Delivering for 
the future
Transformation: How councils are redesigning
and delivering more efficient services
Prepared by Audit Scotland
May 2026

Page 2

2Delivering for the future: Transformation
Contents
Key messages 3
Commission expectations 5
1. Introduction 7
2. Planning 13
3. Programme management 18
4. Partnership working, community
engagement and impacts 22
Accessibility
You can find out more and read this report using assistive
technology on our website www.audit.scot/accessibility.
Audit team
The core audit team
consisted of:
Kathrine Sibbald,
Emma Brown, Liam
Prior and Jack Nixon
under the direction of
Blyth Deans.

Page 3

Key messages 3
Key messages
1 Scotland’s councils continue to face deepening financial
challenges, with increasing demand, the cost of delivering
services rising faster than available funding, mounting debt
and falling reserves. The need for sustainable change is
urgent. Transformational approaches to redesign services are
an important part of the solution and delaying transformation
could risk greater costs, tougher decisions and increased
challenges in future years. However, our analysis highlights that
the understanding of the anticipated financial and non-financial
benefits of transformation projects varies across councils.
Half of the councils in our sample still need to set out how
transformation activity will support future financial sustainability.
Integrating this information into council medium- and long-term
financial plans is key to understanding whether the scale of
transformation being delivered is sufficient to respond to the
challenges facing local government.
2 Some councils have shown progress with articulating their
approaches to transformation, but the picture is mixed across
the sector. Those councils that have done this well are able to
set out clear objectives and measurable outcomes, as well as
clear alignment with strategic priorities and wider plans. In some
councils, oversight of transformation activities is not always clear,
and reporting to councillors is often not comprehensive enough
to fully inform their leadership and scrutiny responsibilities.
The timely and effective delivery of transformation plans
requires appropriate workforce capacity and skills, in leadership,

Page 4

4Key messages
management and frontline roles. While some councils manage
this well, resourcing challenges have been a barrier to faster
progress in others.
3 It is essential that councils work with their partners in the public,
private and third sectors to deliver transformation. Although there
are some positive examples of effective partnership working,
challenges persist in achieving real change for service users
and delivery of clear cost savings. Barriers include funding,
capacity and resource constraints, governance, and IT and
data-sharing issues.
4 While there are examples of consultation with communities
on transformation projects, it is often not clear how this
engagement has been reflected in service redesign proposals.
Councils are also often unable to clearly report the financial
impact and wider benefits of their transformation activities.
As a result, it is difficult for communities to understand how
transformation is contributing to strategic priorities, financial
sustainability and service delivery.
5 Not all councils are using Equality Impact Assessments in a
consistent or effective manner to identify and monitor the effects
of transformation activities on vulnerable and protected groups.
This inconsistency can result in gaps in understanding how
changes may disadvantage certain sections of the community.
Where Equality Impact Assessments are not fully embedded
in the planning and monitoring processes, there is a risk that
the potential impacts on those most at risk are not adequately
considered or addressed.

Page 5

5Commission expectations
Commission expectations
In its October 2024 report, Transformation in councils,
the Accounts Commission urged councils to ‘prioritise and
urgently progress the delivery of their local transformation
ambitions and engage effectively in sector-led transformation
activity, securing political backing and committing resources’.
As set out in the key messages on pages 3 and 4, the local
Best Value audit work has shown mixed progress across
councils with transformation. With the financial sustainability
of councils becoming increasingly at risk, the Commission
asks councils to reflect on the messages in the 2024 report
and ensure they have effective arrangements in place
to support transformation, are learning from and sharing
effective practice with others and are engaging with national
sector-led approaches.
This report summarises learning from local work and highlights
specific expectations of all councils.
The Commission expects, in respect of transformation plans,
that councils ensure these:
• are sufficiently ambitious to respond to the
financial challenges
• are clearly linked and reflect wider strategic plans
and priorities
• clearly set out details to support effective implementation,
monitoring and reporting
• clearly set out planned savings from transformation
programmes and plans, linking these to financial plans
including medium- and long-term financial plans.
In respect of programme management and resourcing,
councils need to ensure:
• they have clear oversight at a strategic level of all
transformation activity

