Page 1

STATEMENT OF CASE 
FOR 
ARGYLL AND BUTE COUNCIL 
LOCAL REVIEW BODY
23/0002/LRB 
APPEAL AGAINST CONDITION 6 OF PLANNING PERMISSION 22/000693/PP 
ERECTION OF DWELLINGHOUSE AND FORMATION OF VEHICULAR ACCESS 
LAND SOUTH OF BROOMHILL, BREADALBANE STREET, OBAN 
3 APRIL 2023

Page 2

STATEMENT OF CASE 
The Planning Authority is Argyll and Bute Council (‘the Council’). The appellants are Mr and
Mrs Andrew Cripps (“the appellants”). 
Planning permission 22/00693/PP for erection of dwellinghouse and formation of vehicular
access on land to the south of Broomhill, Breadalbane Street, Oban (“the appeal site”) was
granted under delegated powers on 20 December 2022. 
Condition 6 of the planning permission has been appealed and is subject of referral to a
Local Review Body. 
DESCRIPTION OF SITE 
The site is located to the east of the public UC68 Breadalbane Street, sitting lower in the
landscape than the public road.  The site slopes down from west to east towards Eas Brae
with a covering of scrub and small trees, with no trees of merit within the site.  The site is
bounded by dwellinghouses to its northern and southern boundaries.  In order to achieve
suitable development levels there is a need for retention, such as Gabion Baskets, running
parallel with Breadalbane Street along the north / south axis of the site. 
Permission was granted for a dwellinghouse comprising a single storey, pitched roof
structure taking a ‘T’ shaped form oriented parallel with the public road reflecting the
established development in the surrounding area.   
During the processing of the application the Council’s Structures Team brought to the
attention of the Planning Authority that there was Japanese Knotweed on the site which
required to be addressed.  In this regard the Agent submitted a survey which identified that,
whilst Japanese Knotweed was not present within the site, it was present within the wider
area.  Accordingly, the Planning Authority imposed a condition on the grant of permission
requiring the developer to retain a Watching Brief for Japanese Knotweed during the
proposed development. 
Condition 6 stated: 
“Notwithstanding the provisions of Condition 1, a Watching Brief for the presence of
Japanese Knotweed on site shall be kept during the construction period of the development. 
If Japanese Knotweed is found on the site regard should be had to the guidance provided by
SEPA with regard to on-site management of Japanese Knotweed and knotweed infested
soil”. 
Condition 6 is now being appealed by the Appellants.   
STATUTORY BASIS ON WHICH THE APPEAL SHOULD BE DECIDED
Section 25 of the Town and Country Planning (Scotland) Act 1997 provides that where,
in making any determination under the planning Acts, regard is to be had to the
development plan, the determination shall be made in accordance with the plan unless
material considerations indicate otherwise.  This is the test for this application.

