1 
Integration Joint Board   
Date of Meeting: 24 August 2022 
Title of Report: Budget Monitoring – 3 months to 30 June 2022 
Presented by: James Gow, Head of Finance and Transformation     
The Integration Joint Board is asked to:
 Note that the transition to a new ledger system within the Council has had an
impact on the Quarter 1 financial reporting as transaction processing has
been prioritised. 
 Note that the current position is a small overspend in respect of NHS
budgets. 
 Note that there is a small forecast revenue overspend of £346k as at 30
June 2021 and that it is anticipated that the HSCP will operate within budget
in the current year. 
 Note the summary of financial risks. 
 Note progress with the savings programme and confirmation of £3.5m in
savings delivered, 42% of target. 
 Note that earmarked reserves of £2.6m have been committed to date for
spend in 2022/23. 
1. EXECUTIVE SUMMARY 
1.1 This report provides a summary of the financial position of the Health and
Social Care Partnership as at 30 June 2022 and provides an early forecast
for the year. It also updates in respect of the delivery of the savings
programme and utilisation of reserves. The contents of this report have been
considered by the Finance and Policy Committee on 5th August. 
1.2 There has been an impact on the Social Work figures as a result of the
transition to a new financial ledger system. It is anticipated that reporting will
return to normal for the period 4 reporting cycle, the figures provided in this
report are consistent with those reported to Council. 
1.3  The forecast for the current year is a small overspend of £346k, it is
anticipated that this can be managed as the year progresses. The forecast

Page 2

2 
is based on a number of assumptions and therefore there are risks
associated with it. These are outlined in the Financial Risks report, inflation
and pay settlements are key risks. It is assumed in the forecast that any
nationally agreed pay settlement within the NHS will be fully funded.  
1.4 The HSCP is still experiencing challenges in filling posts and as a result
there remains some slippage in spend against specific allocations aimed at
easing pressures within the health and care sector. The HSCP continues to
be under pressure to maintain and increase capacity where possible in
advance of the winter period. 
2.  INTRODUCTION 
2.1 
2.2
This report provides a summary of the financial position of the Health and
Social Care Partnership as at 30 June 2022. Information is provided in
respect of the year to date position and the forecast outturn. Summary
information is provided in the detail of the report with further analysis
provided within the appendices. 
Unfortunately Argyll & Bute Council have experienced some issues with the
introduction of the new ledger system at the start of the financial year. This
has meant that the figures reported, which are consistent with those reported
to Council, are not as reflective of the actual position as would normally be
the case. The NHS element of the report is unaffected. 
3. DETAIL OF REPORT 
3.1  Year to 30 June 2022 
3.1.1
The table below summarises the position for quarter 1. This is distorted by
the temporary issues associated with the implementation of the new ledger
system within the Council, this has meant that adjustments to budgets have
not been processed as normal and a large underspend which is not
reflective of the actual position is reported. The NHS position is a small
reported overspend of £170k (0.3% of the NHS budget). For Council
services the year to date figure is reported on a cash basis whereas the
Health figures are on an accruals basis.   
Service Actual
£000
Budget
£000
Variance
£000
%
Variance
COUNCIL SERVICES TOTAL 15,936 21,087 5,151 24%
HEALTH SERVICES TOTAL 56,170 56,000 -170 -0.3%          
GRAND TOTAL 72,106 77,087 4,981 6.5% 
Appendix 1 provides an analysis of the variances against budget by service. 
3.1.2  For Social Work budgets the favourable variance is not representative of the
actual position. As with any major ICT related project there have been some
difficulties encountered with the transition to a new ledger system within
Argyll & Bute Council and the focus has been on ensuring transactions
systems and processes transitioned smoothly. Budget monitoring processes

