Finance & Policy Committee     
Date of Meeting:  18 August 2026 
Title of Report: Infrastructure Update – July 2026 
Presented by: James Gow, Head of Finance  
Malcolm McMillan, Senior Manager Strategic Estates
Development & Sustainability 
The Finance & Policy Committee is asked to: 
• Note the contents of this report;
• Note the progress since the increase of Infrastructure Risk to Very High on the
HSCP Strategic Risk Register in June 2024; and
• Note that actions are on-going to mitigate risk and make improvements where
possible but considerable challenges remain.
• Recommend that NHS Highland and Argyll & Bute Council ensure infrastructure
risks are captured on their Strategic Risk Registers. 
1. EXECUTIVE SUMMARY 
1.1 The delivery of HSCP services is reliant on the physical building infrastructure
from which it operates. The infrastructure is owned by both partners (NHS
Highland and Argyll & Bute Council) who are also responsible for its
maintenance. The purpose of this report is to: 
• Update the committee with progress on key projects since the last update
in November 2025; and
• Update the Committee on progress in managing infrastructure risk on the
Strategic Risk Register classed as ‘Very High’. 
1.2 Governance arrangements relating to infrastructure are complex, The
Infrastructure Transformation Board was established in 2023 to strengthen HSCP
governance arrangements, the board continues to meet quarterly to update and
discuss priorities. However, capital spend is not delegated to the HSCP, separate
and very different governance arrangements exist within the Council and NHS
Highland. The HSCP is represented at the relevant groups within both partners
and relationships remain positive. The overall position is that significant backlog
maintenance requirements and equipment replacement needs have been
identified and there is insufficient capital resource to address these (nationally
and locally). The outcome of this is that the risk of failures and/or loss of capacity
due to failure to meet regulatory standards is increasing.

Page 2

2 
1.3 Delivery continues within a constrained capital environment, with investment
focused primarily on statutory compliance, backlog maintenance and service
resilience. Nationally, the Scottish Government’s Strategic Assessment approach
requires NHS Boards to demonstrate long-term infrastructure alignment prior to
project approval, reinforcing prioritisation and limiting progression of non-
essential schemes. 
1.4 Progress is evident in funded compliance projects, including fire safety works at
Lorn & Islands Hospital and Islay Hospital. However, several projects - the Cowal
Community Hospital redesign, Islay roof replacement, and care home
infrastructure upgrades - remain at risk due to funding constraints, scope
reductions or are still at an early-stage of development. The overall programme
reflects a shift toward risk-based investment, with very little capacity for major
transformation projects without additional capital support. 
2. Recommendations 
2.1  The Finance and Policy Committee are Recommended to: 
• Note the contents of this report;
• Note the progress since the increase of Infrastructure Risk to Very High on the
Strategic Risk Register in November 2024; and
• Note that actions are on-going to mitigate risk and make improvements where
possible but there remain considerable long-term challenges to risk reduction.
• Recommend that NHS Highland and Argyll & Bute Council ensure infrastructure
risks are captured on their Strategic Risk Registers. 
3. DETAIL OF REPORT 
3.1  This is an update on the paper presented to this committee in June 2024 that
reported on the Audit & Risk committee decision to increase the risk of
infrastructure failure putting the ability of the HSCP to meet its statutory and
regulatory obligations at risk as well as its ability to deliver on its strategic
objectives to Very High. Whilst this report indicates that good progress continues
to be made in addressing some key risks and making improvements, the risk of
infrastructure failure is reduced but not judged to have reduced significantly
enough to warrant a downgrading of the risk at this time. This is partly because
infrastructure is continuing to age and deteriorate even as the highest risk items
are addressed. Additionally, regulatory bodies appear to be paying increased
attention to the quality of infrastructure, particularly in recent inspections of the
care home estate and fire service inspections of hospitals. 
In addition to the specific progress outlined in this report, it is worth highlighting
that there is also important strategic development work underway. In addition to
the development of the internal infrastructure board, there is also now a strategic
Argyll & Bute place board focusing on development in Lochgilphead, Rothesay
and Dunoon facilitated by Hub North. The Board meets regularly and includes
key partners including the HSCP, Argyll and Bute Council and NHS Highland. It
is hoped that this will help ensure that new investments will be progressed in a
way which is aligned to the strategic direction of partners and will present new
opportunities for innovation, partnership working and shared use of facilities. It
may also present opportunities for new ways of working which could help support
the development of the Single Authority Model Approach.