Page 6

Commission expectations 6
• there is effective engagement with councillors
accompanied by comprehensive reporting on
transformation initiatives
• they regularly review whether workforce capacity
(in terms of time availability and skills) is sufficient to
plan, manage and deliver current and medium-term
transformation plans and programmes
• they strategically plan and establish the necessary
workforce capacity to support transformation initiatives,
ensuring adequate management and staff availability
to facilitate the development and execution of
transformation activities
• transformation plans (at strategic and project level) set out
appropriate success measures so that there is clear data
to support scrutiny and demonstrate progress and impact
against objectives.
In respect of partnership working, community engagement
and impacts, councils should ensure:
• opportunities to work in partnership or to share services
continue to be sought
• they clearly document how community engagement,
data, and equality impact assessments have influenced
plans and implementation
• they have arrangements in place to effectively monitor
and report the impacts of transformation activities.

Page 7

1. Introduction 7
1. Introduction
About the audit work and this report
1. Since 2022, auditors have undertaken thematic Best Value audit work
alongside annual audit work at Scottish councils. In previous years this
has focused on why leadership matters and responding to workforce
challenges. Local transformation was the theme audited alongside the
2024/25 annual audit work. The findings are set out in a management
report to each council.
2. This report draws on the findings of the 22 management reports
available at the time of drafting. The Accounts Commission considered
it important to share the messages and learning from this work as early
as possible. This sample approach allows more timely reporting, while
still including a representative range of councils in terms of size, location
and demographics.
3. This report covers the following areas:
• Transformation planning: To what extent do councils have clear
plans for transformation that link to their priorities and support long-
term financial sustainability?
• Programme management: To what extent do councils’
programme management arrangements facilitate effective oversight
of transformation plans?
• Partnership working, community engagement, and impacts:
To what extent are partners and communities involved in the
development and delivery of councils’ plans for transformation?
And to what extent have councils considered the impact of
transformation activity, including on vulnerable or protected groups?
4. The report sets out a high-level view of progress across councils.
It also aims to support further improvement in the sector by providing
information and assessment of different arrangements for transformation
in councils. A supplement to the report, Delivering for the future –
Case studies, collates case studies from the management reports
reviewed. These are illustrative examples of approaches that are
contributing positively within the respective councils. They are intended
as a resource to support councils learn from others. It is structured to
set out examples against the different factors, considered in this report,
that contribute to effective transformation arrangements. It is a snapshot
of examples at the time of drafting and many other valid approaches
exist beyond those reflected in the supplement. Case studies in the
supplement are referenced but not replicated within this report.
The 22 management
reports in scope
are for the following
councils:
Aberdeenshire,
Angus, Dundee
City, East Ayrshire,
East Lothian, East
Renfrewshire, City of
Edinburgh, Falkirk,
Fife, Highland,
Midlothian, Moray,
North Ayrshire,
North Lanarkshire,
Perth and Kinross,
Renfrewshire,
Scottish Borders,
Shetland
Islands, South
Ayrshire, South
Lanarkshire, West
Dunbartonshire, and
West Lothian. 
The management
reports for the
following ten
councils were not
yet published at
the time of drafting
(owing to a variety of
factors): Aberdeen
City, Argyll and Bute,
Clackmannanshire,
Dumfries and
Galloway, East
Dunbartonshire,
Eilean Siar, Glasgow
City, Inverclyde,
Orkney Islands, and
Stirling.

Page 8

1. Introduction 8
What is transformation?
5. Transformation is about radically changing how local government
operates and delivers services to improve people’s lives in a financially
sustainable way. There is no single, concise definition of transformation
in a local government context. Individual councils must have the
flexibility to transform service delivery appropriately to the needs of
their communities.
6. While there will be differences in approach across councils, the
Accounts Commission’s October 2024 Transformation in councils
report set out five principles that must underpin transformation. This
report summarises learning from local work in these areas to support
councils with delivery.
Transformation
principle: Covered in this report under:
Vision Strategic planning (paragraph 20)
Planning Financial planning (paragraphs 21–24)
Transformation funding (paragraphs 25–27)
Project plans (paragraphs 28–29)
Resourcing (paragraphs 37–39)
Impacts (paragraphs 57–58)
Governance Managing projects and programmes (paragraphs 33–34)
Councillor engagement (paragraphs 35–36)
Collaboration Partnership working (paragraphs 46–50)
Joint funding (paragraphs 51–52)
Community engagement (paragraphs 53–56)
Innovation This has been considered across our transformation work.
Examples of the different approaches councils are taking are
included in our case study supplement.
7. Both local and sector-led approaches have an important role to
play in driving and delivering transformation. In Transformation in
councils, the Accounts Commission set out a specific expectation
for individual councils to ‘prioritise and urgently progress the delivery
of their local transformation ambitions and engage effectively in
sector-led transformation activity, securing political backing and
committing resources’.
Why is transformation important?
8. The Accounts Commission underlined in its Local government
in Scotland: Financial bulletin 2024/25 that the financial challenges

