Democracy Spraffa

Beaufort Wind Limited: Erection of 7 Turbines (Up to 149.9M to Tip) and Ancillary Development and Decommissioning of Existing Beinn Ghlas Wind Farm: Existing Beinn Ghlas Wind Farm, Taynuilt (Ref: 25/01240/Pp)

Argyll and Bute Council · 15 September 2026
Back to Planning, Protective Services and Licensing Committee — 15 September 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Argyll & Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of
the Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning
Permission in Principle 
Reference No: 25/01240/PP
Planning Hierarchy: Major
Applicant: Beaufort Wind Limited
Proposal: Erection of 7 turbines (up to 149.9m to tip) and ancillary
development and decommissioning of existing Beinn Ghlas
wind farm.
Site Address: Existing Beinn Ghlas Wind Farm, Taynuilt 
DECISION ROUTE   
☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997
☒Committee - Local Government Scotland Act 1973    
(A) THE APPLICATION  
(i) Development Requiring Express Planning Permission 
• Erection of 7 turbines (up to 149.9m to tip)
• Hardstanding areas at the base of each turbine, with a permanent area of
approximately 1,400 m2;
• Upgrading of four existing road junctions to support construction and
abnormal road traffic;
• Upgrading of forestry tracks from the A85 through Fearnoch Forest, Glen
Lonan Road (C32) and existing wind farm access track to accommodate the
delivery of abnormal loads to the site and use of existing track for access to
the first construction compound. An internal network of new onsite access
tracks and upgrade of existing Wind Farm access track. The total length of
the Site Access and Internal Access Tracks would be approximately 12.83
km of which 2.71 km is new access track (1.6 km floating) with associated
new watercourse crossings and 8.52 km is existing access track and
watercourse crossings which would need to be upgraded. In total there would
be 4 new watercourse crossings and 22 existing crossings;
• Upgrading of the existing onsite sub-station/control building;
• Installation of Transformers and underground cables to connect the turbines
to the onsite substation;
• Permanent anemometry mast for wind monitoring, including associated
foundation and hardstanding;
• Telecommunications equipment;
• Decommissioning of Existing Beinn Ghlas windfarm.

Page 2

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(ii) Other specified operations 
• Concrete batching plant;(Temporary)
• Preliminary temporary construction compound;
• Temporary construction compound. 
Raeshaw Approach 
The underground grid connection proposals which have been subject to Further
Environmental Information (FEI) submissions, do not form part of the Planning
Application but inform the evaluation of potential Environmental Impacts of the
overall development under the EIA regulations. This additional information has
been required as the Planning Authority considers the construction of the
windfarm and the provision of a related grid connection to Taynuilt Substation
from the windfarm site to be a “single project” for the purposes of EIA evaluation
Under the “Raeshaw” approach which has recently become a matter requiring
consideration by Planning Authorities in respect of EIA development proposals.  
(B) RECOMMENDATION   
Having due regard to the Development Plan and all other material consideration,
it is recommended that planning permission be APPROVED subject to the
conditions appended to this report. 
(C) CONSULTATIONS 
a) External Consultees   
NatureScot : 12.12.25 & 28.08.26 – No Objection. 
Summary: There are natural heritage interests of international importance on the
site with relation to Loch Etive Woods Special Area of Conservation, but our
advice is that these will not be adversely affected by the Proposal. While there
are impacts on protected Schedule 1 bird species, these do not raise issues of
national interest. 
We raised initial concerns around impacts on Ben Nevis and Glen Coe National
Scenic Area and Wild Land Areas 06 and 09. We also raised concerns around
possible impacts from displacement/loss of territory on golden eagle, along with
cumulative impacts from other wind farm developments in the area. 
We then provided post scoping comments in February 2023, when the Proposal
was reduced to 12 turbines at 149.9m. We confirmed that based on the new
layout, Ben Nevis and Glen Coe NSA could be scoped out, and a Wild Land
Impact Assessment was no longer required. In March 2023 we also provided
comments regarding impacts to the favourable conservation status for white
tailed eagle. We then had post scoping meetings with the Applicant in July 2023
and May 2025 where we were provided with updates to the application and
discussed white tailed eagle collision risk at the site. 
3. Assessment of impacts on key natural heritage interests

Page 3

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
3.1 Loch Etive Woods Special Area of Conservation The access track for the
Proposal is located approximately 100m from Loch Etive Woods Special Area of
Conservation (SAC) and Airds Park and Coille Nathais Site of Special Scientific
Interest (SSSI), designated for a number of woodland habitats, marsh fritillary
and otter. The site’s status means that the requirements of the Conservation
(Natural Habitats, &c.) Regulations 1994 as amended (the ‘Habitats
Regulations’) apply or, for reserved matters, 
The Conservation of Habitats and Species Regulations 2017. Consequently,
Argyll and Bute Council is required to consider the effect of the Proposal on the
SAC before it can be consented (commonly known as Habitats Regulations
Appraisal). The NatureScot website has a summary of the legislative
requirements: https://www.nature.scot/professional-advice/protected-areas-and
species/protected-species/legal-framework/habitats-directive-and-habitats-
regulations Our advice is that it is unlikely that the Proposal will have a significant
effect on any qualifying interests either directly or indirectly. An appropriate
assessment is therefore not required. This is because the track is separated
from the SAC by plantation conifers, and any runoff from this track would flow
away from the SAC woodland. 
3.2 Landscape and Visual Our approach to advising on wind farm applications is
to generally focus upon impacts on Scotland’s landscapes that could potentially
raise issues of national interest. Having reviewed the supporting information for
the Proposal, we do not consider that it would raise issues of National
Interest in relation to its landscape, visual or cumulative effects. This is not
to say that the development would not result in significant landscape or visual
effects, rather that NatureScot does not judge these effects to meet our threshold
in respect of our national remit for landscapes. 
3.3 Ornithology 
3.3.1 Golden eagle 
The Proposal falls within a known golden eagle territory and is the third wind farm
application to be submitted within this territory in the last year. The other two
developments are Cruach Clenamacrie (ECU00004841), which we submitted an
advice only response to, and Corr Chnoc (ECU00006023), which we submitted
a holding objection to on the basis of further ornithological survey requirements.
Both developments are waiting to be determined. Due to the three developments
within this territory, there is a risk of loss of functional habitat (territory) due to
cumulative effects. Based on the confidential GET analysis, the golden eagle
territory effected by the Proposal is estimated to be a loss of 1.68% of the
functional habitat. On its own this would not be enough to cause displacement,
however when considered in combination with Cruach Clenamacrie (2.85%) and
Corr Chnoc (11.64%) this would result in 16.17% functional habitat loss. This is
likely to cause displacement of the birds in this territory. As the Proposal is a
repowering application, the majority of the 1.68% habitat loss has already
happened due to the similarity in layout with the Consented Scheme. Therefore
the golden eagle will have habituated to this. Corr Chnoc wind farm, which has
the highest levels of displacement, currently has a holding objection in place
relating to its ornithology work. Due to this holding objection, we do not feel
that the cumulative level of displacement from the current Proposal and
Cruach Clenamacrie is enough to cause displacement of this territory.
However, we do envisage further cumulative pressures arising in this area. 
3.3.2 White tailed eagle

Page 4

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
In Chapter 7 Ornithology, the Applicant has stated that “For non-breeding white-
tailed eagles, it is considered reasonable to assume they would accommodate
any displacement by more intensively exploiting less disturbed areas”. We do not
fully agree with this statement. White-tailed eagle will exploit areas where food is
available but if these areas are located considerable distances away then this
will add unnecessary energetic costs or may cause them to displace. Further to
this, there is an increasing cumulative issue with windfarms in NHZ14. This
means many suitable areas are no longer available which will result in an
increased collision risk as they continue to use more suitable habitat which is
being developed. Collision Risk Modelling (CRM) The CRM for white tailed eagle
is 6.14 birds every 25 years (sub adult: 1 every 5 years; adult: 1 every 18.6
years). This is high, however is acceptable in isolation. As stated in the EIA, this
would mean one less adult would enter the NHZ population every 6 to 10 years.
As with golden eagle territory loss, this loss alone does not raise concerns.
However, cumulatively with the aforementioned neighbouring windfarms, it adds
to the now high cumulative risk in NHZ14. Due to the holding objection on Corr
Chnoc, we can accept this level of collision risk in this instance without additional
mitigation to reduce this, but it should be noted that we are now reaching an
unsustainable level of collision risk for white tailed eagle in NHZ14. 
3.3.3 Biodiversity Enhancement Plan 
Deer fencing around turbines - The Applicant is proposing to install deer and
stock fencing around the turbine locations to prevent carrion attracting raptors
into the fenced area, therefore reducing the potential for collisions. We do not
feel that stock fencing around turbines will necessarily reduce carrion around the
turbines, as it may lead to black grouse and other prey species colliding with the
fences, and it does not prevent other bird species colliding with turbines and
falling inside the fenced area. 
If fencing is implemented, the following mitigation will be required: 
- Any fencing should be marked to reduce risk of collisions for black grouse, white
tailed eagle and other bird species. 
- The habitat inside the fence will inevitably become good rough grazing with a
lowered grazing pressure and as such needs to be monitored and managed if it
is shown to increase the numbers of hunting prey birds such as merlin, kestrel,
owl species and red kite. 
Managing the overall Habitat Management Plan area to lower grazing and
improve the condition of this area would create a diversionary feeding area for
the species mentioned above and could draw scavenging birds away from the
turbine area. 
Installation of diver rafts  - Management of diver rafts, such as targeted predator
control, will be required to ensure that they maintain their effectiveness. 
Riparian planting - While the proposed planting will be beneficial to the overall
habitat at this site, it must not come at the expense of the resident golden eagle
pair in this territory. Any planting works will need to consider roost sites for golden
eagle. Roost sites are protected year-round for Schedule 1/1A birds. There are
multiple roost sites which will be impacted by the planting activities, and the
Applicant will need to ensure that mitigation (such as timing restrictions) is in
place to avoid risk of disturbance or displacement to the golden eagle pair, which
could result in the Applicant committing an offence under the Wildlife and
Countryside Act (as amended).

Page 5

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
This same applies to the peatland restoration which will also need to consider
roost disturbance year-round. 
Installation of artificial white tailed eagle nest - The installation of a white-tailed
eagle platform may not draw any white tailed eagle away from their current nest
sites and could potentially introduce a third pair in the area or encourage other
raptors such as osprey into the area. If this work is carried out, the siting of the
artificial nest needs to be considered, and landowner permission sought. 
White tailed eagle fatality monitoring and carcass recovery scheme 
We are supportive of these trials as they help build a picture of collision risk which
can assist with the assessment of future proposals. All trials will need to follow
the methodology laid out in Caryl et al 2016. This paper hasn’t been referenced
in this section, and there are some discrepancies between the proposed
methodology and those in the paper that will need to be aligned. We support the
removal of carcasses to reduce scavenging activity from the footprint of the
Proposal. In relation to this, proposed carcass persistence trials must be done
remotely from the wind farm footprint in order to avoid drawing in scavenging
eagles and other raptor species. 
3.3.4 Other bird species 
Providing the Applicant complies with the statement in Chapter 7 Ornithology,
Section 7.6 that all known breeding bird sites will be buffered during construction
and operation of the Proposal then this will be sufficient. A qualified Ecological
Clerk of Works should be used to ensure compliance. The only exception being
black grouse, which may be affected by the proposed fencing around the
windfarm (see above). 
3.4 Peatland We note that the Applicant is proposing to restore peatland habitat
at a ratio of 1: 9. While this is below our recommendation of 1:10 plus an
additional 10%, we accept that the current condition of the peatland does not
allow for more restoration on site. The Applicant may wish to consider off-site
restoration in order to achieve the restoration recommendations within our
guidance. 
Officer Comment: 
Although specific conditions are not recommended, matters raised in this
response requiring action/control/monitoring not already set out in submissions
to safeguard Nature interests within the EIAR and supporting documentation
have been introduced as conditions by Officers to ensure that the construction
and operation of the development is in accordance with NatureScot
requirements. 
FEI Response Dated 28.08.26 
Our advice on the proposed wind farm remains unchanged from our response
dated 12 December 2025. Based on the information submitted, the proposed grid
connection, alone and in combination with the wind farm, is unlikely to result in
any new or increased severity of effect on natural heritage interests that raise, or
closely approach, issues of national interest.

Page 6

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Historic Environment Scotland: 30.10.25 & 28.08.26 No Objection 
Our view is that the proposals do not raise historic environment issues of national
significance and therefore we do not object. Further details on the impacts to
settings of assets within our remit and the assessment thereof are included in the
annex to this letter. 
We are content that there will be no direct physical impacts on assets within our
remit as a result of the proposed development. A number of assets are assessed
in the EIA Report, and the information provided has been helpful in clarifying the
likely effects on these sites for our interests. We have no further comments to
make for most of those sites. 
Scheduled Monuments 
Based on the photomontage visualisations provided, we are content that there
would be no adverse impacts on the setting of scheduled monuments that would
raise issues of national interest. The impact of the setting on Barguillean Farm,
dun 250m SWW of (SM3930) could be reduced, however, by the movement or
reduction in height of turbines 6 and 7, so that the hubs would not appear above
the skyline to the southwest of the monument. This would make the impacts of
the proposals similar in nature to their impacts on the other assets in Glen Lonan. 
The proposals would be visible in long distance views from Ardchattan Priory,
priory, burial ground and carved stones (SM13644), and would add to the spread
of turbines on the skyline in views to the south. The turbines would not be more
prominent that others already proposed and, while they would have a similar
impact on the sense of place, they would not significantly detract from the ability
to understand, appreciate or experience the monument in its setting. 
Gardens & Designed Landscapes 
We agree with the assessment in the EIA Report that the development would not
have a significant adverse impact on the setting of Ardchattan Priory
(GDL00019). 
In respect of the FEI  response dated 28.08.26 it is stated that: 
We have considered the information received and do not have any comments to
make on the proposals. … 
We note that the proposed route for the underground cable is in close proximity
to Barguillean Farm, dun 250m SSW of (SM3930). We would expect the
presence of the asset to be taken into consideration and, if necessary,
appropriate measures be taken to prevent accidental damage to the scheduled
monument. 
Scottish Water 06.08.26 No Objection 
…the proposed activity falls within a drinking water catchment where a Scottish
Water abstraction is located. Scottish Water abstractions are designated as
Drinking Water Protected Areas (DWPA) under Article 7 of the Water Framework
Directive. Loch Nell supplies Tullich Water Treatment Works (WTW) and it is

Page 7

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
essential that water quality and water quantity in the area are protected. In the
event of an incident occurring that could affect Scottish Water we should be
notified immediately using the Customer Helpline number 0800 0778 778.  
Given the location of the activity within the catchment, this should present a low
risk to water quality, and no concerns have been raised from a water resource
perspective. However, we would request that water quality protection measures
are still implemented and best practice is followed. 
Scottish Water records indicate that there is live infrastructure in the proximity of
your development area that may impact on existing Scottish Water assets. The
applicant must identify any potential conflicts with Scottish Water assets and
contact our Asset Impact Team via our Customer Portal for an appraisal of the
proposals. The applicant should be aware that any conflict with assets identified
will be subject to restrictions on proximity of construction. Please note the
disclaimer at the end of this response. 
Officer Comment: Water pollution safeguards will be required as part of a
suspensive condition relating to a Construction Environmental Management Plan 
(CEMP) and also a separate water specific pollution prevention plan.   
SEPA:  02.10.25, 20.05.26  & 25.08.26 – No Objection subject to conditions 
Initial holding objection of 02.10.25 withdrawn by response dated 20.05.26
following amendments to the locations of turbines 4 & 5 to reduce peat impacts.
No further issues relating to FEI  in response dated 25.08.26 subject to
adherence to EIAR commitments. Maintained objection unless  conditions set
out below are applied to any grant of consent; 
• Condition Out with the condition that no micrositing shall take place onto
areas of deeper peat than shown on the most up to date site plans (as
shown in additional information dated 28 March 2026), we would not
support any micrositing of the floating track along the west side of the
area of near-natural peat bog between the Temporary Construction
Compound 2 (TCC2) and the junction of the track leading to T1.   
• Condition: that all near-natural condition peatland habitat within 50m of
infrastructure is physically demarked prior to construction commencing
to ensure construction vehicles do not disturb the habitat during
construction. The schedule of mitigation should outline how this habitat
will be safeguarded. 
• Condition: for post-construction monitoring of impacts on near natural
habitat in the vicinity of TCC2, which will require a mechanism to take
specific action should impacts occur: 
A schedule of monitoring should ensure the near-natural peatland
habitat is safeguarded from direct and indirect impacts and must
include: 
o Proposals for fixed point photography and repeat National Vegetation
Classification and hydrological condition surveys.
o Frequency of monitoring, supported by justification.

Page 8

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
o Criteria that will trigger additional action should monitoring reveal that
the near-natural peatland habitat is no longer sequestering or is
degrading to a modified habitat type. 
Any actions taken are required to adhere to NatureScot’s peatland
restoration guidance. 
• Condition: for a Peat Management Plan. To ensure consistency
between energy developments we recommend that the wording of
Condition 31 of the Energy Consent Units Standard onshore wind
condition be used - Standard onshore wind conditions – Standard
onshore wind conditions – section 36 consent and deemed planning
permission: form and guidance - gov.scot 
• Condition: Bottomless arch culverts or span bridges should be used for
all new or upgraded watercourse crossings, and all watercourse
crossings must be designed to convey the 1:200 plus Climate Change. 
Officer Comment : Appropriate conditions are proposed. 
Defence Infrastructure Organisation (DIO): 22.09.25, 02.02.26 & 08.06.26  No
Objection subject to conditions. 
• Condition - Aviation Lighting 
Prior to commencing construction of any wind turbine generators, or deploying
any construction equipment or temporal structure(s) 50 metres or more in height
(above ground level) the undertaker must submit an aviation lighting scheme for
the approval of the Argyll & Bute Council in conjunction with the Ministry of
Defence defining how the development will be lit throughout its life to maintain
civil and military aviation safety requirements as determined necessary for
aviation safety by the Ministry of Defence. This should set out: 
a) details of any construction equipment and temporal structures with a total
height of 50 metres or greater (above ground level) that will be deployed during
the construction of wind turbine generators and details of any aviation warning
lighting that they will be fitted with; and 
b) the locations and heights of all wind turbine generators and any anemometry
mast featured in the development identifying those that will be fitted with aviation
warning lighting identifying the position of the lights on the wind turbine
generators; the type(s) of lights that will be fitted and the performance
specification(s) of the lighting type(s) to be used. 
Thereafter, the undertaker must exhibit such lights as detailed in the approved
aviation lighting scheme. The lighting installed will remain operational for the
lifetime of the development. 
Reason for condition. To maintain aviation safety. 
• Condition -Aviation Charting and Safety Management 
The undertaker must notify the Ministry of Defence, at least 14 days prior to the
commencement of the works, in writing of the following information: 
a) the date of the commencement of the erection of wind turbine generators;

Page 9

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
b) the maximum height of any construction equipment to be used in the erection
of the wind turbines; 
c) the date any wind turbine generators are brought into use; 
d) the latitude and longitude and maximum heights of each wind turbine
generator, and any anemometer mast(s). 
The Ministry of Defence must be notified of any changes to the information
supplied in accordance with these requirements and of the completion of the
construction of the development. 
Members are requested to note that following  the SEPA  request that turbines 4
and 5 were relocated within the site to minimise impacts on deeper peat. DIO
were reconsulted on the amended locations and again raised no objection. The
final response dated 08.06.26 also evaluated the FEI information relating to the
grid connection, again confirming no objection was raised subject to conditions. 
In summary, and after reviewing the documents submitted, I can confirm that the
MOD position set out in our responses dated 22/09/2025 and 02/02/2026 is
unchanged. Subject to the two conditions identified in Appendix A being applied
to any consent issued, the MOD has no objections to the development.   
Scottish Forestry : 27.08.26 No Objection subject to conditions. 
A. Detailed woodland removal plan condition 
• A condition is applied securing production of a detailed woodland removal
plan be produced as part of the route refinement process. 
• This should include very clear woodland removal proposals for any
Ancient woodland, PAWS and other woodland types, including maps and
areas. 
• It should include relevant detail of felling / restocking /compensatory
planting relating to works on Barguillean Estate. 
• It should include a reassessment of the compensatory planting area. This
must exceed the area of woodland removed and demonstrate how this
will compensate for the loss of environmental value. 
• The plan should clearly demonstrates application of the NPF 4 hierarchy
of mitigation. 
• SF should be consulted on the plan. 
B. Compensatory Planting Condition 
• We advise that compensatory planting should be secured by a condition.
Draft wording is provided in Annex 1 of this letter. 
• The applicant should consider the need for EIA Screening of the
compensatory woodland creation (necessary consents) 
Annex 1 - Suggested Condition for Compensatory Planting 
“Commencement of Development” means the implementation of this consent by
the carrying out of- 
(a) a material operation within the meaning of section 27(4) of the Town and
Country Planning Act 1997; (other than any operations associated with ground
or site investigation works); or 
(b) any deforestation associated with the implementation of this consent.

