Page 1

1 
Integration Joint Board (IJB) 
Date of Meeting: 29 November 2023 
Title of Report: Argyll and Bute Winter Plan 
Presented by: Caroline Cherry, Head of Service, Health and Community
Care and Karl McLeish, Unscheduled Care Programme Lead    
The Board is asked to:
 Consider the winter plan for Argyll and Bute HSCP 
1. EXECUTIVE SUMMARY
This report provides a summary of the overall winter plan for the Argyll and Bute
Health and Social Care Partnership (HSCP). The plan spans the period from 30
November 2023 to 1 April 2024. 
The report highlights specific elements of planning and is intended to both guide
work-streams, provides assurance for relevant Boards and is consistent with the
Scottish Government Winter Planning checklist. 
The plan is a whole system approach, recognising the interdependencies of the
system to meet the needs of the local population. It is an annual national planning
requirement and provides assurance that the system and partners have the
necessary measures in place to deliver health and care for the local population
during winter months.
2. INTRODUCTION
Locally and nationally, health and care systems are experiencing significant
operational pressure across many of their services. Some patients are
experiencing delays in accessing both planned and unplanned healthcare. There
has been little/no reduction in operational pressures over the summer months
and providers are entering winter with significant capacity pressures in availability
of workforce and service capacity across service delivery areas. 
As noted within the Strategic Risk Register the partnership is experiencing higher
levels of vacancy and staff absence in both NHS and Local Authority posts
against a pre-COVID baseline. This is particularly challenging where vacancies
impact on skillsets critical to whole system working such as District Nursing and
Social Work (including Mental Health Officer) specialisms. Above expected
vacancy levels across several pinch point roles continues to drive overspends in
bank and agency staff usage that further pressurise depleted HSCP budgets. 
In addition to the current pressures, we face a range of hard to quantify risks such
as the potential for further Covid-19 pressures, high incidence of flu cases,

Page 2

2
increases in respiratory illnesses and the impact of the cost of living on both our
workforce and our patients. 
Scottish Government has described the actions they expected all systems and
providers to take to increase capacity and operational resilience in planned,
urgent and emergency care ahead of winter. 
A review of winter planning processes and priorities has been undertaken in early
autumn 2023. Our winter plan is set out in a format which considers:
1. Current Position: An outline for services, describing the current position
regarding system pressures and preparatory actions we will undertake to
mitigate for these, and;
2. Action Plan: An action plan setting out the specific whole system actions we
will undertake to support and manage winter pressures. The whole systems
action plan sets out a description of the action, the intended impact of each
action and how we propose to measure the successful delivery of each action. 
3. DETAIL OF REPORT 
Governance of The Winter Plan will be led by the Executive Lead for winter
planning. A cycle of system wide meetings are to be implemented to ensure we
have a mechanism for escalating issues and making decisions on critical issues,
in a joined-up way, across system partners. Along with regular data insights, we
plan to operationalise a bespoke weekly data file which facilitates the monitoring
of/responding to emerging risks and trends and compliance against agreed
actions. The progress of the plan, together with risks and challenges, will be
reportable to the NHS Highland Urgent and Unscheduled Care Programme
Board. 
We recognise that there will be challenging decisions to be taken over the course
of this winter and robust governance processes ensure a mechanism to do that
in a way that considers the needs of our entire population and the needs of staff
working across both health and care. 
4. RELEVANT DATA AND INDICATORS
This plan is considered in line with the following key overarching principles, as
defined by Scottish Government: 
 Enhancing Community Services and Planned Care.
 Optimising discharge home as first choice, ensuring patients are discharged
as soon as they are medically fit, wherever appropriate and enhancing care
in the community to reduce unmet need and delays.  
 Avoiding admission with services developed to provide care at home across
7 days, hospital at home, discharge to assess, rapid access to assessment
and a single point of access for health and social care. 
 Reducing attendances by managing care closer to home or at home
wherever possible including community step up facilities for assessment,
reablement and rehabilitation, prof to prof referral services, support OOH,
managing long term conditions to avoid unnecessary exacerbation utilising
digital and remote monitoring where possible.

Page 3

3
 Sufficient staffing across acute, primary and social care settings including
over the weekends and festive period with access to senior decision makers
to prevent delays in discharge and ensure patient flow. This includes
recruitment and wellbeing priorities.
 Surge Capacity with the ability to flex up capacity when required including a
surge plan. 
5. CONTRIBUTION TO STRATEGIC PRIORITIES
The plan is considered in line with the winter preparedness checklist, issued by
Scottish Government in late autumn 2023. The plan also has clear links with
established KPIs and Strategic Priorities for Urgent and Unscheduled Care. 
6. GOVERNANCE IMPLICATIONS
6.1 Financial Impact
No financial impact to existing service delivery is anticipated. Designated funds
are made available to support the period defined as ‘’winter pressures’’. Any such
funding will be managed within the parameters of established financial
governance as required.
6.2 Staff Governance
Key considerations as to staff health and wellbeing are noted within the document
at section 7 ‘’workforce’’. The plan does not envisage any necessity for changes
to existing terms and conditions for any colleague/any division. Any additional
resources would be procured and recruited with full and appropriate deference to
established staff governance protocols.
6.3 Clinical and Care Governance
All clinical and care governance standards and processes per service area are
as per usual arrangements. Additionally the systems pressures group provides
an oversight of any escalations. 
7. PROFESSIONAL ADVISORY
The HSCP has developed its Winter Plan in conjunction with key stakeholders
from across the system to ensure that we can maximise our shared knowledge,
resilience and resources with a view to delivering safe and effective services for
throughout the winter months. Initial engagement meetings were held in late
autumn 2023. The plan has been developed taking into account feedback and
learning following evaluation of the Winter Plan for 2022/23. The plan has been
sighted and contributed towards by all relevant professional leadership. 
8. EQUALITY & DIVERSITY IMPLICATIONS
None Noted.
9. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
None noted.
10. RISK ASSESSMENT
Risks are managed as per described within the plan. The board is assured on
wider risks e.g. workforce through the workforce plan. 
11. PUBLIC & USER INVOLVEMENT & ENGAGEMENT

Page 4

4
None noted.
12. CONCLUSIONS
Conclusions are per the action summaries detailed within each section of service
delivery. 
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required 
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland Health Board x 
REPORT AUTHOR AND CONTACT 
Author Name: 
 Caroline Cherry, Executive Lead for Winter Pressures and Head of
Service.
 Karl McLeish, Programme Lead for UUSC and Winter Plan. 
Email   
Caroline.cherry@argyll-bute.gov.uk 