MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE held BY MICROSOFT TEAMS on WEDNESDAY, 22 APRIL 2026 
Present: Councillor Gordon Blair (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Kieron Green
Councillor Amanda Hampsey 
Councillor Graham Hardie
Councillor Paul Donald Kennedy
Councillor Reeni Kennedy-Boyle 
Attending: Stuart McLean, Committee Manager
David Walker, Solicitor
Sandra Davies, Major Applications Team Leader
Arlene Knox, Senior Planning Officer
Francis Newton, Senior Planning Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Audrey Forrest, Daniel Hampsey,
Fiona Howard, Andrew Kain, Dougie Philand and Peter Wallace. 
2. DECLARATIONS OF INTEREST 
Councillor Paul Kennedy declared a financial interest in respect of the report dealt with at
item 4 of this Minute – Civic Government (Scotland) Act 1982: Taxi Fare Scale Review. 
He advised that although he was a Taxi Driver, as no decisions were being taken on the
fares at this meeting, he would remain in the meeting for this item. 
3. MINUTES 
a) The Minute of the Planning, Protective Services and Licensing Committee held on 18
March 2026 at 11.00 am was approved as a correct record. 
b) The Minute of the Planning, Protective Services and Licensing Committee held on 18
March 2026 at 2.30 pm was approved as a correct record. 
c) The Minute of the Planning, Protective Services and Licensing Committee held on 30
March 2026 was approved as a correct record subject to the following amendments: 
Rewording of paragraph 5 at page 27 of the Agenda Pack to now read as “Mr
Anderson offered further perspective, explaining that when towing gear northwards up
the Kilbrannan Sound, sailing yachts had right-of-way over fishing vessels under
navigational rules.  He stated that fishing vessels could not move eastward due to the
presence of hard rock and therefore could not avoid the fish farm site easily when
meeting other marine traffic.  He also noted that while creelers used static gear in
some circumstances, towing gear near the fish farm created substantially more risk
than working with static gear.” 
Change “she” to “he” at the beginning of the 2nd sentence of the 2nd paragraph at page
28 of the Agenda Pack.

Page 2

4. CIVIC GOVERNMENT (SCOTLAND) ACT 1982: TAXI FARE SCALE
REVIEW 
In terms of Section 17 of the Civic Government (Scotland) Act 1982, the local authority
requires to fix maximum fares and other charges in connection with the hire of taxis
operating in their area.  The fares were last reviewed by Members on 18 December 2024
and took effect on 22 April 2025.  The next fare scale will need to come into force in
October 2026. 
Consideration was given to a report seeking approval of the commencement of the next
review of taxi fares and other charges. 
Decision 
The Committee agreed: 
1. to commence the review of fares in order that this could be completed within the 18
months required in terms of the Act; and 
2. that the consultation required in terms of the Act would be in writing. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 22 April 2026, submitted) 
5. ESB ASSET DEVELOPMENT (UK) LTD: SCOTTISH GOVERNMENT
SECTION 36 CONSULTATION FOR WEST TORRISDALE WIND FARM
COMPRISING OF UP TO 9 WIND TURBINES WITH A TIP HEIGHT OF UP
TO 149.9 METRES WITH A PREDICTED OUTPUT OF UP TO 6 MW PER
WIND TURBINE, INSTALLATION OF BATTERY ENERGY STORAGE
SYSTEM (BESS) OF UP TO 20 MW OF ENERGY STORAGE AND
ANCILLARY INFRASTRUCTURE: TORRISDALE (REF: 25/00043/S36) 
The Senior Planning Officer spoke to the terms of the report which provided a
recommended response to the Scottish Government’s Energy Consents Unit (ECU)
Section 36 Consultation for West Torrisdale Wind Farm. 
This report reviews the policy considerations which are applicable to this proposal and the
planning merits of the development, the views of bodies consulted by the Scottish
Government along with other consultations undertaken by the Council, and third party
opinion expressed to the Scottish Government. 
The Committee was asked to agree the recommended response to the ECU set out in the
report. 
Decision 
The Committee agreed that the ECU be notified accordingly that: 
1. Argyll and Bute Council objected on the grounds that the proposal would have an
unacceptable significant landscape and visual impact upon residents and the integrity
of the East Kintyre Local Landscape Area contrary to the provisions of National
Planning Framework 4 (NPF4) Policy 4d and 11e and Argyll and Bute Local
Development Plan 2 (LDP2) Policy 71 – Development Impact on Local Landscape
Areas and Argyll & Bute Landscape Wind Energy Capacity Study.