Page 9

1. Introduction 9
facing Scotland’s councils continue to deepen. With increasing demand,
the cost of delivering services is rising faster than available funding,
together with mounting debt, falling reserves and a continued reliance
on non-recurring measures to close significant budget gaps. This risks
the financial sustainability of councils over the next three to five years.
Meanwhile, national indicators show satisfaction with council services
is decreasing.
9. In this context, the need for sustainable change is urgent. Councils
have made considerable savings, including those stemming from
transformation, but these have been insufficient to close the gap
between the funding needed and funding available. While only part of the
solution, transformational approaches (in areas such as early intervention,
prevention, partnership working or digital) can reduce costs while bringing
meaningful improvements for those who use council services.
10. Alongside transformation, difficult decisions will be needed, which
could include stopping services, reducing services, or making new
or additional charges. The Accounts Commission recognises that
implementing transformation is challenging and that some initiatives may
not succeed. However, delaying transformation could risk greater costs,
tougher decisions and increased challenges in future years.
Progress with national approaches
11. The audit work and this report focus on progress at each council
with their local approach to transformation, however national sector-led
transformation work, alongside local approaches, has the potential to
help councils achieve financial sustainability and deliver better outcomes
in the medium to long term. It offers an opportunity to build consensus
across the sector and with communities on what local government
transformation should look like and how and when that will be achieved.
12. Councils face many of the same challenges. For example, many
councils are being impacted by demographic change, including the
challenges of either growing or declining populations, or a growing older
population. There is an opportunity to share knowledge, data, expertise
and experience around planning and delivering change, with greater
efficiencies from shared learning.
13. In 2023, the Society of Local Authority Chief Executives (SOLACE)
and the Improvement Service launched the local government
transformation programme following the publication of Delivering a
future for Scottish Local Authorities. Within the programme, a range
of national approaches are being undertaken in three workstreams, as set
out in Exhibit 1 (page 10).

Page 10

1. Introduction 10
Exhibit 1. 
SOLACE and Improvement Service Transformation Programme structure
Anchor 1.
Unlocking
community action
Anchor 2. 
Tackle
inequality
and meet the
needs of all
citizens
Anchor 3. 
Enable a functioning,
trusted local and central
government relationship 
Anchor 4. 
Design for
people’s needs 
Anchor 5.
Create digital,
design and
technology-
enabled
transformation 
Anchor 6. 
Lead council
and cross-sector
partnerships
Workstream 1
Officer-led 
conversation on
public sector
reform
Workstream 2
Short-term
local government
transformation 
projects 
Workstream 3
Building capacity
to lead and deliver
transformation1
14. Progress reported by SOLACE and the Improvement Service against
each workstream is set out at Exhibit 2 (page 11).
Note 1: Including the Leadership Practitioner Forum.
Source: Audit Scotland

Page 11

1. Introduction 11
Exhibit 2. 
Progress with the Transformation Programme
Workstream 1
Officer-led 
conversation on
public sector
reform
A draft report on public service reform from a local government
perspective that will set out challenges and opportunities for the
sector is due for publication in summer 2026.
Workstream 2
Short-term
local government
transformation 
projects
• Duties and powers portal – in April 2026, a portal was launched
that brings together the statutory duties and powers held by
councils, to ‘make the legislative landscape easier to navigate
and to provide a shared, consistent foundation to support service
improvement and transformation activity’.
• National self-evaluation framework – in April 2026 the framework
was launched with four councils due to pilot the framework
over 2026/27.
• Other areas of work under way including collaboration on
procurement, guidance and toolkits for digital programmes,
potential shared digital services and opportunities for wider shared
services arrangements.
Workstream 3
Building capacity
to lead and deliver
transformation
Each council has appointed a senior leader in their organisation to
be the single point of contact for the transformation programme
and a network for senior officers, the Leadership Practitioner
Forum, brings together officers from across the sector to discuss
and contribute to the programme as it progresses.
Note: Further information and progress updates are available on the Improvement Service website
Source: SOLACE and Improvement Service