Page 3

3 
3.1.1 NHS Highland Infrastructure Improvements  
NHS Highland capital investment has been focused on prioritised maintenance
as advised in Directorate Letter (DL) 2024 02 and 2025 15. Health Boards have
been instructed to create a prioritised maintenance only investment plan referred
to as the Business Continuity Investment Plan (BCIP) for which some additional
funding would be allocated only for board’s top risks. Health Boards are also
instructed to allocate existing annual capital allowances (Formula Capital) should
be focused to the priorities identified as well. It is worth noting that formula capital
still falls considerably short of what is required on an annual basis for addressing
backlog maintenance alone. 
The BCIP process produced a list of risk assessed capital investment priorities
for Argyll & Bute NHS premises and was submitted to Scottish Government in
November 2024. Following this submission additional capital funding was
secured for Lorn & Islands and Islay Hospital fire improvement works and for
scoping a solution to the fire improvement actions required for Cowal Community
Hospital. Project progress is detailed later in the report but funding for a
replacement fuel tank at Campbeltown Hospital was secured and a major point
of failure risk has been removed from the risk register. 
In terms of strategic capital development, the Scottish Government have
indicated to Boards that they can now progress work on a small number of new
capital projects. NHS Highland is working with Hub North on identifying priorities
and it is expected that this will include replacement of Argyll & Bute Facilities. It
must be noted that this will take some time to progress with initial assessments
due to be considered by Scottish Government in September 2026 with successful
projects not expected to start development until 2031 at the earliest. 
3.1.2    Argyll & Bute Council Capital Funding 
Capital budgets have been agreed to 2027/2028 and have been reduced from
£428k in 24/25 to £382k per annum in 27/28 for the HSCP care homes, children’s
homes, learning resource centres and offices. This reduction in capital
significantly hampers the ability of the HSCP to operate safe, compliant and fit
for purpose facilities. Argyll & Bute Council have increased the availability of
preventative maintenance funding in recognition of the challenges that all its
property users face within an ageing estate. This will help with tackling reactive
and preventative maintenance issues that should ease some of the burden on
the capital budget, but the backlog of capital improvements remains. 
Care Home Strategic Assessment work is expected to provide clarity on the
future of care home provision in Argyll & Bute and will assist in the prioritisation
of key capital works. The output of the Strategic Assessment provides further
evidence on the disparity between budget allocation and budget required to
maintain properties effectively. 
The HSCP is working closely with the Council on our priorities, once the strategic
direction for each of the existing Care Home facility is agreed the HSCP would
seek to take a property-by-property approach to the refurbishment of each asset
that it intends to operate in the longer term (as it has done with Tigh a Rudha
care home, Tiree), in preference to a piecemeal, reactive approach. There is a
potential ask for a significant capital investment for our care home estate as
outlined in the Strategic Assessment programme reports presented previously.

Page 4

4 
3.1.3 Key Worker Housing 
Progress continues on key worker accommodation, supported by close working
with Argyll & Bute Council’s Housing team. Housing remains a significant barrier
to recruitment across HSCP services, and a temporary part-time Housing
Improvement Officer has been appointed by the HSCP to strengthen operational
support, improve procedures and help staff secure suitable accommodation.
Rental charges for HSCP-owned properties are also being reviewed to support
future maintenance costs. 
Four staff have now moved into key worker accommodation in Oban, with further
moves planned. Joint working with the Council, housing associations and Shelter
Scotland is delivering new or improved accommodation in Tiree, Coll, Islay and
Oban, reducing costs and strengthening the recruitment offer for staff relocating
to Argyll and Bute. 
Recent service pressures, including the liquidation of a Care at Home provider,
have reinforced the importance of responsive housing arrangements, with
registered social landlords providing valuable support to the HSCP. 
Strategic Housing Fund support has been secured to redevelop the former
Bowmore dental surgery into a two-bedroom key worker property on Islay,
expected to be available before the end of the financial year. 
3.1.4 Carbon Reduction (Net Zero) 
The Scottish Government have indicated that funding for energy efficiency and
adoption of renewable energy measures for NHS boards will be able to apply for
in FY 26/27 and 27/28 with approximately £20M available across Scotland per
year. NHS Highland will receive an estimated £625k per year to invest in
sustainability projects. It is hoped that the HSCP, will be able to apply for funding
over the course of the coming years to reduce its carbon footprint and running
costs as well as deal with some infrastructure liabilities. Additional government
funding from third parties for a range of net zero projects is also available, but the
lead applicants are required to be NHSH and Argyll & Bute Council. 
This financial year, funding has been secured from Scottish Government
Sustainability Division by NHS Highland to complete a detailed decarbonisation
plan for Raigmore and Lorn & Islands Hospital that will produce a route map to
net zero for the sites. The scope of the project is being finalised (July 26) with
completion of the report due March 2027. This will enable NHS Highland and the
HSCP to understand the opportunities available that future sustainability capital
funding can be applied for. Additional funding for LED lighting and lighting control
measures has also been secured for this financial year. 
Work is on-going to de-carbonise the HSCP fleet and concurrently to provide a
suitable charging infrastructure to support this. Funding was secured for the
25/26 financial year for the installation and upgrade of more chargers across
Argyll & Bute NHS sites to provide greater resilience to EV fleet users.
Additionally, a further 17 zero emission vehicles and 12 hybrid vehicles were
procured replacing older petrol and diesel vehicles and reducing the average fleet
emissions of the replaced vehicles from 101g/km to 62g/km.   
3.1.5 Estates Rationalisation

