Democracy Spraffa

Public reports pack

Argyll and Bute Council · 2 March 2023
Back to Argyll and Bute Harbour Board — 2 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
23 February 2023 
NOTICE OF MEETING 
A meeting of the ARGYLL AND BUTE HARBOUR BOARD will be held ON A HYBRID BASIS IN
THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS on
THURSDAY, 2 MARCH 2023 at 1:00 PM, or at the conclusion of the Environment, Development
and Infrastructure Committee at 10.30 am, whichever is later, which you are requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST (IF ANY) 
3. MINUTES 
(a) Argyll and Bute Harbour Board held on 1 September 2022 (Pages 3 - 4)  
(b) Special Argyll and Bute Harbour Board held on 22 December 2022 (Pages
5 - 8) 
4. OBAN BAY UPDATE (Pages 9 - 12)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
5. PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN (Pages 13 - 22)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
6. PORT MARINE SAFETY CODE 
Report by Executive Director with responsibility for Roads and Infrastructure Services
(to follow) 
REPORTS FOR NOTING 
7. DRAFT HARBOUR BOARD WORKPLAN (Pages 23 - 24) 
Public Document Pack

Page 2

Argyll and Bute Harbour Board 
Councillor John Armour Councillor Jim Lynch
Councillor Andrew Vennard Councillor Garret Corner
Councillor Andrew Kain (Chair) Councillor Ian MacQuire
Councillor Ross Moreland (Vice-Chair) Councillor Amanda Hampsey   
Contact: Hazel MacInnes Tel: 01546 604269

Page 3

MINUTES of MEETING of ARGYLL AND BUTE HARBOUR BOARD held ON A HYBRID BASIS BY
MICROSOFT TEAMS AND IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD 
on THURSDAY, 1 SEPTEMBER 2022 
Present: Councillor Andrew Kain (Chair) 
Councillor John Armour
Councillor Garret Corner
Councillor Jim Lynch 
Councillor Ian MacQuire
Councillor Ross Moreland
Councillor Andrew Vennard 
Attending:  Kirsty Flanagan, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
Stuart McLean, Committee Manager
Scott Reid, Marine Operations Manager 
1. APOLOGIES FOR ABSENCE 
There were no apologies for absence. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. MINUTES 
(a) Argyll and Bute Harbour Board held on 3 March 2022 
The Minutes of the meeting of the Argyll and Bute Harbour Board held on 3 March
2022 were approved as a correct record. 
(b) Special Argyll and Bute Harbour Board held on 4 August 2022 
The Minutes of the meeting of the Special Argyll and Bute Harbour Board held on 4
August 2022 were approved as a correct record. 
During consideration of the following item of business there were technical issues with the
Hybrid meeting.  The Chair ruled, and the Harbour Board agreed, to adjourn the meeting
for 5 minutes and to reconvene on a remote only basis. 
4. MARINE ASSET MANAGEMENT PLAN UPDATE 
The Harbour Board gave consideration to a report providing a further update on significant
and major programmes currently being addressed within Argyll and Bute Council’s Marine
Asset Management Plan following on from the update provided to the Board in March
2022. 
Decision 
The Argyll and Bute Harbour Board noted – 
Page 3 Agenda Item 3a

Page 4

1. the update on significant and major programmes that were currently being addressed
within Argyll and Bute Council’s Marine Asset Management Plan; and 
2. that £15.5 million worth of capital works were programmed for the financial year 2022 /
2023 plus works continuing from 2021 / 2022. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted) 
5. PORT MARINE SAFETY CODE 
The Harbour Board gave consideration to a report providing an update on progress being
made towards compliance with the Port Marine Safety Code (PMSC) following on from the
update provided to the Harbour Board in March 2022. 
Decision 
The Argyll and Bute Harbour Board endorsed the content of the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted) 
6. OBAN BAY UPDATE 
The Harbour Board gave consideration to a report providing an update on progress being
made since the decision of the Special Harbour Board in December 2021 and the
previous updates provided to the Harbour Board in March and August 2022, in respect of
Oban Bay. 
Decision 
The Argyll and Bute Harbour Board noted the update provided in the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated 11 August 2022, submitted) 
7. DRAFT HARBOUR BOARD WORKPLAN 
The draft Workplan was before the Harbour Board for noting. 
Decision 
The Argyll and Bute Harbour Board noted the content of the Workplan. 
(Reference:  Draft Argyll and Bute Harbour Board Workplan dated September 2022,
submitted) 
Page 4