Page 10

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
“Necessary Consents” means 
a) any consent or permission required by an enactment to enable the approved
Replanting to be implemented in accordance with the phasing and associated
timescales for implementation contained in the approved Replanting Scheme;
and b) any right or permission to take entry to or access over land required by
the Company or parties acting on its behalf to implement the approved
Replanting Scheme. 
1. There shall be no Commencement of Development until a woodland planting
scheme to compensate for the removal of XXX hectares of existing woodland
(“the Replanting Scheme”) has been submitted to and approved in writing by
Argyll and Bute Council in consultation with Scottish Forestry. 
2. The Replanting Scheme must comply with the requirements set out in the UK
Forestry Standard (Forestry Commission, 2017. ISBN 978-0-85538-999-4) and
the guidelines to which it refers. The Replanting Scheme submitted for approval
must include- 
a. details of the location of the area to be planted; 
b. details of land owners and occupiers of the land to be planted; 
c. the nature, design and specification of the proposed woodland to be planted; 
d. details of all Necessary Consents for the Replanting Scheme and timescales
within which each shall be obtained; 
e. the phasing and associated timescales for implementing the Replanting
Scheme; f. proposals for the maintenance and establishment of the Replanting
Scheme, including; annual checks; replacement planting; fencing; ground
preparation; and drainage; and 
g. proposals for reporting to Argyll and Bute Council on compliance with
timescales for obtaining the Necessary Consents and thereafter implementation
of the Replanting Scheme. 
3. The approved Replanting Scheme shall thereafter be implemented in full and
in accordance with the phasing and timescales set out therein, unless otherwise
agreed in writing by Argyll and Bute Council after consultation with Scottish
Forestry. 
4. There shall be no Commencement of Development until all relevant Necessary
Consents for implementation of the Replanting Scheme in accordance with the
phasing and timescales set out therein have been obtained. 
Reason: To secure compensatory planting to mitigate against effects of
deforestation arising from the Development. 
Officer Comment: Appropriate conditions to safeguard these matters and ensure
appropriate consultation with Scottish Forestry are proposed. 
National Air Traffic Services (NATS) : (02.09.25 & 30.07.26) No Objection 
The proposed development has been examined from a technical safeguarding
aspect and does not conflict with our safeguarding criteria. Accordingly, NATS
(En Route) Public Limited Company ("NERL") has no safeguarding objection to
the proposal 
Oban Airport 19.05.26 – No Objection 
Argyll and District Salmon Fishery Board: 04.08.26 No Objection 
We note that the recent additional to the documents folder of Further
Environmental Information has some relevant information on aquatic ecology.

Page 11

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
This recognises the importance of the River Nant, River Nell / Feochan and Allt
Nathais which host spawning and nursery habitat for Atlantic salmon and brown
trout. Argyll DSFB request that appropriate baseline, real time and post works
monitoring is put in place to ensure any issues arising from the proposed
development are identified and rectified in a timely manner as to prevent any
deterioration of fish habitats and demonstrate that the development does not
impact on the salmon populations or the fisheries in the Argyll DSFB area. Argyll
DSFB would welcome an opportunity to constructively engage with any such
process. 
Officer Comment:  An appropriate condition to safeguard these matters is
proposed.  
The Joint Radio Company Limited ( Arqiva)  16.09.25 & 16.09.26 
16.09.25: No Objection to windfarm application. Suggested condition relating to
domestic TV and Radio interference survey being undertaken and any required
mitigation being carried out in respect of individual properties. A condition to this
effect is proposed. 
17.08.26 – Objection unless exact route of grid connection provided as grid
connection corridor has potential intersection with two links protected by JRC 
(Refs 0976814/4 & 0929167/2) 
Officer Comment : The grid connection does not form part of the current planning
application, only the EIA submissions and therefore objections to the grid
connection on Non-EIA related grounds are not material to the determination of
the windfarm application. The grid provider will require to address these matters
when detailed proposals for this grid connection are brought forward. 
Transport Scotland : 10.09.25 & 30.07.26 No Objection subject to conditions 
1. Prior to the commencement of the development, the proposed upgraded
access on the A85 trunk road, as generally illustrated by RSK nadara Figure
10.4 Access Junction Design Rev 03 dated 17/06/2025, shall be constructed
to a layout and type (and method) of construction to be approved by the
Planning Authority, after consultation with Transport Scotland 
Reason : To ensure that the standard of access layout complies with the
current standards and that the safety of the traffic on the trunk road is not
diminished. 
2. Prior to the commencement of the development, visibility splays, as generally
illustrated by RSK Figure 2.10a: Indicative Site Access - A85 to Fearnoch
Forest Track Rev 03 dated 14/08/2025, shall be provided and maintained to
the satisfaction of the Planning Authority, after consultation with Transport
Scotland.
Reason: To ensure that the standard of access layout complies with the
current standards and that the safety of the traffic on the trunk road is not
diminished. 
3.  Prior to commencement of deliveries to site, the proposed route for any
abnormal loads on the trunk road network must be submitted to and approved
by the Planning Authority, in consultation with Transport Scotland.

Page 12

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Reason:  To ensure that the transportation of abnormal loads will not have
any detrimental effect on the trunk road network. 
4. Prior to the movement of any abnormal load, any accommodation measures
required, including the removal of street furniture, junction widening and traffic
management must be approved and implemented to the satisfaction of the
Planning Authority, in consultation with Transport Scotland. 
Reason:  To ensure that the transportation of abnormal loads will not have
any detrimental effect on the trunk road network. 
5. Prior to the movement of any components and/or construction materials, any
additional signing or temporary traffic control measures deemed necessary
due to the size or length of any loads being transported must be undertaken
by a recognised QA traffic management consultant, to be approved by
Transport Scotland.
Reason:  To ensure that the transportation of abnormal loads will not have
any detrimental effect on the trunk road network. 
6. Prior to commencement of the grid connection element of the development,
a Construction Traffic Management Plan (CTMP) shall be submitted to, and
approved by, the Planning Authority, after consultation with Transport
Scotland. In particular, the CTMP shall identify measures to control the use
of any direct access onto the trunk road. Thereafter, all construction traffic
associated with the development shall conform to the requirements of the
agreed Plan. 
Reason: To mitigate the adverse impact of construction traffic on the safe and
efficient operation of the trunk road network 
Officer Comment : Appropriate conditions are proposed. 
Avich and Kilcrennan Community Council : 29.07.26 
Email  indicating its Terms of Office expire on 28.08.26 which is before the
FEI response deadline of 05.09.26. They state this is likely to be the same for
all CC’s in Argyll and Bute. 
Officer Comment. The deadline referenced by the Community Council of
05.09.26 relates only to the FEI information for the grid connection and not
the consultations undertaken with Community Councils between  02.09.25
and 09.09.25 relating to the  planning application and EIAR for the windfarm.
This is the matter before the Planning Authority for determination.   
Community  Councils have therefore been aware of the windfarm application
since early September 2025 when notifications were undertaken. No
responses have been received. Officers are therefore content that sufficient
time and opportunity has been provided for comments to be provided on the
planning application and any late FEI responses following the production of
this report will be presented to Members in accordance with normal practice. 
b) Internal ABC Consultees 
ABC Area Roads: 19.08.26 No Objection subject to conditions

Page 13

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• New accesses and existing accesses in need of amending or modification
to be upgraded in accordance with Operational Services Drg No
SD08/001b. 
• Visibility splays measuring 42m x 2.4m to be cleared and maintained. 
• Additional road signs and markings will be required, as per TSRGD. Exact
specifications and locations to be agreed with this department. 
• A statement in respect to the materials and plant to be transported over
the C32 to serve the works is required. The statement should also state
where materials will be imported from along with estimated quantities, so
the effect on local quarry roads can be assessed. 
• A pre start site meeting is required, to discuss planned changes to the
C32.
• Major works notice will be required for the planned C32 upgrades.
• TTRO applications will be required for works within the C32 corridor.
• Detailed engineering, technical drawing required in relation to C32
upgrades. Details to be approved by this department. General illustrations
as per Fig 2.10b. 2.10c and 2.10d. 
• A system of traffic management to be in place to accommodate the
traversing of abnormal loads over the C32. Details to be agreed with this
department. 
• A pre start road inspection to be carried out. Any extraordinary damage
to the C32 road corridor caused by the associated proposal works to be
made good at no expense to Argyll and Bute Council. 
• A pre start site meeting is required, to discuss planned changes to the
C32. 
Officer Comment: Thise matters can be addressed through suspensive
conditions requiring a Construction Traffic Management Plan To be approved by
the Area Roads Engineer . Specific details referenced by the Area Roads
Manager can be referenced in the condition(s).   
ABC Environmental Health: 04.09.25 
This unit advises that Environmental Health are not able to review the application,
and we recommend that Planning consider employing a noise consultant to
assess the effects that this application may have on the local amenity of the area. 
Officer Comment: Independent Noise Expert appointed. (see below) 
ABC Noise Consultant. November 2025 & 26.08.26 No Objection 
There are no reasons to object to the scheme on noise grounds, but a suitably
worded condition to limit the noise levels, tonality and amplitude modulation
should be applied as per the example in Annex B. 
Officer Comment:  Additional submissions were made by the applicant
comprising an amended condition proposal following the updating of the relevant

Page 14

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
guidance on how to evaluate such matters. This revised condition has been
reviewed by the Councils Noise advisor and is considered acceptable. An
appropriate Condition is proposed. 
ABC Consultant Landscape Architect :  09.12.25 & 11.05.26:  No Objection  
The Councils Landscape Architect has raised no objections to the proposals on
Landscape impacts in respect of the main application or the additional FEI
information provided. The initial evaluation raised a number of questions about
methodology and findings within the LVIA. The applicants provided clarification
by additional submissions dated 18.12.25. The evaluation of these additional
submissions was undertaken by response dated 11.05.26.  Relevant Extracts
from the Landscape Advisors evaluation of the proposals  evaluation Report  are
set out below: 
The proposal is predicted to have localised significant direct effects over a
limited area approximately 1km from the proposed turbines on the host LCT 7
Craggy Upland. When compared with a theoretical zero future baseline (in which
the existing Beinn Ghlas wind farm has been decommissioned to form a blank
canvas) direct significant effects would extend to approximately 4km. 
No significant effects are predicted on any of the landscape designations.
However, in the TFB scenario isolated significant effects were identified within
the North Argyll LLA within approx. 10km of the proposal which were not
predicted to result in a significant effect on the integrity of the designation. 
The EIAR found that significant visual effects would be experienced at two of
the 19 representative viewpoints, at VP2 Clach Bhadan and VP7 Ardchattan
Priory. When compared to TFB scenario, this number would increase to six. 
Significant visual effects are predicted in the EIAR for users of a very limited part
of the nearest recreational route (C171). When assessed against TFB scenario,
two further core paths were found to be subject to significant effects (Core Path
C517 and C158).
The assessment of roads found that receptors would experience significant
effects from a section of the minor road between A828 and B845 near to
Ardchattan Priory. In the TFB scenario significant effects would be experienced
from a section of the B845 to the north of Loch Etive. 
Significant effects on residential properties are predicted for the cluster around
Balindore (3.8 km away from the proposal). When compared to a zero-baseline
scenario, significant effects would extend to also include some properties within
Taynuilt (approx. 4.8 km away) but are not predicted to be of such a scale as to
become dominant or overbearing. 
The LVIA concludes that any significant effects that would arise as a result of
the proposal are limited and would be highly localised in their nature, restricted
to within 8.3 km of the Site. 
The proposal is not predicted to significantly affect the Lynn of Lorn or the Ben
Nevis and Glen Coe NSAs. I have not undertaken a detailed review to assess
whether the overall integrity of the NSA might be compromised. I would expect
such an assessment to be undertaken by NatureScot.

Page 15

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The EIAR does not predict significant effects on the North Argyll or any other
LLAs under the current baseline scenario. For the TFB scenario the EIAR
predicts isolated significant effects within the North Argyll LLA within approx.
10km of the proposal although these are not predicted to result in a significant
effect on the integrity of the designation. 
Policy 11e requires project design and mitigation to demonstrate how impacts
on communities and significant landscape and visual impacts are addressed. In
terms of significant landscape and visual impacts, 11e ii states that such impacts
are to be expected for some forms of renewable energy and where impacts are
localised and/or appropriate design mitigation has been applied, they will
generally be considered acceptable. NPF4 provides no guidance on the definition
of what constitutes ‘localised’ effects. 
The EIAR Chapter 2 Proposed Development and Design Evolution and the
Design and Access Statement summarise the evolution of the design and
mitigation embedded into the design to reduce landscape and visual effects. The
initial turbine layout comprising 20 turbines with 180m blade tip height has been
reduced to the 7 turbines of up to149.9m to blade tip assessed in the EIAR. In
addition to a reduction in the numbers of turbines, the turbines were consolidated
within the site, resulting in the layout being more compact and less visible within
the landscape. I consider the residual significant effects as fairly ‘localised’ and
the above design/mitigation measures appropriate. 
The Applicant’s landscape consultant responded to the initial Jacobs review in
an email to A&BC dated 18 December 2025. The report dated 11.05.26 provides
Jacobs’ comments on the Applicant’s clarifications to the Planning Authority. 
The following updated comments from the Councils Landscape Architect were
provided at Section 3.0 of this report as follows; 
• Agree that the location of Compound 1 in LCT7a will not change the
findings of the LVIA and that the overall effect on this LCT would remain
not significant. 
• Content with the amended Figure (5.47) which will not alter the findings
of the LVIA. 
• Clarification that a formal RVAA has not been undertaken due to there
being no properties within 2km of the turbines, and thus wirelines from
properties have not been provided, is helpful. Jacobs have not been able
to locate any reference in the EIAR to discussions with A&BC regarding
the provision of a RVAA but agree that the LI RVAA guidance does
suggest that this distance would not require a RVAA. 
• Content with this explanation and that there will be no effects on SLQs or
the overall integrity of the Lynn of Lorn NSA. 
• Content with this explanation of a typographical error. 
Full information can be found at section 3.0 of this report. The Councils
Landscape advisor is content with the clarifications provided by the applicant’s
submissions and raises no Objection to the proposals.

Page 16

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
In respect of FEI information. As the grid connection cable is to be wholly
underground additional landscape advice on this matter was not taken as
Officers are content that this is not a matter that requires additional detailed LVIA
consideration.   
ABC Flood Risk Assessor 22.09.25 & 27.08.26  – no objection subject to
conditions. 
In respect of FEI information, the Councils consultants have raised no objection 
It is recommended that the following  conditions are attached to any consent
granted for this application: 
1. New or upgraded watercourse crossings along the access tracks should be
designed so as to convey at least the same capacity as existing and ideally the
1 in 200 year plus climate change (56% allowance) flood event. 
2. Any modifications to watercourse crossings along the route of the proposed
grid connection cable should not reduce the existing capacity of the structures. 
3. Surface water drainage should be designed in accordance with CIRIA C753
and ensure that post development surface water runoff does not exceed the pre-
development surface water runoff. The surface water drainage should be in
operation prior to the start of construction. 
Officer Comment: Appropriate conditions are proposed 
West of Scotland Archaeologist Service 31.07.26   No Objection 
I have studied the proposed application which is a repowering of an earlier wind
farm development to extend the use of the site. Although the proposed new
turbines are taller than the previous one there are fewer of them and they will be
less than 150m tall. The development has been designed to avoid disturbing the
limited number of known heritage assets within the site and little likelihood of
disturbing currently unknown archaeological remains. I am satisfied these effects
and the setting of designated and non-designated monuments in the wider
landscape have been considered and that no significant impacts will result from
the proposals. 
It should be noted that policy 21 of Argyll and Bute’s Local Development Plan
makes provision for the discovery of archaeological remains after development
has commenced. The applicant or their agent should therefore prepare a protocol
for archaeological discoveries made during development. The PAD is standard
"safety net" deployed in offshore windfarm construction. 
Officer Comment: Appropriate Conditions are proposed.   
Local Biodiversity Officer. 07.10.25, 19.01.26, 31.03.26 & 19.08.26  No
Objection. 
The original holding objection of 07.10.25 was withdrawn as additional
information was provided by the applicant on potential impacts on Ancient
Woodland and  related biodiversity matters. (Ornithology and protected species
matters have primarily been addressed by NatureScot in their consultation
response).

Page 17

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
31.03.26 Response 
There are several trees and woodland habitat along the access track which are
of biodiversity value. It is stated that these will aim to be avoided. There also
several trees with bat PRF’s either present or with the potential to become a PRF
along the access track. Pre-works surveys will determine presence / absence of
bats, the results of which will feed into further mitigation measures necessary and
the need for any potential licences from NatureScot. 
I am satisfied that no ancient woodland or rainforest habitat will be impacted upon
by the proposed development. I ask that the final design of the access track is
agreed with Argyll & Bute Council prior to construction to ensure every effort has
been made to avoid impact to notable trees and habitat as outlines in the survey.
I welcome the creation of 3 nature networks in addition to the compensation
planting. 
I therefore withdraw my holding objection to this application. 
19.08.26 – FEI  Grid Connection Response 
I note that no ecological surveys have been undertaken to inform the appraisal.
As ancient woodland is present on site, as well as Class 2 peat and the potential
for a range of protected species to be present, I ask that a full set of ecological
surveys are undertaken. Ancient woodland and peatland are irreplaceable
habitats and any adverse impacts to their integrity must be avoided. If any
protected species are present, licenses may be required and again, adverse
impact to their habitat should be avoided. There is the potential for bats, otter,
badgers, red squirrel, pine marten, water vole, fish, reptiles, amphibians, and
invertebrates. 
I note that the Argyll District Salmon Fisheries Board have responded ‘Argyll
DSFB request that appropriate baseline, real time and post works monitoring is
put in place to ensure any issues arising from the proposed development are
identified and rectified in a timely manner as to prevent any deterioration of fish
habitats and demonstrate that the development does not impact on the salmon
populations or the fisheries in the Argyll DSFB area. Argyll DSFB would welcome
an opportunity to constructively engage with any such process.’ It would be
advisable to engage in discussions with Argyll DSFB to ensure minimal impact
to fish and their habitat. 
I am also unclear about the proposed enhancement measures. Can there please
be a clarification on proposed enhancement measures for this proposed grid
connection route? 
Officer Comment: The Biodiversity Officer has withdrawn their previous objection
to the proposals which form this planning application.   
However, the FEI information indicating that the underground grid connection
has raised questions over the exact detail of these proposals. These grid
connection proposals do not form part of the current planning application , only
the EIA.  It is considered that sufficient detail on this matter has been provided at
this stage to allow matters to be considered in terms of potential significance of
cumulative environmental Impacts of the overall project.

Page 18

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Please note: the above are summaries and the full consultee responses
can be viewed on Argyll & Bute Council website. 
(D) HISTORY:  Planning history which is relevant to the current application is set out
below; 
• 97/00719/DET The main/original application for development of a wind farm
consisting of 14 turbines and associated infrastructure at Beinn Ghlas was
Approved August 1998 with 37 planning conditions attached to the Consent and
a Section 75 which contained 13 Clauses. 
• 21/00870/PP A Section 42 application to vary condition 2 relative to planning
permission (ref: 97/00719/DET) to allow Beinn Ghlas Wind Farm to operate for an
additional 10 years to 21 August 2033 was granted consent in June 2022. The
original S75 agreement was amended to remove a number of previously imposed
clauses either because they were no longer relevant or due to conditions being
used as per best practice advice. 
• 22/01586/SCOPE A Section 36 application was progressed in relation to Beinn
Ghlas Repowering which resulted in a request for a scoping opinion being
submitted to Scottish Ministers in July 2022 (scoping opinion received in May
2023). Following further site design work and consideration of ornithology
mitigation, a decision was made to reduce the scale of the proposed Beinn Ghlas
Wind Farm Repowering project from the 12 turbines presented at public
exhibitions held in January 2023 to 7 wind turbines at up to 149.9 m to tip. This
change brought the size of the Proposed Development below 50 MW requiring
any subsequent planning application to be submitted under the Town and Country
Planning (Environmental Impact Assessment) (Scotland) Regulations 2017. It is
as a result in the reduction in the scale of this scheme that the current application
is before the Planning Authority for determination. 
Officer Comment on S75 Matters: 
Members are requested to note that unlike 21/00870/PP this is not a variation of
the original Planning Permission for the windfarm and therefore the current
proposal, if approved and implemented, creates a new planning chapter for the
use of the site. Officers are of the view that the use of a S75 agreement is no
longer in accordance with good practice for the determination of windfarms and
therefore no S75 is proposed in this instance. 
Officers are content that all relevant matters can be addressed by means of
Planning Conditions and by reference to the published good practice advice from
the Scottish Ministers on the use of Planning Conditions for Windfarm Proposals.
This advice was not available when the original windfarm proposal was approved. 
(E) PUBLICITY:   
• Regulation 20 Advert Major Application:  Expired 02.10.25 
• Environmental Assessment Regulations Advert: Expired 11.10.25

Page 19

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• (FEI)  Environmental Assessment Advert: Expired 05.09.26 
(F) REPRESENTATIONS:   
Representations are published in full on the planning application file and are
available to view via the Public Access section of the Council’s website. A list of
those who have made representations is contained at Appendix B attached to
this report. At time of writing there has been 3 objections, and 26 submissions in
support of the proposals. 
(Officer Note: The single representation identified on the system is in fact a no
objection response from Arqiva already referenced in external consultee
responses at Section C of this report.) 
(i) Summary of matters raised: Objections 
• The proposal will have an unacceptable visual and environmental impact
• The proposals will adversely impact on Eagles
• Existing turbine bases should be used not new ones to reduce impacts on
the site. 
Officer Comment : These matters are addressed in the main report. 
(ii) Summary of Issued Matters Raised : Support 
• The clean energy this will supply is much needed and it is essential that
we produce power from renewable energy to support Scotland’s Green
Energy Plan. This proposal ticks all the boxes regarding sustainability and
green energy.
• The site has shown it is well suited to hosting this type of use
• Very little visual impact will occur
• Site is remote enough not to cause noise nuisance
• The Windfarm on this site is an asset to the community it is rarely seen
and not heard
• The windfarm is visible from my house and a wonderful place to visit
• Having lived close by to the windfarm we have had no problems over the
past years. Happy to support the proposals.
• Proposals cover a very similar envelope to the existing windfarm
• Proposals have been reduced by a significant amount to respect protected
eagles of very high conservation value. The protection of wildlife has been
a key feature of the EIA and project design.
• As a neighbouring landowner I support the project. Although the turbines
will be larger, they will contribute to the security of our country’s electrical
power in uncertain times.
• The revised number of turbines makes the proposals more acceptable.
Visual impact will increase but larger turbines will be more efficient.
• Older sites such as this should be upgraded as the initial environmental
impact of establishing the wind farm has already taken place.