Page 3

2. Argyll and Bute Council objected on the grounds that the Applicant had failed to
resolve SEPA’s holding objection and that the proposal would therefore have an
adverse impact on peat contrary to the provisions of Policies 11 – Energy, 3
Biodiversity, 5 – Soils and Policies 30 – The Sustainable Growth of Renewables and
79 – Protection of Soil and Peat Resources of LDP2. In the event that consent was
granted it was expected that any conditions recommended by NatureScot, SEPA,
RSPB Scotland, the Argyll District Salmon Fishery Board and the Local Biodiversity
Officer were attached to the consent. 
3. Argyll and Bute Council objected on the grounds that the Applicant had failed to
resolve Highlands & Islands Airports holding objection and that the proposal would
therefore have an adverse aviation impact contrary to the provisions of Policy 11 –
Energy of NPF4 and Policies 30 – The Sustainable Growth of Renewables and 43 –
Safeguarding of Aerodromes, of the LDP2. 
4. Argyll and Bute Council objected on the grounds that the Applicant’s Peat Landslide
Hazard Risk Assessment had failed to satisfy Ironside Farrar and that the proposal
would have an adverse Peat Landslide Hazard contrary to the provisions of Policies 11
– Energy, 3 Biodiversity, 5 – Soils and Policies 30 – The Sustainable Growth of
Renewables of and 79 – Protection of Soil and Peat Resources of LDP2. 
5. Argyll and Bute Council objected on the grounds that the Applicant had failed to satisfy
the requirements of Scottish Forestry and that the proposal would have an adverse
impact on Forestry contrary to the provisions of Policies 11 – Energy and 6 – Forestry,
woodland and Trees of NPF4, and Policies 30 – The Sustainable Growth of
Renewables; 77 – Forestry, Woodland and Trees and 78 – Woodland Removal of the
LDP2. 
6. Argyll and Bute Council had no objection in respect to archaeological impact, subject
to a condition to secure a written scheme of investigation being attached to any grant
of consent. 
7. Argyll and Bute Council had no objection in respect to Biodiversity Impact, subject to
conditions to secure the recommendations of the Local Biodiversity Officer on the
Revised Outline Habitat Management Plan and the Species Protection Plan being
attached to any grant of consent. 
8. Argyll and Bute Council had no objection in respect to noise impact, subject to suitably
worded conditions to secure a BS4142 assessment for the BESS, limit the noise
levels, tonality, and amplitude modulation (operational turbine noise and amplitude
modulation conditions) to control noise levels from the proposal and provide
appropriate noise mitigation as recommended and agreed by the Council’s Noise
Consultant. 
9. Argyll and Bute had no objection in respect to flood risk subject to conditions to secure
the recommendations of the Flood Risk Assessor being attached to any grant of
consent: 
• Watercourse crossings should be designed to convey the 1 in 200 year plus climate
change (56% allowance) flood event.
• Surface water drainage is designed in accordance with CIRIA C753 and ensures
that post development surface water runoff does not exceed the pre-development

Page 4

surface water run-off, the surface water drainage should be in operation prior to
construction 
10. Argyll and Bute Council had no objection in respect to Access subject to a condition to
secure the recommendation of the Access Manager being attached to any grant of
consent: 
• Outdoor Access Plan to be submitted and agreed in writing by the Council prior to
the commencement of development. 
11. Argyll and Bute Council requested that all conditions recommended by other
consultees were included in any Consent. 
NOTE – Should any of the above matters be resolved to the satisfaction of the relevant
consultees Argyll and Bute Council’s objection may be treated as withdrawn. 
(Reference: Report by Head of Development and Economic Growth dated 9 April 2026,
submitted) 
6. SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC (SSEN
TRANSMISSION): PROPOSAL OF APPLICATION NOTICE FOR
DEVELOPMENT OF ELECTRICITY SUBSTATION ON A NEW SITE TO
REPLACE THE EXISTING ARDNADAM STATION: DUNOON ELECTRICITY
SUB STATION, HIGH ROAD, SANDBANK (REF: 26/00366/PAN) 
The Senior Planning Officer spoke to the terms of the report. 
The site comprises two distinct parts linked by the A885, High Road, which is also
included as part of the red line boundary.  The western part of the site forms the existing
Ardnadam Substation which is served by a vehicular access from the A885.  The Local
Development Plan 2 (LDP2) designates this land as Countryside Zone.  The southern part
of the site lies to the north of the existing junction with the A885 High Road and Ferry
Road.  This location is identified for the proposed new substation.  The LDP2 designates
this land as a Strategic Economic Investment Location for industry, business and storage
(Allocated Business Site BI-AL-2/2).  These are key locations to promote HIE Priority
Sectors to be safeguarded from inappropriate uses. 
The report sets out the information submitted to date as part of the Proposal of Application
Notice (PAN) and summarises the policy considerations, against which any future
planning application will be considered as well as potential material considerations and
key issues based upon the information received to date.   
It was recommended that Members note the content of the report and submissions and
provide such feedback as they consider appropriate in respect of the PAN to allow these
matters to be considered by the Applicant in finalising any future planning application
submission. 
Decision 
The Committee noted the content of the report and requested that the following matters be
given consideration in finalising any future planning application submission –

Page 5

1. Investigate whether Policy 21 of Local Development Plan 2 – Sites of Archaeological
Importance would be of relevance in respect of any future planning application. 
2. In respect of future use of the site where the existing substation is, investigate if there
has been any contamination of the land. 
3. Investigate if any significant peat deposits could impact the Holy Loch. 
(Reference: Report by Head of Development and Economic Growth dated 7 April 2026,
submitted)