Argyll and Bute Council · 22 December 2022
Back to Argyll and Bute Harbour Board — 22 December 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

MINUTES of SPECIAL MEETING of ARGYLL AND BUTE HARBOUR BOARD held ON A HYBRID
BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 22 DECEMBER 2022 
Present: Councillor Andrew Kain (Chair) 
Councillor John Armour (by Teams)
Councillor Jim Lynch (by Teams)
Councillor Andrew Vennard (by Teams) 
Councillor Garret Corner (by Teams)
Councillor Ross Moreland (by Teams) 
Attending: Douglas Hendry, Executive Director
Kirsty Flanagan, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
David Logan, Head of Legal and Regulatory Support
Scott Reid, Marine Operations Manager
Stuart McLean, Committee Manager
Frank Roberts, Oban Community Council
Phil Hammerton, Oban Bay Stakeholders
Ross Wilson, Oban Community Harbour Development Association 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Ian MacQuire. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interested intimated. 
DEPUTATION
The Chair intimated that a request for a deputation by Oban Community Harbour
Development Association to be heard by the Harbour Board had been received. It was
unanimously agreed to hear this deputation prior to item 4 of the Agenda.
.
3. PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN FEES &
CHARGES 2023 / 2024 
The Harbour Board gave consideration to a report in respect of a necessary increase in
fees and charges for the forthcoming financial year 2023 / 2024, in order to meet the
requirements for the Argyll and Bute Council Asset Management Plan that had been
referenced in the report to the Harbour Board in September 2022. 
Decision 
The Harbour Board agreed to - 
1. recommend to the Council, when setting the fees and charges for 2023/2024 that it
approves an increase to piers and harbours fees and charges of 5%, over and above
an inflationary increase which would be ring fenced to develop the Council’s marine
infrastructure;

Page 2

2. note that this presented a stepped “proposed increase to allow smoothing” over a 10
year period for meeting both the sustainability costs and future improvement costs
associated with the marine infrastructure which Argyll & Bute Council has responsibility
for; and 
3. that the asset management plan would continue to be updated on a rolling 10 year
basis. 
(Reference:  Report by Executive Director with Responsibility for Roads and Infrastructure
dated November 2022, submitted) 
During discussion of agenda item 4 (Oban Bay Update), the Chair moved and the Board
agreed that a short adjournment be taken to allow officers an opportunity to confirm the
detail contained within the draft Harbour Revision Order (HRO).   
The meeting reconvened at 11:35am with all those present as per the sederunt.  
.
4. OBAN BAY UPDATE 
The Harbour Board gave consideration to a report providing an update on the status of
plans to establish the Municipal Oban Harbour and the progress of the Oban Harbour
Revision Order (HRO). The HRO included proposed external harbour limits that had been
justified by an independent Navigational Risk Assessment (NRA) process. 
Decision 
The Harbour Board agreed to– 
1. note the update provided in the submitted report; 
2. note the comments referenced from the Consultation period and the Council’s
response thereto; 
3. approve the draft HRO (under deletion of paragraph 26 (n), being a repetition and the
correction of non-material errors) for submission to Transport Scotland as the
submission to be confirmed as an HRO; 
4. note that the HRO would be submitted to Transport Scotland in the first case on an
informal basis as part of their best practice advice and that should there be any
material alterations requested by Transport Scotland then they would be brought back
to the Harbour Board for approval; 
5. note the governance arrangements in respect of the Harbour Authority; and 
6. note the technical advice given in the meeting by Officers in relation to the detailed
definition of the external limits to Oban Harbour, contained with Appendix 3 of the
report.   
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated December 2022, submitted)