024/25
was £72.7m. The local
procurement-related
spend has increased
from the previous two
years, (£65.7m in
2023/24 and £60.8m in
2022/23).

Page 29

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Seeking to maximise
scope for community
involvement and
participation, including
exploring the role that
community transfers
can play. 
•  Argyll and Bute Community
Planning Partnership to agree the
actions for the ABOIP priority
outcome of Community Wellbeing,
which has a long-term objective to:
support community cohesion, the
sustainability of community services
and a voice in collective decision
making. 
• Explore the potential to have the
Community Development Team
work in collaboration with Estates
Team to ensure effective
Community Asset Transfer, dealing
with requests from community
groups in a timeous manner and
providing comprehensive support.
• An Engaging Communities
Framework will be developed and
launched to facilitate and support a
corporate approach to community
engagement, including the
development of training and support
materials
• Members of the Community
Planning and Community
Development team will undertake
training in Art of Hosting techniques
to enable a suite of practical
methods of community engagement
•  Community
Planning
Partnership
agreement and
endorsement of
Community
Wellbeing actions. 
• Community Asset
Transfer requests
will be considered
and processed
according to the
requirements of
section 5 of the
Community
Empowerment
(Scotland) Act
2015. The
Community Asset
Transfer web page
will be updated as
required with an
annual report
produced and
uploaded for
2024/25.
• Launch of the
Engaging
Communities
Framework with
• In December 2024, the
CPP agreed a set of 6
actions under the
priority outcome of
Community Wellbeing. 
• Successful trial project
of Community
Development team and
the Estates team
collaboration
throughout 2024-25
ensuring the
Community Asset
Transfer process
worked effectively
ensuring requests from
community groups
were dealt with
timeously with
comprehensive
support. The
Community Asset
Transfer web page has
been updated with
detailed information on
the process for
Community Transfer
Bodies and an annual
report has been
produced for 2024/25.

Page 30

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
to be incorporated into professional
practice.
appropriate
training and
support materials
developed to
enable a corporate
approach.
• Members of the
Community
Planning and
Community
Development
team will
successfully
undertake training
in Art of Hosting
techniques, will
cascade learning
to the full team
and will use these
techniques in
community
engagement
practice.
• Engaging Communities
Framework developed,
launched in January
2026 with online
training on LEON for
staff.
• Staff members have
successfully trained in
Art of Hosting,
contributing to the
development of a
Community of Practice
in Argyll and Bute.
Skills developed for
use in community and
partnership settings
shared with colleagues
i.e. Heretohearyou, and
practical application of
techniques has
encouraged new forms
of community
participation.
Potential and growth; turning opportunities into reality    
Economic development

Page 31

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Achieving sign-off of the
Rural Growth Deal
business and cases
and begin delivering
priority projects like The
Marine Industry
Training Centre, UAV
Drone Hub and
Seaweed Academy. 
• Deal signed on
10th March 2025.
Conditional
endorsement of
Rothesay Pavilion
FBC achieved;
FQ4 grant claims
submitted to
Central
Government.
• Rural Growth Deal
signed on 10th March
2025.  Drawdown of
2024/25 Q4 funding to
support Rothesay
Pavilion.  Most OBC’s
now endorsed and
FBC’s being
progressed for KSS
and Tobermory
Housing projects. 
Further work
necessary to deliver
Action Plan and
achieve full
endorsement of
Rothesay Pavilion
FBC.
Securing of Levelling
Up funding for projects,
including Argyll and
Bute Western Seaboard
Marine Gateways
Initiative, Whisky
Islands and Lorn
Economic Growth
Zone.
• Funding re-branded as Community
Regeneration Partnership following
change in UK Government. 
£20.3m of funding committed to
Argyll and Bute and negotiations
are on-going with UKG and
external partners to agree final
priority projects.  All funding
requires to be committed by
2026/27 and as such, projects
require to demonstrate
deliverability within these
• Confirmation of
funding via
Community
Regeneration
Partnership;
Support UKG
fieldwork visits.
Identify a long-list
of project options.
• These applications
were not successful,
but Community
Regeneration
Partnership funding,
circa £20m, was
secured by Argyll and
Bute Council.