Page 12

1. Introduction 12
15. In Transformation in councils, the Accounts Commission was clear
that both SOLACE and the Improvment Service needed to sustain the
momentum of their Transformation Programme and be clear on actions
needed, timescales, costs, resources, outcomes, outputs and impacts.
16. Given the major risks to financial sustainability across the sector, fast
progress from this initiative is essential. Sector-led improvement activity is
more important than ever, as it can be instrumental in driving meaningful
change locally and improving outcomes for communities.

Page 13

132. Planning
2. Planning
To what extent do councils have clear plans for
transformation that link to their priorities and support long-
term financial sustainability?
Why it is important
17. The scale, pace and ambition of transformation must increase
to meet rising demand, rising expectations and rising costs facing
councils. Significant change cannot be delivered in the short term. Early
intervention and preventative approaches take time to deliver benefits,
and major digital transformation projects often require significant
investment and lengthy implementation periods. Officers and councillors
will need to work collaboratively to plan change over the longer term. The
Accounts Commission recognises the challenges that councils face in
planning for the long term, while managing day-to-day demands within
a difficult financial context. However, proactively planning for change will
reduce the need for more difficult measures and further costs in future.
18. Delivering meaningful change is complex. It can and should involve
coordination across different areas of the council, across political
groupings and more widely with partners. Success depends on having
clear aims, realistic timescales, and a shared understanding of the
expected costs, outcomes, and impacts. Clearly establishing these at the
outset enables councils and their partners to better direct their limited
time and resources.
19. When planning changes to how services are delivered, it is vital that
councillors and officers consider and assess the impacts on service
users. Decisions can have unintended consequences, particularly for the
more vulnerable members of communities who often have a greater
need for council services.
What we found
Councils that have articulated their approaches to transformation
well have underpinned plans with clear objectives and measurable
outcomes, as well as demonstrating clear alignment with strategic
priorities and wider plans.
The quality and availability of details about projects and their
planned impact (both financial and non-financial) varies across
councils:

Page 14

2. Planning 14
• Over a third of the councils in our sample have not
sufficiently determined the financial impacts of their
transformation plans.
• Half of the councils in our sample have not clearly set out the
anticipated financial impacts of their transformation activity
in their medium- and long-term financial plans.
• Most councils in our sample need to improve how they
identify, monitor and report on wider benefits.
Where these are lacking, councils face risks around delivery,
financial planning and achieving improvements for communities.
Strategic planning
20. Whether transformation plans are stand-alone or embedded in wider
strategic plans, councils need to ensure there are clear links between
projects and their contribution to the council’s strategic priorities and
aims. In addition, there should be clear links with other corporate
programmes such as financial, workforce, digital, capital and asset
strategies and plans.
Strategic planning Case studies:
1. East Ayrshire Council – a service embedded approach that is well
linked to wider corporate strategies.
2. North Lanarkshire Council’s ‘Programme of Work’ and
accompanying delivery plan – seeing transformation through
a regional lens.
3. The Highland Council’s ‘Delivery Plan 2024–2027’ – a strong
example of the transformation programme sitting within the corporate
strategic plan.
4. West Lothian Council – an example of a stand-alone ‘Performance
and Transformation Strategy’ with projects embedded in services.
All case studies
are provided
in a separate
supplement.
View case
studies