Page 3

STATEMENT OF CASE 
Argyll and Bute Council considers the determining issues in relation to the case are as
follows: 
 Whether or not Condition 6 should have been imposed on the grant of planning
permission. 
The Report of Handling (Appendix 1) sets out the Council’s detailed assessment of the
application in terms of Development Plan policy and other material considerations. 
REQUIREMENT FOR ADDITIONAL INFORMATION AND A HEARING 
It is not considered that any additional information is required in light of the appellant’s
submission.  The issues raised were assessed in the Report of Handling (ROH) which is
contained in Appendix 1.  As such it is considered that Members have all the information
they need to determine the case. Given the above and that the proposal is small-scale, has
no complex or challenging issues, and has not been the subject of any significant public
representation, it is not considered that a Hearing is required. 
COMMENT ON APPELLANT’S SUBMISSION 
In summary, the appellants contend that the Planning Authority did not use due diligence
when they imposed Condition 6 on the grant of planning permission as it had been
demonstrated, through the report submitted to the Planning Authority during the processing
of the application, that Japanese Knotweed was not present on the application site. 
The Planning Authority noted in the ROH that the survey submitted in support of the
application identified that, whilst Japanese Knotweed was not present within the site at the
time that the survey was carried out i.e. on 21 April 2021, it was present within the wider
area. 
In this regard, due to the invasive nature of Japanese Knotweed, and the speed in which it
can spread, the Planning Authority imposed a condition requiring the developer to retain a
Watching Brief for Japanese Knotweed during the construction period of the proposed
development.  Members are reminded that planning permissions have an initial life of three
years from the date upon which permission is originally granted. Just because there might
not be Japanese Knotweed on a site at the start of year one does not mean that the site can
be guaranteed to be free of Knotweed by the end of year three (or beyond if the permission
is renewed).  
The condition was imposed as a matter of good practice and in accordance with national and
local planning and environmental policy with no requirement for the Appellant to do anything
in order to comply with the condition, only a requirement for good site management practice
to be undertaken during the construction period of the proposed development to ensure that
the site remains free from Japanese Knotweed.  If Japanese Knotweed were to be found
during the construction period, the only requirement for the Appellant would be to comply
with SEPAs guidance to the on-site management of Japanese Knotweed and Knotweed
infested soil, again in line with local and national planning and environmental policy. If
Knotweed continues to be absent from the site at the time of construction then there is no
requirement on the developer to do anything at all. 
Officers have sought to explain the very limited implications of the planning condition with
the appellant’s agent. This is a planning condition designed to reflect current best practice
having proper regard to national biodiversity considerations.

Page 4

CONCLUSION 
Section 25 of the Town and Country Planning Act 1997 requires that all decisions be made
in accordance with the development plan unless material considerations indicate otherwise. 
Taking all of the above into consideration, as set out in the ROH appended to this Statement
of Case, it remains the view of the Planning Service that Condition 6 was imposed
appropriately in order to ensure that the development site remained free of Japanese
Knotweed.  This condition is considered to comply with the appropriate legal tests for the
imposition of planning conditions. 
Taking account of the above, it is respectfully requested that the application for review be
dismissed.

Page 5

APPENDIX 1 
Argyll and Bute Council
Development & Economic Growth 
Delegated Planning Application Report and Report of Handling as required by
Schedule 2 of the Town and Country Planning (Development Management
Procedure) (Scotland) Regulations 2013 relative to applications for Planning
Permission or Planning Permission in Principle 
Reference No: 22/00693/PP
Planning Hierarchy: Local 
Applicant: Mr and Mrs Andrew Cripps 
Proposal: Erection of Dwellinghouse and Formation of Vehicular Access 
Site Address:  Land South of Broomhill, Breadalbane Street, Tobermory, Isle of
Mull    
DECISION ROUTE 
Section 43 (A) of the Town and Country Planning (Scotland) Act 1997 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission 
 Erection of dwellinghouse 
 Formation of vehicular access 
(ii) Other specified operations 
 Connection to public water main 
 Connection to public drainage system 
(B) RECOMMENDATION: 
Having due regard to the Development Plan and all other material considerations,
it is recommended that planning permission be granted subject to the conditions
and reasons appended to this report. 
(C) CONSULTATIONS:   
Argyll and Bute Council - Roads Authority 
Report dated 10/06/22 advising no objection to the proposed development subject
to conditions being imposed on the grant of permission to secure the appropriate
construction of the access at the junction with the public road, clearance of visibility
splays and provision of an appropriate parking and turning area within the site.

