0
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24 
ARGYLL AND BUTE HEALTH AND SOCIAL
CARE PARTNERSHIP (HSCP) WINTER PLAN 
2023-2024

Page 2

1
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Introduction 
This report provides a summary of the overall winter plan for the Argyll and Bute Health and
Social Care Partnership (HSCP). The plan spans the period from 30 November 2023 to 1 April
2024. The report highlights specific elements of planning and is intended to both guide work
streams and provide assurance for relevant Boards. The plan is a whole system health and
social care plan, recognising the interdependencies of the system to meet the needs of the
local population. It is an annual national planning requirement and provides assurance that
the system and partners have the necessary measures in place to deliver health and care for
the local population during winter months.
Background
The HSCP system faces an extremely challenging winter. Locally and nationally, health and
care systems are experiencing significant operational pressures across many of their
services. Some patients are experiencing delays in accessing both planned and unplanned
healthcare, despite the best efforts of our workforce. There has been little/no reduction in
operational pressures over the summer months and providers are entering winter with
significant capacity pressures (availability of workforce and service capacity) across a
number of service delivery areas. 
The partnership is experiencing higher levels of vacancy and staff absence in both NHS and
local authority posts against a pre-COVID baseline(s). This is particularly challenging where
vacancies impact on skillsets which are critical to whole system working such as District
Nursing and Social Worker (i.e. Mental Health Officer) specialisms. Above expected vacancy
levels across several pinch point roles continues to drive overspends in bank and agency
staff usage that further pressurise depleted HSCP budgets.
In addition to the current pressures, we face a range of hard to quantify risks such as the
potential for further Covid-19 pressures, high incidence of flu cases, increases in respiratory
illnesses and the impact of the cost of living on both our workforce and our patients. 
Scottish Government has described the actions they expected all systems and providers to
take to increase capacity and operational resilience in planned, urgent and emergency care
ahead of winter. 
A review of winter planning processes and priorities has been undertaken in early autumn
2023. Our winter plan is set out in a format which considers:
1. Current Position: An outline for services, describing the current position regarding
system pressures and preparatory actions we will undertake to mitigate for these, and;
2. Action Plan: An action plan setting out the specific whole system actions we will
undertake to support and manage winter pressures. The whole systems action plan sets
out a description of the action, the intended impact of each action and how we propose
to measure the successful delivery of each action.

Page 3

2
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Table of Contents
Introduction ................................................................................................................................ 1
1. Overarching Principles and Governance ................................................................................ 3
2. Resilience Preparedness ....................................................................................................... 4
3. Infection Control - Seasonal Outbreak ................................................................................... 6
4. Communication Plan ............................................................................................................. 9
5. Urgent and Unscheduled Care ............................................................................................. 11
6. Planned Care Services ......................................................................................................... 13
6.1 Professional Areas in Focus ......................................................................................... 14
6.2 Integrated Community Care Services ........................................................................... 16
6.3 General Practice ............................................................................................................... 17
6.4 Hospitals .......................................................................................................................... 18
6.5 Children and Families ........................................................................................................ 19
6.6 Mental Health Services ..................................................................................................... 20
6.7 Care Homes and Housing .................................................................................................. 21
6.8 Care at Home .................................................................................................................... 23
7. Workforce .......................................................................................................................... 25
8 Finance and Resources ........................................................................................................ 27
8.1 Digital Support ................................................................................................................. 27
8.2 Technology Enabled Care (TEC) ......................................................................................... 28 
Version Control
Version 3.0
Date 6 November 2023
Accountable Officer Caroline Cherry, Winter Planning Executive Lead and Head of Service
Professional Lead Elizabeth Higgins, Associate Nurse Director – Professional Lead
Programme Lead Karl McLeish, Urgent and Unscheduled Care Programme Lead
Governance Route SLT 8 November 2023 (approved).
UUSC Programme Board  15 November 2023 (Approved)
IJB 29 November 2023
Status Final Draft 21 November 2023

Page 4

3
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
1. Overarching Principles and Governance 
Development of the Winter Plan 
The HSCP has developed its Winter Plan in conjunction with key stakeholders from across
the system to ensure that we can maximise our shared knowledge, resilience and resources
with a view to delivering safe and effective services throughout the winter months. Initial
engagement meetings were held in late autumn 2023. The plan has been developed taking
into account feedback and learning following evaluation of the Winter Plan for 2022/23. 
Governance 
Governance of The Winter Plan will be led by the Executive Lead for winter planning. A cycle
of system wide meetings are to be implemented to ensure we have a mechanism for
escalating issues and making decisions on critical issues, in a joined-up way, across system
partners. Along with regular data insights, we plan to operationalise a bespoke weekly data
file which facilitates the monitoring of/responding to emerging risks, trends and compliance
against agreed actions. The progress of the plan, together with risks and challenges, will be
reportable to the NHS Highland Urgent and Unscheduled Care Programme Board and
Clinical Care Governance.
We recognise that there will be challenging decisions to be taken over the course of this
winter and robust governance processes will ensure a mechanism to do that in a way that
considers the needs of our entire population, and the needs of staff working across both
health and social care.
This plan is considered in line with the following key overarching principles:
 Enhancing Community Services and Planned Care.
 Optimising discharge home as first choice, ensuring patients are discharged as soon as
they are medically fit, wherever appropriate and enhancing care in the community to
reduce unmet need and associated delays.  
 Avoiding admission with services developed to provide care at home across 7 days,
hospital at home, discharge to assess, rapid access to assessment and a single point of
access for health and social care (including technology and digital solutions).
 Reducing attendances by managing care closer to home or at home wherever possible
including community step-up facilities for assessment, reablement and rehabilitation,
prof-to-prof referral services, support for OOH, managing long term conditions to avoid
unnecessary exacerbation utilising digital and remote monitoring where possible. 
 Sufficient staffing across acute, primary and social care settings, including over the
weekends and festive period, with access to senior decision makers to prevent delays in
discharge and ensure patient flow. This includes recruitment and wellbeing priorities.
 Surge Capacity with the ability to flex up capacity when required including a surge plan.

Page 5

4
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
2. Resilience Preparedness 
Partnership Working 
Structures are in place via planning and performance to ensure that the HSCP works
collaboratively with all partner organisations, including in Greater Glasgow and Clyde and
System Resilience leads. Care at Home and Care Home Assurance functions are in place, on
a multi-disciplinary team basis, with clear escalations and protocols for risk management.
Daily Huddle meetings will take place at system level and can be adjusted in line with
demand. Any escalations relating to workforce/capacity are logged, directed and managed
via that process.  Weekly System Pressures Oversight Group (and by way of this, direct
access to SLT) is in place. Heads of Service and Professional Leaders from across the HSCP
are core attendees. These will link very closely with acute/hospital based ward
rounds/virtual wards to ensure flow is maximised and maintained, with appropriate
escalation management where required.
Business Continuity
Business Continuity Plans are in place across all areas and services. A priority piece of work
is underway to ensure that these are updated, visible and practicable. This work is due to be
finalised by 30 November 2023. Links with the Local Resilience Partnership (LRP) are clear.
There is also wide engagement with multi-agency partners through the Local Resilience
Partnerships in Argyll & Bute, with a particular emphasis on Caring for People arrangements
across our areas of responsibility. 
Operational Management and Local Plans
Management structures across the HSCP have led on the development of local winter
delivery plans, which are calibrated to respond to both area-based pressures and system
priorities. These local planning processes include a focus on key community, primary care,
acute, mental health and social care services to address the expected and unexpected
challenges in demand across the winter months, reflecting on learning from experience of
last winter. 
As in previous years these locality plans are expected to consider the following areas:
 Staff rotas including Public Holiday Cover for health and social work/social care (as per
agreed NHS and Council Public Holiday Rates).
 Virtual wards of multi-disciplinary standard including SAS input where possible.
 Business Continuity Plans for each site.
 Monitoring of unmet need protocols are in place (where people are waiting for care at
home).
 Vulnerable patient lists and associated planning is updated, with processes to access this
list in the event of system failure. Ensure interface with OOH teams.