Page 20

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(iii) Matters raised not considered material to determination of Planning
Application 
• The windfarm community benefits package has enabled the Taynuilt
Community Council to help finance several significant local projects. If
approved, the repowering of Beinn Ghlas will continue to benefit the local
environment and the Community Councils investment fund for many years
The proposals will boost the community to the tune of £6m. 
Officer Comment: Members are advised that monetary payments to communities
are not a material planning consideration in the determination of this application. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact Assessment Report (EIAR): Yes 
The EIA Report is presented in 4 volumes 
• Volume 1: Non-Technical Summary; 
• Volume 2: Environmental Impact Assessment Report; 
Chapter 1 – Introduction (this chapter) introduces the Proposed
Development and explains the underlying objectives of the proposals,
describes the statutory basis for the EIA, outlines the structure adopted in
this EIA Report and identifies the team of competent experts responsible
for undertaking and reporting the EIA. 
Chapter 2 – Proposed Development and Design Evolution provides an 
overview of the Proposed Development, giving a brief description of the 
permanent and temporary components. This chapter also details
construction activities, the indicative construction programme and
maintenance, as well as decommissioning activities. 
Chapter 3 – Environmental Impact Assessment Process summarises the 
Scoping process undertaken to establish the scope of the EIA, the adopted 
approach to the EIA and format of the individual technical assessments,
and modifications made to the EIA scope that have arisen during the
design development and assessment of the Proposed Development. 
Chapter 4 – Statutory & Policy Framework provides a summary of the 
legislative and policy framework relevant to the development including an 
overview on the climate emergency.   
Chapter 05 to 13 – Technical Assessments report the findings of the
detailed environmental assessments and the residual effects on the
environment predicted to occur as a result of implementation of the
Proposed Development. 
Chapter 14 – Schedule of Environmental Commitments summarises the 
additional and embedded environment mitigation suggested in the
technical chapters.

Page 21

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
References of the documents used or considered during the EIA are
provided at the end of each section, where relevant.  
• Volume 3: Application Drawings, Figures and Visualisations: 
Volume 3 comprises a series of plans, figures and photographs, which are
referenced in Volume 2, to illustrate the relationship between the existing
environment and the Proposed Development. 
o Volume 3a: Figures 
o Volume 3b: Landscape and Visual Impact Assessment
Photomontages 
o Volume 3c: Cultural Heritage Photomontages 
• Volume 4: Technical Appendices 
Comprises technical appendices, referred to in Volume 2, which contain 
detailed reports of the individual environmental assessments and other
relevant supporting documentation. 
The following additional documents are also included as part of the original
EIA Report (EIAR): 
o Planning Statement; 
o Design and Access Statement; and 
o Pre-Application Consultation (PAC) report. 
Further Environmental Information (FEI) Dated 03.08.26 
Additional Information was submitted by the applicant in response to the
Raeshaw Court decision. In terms of relevance to this project Officers
came to the view that the grid connection was part of the same project as
the windfarm under the EIAR Regulations, and therefore information was
provided to clarify potential environmental impacts associated with this. 
The FEI evaluates the future grid proposals against similar criteria to those
contained within the main EIAR and considers that no separate of
cumulative significant Environmental Impact will occur. 
Officer Clarification; as the future grid connection cable is underground
further detailed LVIA information was not requested by Officers, taking a
proportionate approach to matters that cannot as yet be specified in detail,
and do not form part of the current planning application. 
Additional Submissions made by Applicant in support of proposals 
23.12.25 – Response and clarifying information to initial Jacobs
Landscape Report 
27.01.26 – Submissions relating to Ancient woodland and Ecological
Monitoring 
25.03.26 – Additional Information on Ancient woodland and access track

Page 22

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
31.03.26 – Additional Peat Information 
30.07.26 – Additional Noise Submissions following updated National
Guidance on Windfarm Noise Evaluation. 
26.08.26 – Submission of proposed revised noise condition to accord with
new national guidance 
02.08.26 – Clarification of Forestry Felling data in EIAR in response to
Scottish Forestry consultation comments. 
03.09.26 -  Project Overview submission  
(ii) An Appropriate Assessment under the Conservation (Natural
Habitats) Regulations 1994:No – NatureScot have advised there is not
any requirement for an Appropriate Assessment in their consultation
response dated 12.12.25. 
(iii) A Design or Design/Access statement:   Yes.   
(iv) Sustainability Checklists (with reference to the requirements of LDP2
Policy 04) – Not required 
Note: As the planning application information requirements for wind farm
development are detailed and most require associated Environmental
Impact Assessment, it is not intended that the sustainability/sustainable
buildings checklist or LVIA will apply to wind farm development proposals
unless an EIA is not required.  
(v) A report on the impact of the proposed development e.g. Retail
impact, transport impact, noise impact, flood risk, drainage impact
etc.: Not required - All relevant reports are encompassed within the  EIAR
and FEI information and previously listed in this report.   
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:  No   
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  No    
(J) Section 25 of the Act; Development Plan and any other material
considerations over and above those listed above which have been taken
into account in the assessment of the application 
(i) List of all Development Plan Policy considerations taken into account in
assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy

Page 23

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 5 – Soils
NPF4 Policy 6 – Forestry, Woodland and Trees
NPF4 Policy 7 – Historic Assets and Places
NPF4 Policy 11 – Energy
NPF4 Policy 22 – Flood Risk and Water Management 
NPF4 Policy 23 – Health and Safety
NPF4 Policy 29 – Rural Development
NPF4 Policy 33 – Minerals 
Annex B – National Statements of Need 
3. Strategic Renewable Electricity Generation and Transmission Infrastructure 
Argyll and Bute Local Development Plan 2 (Adopted 2024) 
Policy 02 – Outwith Settlement Areas
Policy 04 – Sustainable Development
Policy 14 – Bad Neighbour Development
Policy 15 – Supporting the Protection, Conservation and Enhancement of Our
Historic Built Environment
Policy 19 – Scheduled Monuments
Policy 21 – Sites of Archaeological Importance
Policy 30 – The Sustainable Growth of Renewables
Policy 31 – Minerals
Policy 32 – Active Travel
Policy 35– Design of New and Existing, Public Roads and Private Access
Regimes
Policy 37 – Development Utilising an Existing Private Access or Existing Private
Road
Policy 38 – Construction Standards for Public Roads
Policy 39 – Construction Standards for Private Accesses
Policy 41 – Off Site Highway Improvements
Policy 43 – Safeguarding of Aerodromes
Policy 48 – Developer Contributions
Policy 55 – Flooding
Policy 56 – Land Erosion
Policy 57 – Risk Appraisals
Policy 58 – Private Water Supplies and Water Conservation
Policy 59 – Water Quality and the Environment
Policy 60 – Private Sewage Treatment Plants and Wastewater Drainage Systems
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 62 – Drainage Impact Assessments
Policy 63 – Waste Related Development and Waste Management
Policy 70 – Development Impact on National Scenic Areas (NSA’s)
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 77 – Forestry, Woodland and Trees
Policy 78 – Woodland Removal
Policy 79 – Protection of Soil and Peat Resources

Page 24

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(ii) List of all other material planning considerations taken into account in the
assessment of the application, having due regard to Annex A of Circular
3/2013. 
• Draft Energy Strategy and Just Transition Plan (January 2023) 
• Onshore Wind Policy Statement (OWPS) (December 2022) 
• Historic Environment Policy for Scotland (HEPS, 2019) Managing
Change     
• Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 
• Scottish Government Good Practice Principles for Shared Ownership and
Community Benefit of Onshore Renewable Energy Developments (May
2019) 
• Argyll & Bute Landscape Wind Energy Capacity Study (2017) (LWECS) 
• Siting and Designing Wind Farms in the Landscape, SNH (August 2017) 
• Onshore Wind Turbines: Planning Advice, Scottish Government (May 2014) 
• Guidance for Landscape and Visual Impact Assessment, 3rd Edition,
Landscape Institute, and Institute of Environmental Management &
Assessment, (2013) 
• PAN 1/2011: ‘Planning and Noise’ (March 2011) 
• The Scottish Government’s Policy on ‘Control of Woodland Removal’
(Forestry Commission Scotland 2009)  
• PAN 60 – Planning for Natural Heritage (Jan 2008) 
• Views of statutory and other consultees 
• Planning history of the site
• Legitimate public concern or support expressed on relevant planning
matters 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  No    
(L) Has the application been the subject of statutory pre-application
consultation (PAC):  Yes 
(M) Does the Council have an interest in the site:  No 
(N) Requirement for a pre-determination hearing: No   
(O) Summary assessment and summary of determining issues and material
considerations 
All consultees are satisfied  that planning permission can be granted for the
proposal subject to appropriate planning conditions. 
The proposal is consistent with the primary renewable energy policies of NPF4
and LDP2 and other relevant policies providing the recommended conditions
are attached. 
This proposal is EIA development, and the determination of this application is
also subject to the Town and Country Planning (Environmental Impact

Page 25

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Assessment) (Scotland) Regulations 2017.  There is a requirement to examine
the environmental information submitted and reach a reasoned conclusion on
the significant environmental effects of the proposal including those matters set
out in FEI relating to the proposed grid connection. 
The applicant has engaged with important stakeholders such as NatureScot
and has reduced the scale of the development to respect and ensure no
adverse impact upon protected species or protected landscapes.  This is noted
and welcomed by officers. 
The recommendation on this application has been guided by the conclusions of
the EIAR, and the proposal has been assessed against the polices of the
adopted Development Plan with particular regard to the policies of NPF4 and to
the policies of LDP2 as well as other material considerations. 
In light of the above, it is considered that the proposal is consistent with planning
policy, will not cause unacceptable and significant environmental impacts, and
that conditional planning permission should be granted. 
(P) Is the proposal consistent with the Development Plan: Yes 
(Q) Reasons why Planning Permission or Planning Permission in Principle
Should be Granted: 
As per the detailed assessment in this report, and taking into account all consultee
responses, third party representations, the submitted EIAR, FEI and relevant
planning policy it is considered that this proposal is acceptable and consistent with
the Development Plan.  It is therefore recommended that permission is granted
subject to the conditions recommended in this report. 
(R) Reasoned justification for a departure to the provisions of the Development
Plan: 
N/A - the proposal does not constitute a departure from the Development Plan. 
(S) Need for notification to Scottish Ministers or Historic Environment Scotland:
No 
Author of Report:      David Moore                                                    Date:  02.09.26 
Reviewing Officer:     Peter Bain                                                       Date:  03.09.2026 
Fergus Murray
Head of Development & Economic Growth

Page 26

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 25/01240/PP 
1.  PP - Approved Details & Standard Notes – EIA Development 
The development shall be implemented in accordance with the details
specified on the application form dated 21.07.25 and the Environmental Impact
Assessment Report dated 25.07.25, supporting information and the approved
drawings listed in the table below unless the prior written approval of the
planning authority is obtained for an amendment to the approved details under
Section 64 of the Town and Country Planning (Scotland) Act 1997. 
The developer and subsequent operators shall at all times construct and
operate the development hereby permitted in accordance with the provisions
of the Environmental Impact Assessment Report (and FEI submissions),
accompanying the application with mitigation measures adhered to in full, and
shall omit no part of the operations provided for by the permission except with
the prior written approval of the Planning Authority. 
Plan Title. Plan Ref.
No.
Version Date
Received
Location Plan Fig 1.1 Rev 05 02.09.25
Site Aerial Context Fig 1.2 Rev 05 02.09.25
Site Layout (Full) Fig 2.5a Rev 05 02.09.25
Site Layout  (zoomed) Fig 2.5b Rev 14 10.08.26
Inset 1: Temporary
Compound 1
Fig 2.5c - 02.09.25
Inset 2: Temporary
Compound 2
Fig 2.5d - 02.09.25
Existing Substation &
Indicative Induction Reactor
Layout
Fig 2.13 Rev 02 02.09.25
Existing Substation &
Indicative Induction Reactor
Elevation view
Fig 2.14 Rev 02 02.09.25
Indicative Wind Turbine Fig 2.6 Rev 03 02.09.25
Indicative Wind Turbine
Foundation
Fig 2.7 Rev 02 02.09.25
Indicative Crane
Hardstanding
Fig 2.8 Rev 02 02.09.25
Indicative Permanent
Anemometer Mast Details
Fig 2.9 Rev 02 02.09.25
Indicative Access Track
Details
Fig 2.11 Rev 03 02.09.25
Access Junction Design Fig 10.4 Rev 03 02.09.25
Indicative Site Access (A85
to Fearnoch)
Fig 2.10a Rev 03  02.09.25
Indicative Site Access 
(Fearnoch Forest Track)
Fig 2.10b Rev 04 02.09.25
Indicative Site Access
(Fearnoch Forest Track to
C32 Glen Lonan Road)
Fig 2.10c Rev 04 02.09.25
Indicative Temporary
Construction Compound
Fig 2.10d Rev 02 02.09.25

Page 27

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Access Options -Glen
Lonan Road
Indicative Cable Trench
Details
Fig 2.12 Rev 02 02.09.25 
Reason: For the purpose of clarity, to ensure that the development is
constructed and operated in the manner advanced in the Environmental
Impact Assessment Report, upon which the environmental effects of the
development have been assessed and determined to be acceptable. 
2.  Notification of Date of First Commissioning and Final Commissioning. 
(1) Written confirmation of the Date of First Commissioning shall be provided
to the Planning Authority no later than one calendar month after that date.
(2) Written confirmation of the Date of Final Commissioning shall be provided
to the Planning Authority no later than one calendar month after that date. 
Reason: To allow the Planning Authority to calculate the date of expiry of the
consent. 
3.  Commencement of Development 
(1) The Development shall be commenced no later than five years from the
date of this consent,   
(2) Written confirmation of the intended date of Commencement of
Development shall be provided to the Planning Authority as soon as is
practicable after deciding on such a date and in any event no later than
one calendar month prior to the Commencement of Development.   
Reason:  To ensure that the consent is implemented within a reasonable
period and to allow the Planning Authority to monitor compliance with
obligations attached to this consent and deemed planning permission as
appropriate. 
4.  Period of Permission 
The planning permission hereby granted shall endure for a period of 35 years
from the date of final commissioning. Written confirmation of the date of final
commissioning shall be provided to the planning authority no later than one
calendar month after that date. 
Reason: In order to define the terms of this permission, to minimise the level
of visual intrusion, and to ensure the satisfactory reinstatement of the site. 
5.  Decommissioning 
The development shall cease to generate electricity by no later than the date
falling 35 years from the date of final commissioning. The decommissioning
and restoration of the site shall be completed within three years from the date
on which the development ceases to generate electricity unless otherwise
agreed in writing with the planning authority. 
Reason: In order to define the terms of this permission, to minimise the level
of visual intrusion, and to ensure the satisfactory reinstatement of the site.

Page 28

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
6.  Decommissioning, Restoration and Aftercare Strategy 
No development shall commence unless a decommissioning, restoration and
aftercare strategy has been submitted to and approved in writing by the
planning authority in consultation with SEPA and NatureScot. The scheme
shall detail measures for the decommissioning of the development, restoration
and aftercare of the site and will include, without limitation, proposals for the
removal of the above ground elements of the development, the treatment of
ground surfaces, opportunities for habitat and biodiversity enhancement, the
management and timing of the works, and environmental management
provision. 
Reason: To ensure the decommissioning and removal of the Development in
an appropriate and environmentally acceptable manner and the restoration
and aftercare of the site, in the interests of safety, amenity and environmental
protection. 
7.  Redundant Turbines 
If any wind turbine(s) fails to produce an electricity supply to the grid for a
continuous period of 12 months then, unless otherwise agreed in writing by the
planning authority, the wind turbine and any associated above ground
infrastructure solely required for that turbine(s), together with turbine
foundations to a depth of one metre below ground level shall be dismantled
and removed from the site and the area around the turbine restored in
accordance with a scheme to be submitted to and approved in writing by the
Planning Authority in consultation with SEPA and NatureScot. The scheme
shall be submitted to the planning authority within three months of the expiry
of the 12-month period and shall include a timetable for its implementation. 
Reason :To ensure that any redundant wind turbine is removed from the site,
in the interests of safety, to minimise the level of visual intrusion and to ensure
the satisfactory reinstatement of the site. 
8.  Financial Guarantee
(a) At least three months prior to the commencement of development, the
developer shall provide to the planning authority written details of the bond or
other financial guarantee to cover the cost of all decommissioning, restoration
and aftercare of the site as required by condition 6, for the written approval of
the planning authority. These written details shall include evidence from a
competent independent professional who has relevant experience in such
matters that the guarantee is sufficient to meet the requirements of condition
6. 
(b) No work shall commence on site until the developer has delivered the
approved bond or other financial guarantee to the planning authority and the
planning authority has provided written confirmation that the bond or other
financial guarantee is satisfactory. 
(c) The developer shall ensure that the approved bond or other financial
guarantee is maintained throughout the duration of this permission and until
the date of completion of all decommissioning, restoration and aftercare
obligations as required by condition 6 of this permission.

Page 29

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(d) The adequacy of the approved bond or other financial guarantee will be
subject to review at five yearly intervals, or such other intervals as agreed by
the planning authority, from commencement of development, to be paid for by
the developer and conducted by a competent independent professional who
has relevant experience in such matters. The findings of such reviews will be
provided to the developer and the planning authority within 14 days of the
review taking place. Any revisions to the bond or other financial guarantee
recommended by the review and agreed in writing by the planning authority
shall be made by the developer within 28 days of receiving said written
agreement from the planning authority and documentary evidence shall be
provided to the planning authority by the developer to that effect. 
Reason: To ensure there are sufficient funds available for the full costs of
decommissioning, restoration and aftercare. 
9.  Peat Management Plan 
(1) There shall be no Commencement of Development until a detailed Peat
and Carbon Rich Soils Management Plan (PMP) has been submitted to and
approved in writing by the Planning Authority in consultation with SEPA. 
(2) The PMP shall: 
(a) take account of site and ground investigations to minimise the loss of
peat and other carbon rich soil and minimise carbon loss;
(b) include actions, including micrositing, to minimise excavated peat and
other carbon rich soils volumes 
(c) encourage use of excavated peat and other carbon rich soils in an
appropriate manner; and
(d) follow good practice for handling, storing and reinstating peat and other
carbon rich soils. 
(3) The Peat and Carbon Rich Soils Management Plan shall thereafter be
implemented as approved upon the Commencement of Development.
having specific regard to the SEPA requirements set out below:
a) All near-natural condition peatland habitat within 50m of infrastructure
shall be physically demarked prior to construction commencing to
ensure construction vehicles do not disturb the habitat during
construction. The schedule of mitigation should outline how this habitat
will be safeguarded.
b) Post-construction monitoring of impacts on near natural habitat in the
vicinity of TCC2,  and which will require a mechanism to take specific
action should impacts occur:
c) A schedule of monitoring should ensure the near-natural peatland
habitat is safeguarded from direct and indirect impacts and must
include: 
• Proposals for fixed point photography and repeat National
Vegetation Classification and hydrological condition surveys.
• Frequency of monitoring, supported by justification.
• Criteria that will trigger additional action should monitoring
reveal that the near-natural peatland habitat is no longer
sequestering or is degrading to a modified habitat type.

