Ladyfield Renewable Energy Park Ltd: Proposal of Application Notice for the Installation and Operation of Approximately 3.2Km of Underground Electrical and Telecommunications Cabling and Associated Temporary Works Required to Connect the Ladyfield Renewable Energy Park to the Ssent Creag Dhubh Substation: Land Between Ladyfield Energy Park and Creag Dhubh Substation Approximately 8Km North of Inveraray (Ref: 26/00986/Pan)

Argyll and Bute Council · 19 August 2026
Back to Planning, Protective Services and Licensing Committee — 19 August 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Council
Development and Economic Growth 
PROPOSAL OF APPLICATION NOTICE 
____________________________________________________________________________  
Reference: 26/00986/PAN 
Applicant: Ladyfield Renewable Energy Park Ltd  
Proposal: Proposal of application notice for the installation and operation of approximately
3.2KM of underground electrical and telecommunications cabling and associated
temporary works required to connect the Ladyfield Renewable Energy Park to the
SSENT Creag Dhubh Substation. 
Site Address: Land Between Ladyfield Renewable Energy Park and Creag Dhubh substation
Approximately 8KM North of Inveraray
____________________________________________________________________________ 
1.0 BACKGROUND 
The submitted Proposal of Application Notice (PAN) is for the installation and operation of
approximately 3.2KM of underground electrical and telecommunications cabling and associated
temporary works required to connect the Ladyfield Renewable Energy Park to the SSEN Creag
Dhubh Substation currently under construction by SSEN. 
Members are requested to note that a planning application is required in this instance as the
applicants do not have permitted development rights as a statutory undertaker in respect of
Electricity Undertakings under Class 40 of the GPDO. 
The electrical cabling will comprise 33kV infrastructure installed underground within a trench
typically approximately 1.2m in width and buried at a depth of approximately 1.0-1.2m below
ground level. Telecommunications cabling will also be installed in the same trench. The
installation of the cabling will involve trench excavation, cabling laying, backfilling and restoration
of the disturbed ground. 
Ladyfield Energy Park was granted S36 Consent by the Scottish Ministers on 02.05.2025. This
comprises up to 13 wind turbines anticipated to generate around 58.5 megawatts (“MW”), and a
battery electricity storage system (“BESS”) of around 41.4MW capacity.  For general information
the Planning Authority raised no objection to this proposal.  A link to the company’s website in
respect of the project which contains general information relating to the approved S36 Energy
Park and the proposed grid connection which this PAN relates to is provided below. 
Ladyfield Renewable Energy Park 
The submitted PAN notice took effect from 09.06.2026 from which a minimum of 12 weeks must
elapse prior to the submission of a formal application for planning permission. The proposed
public consultation strategy set out in the PAN to undertake appropriate notifications and hold
four public consultation events is considered to be acceptable and in accordance with the PAN
regulations. As there was no PPSL in July the PAN is being reported to August PPSL. 
The Council has also recently undertaken an EIA screening for this proposal under REF
26/00852/SCREEN. It was the view of Officers that no EIA was required. 
2.0 SITE DESCRIPTION