Page 5

MINUTES of SPECIAL MEETING of ARGYLL AND BUTE HARBOUR BOARD held ON A HYBRID
BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 22 DECEMBER 2022 
Present: Councillor Andrew Kain (Chair) 
Councillor John Armour (by
Teams)
Councillor Jim Lynch (by Teams)
Councillor Andrew Vennard (by
Teams) 
Councillor Garret Corner (by Teams)
Councillor Ross Moreland (by Teams) 
Attending: Douglas Hendry, Executive Director
Kirsty Flanagan, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
David Logan, Head of Legal and Regulatory Support
Scott Reid, Marine Operations Manager
Stuart McLean, Committee Manager
Frank Roberts, Oban Community Harbour Development Association
Phil Hammerton, Oban Community Harbour Development Association
Ross Wilson, Oban Community Harbour Development Association 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Ian MacQuire. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interested intimated. 
DEPUTATION
The Chair intimated that a request for a deputation by Oban Community Harbour
Development Association to be heard by the Harbour Board had been received. It was
unanimously agreed to hear this deputation prior to item 4 of the Agenda.
.
3. PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN FEES &
CHARGES 2023 / 2024 
The Harbour Board gave consideration to a report in respect of a necessary increase in
fees and charges for the forthcoming financial year 2023 / 2024, in order to meet the
requirements for the Argyll and Bute Council Asset Management Plan that had been
referenced in the report to the Harbour Board in September 2022. 
Decision 
The Harbour Board agreed to - 
1. recommend to the Council, when setting the fees and charges for 2023/2024 that it
approves an increase to piers and harbours fees and charges of 5%, over and above
Page 5 Agenda Item 3b

Page 6

an inflationary increase which would be ring fenced to develop the Council’s marine
infrastructure; 
2. note that this presented a stepped “proposed increase to allow smoothing” over a 10
year period for meeting both the sustainability costs and future improvement costs
associated with the marine infrastructure which Argyll & Bute Council has responsibility
for; and 
3. that the asset management plan would continue to be updated on a rolling 10 year
basis. 
(Reference:  Report by Executive Director with Responsibility for Roads and Infrastructure
dated November 2022, submitted) 
During discussion of agenda item 4 (Oban Bay Update), the Chair moved and the Board
agreed that a short adjournment be taken to allow officers an opportunity to confirm the
detail contained within the draft Harbour Revision Order (HRO).   
The meeting reconvened at 11:35am with all those present as per the sederunt.  
.
4. OBAN BAY UPDATE 
The Harbour Board gave consideration to a report providing an update on the status of
plans to establish the Municipal Oban Harbour and the progress of the Oban Harbour
Revision Order (HRO). The HRO included proposed external harbour limits that had been
justified by an independent Navigational Risk Assessment (NRA) process. 
Decision 
The Harbour Board agreed to– 
1. note the update provided in the submitted report; 
2. note the comments referenced from the Consultation period and the Council’s
response thereto; 
3. approve the draft HRO (under deletion of paragraph 26 (n), being a repetition and the
correction of non-material errors) for submission to Transport Scotland as the
submission to be confirmed as an HRO; 
4. note that the HRO would be submitted to Transport Scotland in the first case on an
informal basis as part of their best practice advice and that should there be any
material alterations requested by Transport Scotland then they would be brought back
to the Harbour Board for approval; 
5. note the governance arrangements in respect of the Harbour Authority; and 
6. note the technical advice given in the meeting by Officers in relation to the detailed
definition of the external limits to Oban Harbour, contained with Appendix 3 of the
report.   
Page 6

Page 7

(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated December 2022, submitted) 
Page 7

Page 8

This page is intentionally left blank

Page 9

ARGYLL AND BUTE COUNCIL  HARBOUR BOARD 
ROADS AND INFRASTRCUTURE
SERVICES 
2nd MARCH 2023 
OBAN BAY UPDATE 
1.0 INTRODUCTION 
1.1 This report is provided to update Members on the status of plans to establish the
Municipal Oban Harbour and the progress of the Oban Harbour Revision Order
(HRO). 
1.2 It follows from the 22nd December meeting of the Harbour Board at which
approval was given for a draft HRO to be submitted to Transport Scotland on an
informal review basis. 
2.0  RECOMMENDATIONS 
It is recommended that the Harbour Board notes and considers the update
provided in this report.   
3.0 DETAIL   
Harbour Revision Order (HRO) 
3.1.1 The Council’s Harbour Board at its meeting on 22nd December gave approval
for the draft Harbour Revision Order to be submitted to Transport Scotland.  
3.1.2 The draft was submitted prior to the festive break, in this first instance on an
informal basis. This is considered to be best practice and allows Transport
Scotland the opportunity for informal discussion with the Council on the content
before they then accept as a formal submission for public consultation. Argyll &
Bute Council will then undertake a 42 day period public consultation. 
3.1.3 Positive discussions have taken place between Argyll & Bute Council technical
and legal officers; the Council’s legal advisors and Transport Scotland.
Transport Scotland have asked for some non-material alterations in style and
presentation which are being incorporated in the draft. 
3.1.4 Scottish Government’s legal team will then review the draft HRO and following
any comments from them being addressed.  Should there be any material
alterations requested by Transport Scotland then they would be brought back to
the Harbour Board for approval.
Page 9 Agenda Item 4

