Integration Joint Board     
Date of Meeting:  17 September 2025 
Title of Report:    Strategic Risk Register Review 
Presented by:      James Gow, Head of Finance 
The Integration Joint Board is asked to: 
• Note that the Strategic Risk Register has been reviewed by the Leadership Team
and the Audit & Risk Committee. 
• Review and approve the Strategic Risk Register and Risk Appetite.
• Note that a Board Development session to review the Risk Appetite is scheduled
for November 2025. 
1. EXECUTIVE SUMMARY 
1.1 An important element of effective Risk Management is to regularly review the
Strategic Risk Register (SRR). The Audit & Risk Committee undertake this on
behalf of the IJB. This report provides an opportunity for the IJB to review the
Strategic Risk Register, it is required to do this twice per year within the terms of
the Risk Management Strategy. The SRR has been reviewed by the
management team and the Audit & Risk Committee in recent months, it is
unchanged in respect of risk ratings but the overall context remains one of high
and increasing risk. Several risks were increased at the time of the last review in
December 2024. 
2. RECOMMENDATIONS 
2.1 The Integration Joint Board is recommended to: 
• Review and Approve the Strategic Risk Register and Risk Appetite.
• Note that a Board Development session to review the Risk Appetite is
scheduled for November 2025. 
3. DETAIL OF REPORT 
3.1  The Risk Register is used to identify risks, assess their perceived likelihood and
impact and outline how they are being mitigated. It is a dynamic document and
is reviewed by the IJB twice annually. The current version is attached as appendix
1. The Register describes 21 strategic risks facing the HSCP. The table below
summarises the number and assessment of perceived residual risks:

Page 2

2 
Residual Risks  Very High High Medium Total
May 2021  2 9 9 20
June 2022  4 14 6 24
June 2023  4 13 7 24
June 2024  5 15 1 21
August 2025  6 15 0 21 
Total risks have been reduced with some consolidated post pandemic. Overall the risk
ratings have not changed but new issues of note are: 
• Leadership team – recent changes have reduced professional level social work
capacity within the leadership team increasing reliance on the Chief Social Work
Officer. (SSR 5 – High)
• The Care Reform Bill has been passed (now Act) and is likely to have implications
for expectations relating to social care delivery which will add to financial
pressures or result in re-prioritisation of services. (SSR10 – High)
• The Government are increasing scrutiny on waiting times and long waits. (SSR
15 – High) 
3.2 The risk register incorporates an indicator which illustrates the perceived direction
of each risk, the six ‘Very High’ risks are: 
Financial Sustainability (SSR01) 
The underlying budget gap for 2025/26 is substantial and deteriorates further in
2026/27. The most recent modelling outlines a series of risks relating to funding
and costs as well as severe challenges facing public funding. It is recommended
that this risk remains very high.  
Sustainability of Commissioned Service Providers (SSR08) 
This risk remains very high as service providers continue to struggle to recruit
staff and deliver the services they are contracted to. Several are also requesting
unaffordable uplifts in contract values. Work is on-going to provide additional
support and change ways of working, particularly for care at home services. It is
difficult to estimate the impacts the actions taken by the HSCP have had but it is
0
2
4
6
8
10
12
14
16
May-21
Aug-21
Nov-21
Feb-22
May-22
Aug-22
Nov-22
Feb-23
May-23
Aug-23
Nov-23
Feb-24
May-24
Aug-24
Nov-24
Feb-25
May-25
Residual Risk Trend
Medium
High
Very High

Page 3

3 
likely that some services have been protected that would have otherwise been
withdrawn, this has come at a financial cost. The increase in the employer
national insurance rate has added to the risk and the independent sector have
recently written an open letter to Government re-stating the fragility of the sector. 
Workforce Recruitment and Retention (SSR11) 
The HSCP continues to experience difficulty in recruiting staff to a variety of roles.
This is a constraint on service delivery in some areas. This risk is a national one,
however the ageing and reducing population and the housing emergency provide
an increasingly difficult local context. The workforce group is meeting regularly
and is in the process of implementing the Workforce Strategy. The HSCP is
improving accommodation options in the most challenging localities. However,
the perception is the problem is not improving and some agency and locum rates
are increasing. 
Socio-Economic Situation & Increasing Poverty (SSR21) 
This risk continues to be considered as very high and has multiple strands. It is
largely outwith the influence of the HSCP. It is expected that the cost of living
crisis will continue to drive increased poverty and deprivation and service
demand. The HSCP continues to experience increased costs and reduced real
terms value of resourcing. Recent public health publications and performance
data support the evaluation. Addressing health inequality is a strategic objective
for the HSCP and Government (Population Health Framework) but it is not clear
how this sits alongside the scale of the financial challenge facing health and
social care services. 
Infrastructure and Assets (SSR07) 
Significant backlog maintenance requirements have been identified, there is
insufficient funding available to address all of these although some additional
capital has been allocated. Additionally, there are excess requests for equipment
replacement across the NHSH area and insufficient funding for digital
infrastructure replacement and development. This risk to a large extent is not in
the control of the HSCP and is the responsibility of partners. The risk of building
failure is perceived to be increasing but there is an improved understanding of
the problem and some steps are being taken to address the areas of most
concern. Communication with both partners is on-going, some funding is being
allocated and projects are now progressing. 
There is insufficient budget to maintain all properties to an acceptable standard
in the longer term and spend is increasingly targeted at addressing issues raised
by regulators and the Fire Service. 
Support Services (SSR 16) 
The management team no longer has a dedicated and integrated HR
representative as part of its structure. This means qualified HR support is often
not available when decisions are being considered and made. Additionally, the
absence of such a role places additional pressure on senior management
Effective HR management is key to change management and the situation
impacts on transformation planning and delivery. HR is a key technical expert in
partnership working for both senior staff and operational leadership for early