Page 3

3 
have taken place but are not fully reflected in the ledger system. The only
area of potential concern being investigated at present relates to the LD and
PD budgets. 
3.1.3  For Health Service budgets, a small overspend of £170k is reported. The
main causes of the year to date overspend are shortfalls on savings, agency
medical staffing particularly in Lorne & Islands Hospital and Oban, Lorne
and the Islands out of hours services, and agency nursing costs across a
number of our hospitals. 
3.2 
3.2.1
Forecast Outturn 
The forecast outturn position is summarised below. For social work services
the outturn has been set to match budget. The Social Work finance team
completed an off-ledger forecast which showed that services are currently
on track to come in on budget overall, but were unable to reflect the forecast
in the ledger. For NHS services a small adverse variance of £346k (0.1% of
budget) is forecast, further detail is provided in appendix 2. 
Service Annual
Budget
£000
Forecast
Outturn
£000
Variance
£000
%
Variance
COUNCIL SERVICES TOTAL 87,471 87,471 0 0%
HEALTH SERVICES TOTAL 235,647 235,993 -346 -0.1%          
GRAND TOTAL 323,118 323,464 -346 -0.1% 
3.2.2 
The forecast variance is not a concern at this stage in the year as it is
anticipated that spend will be managed within budget. Additionally, the
HSCP carried significant levels of reserves into the current year. The main
focus in respect of budget management at present is delivery of the savings
programme. 
Within Social Work there is one early specific area of concern regarding
Learning Disability spend. This has not been reflected in the ledger position
at present and work is on-going to further analyse the position as significant
additional resource was allocated as part of the budgeting process. The
period 4 reporting is expected to provide improved quality of forecast
information. 
3.2.3  The forecast for Health budgets is a small overspend totalling £346k.
Appendix 2 provides details on a service level basis. The main area of
concern at present relates to spend on Community and Hospital Services.
Forecast overspending here is at £954k with some of this being offset by
underspending on other services. The main driver of the projected
overspend relates to the steps that are having to be taken to seek to stabilise
medical staffing at Lorne and Islands Hospital. Recruitment continues to be
a challenge, however, given the level of pressure on services nationally we
are accepting that increased spend is likely to be required to maintain
services and avoid increasing pressures elsewhere in the system.

Page 4

4
3.2.4  The forecast takes account of anticipated shortfalls against recurring
savings targets and emerging cost pressures with an expectation that these
will be largely, but not fully, offset by non-recurring savings and
underspends. It is assumed within the forecast that all additional costs
associated with our direct response to Covid-19 and for both the Covid
Booster & Flu Vaccination Programmes will be fully funded from IJB held
Covid reserves and not additional funding allocations.   
Annual
Budget
(£’000)
Forecast
Outturn
(£’000)
Forecast
Variance
(£’000) 
Explanation
Health Services 235,647 235,993 (346) Hospital staffing, inflation and
expected slippage with savings. 
With nine months of the financial year remaining, there is sufficient scope
for to address the modest forecast year-end overspend and deliver a break-
even outturn position. The intention is to continue to ensure that the HSCP
operates within budget, delivers on the savings programme and increases
capacity where it can with its growth funding.
3.3 Savings Delivery 
3.3.1 
3.3.2 
3.3.3 
The Service Improvement Team and the Project Management Office, co-
ordinated by NHS Highland, continue to work with managers to progress,
monitor and report progress on the savings project. This is done in
conjunction with the management accounting teams. As at the end of June,
£2.5m (42%) of the £6m savings target has been achieved and declared: 
2022/23 Savings    Year to 30 June 2022    
Target Achievement Balance %  
£' 000 £' 000 £' 000 
Fully Achieved 2,213 2,213 0 
Remaining
Programme 3,789 287 3,502 
Total 6,002 2,500 3,502 42% 
Appendix 3a lists the projects that have been fully delivered and declared.
The projects which are declared on a non-recurring basis will be addressed
as part of the capital project at Cowal Community Hospital. Appendix 3b
provides further detail in respect of the remaining balance of £3.5m, risk
rated per below: 
Savings Perceived as Low Risk £784k 
Savings anticipated to be difficult to achieve in full in
2022/23
£2,227k 
Savings unlikely to be deliverable in 2022/23 £491k 
It is not proposed that the IJB are asked to consider the removal of projects
from the plan at present. The appendix provides an explanation in respect
of progress and the detailed service deep dive reports provided to the
Finance & Policy Committee give further detail.

