Page 1

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES                                   16 DECEMBER 2025 
PERFORMANCE REPORTING UPDATE 
1.0 EXECUTIVE SUMMARY 
The aim of this paper is to update the Audit and Scrutiny Committee with the
progress on the review of the Council’s Performance and Improvement
Framework (PIF) that is being undertaken as part of the Performance
Excellence Project. The main overall deliverable from this project will be an
updated PIF which includes a simplified, compliant and proportionate approach
to performance and improvement activities.    
The report highlights work completed to date on activities in Phase Two of
the project and plans for the outstanding work packages. 
It is recommended members note and consider the progress of the
Performance Excellence Project and activities to conclude Phase Two.

Page 2

ARGYLL AND BUTE COUNCIL            AUDIT AND SCRUTINY COMMITTEE 
CUSTOMER SUPPORT SERVICES                                    16 DECEMBER 2025 
PERFORMANCE REPORTING UPDATE 
2.0 INTRODUCTION 
2.1 The performance excellence project was commenced in May 2020 with the
aim of reviewing the council’s approach to performance and improvement
activities and simplifying them where possible. The report sets out the
progress of Phase Two of the project and the planned activities to bring the
remainder to a conclusion and deliver the updated Performance and
Improvement Framework (PIF). 
3.0 RECOMMENDATIONS 
3.1 It is recommended members note and consider the progress of the
Performance Excellence Project and activities to conclude Phase Two. 
4.0 DETAIL 
4.1 The initial performance excellence project commenced in May 2020 with a
mandate to review the council’s performance management approach and
implement a simplified, proportionate and compliant approach which meets
the needs of a transforming council. Following a Best Value audit, the project
included within its scope actions to improve performance reporting to provide
a balanced picture of long term trends in performance against targets, and to
use benchmarking information to drive continuous improvement.   
4.2 The project then progressed to phase two with the overall objective to present
an updated Performance and Improvement Framework which is in alignment
with the Connect for Success Change Programme, further simplifies our
approach to performance and improvement, while maximising the use of the
technology available to us. Specifically, the project included five work streams
which are largely based on the existing elements of the Performance and
Improvement Framework.  Progress on activities contained within each
workstream is detailed below. 
4.3  Workstream One: Planning 
This workstream focused on the design and development of plans that support
delivery of the council’s strategic outcomes. As the Administration changed
during the project, a new Corporate plan was developed which had not been

Page 3

in the original scope of the project.  The pre-existing priorities were continued
for the financial year 2024 – 2025 as the new Corporate Plan took effect within
this period.  This workstream focused on the following activities: 
- Review of corporate strategies and mapping of strategic outcomes – work
on this continues.  Sessions have taken place with senior leaders to
agree rationalisation of strategies and a template for future and reviewed
strategies.
- Development of a team plan template to manage service standards
aligned with strategic objectives – an initial pilot was undertaken by the
HR and OD team using MS planner  for non-core business, followed by
further pilots in Catering and Cleaning and Education with overall positive
feedback and most challenges coming from the behavioural shift in using
the tool as opposed to the method. At Senior Leadership Forum in
November 2024 the proposed approach using planner for non-core
business activities was shared and a survey was issued seeking
feedback.  Strategic Management Team considered this and agreed that
HROD should consider current use of MS Teams by Third Tier Managers
and assess the potential challenges of transitioning to using Planner –
this will be incorporated into ongoing work with Third Tier Managers.
- Development of an updated Corporate Improvement Plan – this has been
delivered. 
4.4 Workstream Two: Review and Evaluation 
This workstream focused on the design and development of methods to
review and evaluate performance at all levels. The aim of this work is to
replace the scorecards that were previously in pyramid with a new approach
that reduces manual input by collecting data at source wherever possible.
This work took a themes AND teams approach, seeking to use the data
platform to allow presentation of performance data in various formats for a
variety of purposes and audiences.  This workstream continues in regard to
core business.  Following a successful pilot, work is underway to implement
reporting dashboards across the remaining teams, to be in place across the
whole of the council service areas by 31 March 2026. 
4.5 Workstream Three: Reflection 
This workstream focused on the learning that informs our plans for change
and improvement. Other pieces of work took place on across the council,
such as the review of our approach to Consultation and Engagement and our
review of Service Design to embed the principles of Scottish Approach to
Service design, which inform this project. Specifically within the scope of this
work stream were 
• Self-assessment activities – a review of pilots was completed and
templates are available for self-assessment in team and thematic
approaches. 
• Annual Performance Review – a review of how we collect and reflect
on annual performance at individual, team and organisational level
took place and a revised approach to our Council Annual report is in