Page 6

5
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Capacity Surge Management
All community services, community hospitals and the RGH have very limited capacity to
offer a response to surge escalation, in the form of contingency beds and limited flexibility
in staffing resources. The focus for A&B will be on effective approaches to admission
avoidance and bolstering care at home/within a homely setting where appropriate.
Continuous flow models, including effective discharge without delay are a critical focus for
the HSCP. Further work streams, including intermediate care beds will also be critical to
managing surges in capacity and demand. 
Adverse Weather Policy and Planning
NHS Highland/Argyll and Bute Council has an adverse weather policy in place which serves
as an overarching guideline for all managers and teams. Service impact assessments and
business continuity plans will also outline appropriate responses to enact the policy, and
respective timescales. Managers are advised to access and revise the policy provisions.
Adult Support and Protection
All protection functions are in place and are reviewed through professional leadership and
forums such as the Adult Protection Committee. A clear escalation process is in place to
manage pressures and provide a responsive service. This is a key priority. 
Unpaid Carers 
There are 6 Organisations providing Carer Support across A&B, with offices based in; Oban,
Helensburgh, Dunoon, Lochgilphead and Campbeltown. Carer support workers are also
physically based on; Mull, Tiree, Islay, and Bute with outreach support covering the other
remaining islands. Across the 6 organisations there are 80 FT/PT staff who provide Carers
support, with one current vacancy. This vacancy is for the Isle of Coll and will be re-
advertised. The vacant post is currently covered by the team in Oban.  
Over 2,000+ Carers are registered with Carer Organisations. Information can be and is
quickly shared with Carers via email and social media posts. Carer registrations have grown
since last winter, meaning more carers are now accessing the support available.    
Adult Carer Support Plans and Young Carer Statements are completed by Carer
Centres. Emergency planning is discussed with every Carer as part of ACSP/YCS. Information
regarding Carer Support has been shared with GP practises, raising the awareness of
available local services.    
Carer centres are creative about increasing the choice of groups that carers can access;
these groups enable Carers to meet other Carers for peer support.

Page 7

6
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
3. Infection Control - Seasonal Outbreak 
A key priority for the HSCP is to undertake a robust approach to vaccination and infection
prevention control in order to:
 Minimise seasonal influenza transmission/Covid-19.
 Minimise the risk and impact of outbreak and transmission on patients and services. 
Vaccination Programme – Seasonal Flu
The winter vaccination programme for commenced in September 2023 for seasonal Flu. A
high percentage of people across our population will be eligible for vaccination - we aim to
offer all those eligible an appointment by the 11th December 2023, however, as flu is
seasonal, this will continue to be offered until the end of March 2024. The flu programme
will include: 
 All school age young people, those aged 2-5, 5-16 (and those aged 6 months to 2 years
who are at risk).
 Adults aged 50 and over and those aged 16 and over at risk due to certain health
conditions will also be eligible. 
 A wide range of health and social care staff, with a focus on those delivering ‘front-line’
services.
 Teachers and Childcare Workers.
 Care Home Residents.
 Unpaid Carers and household contacts of those who are immunosuppressed.
 Those who are pregnant. 
Vaccination Programme – Covid 19 (Boosters)
In terms of the Winter Covid Programme, a further COVID booster is expected to be offered
to:
 Those aged 5 and over at higher risk.
 Adults 65 years old and over.
 A wide range of health and social care, prioritising those who deliver ‘front-line’ services.
 Unpaid Carers and Care Home Staff. 
Delivery 
The Seasonal Flu and COVID vaccinations programme is delivered via a mix of scheduled
appointments, drop-ins and peer vaccinations. Availability/communications are made
available to all staff and teams. In addition to this the programme will be delivered through
the following methods: 
 Appointing of over 75s by the National Scheduling Team.

Page 8

7
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
 Prompts to all others who are eligible from the National Scheduling Team:
o Access is given to a national booking portal. Clinics are available in all Argyll &
Bute community hospital settings. There are also local community clinics
accessible to all staff including non-hospital based.
 Drop in clinics for those aged 2-5.
 School age children will receive vaccinations within the school setting. School age
children will be offered the flu vaccine at school and younger children at children’s
community clinics. Community pharmacies will also offer the Flu vaccine to older people
and those at higher risk from flu including those with well controlled asthma. 
 Vaccination Clinics are being held close to GP surgeries.
 HSCP Community Teams will provide a service to those who are unable to attend
community vaccination centres and will support care homes 
 Maternity services will offer pregnant women the flu and COVID vaccines. 
 For staff: The flu vaccine programme will be publicised through local managers, pay
slips, NHS/Council Intranet site, and HSCP Bulletins. 
Infection Prevention Control 
From a staffing, services and resources perspective, surges in infection outbreak which
impacts capacity would be anticipated, monitored and managed via the system huddles and
system pressures oversight group. This would include end-to-end management, with multi-
professional input, from onset of outbreak through to the implementation of lessons
learned. There are close links with established communication mechanisms and business
continuity plans. A formal process map is to be agreed to support and standardise local
process of escalation and management. 
Cluster management policies are in place and are accessible on all locations. Covid
prevention requirements, i.e. face coverings as per guidance, reducing crowding in
departments, hand hygiene, cough etiquette, social distancing is in place.
Care Home and Care at Home Guidance is managed through local process management
protocols, and adheres to national guidance.
Increased use on non-face to face appointments/contacts can be used to manage outbreak
where appropriate. Visiting would be restricted where required, and safe staffing
arrangements would be held in review in line with business continuity plans. 
In summary our key actions for winter are as follows: 
Summary of Key Actions for Infection Prevention Control:
 Flu and Covid-19 vaccination programme implemented across the area as a part of preparing for
winter, managed through local vaccination group.
 The majority of individuals eligible for flu immunisation should be offered the opportunity to be
vaccinated during the period Sep-November 2023, though it is noted that clinics may be

Page 9

8
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
required into February-March 2024.
 Majority of staff will be offered the opportunity to be vaccinated at their place of work, or as
close as possible.
 Care Home residents, clinically vulnerable groups and front line staff are prioritised.
 Care home residents vaccinated at care homes.
 Consideration should be given to undertaking targeted immunisation campaigns in areas of high
flu incidence & low vaccine uptake.
 In the event of a flu outbreak on any site there will be further promotion of staff flu vaccination
and encouragement of uptake within those teams (and those affected more widely).
 Winter infection Prevention and control guidance, outbreaks and management is to be a core
agenda item at system meetings – it is an expectation that all relevant guidance is proactively
promoted and adhered to within local area teams, and that escalations  are managed in close
collaboration with Infection Control and Public Health colleagues.