Page 30

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
d) Bottomless arch culverts or span bridges should be used for all new
or upgraded watercourse crossings, and all watercourse crossings
must be designed to convey the 1:200 plus Climate Change.
e) Any actions taken shall adhere to NatureScot’s peatland restoration
guidance. 
Reason: To ensure that peat is protected, extracted, stored, reinstated or
restored in a manner which minimises waste and maximises peat restoration
on site. 
10.  Floating Tracks
Prior to commencement of development a plan showing details of the extent
and construction methodology of any required floating tracks shall be
submitted for the further written approval of the Planning Authority in
consultation with SEPA. 
Thereafter construction of the floating tracks shall be undertaken in full
accordance with the approved details. 
Reason: To minimise the impact on peat 
11.  Design and operation of wind turbines
(1) No turbines shall be erected until details and specification of the
proposed wind turbines, (including the size, make and model, power
rating and sound power levels, nameplate generating capacity, type,
external finish and colour) any anemometry masts and all turbine
associated apparatus have been submitted to and approved in writing
by the Planning Authority.
(2) For the avoidance of doubt the scale of the turbines shall not exceed
the parameters assessed in the EIA Report and set out in the
description of the Development approved.
(3) The submission shall demonstrate that all wind turbine blades shall
rotate in the same direction.
(4) Thereafter the wind turbines, any anemometry masts and all
associated apparatus shall be constructed and operated in
accordance with the details approved under part (1) and shall be
maintained in the free from external rust, staining or discolouration,
until such time as the Development is decommissioned unless
otherwise agreed in writing by the Planning Authority. 
Reason: To ensure that the environmental impacts of the turbines forming part
of the Development conform to the impacts assessed in the EIA Report and in
the interests of the visual amenity of the area. 
12.  Design of Sub-station and ancillary development 
(1) There shall be no Commencement of Development  until final details of
any proposed changes to the location, layout, external appearance,
dimensions, and surface materials of   any substation  and control room
buildings on the site, any above ground electrical equipment,
associated compounds, construction compound, boundary fencing,
external lighting and parking areas have been submitted to, and
approved in writing by, the Planning Authority.  For the avoidance of
doubt the details of the sub-station shall not exceed the parameters
assessed in the EIA Report and application submissions.

Page 31

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(2) Thereafter, the substation and control room buildings, any above
ground electrical equipment, associated compounds, fencing, external
lighting and parking areas shall be constructed in accordance with the
details approved under part (1).  
Reason: To ensure that the environmental impacts of the sub-station and
ancillary development forming part of the Development conform to the impacts
assessed in the EIA Report and in the interests of the visual amenity of the
area. 
13.  Implementation of mitigation measures 
(1) No development (including the Site Enabling Works) shall commence
until a Schedule of Mitigation has been submitted to and approved in
writing by the Planning Authority. This Schedule shall encompass a list
of all mitigation measures from the EIA Report, any other commitments
made by the applicant, and all relevant mitigation secured by conditions
attached to this permission with defined timescales for implementation
of each mitigation measure. 
(2) Thereafter, the approved Schedule of Mitigation shall be implemented
in full unless otherwise approved in writing by the Planning Authority. 
Reason: to ensure that the identified mitigation through the EIA Report is
carried out in accordance with the approved details. 
14.  Enabling Works 
(1) No development or works shall commence on the Site unless and until a
programme of Site Enabling Works, detailing the extent, area and timings
of such works (the ‘Site Enabling Works Programme’) has been submitted
to and approved in writing by the Planning Authority.  The Site Enabling
Works Programme must as a minimum provide for the following: 
(a) A plan showing the extent and layout of the enabling works;
(b) The employment of a suitably qualified and experienced Ecological Clerk
of Works, or equivalent, for the project, with specific responsibility for
environmental management and the authority to take action when
required, including stopping operations and implementing mitigation
measures; 
(c) The employment of a Planning Monitoring Officer, to discharge and to
monitor compliance with this condition, including provision of a quarterly
compliance report to the Council;
(d) A programme for environmental auditing and monitoring within the Site,
before and during the Site Enabling Works, to provide the establishment
of an environmental checklist, to monitor and input into the planning of
construction activities and ensure implementation of all environmental
mitigation measures;
(e) A site-specific statement outlining drainage and sediment management
for all exploration areas and measures to limit above ground construction
(f) activities during periods of high rainfall, including weather forecasting
and actions to be taken in advance of adverse forecasts. 
(g) Working arrangements, including a programme for the phasing of
operations, and particularly the movement of plant, materials and rock

Page 32

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
into, across and out of the site to minimise, so far as reasonably
possible, impact on communities or businesses adjacent to or in close
proximity to the Site.;
(h) Waste Management and Pollution Controls including contingency plans
in case of pollution incidents;
(i) A programme of work for the evaluation, preservation and recording of
any archaeological and historic features affected by the Development,
including a timetable for investigation, which must be submitted for the
written approval of the Planning Authority. The approved programme
must be implemented in accordance with the agreed timetable for
investigation unless otherwise agreed in writing with the Planning
Authority;
(j) Measures to protect any scheduled monument(s) within the area of the
enabling works;
(k) Details for the delivery, storage, loading and unloading of plant and
materials to be used in constructing the development, with particular
regard for the deployment of HGVs and any abnormal loads;
(l) Measures to control the emission of dust and dirt during construction; 
(m) Provision of welfare facilities on site during construction and the means
of disposal of foul drainage;
(n) Measures to protect all existing public water, private water and drainage
arrangements, with suitable back up arrangements in case of any
disruption to these provisions from Site Enabling Works;
(o) An Access Management Plan to maintain public access and promote the
general safety of walkers, cyclists, and users out-with the principal
construction areas and access roads serving the Development during
the Site Exploratory Works. A key principle to be advanced within the
Plan is to minimise restrictions on public access to important recreational
facilities; 
(p) Wheel washing facilities to prevent vehicles associated with the Site
Enabling Works from depositing mud or dirt on the public road network
when leaving the Site. 
(q) Lighting for Site Enabling Works which will minimise illumination, glare or
light spillage outwith the site boundary. 
(2) All Site Enabling Works must be carried out in accordance with the
approved Site Enabling Works Programme unless otherwise agreed in
writing with the Planning Authority. 
Reason: To ensure that all Site Exploratory Works are carried out in a manner
that minimises their impact on amenity and the environment, and that the
mitigation measures contained in the EIA Report accompanying the application
are fully implemented. 
15.  Planning Monitoring Officer 
(1) There shall be no Commencement of Development until the terms of
appointment by the Company of an independent and suitably qualified
consultant as Planning Monitoring Officer (“PMO”) have been submitted to,
and approved in writing by, the Planning Authority.  The terms of
appointment shall: 
(a) impose a duty to monitor compliance with the terms of the deemed
planning permission and the conditions attached to it;

Page 33

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(b) require the PMO to submit a quarterly report to the Planning Authority
summarising works undertaken on site, matters of compliance or
otherwise with the terms of the deemed planning permission and
conditions attached to it, alongside a summary of the incidents
recorded and reported by the ECoW and GCoW; and
(c) require the PMO to report to the Planning Authority any incidences of
non-compliance with the terms of the deemed planning permission and
conditions attached to it at the earliest practical opportunity, and no
later than 10 working days following the incidence of non-compliance. 
(2) The PMO shall be appointed on the approved terms throughout the period
from Commencement of Development to completion of construction works
and post-construction site reinstatement works. 
(3) Prior to the decommissioning, restoration and aftercare phases of the
Development or the expiration of the operational period of the consent
(whichever is the earlier), details of the terms of appointment of a and
suitably qualified consultant as PMO by the Company throughout the
decommissioning, restoration and aftercare phases of the Development
shall be submitted to, and approved in writing by, the Planning Authority. 
(4) the PMO shall be appointed on the terms approved under part (3)
throughout the decommissioning, restoration and aftercare phases of the
Development. 
Reason: To ensure compliance with the planning permission and the
conditions attached to it. 
16.  Ecological Clerk of Works
(1) There shall be no Commencement of Development until the terms of
appointment of a suitably qualified, experienced, and independent
Ecological Clerk of Works (“ECoW”) by the Company have been
submitted to, and approved in writing by, the Planning Authority. The
terms of appointment shall: 
(a) impose a duty to monitor compliance with the ecological and
hydrological commitments provided in any approved Schedule of
Mitigation, any approved Construction and Environmental
Management Plan, any approved Habitat Management Plan, 
and any approved species protection plans,
(b) require the ECoW to report to the nominated construction project
manager any incidences of non-compliance with the ECoW
works at the earliest practical opportunity; 
(c) require the ECoW to submit a quarterly report to the Planning
Authority summarising works undertaken on site; and
(d) require the ECoW to report to the Planning Authority any
incidences of non-compliance with the ECoW works at the
earliest practical opportunity, and no later than 5 working days
following the incidence of non-compliance. 
(2) The ECoW shall be appointed on the terms approved under part (1)
throughout the period from pre-construction works1, Commencement 
1 This may include Site Enabling Works. If the Site Enabling Works condition is included the wording should be
updated to reflect this.

Page 34

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
of Development to completion of construction works and post-
construction site reinstatement works. 
(3) Prior to the decommissioning, restoration and aftercare phases of the
Development or the expiration of the operational period of the consent
(whichever is the earlier), details of the terms of appointment of a
suitably qualified, experienced, and independent ECoW by the
Company throughout the decommissioning, restoration and aftercare
phases of the Development shall be submitted to, and approved in
writing by, the Planning Authority. 
(4) the ECoW shall be appointed on the terms approved under part (3)
throughout the decommissioning, restoration and aftercare phases of
the Development. 
Reason: To secure effective monitoring of and compliance with the
environmental mitigation and management measures associated with the
Development during the construction, post-construction restoration,
decommissioning, restoration and aftercare phases. 
17.  Environmental Clerk of Works 
(1) There shall be no Commencement of Development until the terms of
appointment of an independent Environmental Clerk of Works (“EnvCoW”) by
the Company have been submitted to, and approved in writing by, the Planning
Authority. The terms of appointment shall: 
(a) impose a duty to monitor compliance with the environmental
commitments provided in the EIA Report, any approved Construction
Environmental Management Plan, any approved Habitat Management
Plan, and any species or habitat management plans identified in the
EIA Report;
(b) require the EnvCoW to report to the nominated construction project
manager, developer and Planning Authority any incidences of non-
compliance with the EnvCoW works at the earliest practical
opportunity; 
(c) require the EnvCoW to submit a monthly report to the construction
project manager, developer and Planning Authority summarising works
undertaken on site. 
(2) Prior to the decommissioning, restoration and aftercare phases of the
Development or the expiration of the operational period of the consent
(whichever is the earlier), details of the terms of appointment of a suitably
qualified, experienced, and independent EnvCoW by the Company throughout
the decommissioning, restoration and aftercare phases of the Development
shall be submitted to and approved in writing by the Planning Authority. 
(3) the EnvCoW shall be appointed on the terms approved under part (2)
throughout the decommissioning, restoration and aftercare phases of the
Development. 
Reason: To secure effective and transparent monitoring of and compliance
with the environmental mitigation and management measures associated with
the Development during the construction, decommissioning, restoration and
aftercare phases

Page 35

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
18.  Geotechnical Clerk of Works 
(1) There shall be no Commencement of Development until the terms of
appointment by the Company of an independent and suitably qualified
engineer as a Geotechnical Clerk of Works (“GCoW”) have been submitted to,
and approved in writing by, the Planning Authority.  The terms of appointment
shall: 
(a) impose a duty to monitor compliance with any approved  Construction
and Environmental Management Plan, any approved  Peat
Management Plan,  and any approved Peat Landslide Risk
Management Plan, 
(b) require the GCoW to report to the Planning Authority and nominated
construction project manager any incidences of geotechnical risks at
the earliest practical opportunity, and no later than 5 working days
following the incidence of non-compliance; and
(c) require the GCoW to report to the Planning Authority any incidences
of peat land slips at the earliest practical opportunity to SEPA where
there are risks to the wider environment, and no later than 5 working
days following the incidence of peat land slips. 
(2) The GCoW shall be appointed on the terms approved under part (1)
throughout the period from Commencement of Development to completion of
construction works and post-construction site reinstatement works. 
(3) Prior to the decommissioning, restoration and aftercare phases of the
Development or the expiration of the operational period of the consent
(whichever is the earlier), details of the terms of appointment of a suitably
qualified engineer as a GCoW by the Company throughout the
decommissioning, restoration and aftercare phases of the Development shall
be submitted to, and approved in writing by the Planning Authority.   
(4) the GCoW shall be appointed on the terms approved under part (3)
throughout the decommissioning, restoration and aftercare phases of the
Development. 
Reason: To secure effective monitoring of and compliance with the mitigation
related to geotechnical matters, particularly peat land slip and management
measures associated with the Development during the construction, post-
construction restoration, decommissioning, restoration and aftercare phases. 
19.  Construction and Environmental Management Plan (CEMP)   
(1) There shall be no Commencement of Development until a Construction
and Environmental Management Plan (CEMP) containing site specific details
of all on-site construction works, post-construction reinstatement, drainage and
mitigation, together with details of their timetabling, has been submitted to, and
approved in writing by, the Planning Authority.  The CEMP shall be informed
by the site and ground investigation works and best practice guidance. 
(2) The CEMP shall provide: 
(a) a site waste management plan (dealing with all aspects of waste produced
during the construction period other than peat and other carbon rich soils),
including details of contingency planning in the event of accidental release

Page 36

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
of materials which could cause harm to the environment, evidencing all
proposals comply with SEPA’s guidance and the requirements of the
waste management licensing regime as appropriate;
(b) details of the location, layout, formation of the construction compound,
welfare facilities, any areas of hardstanding, turning areas, internal access
tracks, car parking, material stockpiles, oil, fuel and chemical storage,
lighting columns, and any construction compound boundary fencing
required for the construction period;
(c) a dust management plan detailing all mitigation/dust suppression
measures intended to reduce the impacts of dust on site, including
measures to reduce dust on roads;
(d) site specific details for management and operation of any concrete
batching plant (including disposal of pH-rich waste water and substances);
(e) details of measures to be taken to prevent loose or deleterious material
being deposited on the local road network including wheel cleaning and
lorry sheeting facilities, and measures to clean the site entrances and the
adjacent local road network;
(f) a Pollution Prevention and Incident Plan incorporating a Pollution
Prevention Plan, Pollution Incident Plan and a Pollution Control Monitoring
Plan, this shall provide measures to protect watercourses, groundwater,
management of natural surface hydrological flows (flushes, springs, etc.)
and protection of peatland/soils, arrangements for the storage and
management of oil and fuel and other chemicals on the site and sewage
disposal and treatment;
(g) details of soil storage and management including outline quantities,
locations (other than peat and other carbon rich soils) management of long
term storage of construction generated to facilitate future site restoration;
(h) a drainage management strategy, demonstrating how all surface and
waste water arising during and after construction is to be managed and
prevented from impacting on the water environment and to mitigate flood
risk;
(i) a surface water and groundwater management and treatment plan,
including details of the separation of clean and dirty water drains, and
location of settlement lagoons for silt laden water;
(j) details of temporary site illumination, including measures to ensure light
spill/pollution is minimised and avoids habitats within the site and does not
extend beyond the immediate working area, and not beyond the site
boundary;
(k) Any required Protected Species Plans. The Plan(s) shall be informed by
surveys carried out by a suitably qualified person (and updated surveys
should the existing survey information be more than 18 months old at start
of development works). The ecological and species surveys shall inform
the mitigation measures required to protect protected species during
construction of the Development. The Plan shall provide mitigation
measures, as required, and a timetable for implementation.
(l) details of the construction of the access into the site, including associated
drainage and the creation and maintenance of associated visibility splays;
(m) Site-specific Construction Method Statements for the following:
i. crane pads;
ii. turbine foundations;
iii. working cable trenches;
iv. erection of the wind turbines and meteorological masts; 
v. Energy storage compound formation and installation of energy
storage equipment;

Page 37

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
vi. Substation compound formation, erection of associated buildings
and ancillary infrastructure; 
vii. watercourse crossings including full details and plans of the
design and specification of all new and upgraded watercourse
crossings to be constructed, ensuring continuous flow and fish
passage with no hanging culverts, noting all crossings shall be
oversized bottomless arched culverts or traditional style bridges; 
(n) details of post-construction restoration/reinstatement of the working
areas not required during the operation of the Development;
(o) Historic Environment Protection Plan including details of protective
fencing of the location of the historic environment features to be
protected during construction works, including appropriate buffers; 
(p) a wetland ecosystems survey and mitigation plan; 
(q) a tree felling and management plan;
(r) A Construction Noise Management Plan including details of the
management of noise and vibration during construction and post-
construction restoration, including that caused by construction traffic,
to the lowest practicable levels and in accordance with BS 5228:2009
“Code of Practice for noise and vibration control on construction and
open sites – Part 1: Noise and Part 2: Vibration” (or any updated
version/document which superseded this document) and how any
properties likely to be affected by construction noise will be kept
informed;
(s) Construction Method Statements for all roads/tracks to be
altered/formed associated with the development, including their width,
likelihood of widening or passing places, means of drainage (which
shall have regard to SUDS principles), means of construction, and
edge reinstatement including verge width. The specification shall be
accompanied by relevant plans at a sufficient scale; 
(t) the cable trenches;
(u) A phasing plan for the construction works; and
(v) A written scheme which details the methodology for dealing with any
revisions to any of the documents required under this part (3). Any
revised documents will require to be submitted to and approved in
writing by the Planning Authority prior to the revisions being
implemented on site. 
(3) The Development shall be implemented in accordance with the CEMP
approved under part (1) unless otherwise approved in advance in writing by
the Planning Authority. 
Reason: To ensure that all construction operations are carried out in a manner
that minimises their impact on road safety, amenity and the environment, and
that the mitigation measures contained in the EIA Report accompanying the
application, or as otherwise agreed, are fully implemented.

Page 38

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
20.  Construction Hours 
(1) Construction work shall only take place between the hours of 07.00 to 19.00
on Monday to Friday inclusive and 07.00 to 16.00 on Saturdays, with no
construction work taking place on a Sunday or Public Holiday. Outwith
these specified hours, maintenance works, emergency works and
construction works shall be limited to concrete pours, wind turbine erection,
dust suppression, and the testing of plant and equipment, unless otherwise
approved in advance in writing by the Planning Authority.   
(2) HGV movements (excluding abnormal loads) to or from the site during
construction of the wind farm shall be limited to [07.00 to 19.00 Monday to
Friday (inclusive), and 07.00 to 16.00 on Saturdays, with no HGV
movements to or from site taking place on a Sunday or Public Holiday.
Outwith these hours, and subject to paragraph (1), HGV movements are to
be limited to wind turbine delivery (unless otherwise approved in advance
in writing by the Planning Authority).   
Reason: In the interests of local amenity. 
21.  Traffic Management Plan 
(1) There shall be no Commencement of Development until a Traffic
Management Plan has been submitted to, and approved in writing by, the
Planning Authority in consultation with the Area Roads Manager and Transport
Scotland.  The Traffic Management Plan shall provide: 
(a) the routeing of all traffic associated with the Development on public
roads;
(b) measures to ensure that the specified routes are adhered to, including
monitoring procedures;
(c) details of all signage and lining arrangements to be put in place;
(d) provisions for emergency vehicle access; 
(e) provision for the submission and agreement of a roads condition survey
pre-and post-construction accompanied by an appropriate agreement
between the Planning Authority and the Company to ensure the
delivery of any post-construction public road restoration that may be
required; and
(f) identification of a nominated person to whom any road safety issues
can be referred. 
(2) The approved Traffic Management Plan shall be implemented in full,
unless otherwise approved in advance in writing by the Planning
Authority. 
Reason: In the interests of road safety. 
22.  On site Electricity and control cables 
All electricity and control cables between the turbines, substations and control
buildings shall be laid out underground unless as otherwise agreed in writing
with the Planning Authority and NatureScot. 
Reason: In the interests of the protection of Nature Interests and to avoid any
additional above ground visual impacts arising from the development.

Page 39

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
23.  Biodiversity Enhancement and Habitat Management Plan 
No development in respect of this planning permission shall take place unless
a Biodiversity Enhancement and Habitat Management Plan (BE-HMP) has
been submitted to and approved by the Planning Authority in consultation with
NatureScot. The BE-HMP shall set out the proposed Biodiversity
Enhancement and Habitat Management of the development site during the
period of construction, operation, decommissioning and restoration of the site
and set out proposals for habitat and biodiversity restoration and
enhancement. 
The approved BE-HMP shall be implemented in full to the agreed timescale. 
Reason : In order to define the terms of the permission and in order to prevent
undue adverse impacts to wildlife and habitats and provide biodiversity
enhancement and to protect and improve habitats which may be affected by
the development. 
24.  Programme of Archaeological Works 
No development shall take place within the development site as outlined in red
on the approved plan until the developer has secured the implementation of a
programme of archaeological works in accordance with a written scheme of
investigation which has been submitted by the applicant, agreed by the West
of Scotland Archaeology Service, and approved by the Planning Authority.
Thereafter the developer shall ensure that the programme of archaeological
works is fully implemented and that all recording and recovery of
archaeological resources within the development site is undertaken to the
satisfaction of the Planning Authority in agreement with the West of Scotland
Archaeology Service. 
Reason To ensure the protection and recording of archaeological features. 
25.  Access Management Plan 
No development shall commence unless and until an Access Management
Plan (AMP) has been submitted to and approved in writing by the Planning
Authority. The AMP shall include (but shall not necessarily be limited to): 
(a) identification of limitations on site access rights during the construction
phase; 
(b) details of appropriate access management during the construction and
operational periods of the Development, including such matters as the
maintenance of public access and temporary or permanent diversion or
stopping up of public rights of way; 
(c) details of warning and management signage which is appropriate and takes
account of both the operational needs and access rights during both the
construction and the operational periods of the Development; and
(d) set out the access management regime to be implemented during the
operational phase of the Development. 
(e) Provision for operational use of the wind farm tracks/access road for leisure
access, including procedures to maintain amenities. 
The approved AMP shall thereafter be implemented in full.