Page 6

Argyll and Bute Council – Structures Team 
Finalised response dated 11/11/22 advising that they do not have any specific
comments but advised that the footprint of the building and associated
infrastructure should not encroach onto the embankment that retains the road and
that as there is Japanese Knotweed on the site which requires to be addressed 
Scottish Water 
Letter dated 14/06/22 advising no objection to the proposed development which will
be served by the Tobermory Water Treatment Works and the Tobermory Waste
Water Treatment Works.  Scottish Water do however advise that further
investigations may be required once formal applications for connection are
submitted to them for consideration. 
Scottish Environment Protection Agency (SEPA) 
Letter dated 14/06/22 advising no objection to the proposed development on flood
risk grounds. 
JBA Consulting Ltd (JBA)
Report dated 24/06/22 advising no objection to the proposed development subject
to a condition being imposed on the grant of permission to secure a suitable
surface water drainage scheme. 
The above represents a summary of the issues raised.  Full details of the
consultation responses are available to view via the Public Access section of the
Council’s website. 
(D) HISTORY:   
17/00180/PP
Erection of dwellinghouse and formation of vehicular access – Granted: 21/08/17 
(E) PUBLICITY:   
The proposal has been advertised in terms of Regulation 20 and Neighbour
Notification procedures, overall closing date 07/07/22. 
(F) REPRESENTATIONS:   
Two representations have been received regarding the proposed development. 
Elizabeth MacIver, Oran na Mara, Breadalbane Street, Tobermory (11/06/22)
Dr V. Linnerman - by e-mail only (20/06/22) 
Summary of issues raised: 
 Advising that the boundary line between Dunard and Oran na Mara has been
shown incorrectly in the application. 
Officer Comment:  This has since been amended by the Agent only requiring an
amendment to the blue line indicating the other land in the ownership of the
Applicant and note the red line delineating the application site.

Page 7

 How does the proposed access affect the boundary wall of the neighbouring
dwellinghouse? 
Officer Comment: This is not a material planning matter in the consideration of
this application but a matter between the developer and neighbouring property. 
 Concerns over the drainage to serve the development as the main drain under
the site runs slowly and this could be affected by the proposed increase in use. 
Officer Comment: Scottish Water was consulted on the proposed development
and raised no objection to connection to their infrastructure.  With regards to
surface water drainage, the Council’s flooding advisors JBA Consulting Ltd
requested that a condition be imposed on the grant of permission to secure a
suitable scheme for the treatment of surface water drainage. 
 Concerns over the mature beech tree within the neighbouring ground which is
close to the proposed parking area, how will this be affected by the proposed
development. 
Officer Comment: This is not a material planning matter in the consideration of
this application but a matter between the developer and neighbouring property. 
The above represents a summary of the issues raised.  Full details of the letters
of representation are available to view via the Public Access section of the
Council’s website. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Statement: No  
(ii) An appropriate assessment under the
Conservation (Natural Habitats) Regulations
1994:   
No  
(iii) A design or design/access statement:    Yes  
(iv) A report on the impact of the proposed
development e.g. Retail impact, transport
impact, noise impact, flood risk, drainage
impact etc:  
No   
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   No   
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  No

Page 8

(J) Section 25 of the Act; Development Plan and any other material
considerations over and above those listed above which have been taken
into account in the assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account
in assessment of the application. 
‘Argyll and Bute Local Development Plan’ Adopted March 2015 
LDP STRAT 1 – Sustainable Development 
LDP DM 1 – Development within the Development Management Zones
(Settlement Zone) 
LDP 3 – Supporting the Protection Conservation and Enhancement of our
Environment 
LDP 8 – Supporting the Strength of our Communities 
LDP 9 – Development Setting, Layout and Design 
LDP 10 – Maximising our Resources and Reducing our Consumption 
LDP 11 – Improving our Connectivity and Infrastructure 
‘Supplementary Guidance to the Argyll and Bute Local Plan 2015’ (Adopted
March 2016) 
Natural Environment 
SG LDP ENV 6 – Impact on Trees / Woodland 
Landscape and Design 
SG LDP ENV 14 – Landscape 
Historic Environment and Archaeology 
SG LDP ENV 17 – Development in Conservation Areas and Special Built
Environment Areas (SBEAs) 
General Housing Development 
SG LDP HOU 1 – General Housing Development Including Affordable Housing
Provision 
Sustainable Siting and Design 
SG LDP Sustainable – Sustainable Siting and Design Principles 
Resources and Consumption 
SG LDP SERV 2 – Incorporation of Natural Features / SuDS 
Addressing Climate Change 
SG LDP SERV 7 – Flooding and Land Erosion – Risk Framework 
Transport (Including Core Paths) 
SG LDP TRAN 4 – New & Existing, Public Roads & Private Access Regimes

