ARGYLL AND BUTE COUNCIL     COMMUNITY SERVICES COMMITTEE
EDUCATION                                   25 AUGUST 2022 
SCHOOLS (CONSULTATION) (SCOTLAND) ACT 2010 – MINARD PRIMARY
SCHOOL 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides details of the Options Appraisal for Minard Primary School,
carried out in accordance with the preliminary requirements set out in Section 12A
of the Schools (Consultation) (Scotland) Act 2010, as amended. 
1.2 It is recommended that the Community Services Committee: 
a. Note the outcome of this consideration of the preliminary requirements; and,
b. Agree that officers now formulate a draft closure proposal that will come
back to the June 2023 meeting of the Committee for approval by members
which would subsequently trigger the formal consultation process under the
Schools (Consultation) (Scotland) Act 2010.

Page 2

ARGYLL AND BUTE COUNCIL    COMMUNITY SERVICES COMMITTEE 
EDUCATION 25 AUGUST 2022 
SCHOOLS (CONSULTATION) (SCOTLAND) ACT 2010 – MINARD PRIMARY
SCHOOL 
2.0 INTRODUCTION 
2.1 When considering the future of a rural school the Education Authority must first
satisfy the preliminary requirements as set out in Section 12A the Schools
(Consultation) (Scotland) Act 2010, as amended.
2.2 On 8th December 2020, the Community Services Committee agreed that officers
would undertake a preliminary consultation process in respect of Minard Primary
School. As Minard Primary School is a rural school, the preliminary requirements
require that a possible closure proposal, and all the reasonable alternatives, are
assessed having particular regard to the following:
a. Their likely educational benefits.
b. Their likely effect on the local community – having particular regard to the
sustainability of the community and the availability of the school premises
to the community.
c. The likely effect that would be caused by any different travelling
arrangements on the school's pupils and staff and any other users of the
school's facilities, as well as the possible environmental impact.    
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Community Services Committee:
a. Note the outcome of this consideration of the preliminary requirements;
and,
b. Agree that officers now formulate a draft closure proposal that will come
back to the June 2023 meeting of the Committee for approval by
members which would subsequently trigger the formal consultation
process under the Schools (Consultation) (Scotland) Act 2010.

Page 3

4.0 DETAIL 
4.1 This report provides details of the Options Appraisal, carried out in accordance
with the preliminary requirements of the Schools (Consultation) (Scotland) Act
2010, as amended (the 2010 Act), in respect of Minard Primary School. 
4.2 The Options Appraisal for Minard Primary School is attached as Appendix 1
4.3 Three alternative options have been assessed whilst considering the future of
Minard Primary School. For each option, information was collated and particular
regard was given to:
 Community feedback;
 Pupil numbers;
 Assessment of rural factors – namely the likely effect on the local community
(having particular regard to the sustainability of the community and
availability of the school’s premises and its other facilities for use by the
community); and the likely effect of any different travelling arrangements
that may be required (having particular regard to the effect on pupils, staff
and any other users of the school’s facilities, and any environmental impact).
 Educational benefits; and
 Financial information
4.4 An authority that is contemplating a rural school closure proposal must satisfy
the preliminary requirements set out in Section 12A of the 2010 Act prior to
formulating any proposal.
4.5 Consideration was given to the underlying reasons as to why the future of
Minard Primary School is being reviewed, and all reasonable alternatives to
closure of the school as a response to those underlying reasons, were
identified. All three options (including closure) were then assessed – having
particular regard to likely educational benefits, likely effect on the local
community and likely effect on travelling arrangements. Following this
assessment, closing Minard Primary School and realigning the north section of
its catchment area from Achagoyle Bay to Blackstone Bay to Furnace Primary
and the south section of its catchment area from Achagoyle Bay to Kilmichael
Beg to Lochgilphead Primary School is considered to be the most reasonable
option to address the underlying reasons for the possible proposal.
5.0 CONCLUSION
5.1 The Options Appraisal for Minard Primary School has been prepared in
accordance with the preliminary requirements of the 2010 Act.
5.2 After consideration of the preliminary requirements, all identified reasonable
alternatives and the reasons for why the future of the School is being
considered, closing Minard Primary School and redrawing its catchment area
realigning the north section of the catchment area from Achagoyle Bay to

Page 4

Blackstone Bay to Furnace Primary and the south section of the catchment area
from Achagoyle Bay to Kilmichael Beg to Lochgilphead Primary School is
considered to be the most reasonable option to address the underlying reasons
for the possible proposal. Officers are now in a position to formulate a draft
proposal that will come back to a future meeting of the Committee for approval
by members which would subsequently trigger the formal consultation process
under the 2010 Act. 
6.0 IMPLICATIONS
6.1 Policy - An authority that is considering formulating a rural school closure 
proposal must first satisfy the preliminary requirements set out in Section 12A of the 
Schools (Consultation) (Scotland) Act 2010, as amended. 
6.2 Financial - there are financial implications for each option, as set out in the 
Options Appraisal. 
6.3  Legal - The Options Appraisal for Skipness Primary School has been prepared in
accordance with the preliminary requirements as set out in Section 12A of the Schools
(Consultation) (Scotland) Act 2010, as amended.
6.4  HR  - none
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none at present 
6.5.2   Socio-economic Duty – none at present 
6.5.3  Islands – none at present
6.6 Climate Change – none at present 
6.7 Risk – none at present
6.8  Customer Service – none at present 
Douglas Hendry - Executive Director with responsibility for Education
Councillor Yvonne McNeilly – Policy Lead for Education
30 June 2022

Page 5

For further information contact: 
Wendy Brownlie, Head of Education – Teaching and Learning
Wendy.Brownlie@argyll-bute.gov.uk 
Sandra Clarke, Education Officer
Sandra.Clarke@argyll-bute.gov.uk 
APPENDICES
Appendix A – Options Appraisal - Minard Primary School