Page 4

development with options to be submitted to DMTs and SMT for views. 
Finalisation of this work package is dependent on agreement of
Corporate Outcome Indicators. 
• Benchmarking – a review of our approach to the use of benchmarking
including the Local Government Benchmarking Framework (LGBF)
within our Performance and Improvement Framework.  This work
package has been delayed.  Work is taking place with managers to
explore their use of the LGBF. 
• Lessons learned – development of an approach that allows lessons
learned to be shared widely across teams.  This activity has been
descoped from the project due to parallel work in regard to
establishment of a Corporate Programme Office and will be
incorporated into that. 
4.6 Workstream 4: SPI Compliance / Public Performance Reporting 
This workstream focused on how we tell people about our performance in a
way that is proportionate and meets the requirements set out in the Accounts
Commission’s Statutory Performance Direction. The objective is for timely
and meaningful public performance reporting and scrutiny.  This workstream
was completed in respect of the December 2024 statutory direction which
covers the period up to and including 2027 – 2028.  Additionally, work has
taken place to review and update our website Performance pages which is in
the process of going live. 
4.7 Workstream 5: Updated Performance and Improvement Framework 
The final deliverable of the project will be an updated Performance and
Improvement Framework which reflects the work carried out in each of the
work streams above.  This will incorporate all the resources currently
available and in development.  The updated PIF will be presented on
conclusion of the other work packages. 
4.8 Due to unanticipated delays as a result of dependencies relating to work
requiring senior leadership involvement and direction, there is a need to
extend specific elements of this project.  It is anticipated that the outstanding
work packages will be complete by the end of March 2026 and sooner in
some cases.   
5.0 CONCLUSION 
5.1 In conclusion, this report outlines the progress made in regard to Phase Two of
the Performance Excellence Project and arrangements to bring the outstanding
work packages to a conclusion.

Page 5

6.0 IMPLICATIONS 
6.1 Policy   this project will deliver an updated Performance and
Improvement Framework (PIF) for the Council. 
6.2 Financial   none arising directly from this report. 
6.3  Legal    the Council has a statutory duty to ensure Best
Value and to comply with the Accounts
Commission’s SPI directive. 
6.4  HR      none arising directly from this report. 
6.5 Customer Service   delivery of Best Value through our Performance and
Improvement Framework ensures that our
customers get value for money in the services that
we provide them with. 
6.6 Risk    failure to deliver this project would result in the
Council not having performance and improvement
arrangements in place that satisfy the needs of a
transforming Council. 
6.7 Climate Change  none arising directly from this report. 
6.8  Fairer Scotland Duty  none arising directly from this report - any Integrated
Impact Assessments required will be completed as
part of the project. 
6.9 Equalities - protected  none arising directly from this report - any Integrated 
Characteristics   Impact Assessments required will be completed as
part of the project. 
6.10 Consumer Duty  none arising directly from this report. 
6.11 Island Communities   none arising directly from this report - any Integrated
Impact Assessments required will be completed as
part of the project. 
6.12 Children’s Rights and  none arising directly from this report - any Integrated 
Wellbeing    Impact Assessments required will be completed as
part of the project. 
Kirsty Flanagan
Executive Director with responsibility for Customer Support Services 
Policy Lead Councillor Mark Irvine 
28 October 2025

Page 6

For further information contact: 
Jane Fowler, Head of Customer Support Services, jane.fowler@argyll-bute.gov.uk 
Jennifer Coyle, Senior HR Business Partner, jennifer.coyle@argyll-bute.gov.uk