Page 40

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Reason: To ensure that public access is managed appropriately throughout
the construction and operational period of the Development.  
26.  Roads and Infrastructure 
Prior to the commencement of development written confirmation of adherence
the following matters shall be submitted for the approval of the Planning
Authority in consultation with the Area Roads Manager. All required works to
be undertaken in accordance with the requirement of the Area Roads Manager
as agreed. 
• New accesses and existing accesses in need of amending or
modification to be upgraded in accordance with Operational Services
Drg No SD08/001b. 
• Visibility splays measuring 42m x 2.4m to be cleared and maintained in
perpetuity. 
• Additional road signs and markings will be required, as per TSRGD.
Exact specifications and locations to be agreed with this department. 
• A statement in respect to the materials and plant to be transported over
the C32 to serve the works is required. The statement should also state
where materials will be imported from along with estimated quantities,
so the effect on local quarry roads can be assessed.  
• Major works notice will be required for the planned C32 upgrades. 
• TTRO applications will be required for works within the C32 corridor
.
• Detailed engineering, technical drawing required in relation to C32
upgrades. Details to be approved by this department. General
illustrations as per Fig 2.10b. 2.10c and 2.10d. 
• A system of traffic management to be in place to accommodate the
traversing of abnormal loads over the C32. Details to be agreed with
this department. 
• A pre start road inspection to be carried out. Any extraordinary damage
to the C32 road corridor caused by the associated proposal works to
be made good at no expense to Argyll and Bute Council. 
• A pre start site meeting is required, to discuss planned changes to the
C32. 
Reason: To ensure that the construction activities associated with the
proposals and  transportation of abnormal loads will not have any detrimental
effect on the  road network. 
27.  Construction Traffic Management Plan (CTMP) 
Prior to commencement of the development, a Construction Traffic
Management Plan (CTMP) shall be submitted to, and approved by, the
Planning Authority, after consultation with Transport Scotland and the Area
Roads Manager. Thereafter, all construction traffic associated with the
development shall conform to the requirements of the agreed plan.

Page 41

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
This shall include: 
a) Details of any additional signing or temporary traffic control measures
deemed necessary due to the size or length of any loads being
transported must be undertaken by a recognised QA traffic
management consultant 
b) Details of proposals for an abnormal load delivery trial-run to be
undertaken with the involvement of Police Scotland and prior to the
commencement of abnormal loads deliveries. Trial-run proposals shall
be submitted to and approved in writing by the Planning Authority in
consultation with Transport Scotland. 
c) Details of any accommodation measures required, including the
removal of street furniture, junction widening, over-sail of the trunk
road, and traffic management must be approved and implemented to
the satisfaction of the Planning Authority, in consultation with Transport
Scotland. 
Reason :To mitigate the adverse impact of construction traffic on the safe and
efficient operation of the trunk road network. 
28.  Decommissioning Traffic Plan 
Prior to any decommissioning of the development, a Decommissioning Traffic
Plan in respect of traffic management shall be prepared and approved in
writing by the Planning Authority, in consultation with Transport Scotland. 
The Development shall be decommissioned in accordance with the approved
decommissioning traffic plan. 
Reason To mitigate the adverse impact of construction traffic on the safe and
efficient operation of the trunk road network 
29.  Aviation Lighting 
That no turbine shall be erected unless a scheme for aviation lighting for the
wind farm, consisting of Civil Aviation Authority-compliant visible aviation
lighting and Ministry of Defence (DIO) accredited infra-red aviation lighting, has
been submitted and approved by the planning authority in consultation with
DIO and Civil Aviation Authority. The turbines shall be erected with the
approved lighting installed and the lighting shall remain operational throughout
the duration of this permission. 
Reason In the interests of aviation safety and landscape amenity. 
30.  Defence Infrastructure Safeguarding 
(i) Aviation Lighting 
Prior to commencing construction of any wind turbine generators, or deploying
any construction equipment or temporal structure(s) 50 metres or more in
height (above ground level) the undertaker must submit an aviation lighting
scheme for the approval of the Argyll & Bute Council in conjunction with the
Ministry of Defence defining how the development will be lit throughout its life

Page 42

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
to maintain civil and military aviation safety requirements as determined
necessary for aviation safety by the Ministry of Defence. This should set out: 
a) details of any construction equipment and temporal structures with a
total height of 50 metres or greater (above ground level) that will be
deployed during the construction of wind turbine generators and details of
any aviation warning lighting that they will be fitted with; and 
b) the locations and heights of all wind turbine generators and any
anemometry mast featured in the development identifying those that will
be fitted with aviation warning lighting identifying the position of the lights
on the wind turbine generators; the type(s) of lights that will be fitted and
the performance specification(s) of the lighting type(s) to be used. 
Thereafter, the undertaker must exhibit such lights as detailed in the approved
aviation lighting scheme. The lighting installed will remain operational for the
lifetime of the development. 
(ii)   Aviation Charting and Safety Management 
The undertaker must notify the Ministry of Defence, at least 14 days prior to
the commencement of the works, in writing of the following information: 
a) the date of the commencement of the erection of wind turbine
generators; 
b) the maximum height of any construction equipment to be used in the
erection of the wind turbines; 
c) the date any wind turbine generators are brought into use; 
d) the latitude and longitude and maximum heights of each wind turbine
generator, and any anemometer mast(s). 
The Ministry of Defence must be notified of any changes to the information
supplied in accordance with these requirements and of the completion of the
construction of the development. 
Reason In the interests of aviation safety.

Page 43

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
31.  Television and Radio Reception Mitigation  
(1) No development shall commence unless and until a baseline Television
and Radio Reception survey has been undertaken. 
(2) In the event of a claim by any individual person regarding TV picture loss
or interference, including radio reception, at their house, business premise or
other building, this shall be investigated by an independent qualified engineer,
appointed by the Company (at  the companies expense), and the results,
including any mitigation measures, shall be submitted to the Planning
Authority, alongside a copy of the results of the baseline survey undertaken
under the terms of part (1). 
(3) Should any impairment to the TV signal or radio reception be attributable
to the Development, the Company shall remedy such impairment so that the
standard of reception at the affected property is equivalent to the baseline TV
or radio reception as relevant. For the avoidance of doubt, the resolution of
disputes shall be determined by an independent arbiter e.g. OFCOM or other
professional body as appropriate. 
Reason: To ensure local radio [and television] services are sustained during
the construction and operation of the Development.
32.  Operational Noise Planning Condition
1) The rating level of noise from the combined effects of the wind turbines
hereby permitted (including the application of any tonal and/or
amplitude modulation (AM) character correction), when determined at
any residential properties lawfully existing or with planning permission
at the time of the consent in accordance with the Assessment and
Rating of Wind Turbine Noise 2026 Planning Condition Technical
Guidance Notes (“ARWTN Technical Guidance Notes”), shall not
exceed the values for the relevant integer wind speed set out in or
derived from the table attached to this condition. In the event that a
complaint is made, the following steps shall be carried out: 
2) The turbines shall be designed to permit individually controlled
operation or shut down at specified wind speeds and directions in order
to facilitate compliance with noise criteria. 
3) The Company shall continuously log power production, wind speed and
wind direction at each wind turbine all (in accordance with Guidance
Notes).  This data shall be retained for a period of not less than 24
months. The Company shall provide this information to the Planning
Authority, in the format set out in the Guidance Notes, within 14 days
of receipt in writing of a request to do so. 
4) Prior to the Date of First Commissioning, the Company shall have
submitted to, and received written approval of the Planning Authority
of, a list of proposed independent consultants who will undertake
compliance measurements in accordance with this condition.
Amendments to the list of approved consultants shall be made only
with the prior written approval of the Planning Authority. 
5)  Within 21 days from receipt of a written request of the Local Planning
Authority, following a justified complaint to it alleging noise disturbance

Page 44

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
at a specified residential property, the wind farm operator shall, at its
own expense, employ an appropriately qualified and experienced
acoustician and provide a written protocol (“the Protocol”) to be
approved in writing by the Local Planning Authority. The Protocol shall
confirm the applicable noise limit, describe the procedure to assess the
level and character of noise from the wind farm at the specified property
in accordance with the procedures described in the ARWTN Technical
Guidance Notes and set out a timescale within which the assessment
described in the Protocol will be completed. The written request from
the Local Planning Authority shall set out as far as possible the time or
meteorological conditions to which the complaint relates and whether
the character of the noise is likely to include tonal noise or AM
components if applicable. Measurements to assess compliance with
the noise limits shall be undertaken in accordance with the agreed
Protocol. If the Local Planning Authority or acoustician determine the
character of noise is likely to include tonal or AM components, the
Protocol needs to consider the assessment of these characteristics. 
6) The wind farm operator shall provide to the Local Planning Authority
the acoustician's assessment of the rating level of noise at the specified
property. The assessment shall include, if requested by the Local
Planning Authority, all data collected for the purposes of undertaking
the compliance measurements and analysis, such data to be provided
in a format to be agreed with the Local Planning Authority. Certificates
of calibration of the equipment shall be submitted to the Local Planning
Authority with the acoustician's assessment report. 
7) Where a further assessment of the rating level of noise from the wind
farm at the specified property is required to correct for other noise
sources pursuant to the ARWTN Technical Guidance Notes, the wind
farm operator shall submit a copy of the further assessment within 21
days of submission of the acoustician's initial assessment unless
otherwise agreed by the Local Planning Authority. The wind farm
operator shall facilitate wind turbine shut downs as suitably justified by
the acoustician to allow the contribution from other sources to be
determined, if suitable data is not already available. D. Wind farm
operational and wind data logged by the operator, as defined in the
ARWTN Technical Guidance Notes, shall be supplied to the relevant
Local Planning Authority on its request, within 14 days of receipt in
writing of such a request. 
Table 1. Simplified operational site-specific noise limits (SSNL) at
receptor locations (dB LA90) for day and night periods
Receptor Location (Easting, Northing
in BNG) 
Noise limit at standardised
wind speeds up to 10 m/s, dB
LA90 
Duntanachan (196710, 728227) 
Clachadubh (194756, 727375) 
Barguillean Farm (198045, 728811)
Sithean/Bunanta (198330, 728610)
Bar Glas                (197764, 728716) 
Am Barr                 (197857, 728777)
32 
29 
34  
34
34
34

Page 45

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Reason: To protect amenity and to ensure that noise limits are not exceeded
and to enable prompt investigation of complaints. 
33.  Compensatory Planting  
1) There shall be no Commencement of Development until a woodland
planting scheme to compensate for the removal of existing woodland (“the
Replanting Scheme”) has been submitted to and approved in writing by Argyll
and Bute Council in consultation with Scottish Forestry. 
2) The Replanting Scheme must comply with the requirements set out in the
UK Forestry Standard (Forestry Commission, 2017. ISBN 978-0-85538-999-4)
and the guidelines to which it refers. The Replanting Scheme submitted for
approval must include- 
a. details of the location of the area to be planted; 
b. details of land owners and occupiers of the land to be planted; 
c. the nature, design and specification of the proposed woodland to be
planted; 
d. details of all Necessary Consents for the Replanting Scheme and
timescales within which each shall be obtained; 
e. the phasing and associated timescales for implementing the Replanting
Scheme; 
f. proposals for the maintenance and establishment of the Replanting
Scheme, including; annual checks; replacement planting; fencing; ground
preparation; and drainage; and 
g. proposals for reporting to Argyll and Bute Council on compliance with
timescales for obtaining the Necessary Consents and thereafter
implementation of the Replanting Scheme. 
3) The approved Replanting Scheme shall thereafter be implemented in full
and in accordance with the phasing and timescales set out therein, unless
otherwise agreed in writing by Argyll and Bute Council after consultation with
Scottish Forestry. 
4) There shall be no Commencement of Development until all relevant
Necessary Consents for implementation of the Replanting Scheme in
accordance with the phasing and timescales set out therein have been
obtained. 
Reason To secure compensatory planting to mitigate against effects of
deforestation arising from the Development 
34.  Water Pollution Protection Plan including Private Water Supply
Protection Measures 
Prior to the commencement of development a Water Pollution Prevention Plan
shall be submitted to the planning authority for its approval, providing details
related to safeguard any local private water supplies and the water
environment generally to ensure pollution does not take place associated with
the implementation of this permission. Such details shall be submitted for 
approval in consultation with Environmental Protection, SEPA and Scottish
Water. 
Reason : To ensure the protection of the water environment 
35.  Water Quality and Fish Monitoring Plan

Page 46

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(1) There shall be no Commencement of Development until an integrated
Water Quality and Fish Monitoring Plan (WQFMP) has been submitted
to and approved in writing by the Planning Authority in consultation with
Argyll District Salmon Fishery Board (ADSFB).
(2) The WQFMP must take account of the Marine Directorate’s guidance
and shall provide: 
a) provision that water quality sampling should be carried out prior
to Commencement of Development, during construction and for
at least 12 months after construction is complete; 
b) key hydro chemical parameters (including turbidity and flow
data), the identification of sampling locations (including control
sites), frequency of sampling, sampling methodology, data
analysis and reporting;
d)  Any required site specific mitigation measures including those
detailed in the EIA Report. 
(3) Thereafter, the WQFMP shall be implemented in full within the
timescales set out in the WQFMP. 
Reason: To ensure no deterioration of water quality and to protect fish
populations within and downstream of the development area. 
36.  Forestry Felling Plan 
(1) No felling shall take place until a Forestry Felling Plan (FFP) has been
submitted to and approved in writing by the Planning Authority in consultation
with Scottish Forestry. The FFP shall cover the Development site and shall
provide: 
(a) details of felling and restocking proposals;
(b) details of the management measures to reduce the amount of felling
required to accommodate the Development;
(c) measures to deal with forest waste including brash in line with the UK
Forestry Standard;
(d) timelines for implementing the plan;
(e) details setting out annual monitoring of the felled area and reporting
procedures to be carried out by a qualified expert;
(f) details of forestry management practices; and
(g) details demonstrating compliance with The UK Forestry Standard and
the Scottish Government’s Policy on Control of Woodland Removal (as
amended or replaced from time to time) 
(2) The approved FFP shall be implemented in full upon Commencement of
Felling. 
Reason: to minimise and manage the effects of forestry felling required to
accommodate the Development. 
37.  Eskdalemuir Seismic Array 
(1) Within [three months] of the completion of construction of the turbines, the
Company shall provide written confirmation to the Scottish Ministers, the

Page 47

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Planning Authority, the Ministry of Defence, the Defence Geographic
Centre and NATS of the following: 
(a) the as-constructed position of each turbine in eastings and
northings (each to six figures); and
(b) the hub height and rotor diameter of each turbine (in metres). 
Reason:  To manage any impact on the Eskdalemuir Seismic Array. 
38.  Ongoing Operation and Maintenance 
The wind turbines shall be maintained in the approved colour, free from
external rust, staining or discolouration and in accordance with predicted
operational noise outputs, until such time as the wind farm is decommissioned.   
Reason:  In the interests of the visual and residential amenity of the area. 
39.  Site Inspection Strategy 
(1) Prior to the Date of Final Commissioning, the Company shall submit an
outline Site Inspection Strategy (Outline SIS) for the written approval of
the Planning Authority. The Outline SIS shall set out a strategy for the
provision of site inspections and accompanying Site Inspection
Reports (SIR) to be carried out at 25 years of operation from the Date
of Final Commissioning and every five years thereafter. 
(2) No later than 24 years after the Date of Final Commissioning, the
Company shall submit a final detailed Site Inspection Strategy (Final
SIS), based on the principles of the approved Outline SIS for the written
approval of the Planning Authority. The Final SIS shall set out updated
details for the provision of site inspections and accompanying Site
Inspection Reports (SIR), in accordance with relevant guidance at that
time, to be carried out at 25 years of operation from the Date of Final
Commissioning and every five years thereafter. 
(3) At least one month in advance of submitting each SIR to the Planning
Authority, the scope of the SIR shall be agreed with the Planning
Authority.   
(4) The SIR shall provide: 
(a) Details to demonstrate that the infrastructure components of the
Development are still operating in accordance with the operational
noise condition; and
(b) An engineering report which details the condition of tracks, turbine
foundations and the wind turbines and sets out the requirements and
the programme for the implementation for any remedial measures
which may be required. 
(5) The SIS and each SIR shall be implemented in full following the Date
of Final Commissioning unless otherwise agreed in advance in writing
by the Planning Authority. 
Reason: To ensure the Development is being monitored at regular intervals
after the first 25 years of operation.

Page 48

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
40.  Micro Siting 
(1) All wind turbines, shall be constructed in the approved locations shown on
plan reference ( Fig2.5b ) The locations of wind turbines, buildings, masts,
areas of hardstanding and tracks may be adjusted by micro-siting within
the redline boundary shown on plan reference (Fig2.5b). Any such micro-
siting is subject to the following restrictions unless otherwise approved in
advance in writing by the Planning Authority 
(a) No wind turbine, building, mast or hardstanding shall be moved more than
50m from the position shown on plan reference Fig 2.5b.
(b) no access track shall be moved more than 50m from the position shown
on plan reference Fig 2.5b 
(c) No micro-siting shall take place with the result that infrastructure has a
greater overall adverse impact on peat than the original location;
(d)  No infrastructure other than as required for a water course crossing shall
be microsited to within 50 metres of a water course; 
(2) All micro-siting permissible under this condition shall be submitted to, and
approved in writing by SEPA, DIO  and the Ecological Clerk of Works
(“ECoW”) in advance of any works or development associated with the
micro-siting request being implemented; (DIO will only require to be
consulted in relation to any proposed wind turbine relocation) 
(3) No later than six months after the Date of First Commissioning an updated
site layout plan showing the final position of all wind turbines, buildings,
masts, areas of hardstanding, tracks and associated infrastructure
forming part of the Development shall be submitted to the Planning
Authority. The plan shall also specify areas where micro siting has taken
place and, for each instance, be accompanied by copies of SEPA, DIO
and ECoW approval, as applicable. 
Reason: to control environmental impacts while taking account of local ground
conditions, DIO aviation safety and SEPA peat impact restrictions on such
matters. 
41.  Trunk Road Authority Requirements 
Prior to the commencement of development details of the following matters
shall be submitted to the planning Authority for its approval in consultation with
Transport Scotland; 
a) Prior to the commencement of the development, the proposed
upgraded access on the A85 trunk road, as generally illustrated by RSK
nadara Figure 10.4 Access Junction Design Rev 03 dated 17/06/2025,
shall be constructed to a layout and type (and method) of construction
to be approved by the Planning Authority, after consultation with
Transport Scotland 
b) Prior to the commencement of the development, visibility splays, as
generally illustrated by RSK Figure 2.10a: Indicative Site Access - A85
to Fearnoch Forest Track Rev 03 dated 14/08/2025, shall be provided
and maintained to the satisfaction of the Planning Authority, after
consultation with Transport Scotland.