Page 15

2. Planning 15
Financial planning
21. Given the significant financial challenges outlined at paragraph 8, it
is essential that councils establish strong links between transformation
plans and medium- to long-term financial planning.
22. Auditors reported that just over half of the 22 councils in our sample
identified savings from transformation initiatives. For just over a third of
councils, savings were either identified for some projects or not at all.
At four councils, auditors made recommendations around identifying
transformation savings, while at others they noted this reflected the
stage projects had reached at the time of audit work.
23. Where savings have been identified, all but two councils in our
sample appropriately incorporated these into wider financial plans, such
as medium-term financial strategies and budget documentation. Half
of the councils in our sample still need to progress this further. This is
important to give councillors and communities a clear picture of how far
budget gaps are being addressed through transformation. Not doing so
could undermine the level of support for transformation.
24. North Ayrshire Council is one council that demonstrates a strong and
clear approach to transformation in its financial planning. The primary
driver behind the council’s transformation programme is to deliver
savings to address financial challenges and protect frontline services. The
council has also been clear that transformation is only part of the solution
to closing its budget gap, with significant further measures also needed.
It has recognised that these will need to include future recurring savings
through workforce changes, cuts to services, and increases to council tax
and fees and charges.
Financial planning Case study:
1. North Ayrshire Council – a strong approach to planning
transformation to deliver savings and protect frontline services.
All case studies are provided in a separate supplement. View case
studies

Page 16

2. Planning 16
Transformation funding
25. Almost all councils reviewed have earmarked reserves set aside
for transformation, but these vary in purpose and value. About two-
thirds of the councils in our sample have a fund that supports general
transformation or change activity. Meanwhile, other councils have set
aside funds for more specific purposes, such as digital transformation,
capital investment, adult social care or early intervention and prevention.
26. Some councils have set out timeframes for the use of transformation
reserves, ranging from the medium term (three to five years) to the
long term (up to 15 years). Others use spend-to-save models, allowing
ongoing replenishment of funds, for example Falkirk and Scottish
Borders councils.
27. It is difficult to get a clear picture of the amount set aside across the
sector for transformation given ongoing movements in reserve levels
and some reserves being used for a mixture of transformation and other
activity. North Lanarkshire Council has used its £793.1 million Community
Investment Fund to support transformation through capital investment
and economic regeneration (see case studies). Other reserves
referenced in local reports as being used for transformation ranged from
£1.6 million to £40 million. Some examples of larger transformation
reserves are set out in the case studies.
Transformation funding Case studies:
1. North Lanarkshire Council Community Investment Fund – supporting
capital investment and economic regeneration by setting aside council
tax income.
2. Renfrewshire Council Service Modernisation and Reform Fund –
supporting transformation through a combination of reserves, short-
term capacity within service budgets and external funding.
3. Scottish Borders Council Change Fund – a £20 million self-
replenishing reserve to support transformation projects.
4. East Ayrshire Council Early Intervention and Prevention Fund – using
funding generated on a one-off basis from financial flexibilities to
support early intervention and prevention.
All case studies
are provided
in a separate
supplement.
View case
studies

Page 17

2. Planning 17
Project plans
28. Auditors reviewed samples of councils’ project plans for
transformation as part of local audit work. Those councils who have good
project plans were able to set out clearly:
• planned annual costs and savings
• potential impact on service delivery, performance, staffing, and
service users
• alignment with strategic plans and priorities
• timescales for delivery
• risk management
• consultation requirements
• whether a full integrated impact assessment is required.
29. Our work has shown that some councils do not have the level
of detailed project planning in place needed to support delivery of
transformation. Some projects were at an early stage in the planning
cycle when audit work was carried out. For others, auditors noted
slow progress developing detailed project plans or project plans
not consistently covering all the expected areas. This presents risks
to timely delivery and brings a lack of clarity over how strategic
plans will be achieved.
Project plans Case study:
1. West Lothian Council – a comprehensive template for budget
reduction measures, which include transformation projects.
All case studies are provided in a separate supplement. View case
studies
What needs to happen
30. Councils need to ensure transformation plans:
• are sufficiently ambitious to respond to the financial challenges
• are clearly linked and reflect wider strategic plans and priorities
• clearly set out details to support effective implementation,
monitoring and reporting
• clearly set out planned savings from transformation programmes
and plans, linking these to financial plans.