Page 10

9
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
4. Communication Plan 
Communication and public messaging is central to our 2023/24 winter plan. There are a
number of key areas of focus within to our communication and engagement plan for winter
2023/24. These are as follows: 
Internally Focussed Communication:
 Governance and Management Structure – we will work closely with winter planning
governance groups and Planning and Performance to effectively adapt messaging based
on developing service needs. We will strive to ensure that our messaging remains as
responsive and current as possible. 
 Staff Communications - we will continue utilise internal communications to staff e.g.
core briefs and staff social media pages. We will also make extensive use of the intranet
to provide information and resources for colleagues across Argyll and Bute concerning
winter planning and management. We will endeavour to facilitate targeted
communication aimed at those who are most impacted by winter pressures, i.e. those
working in isolated, remote and/or rural communities, in circumstances such as adverse
weather, where connectivity may be reduced as a result. 
In addition to standard winter messaging, we will focus on messaging to support
attendance avoidance and early discharge of patients wherever possible, alongside
promoting the uptake of power of attorney, self-management materials and
Technologically Enabled Care (TEC). We will also continue to promote our Flow
Navigation Centres (via NHS 24) and vaccine programmes, supporting Right Care Right
Place messaging to our workforce and service users. 
Externally Focussed Communication: 
 Public Messaging – Winter Planning and Urgent and Unscheduled Care management has
a critical dependency on effective public communications. In line with national Scottish
Government campaigns, we will continue to run local messaging to support national
campaigns. This includes our ‘Right Care, Right Place’ campaign for urgent and
unscheduled care, where we are actively promoting alternatives to attendance at A&E.
We will also deliver strong public messaging around the importance of the vaccination
programme for both Flu and the COVID vaccination booster.  We will continue to raise
awareness around power of attorney. 
 Patient and Public Feedback – We will continue to facilitate patient and public feedback
and this will be utilised to help shape and focus our key public messaging throughout the
winter programme. Engagement with key communities will continue, via our focussed
worksteeams, Locality Planning Groups (LPGs).

Page 11

10
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
 Partnership Working - We will continue to work closely with community partners,
including Primary Care, Mental Health and Local Authority colleagues, to ensure a
joined-up approach to system messaging and communication. We will continue to
engage Third Sector partners in order to maximise our ability to coordinate and share
information, respond effectively to emerging local challenges and help facilitate
resolution where possible. 
In summary our key actions for winter 2023/24 are as follows: 
Priorities for Internal Communication:
 Ensure robust and consistent membership from communications at relevant system forums.
 Agree and establish clear roles, responsibilities and escalation structures. Within this approach
we will agree and action communication activity according to agreed priorities.
 Articulate clear process for authorising communication internally and externally.
 Development of single implementation plan/schedule of outcomes from changes, with
associated information on go live dates, governance and SRO/Sponsors
 Every plan for change implementation as part of winter planning to include staff communication
as an implementation step
 Recommunicate the roles and functions of Gold, Silver and relevant Bronze meetings
 Review and refresh Intranet materials for staff relating to safety, pathways, reference materials,
etc.
 Ensure Argyll And Bute HSCP council employees receive the same messages as NHS Highland
employees simultaneously (N.B with appropriate caveats)
 Continue to work in a system-focussed way to adapt communication for both staff and service
users in a way which is responsive to changing service pressures and needs. 
Priorities for External Communication:
 In partnerships with other providers review and refresh materials distributed in health and social
care settings (posters, leaflets, etc.).
 3rd Sector providers briefed/engaged in implementation of the changes
 Continue to deliver campaign ‘Right Care Right Place’ targeted messaging, to ensure
communities are able to make greater use of alternatives to attendance and admission. This
includes the promotion of pharmacy and self-management.
 Continue to develop and build on our public messaging campaign about the importance of being
vaccinated for both Flu and COVID from 2022/23.
 Continue to develop and build on our public messaging around Power of attorney to increase
awareness of the importance of having this in place.
 Every plan for change implementation as part of winter planning to include public
communication as an implementation step.

Page 12

11
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
5. Urgent and Unscheduled Care 
Urgent and Unscheduled Care pressures continue to be considerable at a National Level.
Within A&B HSCP our redesign of urgent and unscheduled care continues, in line with the
Scottish Government Collaborative for Urgent and Unscheduled Care. This is intended to
transform the way in which people access urgent and unscheduled care, enabling patients
to receive the right care at the right time. 
Key priorities that will make the greatest impact during winter 2023/24 includes:
 The reduction and/or avoidance of admissions – including signposting and redirection
(of those whose care requirements are not an emergency) to more appropriate and
safer care, closer to home, by optimizing clinical consultations through telephone and
virtual ‘Near Me’ consultations. Those who require a face to face appointment will have
their attendance scheduled, where appropriate and possible,
 Increased virtual capacity - to support the assessment of patients at home or within a
homely setting, avoiding the need to attend services. Increased capacity for virtual
monitoring and ongoing treatment, preventing admission.
 Focus on Hospital at Home provision, where available.
 Supporting ‘Out of Hours’ (OOH) care – sustainable, responsive, safe provision.
 Optimising flow - within our hospital settings, through the embedding of our DwD
programme, including effective planned date of discharge management. Reducing
length of stay on admission – increasing the number of patients on a rapid assessment
and short stay pathway, focussing on lower risk – high impact presentations supporting
safe and early discharge home 
Discharge without Delay (DwD)
As part of the redesign of Urgent and Unscheduled Care programme we are in the process
of fully reviewing and implementing the DwD process within our inpatient areas. Our key
priority arears for DwD over winter months are to:
 Limit hospital length of stay (LoS) - to what is clinically and functionally essential,
getting patients’ home at the earliest and safest opportunity, with the right care and
support in place. This links with step down and discharge to assess frameworks.
 Improve  and expedite the patient journey, from the initial point of a hospital
admission, via effective access to services, planning and implementation of resources to
support ongoing care at home, or in a homely setting, where needed. 
 Preventing delays through early and effective discharge planning which includes robust
and standardised approaches to all areas assessment and communication – including
key aspects such as financial planning and AWI processes.
 Ensure appropriate escalation and management structures are in place to support
resolutions to any barriers as they arise.

