Report to:  Integration Joint Board
Title of report:  Joint Strategic Plan: Year One Monitoring: Engagement 
Presented by: Kristin Gillies, Head of Service Strategic Planning,
Performance and Technology
Date: 16 August 2023 
The Integration Joint Board is asked to:
 Note the Engagement Report and discuss the recommendations on utilisation
and incorporation of the feedback into the planning process. 
1. Executive Summary: 
1.1 Argyll and Bute Integration Joint Board approved Joint Strategic Plan (JSP) to
cover the period April 2022 to March 2025, the JSP was launched in March
2022. 
1.2 The JSP is a high level strategy which sets out our vision, strategic objectives
and priorities. The JSP is closely linked with the Joint Strategic Commissioning
Strategy (JSCS) which was approved in March 2022. 
1.3 A paper was presented to SLT/IJB in May 2023 with the Year One Monitoring
Report which included a commitment to manage progress against the priorities
and to further community engagement. 
1.4 This paper presents the JSP Engagement Report following engagement with
communities and online covering the period April to June 2023 and provides
recommendations on how the report will be utilised. 
2. Detail of the Report: 
2.1 The HSCP is responsible for the planning and delivery of high quality health
and social care services to and in partnership with the communities of Argyll
and Bute to achieve the National Health and Wellbeing Outcomes (NHWBO)
and the Children and Young People Outcomes. 
2.2 The methodology used for the JSP was agreed by the Strategic Planning Group
(SPG) and involved each of the strategic leads completing a template detailing
how their actions progressed over the time period of the last JSP, what
challenges they faced including the impact of Covid, their objectives and
priorities over the next three years.

Page 2

2.3 There was a decision made by the SPG that quarterly monitoring would be too
onerous, however given that is essential to monitor progress annually and to
review for any changes to priorities the Planning Team developed a template
to be sent out to all strategic leads which asks for updates, challenges and
barriers to meeting the Year 1 priorities and to give the opportunity for strategic
leads to revise Year 2 priorities to ensure they are still appropriate and
achievable and linking to the financial strategy. This was presented to SLT/IJB
as the JSP Year One Monitoring Report. 
2.4 There was a further commitment that engagement would take place within
communities and with invited special interest groups to understand service
experience and to triangulate this with the JSP Year One Monitoring Report. 
2.5 In line with the HSCP Engagement Specification, the aim of the engagement
was to: 
Consult Obtaining feedback to inform development and/or
improvement
Involve Engaging stakeholders in the process, ensuring their
concerns and aspirations are listened to, understood and
considered.  Providing feedback on how their input
influenced the decision 
2.6  A single Engagement and Communications Action Plan was developed to
ensure that everyone has the opportunity to let us know how A&BHSCP are
doing, now that we are one year into the Joint Strategic Plan. Community Drop
in events were held throughout A&B with an online blog and an online event
taking place as well as a survey to attempt to include those living in remote and
island areas. The engagement was around the four priority areas and what we
are doing well and what could we do better. 
2.7 While there were overall themes which came from the feedback, there were also
distinctive themes and challenges from each of the areas. The Carer’s centres
were heavily involved in some of the areas we visited. 
2.8 The main themes were: 
 More involvement in communities and consult alongside provider events
and community development trusts as there is a perceived lack of visibility
in communities
 Many barriers to choice and control including stretched services and lack
of choice
 Utilise community hubs/spaces
 More and better range of carer’s breaks
 Lack of patient transport
 Prevention for mental health
 Specialised services and specific social work team for children with
disabilities including autism 
2.9 On approval, we will publish this report and have suggested recommendations
below. The Engagement Report is attached at Appendix One.

Page 3

3. GOVERNANCE IMPLICATIONS 
3.1      Financial Impact  
No Financial Impact 
3.2      Staff Governance  
No Staff Governance Impact 
3.3      Clinical and Care Governance  
Included within the Joint Strategic Plan 
4. EQUALITY & DIVERSITY IMPLICATIONS
As there is no change in policy an equality impact assessment is not required. 
5. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
No impact on GDPR or current data sharing agreements. 
6. RISK ASSESSMENT
Impact on strategic and operational risks will be assessed within existing risk
assessment processes. 
7. PUBLIC & USER INVOLVEMENT & ENGAGEMENT   
Engagement Report. 
8. RECOMMENDATION 
We would ask Board to note the following:
 Each areas feedback will be presented to Locality Planning Groups (LPG)
and incorporated into any LPG Action Plans 
 Service Transformation will take into account the feedback and ensure that
all suggested actions are considered
 Projects and Operational Plans within the HSCP are recommended to take
cognisance of the feedback
 The feedback should influence the Commissioning Strategy, Carer’s
Strategy and Prevention Strategy