Page 2

The site comprises a linear area of land between the boundary of the Ladyfield Energy Park site
and the Creag Dhubh substation. The underground cable will generally follow the line of the A819  
and then branch off to the northwest at an appropriate point to connect to the substation. The
intention of the applicant is to run the cable a close to the line of the road as possible. 
The Proposed Development is located within both public highway and a rural area of Argyll and
Bute characterised by upland moorland and forestry areas. It’s anticipated that the area of works
will be approximately 12m in width and the boundary to be used for planning refined accordingly.
The Proposed Development is linear, located approximately 8km north of Inveraray, between
National Grid Reference (NGR) 209092, 716491 and NGR 208806, 719448 (the Site). 
The cabling would be installed in the public highway verge, where feasible, in a northerly direction
for approximately 1.9km. Where verge installation is not possible, installation would take place
within the carriageway itself. After approximately 1.9km, the cabling would leave the A819 corridor
and run northwest across upland / commercial forestry land for approximately 1.3km before
connecting into the Creag Dhubh Substation. 
Some tree felling may be required, although this is likely to be minimal as works will utilise the
existing access tracks and previously sterilised land where possible. 
Construction within the public highway corridor will require the implementation of traffic
management measures, likely including temporary two-way traffic signals to maintain access in
both directions. A temporary working area around the cabling trench will be required. Construction
within the forestry / upland area will be facilitated by utilising the existing forestry tracks, and
temporary tracks where forestry tracks are not currently present. 
Land uses along the route include public highway infrastructure associated with the A819,
commercial forestry and areas of rough grazing. The Site lies within a sparsely populated area
with limited residential receptors, with the nearest being North Tullich, approximately 500m from
the Proposed Development. The northern section of the Site lies within the North Argyll Area of
Panoramic Quality, a designated local landscape, while a portion along the A819 corridor is
situated adjacent to the Glen Etive and Glen Fyne Special Protection Area (SPA) to the east. 
3.0 DEVELOPMENT PLAN POLICY 
These PAN submissions are not a planning application and therefore do not require to be
evaluated and determined in accordance with Section 25 of the Planning Act against the
Development Plan at this stage.  However, a number of Development Plan Policies will inform the
assessment of any future detailed application. The relevant policies are set out below: 
LDP 2 
Spatial and Settlement Strategy 
Policy 02 – Outwith Settlement Areas 
High-Quality Places 
Policy 09 – Sustainable Design
Policy 15 – Protection, Conservation and Enhancement of Our Historic Environment
Policy 16 – Listed Buildings
Policy 17 – Conservation Areas
Policy 19 – Scheduled Monuments
Policy 20 – Gardens and Designed Landscapes
Policy 21 – Sites of Archaeological Importance

Page 3

Diverse and Sustainable Economy 
Policy 22 – Economic Development
Policy 30 – The Sustainable Growth of Renewables 
Sustainable Communities 
Policy 55 – Flooding
Policy 57 – Risk Appraisals
Policy 58 – Private Water Supplies and Water Conservation
Policy 59 – Water Quality and the Environment
Policy 63 – Waste Related Development and Waste Management 
High-Quality Environment 
Policy 71 – Development Impact on Local Landscape Areas (LLA’s)
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 74 – Development Impact of Sites International and National Importance
Policy 78 – Woodland Removal
Policy 79 – Protection of Soil and Peat Resources
Policy 80 – Geodiversity 
National Planning Framework 4 
This is a statutory Plan for the purposes of determining Planning Applications under Section 25
of the Planning Act and therefore NPF 4 Policies will also have to be considered in the
determination of any future planning application. 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 2 – Climate Mitigation and Adaption
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 5 – Soils
NPF4 Policy 6 – Forestry, Woodland and Trees
NPF4 Policy 7 – Historic Assets and Places
NPF4 Policy 11 – Energy 
Liveable Places 
NPF4 Policy 22 – Flood Risk and Water Management
NPF4 Policy 24 – Digital Infrastructure 
Productive Places 
NPF4 Policy 25 – Community Wealth Building
NPF4 Policy 29 – Rural Development 
4.0 POTENTIAL MATERIAL CONSIDERATIONS 
Material considerations include: 
• Statutory/Non-Statutory Consultee Comments/
• Third Party Comments
• Comments from Area Roads Manager in respect of the potential impacts on the  operation of
the A819 will be of particular importance in respect of considering and future proposals and a

Page 4

Construction Traffic Management Plan will be required. (It is noted and welcomed that this
matter has already been recognised by the applicants in their screening submissions). 
5.0 CONCLUSION 
This report sets out the information submitted to date as part of the PAN. Summarised are the
policy considerations, against which any future planning application will be considered as well as
potential material considerations. The list is not exhaustive, and further matters may arise as and
when any planning application is received, and in the light of public representations and
consultation responses. 
Officers are content that the steps set out within the PAN are acceptable and in accordance with
the necessary community engagement requirements. 
6.0  RECOMMENDATION 
That Members have regard to the content of the report and submissions and provide such
feedback as they consider appropriate in respect of the submitted PAN to allow these matters to
be considered by the Applicant in finalising any future planning application submissions. 
Author of Report: David Moore  Date: 27.07.2026 
Reviewing Officer: Sandra Davies  Date: 28.07.2026 
Fergus Murray
Head of Development & Economic Growth