Page 13

12
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
The immediate focus ahead of winter is to support care services to realise full resource
potential and fully implement effective discharge with minimum delay. This includes the
procurement of additional short-term resources where required.
Out of Hours Provision (OOH)
The Out of Hours service is working effectively to provide access to urgent care during out of
hours periods. As we approach winter months, a number of key system pressures are known
which present a risk for sustainable out of hours provision. Beyond rurality and transport
issues, other significant risks include increases in unplanned attendance, breakdowns in care
packages, access to pharmacy and increasing needs relating to the management of palliative
care and complex presentations. There is also a priority need to focus on/refresh Key
Information Summaries and Future Care Plans, to ensure effective OOH and partnership
working and care. 
Priority Actions for Admission Avoidance and Signposting 
 Continue to promote access to Flow Navigation Centre for Urgent Care.
 Continue to prioritise attendances for urgent/emergency care as scheduled attendance.
 A focus on our ability to receive and effectively manage referrals from NHS 24 & schedule face to
face appointments for urgent care in acute settings as required.
 Continue to promote and facilitate access and triage through 111, 24/7.
 Maintain a clear focus on supported self-management - Clear and concise public and staff
information – ensure appropriate co-production with Comms team.
 Continue to drive worksteeams which expand the role of the Third Sector/localised support.
Priority Actions for Virtual Capacity
 Ensure contingency arrangements in place to support patient consultations from home etc.  if
required – this will be critical in the event of adverse weather.
Priority Actions for Out of Hours Care
 Ensuring that the Professional to Professional line is available OOH to all pharmacists,
paramedics etc. and is well used throughout the year.
 Ensure OOH clinicians have pan Highland ECS access. NHS24 Patients appointed via Hub.
 Ensure that emergency Social Work Service are in place for all public holidays and OOH periods
as usual. Referral is direct to Emergency SWES. 
 Ensure that all relevant paperwork is in place; including the prescribing of ‘just in case’
medications (ensure that the medication is in the house, rather than in a pharmacy).
Priority Actions for Optimising Flow 
 Prioritise the use of Technology Enabled Care (TEC) including ‘’Near Me’’ – ensure process & kit
is available in A&E ensuring that technology solutions for urgent care are optimised.
Priority Actions for Discharge without Delay
 A pathway which has resilience, resource and governance to meet anticipated greater demand
from Winter Pressures-monitor weekly through the Winter Planning Group.
 Ensuring that Planned Date of Discharge (PDD) is implemented and effectively managed through
virtual wards and board rounds (including clear escalation strategies).
 Continue to promote the role of/inclusion of unpaid carers and/or carers’ services in discharge
planning.

Page 14

13
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6. Planned Care Services 
An integrated approach to community health and social care planning for winter supports
and maintains capacity for Community Hospitals, Primary and Secondary care services and
enables patients to remain in community settings where clinically appropriate. This
approach should focus on initiatives which preserve and prioritise capacity for those most in
need, under the principles of ‘Right Care, Right Time’.
The HSCP envisages a repeat of the increased demand for community health and social care
services as experienced in previous years. Particular pressure around care demand for our
older adult population is anticipated, given the demographic profile for Argyll and Bute. In
order to achieve this work, particular focus is required from all areas of planned care on:
 Future Care Planning and Key Information Summaries (accurate content and access).
 Admission Prevention/Avoidance, including alternatives to admission and self-care.
 Single Point of Access, with effective referral coordination and management.
 Optimisation of Flow, Including integrated discharge management and resource
planning. 
Planned episodes of care are expected to continue across all community Outpatient Services
during winter months. Business continuity/service impact planning will be regularly
reviewed to take account of the risks of reduced capacity, increased admissions, etc. with a
view to minimising any associated impacts. 
Home care (Care at Home) provision continues to present challenge for occupancy and flow.
This will continue to be a pressure and runs risk of impacting on the need to cancel some
planned activity. H@H and the introduction of additional rapid response/care at home
capacity in Oban is expected to have an impact on reducing unmet need.
Close partnership working is currently in place via Discharge without Delay (DwD)
frameworks, including package funding decision making groups, to ensure that care needs
and resource are managed effectively within scope of capacity and matched need. This
includes core system partners but could be further expanded to include third and
independent sectors. Cases defined as Adults with Impairment (AWI) continue to present a
significant challenge for occupancy and flow across the system.
Overarching Priority Actions for Planned Care Services
 A refresh of core workload and adjust capacity in line with current need and resources.
 Increasing staffing for predicted peak times across the actual public holidays and weekends. 
 Identification of Service users who are defined as vulnerable and/or complex – these individuals
should be an area of key focus, with appropriate MDT arrangements to manage ongoing care.
 Palliative and End of Life Pathways and Caseloads, in all areas, should be reviewed, with
appropriate contingency plans in place to manage increased pressures which may result due to
seasonal outbreak and/or the impacts of adverse weather.

Page 15

14
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.1 Professional Areas in Focus 
Nursing 
The focus for nursing workforce as we approach winter 2023/24 is on quality and safety.
Falls prevention within hospital and homely environments, with improvement work
supported by Lead Nurses is a key area of work. In addition to this work, the roll out of Daily
Care Plan in Inpatient areas is moving at pace to enhance and maintain quality care delivery
and assurance. Work will also focus on tissue viability training and standards of practice to
reduce risks around pressure ulcers for patients in hospital and at home with restricted
mobility. Infection Prevention and Control Nurses (IPCNs): Ongoing training programme in
preparation for winter, including continued support from IPCNs in the management of
outbreaks. 
3 Key Challenges
1. Recruitment generally but also to key leadership (SCN) posts.  
2. Maintaining quality with the level of system pressures. 
3. Staffing wellbeing and morale. 
3 Priority Actions
1. Expand International Recruitment to more areas with A&B. Review hard to recruit roles and
identify viable alternatives. 
2. Targeted support from Lead Nurses to support quality agenda. Also planned QI support for
TV in high prevalence Acute areas 
3. Learning from Development Events - share and spread. Wellbeing challenges such a bespoke
Step Count Challenge.   
Allied Health Professionals
Focus on surge and real-time staffing through described escalation routes, including short-
term increases to staffing by utilising winter pressures funding. Continue to focus attention
around falls in in-patients units, including a meaningful activity project on all wards to
increase activity, reduce deconditioning/falls, as well as increasing purposeful occupation
and reducing distress for patients during their hospital stay.  Refresh the response to
uninjured fallers in community by our newly appointed Lead AHP alongside system partners.
Continue to provide AHP leadership on in the HSCP’s Living Well programme with
recruitment to posts to support proactive frailty prevention work and increase community
rehab and wellbeing programmes, with expected reduction in primary and secondary care
visits, and increased levels of physical activity and independence in our communities.
3 Key Challenges
1. Recruitment and staffing gaps in very small teams.
2. Lengthy waiting times in community with lower priority work being particularly impacted.
3. Staffing wellbeing & morale.
3 Priority Actions
1. Progress proactive early intervention work at pace.
2. Roll-out of work planning tool to ensure staff have appropriate work plans and time for CPD.
3. Roll-out of digital dictation across teams at pace.