Page 18

183. Programme management
3. Programme management
To what extent do councils’ programme management
arrangements facilitate effective oversight of
transformation plans?
Why it is important
31. Effective programme management and governance arrangements are
vital to ensure that transformation activities are effectively coordinated,
resourced, monitored and evaluated.
32. Councils will not achieve transformation at the scale needed to
address current challenges if they do not have staff with the right skills
and sufficient capacity to deliver it.
What we found
• Not all councils have clear oversight at a strategic level of
all transformation activity. More broadly there is a need for
better and more comprehensive reporting of the planned
benefits to support effective management and scrutiny
by councillors.
• Councillors have a crucial role in supporting and scrutinising
transformation. Open and effective collaboration across
political lines, as well as with senior officers, is critical when
making the difficult decisions that transformation work
can involve.
• Many councils need to improve the workforce capacity
available to make better progress with transformation.
However, there are strong examples of councils managing
these challenges effectively.
Managing projects and programmes
33. Councils manage transformation projects and programmes in
different ways. In some councils, they are managed as a central
portfolio of projects and in others they are managed within service
areas. Regardless of the approach taken, it is important that there
is clear oversight at a strategic level of all transformation activity so
that the impact on council priorities, finances and communities can
be understood.
34. Auditors found some councils do not have this central oversight, or
lack a clear sense of what activity should be treated as transformation.
This brings risks that transformation activity is not sufficiently focused on
strategic priorities.

Page 19

3. Programme management 19
Managing projects and programmes 
Case studies:
1. Falkirk Council – strong arrangements for officer monitoring of
transformation activity.
2. Highland Council, 3. North Lanarkshire Council and 4. Renfrewshire
Council – operational governance arrangements align with
arrangements for strategic and financial priorities.
5. Fife Council and 6. North Ayrshire Council –
transformation/reform boards.
7. Dundee City and 8. Perth and Kinross councils – Programme
Management Offices.
All case studies
are provided
in a separate
supplement.
View case
studies
Councillor engagement
35. Auditors regularly highlight the importance of councillors collaborating
well with each other, including across political lines, and with officers
when making long-term strategic decisions to address financial
sustainability risks. Three 2024/25 annual audit reports (out of 20
published at the time of drafting) raised concerns around a lack of
collaborative leadership.
36. A common finding from audit work on transformation is the need
for more comprehensive reporting to councillors about transformation
initiatives, with recommendations around this at ten councils. Most
formal engagement with councillors on transformation is through Full
Council meetings and policy committees, but some councils have
dedicated councillor forums for transformation. These have been used to
allow early engagement and in-depth scrutiny of transformation plans by
councillors. This supports a collaborative approach between officers and
councillors, which is needed to underpin meaningful change.
Councillor engagement Case studies:
1. Midlothian Council – effective governance arrangements for
reporting progress to the senior leadership team and councillors.
2. Scottish Borders Council – improving transformation visibility
for councillors.
All case studies are provided in a separate supplement. View case
studies

Page 20

3. Programme management 20
Resourcing
37. A lack of capacity (both time and skills) is a significant risk to delivery
of transformation across the sector. Around a third of the reports
reviewed as part of our sample made recommendations about improving
workforce capacity to deliver transformation. These stemmed from risks
identified around capacity across leadership, service staff, and dedicated
transformation teams.
38. Councils have had varying levels of success in managing staff
capacity to deliver transformation work. Some councils have handled
this well through close monitoring and ongoing management of staffing
arrangements. At others, a lack of capacity has led to slower than
anticipated progress.
39. Councils have used different staff structures to deliver transformation.
Some use a centralised management approach, finding this supports
more collaborative working and sharing of learning. At other councils,
staff within specific service areas lead transformation. This means
implementation is owned within services and not seen as the
responsibility of others. Stronger examples of this approach have ensured
that there is specialist skills capacity embedded in services. There are
risks and benefits for councils to manage under both approaches. In all
cases, councils need to ensure that their arrangements are clear and
support achieving their overall objectives.
Resourcing Case studies:
1. Midlothian Council – Programme Management Office provides
coordination, skills and support.
2. West Lothian Council – Service Design Champions Group
embedded in the workforce.
All case studies are provided in a separate supplement. View case
studies

Page 21

3. Programme management 21
What needs to happen
40. Councils need to ensure:
• they have clear oversight at a strategic level of all
transformation activity
• there is effective engagement with councillors accompanied by
comprehensive reporting on transformation initiatives
• they regularly review whether workforce capacity (in terms of time
availability and skills) is sufficient to plan, manage and deliver current
and medium-term transformation plans and programmes
• they strategically plan and establish the necessary workforce
capacity to support transformation initiatives, ensuring adequate
management and staff availability to facilitate the development and
execution of transformation activities
• transformation plans (at strategic and project level) set out
appropriate success measures so that there is clear data to support
scrutiny and demonstrate progress and impact against objectives.