Page 49

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
c) Prior to commencement of deliveries to site, the proposed route for any
abnormal loads on the trunk road network must be submitted to and
approved by the Planning Authority, in consultation with Transport
Scotland. 
d) Prior to the movement of any abnormal load, any accommodation
measures required, including the removal of street furniture, junction
widening and traffic management must be approved and implemented
to the satisfaction of the Planning Authority, in consultation with
Transport Scotland. 
e) Prior to the movement of any components and/or construction
materials, any additional signing or temporary traffic control measures
deemed necessary due to the size or length of any loads being
transported must be undertaken by a recognised QA traffic
management consultant, to be approved by Transport Scotland. 
f) Prior to commencement of the grid connection element of the
development, a Construction Traffic Management Plan (CTMP) shall
be submitted to, and approved by, the Planning Authority, after
consultation with Transport Scotland. In particular, the CTMP shall
identify measures to control the use of any direct access onto the trunk
road. Thereafter, all construction traffic associated with the
development shall conform to the requirements of the agreed Plan. 
Reason: To protect the Trunk Roads Network, ensure compliance with
necessary standards and in the interests of traffic safety   
Advisory notes 
(1)   Notice of the start of development: The person carrying out the development
must give advance notice in writing to the planning authority of the date when
it is intended to start. Failure to do so is a breach of planning control. It could
result in the planning authority taking enforcement action (See sections 27A
and 123(1) of the Town and Country Planning (Scotland) Act 1997 (as
amended)). 
(2)  Notice of the completion of the development: As soon as possible after it is 
finished, the person who completed the development must write to the
planning authority to confirm the position (See section 27B of the Town and
Country Planning (Scotland) Act 1997 (as amended)). 
(3)  Display of notice: A notice must be displayed on or near the site while work is
being carried out. The planning authority can provide more information about
the form of that notice and where to display it (See section 27C of the Town
and Country Planning (Scotland) Act 1997 Act (as amended) and Schedule 7
to the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013).  
(4)  Right to challenge this decision: This decision is final, subject to the right of
any person aggrieved by this decision to question its validity by making an
application to the Court of Session. An application to the Court of Session must
be made within 6 weeks of the date of the decision. Your local Citizens’ Advice

Page 50

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Bureau or your solicitor will be able to advise you about the applicable
procedures. 
(5)  Notification of this decision by the planning authority: The planning authority is
required (a) to inform the public and bodies consulted in respect of the EIA
report of this decision by publishing a notice on the application website or
newspaper circulating the in locality of the proposed development or by other
reasonable means and (b) to make a copy of the decision available for public
inspection in an office of the planning authority where its planning register may
be inspected and on the application website.  
(6)  Requirements relating to works within the trunk road boundary: 
i. The applicant should be informed that the granting of planning consent does
not carry with it the right to carry out works within the trunk round boundary
and that permission must be granted by Transport Scotland Roads Directorate. 
ii. Trunk road modification works shall, in all respects, comply with the Design
Manual for Roads and Bridges and the Specification for Highway Works
published by HMSO. The developer shall issue a certificate to that effect,
signed by the design organisation. 
iii. Trunk road modifications shall, in all respects, be designed and constructed
to arrangements that comply with the Disability Discrimination Act: Good
Practice Guide for Roads published by Transport Scotland. The developer
shall provide written confirmation of this, signed by the design organisation 
iv. The road works which are required due to the above Conditions will require
a Road Safety Audit as specified by the Design Manual for Roads and Bridges. 
v. Any trunk road works will necessitate a Minute of Agreement with the Trunk
Roads Authority prior to commencement. 
vi. To obtain permission to work within the trunk road boundary the developer
should contact the Area Manager through the general contact number 0141
272 7100. 
vii. The Operating Company has responsibility for co-ordination and
supervision of works and after permission has been granted it is the
developer's contractor's responsibility to liaise with the Operating Company
during the construction period to ensure all necessary permissions are
obtained.  
(7)  Environmental Health Notes to Applicant 
1.Regulatory requirements for private water supplies should be discussed with
the Council’s Environmental Health Service in the first instance. 
2.If the development is likely to use 10m3 water per day then the applicant will
need to apply for a registration or licence for water abstraction from SEPA
https://www.sepa.org.uk/regulations/authorisations-and-permits/application-
forms/#Water   
3.If the proposed development is a commercial undertaking including but not
limited to; use as a holiday or long term private let, workplace, food business,

Page 51

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
campsite etc. then the applicant must apply to the Environmental Health
service 8 weeks before the intended use date for the private water supply to
be registered and certified as fit for use. Email: pws@argyll-bute.gov.uk   
4.It is recommended that should planning permission be granted, that the
applicant contact this Service to discuss further the measures needed to
comply with the requirements of Water Intended for Human Consumption
(Private Supplies) (Scotland) Regulations 2017 or the Private Water Supplies
(Scotland) Regulations 2006, as is applicable   
ENVIRONMENTAL IMPACT ASSESSMENT 
Regulation 3 of the Town and Country Planning (Environmental Impact Assessment)
(Scotland) Regulations 2017, prohibits the granting of permission for EIA development
unless an environmental impact assessment has been carried out and that information has
been taken into account when undertaking an assessment of the proposal. 
The applicant has submitted an Environmental Impact Assessment Report (EIA Report
dated 25.07.25 and Further Environmental Information dated 27.07.26. The environmental
information contained within this and the comments made on the application by consultees
and representations made by members of the public have been taken into account in coming
to this decision. 
The Council is satisfied that the requirements of the EIA Regulations have been met. 
Reasoned Conclusion: 
The Council's assessment of the information presented within the EIA Report and other
environmental information in relation to the development is contained within the Report of
Handling. Elements of the proposal with the potential to result in likely significant effects are: 
noise and shadow flicker, landscape and visual impacts, aviation and defence interests
including seismological recording, telecommunications and broadcasting installations, road
traffic and adjacent trunk roads, historic environment, hydrology, the water environment and
flood risk, biodiversity, trees, woods, and forests, decommissioning, site restoration and
quality of site restoration plans, cumulative impacts, renewable energy generation targets
and greenhouse gas emissions reduction targets.   
These issues are addressed in the Report on Handling and it is considered that subject to
the mitigation measures which are set out in the EIAR and reflected in the planning
conditions attached to this permission, no likely significant effects are anticipated as a result
of the proposal. 
The Council is satisfied that this reasoned conclusion is still up to date at the time of this
decision. 
All documents can be viewed online at: https://www.argyll-bute.gov.uk/planning-and-
environment/find-and-comment-planning-applications and searching using the case
reference number. 
COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER: 25/01240/PP 
PLANNING LAND USE AND POLICY ASSESSMENT

Page 52

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
1.0 SPATIAL AND SETTLEMENT STRATEGY 
1.1 Policy 02 – Outwith Settlement Areas establishes acceptable scales of development in
three different zones. The main wind farm site is located within Remote Countryside Area.
Within the Remote Countryside Areas, only specific categories of development are
supported. This includes renewable energy related development. In principle, Policy 02
supports renewable energy and ancillary developments in these areas, providing they are
consistent with all other relevant LDP2 Policies. With respect to the requirement for
developments to accord with all other relevant policies of LDP2, particular attention is drawn
to the need for proposals to accord with Policies 70 to 76 with respect to landscape and the
natural environment.  Proposals will also be required to demonstrate that there will be no
unacceptable adverse effects (either individually or cumulatively) on natural heritage
resources, built and/or cultural heritage resources, and landscape and visual amenity.   
1.2 Policy 04 – Sustainable Development requires that in preparing new development
proposals, developers should seek to demonstrate the following sustainable development
principles (where relevant): 
a) Maximise the opportunity for local community benefit; 
b) Make efficient use of vacant and/or derelict land including appropriate buildings; 
c) Support existing communities and maximise the use of existing infrastructure and
services; 
d) Maximise the opportunities for sustainable forms of design including minimising waste,
reducing our carbon footprint, increasing energy efficiency, solar panels, ground, water and
air source heat pumps and other forms of renewable energy generation; 
e) Avoid the use of locally important good quality agricultural land; 
f) Utilise public transport corridors and active travel networks; 
g) Avoid the loss of important recreational and amenity open space; 
h) Conserve and enhance the natural and built environment and avoid significant adverse
impacts on biodiversity, natural and heritage assets;
i) Respect the landscape character of an area and the setting and character of settlements;
j) Avoid places with significant risk of flooding, tidal inundation, coastal erosion or ground
instability; and 
k) Avoid having significant adverse impacts on land, air and water environment.  
The application is supported by an Environmental Impact Assessment Report (EIAR) which
sets out in detail the measures proposed to ensure the proposal is ‘Sustainable
Development.’  
1.3 Policy 11 – Energy of NPF4 and Policy 30 – Sustainable Growth of Renewables of LDP
2 provide the primary policy framework for assessing wind farms. In this case, it is considered
that the Landscape & Visual Impact of the proposal is acceptable, and that all other matters
can be suitably mitigated by appropriate conditions. Therefore, it is concluded the proposal
is consistent with Development Plan Policy relating to the  spatial and settlement strategy. 
1.4 For the reasons detailed below in this report, it is considered that this proposal satisfies
Development Plan Policy and associated guidance in respect of renewable energy
development. 
1.5 Having due regard to the above it is concluded that this proposal can be
considered ‘sustainable’ and therefore consistent with the provisions of LDP 2 Policy
02 – Outwith Settlement Areas and LDP Policy 04 – Sustainable Development. 
2.0 ENERGY & SUPPORTING THE SUSTAINABLE GROWTH OF RENEWABLES

Page 53

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
2.1 Argyll & Bute Council is keen to ensure that Argyll & Bute continues to make a positive
contribution to meeting the Scottish Government’s targets for renewable energy generation.
These targets are important given the compelling need to reduce our carbon footprint and
reduce our reliance on fossil fuels, reinforced by the Climate Change (Emissions Reduction
Targets) (Scotland) Act 2019. The Council will support renewable energy developments
where these are consistent with the principles of sustainable development, and it can be
adequately demonstrated that there would be no unacceptable significant adverse effects.   
2.2 This proposal has been assessed primarily against the criterion in the two lead Statutory
Development Plan policies relating to renewable energy. These are: Policy 11 – Energy of
National Planning Framework 4 and Policy 30 – the Sustainable Growth of Renewables of
the Argyll & Bute Local Development Plan 2. Other policies are referred to where relevant. 
3.0 LOCATION, NATURE, AND DESIGN OF PROPOSAL 
3.1 The Site currently contains the existing Beinn Ghlas Wind Farm comprising 14 wind
turbines (approximately 54.1 m to blade tip), each with a capacity of 600 kilowatts (kW)
providing an overall installed capacity of 8.4 MW. The Wind Farm has been operational since
May 1999. In June 2022, an application to extend the life of the Wind Farm (ref:
21/00870/PP) was approved to allow the Wind Farm to operate to August 2033. 
3,2 The Site has therefore already been used for a wind farm since 1999 for a range of
reasons which included high average wind speed and access to grid infrastructure. The Site
is not located within any area of national environmental importance, and through the
undertaking of various technical assessments (including but not limited to feasibility
assessments, ecology, ornithology, peat and landscape and visual studies since 2020). The
application site area is circa  436ha. 
3,3 The nearest settlements to the Site are the town of Oban and village of Taynuilt, which
are approximately 12 kilometres (km) and 4 km respectively from the Site. Both are
predominantly separated from the Site by a range of hills to the south of Loch Etive. 
3,4 The site landscape context comprises low, rugged hills, scattered with small outcrops of
rocks and scoured with steep sided streams. There is open moorland, predominantly upland
heath and mires including bog pools on the higher ground and a mixture of rough grassland
and woodland on the lower slopes. Within the surrounding area there is a combination of
native deciduous woodland and commercial coniferous forestry to the north and southeast
of the Site. There is evidence in the wider area of cultivated land and improved grazing but
generally the land has been used non-intensive. The existing (and to be widened) access
track is bounded by Ancient Woodland along part of its length 
3.5 The applicants submit that the design of the Proposed Development has been driven by
the objective of positioning the turbines and associated infrastructure so that they capture
the maximum wind energy within a suitable area, whilst taking into consideration and
minimising potential impacts on environmental and technical constraints where possible. 
3.6 Proposed Development –The Proposed Development infrastructure would comprise the
following components:  
• Up to seven wind turbines of approximately 4.8 MW each, with a maximum blade tip height
of up to 149.9 m; 
• Hardstanding areas at the base of each turbine, with a permanent area of approximately
1,400 m2; 
• Upgrading of four existing road junctions to support construction and abnormal road traffic;

Page 54

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• Upgrading of forestry tracks from the A85 through Fearnoch Forest, Glen Lonan Road
(C32) and existing wind farm access track to accommodate the delivery of abnormal loads
to the site and use of existing track for access to the first construction compound. 
• An internal network of new onsite access tracks and upgrade of existing Wind Farm access
track. The total length of the Site Access and Internal Access Tracks would be
approximately 12.83 km of which 2.71 km is new access track (1.6 km floating) with
associated new watercourse crossings and 8.52 km is existing access track and
watercourse crossings which would need to be upgraded. In total there would be 4 new
watercourse crossings and 22 existing crossings; 
• Upgrading of the existing onsite sub-station/control building; 
• Transformers and underground cables to connect the turbines to the onsite substation; 
• Permanent anemometry mast for wind monitoring, including associated foundation   and
hardstanding; 
• Telecommunications equipment; 
• Concrete batching plant; 
• Preliminary temporary construction compound; and 
• Temporary construction compound. 
3.7 Connection to Electricity Grid - The grid connection will be the subject of a separate
application. However, the FEI information gives general details of the likely route and design
of the required underground cable. 
4.0 LANDSCAPE AND VISUAL IMPACTS 
4.1 Policy 11 – Energy of NPF 4 requires that project design and mitigation demonstrate
how significant landscape and visual impacts have been addressed, recognising that such
impacts are to be expected for some forms of renewable energy.  Where impacts are
localised and/or appropriate design mitigation has been applied, they will generally be
considered acceptable. Policy 4 a) – Natural Places of NPF4 states that proposals which by
virtue of type, location or scale will have an unacceptable impact on the natural environment,
will not be supported. Policy 30 – The Sustainable Growth of Renewables of LDP 2 requires
all applications for wind turbine developments to be assessed against landscape and visual
impacts. 
4.2 The site covers 436ha and is situated around Carn Gaibhre summit on the Lorn plateau
at an elevation between 335m to 461m AOD. It comprises an undulating upland of rounded
knolls, rock outcrops, steep sided streams, lochs and lochans. The site is covered by open
moorland, predominantly upland heath and mires on the higher ground and a mixture of
rough grassland and woodland on the lower slopes. Within the surrounding area of the site
there is a combination of native deciduous woodland and commercial coniferous forestry to
the north and southeast. 
4.3 The site currently contains the existing Beinn Ghlas Wind Farm which comprises 14
operational turbines of approximately 54.1m to tip, a substation/control building and access
from Barguillean Farm, approximately 2.2km north. These existing turbines would be
decommissioned and removed either prior to or in parallel with the construction of the
proposal and the site would be reinstated except where the existing infrastructure would be
used for the repowering. 
4.4 Outward views from within the site are generally open, unrestricted and panoramic,
looking across the open moorland, coastal transitions and highpoints within National Scenic
Areas (NSA), Areas of Panoramic Quality (APQ) and Wild Land Areas (WLA) to the north,
east and west. The highest areas within the 35km LVIA study area are found beyond 9km
and include Ben Cruachan (1126m AOD) to the northeast and Beinn Mheadhonach (714m

Page 55

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
AOD) to the north. Together with the mosaic of moorland, conifer forest plantation and native
woodland the landscape of the site and surroundings is large in scale. 
4.5 The submitted Landscape Assessment (LVIA) has focussed on a study area 20km from
the proposal and at the time of the LVIA there were three operational wind farms within this
area which are considered as part of the baseline. Two consented/under construction wind
farms and four proposed wind farms were in planning, and these have been considered
within the cumulative impact assessment.  Schemes that were at scoping stage at the time
of the LVIA, Musdale and Barachander Wind Farms, are considered within Appendix 5.6 to
the LVIA. 
4.6 Design iterations have taken place over several years with Scoping submitted in 2022
and since then the design has developed in response to environmental data, new policies,
economic conditions and consultee response and advice. Since Scoping the proposal has
evolved from 18 turbines with a proposed blade tip height of 180m, to the final layout of 7
turbines of up to149.9m to blade tip. The design has undergone six principal iterations of the
initial layout (Layout A) which have been developed at different stages in the project design
process. Design iterations (A to F) are shown on Volume 3a, Figure 2.4 and are discussed
in detail within the Design and Access Statement. 
• Layout A – 20 turbine initial layout, each with a maximum height to blade tip of 180m,
representing a layout which considered basic onsite constraints only.
• Layout B – 18 turbine Scoping layout, each with a maximum height to blade tip of
180m, representing a layout that avoided the northern edge of the site to minimise
landscape impact and to avoid ornithology constraints; 
• Layout C – 14 turbine layout, each with a maximum height of 149.5m to blade tip,
informed by detailed landscape appraisal and early results of onsite surveys and
consultant inputs;
• Layout D – 12 turbine refined layout with a maximum height of 149.5m for public
consultation informed by the presence of ornithological constraints with a track layout
designed to minimise impact on ecological constraints; and
• Layout E – 11 turbine refined layout with a maximum height of 149.5m, including
reflecting further baseline environmental surveys, alongside further design of
ancillary infrastructure.
• Layout F – 7 turbine refined layout with a maximum height of 149.9m, accounting for
protected ornithology species. 
4.7 The submitted Design and Access Statement states that a key consideration has been
to reduce landscape and visual effects; this being done by a reduction in the numbers of
turbines, consolidation of turbines within the heart of the site and constraining the turbine
heights to below 150m, resulting in the layout being more compact and less visible within
the landscape and thus reducing landscape and visual effects for receptors whilst reusing
existing infrastructure as much as practicable. 
4.8 National Landscape Designations - Lynn of Lorn National Scenic Area (NSA) is situated
13.9 km to the northwest and Ben Nevis and Glen Coe NSA 15.3 km to the northeast of the
proposal. An assessment of effects on the Special Landscape Qualities (SLQs) of these
NSAs is included in Appendix 5.7. Members are requested to note that NatureScot has
raised no objections in respect of potential impacts upon these sensitive landscape areas. 
4.9 Local Landscape Designations – The following LLA’s are located within 20km of the
proposals;
• North Argyll LLA (3.8km to the east); 
• North West Argyll (Coast) LLA (7.9km to the west);

Page 56

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• Knapdale/ Melfort LLA and (12km to the southwest); and 
• West Loch Fyne LLA (18.2km to the southeast). 
4.10 Potential effects on the North Argyll LLA are illustrated by VPs 8, 9, 10, 11, 14 and 15.
The Councils Landscape advisor has stated that: 
“The EIAR quotes the ABLWECS which states that “the special qualities of the [this LLA] are
likely to comprise dramatic mountain landform and the juxtaposition of these mountains with
narrow lochs and the sea and with settled loch fringes which produce a richly scenic
landscape composition.” The EIAR states that theoretical visibility within the LLA is generally
limited to the southern edge of the designation within 10km of the proposal, with isolated
locations where views are channelled further north. The EIAR concludes that there would
be indirect effects on the LLA resulting from changes to views to the south, however, they
would not be significant as the area would continue to be defined by its scenic, panoramic
quality and I agree with this assessment. For the TFB scenario the EIAR predicts isolated
significant effects within the North Argyll LLA within approx. 10km of the proposal although
these are not predicted to result in a significant effect on the integrity of the designation.” 
4.11 Wild Land Areas - Seven Wild Land Areas (WLAs) are located within 35km of the
proposal. The nearest of those is Loch Etive Mountains WLA located approximately 7.5km
to the northeast and illustrated by VPs 9, 14 and 17. This WLA overlaps part of the North
Argyll LLA. Indirect effects on WLAs have been scoped out of the assessment. 
4.12 Gardens and Designed Landscapes - There are 11 Gardens and Designed Landscapes
(GDLs) situated within the 35km study area. Of those, only one, Ardchattan Priory GDL
located 8.2 km north of the proposal, is covered by the ZTV and considered in the
assessment. The worst-case scenario of effects on views experienced from this GDL is
represented by VP 7, where visitors may be approaching or leaving the GDL, but outwith the
extent of the designation. The overall effect on the designation is not predicted to be
significant due to the intervening walls, buildings and trees and the enclosed nature of the
gardens focussed on the relationship of the grounds with Ardchattan House. Historic
Environment Scotland have raised no objections in respect of these matters. 
4.13 Visual Effects - The nearest settlements are the village of Taynuilt and the town of
Oban, which are approximately 4km northeast and 12km west respectively. Settlement close
to the site is sparse with theoretical visibility indicated from seven residential properties in
Glen Lonan within 3km. There are a number of settlements, routes and other locations from
where people are likely to gain views of the proposal. These include: Settlements asset out
in the Landscape consultants report at Chapter 8 (Pages 15&16) 
4.14 Although some of these viewpoints have been identified as having significant impact,
this is localised and therefore is not considered unacceptable in respect of policy evaluation
of the proposals. Localised impacts, even if significant, are not normally considered to be a
reason to refuse permission for such development as some localised and significant impacts
cannot be avoided completely due to the scale and nature of windfarm proposals. 
4.15 Based on the advice of the Council’s Consultant Landscape Architect and NatureScot,
it is considered that the proposed development does not warrant a refusal on landscape
impact or visual impact grounds. 
4.19 Having due regard to the above it is concluded that the proposal complies with
the provisions of Policies 11 – Energy and 4 – Natural Places of NPF4, and Policy 30
– The Sustainable Growth of Renewables of LDP2 in this respect.