Page 10

Next Steps 
3.2 The key statutory and notable milestones for subsequent reports to the Harbour
Board are: 
(1) Any clarifications or amendments requested by Transport Scotland or MCA
will be presented to a Special Harbour Board meeting for Members review
and approval.
(2) Advertisement of the application in Edinburgh and local press following
receipt of the HRO by Transport Scotland.
(3) 42 days for formal consultation as per the HRO process.
(4) Addressing any issues and objections.
(5) Decision by Ministers on HRO.
(6) Order is made. 
4.0 CONCLUSION 
4.1 This report provides an update to Members on the status of plans to establish
the Municipal Oban Harbour and the progress of the Oban Harbour Revision
Order (HRO). 
5.0 IMPLICATIONS 
5.1 Policy – The Harbour Board agreed in December 2021 that the Council should
proceed to make the arrangements to formally manage the unmanaged
section of Oban Bay.   
5.2 Financial – No financial implications at this stage.  As the proposal develops
further detail will be brought to the Harbour Board.   
5.3 Legal – the HRO process is a formal legal process set out in the 1964
Harbours Act. 
5.4 HR – HR implications will be identified as the proposal progresses.   
5.5  Fairer Scotland Duty: 
5.5.1   Equalities – None known 
5.5.2   Socio-economic Duty – None Known
5.5.3 Islands – consultation will be carried out with the island communities as a
continuation and expansion of the Options Appraisal Process reported to the
December harbour Board.
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
Page 10

Page 11

5.7 Risk - The Council progressing to become a Municipal Port Authority for the
unmanaged areas of Oban Bay increases the safety within Oban Bay.  There
is a risk that there could be a number of objections and representations during
the process which could impact on timescale and these will be considered as
and when they arise.  
5.8  Customer Service – Improved and safer environment for all users 
Kirsty Flanagan, Executive Director with responsibility for Roads and Infrastructure 
Jim Smith, Head of Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
February 2023 
For further information contact: Jim Smith, Head of Roads and Infrastructure, or
Scott Reid, Marine Operations Manager 
Page 11

Page 12

This page is intentionally left blank

Page 13

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES       2nd MARCH 2023 
PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN 
1.0 INTRODUCTION 
1.1 This report provides Members with a review of the marine works Asset
Management Plan. It includes an update on significant and major programmes
currently planned and underway within Argyll and Bute Council’s Marine Asset
Management Plan (AMP) as well as schemes added since the last update. 
2.0 RECOMMENDATIONS 
2.1 Members of the Harbour Board are asked to:- 
2.1.1 Consider the update on the major programmes currently being addressed
within the Argyll and Bute Council’s Marine Asset Management Plan.
2.1.2 Note that £6.5 million worth of capital works are programmed for the financial
year 2023 2024.
2.1.3 Note that there is a potential spend of c.£110 million over the next 5 years,
the majority of which will support the new CMAL and CFL / CalMac fleet
renewal.   
3.0 BACKGROUND 
3.1 Argyll and Bute Council continue to work closely with Transport Scotland, CMAL
and CFL / CalMac to support Island and rural communities with marine links to
the mainland, Central Belt resources and tourist revenue.
3.2 Lifeline ferry services are prioritised and the CMAL vessel replacement
programme for Islay, Mull, Iona and Gigha all require infrastructure upgrades to
meet the new vessel’s requirements.
Page 13 Agenda Item 5