Page 9

SG LDP TRAN 6 – Vehicle Parking Provision 
(ii)  List of all other material planning considerations taken into account in
the assessment of the application, having due regard to Annex A of
Circular 3/2013. 
 Scottish Planning Policy (SPP), 2014
 Argyll and Bute Sustainable Design Guidance, 2006 
 Consultation Responses 
 Third Party Responses 
 Argyll and Bute proposed Local Development Plan 2 (November 2019) 
The unchallenged policies and proposals within pLDP2 may be afforded
significant material weighting in the determination of planning
applications at this time as the settled and unopposed view of the
Council. Elements of the pLDP2 which have been identified as being
subject to unresolved objections still require to be subject of
Examination by a Scottish Government appointed Reporter and cannot
be afforded significant material weighting at this time. The provisions of
pLDP2 that may be afforded significant weighting in the determination
of this application are listed below: 
 Policy 35 – Design of New and Existing, Public Roads and Private
Access Regimes
 Policy 36 – New Private Accesses
 Policy 39 – Construction Standards for Private Access
 Policy 78 – Woodland Removal 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  No    
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  No 
(M) Has a sustainability check list been submitted:  No 
(N) Does the Council have an interest in the site:  No 
(O) Requirement for a hearing:  No    
(P) Assessment and summary of determining issues and material
considerations 
The principle of a dwellinghouse on this site has been established by the granting
of planning permission reference 17/00180/PP on 21st August 2017 which remains
live and capable of implementation on site due to the extension to planning
permissions put in place by the Scottish Government in response to the Covid 19
pandemic.

Page 10

The current application is seeking to secure permission for an amended design to
that approved under the previous permission.   
In terms of the adopted ‘Argyll and Bute Local Development Plan’ (LDP) 2015 the
application site is located within the Key Settlement of Tobermory where Policy
LDP DM 1 gives encouragement to sustainable forms of development on
appropriate sites subject to compliance with other relevant policies and
supplementary guidance (SG). 
Policy LDP 3 assesses applications for their impact on the natural, human and built
environment.  The site is within the Tobermory Conservation Area requiring the
provisions of SG LDP ENV 17 to be considered which seeks to ensure that
proposed developments does not detract from the appearance or character of the
Conservation Area. 
Policy LDP 8 supports new sustainable development proposals that seek to
strengthen communities with SG LDP HOU 1 expanding on this policy giving
support to new housing in the settlements on appropriate sites provided there are
no unacceptable environmental, servicing or access issue. 
Policy LDP 9 seeks developers to produce and execute a high standard of
appropriate design and ensure that development is sited and positioned so as to
pay regard to the context within which it is located.  The Sustainable Siting and
Design Standards expand on this policy seeking development layouts to be
compatible with, and consolidate the existing settlement and take into account the
relationship with neighbouring properties to ensure no adverse privacy or amenity
issues. 
Policy LDP 11 supports all development proposals that seek to maintain and
improve internal and external connectivity by ensuring that suitable infrastructure is
delivered to serve new developments.  SG LDP TRAN 4 and SG LDP TRAN 6 of
the LDP and Policies 35, 36 and 39 of pLDP2 expand on this policy seeking to
ensure developments are served by a safe means of vehicular access and have an
appropriate parking provision within the site. 
The site located to the east of the public UC68 Breadalbane Street, sitting lower in
the landscape than the public road.  The site slopes down from west to east
towards Eas Brae with a covering of scrub and small trees, with no trees of merit
within the site.  The site is bounded by dwellinghouses to its northern and southern
boundaries.  In order to achieve suitable development levels there will need to be
retention, such as Gabion Baskets, running parallel with Breadalbane Street along
the north / south axis of the site. 
The extant permission shows a modest, single storey, pitched roof dwellinghouse
taking a ‘T’ shaped form finished in white render and natural stone to the walls with
a natural slate roof.   
The current application is seeking to secure permission for an alternative design for
the site proposing a single storey, pitched roof structure taking a ‘T’ shaped form
but with a larger footprint than that previously approved.  The dwellinghouse has
been oriented parallel with the public road reflecting the established development in
the surrounding area.  Finishing materials comprise a mix of white render and
vertical timber cladding to the walls with a natural Spanish slate roof.  Windows are
alu-clad timber windows with alu-clad and composite doors.

