Democracy Spraffa

Strategic Risk Register

Argyll and Bute Council · 25 September 2024
Back to Argyll and Bute HSCP Integration Joint Board (IJB) — 25 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
Integration Joint Board       
Date of Meeting:  25 September 2024 
Title of Report:    Strategic Risk Register 
Presented by:      James Gow, Head of Finance 
The Integration Joint Board is recommended to: 
• Note that the Strategic Risk Register has been reviewed by the Leadership Team
and the Audit and Risk Committee.
• Note that it is recommended that Infrastructure Risk is added to the very high
Strategic Risks. 
• Review and approve the Strategic Risk Register and Risk Appetite. 
1. EXECUTIVE SUMMARY 
1.1 An important element of effective Risk Management is to regularly review the
Strategic Risk Register. The Audit & Risk Committee undertake this on behalf of
the IJB. This report recommends changes to the Register to reflect perceived
increasing risk and also seeks to reduce the overall number of risks described
within it. These changes have been endorsed by the Audit & Risk Committee. 
1.2 The Scottish government have published the budget for 2024/25 and confirmed
that capital funding will be reduced with projects delayed or cancelled and a ‘do
minimum approach’ to focus on maintenance of existing assets, this is one of
the drivers for increasing the risk associated with infrastructure. As a
consequence of the financial circumstances and potential response across the
system, it is perceived that a number of strategic risks are increasing. It is also
recognised that there are perhaps too many strategic risks and this report
suggests 2 options for streamlining the risk register.   
2. Recommendations 
2.1 The Integration Joint Board is recommended to: 
• Review and Approve the Risk Register and Risk Appetite.
• Endorse the categorisation of Infrastructure Risk as ‘Very High’. 
3. DETAIL OF REPORT 
3.1  The Risk Register is used to identify risks and assess their perceived likelihood
and impact. It is a dynamic document and is reviewed by the IJB twice annually.
The current version is attached as appendix 1. The Strategic Risk Register

Page 2

2
describes 21 strategic risks facing the HSCP, once the two risks which are
being suggested for removal are excluded. The table below summarises the
perceived residual risks: 
Residual Risks  Very High High Medium Total
May 2021  2 9 9 20
June 2022  4 14 6 24
June 2023  4 13 7 24
January 2024  4 14 5 23
August 2024  5 15 1 21 
It is suggested that the risk relating to vaccinations should be removed as this is
now business as usual albeit at a higher level of activity than previously.
Additionally, it is suggested that the risk relating to contingency planning and
resilience is incorporated within the Governance risk to reflect the
mainstreaming of this activity within SLT, the increased participation in training
and scenario events, updating of the on-call guidance and embedding of the
category 1 responder status.   
The Scottish Budget and subsequent further deterioration in the public finances
are indicators that a number of risks are increasing: 
• Financial Sustainability - uplifts were less than assumed for the NHS and
there remains system wide financial sustainability concerns which
appear to be worsening during the current year;
• Industrial Relations and Workforce – the SG budget plans for reductions
in the public sector workforce and there are restricted funds for 2024/25
pay awards. The trade off appears to be between increased pay offers to
reduce industrial relations risks and additional in year cuts to fund the
excess costs. There is also a risk in respect of the differential between
the current offers for the two largest staff groups;
• Delivery of Strategic Objectives – the consequences of the budget and
the response across the whole of the health and social care system is
such that the risk the HSCP will not be able to deliver on its strategic
objectives is perceived to be increasing; and
• Infrastructure – the capital programme is being reduced, one project has
been delayed and there is insufficient capital funding to address backlog
maintenance and replacement requirements across buildings,
equipment and digital infrastructure. This risk has been upgraded to very
high. 
3.2 The risk register incorporates an indicator which illustrates the perceived
direction of each risk, the five ‘Very High’ risks are: 
Financial Sustainability (SSR01) 
The underlying budget gap for 2025/26 is substantial and the most recent
modelling outlines a series of risks relating to funding and costs as well as
severe challenges facing public funding, the outlook has been described as
‘bleak’. It is recommended that this risk remains very high. A separate risk,
SSR01(b) has been added to reflect the short term position separately.