Page 14

3.3 Dunoon and Kilcreggan also have vessel replacement programmes underway
which will see an improvement in the service reliability and resilience for
commuters and visitors.
3.4 Shore power upgrades for overnight charging of vessels and the associated
infrastructure requirements are being completed in Craignure for the Loch Frisa;
and preparation work is also underway for Fionnphort and Gigha.
3.5 Crew and passenger’s safe boarding and access will be improved with our
programmes at Fionnphort, Feolin, Dunoon and Kilcreggan, while studies will be
completed for the Council’s own ferry services infrastructure. 
4.0 DETAIL 
4.1 The latest version of the Marine Asset Management Plan is attached as annex A
and planned expenditure is summarised in table 1 in appendix 1. It includes the
following significant works: 
4.1.1 Iona & Fionnphort
CMAL’s Small Vessel Replacement Programme (SVRP) vessel no3 of 7,
expected Q4 2026 / Q1 2027. A very successful meeting and presentation
took place in January with the residents and users of Iona slipway. 
The EIA has now been received and we are very pleased that there are
now no ‘Red Flag’ issues outstanding and that mitigation measures will be
agreed to allow the project to continue. 
We will now proceed with the Marine licences, planning etc. and hope to
have works commencing next year. 
Alongside this is the preparation is progressing with Fionnphort to ensure: 
  Overnight berth 
  Safe access for crew 
  Sheltered berthing 
  Charging and supply facilities 
  Traffic survey to enhance the passenger road user interface at the
terminal area. 
A public engagement visit, drop in day and presentation at Fionnphort will
take place on 25th April this year and is expected to be well attended. 
4.1.2 Craignure
 New Ferry Terminal
Page 14

Page 15

A well-attended meeting was held in Craignure in December where we
agreed to proceed with Ground Investigations (GI) at the proposed location
close by the existing pier. GI planning and tender compilation is now
underway. Next phase works include completion of the Outline Business
Case (OBC), detailed design and Financial Business Case.
 Power supply for Loch Frisa 
Officers have worked closely with CMAL to provide the shore power supply
for the Loch Frisa and we continue to progress the remaining enabling
works. 
A new power substation is now online from 5th February providing
improved capacity for both present demand and a ‘Phase 1’ for the new
terminal requirements. 
4.1.3 Port Askaig 
Vessels are expected from Q4 2024. The new vessel will have the capacity
to carry a maximum of 100 cars, or 14 HGVs. A new area adjacent to the
approach road has been investigated, however due to the landowner
rejecting the sale of land and excessive letting cost this could no longer be
considered as the preferred option. 
Although now not ‘Plan A’ we will keep the new area as a possible
contingency or overspill area and will proceed with Ground Investigations
on site. 
Options will now be further developed with the aim of Port Askaig being
ready for the new Islay vessel’s arrival. These are looking at all options
which maximise the capacity at the present location. 
4.1.4 Dunoon & Kilcreggan 
Vessels expected from Q1 2026. Public consultation has closed for the
Dunoon infrastructure and it is anticipated that the results will be available
before this Harbour Board meeting date. The results will be discussed with
Argyll and Bute Council Harbour Board, Working Group, Reference Group
and fully available on the Council’s web site. 
Specifications are being drawn up for tender submissions with an aim of
starting GI works in the summer. 
Kilcreggan consultation is now ongoing. The web-based consultation is
being backed up by hard copy booklets; feedback forms in the village and
Pier Office; and ‘QR code’ link posters on the ferry itself. Results and
feedback will be fully available when completed. 
Page 15

Page 16

4.1.5 Feolin 
Plans for Feolin include the new infrastructure required for a new
replacement ferry as well as a pontoon and gangway installation in the
short term, for use when the passenger only contingency is in service. 
4.1.6 Gigha & Tayinloan 
SVRP vessel no7 of 7 expected Q2 of 2028. Feasibility study will be
concluded to confirm the shore power requirements can be met on the
island. An EIA will commence, to be ready for the detailed design and
associated licences to be progressed.
4.2 Other ongoing plans include: 
4.2.1 Campbeltown Pier extension 
Feasibility study is underway with consultants and CMAL for a potential
extension and / or strengthening of Campbeltown New Quay. 
4.2.2 Craignure PAS 
Our consultants Royal Haskoning have a replacement engineer in place
to develop tender documentation and design specs for a compliant
replacement PAS at the existing terminal location. We are reviewing and
confirming an extensive list of potential in scope vessels which include
short, long term and contingency options in the coming weeks. The aim is
to make use of the PAS when the Long-Term Option for Craignure has
been completed to maximise value for money on the build. 
4.2.3 Rothesay Harbour Quay stabilisation works 
Following failed tenders for piling and grouting works at Rothesay Quay,
consultants have assisted in developing new methodology which will
reduce the contract risk and provide the required results for the
stabilisation of the quayside. A further tender exercise will follow when
preparations are completed. 
4.3 Funding for Piers and Harbours is mainly provided by Prudential borrowing paid
back through fees and charges, however external funding can also be sourced
through capital grants, shared cost agreements and funds made available for
specific projects. 
A recent attempt to secure ‘Levelling Up Fund’ grants for Port Askaig and Jura
ferry plans was unsuccessful, however the background work will now be used to
forward the plans through Argyll and Bute Council’s Marine Asset Management
Plan. 
The Marine Asset Management Plan is an adaptable plan fed into by changing
priorities and circumstances. It also relies on steady and predictable income from
those ferry services utilising Argyll and Bute Council infrastructure.
Page 16