Page 57

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
5.0 BIODIVERSITY ECOLOGY and ORNITHOLOGY 
5.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate how
impacts on biodiversity, including birds have been addressed.  Policy 3 – Biodiversity of
NPF4 requires development proposals to protect biodiversity, reverse biodiversity loss,
deliver positive effects from development and strengthen nature networks. Policy 5 – Soils
of NPF4 supports the generation of energy from renewable sources that optimises the
contribution of the area to GHG emissions reduction targets on peatland, carbon-rich soils,
and priority peatland. A detailed site-specific assessment will be required for development
on peatland which will include the likely net effects of the development on climate emissions
and loss of carbon. Policy 30 – The Sustainable Growth of Renewables of the ABLDP2
requires all applications for wind turbine developments to be assessed against impacts
arising from effects on the natural heritage, including birds and to be assessed against
impacts on carbon rich soils, using the carbon calculator (including cumulative)  Policy 73 –
Development Impact on Habitats, Species and Biodiversity requires Development proposals
will be encouraged to incorporate, safeguard and enhance existing site biodiversity wherever
possible.  
5.2 The Ecology and Ornithological chapters of the Environmental Impact Assessment
Report (EIAR) predict no likely significant effects on potentially important ecological or
ornithological interests after embedded mitigation. Therefore, the elements within the OBE-
HMP (Outline Biodiversity Enhancement and Habitat Management Plan) are largely
considered enhancement measures as defined in the EIA Regulations and best practice EIA
guidance. Where elements are defined as compensation/offsetting, these are clearly
identified in the relevant sections. 
5.3 As part of the EIAR, Ecology and Ornithology chapters have been written covering both
disciplines. As part of that work, a series of ecological and ornithological mitigation and
enhancement measures have been recommended. 
5.4 A number of biodiversity enhancement measures are proposed as part of the Proposed
Development’s OBE-HMP. The OBE-HMP includes provisions for the protection,
maintenance, restoration and creation of habitats locally through the implementation of
seven discrete ‘objectives’ for which work packages and methods have been identified. This
is discussed in greater detail in Technical Appendix 6.10: Outline Biodiversity Enhancement
and Habitat Management Plan. 
5.5 Delivery of this OBE-HMP is secured through a planning condition. The overall aim of
this OBE-HMP is to conserve, enhance and restore important habitats and associated
species within the Beinn Ghlas OBE-HMP Study Area (Figure 1). The Existing HMP Area
will continue to be an HMP area for the Proposed Development (Figure 1). Given the
generality of this overall aim, it has been subdivided into the seven discrete ‘objectives’ for
which particular work packages and methods have been identified. 
• Objective 1: Reduce grazing and browsing pressure; 
• Objective 2: Peatland restoration; 
• Objective 3: Creating and strengthening nature networks; 
• Objective 4: Pond/lochan creation; 
• Objective 5: Targeted priority species action; 
• Objective 6: White-tailed eagle fatality monitoring; and 
• Objective 7: Operational Carcass Recovery Scheme 
5.6 The ornithology chapter (Chapter 7) presents the findings of the assessment of likely
significant effects of the proposed Beinn Ghlas Wind Farm Repowering development (the
‘Proposed Development’) on ornithological features. It details the methods used to establish

Page 58

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
the bird populations within the Site and its surroundings, the results of the baseline surveys,
and the process used to determine the sensitivity of the bird populations present. The ways
in which birds might be affected (directly or indirectly) by the construction and operation of
the Proposed Development are assessed, prior to and after the application of any required
mitigation measures. 
5.7. Baseline ornithological conditions to inform the design and assessment of the Proposed
Development have been established through desk studies, ornithological field surveys and
consultation with stakeholders and specialist recording groups. Based on a combination of
field surveys and a desk study, the only species of Nature Conservation Importance that
required detailed consideration was golden eagle and white-tailed eagle. 
5.8. All other species recorded were scoped out of the assessment due to a lack of potential
for significant effects. The identified impact pathways acting on golden eagle and white-tailed
eagle were disturbance and habitat loss during construction (and decommissioning) and
displacement and collision risk during operation. 
5.9. When mitigation and best practice measures were considered (primarily ensuring no
disturbance to breeding golden eagle and white-tailed eagle during construction via the Bird
Protection Plan), no significant effects were identified. Mitigation and enhancement
measures will be delivered through the implementation of a Biodiversity Enhancement and
Habitat Management Plan (BEHMP). Additional enhancement measures were also
committed to and will form part of the BEHMP. 
5.10.  The applicant has confirmed by submission that all potential OBE-HMP sites will be
surveyed prior to any work commencing to ensure that existing potentially important
biodiversity and protected species interests are protected and considered when developing
and implementing the finalised and agreed OBE-HMP, whilst also establishing a ‘before
management baseline’. Both NatureScot and the Councils biodiversity Officer are content
with this approach subject to the imposition of appropriate conditions. 
5.11.  The applicant also confirms that the number of watercourse crossing have been limited
where possible and where required will be designed to improve on existing crossings to
improve habitats and fish migration. The replacement of existing culverted crossings with
bottomless arches or box crossing could be beneficial to improve migratory fish passage
and otter passage particularly along the section of existing access tracks where fish are
more likely to be present. 
5.12.  Argyll District Salmon Fishery Board (ADSFB) note that the recent additional to the
documents folder of Further Environmental Information has some relevant information on
aquatic ecology. This recognises the importance of the River Nant, River Nell / Feochan and
Allt Nathais which host spawning and nursery habitat for Atlantic salmon and brown trout.
Argyll DSFB request that appropriate baseline, real time and post works monitoring is put in
place to ensure any issues arising from the proposed development are identified and
rectified in a timely manner as to prevent any deterioration of fish habitats and demonstrate
that the development does not impact on the salmon populations or the fisheries in the Argyll
DSFB area. Argyll DSFB would welcome an opportunity to constructively engage with any
such process. An appropriate condition to secure this dialog and necessary
actions/monitoring is proposed. 
5.13.  Both NatureScot and the Councils Biodiversity Officer have raised no objection to the
proposals subject to the imposition of appropriate conditions. 
5.14 Having due regard to the above, and subject to the recommended  conditions it
is considered that the proposal is consistent with the provisions of Policies 11 –

Page 59

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Energy, 3 Biodiversity, 5 – Soils of NPF4 and Policy 30 – The Sustainable Growth of
Renewables, Policy 73 – Development Impact on Habitats, Species and Biodiversity
and Policy 79 – Protection of Soil and Peat Resources of LDP2 
6.0 TREES, WOODS, AND FORESTS   
6.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will demonstrate
how impacts on trees, woods and forests have been addressed. Policy 6 – Forestry,
woodland, and Trees of NPF4 intent is to protect and expand forests, woodland, and trees.
Policy 77 – Forestry, Woodland, and Trees of ABLDP2 states that there is a strong
presumption in favour of protecting our woodland resources. Policy 78 – Woodland Removal
of ABLDP2 states that proposals that would involve the removal of woodland resources will
be assessed against the criteria for determining the acceptability of woodland removal, in
accordance with the Scottish Government’s Control of Woodland Removal Policy. Where
this assessment concludes that compensatory planting would be appropriate, developers
will need to provide for this in accordance with the advice in the Scottish Government’s
Control of Woodland Removal Policy.   
6.2 EIAR Chapter 13: Other Issues Section 13.7 addresses forestry impacts. Due to the
proposed widening of the Fearnoch Forest access tracks, the proposal would impact some
commercial plantation managed by Forestry and Land Scotland. Upgrading the existing
access from the A85 would also necessitate the removal of small areas of deciduous
woodland adjacent to the A85 within Barguillean Estate. The total felling area would be 1.61
ha, of which 1.02 ha would be permanent and 0.59 ha would be temporary. The Outline
Biodiversity Enhancement and Habitat Management Plan in Appendix 6.10, states that the
compensatory planting requirement would be met through 14.4 linear km/ circa 7.2ha of
broadleaved riparian planting and 1.5ha of ‘nature networking’ planting between blocks of
existing woodland onsite and in additional locations between the Loch Awe and Loch Etive
catchments. 
6.3 Scottish Forestry have advised that they have no objection subject to conditions to
secure compensatory planting and a native planting scheme. These have been proposed. 
6.4 The Councils Biodiversity Officer is content that appropriate steps have been taken to
avoid or minimise impacts on ancient woodland in accordance with policy advice and raises
no objection to the application proposals. 
6.5 Having due regard to the above it is concluded that subject to the conditions
recommended by Scottish Forestry the proposal is consistent with the provisions of
Policies 11 – Energy and 6 – Forestry, woodland and Trees of NPF4, and Policies 30
– The Sustainable Growth of Renewables; 77 – Forestry, Woodland and Trees and 78
– Woodland Removal of the LDP2.   
7.0 HISTORIC ENVIRONMENT    
7.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrates
how impacts on the historic environment have been addressed. Policy 7 – Historic Assets
and Places of NPF4 intent is to protect and enhance historic environment assets and places,
and to enable positive change as a catalyst for the regeneration of places. Policy 30 – The
Sustainable Growth of Renewables of LDP2 requires all applications for wind turbine
developments to be assessed against impacts on the historic environment, including
scheduled monuments, listed buildings and their settings. Policy 15 – Protection,
Conservation and Enhancement of Our Historic Environment Policy 19 – Scheduled
Monuments Policy 20 – Gardens and Designed Landscapes Policy 21 – Sites of

Page 60

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Archaeological Importance support the key policies and provide guidance on assessing
development proposals against heritage impacts.  
7.2 The Archaeology and Cultural Heritage chapter (Chapter 9) of the EIAR considers the
likely effects on cultural heritage interests arising from the Proposed Development. The
assessment of effects upon cultural heritage has considered potential direct/indirect physical
impacts related to construction of the Proposed Development on the fabric of heritage assets
(including the decommissioning of the currently operational Wind Farm) and impacts on the
setting of a heritage asset that could affect its cultural significance. 
7.3. There are seven known heritage assets located within the Application Boundary as
shown in Volume 3a, Figure 9.1a and Figure 9.1b. Possible accidental direct physical impact
upon HA01 Deirdre Shieling Memorial (a modern memorial and sculpture within the Site) will
be mitigated by its fencing off for protection throughout construction. The monument’s
location will also be included on construction plans and its presence highlighted in project
inductions. 
7.4. No direct or indirect physical impacts as a result of the Proposed Development are
anticipated upon known heritage assets within the Application Boundary. 
7.5. A ‘Stage 1’ Setting Assessment (Volume 4, Technical Appendix 9.1) found the potential
for effects through changes within their setting on the cultural significance of one Inventory
Garden and Designed Landscape, one Category B Listed Building, and six Scheduled
Monuments (Volume 3a, Figure 9.2). These eight heritage assets are assessed in detail in
this chapter, supported with photomontage visualisations (Volume 3a, Figures 9.3 – 9.9). 
7.6. Of these assets agreed for detailed assessment in this chapter, no impact has been
identified within the EIAR upon: 
• GDL00019 / SM13644 / LB4715 Ardchattan Priory / Ardchattan House Garden
and Designed Landscape, Scheduled Monument, Category B Listed Building
(Volume 3a, CHVP01 Figure 9.3) 
• SM4120 Caisteal Suidhe Cheannaidh, dun 470m NW of Achnacraobh (Volume
3a, CHVP05 Figure 9.7) • SM3891 ‘Clachadow, cairn 960m NW of’ (Volume 3a,
CHVP06 Figure 9.8) 
• SM3888 Glenamachrie, cairns 65m & 300m WNW of (Volume 3a, CHVP07 Figure
9.9) 4.6.11 
7.7. Residual adverse operational effects which are minor and not significant are predicted
upon two Scheduled Monuments: 
• SM3910 ‘An Dun, dun 500m ESE of Glenamadrie’ (Volume 3a, CHVP02 Figure
10.4 & CHVP03 Figure 9.5) 
• SM3930 ‘Barguillean Farm, dun 250m SSW of’ (Volume 3a, CHVP04 Figure 9.6) 
7.8. The applicants submit that; 
• In respect of the setting of heritage assets, no additional mitigation beyond that
embedded in the design is proposed.
• No cumulative effects have been identified. 
• No significant residual effects upon cultural heritage have been identified
through EIA as presented in this chapter.

Page 61

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
7.9. Historic Environment Scotland (HES) have raised no objection to the proposals with a
detailed evaluation of the proposals as set out in their consultation response at Section C of
this report.  
7.10 West of Scotland Archaeology Service (WoSAS) – have advised that they have no
objection subject to a condition to secure a programme of archaeological works in
accordance with a written scheme of investigation to be submitted by the applicant for the
written approval of the Planning Authority in consultation with WoSAS. 
7.11 Having due regard to the above subject to the condition recommended by the
West of Scotland Archaeology Service it is considered that the proposal is consistent
with the provisions of Policy 11 – Energy and Policy 7 – Historic Assets and Places of
NPF4, and Policies 30 – The Sustainable Growth of Renewables; 15 – Protection,
Conservation and Enhancement of Our Historic Environment; 19 – Scheduled
Monuments; 20 – Gardens and Designed Landscapes; and 21 – Sites of
Archaeological Importance of the LDP2 
8.0 HYDROLOGY, THE WATER ENVIRONMENT, FLOOD RISK AND PEAT    
8.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate how
effects on hydrology, the water environment. Peat and flood risk have been addressed.
Policy 30 – Supporting the Sustainable Growth of Renewables of ABLDP2 requires all
applications for wind turbine developments to be assessed against impacts arising from
effects on hydrology, the water environment. Peat and flood risk (including cumulative).
Policy 55 - Flooding of ABLDP 2 provides guidance on the type of development that will be
generally permissible within specific flood risk areas. Policy 57 – Risk Appraisals requires
flood risk assessments, and drainage impact assessments, to accompany applications
where required and NPF 4 Policy 5 “Soils” and  LDP 2 Policy 79 -Protection of Soil and Peat
Resources apply in respect of Peat matters.    
8.2 The infrastructure of the Proposed Development will require approximately 12.83 km site
access and internal tracks of which 2.71 km is new access track (1.6 km floating) with
associated new watercourse crossings and 8.52 km is existing access track and watercourse
crossings which would need to be upgraded. The track layout has been designed to avoid
watercourses and use existing access tracks where possible, with a preference for crossing
of smaller scale watercourses or replacing existing crossings that currently impede fish
passage or restrict peak flows. 
8.3. A total of 26 watercourse crossings are required for the Proposed Development. Of
these, 22 are existing crossings to be reused, extended/upgraded or replaced and four are
new watercourse crossings. Of the 22 existing crossings to be re-used, upgrade/extended
or replaced, one is a single span crossing and 21 are culverted crossings, 15 are
watercourse crossings shown on the 1:50,000 scale OS Mapping and six are of
watercourses shown on the 1:25,000 scale OS mapping and one is shown on 1:10,000 OS
mapping (minor crossing). (All proposed watercourse crossings are listed in Table 1 and 2
and shown on Figure 8.6a-8.6c of the EIA Report). 
8.4. Information submitted as part of the EIA at Technical Appendix 8-7 provides an inventory
of information on each watercourse crossing including scale, dimensions, bedload,
vegetation and other characteristics, along with the proposed type of crossing to be installed.
At design phase these crossings will be sized to allow the 1 in 200 year return period flow
event plus allowance for climate change and a freeboard. (This information should be read
in conjunction with EIA Report Chapter 8: Geology, Hydrology, Hydrogeology and Peat of

Page 62

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
the EIA Report, Figures 8.6a-c in Volume 3 of the EIA Report and Chapter 2: Project
Description of the EIA Report). 
8.5 The Site and the Site Access is located within three main surface water catchments: The
River Nant, River Nell/Foechan Mhor and the Allt Nathais. 
• The majority of the Site is within the River Nant and River Nell/Foechan Mhor
catchments with 
• The majority of the Site Access within the Allt Nathais catchment. 
• The majority of the Site drains to the south within the River Nant catchment via Eas
Ruadh and un-named tributaries of the Laggan Burn, the Allt Carnaich and the Garbh
Allt into Loch Nant. Loch Nant discharges to the River Nant that flows northwards to
discharge to Loch Etive, north of Taynuilt. 
• The northern section of the Site drains to south via un-named tributaries of River
Lonan which flows west to Loch Nell before discharge as River Nell/Foechan Mhor
before discharging to Loch Foechan near Kilmore.
• There are three small lochans within the site all located to the north or north west of
the Carn Cairbhre summit. 
8.6. Submissions confirm that the proposals will also be subject to controls under the SEPA
Regulatory Methods for Engineering Activities (SEPA, 2019) which lists conservation,
environmental standards for morphology and good practice as tests for any licence
application. During the determination, SEPA shall consider the specific location, type, size
and existing water quality of the local water features. A Construction Site Licence is
anticipated to be required. This application process shall be undertaken pre-construction,
providing supplementary information to that available at the EIA Report stage as part of
compliance with required SEPA enforced regulatory frameworks. 
8.7. Critical to these works are ensuring potential impacts on ancient woodland along the
access track, impacts on the water environment, and impacts on fish are either avoided or
minimised in accordance with best practice requirements. These matters have all been
considered and addressed by the use of appropriate conditions and as embedded in the
EIAR and appendices. 
8.8. Sustainable Drainage Systems (SuDS) have been proposed to ensure that the rate of 
runoff from the Site post-development is no greater than that prior to development and
would not therefore increase any downstream flood risk. The proposed SuDS allow the
quality of water to be managed at source, prior to any discharge, thereby helping to
prevent any reduction in water quality downstream. 
8.9. Potentially groundwater-dependent terrestrial ecosystems have been identified within
the Application Boundary and assessed on a case-by-case basis to determine their level of 
groundwater dependency and potential impacts from development. Location-specific
mitigation measures are provided to manage potential impacts arising from construction
activities where it has not been possible to avoid these areas. 
8.10. The Council’s Flood Prevention Officer – has no objection to this proposal and
recommends that the following planning conditions are attached to any grant of planning
permission. Any proposed watercourse crossings should not reduce the existing capacity of
the channel and ideally should be designed to convey the 1 in 200 year plus climate change
(56% allowance) flood event. Surface water drainage should be designed in accordance with
CIRIA C753 and ensure that post development surface water runoff does not exceed the
pre-development surface water runoff. The surface water drainage should be in operation
prior to the start of construction.

Page 63

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
8.11. Peat Impact and Management Proposals 
8.12. Details of the proposed approach to minimising impacts on Peat and proposed
management and mitigation measures are set out within the EIAR at Chapter 8. This details
the current environmental baseline in relation to this topic and identifies and assesses the
potential significant effects on identified receptors. The assessment tables present the
effects of each infrastructure section on the receptors identified. These effects are then
grouped for the assessment section which discusses the overall effects. Where relevant,
mitigation, management and monitoring measures are then discussed and the residual
effects determined. The Chapter presents associated links to other chapters or appendices
such as Chapter 6 and the OBE-HMP, Technical Appendix 6.10. 
8.13. A detailed programme of peat depth and peatland condition surveying has been
completed and the results used to inform the Site design to avoid areas of deeper peat
deposits. A Peat Landslide Hazard Risk Assessment and Outline Peat Management Plan
Beaufort Wind Limited Beinn Ghlas Wind Farm Repowering EIA Report Volume 1 have been
produced for the Proposed Development, which show that risks to peat slide have been
avoided and all excavated peat can be appropriately used on site for peat restoration
purposes.   
8.14. In respect of the Peat Landslide Hazard Risk Assessment report, an appropriately
worded condition has been included to ensure that the submitted Peat Hazard Landslide
Report and appropriate safeguarding measures is secured through the appointment of a
Geotechnical Clerk of works with expertise in these matters to ensure adherence to best
practice during future construction activities. 
8.15. The EIAR Chapter 8 submissions clarify that mitigation measures have been identified
for all potential impacts, either through the design process or in accordance with good
practice guidance. It has been shown, as a consequence of the Proposed Development
design and embedded mitigation, that no significant impacts on geology, hydrogeology,
hydrology and peat would arise as a result of the Proposed Development. 
8.16. No objections to the proposals have been raised in respect of these matters by
NatureScot, SEPA or the Councils Biodiversity Officer and Flooding advisor subject to the
imposition of appropriate conditions.  
8.17.  Having due regard to the above, subject to the recommended conditions it is
concluded that the proposal is consistent with the provisions of Policy 11 – Energy 
and Policy 5 Soils of NPF 4, Policy 30 – The Sustainable Growth of Renewables, Policy
55 – Flooding; Policy 57 Risk Appraisals and Policy 79 Protection of soil and Peat
Resources of LDP2.   
9.0 NOISE & SHADOW FLICKER  
9.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will demonstrate
how impacts on communities and individual dwellings, including, residential amenity, visual
impact, noise, and shadow flicker have been addressed. Policy 30 – the Sustainable Growth
of Renewables of the LDP2 requires all applications for wind turbine developments to be
assessed in terms of impacts on communities and individual dwellings, including visual
impact, residential amenity, noise and shadow flicker (including cumulative).   
9.2. Noise and vibration are addressed in detail at Chapter 7 or the EIAR and summarises
the assessment of the potential noise and vibration effects of the Proposed Development on
the residents of nearby dwellings.