Page 22

22
1.
4. Partnership working, community engagement and impacts
4. Partnership working,
community engagement
and impacts
To what extent are partners and communities involved in
the development and delivery of councils’ plans for
transformation? And to what extent have councils
considered the impact of their transformation activity,
including on vulnerable or protected groups?
Why it is important
Partnership working
41. Councils cannot deliver transformation alone and it is essential
that they work with the Scottish Government, Community Planning
partners, and third sector partners on the transformation of local services.
42. Councils and their partners need to radically rethink how they work
together to support more sustainable models of service delivery. While
there are challenges with implementation, working in partnership can
create meaningful changes in how services are delivered, making best
use of workforce skills and capacity, as well as contributing to addressing
financial sustainability challenges.
Community engagement and impacts
43. Communities must be actively involved in the difficult decisions
councils make about their local services. Councils need to be clear on
the need for change, the options and implications. This is vital given
that changes or reductions to services can have a significant impact on
people’s lives.
44. General public consultations need to be supplemented by targeted
consultations with the groups most impacted by changes to specific
services, with consideration given to encouraging participation.
45. Failure to engage over proposed changes exposes councils to
substantial risks, including the need to withdraw proposals or defend
legal challenges. Doing so also means savings and efficiencies have to
be found from other services and budgets.
Community
Planning is led by
Community Planning
Partnerships within
each council area.
It involves councils
and other public
bodies working with
local communities,
businesses and the
voluntary sector
to plan and deliver
services that improve
people’s lives.

Page 23

4. Partnership working, community engagement and impacts 23
What we found
• There are many positive examples of partnership
working, but most of these are on the margins in terms
of transformation. Partnership working that meaningfully
addresses financial sustainability challenges or significantly
changes how services are delivered to communities
remains difficult.
• There is limited evidence of how community engagement
has influenced project design and delivery. For vulnerable
and protected groups, this should be evidenced through
Equality Impact Assessments, but around a quarter of the
councils in our sample need to develop a more consistent,
thorough process for these.
• Councils are often failing to report clearly and transparently
on the progress and impacts of transformation activity. This
means that it is difficult for communities to understand how
transformation is contributing to strategic priorities, financial
sustainability, and service delivery.
Partnership working
46. Councils can point to many positive examples of how they work with
partners across the public, private and third sectors. However, there are
varying degrees to which this work can be considered transformational.
47. Some of the most notable plans for transformation in local
government involve shared services. At the time of audit work, North
Ayrshire, East Ayrshire and South Ayrshire councils were exploring ‘Pan-
Ayrshire’ joint working. The councils highlighted barriers (including the
siloed approach to funding, governance and reporting) and referred to
the vital role of national government in enabling more transformational
partnership working.
48. Some councils are developing partnership or place-based approaches
to support joint delivery with partners. For example, Midlothian Council
established a Multi-Agency Transformation Management Group with
partners to deliver whole system change. Falkirk and Clackmannanshire
councils are exploring future joint transformation opportunities.
49. Councils also provided examples of partnership working on energy
initiatives, property rationalisation, and digital initiatives.
50. The Improvement Service’s September 2025 report on Collaborative
Working in Scottish Local Government identified a number of barriers
to further partnership working in local government that were echoed in
our local audit work. These included:
• funding
• capacity and resource constraints
• variability in local requirements and loss of dedicated local capacity