Page 5

5
3.3.4 
3.3.5 
3.3.6 
3.4 
3.5 
3.5.1 
4
4.1 
One of the biggest challenges relates to the Cowal Community Hospital
project, this is being project managed by NHS Highland and is subject to
delay as additional costs have been identified. If the funding issue is
resolved quickly then the best outcome available will be for construction
work to start in November for March completion. Engagement with the local
community also needs to be progressed in the coming months. We are also
in the process of seeking to bring in additional resource to support the work
on catering, cleaning and hotel services, some slippage with these projects
is expected to continue. 
The medical staffing structure at LIH in Oban is not stable at present, work
is on-going, with support from NHS Highland to stabilise the situation and
establish a stable staffing model which is compliant with the medical staff
training requirements, there is no possibility that plans to deliver additional
services can be implemented in the current year. 
Overall good progress has been made, however, slippage will require to be
covered by non-recurring savings as the year progresses, the NHS forecast
now take this into account and Social Work Forecasts will be updated for the
period 4 reporting. 
Financial Risks 
A separate report on financial risks faced in the current year is provided to
the Finance and Policy Committee. A summary of the August report is
provided below: 
Likelihood /
Range
Remote Unlikely Possible  Likely Almost
certain
Total
£100k - £300k 0 0 0 0 1 1
£300k - £500k 0 0 1 1 0 2
£500k - £1.5m 0 1 1 2 2 6
>£1.5m 0 0 0 0 0 0
Total 0 0 2 6 2 9 
These risks are quantified at £3.3m in total and the most concerning ones
relate to inflation, pay increases and the likely additional costs associated
with current service providers withdrawing or reducing services within the
area. 
Earmarked Reserves 
The IJB carried forward earmarked reserves of £21.2m at the end of
financial year 2022/23. During the first quarter, £2.6m has been allocated to
specific projects / costs. Appendix 4 provides a summary. Reserves are now
considered monthly as part of the SLT financial reporting process. 
RELEVANT DATA AND INDICATORS 
Information is derived from the financial systems of Argyll and Bute
Council and NHS Highland.

Page 6

6
5
5.1   
6
6.1 
6.2 
6.3
CONTRIBUTION TO STRATEGIC PRIORITIES 
The Integrated Joint Board has a responsibility to set a balanced budget
which is aligned to the Strategic Plan. It is required to ensure that financial
decisions are in line with Strategic Priorities and the delivery of high quality
services. 
GOVERNANCE IMPLICATIONS 
Financial Impact – the forecast outturn positon is currently an overspend
of £346k. It is anticipated that the HSCP will be able to manage this during
the year. It is noted that it has carried forward substantial levels of
reserves.       
Staff Governance – None directly from this report but there is a strong link
between HR management and delivering a balanced financial position. 
Clinical Governance – None. 
7. 
7.1 
8.
PROFESSIONAL ADVISORY 
Professional Leads have been consulted with in respect of the implications
of the budget and savings programme. 
EQUALITY AND DIVERSITY IMPLICATIONS 
8.1 None directly from this report at present. 
9. 
9.1 
10
GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
None. 
RISK ASSESSMENT 
10.1 There are a number of financial risks which may impact on the forecast
outturn. These are reviewed regularly and are reported separately. There
remains a small risk in respect of the financial reporting data within the Argyll
and Bute Council ledger system as the new system is implemented. There
is an increasing risk that funding streams will be reduced whilst significant
reserves are held. NHS Highland also continue to experience a particularly
challenging financial situation in 2022/23 
11. PUBLIC AND USER INVOLVEMENT AND ENGAGEMENT 
11.1  None directly from this report, engagement on activities relating to savings
and transformation forms part of the project plans where appropriate. 
12. CONCLUSIONS 
12.1  This report provides a summary of the financial position as at the end of
quarter 1. A small overspend against budget is currently forecast, however
it is anticipated that the position can be managed during the remainder of
the year. On-going high levels of demand for services and the additional

Page 7

7 
12.2 
costs associated with agency and locum cover are contributing to budget
pressures.   
Good progress has been made in delivering 42% of the savings programme
in the first quarter although some challenges with savings delivery have
been identified. Additionally, efforts are on-going to ensure that progress
with allocating reserves continues as there is a risk that in-year allocations
will be reduced until reserves are utilised. Continued action to address
delayed discharges, the autumn covid vaccination programme and efforts to
increase capacity in advance of the winter are likely to add to financial
pressures and spend later in the year. 
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required √
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland
Health Board 
APPENDICES:
Appendix 1 – Year to Date Position 
Appendix 2 – Forecast Outturn for 2022-23 
Appendix 3a – Fully Achieved Savings
Appendix 3b – Live Savings Programme
Appendix 4 – Earmarked Reserves   
AUTHOR NAME: James Gow, Head of Finance and Transformation 
EMAIL: james.gow@argyll-bute.gov.uk