Page 5

5 
HSCP Estate rationalisation activity has been supported through Argyll and Bute
Council's Our Modern Workspace (OMW) project since the project's inception in
2021. As part of OMW, Ellis Lodge, Dunoon, has been rationalised, with all staff
relocating to the renovated Argyll House during 2025/26. This has affected HSCP
social work staff across four departments. Work is ongoing to complete the
rationalisation programme in Dunoon.  
In September 2024, the Board of NHS Highland confirmed that the former Argyll
and Bute Hospital and associated land in Lochgilphead had been declared
surplus to requirements and is being prepared for sale on the open market.
However, some buildings remain operational, and alternative accommodation for
these services would be required as part of any future sale.  
NHS Highland is also adopting a space utilisation policy that will provide clear
guidance and governance on the efficient use of the NHS Highland estate. The
HSCP is currently in discussions with NHS Highland regarding how this policy
could be implemented across Argyll and Bute. 
3.2 Current Projects 
The status of projects of strategic importance currently underway or planned are
summarised below: 
Underway Details Governance Budget
Lorn & Islands
Hospital Fire
Improvement
Works
Phase 1 &2 of 8
awaiting start date. 
NHSH Estates
Capital team
reporting
quarterly to
Infrastructure
Board.
£900K in 26/27
FY. Funded from
SG Business
Continuity
Investment Fund.
Islay Hospital Fire
Improvement
Works
Underway.
Awaiting phase 2
start date. 
NHSH Estates
Capital team
reporting
quarterly to
Infrastructure
Board.
£1,200K in 26/27
FY. Funded from
SG Business
Continuity
Investment Fund. 
Cowal
Community
Hospital Fire
Improvement
Works
Underway.
Design works
ongoing to establish
a compliant layout for
costing.  SFRS notice
requiring
improvement to
compartmentalisation
and evacuation
routes. 
Significant cost
estimated to comply.
Risk of enforcement
action if no action
taken. 
NHSH Estates
Capital team
reporting
quarterly to
Infrastructure
Board.
£250K secured
this FY from
Business
Continuity Fund
for design works.
Birch Drive Islay
(NHS owned)
Project in progress.
Once completed
NHS A&B
Estates team
£220k. £145k
contribution from

Page 6

6 
HSCP will no longer
require to lease as
many third party
properties on the
island. 
reporting
quarterly to
HSCP
Infrastructure
Board.
strategic housing
fund. Remaining
to be found from
HSCP reserves. 
Struan Lodge Re-
Wire
Costs of full rewire
not affordable.
Measures to enable a
24-month stop gap
measure accepted by
ELT. Improvements
to electrical
protection, heating
system and roof
included in package
of works.
Fortnightly
project board
led by A&B
Property
Services,
reporting
quarterly to
Infrastructure
Board and
Care Home
and Housing
Programme
Board
£291k from Argyll
& Bute Council
Capital
allocation.
Campbeltown
Hospital
Generator
replacement and
LV Panel
upgrades.
Upgrade of the
Campbeltown
hospital generator
with the refurbished
generator from LIH to
a larger generator
that can power they
whole hospital is
completed providing
resilience to
additional HSCP
sites. 
NHS Estates
team reporting
quarterly to
Infrastructure
Board.
£200k NHS
Highland formula
capital allocation
26/27 FY
Cowal Hospital
Lift
Refurbishment
Upgrade of both lifts
in Cowal Community
Hospital project
underway.
NHSH Estates
Capital Team
reporting
quarterly to
Infrastructure
Board.
£250k NHS
Highland Capital
formula allocation
26/27 FY.
Thomson Court Temporary
Generator
connection point
upgrades. Project to
provide a generator
hook up point to
improve resilience for
the care home during
power outages. 
Fortnightly
project board
led by A&B
Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board and
Care Home
and Housing
Programme
Board.
£73K from A&BC
Capital
allocation.
Ardfenaig Care
Home
Temporary
Generator
connection point
Fortnightly
project board
led by A&B
£31K from A&BC
Capital
allocation.