Page 16

15
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Social Work 
Within Social Care services there has been significant amount of work undertaken in relation
to smarter commissioning within the HSCP and Care at Home providers, working in
partnership to deliver essential services. Challenges to this, which are also seen nationally,
are the recruitment and retention difficulties faced across the sector. Smarter
commissioning enables daily oversight and scrutiny of required services and actual delivery.  
Following the agreement to implement a Central Adult Support and Protection Team, the
operational model of Adult Social Work is being reviewed and this work is ongoing. A review
framework has been drafted for care homes and work is underway to develop a review
framework for clients in receipt of social work and or social care support in the community.
Work is currently underway to develop a programme to increase our qualified Social Work
Workforce over the next 4 years per the workforce projections. 
Interface with the Third and Independent Sector
The independent sector (mainly care homes and care at home) are engaged for winter with
the HSCP through provider meetings whether one to one or through, for example, the Care
Home Task Force. Third sector initiatives for winter such as warm rooms, sits within the
governance of the Local Authority, but small amounts to support warm boxes for older
people can be made available
Medical Workforce
There are currently 200 medical professionals working across Argyll and Bute. There are 120
GPs providing primary care - 50 of these are in REP (rural emergency practitioner) who also
contribute to Unscheduled/Acute /Rehab care in their community hospital roles. A further
10 work in unscheduled care across Oban and Dunoon. GPs continue to provide OOH
standalone services for Oban, Dunoon and the islands.
Increased demand over winter inevitably impacts relatively small teams, whose input is
needed across the traditional primary/secondary care interface. In RGH and mental health,
rotas are also reliant on very small Consultant teams, supported by a junior medical
workforce. Sustainability of services is considerably enhanced by multi-professional working
and ensuring that roles and skills are carefully planned and utilised to maximum impact.
3 Priority Actions: 
1. Review and ensure business critical protocols are updated, available and visible to on local and
on call managers. This includes a clear process to fill last minute gaps on rotas, especially for
junior workforce and GP OOH.
2. Efficient recruitment processes ensuring workforce availability- we have progressed recruitment
for REPs and need to see these people available to work ASAP and preferably pre winter surge.
3. Oban: ensure that staff responsible for admissions (juniors and locum Consultants, especially
those who are temporary or rotate) have a full understanding of hospital at home uses and
criteria, and other facilities to reduce need for admission. Also encourage ownership of
prevention of admission in ED nurses.

Page 17

16
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.2 Integrated Community Care Services 
Community Services are managed and delivered within 6 local areas:
Area Helensburgh and
Lomond
Cowal Bute Mid-Argyll Kintyre, Islay and
Jura
Oban, Lorne and
the Isles
Community Hospital Beds
(Contingency)
SLA GGC 11
(3)
8
(1)
15
(0)
10
(2) 
Islay
6
(0)
Mull
3
(0)
Rural General Hospital
(Contingency)     
LIH RGH
46
(6)
GP Practices*
(List Count)
5
24,185
8
21,690
8
21,125
8
23,207
Care Homes
No of Beds
4
169
4
141
2
15
1
16
2
56
4
118
*4 practices are not included as work is ongoing to evaluate list sizes. 
Key Challenges for Community Services: 
 Demography - A total population of 85,430 people with 26% were aged over 65. 11% of
people live 8.7% lived in the most deprived quintiles. Access to services, health
management, housing, and employment are among the highest ratings.
 Rurality – Argyll and Bute covers 691,000 hectares, and has 23 inhabited islands, making
it the second largest local authority and one of the most geographically complex areas to
deliver services within. 43% of the population live in remote and rural areas.
 Health Needs - In the financial year 2020/21, in Argyll and Bute HSCP, 24% of the total
population had at least one physical long-term condition (LTC).  4.5 in 10 of those aged
65 to 74, 6 in 3 of those aged 75 to 84 and 7 in 6 of those 85+ have at least 1 LTC. These
include: cardiovascular, neurodegenerative, and respiratory conditions, as well as other
organ conditions (namely liver disease and renal failure), arthritis, cancer, diabetes, and
epilepsy. among the people who have a LTC, 21% of those under the age of 65 have
more than one, compared to 50% of those aged over 65. 
 Transport/Access – sustainable delivery of services in remote and rural areas is an
existing challenge which is made more challenging by staffing gaps, adverse weather and
availability of public and emergency transport. 
Key Actions for winter 23/24: 
Community Services Priority Actions:
 Ensure that resource is maximised by holding system pressure in regular review and continuing
to signpost the public through the media, social media and online to the most appropriate
services for their needs and to ensure our wider public messaging campaign remains credible
and effective and aligned with pressures
 Undertake a review of district nursing hours to ensure alignment with GP practices.
 Ensure adequate equipment (including beds and mattresses) available in the community to
enable the management of more acute conditions at home and facilitate discharge without
delay. Private transport will also be agreed on a needs basis.

Page 18

17
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.3 General Practice 
As winter months approach, Primary Care, alongside other Community Services is at the
forefront of pressures, particularly General Practice and Community Pharmacy. Both
services are reporting ever increasing numbers of patient contacts and increasing
complexity and frailty within their communities.  It is also recognised that the geographical
and demographical challenges for Argyll and Bute are acutely reflected in Primary Care
service delivery - every Practice is different and there is no single solution for all.
Workload pressures are currently being experienced across the whole of the health and
social care system. Such pressures are expected to escalate during winter months.
Practices are asked to consider key priorities that will make the greatest impact during
winter 2023/24 which includes:
 The length of each clinical surgery and length of appointments.
 The mix of appointment types- face to face, video, telephone (this may differ between
days and between clinicians).
 The availability to pre-book appointments, and how far ahead this can/should be
supported.
 The knowledge and skills of administrative teams, who are often the most effective at
identifying issues and redirecting patients where appropriate.
 The Practice website(s), ensuring up to date/appropriate links for patients and to avoid
the need to call the Practice.
 The recognition that no practice is able to carry out everything in times of unusual
pressures - enable practices to prioritise within available capacity and use the escalation
framework to request exceptional departure from contractual activity.
 Consider use of extended hours/Saturday opening to enhance capacity where
appropriate and feasible (LES in negotiation) 
Key Actions for winter 2023/24: 
Priority Actions for General Practice:
 Continually review demand and capacity - allocate resource based on complexity and urgency.
 Focus on those most at risk of deterioration that require support and intervention.
 Focus on those at risk of admission to hospital, care home or significant risk in a community
setting e.g. self-harm, or requiring enhanced support package.
 Focus capacity where there is a clinical need for same day response, to reduce risk of demand
being deferred to the out of hours period and protect hospital resources.
 Delay some activities where this can be done without immediate significant adverse health
impact or impact on other parts of the system.
 Use of Pharmacy first and the advertising of Clinical Pharmacy opening hours during bank
holiday periods.
 Continue to facilitate and prioritise MDT/Partnership working to coordinate and focus resources.

Page 19

18
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.4 Hospitals 
Additional Winter Capacity
Our ability to create additional acute capacity by opening ‘winter beds’ is limited by the
availability of staff, in particular, registrant staff to provide the level of care and
rehabilitation required. 
Although this is carefully planned ahead of the winter period, the provision of true
additionality of resource into wards is extremely challenging. All community services,
community hospitals and the RGH have very limited capacity to offer a response to surge
escalation, in the form of contingency beds and resources. The focus for A&B will be on
effective approaches to admission avoidance and bolstering care at home/within a homely
setting where appropriate. Continuous flow models, including effective discharge without
delay planning are a critical focus for the HSCP. Further work streams, including
intermediate care beds will also be critical to managing surges in capacity and demand.
Alternatives to Admission and Admission Avoidance
A critical focus for the supporting the hospitals across Argyll and Bute is alternatives to
attendance at A&E and admission avoidance.  For Oban locality, this will include a focus on
the Hospital at Home pilot, which will aim to work with complex medical patients –
supporting them to remain in their own home rather than being treated in an Emergency
Department or Hospital ward. 
Flow Navigation Centre (FNC) arrangements are in place to respond to emergency
treatment needs, including appropriate signposting. Current local provision is in place to
direct medically urgent assessments to non-by-pass A&E departments for assessment by a
senior clinical decision maker. The majority of A&Es have Business to Business contracts
with an on-call GP link. Out Of Hours provision is in place. Routine cases are directed via
local Single Points of Access (SPOA) under business as usual arrangements. These are
allocated on needs-based priority to appropriate services. Self-care and attendance
avoidance is advised where appropriate. Examples of good practice for multi-agency Multi-
disciplinary working exist across A&B communities. 
Community responder services will also play a critical role in providing alternatives to
attendance, by way of appropriate signposting and alternative assessment and treatment
models. Services are developing improved access and responsiveness to non-injurious falls,
including supporting call outs to Care Homes. ‘’Call before convey’’ and ‘’Professional to
Professional Conversations’’ are also a critical focus to maintain flow throughout the winter
months. This aims to support referrals into community services and/or stabilise existing care
options as an alternative to conveyance, attendance and ultimately admission.
Where clinically appropriate, we will aim to provide remote medical consultations to
NHS24/111 patients. This avoids the patient having to attend in person, and frees up face to
face capacity for those with more urgent or complex needs.