Page 64

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
9.3. Noise levels from operation of the turbines have been predicted for those locations
around the site most likely to be affected by noise. Noise limits have been derived following
the simplified assessment method stipulated in national planning guidance given the
relatively large separation distance of approximately 1.9 km or more between the turbines
and the nearest Noise-Sensitive Receptors (NSRs). 
9.4. The EIAR confirms that wind developments within 5 km have been considered in the
cumulative assessment: the Cruach Clenmacrie and Corr Chnoc Wind Farms. Other, more
distant wind farms were not considered as the applicants have submitted that they do not
make an acoustically relevant contribution to cumulative noise levels. Predicted operational
noise levels have been compared to the limit values to demonstrate that turbines of the type
and size which would be installed can operate within the limits so derived. It is concluded
that operational noise levels from the Proposed Development will be within levels
recommended in national guidance for wind energy schemes. 
9.5 The Applicant has provided an updated technical note to reflect recently published
guidance on windfarm noise measurement. Importantly the ABC Noise Consultant has
evaluated the information submitted and raised no objection to the proposals subject to the
imposition of a suitably worded condition which has been agreed between parties and
reflects current best practice advice on these matters.  
9.6 Residential/Visual Amenity& Shadow Flicker 
9.7. Residential properties within 3km of the proposed turbines are shown along with the
ZTV in Figure 5.79, except for Barr Bheag (listed in the EIAR as demolished). The LVIA
states in paragraph 5.6.162 that the initial assessment of visual receptors (contained in
Technical Appendix 5.4) identified ‘24 residential properties within 3 km of the proposed
turbines.  The closest properties overlapped by the ZTV are Bar-Ghlas and Am-Barr situated
to the north of Glen Lonan Road, at approximately 2.1 km and 2.2km respectively. No
significant visual effects are predicted in the EIAR on any of the residential properties within
3km of the proposal, due to partial screening by intervening landform and vegetation. The
Councils Landscape Advisor is in agreement with this conclusion. 
9.8. Shadow flicker is an effect that can occur when the shadow of a blade passes over a
small opening (such as window), briefly reducing the intensity of light within the room, and
causing a flickering to be perceived. As a result of the distance from the development to the
nearest properties, shadow flicker effects are not likely as the nearest residential property is
over 10 times the blade tip height away from the development. 
9.9.  It is noted that the Design and Access Statement included in the EIAR states that
consideration of potential effects upon residential visual amenity was part of the design
process and resulted in the omission of T14 from layout A (the turbine located closest to
residential properties which, given its position within the site, could appear dominant within
views from the nearest properties). 
9.10.  Having due regard to the above it is concluded that the proposal is acceptable
in terms of any potential shadow flicker impact, Noise and water supplies subject to
the conditions recommended by the Council’s Noise Consultant and Environmental
Health Officer and is therefore consistent with the provisions of Policy 11- Energy,
and Policy 30 – The Sustainable Growth of Renewables of the ABLDP2 in this respect. 
10.0 ROAD TRAFFIC AND ADJACENT TRUNK ROADS

Page 65

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
10.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate
how impacts on road traffic and on adjacent trunk roads have been addressed, including
during construction. Policy 30 – the Sustainable Growth of Renewables of ABLDP2 requires
all applications for wind turbine developments to be assessed against impacts on road traffic
and impacts on adjacent trunk roads. Policy 35 – Design of New and Existing, Public Roads
and Private Access Regimes of LDP2 acceptance of development utilising new and existing
public roads, private roads and private access regimes is subject to road safety and street
design issues being addressed to the satisfaction of the Roads Authority and the Planning
Authority. Policy 38 – Construction Standards for Public Roads requires that accesses which
connect to or impact significantly on a Trunk Road require consultation with Transport
Scotland. 
10.2. The application proposals involve; 
• Upgrading of four existing road junctions to support construction and abnormal road
traffic 
• Upgrading of forestry tracks from the A85 through Fearnoch Forest, Glen Lonan
Road (C32) and existing wind farm access track to accommodate the delivery of
abnormal loads to the site and 
• use of existing track for access to the first construction compound
• Formation of internal access tracks (this has been minimised by seeking to utilise
existing internal tracks where possible) 
10.3. The Traffic and Transport chapter of the EIAR assesses the potential effects of the
Proposed Development on the road network (in transport terms) and its users. The
assessment detailed within Chapter 10 of the EIAR includes worst-case assumptions made
for the purpose of forming a robust assessment of the Proposed Development within the
parameters identified elsewhere within the EIAR. The Study Area for construction vehicles
is focused on the immediate roads surrounding and leading to the Proposed Development,
as it is expected that traffic flows outside of this area would be dissipated on the wider road
network without any significant effect. This chapter therefore only considers the likely
increases in traffic along these routes associated with the Proposed Development. 
10.4Given the temporary nature of the construction programmes and with the
implementation of mitigation measures through a Construction Traffic Management Plan
(CTMP) and Abnormal Load Traffic Management Plan (ATMP), all traffic and transport
effects (including cumulative) can be effectively managed.  
10.5.  ABC’s Area Roads and Transport Scotland have raised no objection to the proposals
subject to the imposition of appropriate conditions (previously set out in within Section C of
this report). These will involve a Construction Traffic Management Plan, Abnormal Loads
Plan, necessary junction improvements and protection of the public road through monitoring. 
10.6. The Area Roads Manager has requested pre commencement meetings to discuss
these matters and Officers will seek to ensure that both Transport Scotland and the Area
Roads Manager meet with the appropriate parties at an early stage to ensure all Traffic and
Transport matters are properly addressed     
10.7. Having due regard to the above, subject to the recommended conditions it is
considered that the proposal is consistent with the provisions of Policy 11 – Energy
of NPF4, Policy 30 – The Sustainable Growth of Renewables, Policy 35 – Design of
New and Existing, Public Roads and Private Access Regimes and Policy 38 –
Construction Standards for Public Roads in this regard.

Page 66

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
11.0 NET ECONOMIC IMPACT, INCLUDING LOCAL AND COMMUNITY SOCIO-
ECONOMIC  BENEFITS   
11.1 Policy 11 – Energy of NPF4 states that proposals will only be supported where they
maximise net economic impact, including local and community socio- economic benefits
such as employment, associated business and supply chain opportunities. Policy 30 - the
Sustainable Growth of Renewables of LDP2 require all applications for wind turbine
developments to be assessed in terms of net economic impact, including local and
community socio-economic benefits such as employment, associated business and supply
chain opportunities. 
11.2 Submissions relating to the assessment of whether the Proposed Development will
maximise these benefits is based on the commitments and actions that the Applicant has
taken on supply chain development, skills development, the empowerment of communities
and balancing the development with environmental protection and enhancement. This
considered both what the Applicant has direct control over, and how it can enable others to
have a positive impact across these areas. 
11.3 The Applicant has committed to engaging with local suppliers to maximise local benefits
from the wind farm by supporting the local community and working with local contractors
whenever the project requirements and conditions allow. A supplier registration page is
included on the project website (https://www.beinnghlasrepowering.co.uk/suppliers
registration/) to communicate opportunities across all phases of the Proposed Development.
In addition, the Applicant will organise a contractors open day / ‘Meet the Buyer’ event to
ensure maximum engagement with contractors. This will ensure high local supply chain
content and provide opportunities for local employment which are routed in the needs and
context of the Argyll and Bute economy. 
11.4 The Applicant has also developed an Outline Circular Decommissioning Strategy
(Nadara and Reblade, 2025) to identify circular opportunities for the decommissioning of the
existing wind farm and has committed to supporting the protection of the local environment
by minimising waste, reducing carbon emissions and promoting sustainable material use,
and creation of circular jobs, skills and educational opportunities. The Applicant has
proactively engaged with local schools to support skills development in the local onshore
wind sector, including delivering a STEM workshop at Taynuilt Primary School in partnership
with 3DW. An invitation has been extended to Oban High School to provide a similar
workshop. These initiatives will provide opportunities for skills development and support the
continuation of innovative processes to maximise onshore wind benefits. The Applicant is
actively engaging with the communities surrounding their onshore wind farms organising
events such as annual forums to give them an opportunity to provide feedback and also
keep them informed of the development and associated benefits 
11.5 The applicants have also submitted that the Proposed Development is also expected
to provide an annual contribution of approximately £168,000 per annum in community
benefits. During its operations, the Proposed Development is expected to generate
approximately £408,900 in non-domestic rates yearly. These payments will contribute to the
funding of local public services and the investment priorities of local communities. Whilst
these financial contributions are noted, they are  not  a material planning considerations for
the purposes of the determination of this planning application. 
11.6 The applicant contents that: 
The Applicant has proposed a wide range of initiatives in pursuit of the policy intention of
NPF4 Policy 11(c) to “maximise net economic impact”. These are consistent with the
Scottish Renewables guidance (Scottish Renewables, 2025), covering the four themes of

Page 67

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
maximising the supply chain, skills and workforce, community empowerment, and natural
environment benefits. The comprehensive package of measures is expected to deliver
substantial economic and community benefits, in line with the intention of NPF4 Policy 11(c). 
11.7 Having due regard to the above it is considered a degree of net economic impact,
including local and community socio-economic benefits, typical of such
developments will be provided. It is therefore concluded that the proposal is
consistent with the provisions of Policy 11 – Energy of NPF4, and Policy 30 – The
Sustainable Growth of Renewables of the LDP2. 
12.0 IMPACTS ON TOURISM AND RECREATION   
12.1 Policy 11 – Energy of NPF4 does not require Impacts on tourism to be considered.
Policy 30 – The Sustainable Growth of Renewables of LDP2 requires all applications for
wind turbine developments to be assessed against impacts on tourism and recreation.   
12.2 Tourism - Policy 11 of NPF4 does not include a requirement for the impact of proposals
on tourism to be assessed. However, Policy 30 – The Sustainable Growth of Renewables of
the LDP does. In Argyll & Bute the landscape is regarded as being a particularly valued
asset both in terms of its intrinsic qualities and in terms of its value to the tourism economy.
For all types of development, the maintenance of landscape character is an important facet
of decision-making in the countryside in Argyll & Bute, regardless of the scale of
development proposed.   
12.3 As Tourism and Landscape & Visual matters are intrinsically linked, and there is little
evidence to demonstrate whether wind farms adversely affect tourism, it is considered that
such impacts are covered in the landscape and visual impact assessment of the proposal. 
12.4 Having due regard to the above the proposal is consistent with the provisions of
Policy 11 – Energy of NPF4 and Policies 04 – Sustainable Development and 30 – The
Sustainable Growth of Renewables of LDP2 in this respect. 
13.0  PUBLIC ACCESS 
13.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate
how impacts on public access are addressed, including impact on long distance walking,
and cycling routes and scenic routes. Policy 30 – the Sustainable Growth of Renewables of
LDP2 requires all wind turbine developments to be assessed against impacts on public
access, including impact on long distance walking and cycling routes and those scenic
routes identified in NPF4. Policy 32 – Active Travel of ABLDP2 requires that requires active
travel and recreation are integrated in developments from the start of the wider design
process and existing active travel networks should be safeguarded and integrated with the
development.  
13.2 National Cycle Network (NCN) Route 78 passes 8.7km to the northwest and the
reclassified cycle route along Glen Lonan Road is located 1.8 km to the north. 
13.3 ABC Core Paths – At time of writing no response has been received. 
Having due regard to the above subject to the condition to secure an Access
Management Plan it is considered that the proposal is consistent with the provisions
of Policy 11- Energy of NPF4, Policy 30 – the Sustainable Growth of Renewables; and
Policy 32 - Active Travel of the LDP2. 
14.0 AVIATION AND DEFENCE INTERESTS

Page 68

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
14.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate
how impacts on aviation and defence interests including seismological recording have been
addressed. Policy 30 – the Sustainable Growth of Renewables of LDP2 requires impacts on
aviation and defence interests and seismological recording to be addressed. Policy 43 –
Safeguarding of Aerodromes of LDP2 stipulates that Development will not be permitted
where it would compromise the safe operation of an Aerodrome or Technical Site or
constrain their present or future operations. 
14.2 Defence Infrastructure Organisation (DIO) – have advised that, subject to conditions
they have no objection and National Air Traffic Services Safeguarding (NATS) have raised
no objection. Recommended conditions in respect of these matters have been proposed to
safeguard aviation safety. 
14.3 Having due regard to the above, subject to the conditions recommended it is
concluded the proposal is consistent with the provisions of Policy 11 – Energy of
NPF4 and Policies 30 – The Sustainable Growth of Renewables and 43 – Safeguarding
of Aerodromes, of the LDP2 in this respect.   
15.0 TELECOMMUNICATIONS AND BROADCASTING INSTALLATIONS   
15.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate
how impacts on telecommunications and broadcasting installations, have been addressed
particularly, ensuring that transmission links are not compromised. Policy 30 – The
Sustainable Growth of Renewables of LDP2 requires all applications for wind turbine
developments are assessed against impacts on telecommunications and broadcasting
installations, particularly ensuring that transmission links are not compromised. 
15.2 Arqiva -Have raised no objection to the proposals on the potential impact on re-
broadcast Links ( which serve local settlements) but recommended that a condition requiring
any adverse impacts on individual domestic properties be imposed, or a condition to require
these matters to be evaluated in advance of construction , with any necessary mitigation
undertaken is imposed on any grant of consent. An appropriate condition requiring these
matters to be evaluated and addressed is proposed. 
15.3 Having due regard to the above it is concluded that the proposal will not have
any adverse impacts on telecommunications, broadcasting installations and
transmission links (including cumulative impacts) and is consistent with the
provisions of Policy 11- Energy of NPF4 and Policy 30 – The Sustainable Growth of
Renewables of  LDP2 in this respect.   
16.0 DECOMMISSIONING, SITE RESTORATION AND QUALITY OF SITE
RESTORATION PLANS   
16.1 Policy 11 – Energy of NPF4 requires that project design and mitigation demonstrate
how proposals for the decommissioning of developments, including ancillary infrastructure,
and site restoration have been addressed. It also requires that project design and mitigation
demonstrate how the quality of site restoration plans have been addressed including the
measures in place to safeguard or guarantee availability of finances to effectively implement
those plans. Policy 30 – The Sustainable Growth of Renewables of the LDP2 requires
consideration to be given to the long-term environmental management of the site.   
16.2 The operational life of the proposed development is 35 years from the date of
commissioning. At the end of the 35-year operational period, it will be fully decommissioned,
or an application may be made to extend its operational life or replace the turbines. This

Page 69

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
would involve the dismantling and removal of the wind turbines, hardstandings, electrical
equipment, and control building as well as restoring the turbine areas, hardstandings and
tracks. A Decommissioning Plan would set out environmental protection measures and
restoration principles which would be implemented. This Plan would be agreed with ABC. It
is recommended that this matter is covered by planning conditions consistent with other
projects across Argyll & Bute and best practice advice. 
16.3 Having due regard to the above it is concluded that subject to appropriate
decommissioning and site restoration and financial bond condition (s) being attached
to the planning permission the proposal is consistent with the provisions of Policy 11
– Energy of NPF4 and Policy 30 – The Sustainable Growth of Renewables of the LDP2 
17.0 CUMULATIVE IMPACTS 
17.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will demonstrate
how cumulative impacts have been addressed. Policy 30 – The Sustainable Growth of
Renewables of the ABLDP2 also requires cumulative impacts to be addressed. 
Any cumulative impacts which have been identified are covered in the preceding sections of
this report. 
18.0 RENEWABLE ENERGY GENERATION TARGETS AND GREENHOUSE GAS
EMISSIONS REDUCTION TARGETS.   
18.1 Policy 11 – Energy of NPF4 requires that, in considering the impacts of the proposal,
significant weight will be placed on the contribution of the proposal to renewable energy
generation targets and on greenhouse gas emissions reduction targets. Policy 1 – Tackling
the climate and nature crises of NPF4 requires that when considering all development
proposals significant weight will be given to the global climate and nature crises. Policy 30 –
The Sustainable Growth of Renewables of ABLDP2 require all applications for wind turbine
developments to be assessed against the scale of contribution to renewable energy
generation targets and greenhouse gas emissions.   
18.2 A carbon balance assessment has been undertaken regarding the Proposed
Development and is detailed in Technical Appendix 13.4. This assessment uses the Scottish
Government’s Carbon Calculator for wind farms on peat to assess the benefit of displacing
electricity from fossil fuels with renewable generated electricity, compared to the emissions
of carbon required for the construction and operation of the Proposed Development over its
approximately 35-year lifetime, including losses of stored carbon from disturbed peatland
and reduction of carbon fixing vegetation cover. The Carbon Calculator provides an estimate
of the carbon payback time for the Proposed Development. 
18.3 The results of the Carbon Calculator show submitted with the application that the
Proposed Development is estimated to produce annual carbon savings of around 32,000
tonnes of CO2e per year through the displacement of grid electricity, based on the current
average grid mix. 
18.4 The assessment of the Proposed Development estimates losses of around 64,000
tonnes of CO2e, nearly all of which come from the lifecycle emissions of the turbines.
Ecological site-based losses account for just over 10,000 tCO2e while restoration of areas
of degraded bog are estimated to produce gains over the lifetime of the Proposed
Development through blocking of drains and re-wetting of peat; these gains are estimated
at nearly 16,000 tonnes of CO2e, which is greater than the ecological site-based losses.

Page 70

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
18.5 The estimated payback time of the Proposed Development, using the Scottish
Government Carbon Calculator, is 1.5 years, with a minimum/maximum range of 0.87 to 2.3
years. There are no current guidelines about what payback time constitutes a significant
impact, but 1.5 years is only 4 % of the anticipated lifespan of the Proposed Development.
The carbon intensity of the electricity produced by the Proposed Development is estimated
at 0.019 kgCO2e/kWh. This is well below the outcome indicator for maintaining the electricity
grid carbon intensity below 0.05 kgCO2e/kWh required by the Scottish Government in the
Climate Change Plan update and therefore the Proposed Development is evaluated to have
an overall beneficial effect on the carbon balance. 
18.6 Having due regard to the above it is considered that the proposal is consistent
with the provisions of Policies 1 – Tackling the climate and nature crisis and 11 –
Energy of NPF 4, and Policies 30 – The Sustainable Growth of Renewables and 04 –
Sustainable Development of LDP2 
19.0 GRID CAPACITY & ENERGY STORAGE   
19.1 Policy 11 – Energy of NPF4 requires that grid capacity should not constrain renewable
energy development. It is for developers to agree connections to the grid with the relevant
network operator.  Development proposals for all forms of renewable, low-carbon and zero
emissions technologies will be supported, which include energy storage. Policy 30 – The
Sustainable Growth of Renewables of LDP2 requires the Council to have regard to the
opportunities for energy storage.   
19.2 Grid Capacity - Connection to Electricity Grid - There is a viable grid connection
available as has been set out within FEI. The grid connection does not form part of this
planning application and will be the subject of future separate detailed proposals and
controls. 
19.3 Energy storage – battery storage is not proposed as part of this development. 
Having due regard to the above it is considered that the proposal is consistent with
the provisions of Policy 11 – Energy of NPF 4, and Policy 30 – The Sustainable Growth
of Renewables of the LDP2 in respect to Grid Capacity and Energy Storage
(opportunities for energy storage have been explored). 
20.0 CONCLUSION & RECOMMENDATION 
20.1. As per the detailed assessment above, and taking into account all consultee
responses, third party representations and relevant planning policy it is considered that this
proposal is acceptable.  It is therefore recommended that planning permission is granted
subject to the conditions recommended in this report.

Page 71

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Appendix B –  List of Representations 
Objections   3
Support  26
Representation  1 
25/01240/PP  - 31 August 2026 
Objection 
1. Mr Phillips 02.10.2025
2. Mrs Phillips 02.10.2025     
3. Mr Roni Macdonald Riverside Cottage PA34 4XX 10.10.2025 
Support  
1. Lorne Nelson Kilmaronaig Connel Argyll PA37 1PW 12.11.2025 
2. Aubrey Thompson 12 Mavisbank Kinross KY13 8QR  12.11.2025 
3. Ms Janet Lees Westray Deirdre Connel Argyll And Bute 23.01.2026 
4. Alison Dawson Dunalba  Main Road Connel  Oban  08.01.2026 
5. Ishbel Inall 03.11.2025 
6. Marlyn Turbitt 2 Lagan Taynuilt Argyll And Bute PA35 1JY 03.11.2025  
7. Robert Campbell-Preston Allt-An-Dubh Inverawe Argyll And Bute PA35 1HU
03.11.2025 
8. Edna Whyte Gallery Cottage Cullipool Road Isle Of Luing  PA34 4TX 28.10.2025 
9. Roger Soep Railway Cottage Taynuilt PA35 1JE  28.10.2025 
10. Maria Soep Railway Cottage Taynuilt PA35 1JE  28.10.2025 
11. Miss Fiona MacPherson An-Nuadh Balliemeanoch East Lochaweside PA33 1BW
22.10.2025 
12. Mr Anthony Robin Marshall Gorstain Taynuilt Argyll And Bute PA35 1HY 11.12.2025 
13. Morag MacCormick Flat L Regent Court 15 Hughenden Lane Glasgow 18.12.2025 
14. Douglas Baird The Chalet Corachie Clematis Taynuilt Argyll And Bute 10.12.2025 
15. Owner Occupier Ardchaan Glen Lonan Taynuilt  PA35 1HY 12.02.2026 
16. Sam MacDonald The Willows  Bridge Road Connel  PA37 1PJ  
17. R Sinclair Cruachan View Cottage Connel  Oban  Argyll 18.11.2025 
18. Mr Derek Wilkinson Lora House Upper  C52 Connel Village Loop Road Connel 
19. PA37 1PA 18.02.2026 
20. Mr Neil McGougan Brackendale Taynuilt Argyll And Bute PA35 1JQ 11.12.2025 
21. Dr Simon Lawrence 7 Paterson Street Lochgilphead Argyll And Bute PA31 8JP
12.11.2025 
22. Colin Griffiths Woodend Cottage Kirkton Taynuilt PA35 1HQ 19.11.2025 
23. Mr Martin Charlton Bunanta Taynuilt Argyll And Bute PA35 1HY 17.11.2025 
24. Mr James Houston Am Barr Barguillean Taynuilt Argyll And Bute PA35 1HY
01.10.2025 
25. Mr Max Bigham 4 Ferryfield Drive Connel Argyll And Bute PA37 1SP 04.09.2025 
26. Mrs Melanie Currie Highfield Taynuilt Argyll And Bute PA35 1JQ   
Representation 
1. Mr Keith Waudby Arqiva Ltd Borough Hill Daventry NN11 4NB