Page 3

3 
In response to concerns raised by the IJB, the HSCP is seeing to identify and
consult on budget / savings proposals to address the risk earlier than it has in
the past to enable better consultation. Other mitigations in place include greater
scrutiny of vacancies and consistent efforts to reduce usage of agency staffing. 
The HSCP continues to engage with both partners and national value initiatives. 
Sustainability of Commissioned Service Providers (SSR7) 
This risk remains very high as a number of service providers continue to
struggle to recruit staff and deliver the services they are contracted to. Several
are also requesting unaffordable uplifts in contract values. Work is on-going to
provide additional support and change ways of working, particularly for care at
home services. It is difficult to estimate the impacts the actions taken by the
HSCP have had but it is likely that some services have been protected that
would have otherwise been withdrawn, this has come at a financial cost. There
are however examples where the HSCP has not been able to support provision
on a sustainable basis but has been able to step in to ensure withdrawal or
transfer of service was managed as smoothly as possible. There are providers
who have indicated that services are at risk in the near term, service
management continue engage with providers and consider the implications and
alternative approaches. 
Workforce Recruitment and Retention (SSR10) 
The HSCP continues to experience difficulty in recruiting staff to a wide variety
of roles. Staffing is the main constraint on service delivery in some areas. This
risk is both a local and a national one, however the ageing and reducing
population and the housing emergency provide a particularly difficult local
context. The Workforce group is meeting regularly and is in the process of
implementing the Workforce Strategy. This is also being taken into account by
the Infrastructure Transformation Board as it seeks to improve accommodation
options in the most challenging localities. The use of agency staff as a
mitigation remains the biggest threat to financial performance. 
Socio-Economic Situation & Increasing Poverty (SSR24) 
This risk continues to be considered as very high and has multiple strands. It is
largely outwith the influence of the HSCP. It is expected that the cost of living
crisis will continue to drive increased poverty and deprivation and service
demand. The HSCP is experiencing increased costs and reduced real terms
value of its resourcing. The ability of the Scottish Government to fund these
pressures is concerning. Recent public health and performance data support
this evaluation of the risk. The impact of poverty, deprivation and exclusion is
perceived to be being exacerbated by the impact the lockdowns have had upon
some of the most vulnerable in society, particularly those with mental health
issues and some groups of children. 
Infrastructure and Assets (SSR06) 
Significant backlog maintenance requirements have been identified and there is
insufficient funding available to address these. Additionally, there are excess
requests for equipment replacement across the NHSH area and insufficient
funding for digital infrastructure replacement and development. The HSCP
cannot fund capital investment from its reserves, this risk to a large extent is
therefore not in the control of the HSCP and is the responsibility of partners.

Page 4

4
The risk of building failure in the short term is perceived to be increasing and
the lack of a replacement strategy adds to this as business case work is halted
(NHS). Communication with both partners on this topic is on-going. Mitigations
are in place and works are planned or progressing for some of the care home
estate. A detailed report has been considered by the Finance and Policy
Committee and the Infrastructure Board where the evaluation of this risk as
‘Very High’ was endorsed. 
3.4 Risk management within the HSCP relies upon processes and procedures
within the partner organisations, particularly in respect of cyber security, data
protection, infrastructure replacement and financial processes and systems.
Recent Cyber Security breaches within the public sector further highlight the
growing and strategic nature of this risk. Work is on-going to better integrate the
Strategic Risk Register with service owned risk registers. 
3.5 Risk Appetite 
An IJB development workshop was held in October 2023 to develop the risk
appetite for the HSCP. The main purpose is to ensure that the management
understanding of risk appetite aligns with the IJB’s as summarised below: 
RISK
APPETITE
RATING
Risk Grouping 0 1 1.5 2 2.5 3 3.5 4
Operational Risks        
Strategic Risk        
Legal / Regulatory        
Financial        
Development & Innovation        
Clinical & Care        
People & Workforce        
Reputational           
The risk appetite ratings quantitively indicate that there is a willingness within
the board to accept higher levels of risk relating to strategic change, innovation
and workforce. This reflects a recognition through the IJB and HSCP that there
are significant drivers for change and transformation. It is also clear that the IJB
has a lower appetite for clinical, legal / regulatory and financial risks. 
4. RELEVANT DATA AND INDICATORS 
4.1 The identification and rating of risk is based on internal and external data and
indicators as well as a wider environmental scan.    
5 CONTRIBUTION TO STRATEGIC PRIORITIES 
5.1 Robust risk management is an important aspect of the overall strategic
management of the HSCP. 
6. GOVERNANCE IMPLICATIONS 
6.1 Financial Impact – None

Page 5

5
6.2 Staff Governance – None 
6.3 Clinical Governance – None 
7. Professional Advisory 
7.1 Professional leads are embedded in operational and strategic risk management
processes. 
8. EQUALITY & DIVERSITY IMPLICATIONS 
8.1 None arising directly from the contents of this report but it is considered that the
implications of measures that may be required to mitigate a variety of risk and
achieve a sustainable financial position will have an impact upon people with
protected characteristics.   
9. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
9.1 None. 
10. RISK ASSESSMENT 
10.1 This report provides a detailed review of the strategic risks facing the HSCP. 
11. PUBLIC & USER INVOLVEMENT & ENGAGEMENT 
11.1 None arising directly from this report but again the implications of efforts to
achieve a sustainable financial position may result in increasing risk in terms of
the implementation of the HSCP’s engagement strategy. 
12. CONCLUSIONS 
12.1  Overall the risk environment facing the HSCP remains challenging and is
perceived to have worsened as a result of the funding outlined by the Scottish
Government. The financial outlook combined with service pressures and
workforce challenges continue to create significant risk. There are system wide
drivers for change which are, if anything, more acute locally due to
demographics. 
12.2 The Risk Appetite is also provided for further review. The HSCP is in the
process of streamlining the Strategic Risk Register and improve operational risk
management processes and systems. 
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required √
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland Health Board

Page 6

6 
14. PREVIOUS REVIEW OF THE REPORT 
Meeting  Title of report Date Output (if
relevant)
SLT Strategic Risk Register
Review
05/06/24 Changes
endorsed and
wording
strengthened 
in respect of
impacts of
increasing
poverty.
Audit & Risk
Committee
Strategic Risk Register
Review
18/6/24 Amendments
to Strategic
Risk Register
Endorsed 
REPORT AUTHOR AND CONTACT 
James Gow, Head of Finance : james.gow@argyll-bute.gov.uk 
Appendix 1:  Strategic Risk Register