Page 17

In recent years the COVID-19 pandemic and the UK’s withdrawal from the
European Union has made some of the variables less predictable and our ability
to engage contractors and consultants more difficult. 
Costs will be best estimated and closely watched for best value. Rising prices and
availability of resources are risks which will need to be monitored in each of the
projects and forecasts adjusted accordingly.
4.4 It will be apparent from the Marine Asset Management Plan that works are
concentrated within the next 5 years. 
This is mainly a result of the replacement of CMAL fleet for CFL / CalMac services
which require Argyll and Bute Council infrastructure to be upgraded before the
arrival of the vessels for the service. 
5.0 CONCLUSION 
5.1 This report provides Members with an update on various marine infrastructure
projects from the Argyll and Bute Council’s Marine Asset Management Plan,
some future projects in development and a value for the works planned in the
coming financial year. 
6.0 IMPLICATIONS
6.1 Policy - None directly arising from this report. 
6.2 Financial - The increases to fees and charges proposed at the December
Harbour Board will ensure that future income is sufficient to maintain and
develop Argyll and Bute Council marine assets for the coming year. Further
increases or alternative funding routes will be required to sustain the proposed
projects in future years. 
6.3  Legal - Considered to be none directly arising from this report.
6.4  HR -  None.
6.5  Fairer Scotland Duty:  
6.5.1   Equalities - protected characteristics - None directly arising from this report.
6.5.2   Socio-economic Duty - None directly arising from this report.
6.5.3 Islands - Completed works and projects will enhance service reliability and
community connectivity
6.6 Climate Change - there are no direct impacts in regard to climate change from
this report, due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
Page 17

Page 18

6.7 Risk - Completed works will reduce the repair and maintenance on existing
infrastructure.  
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns
and redeployments, Environmental issues (car use), Brexit, Covid 19 and
potential changes in RET. This will pose a potential risk to income. 
6.8  Customer Service - An overall improvement in travel experience and reliability
should result with improved and maintained infrastructure. 
Executive Director with responsibility for Roads and Infrastructure:
Kirsty Flanagan
Policy Lead for Roads and Transport: Councillor Andrew Kain
February 2023                                                  
For further information contact:
Scott Reid, Marine Operations Manager Tel: 01546 604 696
Jim Smith, Head of Roads and Infrastructure Services Tel: 01546 604 324 
APPENDICES 
Appendix 1 - Summary of 2023/2024 works from the Marine Asset Management Plan.
Appendix 2 - Marine Asset Management Plan (Rolling 10 Year Plan)  
Page 18

Page 19

Appendix 1 – Summary of 2023/24 works from the Marine Asset Management Plan 
Page 19

Page 20

This page is intentionally left blank

Page 21

APPENDIX 2 - MARINE ASSET MANAGEMENT PLAN (ROLLING 10 YEAR PLAN) 
Page 21

Page 22

This page is intentionally left blank

Page 23

Harbour Board Work Plan 2023-2024 
This is an outline plan to facilitate forward planning of reports to the Harbour Board. 
Date Report Designation  Lead Service/
Officer 
Regularity of
occurrence/
consideration 
Date of Reports
to Committee
Services
Additional Comment
2 March 2023 
Oban Bay Update  Marine
Operations
Bi-Annual 7 February 2023 
Marine Asset Management
Plan 
Marine
Operations
Bi-Annual 7 February 2023 
Port Marine Safety Code  Marine
Operations
Bi-Annual 7 February 2023 
31 August 2023 
Oban Bay Update  Marine
Operations
Bi-Annual 8 August 2023 
Marine Asset Management
Plan 
Marine
Operations
Bi-Annual 8 August 2023 
Port Marine Safety Code  Marine
Operations
Bi-Annual 8 August 2023 
29 February 2024 
Oban Bay Update  Marine
Operations
Bi-Annual 6 February 2024 
Marine Asset Management
Plan 
Marine
Operations
Bi-Annual 6 February 2024 
Port Marine Safety Code  Marine
Operations
Bi-Annual 6 February 2024 
Page 23
Agenda Item
7

Page 24

Harbour Board Work Plan 2023-2024
Date Report Designation  Lead Service/
Officer 
Regularity of
occurrence/
consideration 
Date of Reports
to Committee
Services
Additional Comment
Future Reports – dates to be determined   
Community Groups &
Berthing Dues     
Review of Marine Services
Working Practices     
Crane Provision at
Campbeltown     