Page 32

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
timescales.  UKG will undertake a
business case for Ministerial sign
off.
Implement £4.5m Argyll
and Bute UK Shared
Prosperity Fund
Investment Plan.    
• The Argyll and Bute
UK Shared Prosperity
Fund (UKSPF)
Investment Plan,
2022-2025 has now
been concluded; all
project spend had to
be completed by the
end of March 2025
and all final claims to
the UK Government
need to be submitted
by the 1st May 2025.
• A final transition year
of UKSPF has been
agreed for 2025/26.
The Transition Year
UKSPF Investment
Plan (further additional
activity for current
projects in the 2022-25
plan) was approved by
the Policy and
Resources Committee
on 20th February 2025
and the MOU was
signed between the

Page 33

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
UK Government and
Argyll and Bute
Council mid-March
2025.
Complete site
development of
Helensburgh Waterfront
project securing long-
term economic benefit.
• Development of site. • Completion of
Helensburgh
Waterfront
Development.
• Marketing of the site
completed and
preferred developer
selected. Site
investigations
completed and utility
connections secured.
Awaiting outcome of
Judicial Review which
was heard in Court of
Session on 4th July –
cannot proceed until
verdict passed.   
Deliver the £15m
Campbeltown Flood
Prevention Scheme.
• A multi-element £15–15.9m
Flood Protection Scheme for
Campbeltown to reduce risk
from
the Millknowe and Balgreggan B
urns and from local surface-
water flooding. To be delivered
as four main work packages: 
1. Millknowe flood storage
reservoir (flood-storage
basin/earthworks). 
2. Upsizing/renewal of
the Dalaruan Street culvert. 
•  Delivered
as
designed: the
key engineered
elements (flood
storage
at Millknowe,
culvert
upsizing, SuDS
at The
Meadows, and
the Burnside
• The Campbeltown
Flood Protection
Scheme was complet
ed and certified in
May 2024, transitioning
into the defects and
monitoring phase. 
• The Property Flood
Resilience
(PFR) programme
continues into 2025–
26, focusing on

Page 34

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
3. Surface Water Management
/ SuDS at The Meadows. 
4. Works at Burnside Square
(public-realm + flood
interventions). 
In addition, some property-level
flood protection measures to be
provided to selected
properties. Argyll and Bute
Council+1 
• Programme / timing:
construction phases to be
completed through 2023–early
2024 with the council reporting
the project on course to be
complete around February
2024, with additional requested
works and follow-up items into
later 2024. 
Square
interventions).
• Hydraulic
modelling and
design quality
• Communit
y / co-
benefits.  
property-level
protection. 
• Revised total cost:
£15.925 million (up
from £15.215 m). 
• Main works
delivered: Millknowe fl
ood
storage, Dalaruan culv
ert, Burnside Square
improvements,
and SuDS at The
Meadows. 
• Benefits noted:
reduced flood risk,
environmental
resilience, and
community economic
benefit. 
• AECOM’s detailed
hydraulic modelling
was used to design the
fluvial and surface
water elements, and
sources indicate the
design intent was
aligned with delivering
improved flood
resilience for the town.
That modelling

Page 35

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
supports the
expectation that the
interventions will
materially reduce flood
risk from Millknowe/
Balgreggan and from
surface water. (Note:
modelling = projected
performance; real-
world success is best
judged after significant
storm events and
monitoring.) Institution
of Civil Engineers
(ICE)+1 
• Community-benefit
activities were reported
in Sept 2024 Argyll and
Bute Council+2Argyll
and Bute Council+2 
•  Funding & cost:
original secured
funding was
~£15.215m with 80%
Scottish Government
support and 20%
council contribution;
later estimates in 2024
put the projected cost
slightly higher (c.

Page 36

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
£15.9m) and an extra
~£710k was listed
for additional works
Regenerate the
waterfront of Ardrishaig.
•  • Support on-going
negotiations with
potential
developers of
Gleaner Oil Site.
Ardrishaig North Public Realm
works were completed April
2023. Negotiations are on-
going with potential developer
at former Gleaner Oil Site. 
Note this site is owned by
Scottish Canals. £250k of
funding available via Tarbert
and Lochgilphead
Regeneration fund to support
remedial works at Gleaner
site subject to an endorsed
business case.
Driving forward
additional strategic
economic development
projects including
progression of the
Dunbeg housing,
commercial and
infrastructure projects
and the North Lorn
Economic Growth Zone
through the Lorn Arc
Tax Incremental
Finance (TIF) scheme.
• Multiple planning applications
submitted for Housing /
infrastructure and commercial area
at Dunbeg. Determination expected
by spring 2026.
• Planning Applications submitted
and approved for business
development and infrastructure at
Oban Airport.
• TIF infrastructure element of FBC at
Oban Airport Approved by Council
and Scottish Gov. 
•   Agreement
reached with
Scottish Gov to
both extend the
TIF income stream
period by 10years
and allow for the
retention of
income prior to
project initiation. 
• This significantly
derisks the TIF
projects and gives
confidence to the
• Oban Airport TIF
element of business
park agreed – awaiting
finalised costs for non
TIF elements to be
agreed by Full Council
in Nov 2025. Once that
takes place the project
will move into the
implementation phase.
• Dunbeg once planning
applications have been
determined, assuming
approval, the