Page 20

19
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.5 Children and Families 
Child Health Services
As winter months approach, Child Health Services, alongside other Community Services is at
the forefront of pressures. During winter pressures teams will continue to use the Traffic
Light Tool to prioritise delivery of the Universal Health Visiting Pathway. Our Allied Health
Professionals as well as Community Paediatrics teams continue to see an increase in
demand for services - in particular, Neurodevelopmental Assessments. In the approach to
winter, there has been a requirement to review demand and prioritise the need within
caseloads. All of child health teams are seeing an increase in presentation complexity within
the community. With the added pressure of a national shortage of ADHD medication,
recruitment struggles and an increase in complex presentations the need for considered
resource management is of vital importance. The uses of assistive technology for
consultations in remote and rural areas will continue to be utilised to extend scope and
maximise impact of pressured service areas. 
Key priorities that will make the greatest impact during winter 2023/24 includes
consideration of:
 Supporting professionals and increasing the range and types of care available to reduce
the risk of burn out and further pressures as a consequence.
 The mix of appointment types- face to face, video, telephone (this may differ between
days and between clinicians and client based needs).
 Ensuring a timely and robust model to reduce and manage waitlists and provide a
responsive and timely service according to complexity of needs.
 Remodelling of neurodevelopmental service to provide biggest impact to families and
communities
 Accessible self-help resources within HSCP websites.
 The recognition that no service can carry out everything in times of unusual pressures -
enable service to prioritise within available capacity. 
Key Actions for winter 2023/24:
Child Health Priority Actions:
 Continually review demand and capacity and allocate resource based on clinical priority,
complexity, and urgency.
 Focus on those most at risk of deterioration that require support and intervention.
 Continue to keep child safety central to all child health work.       
Continue to work collaboratively to meet needs of children and families
 Delay some activities where this can be done without immediate significant adverse health
impact or impact on other parts of the system.
 Continue to facilitate and prioritise MDT/Partnership working to coordinate and focus resources.

Page 21

20
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.6 Mental Health Services 
The challenges for Mental Health Services in relation to the winter period continue.
Particular pressure emanates from RMN nursing and MHO vacancies across the localities. In
addition, our Mental Health psychological therapies service continues to experience long
waiting times with current waiting lists at a 2 year wait for secondary care services, and an
additional waitlist for primary care mental health services. This pressure represents
significant challenges for the provision of timely and responsive interventions, and to step-
up care across the localities. Increasingly, Mental Health teams are focusing their limited
resources on preventative measures in order to minimise an escalation of crisis and
attendances presenting to A&E. Our Urgent and Emergency team continue to ensure that a
timely and robust response and assessment is available to appropriate patients.
Argyll and Bute Mental Health Services recognise the concerns around recruitment and are
committed to proactively developing more innovative ways to extend the reach of services
with the introduction of partner agencies, particularly in relation to accessing psychological
interventions; we are currently completing the commissioning of new partners to assist us
to deliver services across both primary and secondary care services. These approaches are
of particular focus in the approach to winter, and are aimed towards: 
 Promoting resilience for those patients with a mental health need by ensuring
appropriate models of care which support self-management and access to care at home,
 Ensuring a timely and robust model to reduce and manage waitlists, and provide a
responsive and timely service according to complexity of needs.
 Support discharge without delay, where there is a mental health component, by
facilitating appropriate care in the right place, at the right time.
 Supporting professionals and increasing the range and types of care available to reduce
the risk of burn out and further pressures as a consequence. 
Key Actions for winter 2023/24:
Mental Health Priority Actions:
 Ensure a timely pathway for access to a Mental Health Assessment if attending Emergency
Department, Police Scotland and SAS.
 Continue to focus on preventative measures, to reduce pressures on services and maintain
patient care in appropriate settings.
 Proactively manage ongoing recruitment issues, working collaboratively with relevant partner
organisations.
 Promote a joint-working, with innovative approaches to practice and shared responsibility
ensuring that people experiencing distress receive appropriate and timely response.
 Maintain a clear focus on the reduction in the number of crisis/emergency admissions.
 Maintain a clear focus on reduction in the number of people attending the A&E in crisis.
 Continue to work collaboratively in supporting with the resolution of AWI related difficulties –
assessment, discharge, placement and general care planning.

Page 22

21
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.7 Care Homes and Housing 
As at October 1st the Care Home Bed occupancy by area shows the following:
Helensburgh and Lomond
169 Beds 
147 Occupied
90% Occupancy
Cowal
156
137
87% Occupancy
Bute
(Included in Cowal Totals)
Northwood
Occupied
% Occupied
20
20
100%
Struan Lodge
Occupied
% Occupied
12
11
92%
Thomson C
Occupied
% Occupied
8
8
89%
Argyll C Centre 
Occupied
% Occupied
56
48
86%
Ardenlee
Occupied
% Occupied
33
22
67%
Palm Court
Occupied
% Occupied
7
6
86%
Hermitage House
Occupied
% Occupied
64
51
80%
Ardnahein
Occupied
% Occupied
30
28
93% 
Morar Lodge
Occupied
% Occupied
29
28
97%
Ash Grove
Occupied
% Occupied
65
52
95%
Mid Argyll
(Included in Kintyre Totals)
Kintyre, Islay and Jura
72 Beds
62 Occupied
83% Occupancy
Oban, Lorne and The Isles
118 Beds
89 Occupied
71% Occupancy
Ardfenaig
Occupied
% Occupied
16
15
94%
Gortanvogie
Occupied
% Occupied
16
10
63%
Eadar Glinn
Occupied
% Occupied
22
17
77% 
KCC
Occupied
% Occupied
40
37
92%
Tigh A Rudha
Occupied
% Occupied
12
6
50% 
North Argyll
Occupied
% Occupied
25
19
76%
Etive House
Occupied
% Occupied
59
47
80%
*Source: Care Home Assurance Data Reporting. Not all beds are able to occupied and numbers should be interpreted
accordingly in line with most recent data. 
Local Authority Owned Managed 
Privately Owned/Managed 
Overall bed occupancy for Local Authority owned homes is currently 104 out of 127 beds,
with 3 vacancies that can be filled. The remaining 23 vacancies are being reviewed. Overall
bed occupancy for Private and Independent Sector Managed Care Homes is 331 out of 388
beds, with 30 vacancies that can be filled. The remaining 57 vacancies are being reviewed.
Total bed occupancy is 435 occupied beds, from of an overall total of 515 (80 actual
vacancies and 33 vacancies that can be filled), giving an overall occupancy of 84% for Argyll
and Bute.

