Democracy Spraffa

Provisional Year End - 12 months to 31 March 2023

Argyll and Bute Council · 31 May 2023
Back to Argyll and Bute HSCP Integration Joint Board (IJB) — 31 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
Integration Joint Board   
Date of Meeting: 31 May 2023 
Title of Report: Provisional Year End – 12 months to 31 March 2023 
Presented by: James Gow, Head of Finance and Transformation 
The Integration Joint Board is asked to:
 Note that the HSCP expects to report an underspend of £9.1m for 2023/24,
equivalent to 2.7% of the resources allocated to it. 
 Note that it is anticipated the HSCP will be able to carry this underspend
forward to fund the 2023/24 budget gap and key infrastructure and
transformation projects.   
 Note confirmation that savings of £4.1m have been delivered, 68% of
savings plan. 
 Note that total reserves held have reduced from £21.2m at the start of the
year to £16.9m at the year end. 
 Note that all figures provided in this report are provisional and subject to
external audit.   
1. EXECUTIVE SUMMARY 
1.1 This report provides a provisional summary of the financial position of the
Health and Social Care Partnership as at 31 March 2023 and year end position
which will be reported in the Annual Accounts. The report also provides a
summary of the delivery of the savings programme and reserves. 
1.2 
1.3 
Overall the financial position improved markedly as the year end approached
and a significant underspend is reported. The total provisional underspend
against the resources available to the HSCP was £9.1m or 2.7% of total spend
budget. Actual spend for the year totalled £332m, an increase from £312m in
2021/22. The £9.1m underspend will be carried forward in IJB reserves. 
The outturn was substantially better than forecast for a number of reasons
including additional late funding allocations and spend on key contracts being
lower than expected and below previous trends. The positive result for the year
is expected to enable the HSCP to avoid having to make any requests for

Page 2

2
additional financial support in 2023/24 and will also enable important
transformation, prevention and infrastructure improvement projects to proceed. 
2.  INTRODUCTION 
2.1  This report provides a summary of the provisional 2022/23 year end financial
position of the Health and Social Care Partnership. It is subject to external audit
and, at the time of writing there remains potential for minor changes.   
3. DETAIL OF REPORT 
3.1  12 Months to 21 March 2023 
The table below provides a summary for 2022/23. Appendix 1 provides an
analysis of the year end variances by service. The outturn for both Social Work
and Health were better than had been previously forecast. 
Service Actual
£000
Budget
£000
Variance
£000
%
Variance
COUNCIL SERVICES TOTAL 89,184 92,740 3,556 3.8%
HEALTH SERVICES TOTAL 242,496 248,038 5,542 2.2%          
GRAND TOTAL 331,680 340,778 9,098 2.7% 
3.1.2 
3.1.3
For Social Work the main area of concern throughout the year related to the
Learning Disability, Mental Health and Physical Disability budgets. These
finished the year £1.2m overspent. This overspend was offset by slippage on
growth budgets, underspending in other areas and non-recurring savings. 
Within the NHS budget there are overspends reported on Acute & Complex
care budgets (£0.5m), prescribing (£0.9m) and estates (£0.4m). These have
all been offset by non-recurring funding, vacancies and confirmation of funding
streams by Scottish Government at the end of the year.    
3.2 
3.2.1
Year end variance against forecast 
The HSCP had been reporting an improving position throughout the year, it is
recognised that the final position was significantly better than had been
forecast. 
Service M11 Forecast
Favourable
Variance £m
Provisional 
2022/23
Outturn £m
COUNCIL SERVICES TOTAL 2.0 3.6
HEALTH SERVICES TOTAL 2.3 5.5      
TOTAL 4.3 9.1

Page 3

3
3.2.2 
3.2.3
For Social Work there have been a number of favourable movements across
many service areas. The older adults budget ended the year £0.9m better than
forecast (total budget £43.9m). This was due to costs associated with the
smarter commissioning model, implemented towards the end of the year, being
less than expected and income in council owned care homes increasing
towards the end of the year. The final overspend on Learning Disability, Mental
Health and Physical Disability budgets was also £0.3m less than had been
forecast. These variances account for most of the improvement in the forecast. 
Likewise within the NHS budget year end spend was generally less than had
been forecast. The main year end movements were:
1. significant reduction in cost per case charges from NHS GG&C based
on prior month charges and historic trends (£0.9m favourable change).
In 22/23 GGC reporting on these charges ran 3 to 6 months behind the
reporting period making forecasting difficult and placed a reliance on
historic data.  
2. write back of provisions for injury benefits and the regrading of band 2
to band 3 HCSW.  The provisions for these items were assessed as
too high based on the up to date information.
3. reduction in cost per item charges for GP prescribing and additional
year end funding (£0.3m favourable change)
Vacancy savings and slippage on investments also continued through to the
year end.    
3.2.4 
3.2.5 
Overall the favourable outturn does mask underlying cost pressures and
overspending on some services. Financial year 2022/23 was unusual due to
higher than expected pay increases and inflation. The delays in securing pay
settlements and the unexpected strain this placed on government finances
throughout the year meant that many of the NHS funding streams in particular
were confirmed very late. The outcome is extremely positive and provides the
HSCP with the ability to manage its financial position in 2023/24 in a better way
than had been expected. It is acknowledged that forecasting processes require
to be reviewed to ensure that they are not unduly prudent or risk averse
throughout the year. Developmental work will need to consider how service
management engage with the finance teams as well as technical financial
reporting and contract management processes. 
The implications are that the HSCP does not now expect to be reliant on
brokerage via NHS Highland as outlined in its Budget for 2023/24. This has
been communicated to NHS Highland. The Underspend will be carried forward
and the balance that is not required to fund the actual budget gap will be
available for investment and transformation, some of it has been earmarked for
specific projects. 
3.3 Savings Delivery 
3.3.1  In total £4.1m (68%) of the £6m target was achieved during the year. Appendix
2 provides detail on a project by project basis. The balance which has not been
delivered (on a recurring basis), totalling £1.9m will be carried forward into
2023/24. The table below summarises the provisional year end position:

Page 4

4 
3.3.2 
3.4 
3.4.1 
3.4.2 
4
4.1 
5
5.1   
2022/23 Savings    Year to 31 March 2023    
Target Achievement Balance %  
£' 000 £' 000 £' 000  
Fully Achieved 3,076 3,076 0  
Remaining Programme 2,733 818 1,915  
Non recurring 253 253 0  
Total 6,062 4,147 1,915 68% 
The remaining balances will carried forward into savings reports next year, it is
the case that several of these are likely to remain difficult to achieve, it is not
suggested that they are removed from the savings plan at this point in time.
Projects now considered to be fully complete will not be reported on further. 
One of the biggest challenges relates to the Cowal Community Hospital project,
this is being managed by NHS Highland and is subject to delay and additional
costs. The project is now underway with construction work expected to
commence in summer 2023. This project is key to delivery of a number of
savings on the plan. An appointment has also now been made to progress the
shared service catering model with Argyll & Bute Council, the work will initially
be focussed on the HSCP care home facilities.   
Reserves 
Earmarked reserves of £21.2m were carried into 2022/23. Of this total, which
included a general reserve of £682k, £16.5m was spent during the year. This
total spend figure includes a clawback of £6.0m relating to the covid-19
reserve. All covid related expenditure was fully funded by the use of the reserve
during the year. The General Reserve was fully spent: 
 Purchase of the Kintyre Care Centre and fees £330k;
 Completing the refurbishment of the residences in Lochgilphead 130k;
and
 The Learning Disabilities service restructure £220k.  
As is usual there were a number of funding streams received by the HSCP
during 2022/23 that were not fully spent during the year. These have added
£3.1m to the closing earmarked reserve figure. Additionally, the underspend is
also added to reserves which takes the year end balance to £16.9m The £9.1m
underspend carry forward will be earmarked for managing the budget gap
outlined in the HSCP budget for 2023/24 (£4.0m) and for investment,
prevention and transformation projects Appendix 3 provides further detail. 
RELEVANT DATA AND INDICATORS 
Information is derived from the financial systems of both partners. 
CONTRIBUTION TO STRATEGIC PRIORITIES 
The Integration Joint Board has a responsibility to set a balanced budget
which is aligned to the Strategic Plan. It is required to ensure that financial
decisions are in line with Strategic Priorities. The favourable financial

Page 5

5 
6
6.1 
6.2 
6.3
performance in 2022/23 presents an opportunity for service
transformation and investment in strategic priorities going forward. 
GOVERNANCE IMPLICATIONS 
Financial Impact – the underspend will carried forward and will enable the
HSCP to avoid requiring any additional funding to cover its budget gap in
2023/24. 
Staff Governance – None directly from this report but there is a strong link
between HR management and delivering a balanced financial position. 
Clinical Governance – the in-year reduction in resources to support
Primary Care Improvement may have Clinical Governance implications. 
7. 
7.1 
8.
PROFESSIONAL ADVISORY 
Professional Leads have been consulted with in respect of the implications of
the budget and savings programme. 
EQUALITY AND DIVERSITY IMPLICATIONS 
8.1 None directly from this report. 
9. 
9.1 
10.
GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
None. 
RISK ASSESSMENT 
10.1 The favourable position increases the risk of future reductions in funding. The
figures outlined in this report are provisional and subject to external audit. 
11. PUBLIC AND USER INVOLVEMENT AND ENGAGEMENT 
11.1  None directly from this report, engagement on activities relating to savings and
transformation forms part of the project plans where appropriate. 
12. CONCLUSIONS 
12.1 
12.2 
This report provides a provisional summary of the financial position for the
2022/23 year. The outturn is better than expected. It is anticipated that the
underspend will be carried forward by the HSCP into 2023/24 and will be used
to fund the budget gap and enable important investment and transformation.   
Good overall progress has been made with the savings programme and £4.1m
in savings (68% of target) was delivered. There will be a number of projects
carried forward into 2023/24 and these will have to be progressed in addition
to managing the new savings plan.

Page 6

6 
13. DIRECTIONS     
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required √
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland
Health Board 
APPENDICES:
Appendix 1 – 2022/23 Provisional Outturn
Appendix 2a – Fully Achieved Savings Forecast Outturn for 2022-23 
Appendix 2b – Live Savings Programme
Appendix 3 –  Reserves 
AUTHOR NAME: James Gow, Head of Finance and Transformation 
EMAIL: james.gow@argyll-bute.gov.uk