Page 37

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Council to make
investments.
infrastructure design
and detailed costing
phase will begin. This
will inform the final
FBC which is expected
to be presented to
Council’s P&R
Committee early to mid
2027.
Implement
Conservation Area
Regeneration Scheme
(CARS) Projects in
Dunoon, Lochgilphead,
Tarbert and
Helensburgh.
• Proposed Heritage and Place
scheme being developed for
Tarbert.  This will require Council
match funding of circa £635k over 5
years. Development phase
currently being progressed with
formal bids scheduled to be
submitted in August 2025.
Lochgilphead CARS in delivery
stages and due to complete in
March 2026.  At least 4 priority
buildings will be completed in
Lochgilphead.  Helensburgh CARS
is also in the delivery stages and
works to the first two priority
buildings commenced in September
2024. 
• Dunoon now complete.
• Continued
delivery of
Lochgilphead and
Helensburgh
CARS schemes;
• Complete Dunoon
CARS
• Progress Tarbert
HPP
Development
Phase.
• Lochgilphead in final
stages of delivery with
works to priority
buildings complete. 
Helensburgh is
ongoing with all priority
buildings now on-site. 
Funding bids have
been submitted to
NHLF and HES for an
HPP scheme in Tarbert
and funding
announcements will be
made in early 2026.
Maximising community
economic and
employment
The Council’s role is a consultee in this
project which is being led by Scottish
Power Renewables.  
This is led by Scottish Power
Renewables and is going
through consultation stage.

Page 38

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
opportunities from the
Islay Scotwind offshore
wind project.
The Council continues to
engage with the developer via
forums such as ABRA.  The
Council are also continuing to
monitor community benefit
opportunities linked to
renewable developments.  We
have also been engaging with
developers around potential
operations and maintenance
opportunities aligned with this
development.
Preparing an options
appraisal for
implementation of a
transient visitor levy.  
• A draft Visitor Levy
(VL) Scheme will
be supported by
impact
assessments align
to the impact on
businesses
providing
accommodation,
communities,
visitors and the
council who will
need to collect a
levy if as VL
Scheme is
introduced in
across Argyll and
Bute. The options
• The formal consultation
on a draft Visitor Levy
(VL) Scheme for Argyll
and Bute will
concluded on
Thursday, 10th April
2025. 
It is a statutory
requirement to prepare
a Consultation Report,
which will include
updated impact
assessments as
outlined in Appendix 2
of the Special Council
paper, 20th December
2024.

Page 39

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
are to introduce a
levy or not, further
to a formal 12-
week consultation
period from
January to March
2025, again if the
consultation is
approved by
elected members.
The content of this
Consultation Report, to
be prepared by
external consultants,
will provide
recommendations if a
VL Scheme should be
introduced across
Argyll and Bute based
on the evidence
gathered during the 12-
week public
consultation.
Commercial services; making assets work now    
Increasing commercial
development of
business and retail
space, including the
Kilmory Industrial Park,
and identifying other
opportunities wherever
possible.
• Develop business cases for 
* Kilmory Industrial Park 
* Kilarrow House, Bowmore 
* Lorn House, Oban
• Complete
construction of
Kilmory Business
Park.
Completion of
business cases for
Lorn House and
Kilarrow House.
• Kilmory Business Park
under construction with
forecast completion in
Quarter 1 2026
• Killarow and Lorn
House being
considered for housing
delivery options.
Exploring additional
commercial
opportunities at Oban
Airport.
• Develop business case, apply for
planning consent for business units.
• Completion of
Detailed Business
Case for Oban
Airport.
• FBC (contractor
verified costs)
completed, planning
consent received, , Tier
1 contractor appointed,
design team appointed,

Page 40

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
TIF & Community
Regeneration
Partnership funding
approved.
• 26th November Council
meeting for Full
Business Case
approval and award of
contracts.
Delivering the Our
Modern Workspace
project (OMW),
rationalising the council
estate and facilitating
hybrid working
solutions.
• Progress delivery of OMW project
in Lochgilphead, Oban and
Rothesay.
• Completion of
physical works at
Rothesay and
Oban
Production of an
approved by ELT
Phasing Plan for
changes to offices
in Lochgilphead
and Ardrishaig.
• Works at Rothesay and
Oban are complete.
• Dunoon works are
underway at Argyll
House with completion
forecast February
2026.
• Design work at
Lochgilphead and
Ardrishaig progressing
Leading the
development and
creation of
Craigendoran Business
Park as a business,
engineering and
innovation hub.
• Site investigations to be completed.
Site infrastructure and utilities to be
designed and costed.
• Completion of the
pre-development
investigative
works to confirm if
the site is suitable
and viable for
development
• Site investigations
completed,
infrastructure and
utilities designed and
costed. Outcome has
identified challenges
with site utilities and
flood risk requiring
further investigation.