Page 23

22
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Care Planning
The majority of care homes across Argyll and Bute have a weekly review with a GP. Any
concerns or issues raised can be escalated. All care homes have their own future care plans
in place, and there is a lead nurse for care homes in place to advise on clinical issues. A
home first approach is in place to facilitate admission avoidance.
Occupancy and Resources 
In order to meet the known additional winter pressures, we are reviewing our care home
bed occupancy to explore potential capacity for winter bed surge planning. Approximately
33 additional beds may be available this winter, these have been included within the winter
plan costs as being opened on a spot purchase basis from December to March. Please note
the costs within the winter plan are for opening the winter surge beds only and do not
include the costs of the beds that remain open and have been historically been in place for
some time. 
Intermediate Care Options
Step up and step down care, or intermediate care options are currently being scoped at
pace. The HSCP will establish a working group to look at options for models of care. This will
be a key focus for HSCP winter planning/strategic development and will feature in the final
plan. Although Interim Beds (a side move with no rehabilitation whilst waiting for care at
home) are now not in scope as a formal offer, step down arrangements of up to 6 weeks are
in place and can be agreed to facilitate intermediate care where appropriate (and where
there is a realistic prospect of reablement and/or where the longer term care needs are
known, and are being proactively managed). 
Key actions for winter 2023/24 
 Care Homes: Monitored and assured through the Care Home Assurance process, communication
through the Task Force. 
 Weekly review of high risk health issues to be developed by the Associate Lead Nurse Care
Homes
 Interim care (where care at home is not available: confirm spot purchase arrangements with
existing care homes. Take up and use monitored through the Care Home/Care at Home
Assurance. 
 Scope potential growth and options for intermediate care through a SLWG.
 Staff and care home staff offered vaccination in situ
 At pace review of KIS and ACPs for all residents.

Page 24

23
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
6.8 Care at Home 
As at 31 October 2023, the following information relating to total clients and total care
delivery hours was available.
Helensburgh and Lomond
Grand Total Service Users: 306
Grand Total Average Hours: 3297
Percentage with 2 Carers: 16%
Unmet Clients/Hours: 6/99.5
Cowal
Grand Total Service Users: 130
Grand Total Average Hours: 1136
Percentage with 2 Carers: 25%
Unmet Clients/Hours: 5/39.5
Bute
Grand Total Service Users: 124
Grand Total Average Hours: 1594
Percentage with 2 Carers: 24%
Unmet Clients/Hours: 1/7
Service Users:
-
Average Hours:
-
Service Users:
-
Average Hours:
-
Service Users:
-
Average Hours:
-
287 3032.25 120 967.13 121 1549.5
22 264.75 12 160.25 3 44.75
Mid Argyll
Grand Total Service Users: 102
Grand Total Average Hours: 1503.5
Percentage with 2 Carers: 31.5%
Unmet Clients/Hours:
Kintyre, Islay and Jura
Grand Total Service Users: 177
Grand Total Average Hours: 1790
Percentage with 2 Carers: 22%
Unmet Clients/Hours:
Oban, Lorne and The Isles
Grand Total Service Users: 197
Grand Total Average Hours: 2412
Percentage with 2 Carers: 24.6%
Unmet Clients/Hours: 17/128.5
Service Users:
45
Average Hours:
594 
Service Users:
Kintyre: 42
Islay & Jura: 47
Average Hours:
456.75
370.25
Service Users:
Lorn: - 
Mull & Iona: 28
Tiree/Coll: 10
Average Hours:
-
393
69.75
52 659.5 Kintyre: 87  755.5 Lorn: 103
Mull & Iona: 9
Tiree: - 
1024.5
69.25
-
13 250 Kintyre: 7
Islay & Jura: 4
153
55.5
Lorn: 46
Mull & Iona: 2
Tiree/Coll: 2
803
22.75
38.25 
Internally Provided 
Externally Commissioned 
Direct Payments 
Summary of Care Hours and Delivery by Area
As at the end of August 2023, the Care at Home service was being delivered to 1036 people
in total, with 1004 of these people aged over 65 years. Services delivered per-week were
approximately 9572 hours across all types of delivery, across the HSCP.
Of this number, 111 people opted for Self-Directed Support – Option 1 (Direct Payment) and
were in receipt of approximately 1566 hours per week.
779 people received care from externally commissioned service – Self Directed Support
Option 3, delivering approximately 6546 hours per week.
172 people were in receipt of care delivered through internally managed services - Self
Directed Support Option 3, with approximately 1460 hours of service being delivered.
Overall, the average hours per person being delivered per week were 9.24 hours per week.
As at the 31 October, unmet need stood at a total of 40 clients with 382.8 hours unfulfilled.

Page 25

24
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Resources
The internal care at home service currently employs 86 permanent care staff with varying
contracted hours. There are also 67 casual/bank staff. The total workforce has
approximately 23% of staff aged over 60 years, with 27% of the carers aged over 60 years.
The externally commissioned services employ approximately 416 staff through 12
organisations.  All areas now employ mobile responder teams (Oban, Lorne and Isles
progressing through commissioning at pace as at 31 October 2023).
Key Challenges
As we move to winter 2023/24, the key pressures for care at home are:
 Unmet need – with a high percentage of newly identified clients requiring long-term
care at home provision (a high percentage require intensive support (i.e. 4x double-up
daily visits). The most significant pressure for unmet need centres on the Oban, Lorn and
Isles locality.
 Delayed discharge – as at 31 October 2023, 61% of current delayed discharges (21 of 34)
related to Care at Home.  Of the 21 delays relating to Care at Home, 57% (12) related to
Oban, Lorn and Isles locality.
 Recruitment/Accommodation – a number of posts remain vacant across Argyll and
Bute, for both registrant and non-registrant roles. Difficulties in recruitment are further
exasperated by lack of affordable/suitable accommodation in key areas of pressure,
such as Oban. A working group is reviewing this provision at pace. 
Key Actions for winter 2023/24
Priority Actions for Care at Home
 The recruitment and deployment of a mobile team for Oban Locality. Agency staffing is being
implemented in the interim to support/alleviate hospital pressures.
 Bolstering/additional support for responder teams to ensure appropriate use and ability to
provide holistic approaches to care – this in turn supports quality of care at home and ability to
maintain care in the home/homely setting.
 Interim/intermediate care options to both support admission avoidance and reduce length of
stay/support discharge.
 Future Care Planning and Key Information summaries to support winter plans for service users in
receipt of Care at Home.
 Focussed monitoring and review for Unmet Need through Care at Home assurance frameworks
– this incudes closer working with CRGs, DwD pathways and provider relationships.
 A rapid review of all Care at Home services, to ensure efficiency and high quality delivery (and
reduction in pressures for other services, i.e. hospitals and DwD).
 Reviews of packages of care – to ensure that input remains appropriate and that resource is
appropriately managed.