Page 11

Through the granting of the previous permission, which remains live and capable of
implementation on site, the site has been deemed to represent a suitable
opportunity for development with a single dwellinghouse within the defined
Settlement of Tobermory. 
The amended design subject of the current application is considered to be equally
acceptable to that previously approved being of an appropriate scale, form and
massing, incorporating traditional elements and finishing materials which will
ensure that it integrates well within the site and wider landscape and will not detract
from the appearance or setting of the wider Tobermory Conservation Area.  The
proposal is considered to be in accordance with policies and guidance set out
above. 
The application proposes a new vehicular access spurring from the public
Breadalbane Street to serve the proposed development to which the Council’s
Roads Engineer raised no objection to subject to conditions being imposed on the
grant of permission to secure the appropriate construction of the access at the
junction with the public road, clearance of visibility splays and provision of a parking
and turning area for two vehicles within the site.  The application shows the
requisite parking and turning area within the site and therefore there is no need for
this element of the proposal to be conditioned.  With a condition to secure the
appropriate construction of the access at the junction with the public road, and
clearance of visibility splays, the proposal is considered to be acceptable in terms
of Policy LDP 11, SG LDP TRAN 4 and SG LDP TRAN 6 of the LDP and Policies
35, 36 and 39 of pLDP2 detailed above. 
During the processing of the application a comment was sought from the Council’s
Structures Team (ST) due to the proximity of the site to the public road.  Further
information was sought from the ST in the form of a section and topographic
information in order to allow them to assess the impact of the proposed
development on the public road.  The Agent provided a section through the site and
updated the site plan with levels in order to assist the ST.  In their response the ST
team advised that they do not have any specific comments but advised that the
footprint of the building and associated infrastructure should not encroach onto the
embankment that retains the road and that as there is Japanese Knotweed on the
site this requires to be addressed.  A section has been provided showing
development adjacent to, but not encroaching onto the embankment and this will
be reinforced by a condition imposed on the grant of permission.  A survey has
been submitted which identifies that whilst Japanese Knotweed is not present
within the site it is present within the wider area.  In this regard a condition will be
imposed requiring the developer to retain a Watching Brief for Japanese Knotweed
during the proposed development. 
The application proposes connection to the public water main and public drainage
network within the control of Scottish Water.  In their response to the application
Scottish Water raised no objection to the proposal which will be serviced from the
Tobermory Water Treatment Works and the Tobermory Waste Water Treatment
Works where there is currently sufficient capacity, however Scottish Water advise
that further investigations may be required once applications for formal connections
are submitted to them for consideration.  An informative will be attached to the
grant of permission making the Applicant aware of Scottish Waters comments.  In
this regard the proposal is considered to be acceptable in terms of Policy LDP 10
which seeks to ensure that proposed developments are served by suitable
infrastructure.