Page 7

7 
upgrades. Project to
provide a generator
hook up point to
improve resilience for
the care home during
power outages. 
Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board and
Care Home
and Housing
Programme
Board.
Eadar Glinn Care
Home
Temporary
Generator
connection point
upgrades. Project to
provide a generator
hook up point to
improve resilience for
the care home during
power outages. 
Fortnightly
project board
led by A&B
Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board and
Care Home
and Housing
Programme
Board.
£33K from A&BC
Capital
allocation.
Eadar Glinn Care
Home
Shower and Window
replacements.
Following Care
Inspectorate
comments new
shower rooms and
windows are being
installed in the care
home. 
Fortnightly
project board
led by A&B
Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board and
Care Home
and Housing
Programme
Board.
£198K from
A&BC Capital
allocation.
Kintyre Care
Centre
Various 
Electrical Services
Upgrades.
Decorations and
Toilet refurbishment
Window
Replacement
Programme.
Fortnightly
project board
led by A&B
Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board and
Care Home
and Housing
Programme
Board.
£803k from Argyll
& Bute Council
Capital
allocation.
In development

Page 8

8 
Net Zero Project
LED Lighting
improvements
Part of a funding
package for nearly
£1M awarded to NHS
Highland.
Improvements are
pan A&B NHS
properties.
NHS A&B
Estates Team
reporting
quarterly to
Infrastructure
board.
£259K from SG
Sustainability
Directorate. 
Net Zero
Decarbonisation
Plan
Part of a funding
package for nearly
£1M awarded to NHS
Highland. This plan
will provide a detailed
decarbonisation plan
for LIH.
Thomson
Gray.
£250K from SG
Sustainability
Directorate. 
Islay Hospital flat
roof repair/
replacement
Design in
development 26/27. 
Flat roof on Islay
Hospital is beyond
end of life and
regularly leaks or
requires repairs due
to wind damage.
NHS Estates
Capital team
reporting
quarterly to
infrastructure
board.
NHS Highland
formula capital
funded. 
Former Argyll &
Bute Hospital
disposal.
Initial Phase
completed. Further
phases require
additional capital
funding which has
been applied for. 
Former Hospital site
falling into significant
disrepair, New Mid
Argyll Hospital
utilises some of the
original water
infrastructure that is
beyond end of life.
Risk of failure and
possible service
disruption. Also, a
revenue burden for
security of site.
NHS Estates
Capital team
reporting
quarterly to
infrastructure
board.
£402k in 25/26
FY from S.Gov
ADEL fund to
enable asbestos
removal and
design works for
adoption of the
water supply by
Scottish Water.
Mid Argyll
Community
Hospital X-Ray
equipment
replacement. 
The MAH X ray
equipment was
brought across from
the old hospital and is
now obsolete. 
NHS H
Equipment
Purchase
Advisory
Group (EPAG)
£407K in 26/27
Financial Year
from equipm
budget ent
formula capital.
Completed   
Campbeltown
Hospital Fuel
Tank
Replacement
Completed. Original
oil tank showing
signs of failure and
on risk register.
Led by NHS
A&B Estates
Team with
progress
reports to
Funded from
24/25 NHS
Highland Capital
Allocation.

Page 9

9 
Good progress has been made in taking forward a number of projects designed
to reduce risk, improve facilities and help address key worker accommodation
concerns. The HSCP has been able to joint fund some of this work from its
reserves. These are now depleted and the HSCP is no longer in a position to
facilitate the development of further substantial projects in this way. Going
forward the HSCP plans to seek project funding from partners and other
alternative sources. 
3.3 Risk 
The Strategic Risk Register considers infrastructure risk as ‘Very High’ putting
the ability of the HSCP to meet its statutory and regulatory obligations at risk as
well as its ability to deliver on its strategic objectives. In tackling this risk, progress
has been made across multiple fronts improving the situation for the HSCP. This
can be attributed to more staff and financial resources being provided towards
HSCP priority issues but also more effective working relationships with our
partner organisations. Evidence of progress is listed below: 
• Removal of high-risk high impact infrastructure failures such as Campbeltown
Hospital oil tank.
• Refurbishment of Tigh-A-Rudha Care Home to modern standards removing
the risk of regulatory enforcement and improving resilience of service
• Securing of additional capital funding to address Scottish Fire & Rescue
Service improvement notices at Islay and Lorn & Island Hospital.
Replacement now in
situ. 
Infrastructure
Board 
Campbeltown X-
Ray replacement
and re-modelling
Completed. HSCP
funded re-modelling.
Equipment funded by
NHS Highland.
NHS Estates
team reporting
quarterly to
Infrastructure
Board.
£528k, project
delivered on time
and budget. 
Tigh a Rudha
refurbishment
and remodel –
Island
Programme /
HSCP and
Council funded
Completed. A&B Property
Services,
reporting
quarterly to
Infrastructure
Transformation
Board.
£2.4M from A&B
Capital, Strategic
Housing Fund
and HSCP
reserves.  
Coll Houses –
NHS owned with
contribution from
Strategic Housing
Fund
Completed
Nurses House
Completed. GP
House anticipated
completion date of
17th November 2025.
Managed by
NHS A&B
Estates team
reporting
quarterly to
Infrastructure
Board.
£465k.
£365k of HSCP
reserves, £100k
of strategic
housing fund. 
LIH Hospital
Generator
replacement.
Larger generator and
LV panel
modifications enable
hospital to be fully
powered in outage
situations.
NHS Estates
Capital Team /
A&B Estates.
£250k NHS
Highland formula
capital allocation