Page 26

25
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
7. Workforce 
At the end of March 2023, the HSCP employed 1,568 substantive staff (1,277wte). 53% of
staff held full-time contracts. Nursing and Midwifery held the highest numbers of vacancies
across all divisions, followed closely by Allied Health Professionals – this trend is echoed in
the table below.
Vacancies and Recruitment
The winter workforce plan considers the impact of winter pressures across the partnership.
As at 1 November 2023, the HSCP is operating with the following vacancies. These are
detailed for the entire division and then by service area: 
In response to the current challenges and pressures within all Health and Social Care
divisions, there have been a number of actions implemented which in order to ensure
quality care can be maintained and staffing vacancies can be recruited to.  A workforce
establishment tool process has taken place with our Community Team and our Specialist
Teams. The aim is to right size the workforce and is part of the preparation for the
enactment of the H&C Staffing Act. Other improvements related to this are: Real Time
Staffing implementation, including risk mitigation and escalation and the introduction of e-
roster which is currently being rolled out throughout the Board. International recruitment
within Mental Health of Registered Nurses (RNs) is ongoing. 
Growing Our Own RNs is also proving effective, with 24 nurses currently in various stages of
training via the Open University.  Similar initiatives are in place for Social Work and AHPs.
Board wide work on expanding Band 4 roles within more clinical areas is also a priority
focus. This includes a comprehensive review of roles, responsibilities, competencies and
training ahead of winter.

Page 27

26
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
Sickness and Planned Absence
The challenges of winter are carefully thought through and the planned mitigations have
been developed in collaboration with key stakeholders. Traditionally, staff availability is
impacted further in the peak winter months as a result of higher sickness absence levels. 
Key Actions for winter 23/24
Vacancies and Recruitment:
 Ahead of winter this year we are proactively working with Higher Education Institutions (HEI’s)
to develop a communication to students to promote working in HSCP roles during academic
gaps such as festive breaks and between placements. 
 Dedicated winter recruitment is underway, ensuring that additional resources are recruited to
facilitate the provision of increased capacity. 
 Ensuring Safe Staffing - Enhanced rates for key shifts and now sourcing agency locums for
outstanding remote & rural shift periods. Workforce provision under continual review.
 Consideration is also being given as to how we could further develop our staff bank to provide
support to all Allied Health Professionals (AHPs) and Registered Nurses.
 We continue to support colleagues wishing to retire and Return, with this now being managed
via the flexible working process. 
Staff Wellbeing
A range of staff wellbeing and mental health initiatives have been deployed and will be
maintained throughout winter. The HSCP has a focused culture and wellbeing group which
meets bi-monthly. Staff wellbeing is a priority for HSCP; both employing partners take an
integrated approach to ensure an ability to maximise the resources and support available. 
This forum is well supported, action focused and inputs and outputs are well
communicated.
A priority area of focus within our strategy is to ensure there are a number of preventative
interventions in place to ensure that our workforce has access to a range of services that
support and improve their physical and mental health.
Key Actions for winter 23/24 
Priority Actions for Staff Wellbeing:
 Continue to promote access to support through the Argyll and Bute Wellbeing Programme.
 Continue to prioritise clinical and management supervision frameworks so that colleagues
continue to have a safe space to escalate and co-manage any concerns.
 Ensure clear provision and routes of access for confidential support and access to counselling
services, etc.
 Remote Working – Ensure that appropriate arrangements are in place for remote working both
in terms of network capabilities and availability of hardware – this will be a critical action to
maintain safe staffing in the event of adverse weather.

Page 28

27
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
8 Finance and Resources
Allocation of winter funding is in place. A process has been established to collate and
approve requests for additional support, relating to the KPIs for winter planning, as set out
by Scottish Government. Ad-hoc requests will be agreed via established governance
channels and committed spend will be collated and submitted to Scottish Government as
required.
8.1 Digital Support 
As we move towards winter months, the HSCP’s E-Health function continues to complete
work to create an environment that supports flexible/remote and agile working as well as
ensuring that the core infrastructure is optimised to ensure it is effective to support clinical,
care and non-clinical services. 
The HSCP Team continue to work closely with Argyll and Bute Council’s ICT department to
ensure our social care and health staff have seamless access to systems and information as
well as improved communication across the health and care “technological organisational
boundaries” to deliver integrated care.
The prioritised programme of work in the winter period 2023/24 includes:
Digital Priority Actions:
 Federation of Microsoft Teams and 365 e-mail to provide seamless functionality re calendar
access “free busy” video and voice messaging and presence status across council and NHS
Highland instances so we are a single “connected organisation”. Second phase of this project to
be led by the digital office, which will include further exploration of using SharePoint between
365 tenancies.
 Eclipse phase 2. The project is moving towards Phase 2 with Discovery days scheduled for
October to support our four community health teams; Mental Health, Community Nursing,
Allied Health Professionals and Child Health. Discovery sessions with each of the community
continue, to ensure that the partnership agreement meets all the technical requirements of the
teams.
 Completion of business case to support the use of the North of Scotland Care Portal to include
both social care and health information from March 2023. – Ongoing.
 CIVICA data-sync is now in place and this means that all new clients added to Eclipse will appear
in CIVICA.
 Completed the electronic scanning of general medical records in Lorn and Islands Hospital RGH,
Mid Argyll Community Hospital and Integrated Care Centre and Cowal community hospital to SCI
store. Work continues to further enhance Electronic Patient Record to provide clinical staff with
faster access to enhanced clinical information.

Page 29

28
Argyll and Bute Winter Plan (v3 Final Draft) 2023-24
8.2 Technology Enabled Care (TEC) 
Technology Enabled Care plays a critical role in keeping people safe at home. Our remote
health monitoring and online CBT programmes promote supported self-management,
preventing illness or worsening of patients’ conditions and lead to improved longer-term
outcomes.
The Telecare service is vital in facilitating timely discharge from hospital and in preventing
admissions, important especially throughout the coming months as our hospitals face
winter pressures. The service also supports and evidence reviews of care package needs via
“Just Checking” service to ensure the correct level of care is provided to clients meeting
needs.
Key areas of focus for TEC for the winter period 2023/24 includes the following primary
areas of work:
 Increase Telecare provision, awareness and training, particularly among front facing
teams who support care at home, admission avoidance and timely hospital discharges.
 Expanding the use of ‘Just Checking’ to ensure delivery of the right levels of care and
support, in the right setting at the right time.
 Analogue to Digital – Progress project, ensuring readiness of the digital platform for roll
out.
TEC Priority Actions:
 Continue closer working with hospital sites, promoting Telecare team presence at board round,
virtual ward etc. 
 Identify referral patterns and provide familiarisation resources to increase awareness and referral
rates among staff. 
 Ensure purpose of Telecare is clear – response to emergency alarms and not a personal care service
or a replacement to Home Care.
 Ensure Just Checking is being fully utilised to support reablement and support decision making with
appropriate care packages, leading to improved outcomes.
 Ensure that clients who transfers to a digital line have continuity in service/remain supported with
Telecare. 
 Continue to test and work towards long term digital solution. 
 Establish and develop Near Me link from ED/MIUs with EMRS for clinical advice/patient retrieval. Set
up Near Me hubs on Islay, Iona, Coll & Tiree enabling patients to be seen virtually and avoid
unnecessary journeys.
 Transition to Connect Me system (remote health monitoring) and continue expansion of Silvercloud
cCBT programmes, conduct training and advertising. 
 Work with Mental Health to develop SOP for directing patients waiting for treatment into cCBT
programmes.
 Provide operational management with access to activity and trend information to assist performance