Page 41

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
Exploring opportunities
for sharing services
where possible - both to
help grow our income
through providing our
expertise and
enhancing service
delivery in communities
where we need to
source options from
elsewhere.
• Implementation of new shared
management structure with HSCP
in relation to Hostels and care
homes for catering and cleaning.
• Completion of 1
year review of
shared
management
structure.
• The HSCP Shared
Management Project
concluded at the end of
June 2025. While
elements of the project
were successful, HSCP
SLT made the decision
that a return to pre-pilot
arrangements would be
more sustainable.
Driving down further
our own carbon
emissions, achieving
net zero by 2045 and
exceeding our target of
a 75% reduction by
2030, building on our
good track record in
relation to combatting
climate change,
through the delivery of
our Decarbonisation
Plan.
• Progress Argyll and Bute
Decarbonisation Plan for 2022-
2025.
• Commission new
Decarbonisation
Plan (Routemap to
Net Zero).
• Draft under
development with
Climate Change Board
Securing Carbon
Literate Organisation
status by the end of
2023, including
completion of the rollout
of carbon literacy
• Securing Carbon Literate
Organisation by the end of 2023
Deliver more training - application
of Carbon Literate Organisation
submitted and await outcome.
• Completed  • Complete.  Exploring
renewal and
enhancement options

Page 42

Priority Activity 2024/25 Success Measure
2024/25
Annual Update 2024/25
training to all
councillors. 
Partnership and Action - everyone has a part to play in Argyll and Bute’s success 
In our Priorities for the Council Term 2022 to 2027, we set out our areas for action to deliver our vision for Argyll and Bute. There
are elements of that vision which require action from other agencies at all levels - from our communities right up to national
government. We will commit to working in partnership wherever we need to as well as calling on others, with responsibility, to take
the action that is required to safeguard Argyll and Bute’s success. This included: 
1. Continuing to build up our strong track record in partnership working and seeking new ways of working with communities,
other organisations, and the third and private sectors.  
2.  Continuing to work in partnership with further education and higher education providers in Argyll and Bute to ensure young
people have access to high quality innovative educational opportunities that support local employers and the Argyll economy.
3.  Lobbying for support for the higher-than-average energy costs faced by Argyll and Bute communities.  
4.  Pressing the case for retaining delivery of care services locally, where community knowledge, relationships and experience
are best placed to identify and meet local needs and local accountability.  
5.  Calling for funding support to tackle challenges in local social care delivery - including recruitment, retention and
development of care staff in communities - rather than centralisation of services.  
6.  Continuing to call for planning, construction and opening of the replacement route at the Rest and Be Thankful within the life
of this Scottish Parliament. 
7.  Working in partnership with the Rothesay Pavilion Charity Trust to lobby for funding to complete the refurbishment of the
Pavilion.  
8.  Seeking additional funding support to address the unprecedented severe weather damage to the sea defences supporting
Bute’s main island roadway at Ardbeg.  
9.  Working with the Community Planning Partnership to develop a Climate Change Strategy for the region as a whole.  
10.  Adding our voice to those of our local government colleagues across Scotland to call on national government for fair funding
settlements which enable councils to deliver the services that matter to communities and reinforcing the need for recognition
of the vital contribution that local government makes to national priorities and Scotland’s overall success.

Page 43

11.  Delivering the Argyll and Bute Employability Partnership Delivery Plan for 2024-25 through working in partnership with third
sector delivery partners. – Update October 2025 – The ABEP Delivery Plan has concluded with hard stop spend at the end
of March 2025.  The No One Left Behind (NOLB) grant offer letter for 2025/26 has been received from the Scottish
Parliament and a revised Annual Investment Plan, which will include third sector partner delivery, was submitted by 30th April
2025.  There was no Scottish Government requirement to prepare a more detailed ABEP Delivery Plan for 2025/26 (just an
Investment Plan).  However, the ABEP members still wanted to put in place a local and shortened ABEP Delivery Plan,
which was prepared further to an ABEP workshop session on 20th May 2025 and will hopefully be endorsed by the Argyll and
Bute CPP Management Committee on 5th December 2025.