Page 24

4. Partnership working, community engagement and impacts 24
• inconsistencies in service delivery
• cultural, governance, legal and organisational barriers
• HR and employment policies
• IT and data-sharing issues
• sustainability and maintaining momentum
• measuring impact.
Partnership working Case studies:
1. Pan-Ayrshire shared services.
2. Midlothian – Multi-Agency Transformation Management Group.
All case studies are provided in a separate supplement. View case
studies
Joint funding
51. Joint funding arrangements can be a strong enabler to progressing
transformational partnership initiatives. Funding arrangements with
the UK or Scottish governments were highlighted most frequently in
audit work.
52. Joint funding with wider partners is more limited. The Improvement
Service’s report on Collaborative Working in Scottish Local Government,
September 2025 noted that projects could be left in a financially
vulnerable position if one or more partners were to pull out and withdraw
their funding. This risk is heightened by the difficult financial situation
facing councils.
Joint funding Case studies:
1. Aberdeen City, Aberdeenshire, Highland and Moray councils –
expanding electric vehicle infrastructure supported by £7.5 million of
Scottish Government funding.
2. Moray Council’s m.connect project – developing a demand-
responsive council-run bus service using funding provided by the
Scottish Government.
3. Shetland and Orkney Islands councils – working with partners in the
private and third sectors on rural energy hubs.
4. Midlothian Council’s joint venture with private sector to deliver low-
carbon energy projects across the area – Midlothian Energy Limited.
All case studies
are provided
in a separate
supplement.
View case
studies

Page 25

4. Partnership working, community engagement and impacts 25
Community engagement
53. Auditors reported examples of effective community engagement at
individual project level, but only a small number of councils were able
to provide evidence this had influenced project design and delivery.
Examples of project-level engagement included targeted consultation
for individual projects, direct engagement with service users to inform
service redesign, and engagement with vulnerable or protected groups
where projects were likely to have a material impact.
54. Equality Impact Assessments provide a framework for documenting
how consultation with and data on vulnerable and protected groups
has influenced plans and for monitoring impacts as work progresses.
However, auditors found these were not carried out consistently at three
councils and not completed thoroughly at six councils.
55. Councils also consult on their budgets, taking a range of approaches.
Some include engagement on specific transformation savings or wider
engagement on how funding should be prioritised. For example, North
Ayrshire Council carried out extensive engagement in winter 2024 on
its budget, including several areas of transformation work. The council
reported that consulting on specific budget options rather than generic
areas of priority led to increased engagement from communities.
56. Perth and Kinross Council rolled out a structured and user-focused
‘service design’ approach to transforming services. The council uses
various methods (including workshops, events, and meetings) to gather
feedback and ideas from those who deliver, use and interact with
services. This feedback is then used to set clear actions for progress and
agree solutions for future improvement.
Community engagement Case studies:
1. North Ayrshire Council – budget consultation.
2. Perth and Kinross Council – user-focused service design approach.
3. East Renfrewshire Council – use of data.
All case studies are provided in a separate supplement. View case
studies

Page 26

4. Partnership working, community engagement and impacts 26
Impacts
57. Once projects are under way and then implemented, councils are
often failing to report clearly and transparently on progress and impacts.
Councils often do not have stated measures of success in place at the
outset to allow them to track progress. This limits self-evaluation, scrutiny
and accountability on whether anticipated timescales, impacts and value
for money have been met. Councils can also miss opportunities to
review, improve and share learning.
58. Around two-thirds of the reports in our sample included
recommendations about identifying and monitoring the impacts
and benefits of transformation. Several councils have recognised
the opportunity for further progress in this area and are developing
processes to assess how far benefits have been realised. A lack of clear
reporting on benefits makes it difficult for a council to communicate to
councillors and the wider public on the overall impacts and value of its
transformation initiatives.
Impact Case studies:
1. Perth and Kinross Council – benefits realisation log.
2. Highland Council – incorporating success measures into
Performance and Risk Management System.
3. Highland Council – in-house bus service delivering savings while
improving service quality.
4. Angus Council – tracking the impacts of estate rationalisation.
All case studies
are provided
in a separate
supplement.
View case
studies
What needs to happen
59. Councils should ensure:
• opportunities to work in partnership or to share services continue to
be sought
• they clearly document how community engagement, data,
and Equality Impact Assessments have influenced plans and
implementation
• they have arrangements in place to effectively monitor and report
the impacts of transformation activities.

Page 27

Delivering for the future
Transformation: How councils are redesigning
and delivering more efficient services
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 www.audit.scot
ISBN 978 1 918486 07 0