Page 4

4 
resolution. The HSCP is continuing to work with both partners to seek a
resolution. 
3.4 Risk management within the HSCP relies heavily upon processes and
procedures within the partner organisations, particularly in respect of cyber
security, data protection, infrastructure replacement and financial processes and
systems. Recent Cyber Security breaches within the NHS further highlight the
growing and strategic nature of this risk. 
It is also the case that the actions that the HSCP is expecting to have to take in
the coming weeks and months can be expected to have a further negative
impacts on a range of strategic and operational risks, particularly as spend on
social care services is required to reduce further. Further action is however
necessary to manage financial risks and respond to the expectations of partners. 
3.5 Audit Recommendations 
The Risk Management Strategy has been reviewed recently and risks have been
mapped to strategic objectives. A focus of activity at present is to develop
operational risk registers to ensure that they are consistent and complete across
the HSCP.   
3.6 Risk Appetite 
An IJB development workshop was held in October 2023 to develop the risk
appetite for the HSCP. The main purpose is to ensure that the management
understanding of risk appetite aligns with the IJB’s as summarised below: 
RISK
APPETITE
RATING
Risk Grouping 0 1 1.5 2 2.5 3 3.5 4
Operational Risks        
Strategic Risk        
Legal / Regulatory        
Financial        
Development & Innovation        
Clinical & Care        
People & Workforce        
Reputational           
The risk appetite ratings quantitively indicate that there is a willingness within the
IJB to accept higher levels of risk relating to strategic change, innovation and
workforce. This reflects a recognition through the IJB and HSCP that there are
significant drivers for change and transformation. It is also clear that the IJB has
a lower appetite for clinical, legal / regulatory and financial risks. The risk appetite
does require to be reviewed in the current year as actual perceived risks do not
align well with the risk appetite at present, largely due to the impact of the financial
challenge. 
4. RELEVANT DATA AND INDICATORS 
4.1 The identification and rating of risk is based on internal and external data and
indicators as well as a wider environmental scan.

Page 5

5 
5 CONTRIBUTION TO STRATEGIC PRIORITIES 
5.1 Robust risk management is an important aspect of the overall strategic
management of the HSCP. This report also seeks to ensure that risks relating to
strategic objectives are adequately reflected in the SRR. 
6. GOVERNANCE IMPLICATIONS 
6.1 Financial Impact – This report outlines a need for the HSCP to change the way it
operates in order to remain financially sustainable. 
6.2 Staff Governance – the current lack of strategic and operational HR support
within the needs identified has a potential impact on leadership and
management time. 
6.3 Clinical Governance – There would be potential impact in clinical/care delivery
as a consequence of the management of the risks outlined in the SRR 
7. Professional Advisory 
7.1 Professional leads are embedded in operational and strategic risk management
processes. 
8. EQUALITY & DIVERSITY IMPLICATIONS 
8.1 None arising directly from the contents of this report but it is considered that the
implications of measures that may be required to achieve a sustainable financial
position will have an impact upon people with protected characteristics.   
9. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
9.1 None directly but data protection compliance is an important business risk. 
10. RISK ASSESSMENT 
10.1 This report provides a detailed review of the strategic risks facing the HSCP. 
11. PUBLIC & USER INVOLVEMENT & ENGAGEMENT 
11.1 None arising directly from this report. 
12. CONCLUSIONS 
12.1  Overall the risk environment facing the HSCP remains challenging and is
perceived to be worsening. Finance and staffing related issues continue to be
amongst the main challenges. The local assessment aligns well with the national
picture with recent reports published by Audit Scotland providing evidence. There
is significant concern that some of the recent policy and legislative requirements
will further exacerbate workforce and financial risks and are not supported with
the financial investment that is required. 
12.2 The risk that the HSCP will either not be able to remain financially sustainable or
will not be able to deliver on the new and existing strategic priorities is increasing.

Page 6

6 
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required √
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland Health Board 
14. PREVIOUS REVIEW OF THE REPORT 
Meeting  Title of report Date Output (if
relevant)
SLT Strategic Risk Register 11/6/25 Review points
taken into
account 
Audit & Risk
Committee
Strategic Risk Register 20/6/25 Request for
risk appetite
statement
review 
REPORT AUTHOR AND CONTACT 
James Gow, Head of Finance : james.gow@argyll-bute.gov.uk 
Appendix 1:  Strategic Risk Register