Page 12

The site is within an area identified as having potential to flood and accordingly
comments were sought from SEPA and the Council’s flooding advisors, JBA.  In
their response SEPA raised no objection on flood risk grounds advising that the
topographic level information provided demonstrates that the site has a steep
gradient sloping down towards the watercourse and that the site is elevated several
metres above the banks.  JBA raised no objection to the proposed development
subject to a condition being imposed on the grant of permission to secure a suitably
designed schemed for the treatment of surface water drainage in accordance with
CIRIA C753 which should include mitigation for surface water flood risk.  With a
condition to secure the requirements of JBA the proposal is considered to be
acceptable in terms of Policy LDP 10 and SG LDP SERV 7 which seek to ensure
that proposed developments are not at risk of flooding. 
The proposed development will have no materially adverse impact upon the historic
environment including (but not necessarily limited to) the
historic/architectural/cultural value and/or setting or other specified qualities of any
listed building, any scheduled ancient monument, any garden and designed
landscape, any conservation area or any special built environment area. Neither
will the proposed development result in any material harm to the natural
environment including (but not necessarily limited to) the special
environmental/habitat/geological or other specified qualities of any site of special
scientific interest, any special protection area, any ‘Ramsar’ site, any national or
local nature reserve, any designated area of wild land, any marine consultation
area, any area of semi-natural ancient woodland, any carbon and peatland area or
any tree preservation order. 
The development has been assessed against all of the above potential constraints
and designations and has been determined to raise no issues or concerns except
for any specifically referred to within this summary assessment and it is
recommended that planning permission is granted subject to the conditions
appended to this report. 
(Q) Is the proposal consistent with the Development Plan: Yes 
(R) Reasons why Planning Permission Should be Granted: 
The amended design subject of the current application is considered to be equally
acceptable to that previously approved being of an appropriate scale, form and
massing, incorporating traditional elements and finishing materials which will
ensure that it integrates well within the site and wider landscape and will not detract
from the appearance or setting of the Tobermory Conservation Area.   
There are no infrastructural constraints which would preclude the proposed
development. 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan, and there are no other material considerations of sufficient
significance to indicate that it would be appropriate to withhold planning permission
having regard to Section 25 of the Act. 
(S) Reasoned justification for a departure to the provisions of the Development

Page 13

Plan 
N/A 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland:
No   
Author of Report: Fiona Scott Date: 13/12/22 
Reviewing Officer: Tim Williams Date: 20/12/22 
Fergus Murray
Head of Development and Economic Growth

Page 14

ADDITIONAL CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO.
22/00693/PP 
1. PP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on
the application form dated 01/04/22, supporting information and, the approved
drawings listed in the table below unless the prior written approval of the planning
authority is obtained for an amendment to the approved details under Section 64 of
the Town and Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Existing Location Plan  100 D  30/11/22
Site Plan  101  B 01/09/22
Proposed Plans & Elevations  200   04/04/22
Site Section  400   01/09/22
Design Statement – 2 PAGES    04/04/22
Invasive Non-Native Species Survey
Report Management Plan – 19
PAGES 
23/11/22 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
Note to Applicant: 
Please note the advice and guidance contained in the consultation response from
Scottish Water details of which is available to view via the Public Access section of
the Council’s website.  Should you wish to discuss any of the points raised in the
response you are advised to contact Scottish Water direct. 
2. Vehicular Access 
Notwithstanding the provisions of Condition 1, the proposed access shall be formed
in accordance with the Council’s Roads Standard Detail Drawing SD 08/004a and
shall include visibility splays of 2.4 metres to point X by 42 metres to point Y from the
centre line of the proposed access. The access shall be widened to 5.5 metres for a
length of 10 metres and surfaced with a bound material in accordance with the stated
Standard Detail Drawing. Prior to work starting on site the access hereby approved
shall be formed to at least base course standard and the visibility splays shall be
cleared of all obstructions such that nothing shall disrupt visibility from a point 1.05
metres above the access at point X to a point 0.6 metres above the public road
carriageway at point Y. The final wearing surface on the access shall be completed
prior to the development first being brought into use and the visibility splays shall be
maintained clear of all obstructions thereafter. 
Reason: In the interests of road safety. 
Note to Applicant: 
A Road Opening Permit under the Roads (Scotland) Act 1984 must be obtained from