Page 10

10 
• Refurbishment of housing on Coll to enable quality accommodation for key
workers.
• Relocation and replacement of X-ray department in Campbeltown Hospital
avoiding the risk of equipment becoming obsolete while improving staff and
patient experience.
• Replacement of out of contract fleet vehicles ensuring continuity of
community services.
• Upgrade of the LV plant infrastructure at Lorn & Islands Hospital replacing
obsolete and unreliable equipment to enable the Electric Vehicle charger
rollout as well as improve resilience at our only Rural General Hospital. 
While this progress is satisfying there remains considerable complex risks from
infrastructure to HSCP operations; 
• Scale of backlog maintenance is such that a building failure which could result
in a temporary or medium-term closure is still increasing.
• Cowal Community Hospital refurbishment remains in development, and
funding has not yet been identified to deliver the changes required to meet
the Scottish Fire & Rescue Service improvement notice and service needs.
• There is insufficient funding identified to arrest the deterioration of existing
infrastructure and address essential requirements;
• There is a lack of a clear long-term strategy from partners and the government
for dealing with infrastructure backlog;
• Statutory enforcement agency warning notices and threat of enforcement are
still being received with preventable infrastructure related problems cited as
reasons for the issuing of notices;
• Some properties continue to be unsuitable for services and NHS strategic
development work has yet to resume;
• Legacy infrastructure issues remain a significant problem.
• Some properties are not fully compliant with current standards;
• Costs of capital works have increased substantially which reduces the impact
planned spend will have; and
• ICT infrastructure and equipment replacement investment are also well in
excess of available resources. 
At this point it is not possible to recommend a change to the risk status. 
4. RELEVANT DATA AND INDICATORS 
4.1 This report relies on various condition survey reports and in some cases high
level estimates of costs.   
5 CONTRIBUTION TO STRATEGIC PRIORITIES 
5.1 The availability of suitable infrastructure (buildings, ICT and equipment) is
essential for the delivery and safety of service delivery and provision of
appropriate working and living environments. 
6. GOVERNANCE IMPLICATIONS 
6.1 Financial Impact – There is insufficient funding at present to address backlog
maintenance requirements. Spend of reserves on projects reduces capacity to
manage service spend pressures.

Page 11

11 
6.2 Staff Governance – None 
6.3 Clinical Governance – risks highlighted in this report have implications. 
7. PROFESSIONAL ADVISORY 
7.1 Professional leads are represented on the Infrastructure Board and have the
opportunity to contribute to the prioritisation of projects. 
8. EQUALITY & DIVERSITY IMPLICATIONS 
8.1 None 
9. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
9.1 Cyber security risks are linked to investment in infrastructure but are considered
through the Digital Health and Care Programme Board and are the responsibility
of both partners. 
10. RISK ASSESSMENT 
10.1 No change to the risk register is recommended at this time. infrastructure risk
should remain a Very High strategic risk.   
11. PUBLIC & USER INVOLVEMENT & ENGAGEMENT 
11.1 Engagement has taken place in respect of new projects, the community and
partners on Tiree and Coll have been effectively consulted with during their
respective projects. 
12. CONCLUSIONS 
12.1  This report summarises the current priorities for infrastructure projects and
provides an overview of the current context, risk and condition of the facilities the
HSCP is utilising. 
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required √
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland Health Board 
14. PREVIOUS REVIEW OF THE REPORT 
Meeting  Title of report Date Output (if
relevant)
N/A

Page 12

12 
This report draws heavily on a number of documents considered by the
Infrastructure Transformation Board. 