Page 15

the Council’s Roads Engineers prior to the formation/alteration of a junction with the
public road.  
3. Gabion Retaining Wall 
Notwithstanding the provisions of Condition 1, full details, in plan form, of the
proposed gabion retaining wall shall be submitted and approved in writing with the
Planning Authority.  Thereafter the development shall be undertaken in accordance
with the approved details unless otherwise agreed in writing with the Planning
Authority. 
Reason:  In the interests of visual amenity. 
4. Public Road Embankment 
Notwithstanding the provisions of Condition 1, no part of the development shall
encroach onto the embankment that is retaining the public road. 
Reason:  In the interests of road safety in order to protect the integrity of the public
road. 
5.  Sustainable Drainage System 
Notwithstanding the provisions of Condition 1, the development shall incorporate a
surface water drainage system which is consistent with the principles of Sustainable
urban Drainage Systems (SuDS) compliant with the guidance set out in CIRIA’s
SuDS Manual C753 including mitigation for surface water flood risk.  The requisite
surface water drainage shall be operational prior to the development being brought
into use and shall be maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and
to prevent flooding. 
Note to Applicant: 
Further advice on SuDS can be found in SEPA’s Standing Advice for Small Scale
Development – www.sepa.org.uk.  
6. Watching Brief for Japanese Knotweed 
Notwithstanding the provisions of Condition 1, a Watching Brief for the presence of
Japanese Knotweed on site shall be kept during the construction period of the
development.  If Japanese Knotweed is found on the site regard should be had to the
guidance provided by SEPA with regard to on-site management of Japanese
Knotweed and knotweed infested soil. 
Reason:  To ensure the development site is clear of Japanese Knotweed and to
prevent the spread of this non-native invasive species through development works. 
Note to Applicant: 
Further advice on the treatment of Japanese Knotweed can be found on SEPA’s
website: www.sepa.org.uk.  
7. Landscaping

Page 16

No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the
Planning Authority. The scheme shall include details of: 
i) Location, design and materials of proposed walls, fences and gates;
ii) Surface treatment of proposed means of access and hardstanding
areas;
iii) Any proposed re-contouring of the site by means of existing and
proposed ground levels.
iv) Proposed hard and soft landscape works. 
The development shall not be occupied until such time as the boundary treatment,
surface treatment and any re-contouring works have been completed in accordance
with the duly approved scheme. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme during the first planting season following the commencement of
the development, unless otherwise agreed in writing by the Planning Authority. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity.

Page 17

APPENDIX TO DECISION APPROVAL NOTICE 
Appendix relative to application 22/00693/PP 
(A) Has the application required an obligation under Section 75
of the Town and Country Planning (Scotland) Act 1997 (as
amended):
No 
If Yes: The terms of the Section 75 obligation may be viewed on the Council’s
website at www.argyll-bute.gov.uk  by recalling the application reference
number on the Council’s Public Access Module and then by “Clicking”
Section 75 Obligation under the attached correspondence or by viewing the
Public Planning register located at Planning Services, 1A Manse Brae,
Lochgilphead, Argyll, PA31 8RD. 
(B) Has the application been the subject of any “non-material”
amendment in terms of Section 32A of the Town and
Country Planning (Scotland) Act 1997 (as amended) to the
initial submitted plans during its processing.
No 
(C) Is the proposal consistent with the Development Plan? Yes 
(D) Summary justification statement for approval of planning permission 
The proposal is considered to be consistent with the relevant provisions of
the Development Plan, and there are no other material considerations of
sufficient significance to indicate that it would be appropriate to withhold
planning permission having regard to Section 25 of the Act.